You are on page 1of 12

Chapter 12.

1
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS
R ICHARD C. W ARNER

12.1.1 INTEGRATING ENVIRONMENTAL COSTS Table 12.1.1. Stormwater and Sediment Controls
Stormwater conveyance
During past decades, industry has sometimes been viewed Diversions
by the public as an insensitive steward of the environment. Preoc- Temporary
cupation with mineral and energy resource extraction caused the Earthen
mining industry to neglect the integration of environmental cost Mats of straw, nylon, etc.
into their companies’ business plans and developmental policies. Geotextiles
The results of this missed opportunity are mandated regulations, Flexible membrane liners
leaving many critical decisions outside the control of companies. Permanent
With the passage of the Surface Mining Control and Reclama- Rock riprap
tion Act of 1977 (SMCRA), Public Law 95-87, the goal of min- Gabion mattress
Concrete-filled geotextiles
imizing hydrologic impacts to offsite areas was enacted.
Concrete
Specific interpretations of this law in the form of changing Asphalt
regulations do not provide for regional differences with respect Grassed waterways
to the quality of receiving waters and climatologic regimes. Reg- Culverts
ulations focus on many specific criteria, yet neglect the benefits/ Corrugated metal
costs associated with an integrated overall strategy. For instance, Concrete
sediment standards are set for a peak concentration associated PVC
with a design storm (the specified size of storm for which the Polyethylene (PE)
strategy is designed), yet neglect the sediment duration-concen- Steel
Energy dissipators
tration relationship that influences aquatic invertebrates and dis-
Plunge pools
regards the water quality and multiple use of receiving waters. Rock aprons
Criteria quite appropriate for some locales may be entirely un- Gabions
justified, both environmentally and economically, for mine sites Concrete-filled geotextiles
in other regions. Despite regulatory constraints, opportunities Check dams
still exist to implement innovative approaches to achieving the Filter fabric fences
goal of minimizing hydrologic impacts. Brush barriers
What is meant by minimizing the hydrologic impact of a Dewatering
mining operation? Surface mining and surface disturbance from Sumps
System of wells
underground mining create changes to the hydrologic regime,
Sediment controls
usually in the form of increased storm runoff and generated Sediment basins
sediment loads. If minesite stormwater and sediment discharge Contour
can approximate predevelopment conditions, then no significant Dugouts
adverse offsite impacts are expected. The determination of prede- Embankment
velopment conditions should consider both onsite factors and Permanent pool
the quality of receiving waters. A stormwater and sediment con- Passively dewatered
trol plan is created to detain excess stormwater, reduce peak Infiltration
flow, and remove the higher sediment load caused by disturbing Sediment separators
Swirl concentrators
stable landforms. Similar to stormwater, the control of nuisance
Inertial separators
water is particularly important to mining operations. Sediment traps and check dams
For general coverage of environmental regulations, see Excavation pits
Chapters 3.4 and 7.3. Dozer basins
Filter fabric fences
Brush barriers
12.1.2 TYPES OF CONTROLS Vegetative filters

A comprehensive multifaceted approach to storm water, nui-


sance water, erosion, and sediment control, thoroughly integrated
throughout the entire planned life of the mine, can reduce poten-
tial environmental impacts, increase mine productivity, and be trol methods are crucial to a program that is successful overall:
achieved in a cost-effective manner. The types of controls fre- (1) limiting temporal and spatial exposure of highly erodible
quently utilized are (1) water conveyance structures, (2) reten- areas, and (2) the implementation of onsite controls for concur-
tion facilities, (3) energy dissipators, and (4) pumps. A wide rent reclamation through use of grading, terraces, mulches, soil
spectrum of water and sediment controls is listed in Table 12.1.1. amendments, grasses, etc.
As can be seen from this list, numerous options exist for The most common structures designed to minimize the hy-
designing an integrated water and sediment control plan. Al- drologic impact of mining are sediment basins, diversions, cul-
though not explicitly enumerated in this section, two other con- verts, energy dissipators, and dewatering systems. Methods,

