You are on page 1of 6

WK,QWHUQDWLRQDO&RQIHUHQFHRQ5HQHZDEOH(QHUJ\5HVHDUFKDQG$SSOLFDWLRQV 3DULV)5$1&(2FW

From Solar Microgrid Simulation to Field


Deployment: Accuracy and Uncertainties
Fabien Chidanand Robert, Sundararaman Gopalan
Department of Electronics and Communication Engineering,
Amrita Vishwa Vidyapeetham, Amritapuri, India,
chidanand@am.amrita.edu, sundar@am.amrita.edu

Abstract— Economical, stand-alone, solar microgrids stand-alone microgrid when solar resources are lacking and
can be quickly implemented in most un-electrified regions of the load cannot be fully met. There are numerous sources of
the world. Solar resource maps developed by the National inaccuracy: losses in cabling, dust on solar panels, variation
Aeronautics and Space Administration (NASA) and the in load demands, variations in weather and solar irradiance,
National Renewable Energy Laboratory (NREL), together derating of solar cells, shading or even a physical damage on
with HOMER Pro software, have been widely used to a solar cell. Inaccuracies add up and produce imprecisions in
determine the optimal design of microgrids. Repercussions the recommended microgrid design. This leads either to
of imprecise predictions of solar resources and electrical additional project costs or energy shortage during the
power generation lead to an increased likelihood of energy operation phase (see Fig. 1).
shortage in a stand-alone microgrid, or increases overall
project costs. Actual solar energy productions of two sites in Uncertainty in solar resources
Kerala, India, were compared with solar electricity
generation, predicted by the HOMER Pro tool. For both test Inaccuracies in solar PV models and
sites, the results showed that the simulated, solar production internal losses
was within 8.1% of the actual annual production. However,
monthly variations in solar production led to unanticipated
energy shortages in the simulated microgrids. These findings Imprecisions in microgrid design
reaffirm the inexorable need of the following actions for
cost-effective design of microgrids: a) systematic analysis of
reliability of electrical supply, and b) deployment of schemes x Increased project costs or
for demand response and flexible load. Statistical analysis of x Energy shortage during operation
temporal variation of solar irradiance in the United States
were used to inform recommendations for stand-alone Fig 1. Uncertainties and consequences for users
microgrid design. Solar resources are critical inputs in solar microgrid
Keywords—microgrid, solar, model, resource, accuracy, design. At present, satellite data are used to provide solar
HOMER, design. resource maps all over the world. The common practice is to
design a microgrid based on the average solar irradiance that
I. INTRODUCTION can be expected during any hour of the year (without
Access to reliable electrical energy is crucial for material considering that solar radiations vary over the years).
comfort and reduced physical and strenuous work. However, HOMER Pro software can automatically download solar
one person out of five worldwide remains without access to resources from NREL or from the NASA. Both NREL and
electricity. Stand-alone microgrids are quick & easy-to- NASA use different models.
install solutions to light up rural areas and have recently A solar map of India has been developed by NREL in
become affordable. Stand-alone solar microgrids are cooperation with government of India's Ministry of New and
desirable as they require minimal maintenance and technical Renewable Energy. It provides hourly irradiance data, for
expertise [1]. To support their efficient implementation, every 10 km2 of land area. The State University of New
several design techniques have been developed. Due to the York (SUNY) model provided by NREL was developed
complexity of the problem involving numerous parameters, using the semi-empirical satellite model developed by Perez
many researchers [2-7] have used HOMER Pro software and et al. [9], as part of the India-U.S. Energy Dialogue. The
its inbuilt models. HOMER Pro is a simulation software that NREL database was calculated using data from 2002 to 2014
can simulate the design of microgrids, either stand-alone, or and is accessible online, via the following link:
connected to the main electrical power grid. HOMER Pro https://www.nrel.gov/rredc/solar_resource.html.
application can compare several different technologies and
recommend an optimal cost effective design, for a given load Surface meteorology and Solar Energy (SSE) data are
pattern and set of available renewable energy resources. provided by the NASA Science Mission Directorate's
Alternative simulation software (SAM, PVWatts, PVsyst, satellite and re-analysis research programs. Release 8.0 uses
and PV*SOL), which focus only on solar Photo-voltaic data from 1983 to 2013. The solar irradiance data obtained
power generation, were found to estimate the annual solar have been validated, based on recommendations from the
production within 8% of the real solar electricity production NASA’s partners, in the energy industry. Solar data are
[8]. However, there have not been any published reports on available via the web portal: (https://power.larc.nasa.gov/):
the accuracy of HOMER Pro estimations for solar electricity it is supported by the NASA Langley Research Center
production and optimal microgrid design. The accuracy of (LaRC) POWER Project [10].
design is important not only in term of cost but also in term The first aim of this paper is to evaluate the accuracy of
of meeting the demand and avoiding energy shortage (power solar electricity generation calculated by HOMER Pro using
interruptions). Energy shortage is said to have occurred in a

