Calender Week-6 WORK STATUS @ SIET

S.No. Description
1 PQR-008(200 NBx3.74mm Thk,SS 304L) Impact @ -196 0c Qualified.Filler Wire
Make:Ador & EASB

2 PQR-009(250 NBx9.27mm Thk,SS 304L) Impact @ -196 0c Qualified.Filler Wire


Make:Ador & EASB
3 5 Nos LN2 Vaporizers Alignment Inspection witnesed on 04-02-2020

4 PQR-007(2" NB x 8.74mm Thk, DSS Pipe) Sent to Micro lab on 06-02-2020 for
Qualification.
5 40 Nos Pipe Supports Received @ Site on 06-02-2020
6 D-Meter Received at Site on 06-02-2020
2 Nos Vortex Flow Metrs Inward Material Inspection done on 07-02-2020.
7 Make:Emerson

8 15NB Globe valves material Inspection done on 07-02-2020 .Details are Cl 150 -
17, Cl 300 -49,Cl 600 - 13 & Cl 900 - 12 .Make:Forbes Marshell
9 Water Tank,LPRT & MPRT Strctural Columns Fabrication under progress @
Thamirabharani Fab Yard.
Co-ordinates & RL marked by Surveyor for Pipe Supports @ Isrosene Area on 08-
10 02-2020
@ SIET

Remarks
Lab Reports Not Yet Received.

Lab Reports Not Yet Received.

Found Ok.Grouting & Torquing


Balance for all LN2 Vaporizers
RT Found Satisfactory.

Positioned @ Isrosene Area


Calibration Certificate Available.

Physically Verified and Found Ok.

Total 91 Nos Verified &Accepted


Spools Fabrication Started on 11/12/2019
CALENDER WEEK No. Of Joints Inch Dia
50(2019) 29 156
51(2019) 18 145
52(2019) 7 38
1 10 93
2 18 204
3 96 348
4 68 510
5 44 194
6 97 482.00
CUMULATIVE 387 2170.00
Total No Of Joints Radiographed - 244
Total No.Of welders-6