1158
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS 1159
equations, and discussions are provided to illustrate design pro- Table 12.1.2. Runoff Coefficients for the Rational
cedures for these controls. Method
Description of Area Runoff Coefficients
12.1.3 HYDROLOGY Residential
Single-family areas 0.30–0.50
Suburban 0.25–0.40
12.1.3.1 Selection of Analysis Method
Industrial
Stormwater and sediment control facilities are often based Light areas 0.50–0.80
on a design storm of a specified frequency. For simple controls Heavy areas 0.60–0.90
such as diversions or culverts, only a peak flow may be necessary. Unimproved areas 0.10–0.30
In contrast, the design of a sediment basin, which involves stor-
age routing, requires a complete hydrograph. Thus the required Lawns; sandy soil
control defines the complexity of the hydrologic analysis. Flat, ≤ 2% 0.05–0.10
The rational equation (Anon., 1969a; Rossmiller, 1982) is Average, 2–7% 0.10–0.15
Steep, > 7% 0.15–0.20
widely used for peak flow estimation due to its simplicity. Devel-
opment of a design storm hydrograph is more complex but has Rural Areas (clay and silt loam)
been greatly simplified through user-friendly application pro- Woodland
grams (Schwab and Warner, 1987; Anon., 1986b; Anon., 1970). Flat 0–5% 0.30
Rolling 5–10% 0.35
Numerous hydrology texts describe, in detail, all facets of Hilly 10–30% 0.50
peak flow estimation and hydrograph development (Hjelmfelt, Pasture
1975; Linsley et al., 1949; Overton and Meadows, 1976; Viess- Flat 0–5% 0.30
man et al., 1977; Eagleson, 1970; Barfield et al., 1981). Rolling 5–10% 0.36
Hilly 10–30% 0.42
Cultivated
12.1.3.2 Design Rainfall Event Flat 0–5% 0.50
Stormwater management designs are based on a specified Rolling 5–10% 0.60
design storm (e.g., 10 yr–24 hr) precipitation amount, temporal Hilly 10–30% 0.72
distribution of precipitation, and the infiltration characteristics Source: Adapted from Anon., 1969a; Schwab et al., 1962.
of watersheds. The design storm is normally specified by regula-
tions. Storm depth-duration-frequency values are provided in
HYDRO-35 (Frederick et al., 1977) and US Weather Bureau
TP40 (Hershfield, 1961) for the eastern United States and in counts for all hydrologic factors such as rainfall interception,
a series of National Oceanic and Atmospheric Administration infiltration, antecedent moisture conditions, etc. Representative
(NOAA) Atlases for the 11 western states. C coefficients are given in Table 12.1.2 for urban and rural areas.
Where design situations require maximum assurance of The rainfall amount is found in HYDRO 35 (Frederick et al.,
safety, the probable maximum precipitation (PMP) events are 1977).
utilized. PMPs represent the theoretically greatest depth of pre- Time of concentration tc , is the length of time for runoff from
cipitation for a given duration that is physically possible over a the hydraulically most remote point in the watershed to reach
given size area at a specific location at a given time of the year the watershed outlet. Several methods exist to estimate tc , such as
(Anon., 1985). the SCS upland method (Anon., 1973), kinematic wave analogy
To develop a hydrograph, it is necessary to know the design (Ragan and Duru, 1972), and Kirpich (1940). The Ragan and
storm depth-duration-frequency (e.g., 4.2 in. or 107 mm, 10 yr- Duru equation is
24 hr) and the temporal pattern of rainfall throughout the dura-
tion of the storm. The rainfall pattern is usually associated with (12.1.2)
a synthetic rainfall distribution. The Soil Conservation Service
(SCS) has developed four rainfall distribution curves, defined as where tc is time in minutes, n is Manning’s N, L is length in ft
SCS type curves, applicable to specific regions throughout the (m), ie is rainfall excess intensity in in./hr (mm/h), S is slope in
United States (Anon., 1986b). ft/ft (m/m), and C 1 = 0.928 in English units (C 1 = 1.977 in SI
units). Note the equation is valid only when the product of ie
and L is greater than 500 ft (152 m). The Kirpich equation for
12.1.3.3 Peak Flow Determination
estimating tc is
For design of diversions and culverts, only the design storm
peak flow is needed. The most widely used method for peak (12.1.3)
flow determination is the rational method (Anon., 1969a). The
rational formula is where L 1 is the maximum flow length in ft (m), H is elevation
English units difference in ft (m) between the hydraulically most remote point
q = CIA (12.1.1) in the watershed and the watershed outlet, and C 2 = 0.0078 in
SI units English units (C2 = 0.0195 in SI units).
q = 0.0028 CIA (12.1.la)
where q is peak flow in cfs (m3/s), C is a dimensionless runoff
12.1.3.4 Storm Hydrograph Development
coefficient, I is rainfall intensity in in./hr (mm/h) with a dura- A storm hydrograph is a graph of flow rate vs. time. It is
tion equal to the time of concentration tc , and A is the watershed necessary for evaluating alternative designs of basins, since rout-
area in acres or ac (hectares or ha). The runoff coefficient ac- ing of incremental storm volumes is used in determining peak
1160 MINING ENGINEERING HANDBOOK
Table 12.1.3. Typical Topsoil K Factors for the USLE Table 12.1.4. Selected C Factors for the USLE
Estimated K value Surface Conditions C Factor
Texture (ton/ac/ R unit) (Mg/ha/ R unit) Bare soil, seed bed prepared, racked smooth 0.9
Bare soil, seed bed prepared, rough graded 0.8
Clay, clay loam, loam, silty
Bare soil, compacted by a bulldozer 0.9–1.2
clay 0.32 0.72
Undisturbed forest with > 90% ground litter and 0.0001–0.001
Fine sandy loam, loamy very > 75% effective canopy
fine sand, sandy loam 0.24 0.54 Undisturbed forest with 75 to 85% ground litter 0.002–0.004
0.17 0.38 and 40 to 70% effective canopy
Loamy fine sand, loamy sand
Undisturbed forest with 40–70% ground litter and 0.003–0.009
Sand 0.15 0.34 20–25% effective canopy
Rangeland/idle land, no appreciable canopy, 0% 0.45
Silt loam, silty clay loam,
0.37 0.83 groundcover
very fine sandy loam
Rangeland/idle land, no appreciable canopy, 0.10–0.15
Source: Adapted from Anon., 1978. 40% ground cover
Rangeland/idle land, no appreciable canopy, 0.01
80% ground cover
stage, flow through principal and emergency spillways, detention Rangeland/idle land, 50% tall weed or short 0.26
time, and sediment trap efficiency. A description of hydrograph brush canopy, 0% ground cover
developmental methods is beyond the scope of this chapter, Rangeland/idle land, 50% tall weed or short 0.07–0.11
but many excellent texts provide detailed methodologies and brush canopy, 40% ground cover
illustrative examples (Barfield et al., 1981; Linsley et al., 1975; Rangeland/idle land, 50% tall weed or short 0.01–0.04
Overton and Meadows, 1976). Also computer programs are brush canopy, 80% ground cover
available that greatly simplify hydrograph development: SED- Clear cut woodland, 20% residue on soil surface 0.06–0.44
CAD+—Sediment, Erosion, Discharge by Computer-Aided De- Clear cut woodland, 60% residue on soil surface 0.05–0.20
Straw mulch at 1 ton/ac (2.26 Mg/ha) 0.1–0.2
sign (Warner and Schwab, 1990); SEDIMOT II (Wilson et al.,
Straw mulch at 2 tons/ac (4.52 Mg/ha) 0.02–0.08
1982; Warner et al., 1982); TR-55 (Anon., 1986b); and HEC-1 Woodchip mulch at 2 tons/ac (4.52 Mg/ha) 0.65
(Anon., 1970). Woodchip mulch at 4 tons/ac (9.04 Mg/ha) 0.4
Woodchip mulch at 8 tons/ac (18.08 Mg/ha) 0.1
12.1.4 SEDIMENTOLOGY Grass cover < 60 days after emergence 0.1–0.4
Grass cover > 60 days after emergence 0.05

12.1.4.1 Quantity of Sediment Determination Source: Adapted from Wischmeier and Smith, 1978.
The quantity of sediment eroded from a slope depends on
the erosive power of rainfall, soil characteristics, slope length
and gradient, and type and amount of soil cover and conservation The approximate original contour of a representative slope
practices. These parameters have been combined into the univer- has a gradient of 12% and is 200 ft (70 m) in length. Applying
sal soil loss equation (USLE) (Wischmeier and Smith, 1965, these values to Eq. 12.1.6,
1978):

A = R K LS C P (12.1.4) LS = (λ/72.6)m (0.043s2 + 0.30s + 0.43)/6.574 (12.1.6)