,&5(5$
XXX- 
‹,(((
WK,QWHUQDWLRQDO&RQIHUHQFHRQ5HQHZDEOH(QHUJ\5HVHDUFKDQG$SSOLFDWLRQV 3DULV)5$1&(2FW

NREL and NASA solar irradiance data sets. The second aim resulting discomfort experienced by users is modeled in the
is to test the impact of solar electricity generation error, on literature as a second order polynomial function [11]. Thus,
recommended microgrid designs and the likelihood of the monthly average electrical productions from solar panels
energy shortage for the microgrid users. The actual were compared using the NRMSE, which assigns more
electricity output of solar panels and the output calculated by weight to larger deviations. The annual average solar
simulation were compared for a year, at two locations: production is also an important indicator when microgrids
Amritapuri and Cochin, in Kerala, a southwestern state of are connected with the main grid, or users are able to adjust
India. The simulated outputs were calculated using the their demands for electricity. Therefore, the annual average
technical characteristics of solar panels and their associated, predictions were compared with the actual production
realistic derating factors together with NREL and NASA throughout the year.
solar irradiance data. Stand-alone microgrids were designed
by HOMER Pro to provide electrical power to a load Stand-alone microgrid design simulations were
representing an Indian village of 100 households. Three sets performed to evaluate the impact of a mismatch between
of simulation were performed with the following parameters: actual solar production and simulated (expected) production.
A project developer would either use NREL or NASA data
1) NREL solar irradiance data,
set and design a microgrid according to the simulation output
2) NASA solar irradiance data, and
3) Actual solar production data being directly fed as provided by HOMER Pro. NREL and NASA irradiance data
inputs to the simulation software. were fed into HOMER Pro together with the technical
The monthly electrical production of the simulated, characteristics of solar panels, batteries and inverters. The
stand-alone microgrids were compared using the Normalized optimal designs were calculated by the software in both cases
Root Mean Square Error (NRMSE). The recommended for the two locations. A third set of simulations was
microgrid designs were compared in terms of total project performed where the actual solar electricity generated from
cost, number of solar panels and number of batteries. The the two test-sites was directly fed as inputs to the software.
expected distributions of energy shortage in a year were also In the last case, the software scaled the actual solar
computed and compared. The variability of solar irradiance, production up or down and dimensioned the battery bank to
at a given period, for different years is also discussed. satisfy the electricity demand. The factors of uncertainty
Consequences of such variations on the likelihood of energy responsible for the difference in microgrid design
shortage in a microgrid are detailed. Finally microgrid design recommendations are:
recommendations are proposed. 1) the difference between actual solar irradiance and the
expected solar irradiance from NREL and NASA, and
II. METHOD AND ASUMPTIONS
2) the imprecisions related to environmental factors such as
A. Method shading, derating factors of equipment as well as electrical
Both NREL and NASA datasets were used as inputs to losses in the installation.
HOMER Pro software to compare the expected output of
The designs recommended by the software in each of the
solar panels with the actual solar production from October
three cases, the total project cost, as well as the distribution
2016 to September 2017, for two locations (see Fig. 2). A
of energy shortage throughout the year were compared for
lack of electricity generation compared to the expected value
the two locations (see Fig. 3).
would result in energy shortage in the microgrid. The

Comparison: Monthly Mean


Hourly Solar Irradiance
from NREL Simulated Solar
Model of Solar Panel HOMER Pro Electricity Generation
and Derating Factors Simulations
Hourly Solar Irradiance
Actual Solar Electricity
from NASA
Generation

Fig. 2. Comparison of expected electricity generation vs. actual generation.

