You are on page 1of 119

RULE 67- EXPROPRIATION On October 23, 1983, respondent Judge issued a writ of possession in

favor of the plaintiff Municipality.

#1 G.R. No. 69260 December 22, 1989


On February 3, 1984, Erlinda Francisco filed a "Motion for Separate Trial,"
invoking Section 2, Rule 31. 7 She alleged that there had already been no
MUNICIPALITY OF BIÑAN, petitioner,
little delay in bringing all the defendants within the court's jurisdiction,
vs.
and some of the defendants seemed "nonchalant or without special
HON. JOSE MAR GARCIA, Judge of the Regional Trial Court at Biñan,
interest in the case" if not mere "free riders;" and "while the cause of
Laguna (BRANCH XXXIV, Region IV), and ERLINDA
action and defenses are basically the same;" she had, among other
FRANCISCO, respondents.
defenses, "a constitutional defense of vested right via a pre-existing
approved Locational Clearance from the H.S.R.C." 8 Until this clearance
The Provincial Fiscal for petitioner. was revoked, Francisco contended, or the Municipality had submitted and
obtained approval of a "rezoning of the lots in question," it was
Roman M. Alonte for private respondent. premature for it to "file a case for expropriation. 9 The Court granted the
motion. By Order dated March 2, 1984, it directed that a separate trial be
held for defendant Erlinda Francisco regarding her special defenses
mentioned in her .. Motion for Separate Trial and in her Motion to
Dismiss, distinct from and separate from the defenses commonly raised
NARVASA, J.: by all the defendants in their respective motions to dismiss."

Three (3) questions are resolved in the action of certiorari at bar. The first At the separate trial, the Fiscal, in representation of the Municipality called
is whether the special civil action of eminent domain under Rule 67 of the the Trial Court's attention to the irregularity of allowing Francisco to
Rules of Court is a case "wherein multiple appeals are allowed, 1 as present her evidence ahead of the plaintiff, "putting the cart before the
regards which 'the period of appeal shall be thirty [30] days,2 instead of horse, as it were." He argued that the motion to dismiss was in truth an
fifteen (15) days. 3 The second is whether or not the Trial Court may treat answer, citing Rural Progress Administration v. Judge de Guzman, and its
the motion to dismiss" filed by one of the defendants in the action of filing did "not mean that the order of presentation of evidence will be
eminent domain as a "motion to dismiss" under Rule 16 of the Rules of reversed," but the usual procedure should be followed; and the evidence
Court, reverse the sequence of trial in order and hear and determine said adduced should be deemed "evidence only for the motion for
motion to dismiss, and thereafter dismiss the expropriation suit as against reconsideration of the writ of possession." 10
the movant. And the third is whether or not a "locational clearance issued
by the Human Settlements Regulatory Commission relative to use of land
Nevertheless, at the hearing of March 5, and March 26, 1984, the Court
is a bar to an expropriation suit involving that land.
directed Francisco to commence the presentation of evidence. Francisco
presented the testimony of Atty. Josue L. Jorvina, Jr. and certain exhibits
The expropriation suit involved in this certiorari proceeding was the Land Use Map of the Municipality of Biñan, the Locational Clearance
commenced by complaint of the Municipality of Biñan, Laguna 4 filed in and Development Permit issued by the H.S.R.C. in favor of "Erlinda
the Regional Trial Court of Laguna and City of San Pablo, presided over by Francisco c/o Ferlins Realty & Development Corporation, and Executive
respondent Judge Jose Mar Garcia. The complaint named as defendants Order No. 648 and Letter of Instruction No. 729, etc. Thereafter, the
the owners of eleven (11) adjacent parcels of land in Biñan with an respondent Judge issued an Order dated July 24, 1984 dismissing the
aggregate area of about eleven and a half (11-1/2) hectares. The land complaint "as against defendant ERLINDA FRANCISCO," and amending
sought to be expropriated was intended for use as the new site of a the Writ of Possession dated October 18, 1983 so as to "exclude
modern public market and the acquisition was authorized by a resolution therefrom and from its force and effects said defendant .. and her
of the Sangguniang Bayan of Biñan approved on April 11, 1983. property ..." His Honor found that-

One of the defendants was Erlinda Francisco. She filed a "Motion to 1) a Locational Clearance had
Dismiss" dated August 26, 1983, on the following grounds; (a) the been issued on May 4,1983 by
allegations of the complaint are vague and conjectural; (b) the complaint the Human Settlements
violates the constitutional limitations of law and jurisprudence on eminent Regulatory Commission to the
domain; (c) it is oppressive; (d) it is barred by prior decision and "Ferlin's Realty .. owned by
disposition on the subject matter; and (e) it states no cause of defendant Erlinda Francisco to
action. 5 Now, her motion to dismiss" was filed pursuant to Section 3, Rule convert .. (her) lot to a
67 of the Rules of Court: commercial complex;"

Sec. 3. Defenses and objections within the time 2) according to the testimony of
specified in the summons, each defendant, in lieu of Atty. Jorvina of the H.S.R.C., a
an answer, shall present in a single motion to dismiss grantee of a locational clearance
or for other apppropriate relief, all of his objections acquires a vested right over the
and defenses to the right of the plaintiff to take his subject property in the sense
property for the use or purpose specified in the that .. said property may not be
complaint. All such objections and defenses not so subject of an application for
presented are waived. A copy of the motion shall be locational clearance by another
served on the plaintiffs attorney of record and filed applicant while said locational
with the court with the proof of service. clearance is subsisting;"

Her "motion to dismiss" was thus actually a pleading, taking the place of 3) such a clearance should be
an answer in an ordinary civil action; 6 it was not an ordinary motion "considered as a decision and
governed by Rule 15, or a "motion to dismiss" within the contemplation disposition of private property
of Rule 16 of the Rules of Court. co-equal with or in parity with a

