Professional Documents
Culture Documents
When does delay arise? Under the Civil Code, delay begins from the time the
obligee judicially or extrajudicially demands from the obligor the performance of
Facts: the obligation.
SSS approved R’s application for an interim loan amounting to 30M pesos for a
housing project. There are only three instances when demand is not necessary to render the obligor
in default. These are the following:
9,595,000 of the 30M was initially released to R. “(1) When the obligation or the law expressly so declares;
2,659,700 was subsequently released to R. Then R gave SSS a promissory note to (2) When from the nature and the circumstances of the obligation it appears that
SSS for the total amount released to them. the designation of the time when the thing is to be delivered or the service is to be
rendered was a controlling motive for the establishment of the contract; or
R then made a total payment of 23,657,901.84 for the loan principal of 12M (3) When the demand would be useless, as when the obligor has rendered it
released to them. The last payment made by Moonwalk in the amount of beyond his power to perform.
P15,004,905.74 were based on the Statement of Account prepared by P SSS.
This case does not fall within any of the established exceptions. Petitioner is not
After settlement of account, SSS released to R the RELEASE OF MORTGAGE for excused from making a demand. Moonwalk has been long delinquent in meeting
R’s mortgage properties. Then, SSS sent letters to R alleging that it committed and its monthly arrears however mere delinquency in payment does not necessarily
honest mistake in releasing defendant. mean delay in the legal concept.
R replied, stating that it had completely paid its obligation Nowhere in this case did it appear that SSS demanded from Moonwalk the
payment of its monthly amorizations. Thus, moonwalk was never in default
Trial Court - dismissed SSS complain on the ground that the obli was already because it was never compelled of performance.
extinguished by the payment of Moonwalk and by SSS act of cancelling the real
estate mortgages. <R was dismissed Thus, this Court agrees with the decision of the respondent court.
IAC - affirmed trial court The case at bar does not refer to any penalty provided for by law nor does it refer to
the non remittance of premium. The case at bar refers to a contract of loan entered
Hence, this petition into between plaintiff and defendant Moonwalk Development and Housing
Corporation. Note, therefore, that no provision of law is involved in this case, nor is
Issue: WON penalty is still demandable even after the extinguishment of the there any penalty imposed by law nor a case about non-remittance of premium
principal obligation? required by law. The present case refers to a contract of loan payable in
installments not provided for by law but by agreement of the parties.
Held:
Article 1226 of the Civil Code provides… SSS cannot condone a mandatory provision of law providing for the payment of
premiums and for penalties for non remittance. what is sought to be condoned or
A penal clause is an accessory undertaking to assume greater liability in case of waived are penalties not imposed by law for failure to remit premiums required by
breach. It has a double function: (1) to provide for liquidated damages, and (2) to law, but a penalty for non payment provided for by the agreement of the parties in
strengthen the coercive force of the obligation by the threat of greater the contract between them.
responsibility in the event of breach. From the foregoing, it is clear that a penal
clause is intended to prevent the obligor from defaulting in the performance of his
obligation.
RCBC vs. CA
could have easily called the attention of the PR so that the latter could affix his
Facts: signature. Notably, all the other checks issued by the appellee dated subsequent to
Respodent Atty Lustre, purchased a Toyota Corrola from Toyota Shaw to be paid August 10, 1991 and dated earlier than the demand letter, were duly encashed.
in 24 equal monthly installment. Atty. Lustre thus issued 24 postdated checks as This fact should have already prompted the appellant bank to review its action
payment. relative to the unsigned check.
To secure the balance, Atty. Lustre executed a promissory note and a contract of > Nevertheless, contracts of adhesion are not invalid per se; they are not entirely
chattel mortgage over the vehicle in favor of Toyota Shaw. The contract provided prohibited. While ambiguities in a contract of adhesion are to be construed against
for an acceleration clause stating that should the mortgagor default in the the party that prepared the same, stipulations in such contract are obscure or
payment of any installment, the whole amount remaining unpaid shall become ambiguous. If the terms thereof are clear and leave no doubt upon the intention of
due. In addition, the mortgagor shall be liable for 25% of the principal due as the contracting parties, the literal meaning of its stipulations shall control.
liquidated damages.
>Article 1170 of the Civil Code states that those who in the performance of their
Toyota Shaw assigned all its rights and interests to P RCBC. All the checks were obligations are guilty of delay are liable for damages. The delay in the performance
encashed and debited by RCBC from Atty. Lustre’s accounts except for one which of the obligation, however, must be either malicious or negligent. There is no
was unsigned. imputation, much less evidence, that private respondent acted with malice or
> Previously, the amount of such check was debited from PR’s account but was negligence in failing to sign the check.
later recalled and re-credited to him. Because of such recall, the last 2 checks were
no longer presented for payment. Apparently, this was in conformity with the >Petitioner’s conduct, in the light of the circumstances of this case, can only be
bank’s procedure that once a client’s account was forwarded to its account described as mercenary. Petitioner had already debited the value of the unsigned
representative, all remaining checks outstanding as of the date the account was check from private respondent’s account only to re-credit it much later to him.
forwarded were no longer presented for payment. Thereafter, petitioner encashed checks subsequently dated, then abruptly refused
to encash the last two.
