ONE MONTH LOOK A HEAD SCHEDULE

PEMBANGUNAN TANKI KAP. 40.000 KL DI TBBM LOMANIS CILACAP

2019
MAN
NO. ITEM PEKERJAAN SCHEDULE START TARGET FINISH MAR
POWER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Erection Shell Plate & Accessories

- Shell #6 , Stairway & Accessories 25 Hari 11-Feb-19 20 Hari 2-Mar-19


- Radiography

- Shell #5 , Stairway & Accessories 25 Hari 3-Mar-19 20 Hari 23-Mar-19


- Radiography

2 Install Pipe & Welding

- Pipa PMK 90 Hari 1-Feb-19 85 Hari 27-Apr-19


- Pipa Product 90 Hari 1-Mar-19 85 Hari 25-May-19

3 Painting

- Roof PL 21 Hari 15-Feb-19 21 Hari 7-Mar-19


- Shell PL 98 Hari 8-Mar-19 98 Hari 14-Jun-19