ProvRem Rule 67 Fulltext Page 1 of 119


disposition of private property multiple appeals became
through eminent domain; available (Sections 4 and 5, Rule
36, .. Santos v. Pecson, 79 Phil.
4) the clearance was therefore "a 261);"
legal bar against the right of
plaintiff Municipality .. to 3) it was wrong for the Trial
expropriate the said property." Court to have acted exparte on
the motion for execution, the
The Municipality filed on August 17, 1984 a Motion for Reconsideration. motion being "litigable in
Therein it (a) reiterated its contention respecting the irregularity of the character;" and
reversal of the order of trial, supra. 11 (b) decried the act of the Court in
considering the case submitted for decision after the presentation of 4) it (the Municipality) was
evidence by Francisco without setting the case for further hearing for the denied due process when the
reception of the plaintiffs own proofs, (c) pointed out that as admitted by Court, after receiving Francisco's
Atty. Jorvina, the locational clearance did not "mean that other persons evidence and admitting her
are already prevented from filing locational clearance for the same exhibits, immediately resolved
project, and so could not be considered a bar to expropriation, (d) argued the case on the merits as regards
that the locational clearance issued on May 4, 1983, became a "worthless Francisco, without setting the
sheet of paper" one year later, on May 4, 1984 in accordance with the case "for further hearing for
explicit condition in the clearance that it "shall be considered reception of evidence for the
automatically revoked if not used within a period of one (1) year from plaintiff."
date of issue," the required municipal permits to put up the commercial
complex never having been obtained by Francisco; and (e) alleged that all The motion was denied, by Order dated October 18, 1984; hence, the
legal requirements for the expropriation of the property had been duly special civil action of certiorari at bar.
complied with by the Municipality. 12

1. There are two (2) stages in every action of


The Municipality set its motion for reconsideration for hearing on August expropriation. The first is concerned with the
28, 1984 after furnishing Francisco's counsel with copy thereof The Court determination of the authority of the plaintiff to
however re-scheduled the hearing more than two (2) months later, on exercise the power of eminent domain and the
November 20, 1984. 13 Why the hearing was reset to such a remote date is propriety of its exercise in the context of the facts
not explained. involved in the suit. 19 It ends with an order, if not of
dismissal of the action, "of condemnation declaring
On September 13, 1984, Francisco filed an "Ex-Parte Motion for Execution that the plaintiff has a lawful right to take the
and/or Finality of Order," contending that the Order of July 27, 1984 had property sought to be condemned, for the public use
become "final and executory on August 12, 1984" for failure of the or purpose described in the complaint, upon the
Municipality to file a motion for reconsideration and/or appeal within the payment of just compensation to be determined as
reglementary period," 14 i.e "fifteen (15) days counted from the notice of of the date of the filing of the complaint." 20 An order
the final order .. appealed from. 15 of dismissal, if this be ordained, would be a final one,
of course, since it finally disposes of the action and
On October 10, 1984, the Court issued an Order declaring the leaves nothing more to be done by the Court on the
Municipality's motion for reconsideration dated August 15, 1984 to have Merits. 21 So, too, would an order of condemnation
been "filed out of time," on account of which the Court 49 could not give be a final one, for thereafter, as the Rules expressly
due course to and/or act x x (thereon) except to dismiss (as it did thereby state, in the proceedings before the Trial Court, "no
dismiss) the same." 16 It drew attention to the fact that notice of its Order objection to the exercise of the right of
of July 24, 1984 (dismissing the complaint as against Francisco) was condemnation (or the propriety thereof) shall be flied
served on plaintiff Municipality on July 27, 1984, but its motion for or heard. 22
reconsideration was not presented until August 17, 1984, beyond the
fifteen-day period for appeal prescribed by law. And on October 15, 1985, The second phase of the eminent domain action is concerned with the
His Honor promulgated another Order directing the issuance of (1) a writ determination by the Court of "the just compensation for the property
of execution of the Order of July 24, 1984, and (2) a "certificate of finality" sought to be taken." This is done by the Court with the assistance of not
of said order. 17 more than three (3) commissioners. 23 The order fixing the just
compensation on the basis of the evidence before, and findings of, the
The Municipality attempted to have the respondent Court reconsider both commissioners would be final, too. It would finally dispose of the second
and Orders of October 10, and October 15, 1984. To this end it submitted stage of the suit, and leave nothing more to be done by the Court
a motion contending that: 18 regarding the issue. Obviously, one or another of the parties may believe
the order to be erroneous in its appreciation of the evidence or findings
of fact or otherwise. Obviously, too, such a dissatisfied party may seek
1) "multiple appeals are allowed reversal of the order by taking an appeal therefrom.
by law" in actions of eminent
domain, and hence the period of
appeal is thirty (30), not fifteen A similar two-phase feature is found in the special civil action of partition
(15) days; and accounting under Rule 69 of the Rules of Court. 24

2) moreover, the grant of a The first phase of a partition and/or accounting suit is taken up with the
separate trial at Francisco's determination of whether or not a co-ownership in fact exists, and a
instance had given rise "ipso partition is proper (i.e., not otherwise legally prescribed) and may be
facto to a situation where made by voluntary agreement of all the parties interested in the
property. 25 This phase may end with a declaration that plaintiff is not
ProvRem Rule 67 Fulltext Page 2 of 119
entitled to have a partition either because a co-ownership does not exist, proceedings in accordance with Rule 109 of the Rules of Court and other
or partition is legally prohibited.26 It may end, on the other hand, with an cases wherein multiple appeals are allowed, the period of appeal shall be
adjudgment that a co-ownership does in truth exist, partition is proper in thirty (30) days, a record of appeal being required. 45
the premises and an accounting of rents and profits received by the
defendant from the real estate in question is in order. 27 In the latter case, The municipality's motion for reconsideration filed on August 17, 1984
"the parties may, ff they are able to agree, make partition among was therefore timely presented, well within the thirty-day period laid
themselves by proper instruments of conveyance, and the court shall down by law therefor; and it was error for the Trial Court to have ruled
confirm the partition so agreed upon. 28, In either case i.e. either the otherwise and to have declared that the order sought to be considered
action is dismissed or partition and/or accounting is decreed the order is had become final and executory.
a final one, and may be appealed by any party aggrieved thereby. 29