Hourly Solar Comparison: Design, Cost, and


Irradiance from: Model of Distribution of Energy Shortage
- NREL Solar Panel Model of
- NASA - Battery Recommended
HOMER Pro
- Inverter Microgrid Designs
Simulations
- Derating Factors
- Load
Actual Hourly Solar Production

Fig. 3. Comparison of microgrid designs obtained using different input data

,&5(5$ 
WK,QWHUQDWLRQDO&RQIHUHQFHRQ5HQHZDEOH(QHUJ\5HVHDUFKDQG$SSOLFDWLRQV 3DULV)5$1&(2FW

B. Assumption
Several parameters have to be estimated in order to The Net Present Cost represents the total cost of the
simulate solar production. HOMER Pro software used GPS microgrid project over its chosen lifetime, which is assumed
coordinates of the microgrid locations to evaluate precisely to be 25 years: the lifetime of the solar panels. In this
the position of the sun in the sky and the angle of incidence simulation, the electrification project was assumed to benefit
of the radiations on the solar panel. The inclination of solar from a loan free of interest to cover the initial investment
panels was chosen equal to the latitude of the sites. Solar (i.e. the real discount rate was assumed to be zero).
panels were modeled by their efficiency, temperature
coefficient, and nominal operating cell temperature. A single III. RESULTS
derating factor can be applied to account for cabling and The electricity generation per month obtained from
dusting losses, as well as Maximum Power Point Tracking simulations was compared with the actual generated units of
(MPPT) tracking errors [12]. The derating factor due to electricity for the two test-sites, Amritapuri and Cochin (see
temperature was computed hourly by HOMER Pro, using Fig. 5). As observed in Fig. 5, the electricity generation
hourly temperature data at the location, and the temperature expected from simulations is often above the actual
coefficient of the solar panel. The temperature data were production. The annual average generation was
obtained from the NASA database. The characteristics of the overestimated by 8.1% in three cases and underestimated by
chosen solar panels are summed up in Table I. 0.3% in the fourth case. These results are satisfying and
It was assumed for the microgrid simulations that a within the accuracy range of other professional software :
village with 100 households has to be electrified. The load SAM, PVWatts, PVsyst, and PV*SOL [8]. Nevertheless,
profile used is shown in Fig. 4. Such load profile corresponds when the simulated monthly solar electricity generations
to a village where approximately 20% of its electricity is were compared with the actual production, the NRMSE was
consumed by home businesses, enterprises or schools [13]. found to vary from 12% to 20% (see Table III). The results
80% is consumed by households with peak consumption in indicate unexpected variations between the simulated
the morning and early at night. It is not cost-effective to monthly production and actual production of electricity.
design a stand-alone microgrid that meets 100% of the Such differences may not have much significance in grid tied
demand [14]. Therefore, simulation designs were computed systems, while in stand-alone microgrids, they may lead to
with an allowed 3% of energy shortage in a year (compared energy excesses in some months and energy shortage in
to the demand). Lead-acid batteries were used for back-up as others.
they are standard in stand-alone microgrids. Their technical Despite anticipating higher solar production, the microgrid
characteristics are shown in Table II. The lifetime is defined designs that were calculated by the simulation software
as the maximal length of time or maximum energy using NREL and NASA solar irradiance had up to 29%
throughput for a battery. As soon as one of these values is more solar panels and 25% more batteries than the designs
reached during a simulation, the battery bank is replaced by performed using the actual solar electricity generation data
the software. The cost of solar panels, inverters, and batteries (see Fig. 6). Inspite of these differences, costs for the
are the benchmark cost provided by the government of India
microgrid projects simulated with NREL and NASA data
[15]. The actual solar production of the two, 31.5 kW solar
installations were measured using a commercial smart meter are within 4.5% of the costs of the designs performed with
placed just before the inverter, on the DC cables coming the actual solar production data. The small financial
from the solar panels. For the microgrid simulations, the difference can be attributed to batteries that must be
inverter and rectifier were modeled as 95% efficient. replaced, more often, in case of designs with fewer batteries.

