Sl.no Particular item of works No.

L B D Q (cum)
1.00 Earthwork Excavation
LW 2 9.50 0.90 0.65 11.12
SW 2 4.40 0.90 0.65 5.15
16.26
2.00 PCC
LW 2 9.50 0.90 0.20 3.42
SW 2 4.40 0.90 0.20 1.58
5.00
3.00 SSM
a First course
LW 2 9.20 0.60 0.45 4.97
SW 2 4.70 0.60 0.45 2.54
b Second course
LW 2 9.05 0.45 0.40 3.26
SW 2 4.85 0.45 0.40 1.75
12.51
4.00 DPC
LW 2 9.05 0.45 0.20 1.63
SW 2 4.85 0.45 0.20 0.87
2.50
5.00 BBM
LW 2 8.90 0.30 3.00 16.02
SW 2 5.00 0.30 3.00 9.00
Deductions:
Door(D) -2 1.00 0.30 2.10 -1.26
Window(W) -4 1.00 0.30 1.50 -1.80
Shelves(S) -2 1.00 0.15 1.50 -0.45
Lintels(L) -6 1.30 0.30 0.15 -0.35
21.16