2. As already observed, the Municipality's complaint


The second phase commences when it appears that "the parties are for expropriation impleaded eleven (11) defendants.
unable to agree upon the partition" directed by the court. In that event A separate trial was held on motion of one of them,
partition shall be done for the parties by the Court with the assistance of Erlinda Francisco, 46 it appearing that she had
not more than three (3) commissioners. 30 This second stage may well also asserted a defense personal and peculiar to her, and
deal with the rendition of the accounting itself and its approval by the inapplicable to the other defendants, supra.
Court after the parties have been accorded opportunity to be heard Subsequently, and on the basis of the evidence
thereon, and an award for the recovery by the party or parties thereto presented by her, the Trial Court promulgated a
entitled of their just share in the rents and profits of the real estate in separate Order dismissing the action as to her, in
question." 31 Such an order is, to be sure, final and appealable. accordance with Section 4, Rule 36 of the Rules of
Court reading as follows:
Now, this Court has settled the question of the finality and appealability
of a decision or order decreeing partition or recovery of property and/or Sec. 4. Several judgments in an action against several
accounting. In Miranda v. Court of Appeals, decided on June 18, 1986,32 defendants, the court may, when a several judgment
the Court resolved the question affirmatively, and expressly revoked the is proper, render judgment against one or more of
ruling in Zaldarriaga v. Enriquez 33 -that a decision or order of partition is them, leaving the action to proceed against the
not final because it leaves something more to be done in the trial court others.
for the complete disposition of the case, i.e, the appointment of
commissioners, the proceedings for the determination by said
commissioners of just compensation, the submission of their reports, and It is now claimed by the Municipality that the issuance of such a separate,
hearing thereon, and the approval of the partition-and in Fuentebella vs. final order or judgment had given rise "ipso facto to a situation where
Carrascoso 34 -that a judgement for recovery of property with account is multiple appeals became available." The Municipality is right.
not final, but merely interlocutory and hence not appealable until the
accounting is made and passed upon. As pointed out in Miranda, In the case at bar, where a single complaint was filed against several
imperative considerations of public policy, of sound practice and defendants having individual, separate interests, and a separate trial was
adherence to the constitutional mandate of simplified, just, speedy and held relative to one of said defendants after which a final order or
inexpensive determination of every action require that judgments for judgment was rendered on the merits of the plaintiff s claim against that
recovery (or partition) of property with accounting be considered as final particular defendant, it is obvious that in the event of an appeal from that
judgments, duly appealable. This, notwithstanding that further separate judgment, the original record cannot and should not be sent up
proceedings will still have to be rendered by the party required to do so, to the appellate tribunal. The record will have to stay with the trial court
it will be ventilated and discussed by the parties, and will eventually be because it will still try the case as regards the other defendants. As the
passed upon by the Court. It is of course entirely possible that the Court rule above quoted settles, "In an action against several defendants, the
disposition may not sit well with either the party in whose favor the court may, when a several judgment is proper, render judgment against
accounting is made, or the party rendering it. In either case, the Court's one or more of them, leaving the action to proceed against the others.
adjudication on the accounting is without doubt a final one, for it would " 47 In lieu of the original record, a record on appeal will perforce have to
finally terminate the proceedings thereon and leave nothing more to be be prepared and transmitted to the appellate court. More than one
done by the Court on the merits of the issue. And it goes without saying appeal being permitted in this case, therefore, "the period of appeal shall
that any party feeling aggrieved by that ultimate action of the Court on be thirty (30) days, a record of appeal being required as provided by the
the accounting may seek reversal or modification thereof by the Court of Implementing Rules in relation to Section 39 of B.P. Blg. 129, supra. 48
Appeals or the Supreme Court. 35
3. Erlinda Francisco filed a "motion to dismiss"
The Miranda doctrine was reiterated in de Guzman v. C.A.- 36 Valdez v. intraverse of the averments of the Municipality's
Bagaso; 37 Lagunzad v. Gonzales; 38 Cease v. C.A., 39 Macadangdang v. complaint for expropriation. That "motion to dismiss"
C.A. 40 and Hernandez v. C.A., 41 Gabor v. C.A. 42 Fabrica v. C.A . 43 was in fact the indicated responsive pleading to the
complaint, "in lieu of an answer." 49
No reason presents itself for different disposition as regards cases of
eminent domain. On the contrary, the close analogy between the special Now, the Trial Court conducted a separate trial to determine whether or
actions of eminent domain and partition already pointed out, argues for not, as alleged by Francisco in her "motion to dismiss," she had a "vested
the application of the same rule to both proceedings. right via a pre-existing approved Locational Clearance from the HRSC.,"
making the expropriation suit premature. 50 While such a separate trial
The Court therefore holds that in actions of eminent domain, as in actions was not improper in the premises, 51 and was not put at issue by the
for partition, since no less than two (2) appeals are allowed by law, the Municipality, the latter did protest against the Trial Court's (a) reversing
period for appeal from an order of condemnation 44 is thirty (30) days the order of trial and receiving first, the evidence of defendant Francisco,
counted from notice of order and not the ordinary period of fifteen (15) and (b) subsequently rendering its order sustaining Francisco's defense
days prescribed for actions in general, conformably with the provision of and dismissing the action as to her, solely on the basis of said Francisco's
Section 39 of Batas Pambansa Bilang 129, in relation to paragraph 19 (b) evidence and without giving the plaintiff an opportunity to present its
of the Implementing Rules to the effect that in "appeals in special own evidence on the issue. The Trial Court was clearly wrong on both
counts. The Court will have to sustain the Municipality on these points.
ProvRem Rule 67 Fulltext Page 3 of 119
Nothing in the record reveals any valid cause to reverse the order of trial. The National Power Corporation (NAPOCOR) is a government-owned and
What the Trial Court might have had in mind was the provision of Section -controlled corporation vested with authority under Republic Act No.
5, Rule 16 of the Rules of Court allowing "any of the grounds for 6395, as amended, to undertake the development of hydro-electric
dismissal" in Rule 16 to "be pleaded as an affirmative defense and generation of power, production of electricity from any and all sources,
authorizing the holding of a "preliminary hearing .. thereon as if a motion construction, operation and maintenance of power plants, auxiliary plants,
to dismiss had been filed." Assuming this to be the fact, the reception of dams, reservoirs, pipes, main transmission lines, power stations and
Francisco's evidence first was wrong, because obviously, her asserted substations, and other works for the purpose of developing hydraulic
objection or defense that the locational clearance issued in her favor by power from any river, lake, creek, spring and waterfalls in the Philippines
the HSRC was a legal bar to the expropriation suit was not a ground for and to supply such power to the inhabitants thereof.1
dismissal under Rule 16. She evidently meant to prove the Municipality's
lack of cause of action; but lack of cause of action is not a ground for In February 1993, NAPOCOR entered a property located in Barangay San
dismissal of an action under Rule 16; the ground is the failure of the Isidro, Batangas City in order to construct and maintain transmission lines
complaint to state a cause of action, which is obviously not the same as for the 230 KV Mahabang Parang-Pinamucan Power Transmission
plaintiff's not having a cause of action. Project.2 Respondents heirs of Saturnino Q. Borbon owned the property,
with a total area of 14,257 square meters, which was registered under
Nothing in the record, moreover, discloses any circumstances from which Transfer Certificate of Title No. T-9696 of the Registry of Deeds of
a waiver by the Municipality of the right to present contrary proofs may Batangas.3
be inferred. So, in deciding the issue without according the Municipality
that right to present contrary evidence, the Trial Court had effectively On May 26, 1995, NAPOCOR filed a complaint for expropriation in the
denied the Municipality due process and thus incurred in another Regional Trial Court in Batangas City (RTC),4 seeking the acquisition of an
reversible error. easement of right of way over a portion of the property involving an area
of only 6,326 square meters, more or less,5 alleging that it had negotiated
4. Turning now to the locational clearance issued by with the respondents for the acquisition of the easement but they had
the HSRC in Francisco's favor on May 4, 1983, it failed to reach any agreement; and that, nonetheless, it was willing to
seems evident that said clearance did become a deposit the amount of ₱9,790.00 representing the assessed value of the
"worthless sheet of paper," as averred by the portion sought to be expropriated.6 It prayed for the issuance of a writ of
Municipality, upon the lapse of one (1) year from said possession upon deposit to enable it to enter and take possession and
date in light of the explicit condition in the clearance control of the affected portion of the property; to demolish all
that it 44 shall be considered automatically revoked if improvements existing thereon; and to commence construction of the
not used within a period of one (1) year from date of transmission line project. It likewise prayed for the appointment of three
issue," and the unrebutted fact that Francisco had not commissioners to determine the just compensation to be paid.7
really made use of it within that period. The failure of
the Court to consider these facts, despite its attention In their answer with motion to dismiss,8 the respondents staunchly
having been drawn to them, is yet another error maintained that NAPOCOR had not negotiated with them before entering
which must be corrected. the property and that the entry was done without their consent in the
process, destroying some fruit trees without payment, and installing five
WHEREFORE, the challenged Order issued by His Honor on July 24,1984 in transmission line posts and five woodpoles for its project;9 that the area
Civil Case No. 8-1960 is ANNULLED AND SET ASIDE, and the case is being expropriated only covered the portion directly affected by the
remanded to the Trial Court for the reception of the evidence of the transmission lines; that the remaining portion of the property was also
plaintiff Municipality of Biñan as against defendant Erlinda Francisco, and affected because the transmission line passed through the center of the
for subsequent proceedings and judgment in accordance with the Rules land, thereby dividing the land into three lots; that the presence of the
of Court and the law. Costs against private respondent. high tension transmission line had rendered the entire property inutile for
any future use and capabilities;10 that, nonetheless, they tendered no
SO ORDERED. objection to NAPOCOR’s entry provided it would pay just compensation
not only for the portion sought to be expropriated but for the entire
property whose potential was greatly diminished, if not totally lost, due to
the project;11 and that their property was classified as industrial land. Thus,
#2 G.R. No. 165354 January 12, 2015 they sought the dismissal of the complaint, the payment of just
compensation of ₱1,000.00/square meter, and attorney’s fees;12 and to be
REPUBLIC OF THE PHILIPPINES, represented by the NATIONAL allowed to nominate their representative to the panel of commissioners
POWER CORPORATION, Petitioner, to be appointed by the trial court.13
vs.
HEIRS OF SATURNINO Q. BORBON, AND COURT OF In the pre-trial conference conducted on December 20, 1995, the parties
APPEALS, Respondents. stipulated on: (1) the location of the property; (2) the number of the heirs
of the late Saturnino Q. Borbon; (3) the names of the persons upon whom
DECISION title to the property was issued; and (4) the ownership and possession of
the property.14 In its order of that date, the RTC directed the parties to
BERSAMIN, J.: submit the names of their nominees to sit in the panel of commissioners
within 10 days from the date of the pre-trial.15