Acting on the theory that PR defaulted in his payments, P demanded from PR the
payment of the balance including the liquidated damages.
PR refused.
RTC - ruled in favor of PR, ordered P RCBC to accept the three checks as payment,
cancel the mortgage on the car, and pay PR for damages.
In the afternoon, P was able to buy from another store but since it was already
dark, the construction would start the following morning - however due to time
constraints, the niche was not finished before christmas day and was only
completed in dec 26, afternoon.
SC - upheld RTC’s decision. Alviar was negligent and incurred in delay in the
performance of his contractual obligation. Contrary to the appellate court’s factual
determination, there was a specific time agreed upon (P inquired if it could be
PANTALEON vs. AMERICAN EXPRESS INTERNATIONAL
Held:
Facts: Generally, the relationship between a credit card provider and its card holders is
P and his wife were about to purchase a diamond, pendant, and chain which that of creditor-debtor, with the card company as the creditor extending loans and
totaled USD 13, 826.00 and to pay for these, P presented his AMEX credit card and credit to the card holder, who as debtor is obliged to repay the creditor.
his passport to the Coster sales clerk. (9:15, 15 mins before the tour group was This relationship already takes exception to the general rule that as between a
scheduled to depart from the store) bank and its depositors, the bank is deemed as the debtor.
> P is asking us, not baselessly, to again shift perspectives and again see
Charge purchase was referred electronically to R’s Amsterdam Office at 9:20 am the credit card company as the debtor/obligor, insofar as it has the obli to
but after 10 mins, it still had not yet been approved. At 9:40, with the entire tour the customer as creditor/obligee to act promptly on its purchases on credit.
group was already waiting for them, P asked the store clerk to cancel the sale.
If there was delay on the part of respondent in its normal role as creditor to the
Clerk asked to wait a few more minutes. 15 minutes later, P was informed that R cardholder, such delay would not have been in the acceptance of the performance
demanded bank references to which P supplied information. of the debtor’s obligation (i.e., the repayment of the debt), but it would be delay in
the extension of the credit in the first place.
10am/45 mins after the presentation of card, Coster decided to release the items >Such delay would not fall under mora accipiendi, which contemplates that
even without R’s approval of the purchase. The tour group’s schedule for the day the obligation of the debtor, such as the actual purchases on credit, has
was cancelled due to lack of time. already been constituted.
Same thing happened to P while they were in the US. Hence, after coming back to Herein, the establishment of the debt itself (purchases on credit of the jewelry) had
Manila, P sent a letter to R demanding an apology for the inconvenience and not yet been perfected, as it remained pending the approval or consent of the
humiliation. respondent credit card company.
R sent a letter stating among others that the delay was attributable to the The findings of the trial court, amply established that the tardiness on the part of
circumstance that the purchase was out of the usual charge purchase pattern the respondent in acting on P’s purchase did constitute delay on its part in
established. complying with its obligation to act promptly on its customer’s purchase request.
Aggrieved, P instituted and action for damages. P argues that the failure to timely The waiting time of one hour was long enough time for the customer to walk to a
approve or disapprove the purchase constituted mora solvendi on the part of the R bank a km away, withdraw money over the counter, and return to the store.
in the performance of its obligation.
Obli was to approve/disapprove in timely dispatch not to approve instantaneously.
RTC - concluded that R had been in clear delay based on the standard that the Had R disapproved P’s purchase within second, this action would have never seen
normal approval time for purchase was “a matter of seconds.” (CAS) record on the the light of day.
Amsterdam transaction shows how Amexco Netherlands viewed the delay as
unusually frustrating. Netherlands office continuously asked Manila office “how The culpable failure of respondent herein is not the failure to timely approve
long will this take?” The Court is convinced that defendants delay constitute[s] petitioner’s purchase, but the more elemental failure to timely act on the same,
breach of its contractual obligation to act on his use of the card abroad “with whether favorably or unfavorably.
special handling. In that way, petitioner would have had informed basis on whether or not to pursue
the transaction at Coster, given the attending circumstances.
The delay committed by defendant was clearly attended by unjustified neglect and
Issue: WON R had committed a breach of its obligations to Pantaleon? bad faith, since it alleges to have consumed more than one hour to simply go over
plaintiff’s past credit history with defendant, his payment record and his credit and
bank references, when all such data are already stored and readily available from
its computer.
LORENZO SHIPPING CORP vs. BJ MARTHEL INTERNATIONAL respondent upon petitioner in contravention of the express provision of Article
1169 of the Civil Code.
Facts:
P is a domestic corporation engaged in coastwise shipping. Hence this petition.
R is engaged in trading, marketing, selling of various industrial commodities.