TABLE I. SOLAR PANEL CHARACTERISTICS TABLE II. BATTERY CHARACTERISTICS


Cost (incl. Life T° Nominal Derating
Effici- inverter and - coeffi operating factor Energy Cost Lifetime Maximal Depth
ency logistic) [15] time cient. cell T° [12] Capacity of Discharge
Capital O&M
(%) Capital O&M (kWh) kWh a %
(a) N.A. (°C) (%) (€) (€/a)
(€) (€/a)
1 75 1.5 800 8 40
18.5 960 10 25 -0.39 47 10

14 TABLE III. ACTUAL ELECTRICAL PRODUCTION VS. ESTIMATED


PRODUCTION BY HOMER PRO USING SOLAR RESOURCE MAPS
Energy Consummed

12 AND MODELED SOLAR PANELS.


10
Amritapuri Cochin
8
(kWh)

6 NREL NASA NREL NASA


Annual vs. vs. vs. vs.
4 average Actual Actual Actual Actual
2 difference
0 (%) -0.3 7.6 8.1 8.1
1 3 5 7 9 11 13 15 17 19 21 23
Hour of the day NRMSE (%) 12.5 12.7 16.0 19.8
Fig. 4. Average daily consumption pattern for the 100 household
community

,&5(5$ 
WK,QWHUQDWLRQDO&RQIHUHQFHRQ5HQHZDEOH(QHUJ\5HVHDUFKDQG$SSOLFDWLRQV 3DULV)5$1&(2FW

Average electricity generation


2.50
Actual NREL NASA Observed
Actual
NREL NASA Observed
2.00

1.50
(kW)

1.00

0.50

0.00

Septemb…

Septemb…
February

June

November
January

March

July
April
May

October
August

December

July

October
August

November
April
May
June
January

March

December
February
a b
Fig. 5. Comparison of actual solar electricity generation vs. expected generation obtained from simulation using satellite data, for 10 kWp of solar panels in
two locations: (a) Amritapuri and (b) Cochin, Kerala, India.

350 NREL
300 NREL
250 NASA NASA
200 Observed
Actual Actual
Observed
150
100 54.5 46.7
42.4 57.1
50 46.7
47.6
0
Solar panels Batteries (kWh) Total Cost (k€)
(kWp) Solar panels Batteries Total Cost (k€)
a b (kWp) (kWh)
Fig. 6. Comparison of microgrid designs recommendations from HOMER Pro using for input: 1) NREL solar irradiance data, 2) NASA irradiance data, and
3) actual solar electricity generation. Two locations: (a) Amritapuri and (b) Cochin.

In spite of anticipating more solar production than the actual microgrid was found to be 18%, when actual solar
production, the designs performed using NREL and NASA production were used in the simulation.
solar irradiance data, recommended more solar panels and It is recommended to encourage villagers to make a
batteries than the designs performed using the actual solar productive usage of electricity to revitalize rural
production data, at both the test locations. This counter development [16]. Unplanned energy shortages adversely
intuitive result can be explained by analyzing the distribution impact users who depend on electricity to generate revenue
of energy shortage during the year. Although the annual (e.g. tailors, small workshop owners). Preventive measures
average solar irradiance may be well estimated, it is not the may be taken to inform them about the expected frequency
case for the distribution of solar resources within a year. The and duration of power interruptions. Forecasting the power
monthly average energy shortage is illustrated in Fig. 7, for output [17] and resorting to demand response mechanisms or
both locations. Even though all the microgrids in this study sequential load shedding [18, 19] may protect such users
were designed with an average energy shortage of 3% per from financial losses when solar energy resources are not
year, one can observe large variations in monthly energy sufficient.
shortage values. The NRMSE measured the error for the
monthly energy shortage obtained by simulation, compared TABLE IV. DIFFERENCE IN MONTHLY ENERGY SHORTAGE
to the monthly energy shortage obtained using actual solar OBTAINED FROM DESIGNS PERFORMED USING SATELLITE
DATA VS. OBTAINED FROM DESIGNS PERFORMED USING
electricity generation data in the simulation. The NRMSE ACTUAL SOLAR PRODUCTION.
values were found to be in the range of 100% in all the four
cases (see Table IV). This confirms that the expected Amritapuri Cochin
distribution of solar irradiance during the year was
NREL NASA NREL NASA
significantly different from the actual solar irradiance. For
example, the simulations performed using NREL and NASA vs. vs. vs. vs.
solar data, anticipated an average energy shortage of 9% in Actual Actual Actual Actual
the month of June, while the energy shortage in the Normalized
102 84 130 111
RMSE (%)