The expropriator who has taken possession of the property subject of


expropriation is obliged to pay reasonable compensation to the The RTC constituted the panel of three commissioners. Two
landowner for the period of such possession although the proceedings commissioners submitted a joint report on April 8, 1999,16 in which they
had been discontinued on the ground that the public purpose for the found that the property was classified as industrial land located within the
expropriation had meanwhile ceased. Industrial 2 Zone;17that although the property used to be classified as
agricultural (i.e., horticultural and pasture land), it was reclassified to
industrial land for appraisal or taxation purposes on June 30, 1994; and
Antecedents
that the reclassification was made on the basis of a certification issued by

ProvRem Rule 67 Fulltext Page 4 of 119


the Zoning Administrator pursuant to Section 3.10 (d) of the Amended parties were going on with a view to the amicable settlement of the
Zoning Ordinance (1989) of the City of Batangas.18 The two case.30
commissioners appraised the value at ₱550.00/square meter.19 However,
the third commissioner filed a separate report dated March 16, On January 3, 2014, NAPOCOR filed a Manifestation and Motion to
1999,20 whereby he recommended the payment of "an easement fee of at Discontinue Expropriation Proceedings,31informing that the parties failed
least ten percent (10%) of the assessed value indicated in the tax to reach an amicable agreement; that the property sought to be
declaration21 plus cost of damages in the course of the construction, expropriated was no longer necessary for public purpose because of the
improvements affected and tower occupancy fee."22 intervening retirement of the transmission lines installed on the
respondents’ property;32 that because the public purpose for which such
The parties then submitted their respective objections to the reports. On property would be used thereby ceased to exist, the proceedings for
their part, the respondents maintained that NAPOCOR should expropriation should no longer continue, and the State was now duty-
compensate them for the entire property at the rate of ₱550.00/square bound to return the property to its owners; and that the dismissal or
meter because the property was already classified as industrial land at the discontinuance of the expropriation proceedings was in accordance with
time NAPOCOR entered it.23 In contrast, NAPOCOR objected to the joint Section 4, Rule 67 of the Rules of Court. Hence, NAPOCOR prayed that
report, insisting that the property was classified as agricultural land at the the proceedings be discontinued "under such terms as the court deems
time of its taking in March 1993; and clarifying that it was only seeking an just and equitable,"33 and that the compensation to be awarded the
easement of right of way over a portion of the property, not the entire respondents be reduced by the equivalent of the benefit they received
area thereof, so that it should pay only 10% of the assessed value of the from the land during the time of its occupation, for which purpose the
portion thus occupied.24 case could be remanded to the trial court for the determination of
reasonable compensation to be paid to them.34
In the judgment dated November 27, 2000,25 the RTC adopted the
recommendation contained in the joint report, and ruled thusly: In light of its Manifestation and Motion to Discontinue Expropriation
Proceedings, NAPOCOR contends that the expropriation has become
The price to be paid for an expropriated land is its value at the time of without basis for lack of public purpose as a result of the retirement of the
taking, which is the date when the plaintiff actually entered the property transmission lines; that if expropriation still proceeds, the Government will
or the date of the filing of the complaint for expropriation. In this case, be unduly burdened by payment of just compensation for property it no
there is no evidence as to when the plaintiff actually entered the property longer requires; and that there is legal basis in dismissing the
in question, so the reference point should be the date of filing of the proceedings, citing Metropolitan Water District v. De los Angeles35 where
complaint, which is May 5, 1995. the Court granted petitioner’s prayer for the quashal of expropriation
proceedings and the eventual dismissal of the proceedings on the ground
that the land sought to be expropriated was no longer "indispensably
On this date, the property in question was already classified as industrial. necessary" in the maintenance and operation of petitioner's waterworks
So, the Joint Report (Exhibit "1") is credible on this point. The two system.
Commissioners who submitted the Joint Report are government officials
who were not shown to be biased. So, that their report should be given
more weight than the minority report submitted by a private lawyer The issue to be considered and resolved is whether or not the
representing the plaintiff. In view of these, the Court adopts the Joint expropriation proceedings should be discontinued or dismissed pending
Report and rejects the minority report. The former fixed the just appeal.
compensation at ₱550.00 per square meter for the whole lot of 14,257
square meters.26 Ruling of the Court

