Professional Documents
Culture Documents
Installationofaplindiafirst660mwsupercriticalunitmundra Sundarakavidass Adanipower PDF
Installationofaplindiafirst660mwsupercriticalunitmundra Sundarakavidass Adanipower PDF
Sundara Kavidass
Vice President , Engineering Services
Adani Power Ltd, Ahmadabad
1
Presentation Overview
• Introduction
• Supercritical technology
• Design aspects of 660 MW unit
• First 660 MW Project implementation
• Operating Experience
• Conclusion
2
Introduction
• India’s current installed capacity is 156,784
MW
• Projected additional power demand is 95,750
MW up to 2012
• Plan to add 1,58,124 MW of power generation
capacity in year 2007-17 (ten years)
• Adani Power Limited is contributing to add
power generation capacity
3
What is Supercritical Technology?
• The supercritical technology is the thermodynamic state where
there is no clear distinction between the Water and Steam phase
in the Rankine Cycle
Rankine Cycle
• The “efficiency “of the thermodynamic process is the heat energy
fed into the Rankine cycle is converted into electrical energy.
• Heat energy input to the Rankine cycle is kept constant, the output
can be increased by selecting high pressures and high temperatures.
• The key components are supercritical once through boiler and high
pressure & high temperature steam turbine.
4
Rankine Cycle Subcritical Unit
1 - 2 > CEP work
2 - 3 > LP Heating
3 - 4 > BFP work
4 - 5 > HP Heating
5 – 6 > Eco, WW
6 – 7 > Superheating
7 – 8 > HPT Work
8 – 9 > Reheating
9 – 10 > IPT Work
10–11 > LPT Work
11 – 1 > Condensing
Rankine Cycle Supercritical Unit
7
Effect of Increasing Steam Temperature and
Pressure on Cycle Efficiency
8
HRH
MS
LP-BP LTSH
LTRH
HP-BP
ECO
G
LTRH I/L
LPT IPT HPT ECO I/L
Header
Header
CRH
CONDENSER
Water Wall
A B C
CEP
Deareator
GSC
A B
BFBP
LP Heater
#1 A B
BFP WW LOWER
Header
LP Heater #2
HP
LP Heater #3 No. 1 No. 2 No. 3
BFWP
HP Heater HP Heater HP Heater
Natural Circulation Vs. Once Through System
10
660 MW SC Unit Design Coal Data
MUNDRA TIRODA
Parameters Value Parameters Value
Moisture % 33.00 Moisture % 10.0
Ash % 4.02 Ash % 37.0
FC% 32.50 FC% 25.4
VM% 30.48 VM% 27.6
GCV Kcal/kg 4500 GCV Kcal/kg 3927
660 MW Unit Design Aspects
Boiler
Description Unit Mundra Data Tiroda Data
Furnace Size : mxm 20.4023x20.072 19.824x17.64
Height : m 68 69
12
Supercritical Boiler Features
Bottom spiral & top vertical tube furnace arrangement
• Once through design feature is used for boiler water wall design
• The supercritical water wall is exposed to the higher heat flux
• Utilize intensive radiant heat transfer in the furnace firing zone
• Spiral tube wall design (wrapped around the unit) with high
mass flow & velocity of steam/water mixture through each spiral
tube (2630 kg/m2/s & mass flow velocity for vertical tubes ~
1259 kg/m2/s)
• Higher mass flow improves heat transfer between the WW tube
and the fluid at high heat flux.
