Professional Documents
Culture Documents
Outline
DEPENDENT INVENTORY MODEL
REQUIREMENTS
Master Production Schedule
Bills of Materials
Accurate Inventory records
Purchase Orders Outstanding
Lead Times for Each Component
MRP STRUCTURE
Collins Industries
Largest manufacturer of ambulances in the world
International competitor
12 major ambulance designs
18,000 different inventory items
6,000 manufactured parts
12,000 purchased parts
MRP: IBM’s MAPICS
Collins Industries
Collins requires:
Material plan must meet both the requirements of the master
schedule and the capabilities of the production facility
Plan must be executed as designed
Effective “time-phased” deliveries, consignments, and
constant review of purchase methods
Maintenance of record integrity
Material Requirements Planning
(MRP)
Manufacturing computer information system
Determines quantity & timing of dependent demand
items
1 2 3 4 5
Gross Requirements 2 20 25 15
Scheduled Receipts 5 30
Available 25 23 33 33 8
Net Requirements 7
Planned
© 1995Order Receipts 7
Corel Order Releases
Planned 7
Corp.
MRP: Types of Items
Independent demand
items; complete product
ready for use
Dependent demand
items; sub-assemblies,
components
Service Level & ROP
Computer system
Mainly discrete products
Accurate bill-of-material
Accurate inventory status
99% inventory accuracy
Stable lead times
© 1984-1994 T/Maker Co.
MRP Benefits
Lead Times
Planned order report
Exception report
Inventory Data
Exception report
MRP planning
programs
(computer and
software)
Purchasing data
Static Data Files Dynamic Data Files
Master files
Master files
Customer master Information associated with a particular customer
(name, address, etc.).
Supplier master. Information associated with a particular supplier
(name, address, etc.).
Item master This is perhaps the key file in the entire system. It
defines each item that is made, sold or purchased by the organization.
Information stored on this file includes descriptions, the batch
quantity for manufacture and the lead time for supply.
Routing master This defines the process by which a particular
component is manufactured. It defines the equipment needed and
time taken at every operation. This file also provides textual
information specifying exactly how an item will be produced.
Bill of material (BOM) Relationship between different items. That is
to say, it defines which items are required to assemble another
The Planning Process
Aggregate production plan
Change
production plan?
Master production
schedule
Change master
Change requirements? production schedule?
Material requirements plan
Change capacity?
Detail capacity plan
Is capacity Is
Realistic plan being execution
No meeting
Yes met?
the plan?
Execute capacity plans
Marketing
Production Customer Finance
Capacity Demand Cash Flow
Inventory
Aggregate Human
Procurement
Production Plan Resources
Supplier
Manpower
Performance
Planning
Management Engineering
Return on Design
Investment Completion
Capital
MRP and The Production Planning Process
Aggregate
Forecast & Resource
Production
Firm Orders Availability
Planning
Material Master
Requirements Production
Planning Scheduling
Capacity Shop
Requirements Realistic? Floor
Planning Yes Schedules
MRP INPUT DATA
Master
Production
Schedule
Bill of Inventory
Materials Status
Material
Requirements
Planning System
Purchasing
Item Master
Data
Planned Order
& Other Reports
Inventory Classifications
Inventory
Demand
Company Customers Parent Items
Source
Material
Finished Goods WIP & Raw Materials
Type
Method of
Forecast & Booked Calculated
Estimating
Customer Orders
Demand
Planning
EOQ & ROP MRP
Method
Typical Focus of the Master Production Schedule
Assemble to Order Stock to Forecast
Make to Order or Forecast
(Process Focus) (Repetitive) (Product Focus)
Schedule finished
Number of end product
items
Number of
inputs
Print shop Motorcycles, autos, Steel, Pepsi,
Examples: Machine shop TVs, fast-food Bread, Light
Fine dining restaurant restaurant bulbs, Paper
Aggregate Production Plan Leads to Master Production Schedule (MPS)
A S
B C B C
Derivation of Master Schedule
A S
B C B C Master
Lead time = 4 for A
schedule for S
Lead time = 6 for S sold directly
Master schedule for A
Master schedule for S
5 6 7 8 9 10 11
8 9 10 11 12 13 1 2 3
Periods 40 50 15 40 20 30 10 10
A is required S is required
Week 6 : 40 Week 9 : 40
8 : 50 11 : 20
11 : 15 13 : 30
Derivation of Master Schedule
A S
B C B C Master
schedule for S
sold directly
5 6 7 8 9 10 11
8 9 10 11 12 13 1 2 3
Periods 40 50 15 40 20 30 10 10
Periods 1 2 3 4 5 6 7 8
Therefore, these
are the gross
Gross requirements: B
10 40+10
= 50 40 50 20 15+30
= 45 requirements for B
B Requirements
Bill-of-Material (BOM)
Bicycle(1)
P/N 1000
Phantom bills
Used for subassemblies that exist temporarily
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Product Structure for “Awesome” A
Time-Phased Product Structure
LEAD TIMES
Time-Phased Product Structure
WEEKS 1 2 3 4 5 6 7 8 9 10
GR
SR
OHI
NR
POT
POR
MRP Table Calculations
OHI(t) : on-hand inventory