Accordingly, the RTC ordered NAPOCOR to pay the respondents: (1) just The dismissal of the proceedings for expropriation at the instance of
compensation for the whole area of 14,257 square meters at the rate of NAPOCOR is proper, but, conformably with Section 4,36 Rule 67 of the
₱550.00/square meter; (2) legal rate of interest from May 5, 1995 until full Rules of Court, the dismissal or discontinuance of the proceedings must
payment; and (3) the costs of suit.27 be upon such terms as the court deems just and equitable.

NAPOCOR appealed (CA-G.R. No. 72069). Before anything more, we remind the parties about the nature of the
power of eminent domain. The right of eminent domain is "the ultimate
On April 29, 2004,28 the CA promulgated its decision, viz: right of the sovereign power to appropriate, not only the public but the
private property of all citizens within the territorial sovereignty, to public
purpose."37 But the exercise of such right is not unlimited, for two
WHEREFORE, premises considered, the Decision dated November 27, mandatory requirements should underlie the Government’s exercise of
2000 of Branch I of the Regional Trial Court of Batangas City, is hereby the power of eminent domain, namely: (1) that it is for a particular public
AFFIRMED with the MODIFICATION that plaintiff-appellant shall pay only purpose; and (2) that just compensation be paid to the property
for the occupied 6,326 square meters of the subject real property at the owner.38 These requirements partake the nature of implied conditions that
rate of ₱550.00 per square meter and to pay legal interest therefrom until should be complied with to enable the condemnor to keep the property
fully paid. expropriated.39

SO ORDERED.29 Public use, in common acceptation, means "use by the public." However,
the concept has expanded to include utility, advantage or productivity for
Hence, this appeal by NAPOCOR. the benefit of the public.40 In Asia's Emerging Dragon Corporation v.
Department of Transportation and Communications,41 Justice Corona, in
Issue his dissenting opinion said that:

On December 3, 2012, during the pendency of the appeal, NAPOCOR filed To be valid, the taking must be for public use. The meaning of the term
a Motion to Defer Proceedings stating that negotiations between the "public use" has evolved over time in response to changing public needs
and exigencies. Public use which was traditionally understood as strictly

ProvRem Rule 67 Fulltext Page 5 of 119


limited to actual "use by the public" has already been abandoned. "Public public use, then it would become the duty and the obligation of the
use" has now been held to be synonymous with "public interest," "public appellate court to dismiss it.
benefit," and "public convenience."
In the present case the petitioner admits that the expropriation of the
It is essential that the element of public use of the property be maintained land in question is no longer necessary for public use. Had that admission
throughout the proceedings for expropriation. The effects of abandoning been made in the trial court the case should have been dismissed there. It
the public purpose were explained in Mactan-Cebu International Airport now appearing positively, by resolution of the plaintiff, that the
Authority v. Lozada, Sr.,42 to wit: expropriation is not necessary for public use, the action should be
dismissed even without a motion on the part of the plaintiff. The moment
More particularly, with respect to the element of public use, the it appears in whatever stage of the proceedings that the expropriation is
expropriator should commit to use the property pursuant to the purpose not for a public use the complaint should be dismissed and all the parties
stated in the petition for expropriation filed, failing which, it should file thereto should be relieved from further annoyance or
another petition for the new purpose. If not, it is then incumbent upon litigation.46 (underscoring and emphasis supplied)
the expropriator to return the said property to its private owner, if the
latter desires to reacquire the same. Otherwise, the judgment of It is notable that the dismissal of the expropriation proceedings in
expropriation suffers an intrinsic flaw, as it would lack one indispensable Metropolitan Water District v. De los Angeles was made subject to several
element for the proper exercise of the power of eminent domain, namely, conditions in order to address the dispossession of the defendants of
the particular public purpose for which the property will be devoted. their land, and the inconvenience, annoyance and damages suffered by
Accordingly, the private property owner would be denied due process of the defendants on account of the proceedings. Accordingly, the Court
law, and the judgment would violate the property owner's right to justice, remanded the case to the trial court for the issuance of a writ of
fairness and equity.43 possession ordering Metropolitan Water District to immediately return
possession of the land to the defendants, and for the determination of
A review reveals that Metropolitan Water District v. De los Angeles44 is an damages in favor of the defendants, the claims for which must be
appropriate precedent herein. There, the Metropolitan Water District presented within 30 days from the return of the record to the court of
passed a board resolution requesting the Attorney-General to file a origin and notice thereof.47
petition in the Court of First Instance of the Province of Rizal praying that
it be permitted to discontinue the condemnation proceedings it had Here, NAPOCOR seeks to discontinue the expropriation proceedings on
initiated for the expropriation of a parcel of land in Montalban, Rizal to be the ground that the transmission lines constructed on the respondents’
used in the construction of the Angat Waterworks System. It claimed that property had already been retired. Considering that the Court has
the land was no longer indispensably necessary in the maintenance and consistently upheld the primordial importance of public use in
operation of its waterworks system, and that the expropriation complaint expropriation proceedings, NAPOCOR’s reliance on Metropolitan Water
should then be dismissed. The Court, expounding on the power of the District v. De los Angeles was apt and correct. Verily, the retirement of the
State to exercise the right of eminent domain, then pronounced: transmission lines necessarily stripped the expropriation proceedings of
the element of public use. To continue with the expropriation proceedings
There is no question raised concerning the right of the plaintiff here to despite the definite cessation of the public purpose of the project would
acquire the land under the power of eminent domain.1âwphi1 That power result in the rendition of an invalid judgment in favor of the expropriator
was expressly granted it by its charter. The power of eminent domain is a due to the absence of the essential element of public use.
right reserved to the people or Government to take property for public
use. It is the right of the state, through its regular organization, to reassert Unlike in Metropolitan Water District v. De los Angeles where the request
either temporarily or permanently its dominion over any portion of the to discontinue the expropriation proceedings was made upon the
soil of the state on account of public necessity and for the public good. authority appearing in the board resolution issued on July 14,
The right of eminent domain is the right which the Government or the 1930,48 counsel for NAPOCOR has not presented herein any document to
people retains over the estates of individuals to resume them for public show that NAPOCOR had decided, as a corporate body, to discontinue
use. It is the right of the people, or the sovereign, to dispose, in case of the expropriation proceedings. Nonetheless, the Court points to the
public necessity and for the public safety, of all the wealth contained in Memorandum dated December 13, 201249 and the Certificate of
the state.45 Inspection/Accomplishment dated February 5, 200550 attached to
NAPOCOR’s motion attesting to the retirement of the transmission lines.
Indeed, public use is the fundamental basis for the action for Also, Metropolitan Water District v. De los Angeles emphasized that it
expropriation; hence, NAPOCOR’s motion to discontinue the proceedings became the duty and the obligation of the court, regardless of the stage
is warranted and should be granted. The Court has observed in of the proceedings, to dismiss the action "if it should be made to appear
Metropolitan Water District v. De los Angeles: to the satisfaction of the court that the expropriation is not for some
public use."51 Despite the lack of the board resolution, therefore, the
Court now considers the documents attached to NAPOCOR’s
It is not denied that the purpose of the plaintiff was to acquire the land in Manifestation and Motion to Discontinue Expropriation Proceedings to be
question for public use. The fundamental basis then of all actions brought sufficient to establish that the expropriation sought is no longer for some
for the expropriation of lands, under the power of eminent domain, is public purpose.
public use. That being true, the very moment that it appears at any stage
of the proceedings that the expropriation is not for a public use, the
action must necessarily fail and should be dismissed, for the reason that Accordingly, the Court grants the motion to discontinue the proceedings
the action cannot be maintained at all except when the expropriation is subject to the conditions to be shortly mentioned hereunder, and requires
for some public use. That must be true even during the pendency of the the return of the property to the respondents. Having said that, we must
appeal or at any other stage of the proceedings. If, for example, during point out that NAPOCOR entered the property without the owners’
the trial in the lower court, it should be made to appear to the satisfaction consent and without paying just compensation to the respondents.
of the court that the expropriation is not for some public use, it would be Neither did it deposit any amount as required by law prior to its entry.
the duty and the obligation of the trial court to dismiss the action. And The Constitution is explicit in obliging the Government and its entities to
even during the pendency of the appeal, if it should be made to appear to pay just compensation before depriving any person of his or her property
the satisfaction of the appellate court that the expropriation is not for for public use.52 Considering that in the process of installing transmission
lines, NAPOCOR destroyed some fruit trees and plants without payment,