LS = (λ/22)m (0.043s2 + 0.30s + 0.43)/6.574 (12.1.6a)
where A is soil loss per unit area in tons/ac (Mg/ha or metric
tons/ha); R is a rainfall factor; K is soil erodibility in tons/ac/ where λ is slope length in ft (m); m is an exponential factor that
R unit (Mg/ha/R units); LS is a dimensionless length-slope equals 0.6, 0.5, 0.4, and 0.3 for slopes of > l0%, >4 to l0%,
factor that accounts for the actual length and slope compared to 4%, and < 4%, respectively; and S is sin θ, θ is the slope angle
a standard slope of 9% and 72.6 ft (22.1 m) in length; C is a factor in degrees; an LS value of 2.8 is calculated.
that accounts for the effectiveness of vegetal cover, mulches, Table 12.1.4 lists selected C factors reported in the literature
etc.; and P is a factor that accounts for the effectiveness of (Barfield et al., 1981). Since the example problem has a regraded
conservation practices such as terraces. Values for these parame- topsoil that has been recently seeded and mulched at 2 tons/ac
ters may be found in Wischmier and Smith (1978). (4.5 Mg/ha), the C factor ranges from 0.02 to 0.08. An average
A prediction of soil loss from a regraded spoil that has been value of 0.04 is selected. Since no conservation practices such as
recently topsoiled, seeded, and mulched at 2 tons/ac (4.5 Mg/ terracing were included, P = 1. Applying Eq. 12.1.4 yields
ha) will be used to illustrate the applicability of the USLE. The
design 10 yr–24 hr storm for western Kentucky (Hershfield,
A = (101.6)(0.24)(2.8)(.04)(l) = 2.7 tons/ac
1961) is 4.2 in. (107 mm). Assuming an SCS Type II rainfall
distribution and applying Eq. 12.1.5 (Barfield et al., 1981), (A = (101.6)(0.54)(2.8)(.04)(l) = 6.1 Mg/ha)
(12.1.5) If mulch was not applied, and rough-grade bare-soil condi-
(12.1.5a) tions were predominant, the C factor would be 0.8, and the
quantity of eroded sediment would be increased by the ratio of
yields Rst of 101.6, where Rst is the rainfall factor on a storm basis, C factors (that is, 0.8/0.04), or by a factor of 20. Thus 54.6 tons/
P is precipitation depth in in. (mm), and D is storm duration in ac (122 Mg/ha) of eroded sediment would be predicted by the
hr. USLE.
A fine sandy loam topsoil has been used during reclamation. The USLE provides an estimate of sediment delivered from
Table 12.1.3 lists estimated soil erodibility K values as a function a field size area. To determine the sediment yield at some point
of soil texture. The K value for this example topsoil is 0.24 (0.54). beyond the base of the field, the eroded sediment needs to be
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS 1161
routed to the point of interest. As such, the USLE provides an a check dam wide enough for a backhoe, facilitates sediment
estimate of the quantity of sediment eroded from a representative cleanout.
area within a relatively homogeneous subwatershed. A delivery Small storm runoff is contained in the primary chamber and
ratio may be used to transfer eroded sediment to a point of is slowly dewatered by either a small drop-inlet perforated riser
interest such as a sediment basin (Barfield et al., 1981). A deliv- and/or a wide rock riprap French drain (see Figs. 12.1.2 and
ery ratio is simply the ratio of the quantity of sediment that 12.1.3). As the primary chamber fills with the larger-sized sedi-
reaches a structure to that quantity of sediment predicted by the ment, it also acts as a slow sand filter that greatly increases the
USLE. It is a rough approximation often based on drainage quality of discharged water. For larger storms, short circuiting
area. As with hydrology, computer techniques have expanded and dead storage are substantially reduced since the internal
predictive capabilities well beyond delivery ratio estimates by check dam evenly distributes flow across the width of pool. The
applying sediment detachment, transport, and deposition meth- check dam is protected by a geotextile fabric and rock riprap or
odologies. Popular programs include SEDCAD+ (Warner and equivalent.
Schwab, 1990) and CREAMS (Chemical, Runoff, Erosion from Optional principal spillway configurations are shown in Fig.
Agricultural Management Systems) (Knisel, 1980). 12.1.1 and detailed in Figs. 12.1.4 and 12.1.5. The drop-inlet
perforated riser should be sized to reduce peak flow to near
premining conditions. The tapered riser perforations slowly de-
12.1.5 SEDIMENT CONTROLS water the storm pool, thereby providing additional storage for
subsequent storms. This also reduces the peak stage, compared
to the permanent pool option, thus reducing embankment con-
12.1.5.1 Sediment Basins
struction cost. Dewatering reduces peak discharge, increases sed-
A wide variety of sediment basins has been used throughout iment trap efficiency with respect to total sediment load, and
the mining industry. Small elongated basins are often located reduces peak and average effluent sediment concentrations. The
along benches near the highwall in contour mining. Dugouts, floating siphon tube (Fig. 12.1.5) provides an added advantage
which are primarily excavated basins with 4- to 8-ft (1.2- to by dewatering only the uppermost water level, thus increasing
2.4-m) berms, are prevalent in area mining and mountaintop sediment trap efficiency. Stationary or floating siphon tubes can
removal. The most common basins consist of a dam embankment be used in conjunction with either trickle tubes or drop-inlet
12 to 19 ft (3.6 to 5.8 m) in height with added storage capacity principal spillways (Warner and Schwab, 1989, 1990).
provided through excavation of soils in the pool area. These Impact pools with depressed outlet channels dissipate the
basins often use trickle tube (a straight pipe through the embank- energy of concentrated pipe discharge to reduce downstream
ment) or drop inlet principal spillways, and an emergency spill- impacts (Warner and Schwab, 1990).
way. The principal spillway of a dugout is often a trapezoidal Design of stormwater retention basins is facilitated by using
channel that may also function as the emergency spillway. Con- computer programs such as DAMS2 that routes water through
tour basins often have trickle tube principal spillways and an principal and emergency spillways (Putnam et al., 1982; Anon.,
emergency spillway. 1965). Principal and emergency spillway designs, stormwater
Sediment basins are used to reduce peak flow and trap sedi- and sediment routing, inflow and outflow hydrographs and sedi-
ment. The efficiency of basins to accomplish these two functions mentgraphs, dewatering options, impact pools, sediment trap
is directly related to the basin design with respect to (1) location efficiency, embankment earthwork volumes, etc., can be calcu-
and gradient of inflow channel(s); (2) selection of type, size, and lated through use of the SEDCAD+-Version 3.0 Model (Warner
location of principal and emergency spillways; (3) length-to- and Schwab, 1990).
width ratio of the pool measured at the crest of the principal
spillway; (4) basin shape; (5) percentage of basin capacity allo-
12.1.5.2 Infiltration Basins
cated to sediment and permanent pool storage; (6) dewatering
method(s); (7) detention storage; (8) inlet baffles, turbidity cur- An infiltration basin has no direct discharge for surface
tains, and internal check dams; (9) use of flocculation additives; waters and is used to recharge an aquifer constructed during
etc. As can be seen from this list of engineering considerations, mountaintop or area mining (Dinger et al., 1988). A vertical
the performance of a sediment basin in reducing the incoming durable rock core is constructed during spoil placement to facili-
peak storm flow and retaining sediment is directly achieved tate the rapid downward movement of stormwater. Infiltration
through design rigor. basins have the advantages of recharging groundwater, complete
The objective of minimizing the hydrologic impact can be containment of stormwater and sediment, relatively simple con-
assured if the peak discharge emanating from the basin is reduced struction, avoidance of potential embankment stability problems,
to near premining conditions and a significant percentage of the and allowance of a large degree of flexibility in a spatial siting.
incoming sediment load is captured. To achieve this objective,
consider the application of each of the design factors as explained
in Table 12.1.5. 12.1.5.3 Sediment Basin Hydraulics
A cost-effective sediment basin design that is expected to Design aspects of basin hydraulics encompass (1) principal
minimize the hydrologic impact to offsite streams is illustrated spillway design, (2) emergency spillway design, (3) pond stage-
in Figs. 12.1.1 through 12.1.5. (Warner and Schwab, 1989). The area-capacity, and (4) routing the inflow hydrograph. The basic
function of the identified features in these figures is described. steps in developing an outflow hydrograph for a sediment basin
The length-to-width ratio is approximately 2:1. It may be smaller are listed in Table 12.1.6.
than the recommended ratio due to the internal check dam.
Incoming flow energy is dissipated by the rock impact pool at
the basin entrance. The internal check dam is used to accomplish 12.1.6 SEDIMENT SEPARATORS
many functions. It further slows and spreads out the incoming
flow by rapidly creating a pool of water in the primary chamber. The swirl concentrator and inertial separator have both been
The larger-sized sediments rapidly settle out in this forward designed to intercept sediment-laden inflow. The swirl concen-
chamber, which, in combination with the access road and/or trator separates sediment from the incoming flow through the
1162 MINING ENGINEERING HANDBOOK
Table 12.15 Application of Sediment Basin Design Principles
Design Consideration Implementation
1. Location of inflow channels Locate inlet(s) to provide the hydraulically longest flow path between inlet(s)
and outlet(s). This will help reduce short circuiting of flow.
2. Inlet flow channel gradient Provide a wide, shallow slope entrance. Stabilize steeper slopes with rock
riprap or equivalent protection to avoid severe gully formation.
3. Size of principal spillway Size to significantly reduce the incoming peak flow to near premining condi-
tions.
4. Location of principal spillway Depending on size, and associated flow rate, locate a minimum of at least 2
to 3 ft (0.6 to 0.9 m) above the sediment storage level. Also, locate farthest
point away from inlet(s).
5. Pool length to width ratio (L/W) The L/W ratio measured at the crest of the principal spillway should be 2:1
or greater.
6. Basin shape Provide a L/W ratio of 2:1 or greater and the basin deep enough such that
resuspension of settled sediment is avoided. Refer to design considerations
4 and 5.
7. Sediment storage Base sediment storage needs depend on (1) estimated loads for at least the
life of the project or (2) for the expected sediment load associated with the
10-yr, 24-hr design storm. Sediment storage volumes, based on project life,
may be reduced dependent upon a sediment approval plan.
8. Permanent pool storage Both advantages and disadvantages exist for permanent pools in contrast to
a dewatered or partially dewatered pool. The major advantage is dilution of
the incoming sediment concentration. Disadvantages are (1) higher peak flow
discharged and greater peak stage, (2) increased fall depth of incoming
sediment prior to retention in the sediment storage area, (3) shorter detention
time, and (4) discharge of warm, low-oxygen water during summer months.
9. Pool dewatering (gated risers, perforated risers, station- Dewatering provides numerous advantages when compared to the perma-
ary and floating siphon tubes, small trickle tubes) nent pool option—(1) lower peak discharge, (2) lower storage volume, (3)
higher sediment trap efficiency.
10. Detention storage (time difference between inflow and Detention storage is an indicator of basin performance. Longer detention
outflow hydrograph peaks or hydrograph centroids.) times indicate reduced peak flow and poentially more efficient sediment
trapping.
11. Inlet baffles, turbidity curtains, and internal check dams All of these devices increase the flow path between inlet(s) and outlet(s). In
addition, they decrease dead storage which improves sediment trap effi-
ciency.
12. Flocculation additives Long chain polymers create flocs, a group of soil particles, which settle at
rates significantly faster than individual soil particles, thus increasing sedi-
ment trap efficiency.
13. Outlet stabilization The outlet of principal and emergency spillways should be stabilized by en-
ergy dissipators such as impact pools constructed of rock riprap, gabions, or
concrete-slurry-filled geotextiles to avoid downstream bed scour.