,&5(5$ 
WK,QWHUQDWLRQDO&RQIHUHQFHRQ5HQHZDEOH(QHUJ\5HVHDUFKDQG$SSOLFDWLRQV 3DULV)5$1&(2FW

1
Average demand in the village: 5.7kW NREL
Average energy
shortage (kW)
0.8
NREL NASA
0.6
NASA Observed
Actual
0.4
Actual
Observed
0.2
0

Decem…
Novem…
Septe…

Decem…
Novem…
Septe…
June
February
March
January

April
May

July

October
August

June
February
January

March

July
April
May

October
August
a b
Fig. 7. Monthly energy shortage in microgrids designed, using different input data and with annual energy shortage of 3%: 1) NREL solar irradiance, 2)
NASA solar irradiance, and 3) actual solar electricity generation in a) Amritapuri, and b) Cochin, Kerala, India.

x NREL or NASA solar irradiance data minus 12.5%


IV. VARIABILITY OF SOLAR IRRADIANCE
for the four months with the least irradiance on the
A. Statistics tilted solar panels. (67% confidence rule)
The previous results show that the difference between x NREL or NASA solar irradiance data minus 25%
expected and actual solar irradiance can lead up to 18% of for the four months with the least irradiance on the
the energy demand not being met in a month (twice as much tilted solar panels (95% confidence rule)
as anticipated). The impact of weather variations on
reliability of supply in a stand-alone microgrid has recently Fig. 8 presents the optimal microgrid designs obtained from
been studied [20]. Nevertheless, no statistical data could be HOMER Pro simulations with NREL solar irradiance data
found related to the yearly variability of solar resources in of Amritapuri, in the above-mentioned three cases. The first
India. In the United States (US), NREL conducted a study case is identical to the case illustrated in Fig. 6a. The
for the variability of total irradiance reaching a tilted surface examples shown in Fig. 8 were computed assuming that the
with an angle equal to the latitude of the concerned location yearly variation in solar resources is similar to what is
(the standard tilt angle of solar panels) [21]. Their findings commonly observed in the US but considering that the
show that for the large majority of the US, the annual month with minimal solar irradiance are different in Kerala,
average solar irradiance can be estimated within 8%, with a India: May, June, July and August. The results show that it
confidence rule of 95% (i.e. By assuming a Gaussian costs 12% more than indicated by HOMER Pro (using
distribution for the annual total irradiance, there is a 95% average solar irradiance values) to guarantee that energy
likelihood that measurements for any given year will be shortage constraints are respected with a confidence rule of
within this range). Nonetheless, it is also shown that the 95% (light blue on Fig. 8). If the confidence rule is relaxed
monthly variation in solar irradiance is much higher. In the to 67%, then the cost increase is 6% compared to the
US, minimum solar irradiance occurs, during the months of original HOMER Pro design (dark blue on Fig.8).
November to February, and is commonly 20% less than the Reduced solar resources increased the requirement in
annual average. These four months happen to have the solar panels. Nonetheless, it did not affect the recommended
highest level of variability in solar resources. Based on the number of batteries. This is because in this simulation, the
figures presented in [21], the monthly average solar distribution of solar resources within a month remained
irradiance of those four months can only be estimated within unchanged despite the changes in monthly average. Thus,
25% with a confidence rule of 95%, or within 12.5% with a the reduction of solar resources was fully compensated by
confidence rule of 67%. In other words, over several years, additional solar panels.
5% of observations for the monthly total irradiance are
350 Design performed with
likely to be outside the +/-25% interval around the monthly
NREL solar resources
average, and 33% of the observations are likely to be 300
outside the +/-12.5% interval. Thus, a stand-alone microgrid 250
is likely to lack renewable energy supply during these 173 184
months, if it is designed according to the average irradiance 200 Design performed with
163
value. 150 NREL resources -12.5% on
100 May, June, July and
B. Microgrid Design Recommendations August monthly averages
When designing a stand-alone microgrid, the requirements 50
0 Design performed with
for the reliability of electrical supply have to be well
NREL resources -25% on
understood. It is recommended to explore possibilities of May, June, July and
adjusting the demand when supply of renewable energy is August montly averages
temporarily inadequate. Depending on the requirement for
the reliability of supply, the simulation design for a stand-
alone microgrid can be performed with:
x NREL or NASA solar irradiance data, Fig. 8 Microgrid designs for different assumption of solar resources