ProvRem Rule 67 Fulltext Page 6 of 119


and the installation of the transmission lines went through the middle of eminent domain, is always subject to the condition that the property be
the land as to divide the property into three lots, thereby effectively devoted to the specific public purpose for which it was taken. Corollarily,
rendering the entire property inutile for any future use, it would be unfair if this particular purpose or intent is not initiated or not at all pursued,
for NAPOCOR not to be made liable to the respondents for the and is peremptorily abandoned, then the former owners, if they so desire,
disturbance of their property rights from the time of entry until the time may seek the reversion of the property, subject to the return of the
of restoration of the possession of the property. There should be no amount of just compensation received. In such a case, the exercise of the
question about the taking. In several rulings, notably National Power power of eminent domain has become improper for lack of the required
Corporation v. Zabala,53 Republic v. Libunao,54 National Power factual justification.60
Corporation v. Tuazon,55 and National Power Corporation v.
Saludares,56 this Court has already declared that "since the high-tension This should mean that the compensation must be based on what they
electric current passing through the transmission lines will perpetually actually lost as a result and by reason of their dispossession of the
deprive the property owners of the normal use of their land, it is only just property and of its use, including the value of the fruit trees, plants and
and proper to require Napocor to recompense them for the full market crops destroyed by NAPOCOR’s construction of the transmission lines.
value of their property." Considering that the dismissal of the expropriation proceedings is a
development occurring during the appeal, the Court now treats the
There is a sufficient showing that NAPOCOR entered into and took dismissal of the expropriation proceedings as producing the effect of
possession of the respondents’ property as early as in March 1993 converting the case into an action for damages. For that purpose, the
without the benefit of first filing a petition for eminent domain. For all Court remands the case to the court of origin for further proceedings,
intents and purposes, therefore, March 1993 is the reckoning point of with instruction to the court of origin to enable the parties to fully litigate
NAPOCOR’s taking of the property, instead of May 5, 1995, the time the action for damages by giving them the opportunity to re-define the
NAPOCOR filed the petition for expropriation. The reckoning conforms to factual and legal issues by the submission of the proper pleadings on the
the pronouncement in Ansaldo v. Tantuico, Jr.,57 to wit: extent of the taking, the value of the compensation to be paid to the
respondents by NAPOCOR, and other relevant matters as they deem fit.
Normally, of course, where the institution of an expropriation action Trial shall be limited to matters the evidence upon which had not been
precedes the taking of the property subject thereof, the just heretofore heard or adduced. The assessment and payment of the correct
compensation is fixed as of the time of the filing of the complaint. This is amount of filing fees due from the respondents shall be made in the
so provided by the Rules of Court, the assumption of possession by the judgment, and such amount shall constitute a first lien on the recovery.
expropriator ordinarily being conditioned on its deposits with the Subject to these conditions, the court of origin shall treat the case as if
National or Provincial Treasurer of the value of the property as originally filed as an action for damages.
provisionally ascertained by the court having jurisdiction of the
proceedings. WHEREFORE, the Court DISMISSES the expropriation proceedings due to
the intervening cessation of the need for public use; REMANDS the
There are instances, however, where the expropriating agency takes over records to the Regional Trial Court, Branch 1, in Batangas City as the court
the property prior to the expropriation suit, as in this case although, to of origin for further proceedings to be conducted in accordance with the
repeat, the case at bar is quite extraordinary in that possession was taken foregoing instructions; and ORDERS said trial court to try and decide the
by the expropriator more than 40 years prior to suit. In these instances, issues with dispatch.
this Court has ruled that the just compensation shall be determined as of
the time of taking, not as of the time of filing of the action of eminent SO ORDERED.
domain.
#3 G.R. No. 153974 August 7, 2006
In the context of the State's inherent power of eminent domain, there is a
"taking" when the owner is actually deprived or dispossessed of his MIGUEL BELUSO, NATIVIDAD BELUSO, PEDRO BELUSO, ANGELITA
property; when there is a practical destruction or a material impairment of BELUSO, RAMON BELUSO, and AMADA DANIEL, substituted by her
the value of his property or when he is deprived of the ordinary use heirs represented by TERESITA ARROBANG, Petitioners,
thereof. There is a "taking" in this sense when the expropriator enters vs.
private property not only for a momentary period but for a more THE MUNICIPALITY OF PANAY (CAPIZ), represented by its Mayor,
permanent duration, for the purpose of devoting the property to a public VICENTE B. BERMEJO, Respondent.
use in such a manner as to oust the owner and deprive him of all
beneficial enjoyment thereof. For ownership, after all, "is nothing without
DECISION
the inherent rights of possession, control and enjoyment. Where the
owner is deprived of the ordinary and beneficial use of his property or of
its value by its being diverted to public use, there is taking within the AUSTRIA-MARTINEZ, J.:
Constitutional sense." x x x.58
Before this Court is a petition for review questioning the Decision 1 of the
In view of the discontinuance of the proceedings and the eventual return Court of Appeals (CA) dated March 20, 2002 in CA-G.R. SP No. 47052, as
of the property to the respondents, there is no need to pay "just well the Resolution 2 dated June 11, 2002 denying petitioners’ Motion for
compensation" to them because their property would not be taken by Reconsideration thereof.
NAPOCOR. Instead of full market value of the property, therefore,
NAPOCOR should compensate the respondents for the disturbance of The facts are as follows:
their property rights from the time of entry in March 1993 until the time
of restoration of the possession by paying to them actual or other
Petitioners are owners of parcels of land with a total area of about 20,424
compensatory damages. This conforms with the following
square meters, covered by Free Patent Nos. 7265, 7266, 7267, 7268, 7269,
pronouncement in Mactan-Cebu International Airport Authority v. Lozada,
and 7270. 3 On November 8, 1995, the Sangguniang Bayan of the
Sr.:59
Municipality of Panay issued Resolution No. 95-29 authorizing the
municipal government through the mayor to initiate expropriation
In light of these premises, we now expressly hold that the taking of proceedings. 4 A petition for expropriation was thereafter filed on April 14,
private property, consequent to the Government’s exercise of its power of