Issue: Was there late delivery of the subjects of the contract of sale to justify
R has been supplying P with spare parts for the latter’s marine engines. petitioner to disregard the terms of the contract considering that time was of the
1989, P asked R for a quotation for various machine parts which R furnished and essence thereof?
stipulated in the quotation was:
Delivery: Within 2 months after receipt of firm order Held:
Terms: 25% upon delivery, balance payable in 5 bi- monthly Petitioner theorizes that the quotation embodied the offer from respondent while
equal Installment[s] not to exceed 90 days. the purchase order represented its (petitioner’s) acceptance of the proposed terms
of the contract of sale. Thus, petitioner is of the view that these two documents
P then issued a purchase order but instead of paying the 25% DP, it issued 10 post-
“cannot be taken separately as if there were two distinct contracts.”
dated checks. Subsequently, P issued another purchase order. This order stated the
term of payment to be “25% upon delivery, balance payable in 5 bi-monthly equal
We do not agree. It is a cardinal rule in interpretation of contracts that if the terms
installment[s].” Like the first order, this one did not state the date of the delivery.
thereof are clear and leave no doubt as to the intention of the contracting parties,
the literal meaning shall control
R deposited P’s check however it was dishonored due to insufficiency of funds and
the remaining post-dated checks were returned to P > P claimed that it
In this case, both Purchase Order made no mention at all of the due dates of the
replaced the check with a good one > R insisted that it returned delivery. This court ruled in Bugatti v. CA we reiterated the principle that “[a]
said check with P contract undergoes three distinct stages— preparation or negotiation, its
perfection, and finally, its consummation. Negotiation begins from the time the
R then placed the order with its principal in Japan by opening a letter of credit prospective contracting parties manifest their interest in the contract and ends at
under its own name. R then delivered that cylinder liners at P’s warehouse. The the moment of agreement of the parties. The perfection or birth of the contract
sales invoices both contain the notation “subject to verification” and signed by P’s takes place when the parties agree upon the essential elements of the contract.
warehouseman. The last stage is the consummation of the contract wherein the parties fulfill or
perform the terms agreed upon in the contract, culminating in the extinguishment
R then sent a Statement of Account to P. The 2 cylinder liners remained unsettled. thereof.”
R’s VP sent a demand letter to P requiring P to pay for the liners. >the formal quotation represented the negotiation phase of the contract
> Instead of paying full amount, P offered to pay only 150K, claiming that the and as of that time, the parties had not yet reached an agreement.
cylinder liners were delivered late and due to the scrapping of the M/V, they would
have to sell the cylinder liners and pay the balance from the proceeds. Notably, petitioner was the one who caused the preparation of Purchase Orders
> R sent another demand letter requiring P to settle its obligation. yet it utterly failed to adduce any justification as to why said documents contained
> Due to P’s failure, R filed before RTC. terms which are at variance with those stated in the quotation provided by
respondent. The only plausible reason for such failure on the part of petitioner is
RTC - held R bound to the quotation it submitted with respect to the terms of that the parties had, in fact, renegotiated the proposed terms of the contract of
payment and delivery of the order. It also declared that R had agreed to the sale. Moreover, as the obscurity in the terms of the contract between respondent
cancellation of the contract when it returned the postdated checks issued by and petitioner was caused by the latter when it omitted the date of delivery of the
petitioner. cylinder liners in the purchase orders and varied the term with respect to the due
CA - reversed RTC. Held that respondent could not have incurred delay in the date of the down payment, said obscurity must be resolved against it.
delivery of cylinder liners as no demand, judicial or extrajudicial, was made by
The failure of petitioner to notify respondent of said date is fatal to its claim that
time was of the essence in the subject contracts of sale.
We, therefore, hold that in the subject contracts, time was not of the essence. The
delivery of the cylinder liners on 20 April 1990 was made within a reasonable period
of time considering that respondent had to place the order for the cylinder liners
with its principal in Japan and that the latter was, at that time, beset by heavy
volume of work.
There having been no failure on the part of the respondent to perform its
obligation, the power to rescind the contract is unavailing to the petitioner. Here,
there is no showing that petitioner notified respondent of its intention to rescind
the contract of sale between them.
SOLAR HARVEST VS. DAVAO CORRUGATED CARTON CORPORATION
In reciprocal obligations, as in a contract of sale, the general rule is that the
Facts: fulfillment of the parties’ respective obligations should be simultaneous. Hence, no
P entered into an agreement, not reduced into writing, with R for the purchase of demand is generally necessary because, once a party fulfills his obligation and the
corrugated carton boxes for P’s business of exporting fresh bananas. USD 1.10 each other party does not fulfill his, the latter automatically incurs in delay.
>But when different dates for performance of the obligations are fixed, the
P deposited on March 31, 1998, US$40,150.00 in respondent’s US Dollar Savings default for each obligation must be determined by the rules given in the
Account with Westmont Bank, as full payment for the ordered boxes. first paragraph of the present article, that is, the other party would incur in
delay only from the moment the other party demands fulfillment of the
Despite such payment, P did not receive any boxes from R. former’s obligation. Thus, even in reciprocal obligations, if the period for
Jan 3, 2001, P wrote a demand letter for reimbursement of amount paid. the fulfillment of the obligation is fixed, demand upon the obligee is still
necessary before the obligor can be considered in default and before a
Feb 19, 2001, R replied that the boxes had been completed as early as April 3, 1998 cause of action for rescission will accrue.
and that petitioner failed to pick them up from R’s warehouse 30 days from
completion as agreed upon. R mentioned that P even placed an additional order of Indeed, there was lack of demand by P upon R to fulfill its obligation to
24k boxes, out of which, 14K had been manufactured without any advanced manufacture and deliver the boxes. The complaint only alleged that P made a
payment from P. follow-up.