centrifugal force generated by the inherent inertia of the flow centrator is that no sediment maintenance is needed since it is
(Warner and Dysart, 1983). Effluent with a high sediment load self-cleaning; that is, the concentrated sediment-laden flow,
is transmitted to a small sediment trap while the clearer flow is which represents 5 to 15% of the incoming flow, is automatically
discharged directly to a stream. Fig. 12.1.6 shows a schematic discharged to a small sediment basin.
of the swirl concentrator. The inertial separator is designed to
retain incoming sediment in a tank between a series of V-cut
bottom-slotted troughs (Sterling and Warner, 1984). The sedi- 12.1.7 DIVERSIONS
ment-laden influent is transferred from shallow influent troughs
into the tank, and clearer flow is withdrawn by deep troughs. Diversions are designed to be stable and convey a specified
Plan and elevation cross section of the inertial separator are peak flow. Stability is usually interpreted as avoidance of signifi-
shown in Fig. 12.1.7. cant erosion of the channel bed or sidewalls. Diversions can
The numerous advantages of these devices call attention to be classified as temporary or permanent structures. Temporary
their use as primary sediment control structures on surface- diversions may be constructed of soil and/or a soil/spoil mixture,
mined lands. Both devices are relatively simple, containing no and protected by straw or nylon blankets, geotextiles, and flexible
moving mechanical parts, and no onsite energy requirements are membrane liners. For these diversions, the determination of sta-
needed. Since the devices are relatively small, they can be easily bility is based on either a permissible velocity or a critical tractive
transported on flat-bed trucks and modularized to facilitate rapid force, the assumption being that if the specified velocity or
installation and relocation once reclamation and bond release tractive force is not exceeded, the diversion will remain stable.
have been accomplished. The added advantage of the swirl con- Conveyance capacity is calculated using Q = VA and Manning’s
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS 1163

Fig. 12.1.4. Schematic of perforated riser with tapered


holes for dewatering.