ProvRem Rule 67 Fulltext Page 7 of 119


1997 by the Municipality of Panay (respondent) before the Regional Trial C. IT WAS A SERIOUS ERROR ON THE PART OF THE HONORABLE COURT
Court (RTC), Branch 18 of Roxas City, docketed as Civil Case No. V-6958. 5 OF APPEALS NOT TO DISCUSS, MUCH LESS RULE ON, BOTH IN ITS
QUESTIONED DECISION AND ITS RESOLUTION PROMULGATED ON 11
Petitioners filed a Motion to Dismiss alleging that the taking is not for JUNE 2002 PETITIONERS’ ARGUMENTS THAT RESPONDENT IS WITHOUT,
public use but only for the benefit of certain individuals; that it is LACKS AND DOES NOT HAVE THE LAWFUL POWER TO ACQUIRE ANY OR
politically motivated because petitioners voted against the incumbent ALL OF THE SUBJECT PROPERTIES THROUGH EMINENT DOMAIN, IT
mayor and vice-mayor; and that some of the supposed beneficiaries of BEING EXERCISED BY MEANS OF A MERE RESOLUTION, AND NOT
the land sought to be expropriated have not actually signed a petition THROUGH AN ORDINANCE AS REQUIRED BY LAW AND APPLICABLE
asking for the property but their signatures were forged or they were JURISPRUDENCE, AND ITS PREVIOUS OFFER TO BUY THEM BEING NOT
misled into signing the same. 6 VALID, DESPITE THE FACT THAT THESE OBJECTIONS WERE PROPERLY
PLEADED IN PETITIONERS’ MEMORANDUM WHICH WAS DULY
ADMITTED IN ITS RESOLUTION PROMULGATED ON 29 JANUARY 2001;
On July 31, 1997, the trial court denied petitioners’ Motion to Dismiss and and
declared that the expropriation in this case is for "public use" and the
respondent has the lawful right to take the property upon payment of just
compensation. 7 D. PETITIONERS WERE UTTERLY DENIED PROCEDURAL DUE PROCESS OF
LAW BY THE COURT A QUO, WHEN IT SIMPLY DECLARED IN ITS ORDER
DATED 31 JULY 1997 THAT THE TAKING BY RESPONDENT OF
Petitioners filed an Answer on August 12, 1997 reasserting the issues they PETITIONERS’ PROPERTIES IS PURPORTEDLY FOR PUBLIC PURPOSE
raised in their Motion to Dismiss. 8
WITHOUT RECEIVING EVIDENCE ON THEIR ASSERTED CLAIM THAT
RESPONDENT’S MUNICIPAL MAYOR WAS POLITICALLY MOTIVATED IN
On October 1, 1997, the trial court issued an Order appointing three SEEKING THE EXPROPRIATION OF THEIR PROPERTIES AND NOT FOR
persons as Commissioners to ascertain the amount of just compensation PUBLIC PURPOSE. 16
for the property. 9 Petitioners filed a "Motion to Hold in Abeyance the
Hearing of the Court Appointed Commissioners to Determine Just Petitioners argue that: contrary to Sec. 19 of R.A. No. 7160 of the Local
Compensation and for Clarification of the Court’s Order dated October 1, Government Code, which provides that a local government may exercise
1997" which was denied by the trial court on November 3, the power of eminent domain only by "ordinance," respondent’s
1997. 10 Petitioners’ Motion for Reconsideration was also denied on expropriation in this case is based merely on a "resolution"; while
December 9, 1997. 11
objection on this ground was neither raised by petitioners in their Motion
to Dismiss nor in their Answer, such objection may still be considered by
Petitioners then filed on March 2, 1998 a Petition for Certiorari before the this Court since the fact upon which it is based is apparent from the
CA claiming that they were denied due process when the trial court petition for expropriation itself; a defense may be favorably considered
declared that the taking was for public purpose without receiving even if not raised in an appropriate pleading so long as the facts upon
evidence on petitioners’ claim that the Mayor of Panay was motivated by which it is based are undisputed; courts have also adopted a more
politics in expropriating their property and in denying their Motion to censorious attitude in resolving questions involving the proper exercise of
Hold in Abeyance the Hearing of the Court Appointed Commissioners; local bodies of the delegated power of expropriation, as compared to
and that the trial court also committed grave abuse of discretion when it instances when it is directly exercised by the national legislature;
disregarded the affidavits of persons denying that they signed a petition respondent failed to give, prior to the petition for expropriation, a
addressed to the municipal government of Panay. 12 On January 17, 2001, previous valid and definite offer to petitioners as the amount offered in
petitioners filed a Motion to Admit Attached Memorandum and the this case was only P10.00 per square meter, when the properties are
Memorandum itself where they argued that based on the Petition for residential in nature and command a much higher price; the CA failed to
Expropriation filed by respondent, such expropriation was based only on a discuss and rule upon the arguments raised by petitioners in their
resolution and not on an ordinance contrary to Sec. 19 of Republic Act Memorandum; attached to the Motion to Dismiss were affidavits and
(R.A.) No. 7160; there was also no valid and definite offer to buy the death certificates showing that there were people whose names were in
property as the price offered by respondent to the petitioners was very the supposed petition asking respondent for land, but who did not
low. 13 actually sign the same, thus showing that the present expropriation was
not for a public purpose but was merely politically motivated; considering
On March 20, 2002, the CA rendered its Decision dismissing the Petition the conflicting claims regarding the purpose for which the properties are
for Certiorari. It held that the petitioners were not denied due process as being expropriated and inasmuch as said issue may not be rightfully ruled
they were able to file an answer to the complaint and were able to adduce upon merely on the basis of petitioners’ Motion to Dismiss and Answer as
their defenses therein; and that the purpose of the taking in this case well as respondent’s Petition for Expropriation, what should have been
constitutes "public use". 14 Petitioners filed a Motion for Reconsideration done was for the RTC to conduct hearing where each party is given ample
which was denied on June 11, 2002. 15 opportunity to prove its claim. 17