> R then demanded P to remove the boxes from the factory and to pay the
balance for additional boxes and storage fee. There is ample showing that the boxes had already been manufactured by
respondent. We note that R was willing to shoulder expenses for a representative
P filed a complaint, averred that the parties agreed that the boxes will be delivered of the court to visit the plant and see the boxes. We also believe that the
within 30 days from payment but respondent failed to manufacture and deliver the agreement between the parties was for petitioner to pick up the boxes from
boxes within such time. respondent’s warehouse, contrary to petitioner’s allegation. Thus, it was due to
>R stated that P’s representative went to the factory and saw that the petitioner’s fault that the boxes were not delivered to TADECO.
boxes were ready for pick up and months later, rep visited again and
advised R to sell the boxes as rejects to recoup the cost of the unpaid boxes In sum, the Court finds that petitioner failed to establish a cause of action for
because P’s transaction to ship bananas to China did not materialize. rescission, the evidence having shown that respondent did not commit any breach
of its contractual obligation. As previously stated, the subject boxes are still within
RTC - ruled that R did not commit and breach of faith that would justify rescission respondent’s premises. To put a rest to this dispute, we therefore relieve
of contract and reimbursement of the amount paid by petitioner. respondent from the burden of having to keep the boxes within its premises and,
consequently, give it the right to dispose of them, after petitioner is given a period
CA - held that P failed to discharge its burden of proving what it claimed to be the of time within which to remove them from the premises.
parties’ agreement with respect to the delivery of the boxes. It was unthinkable
that over a period of more than 2 years, P did not even demand for the delivery of
boxes. R would be liable for breach of contract as P had not yet demanded from it
the delivery of the boxes. CATHAY PACIFIC AIRWAYS vs. VASQUEZ
Issue: WON there was delay in the performance of R’s obligation to P? Facts:
Cathay Pacific accords its frequent flyers membership in its Marco Polo Club. One
Held: The right to rescind a contract arises once the other party defaults in the of the several privileges that the members enjoy is that a frequent flyer booked in
performance of his obligation. In determining when default occurs, Art. 1191 the Business Class has priority for upgrading to First Class if the Business Class
should be taken in conjunction with Art. 1169 of the same law. Section is fully booked.
at Dr. Vazquez, although it might seemed that way to the latter. It did not find her
Respondent-spouses Vasquez are frequent flyers and gold card members of its to have acted with deliberate malice, deceit, gross negligence or bad faith.
marco polo club. The pair, together with their friend went to hongkong and on
their return flight to Manila, upon presenting their boarding pass, the ground Issue:
stewardess saw a message that the couple were being upgraded to first class. Ms. 1. WON by upgrading the seat accommodation of the Vazquezes from Business
Chiu informed the pair but they refused as it would not look nice that they would Class to First Class Cathay breached its contact of carriage with the Vazquezes
be in 1st class while their guests would remain in business class. 2. WON the upgrading was tainted with fraud or bad faith
3. WON the Vazquezes are entitled to damages
Ms. Chiu then informed them that if they would not avail of the privilege, they
would not be allowed to take the flight. Respondents fave in after talking to their Held:
friends. 1. Breach of contract is defined as the “failure without legal reason to comply with
the terms of a contract. It is also defined as the “[f]ailure, without legal excuse,
Upon their return to Manila, R demanded that they be indemnified in the amount to perform any promise which forms the whole or part of the contract.” It
of 1M for the humiliation and embarrassment caused by its employees. turned out that the Business Class was overbooked in that there were more
passengers than the number of seats. Thus, the seat assignments of the
After Cathay’s failure to give them any feedback within its self-imposed deadline, R Vazquezes were given to waitlisted passengers, and the Vazquezes, being
instituted before RTC an action for damages against Cathay. members of the Marco Polo Club, were upgraded from Business Class to First
R’s claimed that Ms. Chiu was loud and discourteous and embarrassed them. They Class.
also claimed that they were unjustifiably delayed to board the plane.
The Vazquezes should have been consulted first whether they wanted to
Cathay alleged that it is a practice among commercial airlines to upgrade avail themselves of the privilege or would consent to a change of seat
passengers to the next better class of accommodation, whenever opportunity accommodation before their seat assignments were given to other
arises, such as when a certain section is fully booked. When Dr. Vazquez refused, passengers. They clearly waived their priority or preference when they
he then stood at the entrance & blocked the queue of passengers from boarding asked that other passengers be given the upgrade. It should not have been
the plane, which inconvenienced other passengers. imposed on them over their vehement objection. By insisting on the
upgrade, Cathay breached its contract of carriage with the Vazquezes.