Fig. 12.1.1. Efficient and cost-effective sediment basins.


equation (12.1.7) where Q is discharge in cfs (m3/s), V is the
average channel velocity in fps (m/s), and A is the cross-sectional
area in ft2 (m2), and Manning’s equation is

(12.1.7)
(12.1.7a)

where R is the hydraulic radius in ft (m), which is the cross-


sectional area divided by the wetted perimeter, and s is the
hydraulic gradient (channel slope) in ft/ft (m/m).
Permanent diversions are often constructed of rock riprap,
Fig. 12.1.2. Plan view (cross section A-A1 ) of dewatering type of gabion mattresses, grass, asphalt, concrete, concrete slurry-filled,
internal check dam. Conversion factor: 1 in. = 25.4 mm. double-layer geotextile forms, and interlocking concrete blocks.
Stability of these products is often related to discharge, diversion
gradient, or velocity (Maccaferri, undated; Anon., 1989; Anon.,
1982.) Rock riprap stability is based on selecting riprap that
is large enough such that the gravitational force exceeds the
overturning forces (Anon., 1982). Also an underlying rock filter,
consisting of a range of smaller rocks, is required to avoid erosion
of the base soil. The design of grassed waterways is a function
of grass type and height, permissible velocity, slope, Manning’s
n, and hydraulic radius. Use of retardance classes simplifies the
design process (Anon., 1969b). Computer programs, such as
SEDCAD+ Version 3.0 (Warner and Schwab, 1990), simplify
design procedures.

12.1.8 CULVERTS
The selection of a properly sized culvert is based on design
1 discharge, type of culvert, entrance configuration, pipe length
Fig. 12.1.3. Cross section B-B of dewatering type of internal and slope, headwater constraints, and tailwater condition (Fig.
check dam.
12.1.8). Two of three primary design parameters must be known.
1164

Fig. 12.1.5. Schematic of floating siphon tube used for dewatering.

The primary parameters are (1) discharge, (2) pipe size, and (3) will be in inlet control, and the solid line will describe culvert
headwater. Thus, if discharge is known, the headwater can be performance. Applying Eq. 12.1.8 to the design input values
determined for a specific size of culvert. Depending on these mentioned above and using a 0.02-ft/ft (m/m) slope yields an I
parameters, the culvert may function with inlet, outlet, or full- of 100. A vertical line at 70 cfs (2 m3/s) intersects the solid 300
pipe flow control. index value for the 36-in. (910-mm) culvert (Fig. 12.1.9). Since
Design procedures have been somewhat simplified through the calculated index value is less than the 300 solid line, inlet
the development of culvert capacity charts (Anon., 1962). Such control is specified, and the headwater height of 5.2 ft (1.6 m) is
a chart is illustrated in Fig. 12.1.9. Headwater values are indi- determined by extending a horizontal line to the ordinate. In a
cated on this chart on the ordinate and discharge values on the similar manner for the 0.002 ft/ft (m/m) culvert gradient, an
abscissa. The solid curves designate inlet control and the dashed index value I of 1000 is calculated. Since the calculated index
curves indicate outlet control. Also listed is an index value I, value lies between the solid and dashed curve of the 36-in. (9l-
defined as cm) culvert, outlet control is specified. Referring to Fig. 12.1.9,
a headwater of 6.1 ft (1.9 m) is determined from the interpolated
index value. A calculated index value greater than the dotted
(12.1.8) curve indicates full pipe flow, and an applicable nomograph
should be used. A detailed analysis of culvert design procedures
is available (Normann et al., 1985).
(12.1.8a) The user of these culvert analysis charts should be cautioned
that neither the open-channel flow regime nor submerged outlet
conditions are accommodated by the culvert capacity charts.
where L is pipe length in ft (m), and So, is pipe gradient in ft/ft Computer programs for culvert designs are available (Anon.,
(m/m). 1986; Warner and Schwab, 1990). The SEDCAD+ Version 3.0
Example 12.1.1. Use of the culvert capacity chart is illus- program provides complete performance curves of headwater
trated by a design example. Inputs are (1) a design discharge of versus discharge for all culvert flow regimes.
70 cfs (2m3/s), (2) concrete culvert, (3) grooved-edge entrance,
(4) culvert length of 200 ft (61 m), and (5) a slope of 0.02 and
0.002 ft/ft (m/m), respectively. 12.1.9 PUMPS
Solution. The solution procedure begins with the calculation
of the index value. When the calculated index value is less than Pumps are widely used throughout the mining industry for
or equal to the index value of a specified culvert, the culvert dewatering deep mine operations, an active pit, and predraining
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS 1165
Table 12.1.6. Development of an Outflow Hydrograph
for a Sediment Basin
Item Method
Principal spillway 1. Drop-inlet riser stage-discharge (Bar-
relationship field et al., 1981)
—Weir flow equation
—Orifice flow equation
—Pipe flow equation
2. Trickle tube
Interactive solution to mild and steep
slopes with submerged or unsubmerged
outlets (Warner and Schwab, 1990)
3. Perforated riser
(Warner and Schwab, 1990)
—Step-function orifice flow equation
4. Siphon tubes
(Warner and Schwab, 1989)
—Pipe flow equation
—Siphon flow equation
Emergency spillway 1. Broad crested weir with backflow
analysis
(Putnam et al., 1982)
S t a g e - a r e a - v o l u m e 1. Stage-area from contour map
2. Volume from prismoidal rule Fig. 12.1.7. Inertial separator.
Routing 1. For each time increment, ∆t
a. determine volume of inflow
b. from the stage-volume curve, deter-
mine the stage associated with the
increase in inflow volume
c. from the stage-discharge curve, de-
termine the volume of outflow

Fig. 12.1.8. Culvert input design parameters.

Fig. 12.1.9. Culvert design capacity chart.

adjacent areas prior to pit excavation. Control of groundwater


and surface water can alleviate numerous production problems
and provide safer working conditions. For example, a series of
wells installed adjacent to an area to be mined can decrease
groundwater migration, reduce construction of large sumps, and
Fig. 12.1.6. Swirl concentrator. enhance slope stability.
(12.1.9)

where Hf100 is friction loss per 100 ft (100 m) of pipe; K is the


conversion constant, 1045 with English units and 1.22 × 1012
with SI units; Q is flow rate in gpm (L/s); C is retardation
coefficient = 120 for coated steel and = 150 for PVC; and D is
inside pipe diameter in in. (mm).
Friction loss in fittings is usually approximated by the equiv-
alent pipe length (Table 12.1.8).
The velocity head hv , in ft (m) is usually small and may often
be neglected. It can be calculated using the following relation:

Fig. 12.1.10. Centrifugal pump components. (12.1.10)

where V is velocity of liquid in fps = 0.408 × gpm/ D 2 (English


units) and = 1273 × L/s/D2 (SI units), D is pipe diameter in
12.1.9.1 Basic Principles of a Centrifugal Pump in. (mm), and g is acceleration due to gravity = 32.2 fps2 (9.81
m/s 2 ).
Centrifugal pumps are probably the most popular type in Example 12.1.2. Consider a pump that is to be located 4 ft
mining (Bise, 1986). The basic components of a centrifugal pump (1.2 m) above the water level of a sump. The mine is at 6000 ft
as illustrated in Fig. 12.1.10 are an inlet, the eye of the rotating (1830 m) and the water temperature is not expected to exceed
impeller, curved impeller vanes, volute, and discharge connec- 70°F (21°C). A flow rate of 900 gpm (56.8 L/s) is required. A 6-
tion. A centrifugal pump is a simple device with the only moving in. (152-mm), 40-ft (12.2-m) long suction line was specified with
part being the impeller which is attached to the shaft of a motor two 45°, 6-in. (152-mm) ells, a gate valve, a vacuum gage installed
or engine. Assuming that the suction pipe and pump housing on a tee, and a check valve. Will the total practical lift of the
(volute) is filled with water to the level of the eye (i.e. primed), pump be exceeded?
as the impellers rotate, a partial vacuum is created that allows Solution. Total Dynamic Suction Lift = Lift Height + Fric-
atmospheric pressure to lift more water into the pump housing. tion Head + Velocity Head. Lift height is given as 4 ft (1.2 m).
The water, which entered the inlet opening at the eye of the The equivalent pipe length of fittings totals 153.5 ft (46.8 m).
impeller, is set in rotation by the impeller and creates centrifugal Pipe friction head is calculated for the 40 ft (12.2 m) section
force resulting in pressure at the outer perimeter of the impeller. from Eq. 12.1.9 as 7.1 ft/100 ft of pipe. For the total equivalent
Water moves outward from the impeller at a high velocity and pipe length of 193.5 ft (59 m), the friction head loss is 13.7 ft
pressure into an expanding volute and is discharged. (4.2 m).
A single-stage centrifugal pump, that is, a single impeller, Flow velocity is approximately 10.2 fps (3.1 m/s), and the
usually operate against low to moderate heads. For heads greater velocity head is 1.6 ft (0.5 m) (Eq. 12.1.10). Thus the total
than approximately 250 ft (75 m), multistage pumps are gener- dynamic suction lift is 4 + 13.7 + 1.6 = 19.3 ft (5.8 m). The
ally used. A multistage centrifugal pump consists of two or more practical lift at 6000 ft (1830 m) for water at 70°F (21°C) from
stages and is essentially a high-head pump. The single-stage Table 12.1.7 is 18.3 ft (5.6 m). Thus the practical lift of the pump
pump is normally used for high volume and relatively low head. approximated in Table 12.1.7, will be slightly exceeded, causing
pump cavitation and a drop in pump performance.
Pump manufacturers provide either static suction lift or net
12.1.9.2 Calculating Dynamic Head
positive suction head (NPSH) curves for each pump model over
The essential information needed to properly select a pump the entire operating range. The NPSH subtracted from the values
is the required flow rate in gpm (L/s) and the total dynamic listed in Table 12.1.7 provides an estimate of the maximum
head in ft (m). Flow rate is dependent primarily on operational allowable dynamic suction lift for a given model at a specified
factors such as the anticipated rate of flow into a pit or under- operating point. Selection of a more efficient check valve, reduc-
ground mine. Determination of the total dynamic head requires tion of intake pipe length, lowering the pump closer to the water,
consideration of suction lift, elevation difference between the eliminating fittings, or increasing the suction pipe size will reduce
pump and discharge point, pressure requirements, if any, at the the total dynamic suction head. It should be noted that improper
discharge outlet, friction along pipes and fittings, and velocity design and installation of the suction line are primary causes of
head. poor pump performance.
Dynamic lift of water at the suction side is calculated as the In a similar manner to suction head calculations, the total
required pressure needed to raise water from the water surface dynamic pumping head must be calculated prior to pump selec-
to the height of the centerline of the pump and to overcome tion. The total dynamic head is the sum of (1) suction head, (2)
frictional resistance in the intake pipe and fittings. Twenty-three the elevation difference between the center line of the pump and
ft (6.7 m) is considered the practical limit of suction lift. This is the discharge point, (2) friction loss in pipes and fittings, (3)
further reduced by long or undersized intake pipes, a large num- discharge pressure (zero if atmospheric discharge), and (4) veloc-
ber of fittings, higher mine site elevation, and warmer waters. ity head.
Table 12.1.7 contains the practical static suction lift as a function Example 12.1.3. Assume that a 900-gpm (56.8-L/s) dis-
of site elevation and temperature. charge is required to dewater a pit. The elevation difference
Friction loss in pipes is a function of pipe diameter and between the pump and discharge point is 70 ft (21.3 m) and a
length, type of pipe material, and flow rate. The Hazen-Williams 400-ft (122-m), 6-in. (152-mm) PVC pipe will be used to convey
equation is often used to calculate friction loss: the pumped water. No fittings are needed.
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS 1167
Table 12.1.7. Practical Suction Lift1
Elevation 50°F (10°C) 70°F (21°C) 90°F (32°C)
ft (m) ft (m) ft (m) ft (m)
0 0 23.8 7.2 23.2 7.1 22.6 6.9
1000 305 22.9 7.0 22.4 6.8 21.8 6.6
2000 610 22.0 6.7 21.5 6.6 20.9 6.4
4000 1220 20.4 6.2 19.9 6.1 19.3 5.9
6000 1830 18.9 5.8 18.3 5.6 17.8 5.4
8000 2440 17.5 5.3 16.9 5.2 16.4 5.0
1
70% of theoretical siphon lift.

Table 12.1.8. Equivalent Length of Pipe, ft


Nominal pipe size, in. (mm)
1 (25) 2 (50) 3 (75) 4 (100) 6 (150)
90° ell 2.7 5.5 8.0 11.0 16.0
45° ell 1.3 2.5 4.0 5.0 8.0
Tee 6.0 12.0 17.0 22.0 33.0
Globe valve, open 13.0 29.0 45.0 60.0 110.0
Gate valve, open 0.6 1.3 2.0 2.5 4.5
Check valve 8.0 19.0 32.0 43.0 100.0
Conversion factor: 1 ft = 0.3048 m.
Source: Adopted from Bise, 1986.