• Improved materials are utilized for superheater and reheater
tubes
13
HRP
MSP
SC Unit SEPARATOR
FRH
DRAIN TANK SH DIV FSH
Panel
LP-BP
LTSH
LTRH
HP-BP
ECO
VERTICAL WATER WALL
CRP
CONDENSER
BRCP
A B C
CEP
DEAERATOR
GSC
A B
BFBP
No.7AB&8AB
LP Heater A B
MD-BFP
TD-BFP
No.6 LP Heater
No.5 LP Heater 14
No. 3 No. 2 No. 1
WW LOWER Header HP BFWP
HP Heater HP Heater HP Heater
15
16
Heat Absorption in 660 MW
50 45% Supercritical Boiler
% Heat Absorption
40
29.5%
30
18.5%
20
7%
10
0
Water wall SH RH Economizer Tiroda 660 MW
% Heat Absorption
40
30 24 %
19 %
20
9%
10
0
Water wall SH RH Economizer
17
PF FIRING OPTIONS - COMPARISON
BURNER
FIRE
BALL
BURNER
18
FF (AIR
Coal Burners Arrangement DAMPER)
(Mundra)
F (F ELEVATION COAL
NOZZLE)
EF (AIR DAMPER)
1687 mm
CC (AIR DAMPER)
C (C ELEVATION COAL
NOZZLE)
BC (AIR DAMPER)
OB (HFO OIL NOZZLE)
B (B ELEVATION COAL
NOZZLE) AB (AIR DAMPER)
21
From Reheater
Boiler
FCS
5 6 5 6
7 7 7 7
3 8 8 8 8
1 4 LPH -7A
LPH -7B
HPH - 1
LPH -8A
LPH -8B
Condenser
2
Condenser
Deaerator
HPH - 2
EXT From
CRH
HPH -3
TD BFP 2x50%
(MD BFP 1x35%) CEP
1994 TPH 3x55%
GSC
CPP
1482 TPH
22
LPH -6 LPH -5
660 MW Turbine Cross Section Overview
23
660 MW Mundra Steam Turbine
24
Features of 660 MW Mundra Steam Turbine
25
Key Plant Equipment
26
660 MW Supercritical Unit Design &
Operating Parameters
Item Description Unit TMCR Operating
Data
1 SH steam flow rate TPH 1994 2131
2 Superheated steam temp Deg C 571 567
3 SH steam pressure MPa 25.26 23.57
4 RH steam flow rate TPH 1624 1650
5 RH steam outlet temp Deg C 569 567
6 RH outlet pressure MPa 4.36 4.21
7 FW temperature Deg C 288.7 288
8 FW Pressure MPa 28.4 26.93
9 Separator temp Deg C 421 430
10 Separator pressure MPa 27.02 26.37
11 APH flue gas outlet temp Deg C 147 150
12 Total Air Flow ( To Wind box) TPH 2251 2093
13 Back Pressure KPa 10.2 10.3
14 Fuel Flow Rate TPH 323 293.3
15 Turbine Heat Rate Kcal/kWh 1894 1900
16 MW Output MW 660 663
27
Material Used for 660 MW Unit
(Mundra & Tiroda)
Material Design Allowable
Equipment
Specification Temperature 0 C Stress in MPa
Water Wall SA213T12 440 103
Low Temperature SH SA213T22 490 80
Final SH SA213T91 590 65
Final SH SA213 TP 347H 590 89
Low Temperature RH SA213T22 355 114
High temperature RH SA213T91 605 65
High temperature RH SA213 TP 347H 605 89
Final SH header SA335P91 590 65
Final RH header SA335P91 605 65
Turbine rotor New 12Cr forging 590 65
HP Turbine 1st stage
2Cr11Mo1VNbN 590 65
Blades
28
Recommended Water Chemistry for SC Units
All Volatile Treatment Oxygenated Treatment
(Start Up) (Operation)
