Professional Documents
Culture Documents
The
items highlighted in yellow are additions to the existing spec language.
SECTION 256
RIPRAP AND AGGREGATE CUSHION
256.01 GENERAL.
This work consists of furnishing or salvaging, and placing stone on slopes, channelways,
or other areas.
256.02 EQUIPMENT.
256.03 MATERIALS.
Material Section
Aggregate for
816, Class 8
Aggregate Cushion
816.02 A.2.g and
Quarry Stone
816.02 A.2.h Commented [nah1]: Are these the same tests we would
perform for Quarry Stone?
Wire Mesh 836.03 C
A. Grout.
Proportion grout using one part Portland Cement and two parts sand by volume.
B. Riprap.
Use fieldstone or quarry stone as riprap.
1. Gradation.
Size (Inches) Percent Smaller
28* 80-100
22* 30-80
16 20-50
10 0-5
* The Engineer may allow up to 10 percent of the total stones to be oversized, if
they can be blended into the riprap. Do not use oversized stones greater than
6 inches larger than the specified thickness.
2. Field Stone.
Do not use fieldstone that:
Consists of sandstone, shale, or soft limestone
Contains cracks or flaws that would cause splitting or breakup
Or is easily abraded or crushed
3. Quarry Stone.
Provide quarry stone that consists of materials other than sandstone, limestone, or
stone of sedimentary origin.
256.04 CONSTRUCTION REQUIREMENTS.
A. General.
Place the stones on sloped areas beginning at the toe of the slope. Dig a trench
at least one foot deep and place the largest stones in the trench, filling gaps with
smaller stones. Compact the riprap and provide an even, tight surface.
B. Aggregate Cushion.
Spread aggregate cushion over the specified area before placing the riprap.
Tie adjoining strips with wire every 18 inches. Tie lower layers to upper layers
with wire ties spaced 2 feet center to center longitudinally and transversely.
E. Grouted Riprap
Wet riprap before applying grout. Recess the grout 1 to 3 inches below the top of
the riprap.
B. Aggregate Cushion.
The Engineer will measure the actual surface dimensions of aggregate cushion and
multiply the surface area by the specified depth to determine the cubic yard quantity.
C. Grouted Riprap.
The Engineer will measure the actual surface dimension of grouted riprap to
calculate the grout quantity.
The Engineer will measure Rock used for grouted riprap as specified in Section 256.05
A.
Include excavation and shaping necessary to place the riprap or aggregate cushion in
the price bid for these items.
Such payment is full compensation for furnishing all materials, equipment, labor, and
incidentals to complete the work as specified.