marked 5 (1.5), 10 (3.0), 15 (4.6), 20 (6.1), and 25 ft (7.6 m)


indicate the maximum flow in gpm ( L / s ) the pump is capable
of delivering at designated suction lifts. To read the curve, start
at either the x or y axis.
Example 12.1.4. Assume 200 gpm (12.6 L /s) is needed.
Solution. Follow across the bottom scale until 200 gpm (12.6
L / s) is reached; then proceed up this line until the 3800-rpm
line is intersected. Reading across, it is found that the pump is
capable of discharging 200 gpm (12.6 L /s) against a total head
of 65 ft (19.8 m), provided the suction lift is no more than 7 ft
(2.1 m).
Example 12.1.5. Similarly, if a total head of 80 ft (24.4 m)
is required, proceed horizontally across to the 3800-rpm line and
then vertically to the gpm ( L / s ) axis to read 160 gpm (10.1 L /
s). If the suction lift is 15 ft (4.6 m), the maximum discharge is
150 gpm (9.5 L /s).
Fig. 12.1.11. Pump characteristic curves for engine-driven pump. Pump characteristic curves for an electric-motor-driven
(Modified from Anon., 1966.) pump contain additional information on pump speed, efficiency,
horsepower, and suction head. Motors operate at a constant
speed. Their rpm cannot be varied like a gasoline or diesel engine.
Solution. Applying Eq. 12.1.9 yields a friction loss Hf on the A V-belt pulley arrangement is used to adjust a motor to the
discharge side of 4.7 ft (1.4 m). The total dynamic head is the desired operating speed.
sum of the dynamic suction head 19.3 ft (5.8 m), elevation differ- Example 12.1.6. (a) For a specified operating rpm, (e.g.,
ence 70 ft (21.3 m), and discharge friction loss 4.7 ft (1.4 m), 1750) the brake horsepower (brake watts) can be directly deter-
which yields 94 ft (28.6 m). Thus the selected pump must have mined from Fig. 12.1.12. A ½-hp (0.4-kW) motor is needed. At
the capacity to pump 900 gpm (56.8 L/s) at a total dynamic 3450 rpm, a 3-hp (2.3-kW) motor is required since the 3450-rpm
head of 94 ft (28.6 m), and a dynamic suction lift at this operating line is between the 2 and 3 hp (1.5 2.3 kW) scale. Pump efficiency
point of 19.3 ft (5.8 m). is indicated by the U-shape curves, e.g., 56, 50, 45%. Brake
horsepower can be calculated from Eq. 12.1.11:
12.1.9.3 Pump Selection
A pump characteristic curve shows the relationship among
discharge in gpm ( L / s ) , total dynamic head in ft (m), and either (12.1.11)
suction lift or NPSH in ft (m). A representative pump character-
istic curve is illustrated in Fig. 12.1.11. Along the vertical axis,
the amount of head that will be developed, expressed in ft (m), (12.1.11a)
is shown. The x axis contains discharge in gpm ( L / s ) . The lines
1168 MINING ENGINEERING HANDBOOK
tion, excessive air in water, mechanical defects, etc. Excess pump
vibration may indicate misalignment, worn bearings, bent shaft,
or an obstruction has lodged in one side of the impeller.