Feed Feed
Main Main
Description Unit Water Condensate
steam
Water Condensate
Steam
Quality Quality
pH 9.0 - 9.6 9.0 - 9.6 9.0 - 9.5 8.0 - 9.0 8.0 - 9.0 8.0 - 9.0
Dissolved
Oxygen µg/l <5 < 10 30 - 150 < 10
Hydrazine µg/l < 50
Cation µS
Conductivity /cm < 0.2 < 0.15 < 0.2 < 0.15 < 0.12 < 0.15
Silica µg/l < 20 < 20 < 20 < 15 < 10 < 15
Iron µg/l < 10 <5 < 10 < 10 <5 < 10
Sodium µg/l <5 <3 <5 <5 <3 <5
Chloride µg/l <5 <3 <5 <3
Copper µg/l <3 <2 <3 <3 <2 <3
29
EFFECT OF CYCLE CHEMISTRY – KEY PARAMETERS
Parameter Potential Cause Long -Term Impact
Low pH 1. Condenser tube leak 1. Hydrogen damage
2. Upset in water Treatment 2. Excessive deposits lead to BTF by
3. Improper chemical cleaning overheating.
4. Improper CPU operation 3. Potential for FAC,
4. Stress corrosion cracking.
High pH 1. Excess dosing of NaOH 1. Caustic gouging,
during startup 2. High conc. deposit leads to turbine
2. Upset in water treatment. damage
3. Improper CPU operation.
Chlorides 1. Condenser tube leak 1. Hydrogen damage
2. Upset in water treatment. 2. Pitting on economizer & turbine
blades
3. Stress corrosion cracking in LP
turbine
Sodium 1. Condenser tube leak 1. Caustic gouging
2. Upset in water treatment 2. Deposits on turbine blade lead to rpm
plant reduction.
3. Excess dosing of NaOH
during startup
BOILER WATER TREATMENT FOR SC UNIT
All VolatileTreatment (AVT)
Ammonia & Hydrazine added at feed water & condensate
Boiler water pH to be maintained 9.0 – 9.5
Dissolved oxygen in feed water is <7ppb.
Magnetite layer formation for corrosion protection.
Used during start up to minimize contamination in the system.
Benefits of OT
Minimize FAC in feed water piping & economizer inlet header.
Corrosion product transportation is minimized. Helps to reduce
thermal fatigue , overheating & turbine fouling.
Formed Hematite layer is stronger than Magnetite layer for corrosion
protection.
Operation & Maintenance Challenges
32
Cold Start up Curve for 660 SC Unit
33
SC Unit Load Ramp up Rate
Supercritical unit cyclic operation
120
80
% Load
60
40
20
Recommended Practice
0
-60 -10 40 90 140 190 240 290 340 390
Time
Operating Experience of 660 MW Unit
36
Benefits of Supercritical Unit
• Higher unit cycle efficiency (40 - 42%)
Environmental Benefits
37
Highlights of E&C of 660 MW SC Unit
• Erection and Commissioning were successfully
completed in less than 36 months
• Green field power project and all the environmental
clearances were received in time
• No site pilings are required
• Contractor brought major handling equipment from China
• APL’s QA/QC team are placed in china to ensure the
quality.
• Ensured sequential delivery of the equipment to meet the
schedule and Mundra Seaport is very close to the plant
• Project commissioning was done through DCS
• Good team work between Chinese and Indian project
teams
• Received good cooperation from state and central govt.
authorities 38
Conclusion
• Unit #5 E&C was completed in 36 months
39
Power Business Goal - 20,000 MW
Adani Power Limited
21-Jul-11
Complete excavation for main
plant foundations
41
Concrete roads all over plant
area - Main plant front road
42
APH & duct erection start before ceiling
girder
43
Erection of Coal Bunkers
simultaneously with Main Structure
44
ESP electrodes erection with
exclusive tower crane
45
Furnace hopper assembly with all buckstay
arrangements and erection in two parts only
46
Furnace hopper erection in two
parts
47
Generator stator 276 MT lifting by
2x80T EOT crane
48
Rear arch assembly at site & erection
from boiler top with tower crane
49
Water wall assembly at site & Erection
from Boiler top by tower crane
50
FINAL SUPER
HEATER
51
LTSH COILS
ECONOMISER COILS
ECONOMISER
O/L HEADER
55
56