,&5(5$ 
WK,QWHUQDWLRQDO&RQIHUHQFHRQ5HQHZDEOH(QHUJ\5HVHDUFKDQG$SSOLFDWLRQV 3DULV)5$1&(2FW

In reality, the distribution of solar irradiance within a [5] S. Sinha and S. Chandel, “Review of software tools for hybrid
renewable energy systems”. Renewable And Sustainable Energy
month may vary from year to year, with variable lengths of Reviews, vol. 32, pp 192-205, 2014.
cloudy days in a month. This phenomenon needs to be [6] F.C. Robert and S. Gopalan, “Low cost, highly reliable rural
discussed in a future finer analysis. Nevertheless, in order to electrification through a combination of grid extension and local
avoid unexpected energy shortage the need to consider renewable energy generation”,Sustainable Cities and Society, Vol. 42,
yearly variation in solar resources has been made obvious. pp. 344-354, 2018.
[7] S. R. Alvarez, A. M. Ruiz and J. E. Oviedo, "Optimal design of a
V. CONCLUSION diesel-PV-wind system with batteries and hydro pumped storage in a
Colombian community," 2017 IEEE 6th International Conference on
Generation of solar electricity was estimated by HOMER Renewable Energy Research and Applications (ICRERA), San Diego,
Pro using NREL and NASA solar irradiance data sets. The CA, 2017, pp. 234-239
simulation results, for two locations in Kerala, India, were [8] J. Freeman, J. Whitmore, N. Blair and A. P. Dobos, “Validation of
Multiple Tools for Flat Plate, Photovoltaic Modeling Against
compared with the actual measurements. The impacts of Measured Data”, Technical Report NREL/TP-6A20-61497, Natioanal
errors in prediction were measured by performing microgrid Renewable Energy Laboratory (NREL), 2014.
design simulations. Repercussions on hardware requirement, [9] R. Perez, T. Cebecauer, M. Suri, “Semi-Empirical Satellite Models”,
total cost, and temporal distribution of energy shortage were Solar Resource Assessment and Forecasting (Editor Jan Kleissl),
assessed. The results for the test-sites at Amritapuri and Elsevier, 2013
Cochin in Kerala, India showed that the predicted [10] W. P. Stackhouse Jr , T. Zhang , D. Westberg , A. J. Barnett, T.
Bristow, B. Macpherson and J. M. Hoell, “POWER Release 8 (with
generation of electricity for a complete year was within 8% GIS Applications) Methodology (Data Parameters, Sources, &
of the actual solar production. The observed results are Validation)”, 2018.
acceptable, as they lie within the accuracy of other https://power.larc.nasa.gov/documents/POWER_Data_v8_methodolo
specialized software [8]. However, monthly variations in gy.pdf [accessd on July 2018]
electricity generation were not captured with the same level [11] P. Samadi, A. H. Mohsenian-Rad, R. Schober, V. W. S. Wong and J.
Jatskevich, “Optimal real-time pricing algorithm based on utility
of accuracy. When stand-alone microgrids were designed to maximization for smart grid”, [First IEEE Inter. Conf. on Smart Grid
power a typical village load, the NRMSE values, for the Communications, Gaithersburg, pp. 415-420, 2010].
monthly predicted occurrence of energy shortage were in the [12] F. C. Robert, G. S. Sisodia, and S. Gopalan, “An intelligent approach
range of 100%. Such unplanned power interruptions in to strengthening of the rural electrical power supply using renewable
energy resources”, 2nd Inter. Conf. on Green Energy Technology
stand-alone microgrids may affect users who use electricity (ICGET 2017) [IOP Conf. Series: Earth and Environmental Science,
for their livelihood. In the US, NREL found that the 83, 012005, 2017].
variability of solar resources is higher during the four [13] F. C. Robert, G. S. Sisodia and S. Gopalan, "The critical role of
months with minimal solar resources with an accuracy of anchor customers in rural microgrids: Impact of load factor on energy