Cathay also asserted that its employees at the Hong Kong airport acted in good
faith in dealing with Vazquezes. Cathay also testified that overboooking is a widely 2. Court is not convinced that the upgrading or the breach of contract was
accepted practice in the airline industry and is in accordance with the International attended by fraud or bad faith. They are serious accusations that can be so
Air Transport Association regulations. conveniently and casually invoked, and that is why they are never
presumed. They amount to mere slogans or mudslinging unless
Trial Court - Found for the Vazquezes. According to them, cathay offers various convincingly substantiated by whoever is alleging them. She was honest in
classes of seats from which passengers are allowed to choose regardless of their telling them that their seats were already given to other passengers and
reasons or motives. The choice imposes a clear obligation on Cathay to transport the Business Class Section was fully booked. Needless to state, an
the passengers in the class chosen by them. The carrier cannot, without exposing upgrading is for the better condition and, definitely, for the benefit of the
itself to liability, force a passenger to involuntarily change his choice. Cathay’s passenger.
actuations in this case displayed deceit, gross negligence, and bad faith, which
entitled the Vazquezes to awards for damages. There was no evidence of over- booking of the plane beyond ten percent,
and no passenger was ever bumped off or was refused to board the
CA - Ratiocinated that by upgrading the Vazquezes to First Class, Cathay novated aircraft.
the contract of carriage without the former’s consent. However, Ms. Chiu shouted
3. In this case, we have ruled that the breach of contract of carriage, which
consisted in the involuntary upgrading of the Vazquezes’ seat
accommodation, was not attended by fraud or bad faith.
MERALCO v. RAMOY that “as a public utility, MERALCO has the obligation to discharge its functions with
utmost care and diligence.”
Facts:
1987, National Power Corporation filed with the MTC QC a case for ejectment The Court agrees with CA that Meralco failed to exercise the utmost degree of care
against several persons allegedly illegally occupying its properties in Baesa,QC. and diligence required of it. To repeat, it was not enough for MERALCO to merely
Among the defendants in the ejectment case was Ramoy. rely on the Decision of the MTC without ascertaining whether it had become final
and executory. Verily, only upon finality of said Decision can it be said with
MTC QC - rendered judgment for Meralco and ordered D to demolish or remove conclusiveness that respondents have no right or proper interest over the subject
the building and structures they built on the land of P. property, thus, are not entitled to the services of MERALCO.
NPC wrote Meralco requesting for the immediate disconnection of electric power The utmost care and diligence required of MERALCO necessitates such great
supply to all residential and commercial establishments in Baesa, QC. Ramoy’s was degree of prudence on its part, and failure to exercise the diligence required means
included in the list of establishments. Meralco then issued notice of disconnection that MERALCO was at fault and negligent in the performance of its obligation.
to R
This being so, MERALCO is liable for damages under Article 1170 of the Civil Code.
In due time, the electric service connection of the R was disconnected. R Ramoy
testified that they are the registered owner of the parcel of land and that their
property was OUTSIDE the NPC property. They informed the Meralco foreman of
such fact but since he was threatened and told not to interfere, their electric power
was cut off.
It was found out that the residence of R Ramoy was indeed outside the NPC
Property.
RTC - ruled in favor of Meralco and dismissed R’s claim for damages. However, it
ordered Meralco to restore the electric power supply of respondents.
CA - faulted Meralco for not requiring from NPC a writ of execution or demolition
and in not coordinating with the court sheriff. Held Meralco liabe for damages.
Issue: WON Meralco was negligent when it disconnected the subject electric
service of R?
Held:
R’s cause of action against Meralco is anchored on culpa contractual or breach of
contract for the latter’s discontinuance of its service to respondents under Article
1170 of the Civil Code.
AREOLA vs. CA
Article 1173 also provides that the fault or negligence of the obligor consists in the
omission of that diligence which is required by the nature of the obligation and Facts:
corresponds with the circumstances of the persons, of the time and of the place.
The Court emphasized in Ridjo Tape & Chemical Corporation v. Court of Appeals
P was issued a Personal Accident Insurance Policy by R. However, after 7 months, R Malapit’s fraudulent act of misappropriating the premiums paid by petitioner-
unilaterally cancelled the same since company records revealed that P failed to pay insured is beyond doubt directly imputable to respondent insurance company.
his premiums.
> covered a one year period Malapit was the manager of its Baguio branch. It is beyond doubt that he
> P paid for the premium, documentary stamp and premium tax but did not represented its interests and acted in its behalf. His act of receiving the premiums
receive any official receipt. collected is well within the province of his authority. Thus, his receipt of said
> Subsequently, R sent P an endorsement stating that the policy is premiums is receipt by private respondent insurance company who, by provision of
cancelled for non-payment law, particularly under Article 1910 of the Civil Code, is bound by the acts of its
> P confronted R and demanded issuance of an official receipt. Agent of R agent.
told P that the cancellation was a mistake.
> P demanded that he be insured under same T&C or that the current Malapit’s failure to remit the premiums he received cannot constitute a defense for
commercial rate of increase on the payment he made be returned. private respondent insurance company; no exoneration from liability could result
> He then received a letter that the partial payment he made had been therefrom
exhausted pursuant to the provisions of Short Period Rate Scale at the
back of the policy. Respondent company should be reminded that a contract of insurance creates
> R further added that the amount P paid was in fact received. reciprocal obligations for both insurer and insured. Reciprocal obligations are those
which arise from the same cause and in which each party is both a debtor and a
R offered to extend the policy but P had already filed a complaint for breach of creditor of the other, such that the obligation of one is dependent upon the
contract. obligation of the other.