REFERENCES
Anon., (multi-years), “Precipitation-frequency Atlas of the Western
US,” NOAA Atlas II., Superintendent of Documents, US Govern-
ment Printing Office, Washington, DC. (Vol. 1, Montana; Vol. 2,
Wyoming; Vol. 3, Colorado; Vol. 4, New Mexico; Vol. 5, Idaho;
Vol. 6, Utah; Vol. 7, Nevada; Vol. 8, Arizona; Vol. 9, Washington;
Vol. 10, Oregon; Vol. 11, California).
Anon., 1962, “Culvert Design Aids: An Application of US Bureau of
Public Roads Culvert Capacity Charts,” Portland Cement Associa-
tion, Chicago, IL.
Anon., 1965, “Computer Program for Project Formulation-Hydrology,”
US Department of Agriculture, Soil Conservation Service, Washing-
ton, DC.
Fig. 12.1.12. Pump characteristic curves for electric-motor-driven Anon., 1966, “Gorman-Rupp Pump Manual,” Mansfield, OH.
pump. (Modified from Anon., 1966.) Anon., 1969a, “Design and Construction of Sanitary and Storm Sewers,
Manual of Practice 9,” American Society of Civil Engineers Manual
of Engineering Practice No. 37, Water Pollution Control Federa-
tion, Washington, DC.
where Q is flow rate in gpm (L/min), H is total dynamic head Anon., 1969b, “Engineering Field Manual for Conservation Practices,”
in ft (m), and Eff is pump efficiency expressed as a decimal. Soil Conservation Service, US Department of Agriculture, Washing-
ton, DC.
(b) The required net positive suction head (NPSH) is the
Anon., 1970, “HEC-1 Generalized Computer Program Flood Hy-
minimum net energy required by the pump at the eye of the drograph Package,” Hydrologic Engineering Center, US Army
impeller to avoid cavitation and reduce pump performance. Corps of Engineers.
NPSH is a function of pump design. If the total dynamic suction Anon., 1973, “A Method for Estimating Volume and Rate of Runoff in
lift (i.e., static suction lift plus friction loss and velocity head) Small Watersheds,” SCS-TP-149, Soil Conservation Service, US
exceeds the NPSH required by the pump, then cavitation will Department of Agriculture, Washington, DC.
occur (Anon., 1983). Anon., 1975, “Urban Hydrology for Small Watersheds,” Technical Re-
At a flow rate of 60 gpm (3.8 L / s ) , the NPSH, read from lease No. 55, Engineering Division, Soil Conservation Service, US
the lower dashed line and the NPSH axis, is 6 ft (1.8 m). The Department of Agriculture, Washington, DC.
Anon., 1978, “Water Management and Sediment Control for Urbanizing
total dynamic suction lift is determined by subtracting the NPSH
Areas,” Soil Conservation Service, US Department of Agriculture,
from the appropriate value listed in Table 12.1.7. For example, Columbus, OH.
at 1600 ft (305 m) and 70°F (21°C), a 22.4-ft (6.8-m) practical Anon., 1982, “Surface Mining Water Diversion Design Manual,” OSM/
suction lift is needed. Thus, for the above values, the total dy- TR-8212, Office of Surface Mining, US Government Printing Office,
namic suction lift must be less than 16.4 ft (5.0 m), i.e., 22.4 to Washington, DC.
–6 ft (6.8 to –1.8 m). Anon., 1983, Irrigation, Irrigation Assn., Silver Springs, MD.
The total head and pump discharge can be changed by plac- Anon., 1985, Safety of Dams-Flood and Earthquake Criteria, National
ing pumps in series or parallel or by changing the operating Research Council, National Academy Press, Washington, DC.
speed. To plot characteristic curves for parallel and series pump- Anon., 1986a, “HY8-FHWA Culvert Analysis Software,” Bridge Divi-
sion, HNG-31, Federal Highway Administration, Report prepared
ing installations, it is required to secure each pump’s characteris-
by Pennsylvania State University.
tic curve. For parallel pump characteristic curves, the flow rates Anon., 1986b, “Urban Hydrology for Small Watersheds,” Technical
are added at a given head; for series pump characteristic curves, Release No. 55, Soil Conservation Service, US Department of Agri-
the heads are added at a given flow rate. As the pump speed is culture, Washington, DC.
increased, (1) the discharge is proportionally increased, (2) head Anon., 1989, “Design Manual for Armorform Erosion Protection Mats,”
varies as the square of the RPM ratio, and (3) BHP (brake watts) Nicolon Inc., Norcross, GA.
varies as the cube of the RPM ratio. Refer to Bise (1986) for Barfield, B.J., Warner, R.C., and Haan, C.T., 1981, Applied Hydrology
detailed examples. and Sedimentology for Disturbed Areas, Oklahoma Technical Press,
Stillwater, OK.
Bise, C.J., 1986, Mining Engineering Analysis, SME, Littleton, CO.
12.1.9.4 Pump Troubleshooting Dinger, J.S., Warner, R.C., and Kemp, J.R., 1988, “Building of an
Aquifer in Coal-Mine Spoil-Concept and Initial Construction at the
A properly designed and installed pump will reduce potential Star Fire Tract, Eastern Kentucky,” Proceedings National Sympo-
operational problems. A vacuum gage, installed a minimum of sium on Hydrology, Sedimentology, and Reclamation, University of
one pipe diameter from the pump inlet, can solve the majority Kentucky, Lexington, KY.
of problems. A high gage reading indicates a partially blocked Eagleson, P.S., 1970, Dynamic Hydrology, McGraw-Hill, New York.
suction line, whereas a low reading often indicates air leakage Frederick, R.H., Myers, V.A., and Auciello, E.P., 1977, “Five to 60
through fittings on the suction side. A vacuum gage can easily Minute Precipitation Frequency for the Eastern and Central United
detect common problems such as a non-primed pump; too high States,” National Oceanic and Atmospheric Administration, Tech-
a dynamic lift; excessive air in the water due to the intake being nical Memorandum NWS HYDRO-35, US Department of Com-
merce, Washington, DC.
near the water surface; air leakage in the inlet pipe, fittings, or Hershfield, D.M., 1961, “Rainfall Frequency Atlas of the United States,”
stuffing box; or the strainer, foot valve, or suction pipe is too Technical Paper 40, US Department of Commerce, Weather Bu-
small or restricted by debris. If a discharge pressure gage reads reau, Washington, DC.
too low, the pump may not be primed, rpms too low, total Hjelmfelt, A.T., and Cassidy, J.J., 1975, Hydrology for Engineers and
dynamic head is too high, impeller rotating in the wrong direc- Planners, Iowa State University Press, Ames, IA.
DESIGN AND MANAGEMENT OF WATER AND SEDIMENT CONTROL SYSTEMS 1169
Kirpich, P.Z., 1940, “Time of Concentration of Small Agricultural Wa- Sterling, H.J., and Warner, R.C., 1984, “The Inertial Separator as a
tersheds,” Civil Engineering, Vol. 10, No. 6, pp. 362. Sediment Control Device,” Proceedings, National Symposium on
Knisel, W.G., 1980, “CREAMS: A Field-Scale Model for Chemicals, Surface Mining, Hydrology, Sedimentology, and Reclamation, Uni-
Runoff, and Erosion from Agricultural Management Systems,” US versity of Kentucky, Lexington, KY.
Department of Agriculture, Conservation Research Report No. 26. Viessman, W., Jr., et al., 1977, Introduction to Hydrology, Intext Educa-
Linsley, R.K., Kohler, M.A., and Paulhus, J.L.H., 1949, Applied Hydrol- tional Pub., New York.
ogy, McGraw-Hill, New York. Warner, R.C., and Dysart, III, B.C., 1983, “Potential Use of the Swirl
Linsley, R.K., Kohler, M.A., and Paulhus, J.L.H., 1975, Hydrology for Concentrator for Sediment Control on Surface Mined Lands,” Pro-
Engineers, McGraw-Hill, New York. ceedings, Symposium on Surface Mining Hydrology, Sedimentology,
Maccaferri, G. (undated), “Flexible Reno Mattress and Gabion Linings
and Reclamation, University of Kentucky, Lexington, KY.
for Channel and Canalized Water Courses,” Maccaferri Gabions,
Warner, R.C., and Schwab, P.J., 1989, “Alternative Designs of Sediment
Inc., Williamsport, MD.
Norman, J.M., Houghtalen, R.J., and Johnson, W.J., 1985, “Hydraulic Basins: Environmental and Economic Considerations,” ASAE Sum-
Design of Highway Culverts,” (FHWA-IP-85-15, HDS No. 5), Fed- mer Meeting, Paper No. 89-2020, Quebec, Canada.
eral Highway Administration, US Department of Transportation, Warner, R.C., and Schwab, P.J., 1990, “SEDCAD+ (Sediment, Erosion
Washington, DC. and Discharge by Computer Aided Design) Version 3.0. Design
Overton, D.E., and Meadows, M.E., 1976, Storm Water Modeling, Aca- Training Manual,” Civil Software Design, Lexington, KY.
demic Press, New York. Warner, R.C., et al., 1982, A Hydrology and Sedimentology Watershed
Putnam, E., et al., 1982, “DAMS2 (Interim Version) Structure Site Model. Part II: User’s Manual, Department of Agricultural Engi-
Analysis Computer Program,” Hydrology Unit, Engineering, US neering, University of Kentucky, Lexington, KY.
Department of Agriculture, Soil Conservation Service, Washington, Wilson, B.N., Barfield, B.J., and Moore, I.D., 1982, “A Hydrology and
DC. Sedimentology Watershed Model. Part I: Modeling Techniques,”
Ragan, R.M., and Duru, J.O., 1972, “Kinematic Wave Nomograph for Department of Agricultural Engineering, University of Kentucky,
Times of Concentration,” Proceedings American Society of Civil Lexington, KY.
Engineers, 98(HY10), pp. 1765–1771. Wischmeier, W.H., and Smith, D.D., 1965, “Rainfall Erosion Losses
Rossmiller, R.L., 1982, “Rational Formula Revisited,” Stormwater De- from Cropland East of the Rocky Mountains,” Agricultural Hand-
tention Facilities, W. DeGroot, ed., American Society of Civil Engi- book No. 282, US Department of Agriculture, Washington, DC.
neers, New York. Wischmeier, W.H., and Smith, D.D., 1978, “Predicting Rainfall Erosion
Schwab, G.E., et al., 1962, Elementary Soil and Water Conservation
Losses—A Guide to Conservation Planning,” Agriculture Hand-
Engineering, Wiley, New York.
book No. 537, US Department of Agriculture, Washington, DC.
Schwab, P.J., and Warner, R.C., 1987, “SEDCAD+ (Sediment, Erosion,
and Discharge by Computer Aided Design) Design Manual,” Civil
Software Design, Lexington, KY.

You might also like