prediction of +/-25% with a confidence rule of 95%. This cost," 2017 International Conference on Computation of Power,
Energy Information and Commuincation (ICCPEIC), Melmaruvathur,
finding was extrapolated to India, and the recommendation 2017, pp. 398-403.
is to avoid designing microgrids based on monthly and [14] M. Lee, D. Soto and V. Modi, “Cost versus reliability sizing strategy
yearly average solar resources. Instead, design can be done ˆ‘” ‹•‘Žƒ–‡† ’Š‘–‘˜‘Ž–ƒ‹… ‹…”‘Ǧ‰”‹†• ‹ –Š‡ †‡˜‡Ž‘’‹‰ ™‘”Ž†dzǡ
according to the amount of solar resource that can be ‡‡™ƒ„Ž‡‡”‰›ǡ˜‘ŽǤ͸ͻǡ’’Ǥͳ͸ǦʹͶǡʹͲͳͶǤ
guaranteed at a chosen level of confidence. Such method [15] Ministry of New and Renewable Energy (MNRE), ”Benchmark cost
for off-grid and decentralized solar PV application programme for the
will ensure that the level of energy shortage in microgrids is year 2017-18”, No.30/11/2012-13/NSM, 2017.
acceptable. [16] R. Nair et al., "Community development and energy equality:
Although microgrid modeling has gone through Experiences from micro hydro implementation in a tribal settlement
impressive upgrades in the last ten years, this short study in India," [2016 IEEE Region 10 Humanitarian Technology Conf.
highlights the crucial need for better knowledge of (R10-HTC), Agra, pp1-7, 2016].
prediction errors and accuracy of prevailing weather models [17] R. Nageem and R. Jayabarathi, “Predicting the Power Output of a
Grid-Connected Solar Panel Using Multi-Input Support Vector
and microgrid design recommendations. Accurate short- Regression”, [Procedia Computer Science, vol. 115, pp 723-730,
term weather and energy consumption forecast, as well as 2017].
demand response technics, are promising enhancements [18] F.C. Robert, G. S. Sisodia, S. Gopalan, “A critical review on the
which will foster improved usability of solar resources in utilization of storage and demand response on the implementation of
rural microgrids. renewable energy microgrids”, Sustainable Cities and Society, vol.
40, pp 735-745, 2018.
REFERENCES [19] A. Scalfati, D. Iannuzzi, M. Fantauzzi and M. Roscia, "Optimal sizing
of distributed energy resources in smart microgrids: A mixed integer
[1] K. Palaniappan and R. M. Cuzner, "Educating students as a means to linear programming formulation," 2017 IEEE 6th International
help people in a low income community live in a DC microgrid Conference on Renewable Energy Research and Applications
laboratory," 2017 IEEE 6th Inter. Conf. on Ren. Energy Research and (ICRERA), San Diego, CA, 2017, pp. 568-573.
Applications (ICRERA), San Diego, CA, pp. 339-344, 2017.
[20] A. Abdulkarim, S. M. Abdelkader, D. J. Morrow, A. J. Falade, A.U.
[2] N. Ramchandran, R. Pai, and A. Parihar, “Feasibility assessment of Lawan, Iswadi HR, “Effect of Weather and the Hybrid Energy
Anchor-Business-Community model for off-grid rural electrification Storage on the Availability of Standalone Microgrid”, International
in India” Ren. Energy, vol. 97, pp. 197-209. 2016. Journal of Renewable Energy Research, Vol.6, No.1, 2016. With the
[3] W. Amutha and V. Rajini, “Cost benefit and technical analysis of last paragraph.
rural electrification alternatives in southern India using HOMER”. [21] S. Wilcox, C. A. Gueymard, Spatial and Temporal Variability of the
Ren. And Sustainable Energy Reviews, vol. 62, pp. 236-46, 2016. Solar Resource in the United States, ASES Solar 2010, 2010,
[4] R. Sen, and S. Bhattacharyya, “Off-grid electricity generation with available online:
renewable energy technologies in India: An application of HOMER”. https://www.nrel.gov/grid/solar-resource/assets/data/ases_47760_final.pdf
Renewable Energy, vol. 62, pp. 388-98, 2014.

,&5(5$ 

You might also like