RTC - ruled in favor of P, ordered R to pay damages. Declared that respondent Under the circumstances of the instant case, the relationship as creditor and debtor
insurance company acted in bad faith in unilaterally cancelling subject insurance between the parties arose from a common cause: i.e., by reason of their agreement
policy, having done so only after seven months from the time that it had taken to enter into a contract of insurance under whose terms, respondent insurance
force and effect and despite the fact of full payment of premiums and other company promised to extend protection to petitioner-insured against the risk
charges on the issued insurance policy. Held that there was breach of contract. insured for a consideration in the form of premiums to be paid by the latter.
Bad faith, said the Court of Appeals, is some motive of self-interest or ill-will; a
furtive design or ulterior purpose, proof of which must be established convincingly.
Issue: WON the cancelling of the insurance policy was done with bad faith and/or
gross negligence?
Held:
TANGUILIG vs. CA
Issue/s:
Facts: 1. WON the agreement to construct the windmill system included the installation
P was doing business under the name and style JMT Engineering and General of a deep well
Merchandising when it proposed to R to construct a windmill system for him. 2. WON the P is under obligation to reconstruct the windmill after in collapsed?
> 60,000 with a one year guaranty from the date of completion and
acceptance by respodent. Held:
1. Notably, nowhere in either proposal is the installation of a deep well mentioned, even
Pursuant to the agreement, R paid P a downpayment of 30K and installment remotely. Neither is there an itemization or description of the materials to be used in
payment of 15K constructing the deep well. Moreover, it is a cardinal rule in the interpretation of contracts
that the intention of the parties shall be accorded primordial consideration and in case of
doubt, their contemporaneous and subsequent acts shall be principally considered. \
P then filed a complaint to collect the balance due to the refusal and failure of 2. The second issue is not a novel one. In a long line of cases this Court has consistently held
respondent to pay the balance. R denied the claim saying that he had already paid that in order for a party to claim exemption from liability by reason of fortuitous event
this amount to San Pedro General Merchandising which constructed the deep well under Art. 1174 of the Civil Code the event should be the sole and proximate cause of the
to which the windmill system was to be connected loss or destruction of the object of the contract.
> R argued that since the deep well formed part of the system the payment
he tendered to SPGMI should be credited to his account by petitioner. He Petitioner failed to show that the collapse of the windmill was due solely to a fortuitous
further assumed that his balance should be offset by the defects in the event. Interestingly, the evidence does not disclose that there was actually a typhoon on the
day the windmill collapsed. Petitioner merely stated that there was a “strong wind.” But a
windmill system which cause the structure to collapse after a strong wind
strong wind in this case cannot be fortuitous—unforseeable nor unavoidable. On the
hit their place. contrary, a strong wind should be present in places where windmills are constructed,
otherwise the windmills will not turn.
P denied that the construction of a deep well was included in the agreement to
build the windmill system for the 60K was solely for the windmill. He also disowned
any obligation to repair the system and insisted that its collapse was attributable to
a typhoon, a force majuere, which relieved him of any liability.
RTC - held that the construction of the deep well was not part of the windmill
project as evidenced clearly by the letter proposals submitted by petitioner to
respondent. With respect to the repair of the windmill, the trial court found that
“there is no clear and convincing proof that the windmill system fell down due to
the defect of the construction.
CA - reversed, ruled that the construction of the deep well was included in the
agreement of the parties because the term “deep well” was mentioned in both
proposals. Gave credence to the proprietor of SPGMI which installed the deep well
that P told him that the cost of constructing the deep well would be deducted from
the contract price of 60k.
>R’s payment of 15K to SPGMI should be applied to his remaining balance
with P thus effectively extinguishing his contractual obligation.
> Rejected P’s claim of force majeure and ordered latter to reconstruct the
windmill.
NAKPIL SONS vs. CA An act of God has been defined as an accident, due directly and exclusively to natural causes
without human intervention, which by no amount of foresight, pains or care, reasonably to
Facts: have been expected, could have been prevented. (1 Corpus Juris 1174).
The office building of R Philippine Bar Association was constructed by United Constructions
and it was completed by 1966. There is no dispute that the earthquake of August 2, 1968 is a fortuitous event or an act of
God.
Two years later, an unusually strong earthquake hit Manila and the building sustained major
damage. As a temporary remedial measure, the building was shored up by United To exempt the obligor from liability under Article 1174 of the Civil Code, for a breach
Construction, Inc. at the cost of P13,661.28 of an obligation due to an “act of God,” the following must concur: (a) the cause of
the breach of the obligation must be independent of the will of the debtor; (b) the
Plaintiff commenced this action for recovery of damages arising for the partial collapse of the event must be either unforseeable or unavoidable; (c) the event must be such as to
building against United Construction, Inc. render it impossible for the debtor to fulfill his obligation in a normal manner; and (d)
> Plaintiff alleges that the collapse of the building was due to the defects in the the debtor must be free from any participation in, or aggravation of the injury to the
construction, failure of the contractors to follow plans and specifications and creditor.
violations by the defendants of the terms of the contract.
Thus, if upon the happening of a fortuitous event or an act of God, there concurs a
Defendants in turn filed a 3rd party claim against the architects who prepared the plans and
corresponding fraud, negligence, delay or violation or contravention in any manner of the
specifications, alleging in essence that the collapse was due to the defects in the said plans
tenor of the obligation as provided for in Article 1170 of the Civil Code, which results in loss or
and specifications. damage, the obligor cannot escape liability.
After the protracted hearings, the Commissioner eventually submitted his report with the
findings that while the damage sustained was caused directly by the earthquake, they were The negligence of the defendant and the third-party defendants petitioners was established
also caused by the defects in the plans and specifications prepared by the 3rd party beyond dispute both in the lower court and in the Intermediate Appellate Court. Defendant
defendants’ architects, deviations from said plans and specifications by the defendant United Construction Co., Inc. was found to have made substantial deviations from the plans
contractors and failure of the latter to observe the requisite workmanship in the construction and specifications, and to have failed to observe the requisite workmanship in the
of the building. construction as well as to exercise the requisite degree of supervision; while the third-party
defendants were found to have inadequacies or defects in the plans and specifications
RTC - agreed with the findings of the Commissioner, except as to the holding that the owner prepared by them.
is charged with full time supervision of the construction.
Issue: WON an act of God - earthquake, which caused the failure of the building, exempts
from liability, parties who are otherwise liable because of their negligence?
Held:
The applicable law governing the rights and liabilities of the parties herein is Article 1723 of
the New Civil Code.
On the other hand, the general rule is that no person shall be responsible for events which
could not be foreseen or which, though foreseen, were inevitable.
REPUBLIC vs. LUZON STEVEDORING
Facts:
A barge owned by R was being towed down the Pasig river by tugboats that also belonged to
R. The barge rammed against one of the wooden piles of the Nagtahan bailey bridge,
smashing the posts and causing the bridge to list.
Sued by the Republic for actual and consequential damages, R disclaimed liability on the
ground that it had exercised due diligence in the selection and supervision of its employees,
that the damages were cause by force majeure; Nagtahan bridge is an obstruction to
navigation.
RTC - held the R liable for the damage cause and ordered it to pay the P the actual cost of the
repair of the bridge.
Issue/s:
• WON the collision of appellant's barge with the supports or piers of the Nagtahan bridge
was in law caused by fortuitous event or force majeure, and
Held:
As to the first question, considering that the Nagtahan bridge was an immovable and
stationary object and uncontrovertedly provided with adequate openings for the passage of
water craft, including barges like of appellant’s, it is undeniable that the unusual event that
the barge, exclusively controlled by appellant, rammed the bridge supports raises a
presumption of negligence on the part of appellant or its employees manning the barge or
the tugs that towed it. For in the ordinary course of events, such a thing does not happen if
proper care is used
Force majeure by definition, are extraordinary events not foreseeable or avoidable. It is,
therefore, not enough that the event should not have been foreseen or anticipated, as is
commonly believed, but it must be one impossible to foresee or to avoid. The mere difficulty
to foresee the happening is not impossibility to foresee the same:
P knowing and appreciating the perils posed by the swollen stream and its swift current,
voluntarily entered into a situation involving obvious danger; it therefore assured the risk, and
can not shed responsibility merely because the precautions it adopted turned out to be
insufficient.
FAR EASTERN BANK TRUST CO vs. CA Article 21 of the Code, it should be observed, contemplates a conscious act to
cause harm. Thus, even if we are to assume that the provision could properly relate
Facts: to a breach of contract, its application can be warranted only when the defendant's
PR Luna applied and was accorded a FAREASTCARD issued by P. Upon his request, disregard of his contractual obligation is so deliberate as to approximate a degree
the bank also issued a supplemental card to PR Clarita Luna. of misconduct certainly no less worse than fraud or bad faith. Most importantly,
Article 21 is a mere declaration of a general principle in human relations that clearly
1988, Clarita lost her credit card and P was informed. In cases of this nature, the must, in any case, give way to the specific provision of Article 2220 of the Civil
policy was to record the lost card, along with the principal card, as a Hot Card or Code authorizing the grant of moral damages in culpa contractual solely when the
Cancelled Card in its master file. breach is due to fraud or bad faith.
Luis tendered a despedida lunch for a friend at Hotel Intercontinental Manila. Luis, The Court has not in the process overlooked another rule that a quasi-delict can be
presented his FAREASTCARD to the attending waiter who promptly had it verified the cause for breaching a contract that might thereby permit the application of
through a telephone call to the bank’s credit card dept. Card wasnt honored, Luis applicable principles on tort even where there is a pre-existing contract between
had to pay in cash and was embarassed. the plaintiff and the defendant.
PR demanded from P the payment of damages. This doctrine, unfortunately, cannot improve private respondents' case for it can
aptly govern only where the act or omission complained of would constitute an
VP of the bank expressed their apologies and mentioned that their investigation actionable tort independently of the contract.
revealed that FAREASTCARD failed to inform you about its security policy and that
an employee of them did not consider the possibility that it may have been you Where, without a pre-existing contract between two parties, an act or omission can
who was presenting the card at that time. nonetheless amount to an actionable tort by itself, the fact that the parties are
contractually bound is no bar to the application of quasi-delict provisions to the
Still, PR filed a complaint for damages. case. Here, private respondents' damage claim is predicated solely on their
contractual relationship; without such agreement, the act or omission complained
RTC - rendered a decision ordering P to pay PR of cannot by itself be held to stand as a separate cause of action or as an
CA - affirmed the decision of trial court independent actionable tort.
Issue:
Nevertheless, the bank's failure, even perhaps inadvertent, to honor its credit card
issued to private respondent Luis should entitle him to recover a measure of
Held:
damages sanctioned under Article 2221 of the Civil Code
In culpa contractual, moral damages may be recovered where the defendant is
shown to have acted in bad faith or with malice in the breach of the contract.
Concededly, the bank was remiss in indeed neglecting to personally inform Luis of
his own card's cancellation. Nothing in the findings of the trial court and the
appellate court, however, can sufficiently indicate any deliberate intent on the part
of FEBTC to cause harm to private respondents. Neither could FEBTC's negligence
in failing to give personal notice to Luis be considered so gross as to amount to
malice or bad faith.
SALUDAGA vs. FEU 3. W/N respondents shall be held liable for damages under
Facts: Art. 2180 of the civil code. - NO
Petitioner Saludaga was a.sophomore law student of respondent
FEU when he was shot by Rosete, one of the security guards on
duty at school on Aug. 18, 1996. Rosete was brought to the The incident is not a fortuitous event. In order for force
police where he explained that the shooting was accidental and majeure to be considered, respondents must show that no
he sas eventually released. negligence or misconduct was committed that may have
Saludaga thereafter filed a complaint for dagaes against occasioned the loss. A n act of God cannot be invoked to
respondents on the ground thatthey breached their oligation to protect a person who has failed to take steps to forestall the
provide students with a safe and secure environment and an possible adverse consequences of such a loss. One’s negligence
atmosphere conducive to learning. may have concurred with an act of God in producing damage
Respondents in tirn diled a thir-party companit against Galaxy and injury to another; nonetheless, showing that the immediate
Development and Management Corporation (Galaxy), the or proximate cause of the damage or injury was a fortuitous
agency contracted by FEU to provide security services and event would not exempt one from liability. When the effect is
Imperial, Galaxy’s president to indemnify them for whataver found to be partly the result of a person’s participation—
and pay attorney;s fees and cost of the suit. whether by active intervention, neglect or failure to act—the
Galaxy and Imperial filed a fourth-arty complaint against AFP whole occurrence is humanized and removed from the
General Insurance. rulesapplicable to acts of God.
RTC – FEU AND De Jesus(FEU President) to pay jointly and Article 1170 of the Civil Code provides that those who are
severally Joseph Saladuga; Galaxy Management and
Imperial(Galaxy President) to indemnify jointly and severally negligent in the performance of their obligations are liable for
FEU and De Jesus for the above mentioned amounts.
damages. Accordingly, for breach of contract due to negligence
CA – reversed the decision. Complaint filed by Saludaga in
against FEU is dismissed.
providing a safe learning environment, respondent FEU is
ISSUE/S: liable to
1. W/N FEU breached its contract to ensure and take
adequate steps to maintain peace and order within the petitioner for damages.
campus -NO
2. W/N The shooting incident is a fortuitous event – NO In the instance case, it was established thatpetitioner
spent 35, 298.25 for his hospitalization and
othermedical expenses. While the trial court correctly Liability for illegal or harmful acts committed by the security guards
imposed interest on said amount, however, the case at attaches to the employer agency, and not to the clients or customers
bar involves an obligation arising from a contract and of such agency. As a general rule, a client or customer of a security
not a lon or forbearance of money. As such, the proper agency has no hand in selecting who among the pool of security
rate of legal interest is 6% per annum of the amount guards or watchmen employed by the agency shall be assigned to it;
the duty to observe the diligence of a good father of a family in the
demanded. After this Decision becomes final and selection of the guards cannot, in the ordinary course of events, be
executory, the rate shal l be 12% per annum until its demanded from the client whose premises or property are protected
satisifcation. by the security guards.
CA – reversed the judgment. The facts of robbery have been "ART. 1174. Except in cases expressly specified by law, or when it is
duly established and the loss of jewelry was on a ccount of a otherwise declared by stipulation, or when the nature of the
obligation requires the assumption of risk, no person shall be
responsible for those events which could not be foreseen, or which, WHEREFORE, finding no error in the decision of the Court of
though foreseen, were inevitable." Appeals under review, the petition in this case is hereby
dismissed, with costs against the petitioner.
To avail of the exemption granted in the law, it is not necessary
that the persons responsible for the occurrence should be found
or punished; it would only be sufficient to establish that the
unforeseeable event, the robbery in this case, did take place
without any concurrent fault on the debtor's part, and this can
be done by preponderant evidence.
interest at the legal rate, and P100,000 attorney’s fees. But the