Thus, the present petition claiming that: Respondent for its part contends that its power to acquire private
property for public use upon payment of just compensation was correctly
upheld by the trial court; that the CA was correct in finding that the
A. RESPONDENT IS WITHOUT, LACKS AND DOES NOT HAVE THE LAWFUL
petitioners were not denied due process, even though no hearing was
POWER TO ACQUIRE ANY OR ALL OF THE SUBJECT PROPERTIES
conducted in the trial court, as petitioners were still able to adduce their
THROUGH EMINENT DOMAIN, IT BEING EXERCISED BY MEANS OF A
objections and defenses therein; and that petitioners’ arguments have
MERE RESOLUTION, AND NOT THROUGH AN ORDINANCE AS REQUIRED
been passed upon by both the trial court and the CA and were all denied
BY LAW AND APPLICABLE JURISPRUDENCE;
for lack of substantial merit. 18

B. RESPONDENT IS LIKEWISE WITHOUT, LACKS AND DOES NOT HAVE


Respondent filed a Memorandum quoting at length the decision of the
THE LAWFUL POWER TO ACQUIRE ANY OR ALL OF THE SUBJECT
CA to support its position. 19 Petitioners meanwhile opted to have the
PROPERTIES THROUGH EMINENT DOMAIN, ITS PREVIOUS OFFER TO BUY
case resolved based on the pleadings already filed. 20
THEM BEING NOT VALID; and

We find the petition to be impressed with merit.

ProvRem Rule 67 Fulltext Page 8 of 119


Eminent domain, which is the power of a sovereign state to appropriate The Court in no uncertain terms have pronounced that a local
private property to particular uses to promote public welfare, is essentially government unit cannot authorize an expropriation of private property
lodged in the legislature. 21 While such power may be validly delegated to through a mere resolution of its lawmaking body. 31 R.A. No. 7160
local government units (LGUs), other public entities and public utilities the otherwise known as the Local Government Code expressly requires an
exercise of such power by the delegated entities is not absolute. 22 In fact, ordinance for the purpose and a resolution that merely expresses the
the scope of delegated legislative power is narrower than that of the sentiment of the municipal council will not suffice. 32
delegating authority and such entities may exercise the power to
expropriate private property only when authorized by Congress and A resolution will not suffice for an LGU to be able to expropriate private
subject to its control and restraints imposed through the law conferring property; and the reason for this is settled:
the power or in other legislations. 23 Indeed, LGUs by themselves have no
inherent power of eminent domain. 24 Thus, strictly speaking, the power of
eminent domain delegated to an LGU is in reality not eminent but x x x A municipal ordinance is different from a resolution. An ordinance is
"inferior" since it must conform to the limits imposed by the delegation a law, but a resolution is merely a declaration of the sentiment or opinion
and thus partakes only of a share in eminent domain. 25 The national of a lawmaking body on a specific matter. An ordinance possesses a
legislature is still the principal of the LGUs and the latter cannot go general and permanent character, but a resolution is temporary in nature.
against the principal’s will or modify the same.26 Additionally, the two are enacted differently -- a third reading is necessary
for an ordinance, but not for a resolution, unless decided otherwise by a
majority of all the Sanggunian members.
The exercise of the power of eminent domain necessarily involves a
derogation of a fundamental right. 27 It greatly affects a landowner’s right
to private property which is a constitutionally protected right necessary If Congress intended to allow LGUs to exercise eminent domain through a
for the preservation and enhancement of personal dignity and is mere resolution, it would have simply adopted the language of the
intimately connected with the rights to life and liberty. 28Thus, whether previous Local Government Code. But Congress did not. In a clear
such power is exercised directly by the State or by its authorized agents, divergence from the previous Local Government Code, Sec. 19 of R.A.
the exercise of such power must undergo painstaking scrutiny. 29 [No.] 7160 categorically requires that the local chief executive act
pursuant to an ordinance. x x x 33

Indeed, despite the existence of legislative grant in favor of local


governments, it is still the duty of the courts to determine whether the As respondent’s expropriation in this case was based merely on a
power of eminent domain is being exercised in accordance with the resolution, such expropriation is clearly defective. While the Court is aware
delegating law. of the constitutional policy promoting local autonomy, the court cannot
grant judicial sanction to an LGU’s exercise of its delegated power of
eminent domain in contravention of the very law giving it such power. 34
Sec. 19 of R.A. No. 7160, which delegates to LGUs the power of eminent
domain expressly provides:
The Court notes that petitioners failed to raise this point at the earliest
opportunity. Still, we are not precluded from considering the same. This
SEC. 19. Eminent Domain. - A local government unit may, through its chief Court will not hesitate to consider matters even those raised for the first
executive and acting pursuant to an ordinance, exercise the power of time on appeal in clearly meritorious situations, 35 such as in this case.
eminent domain for public use, or purpose, or welfare for the benefit of
the poor and the landless, upon payment of just compensation, pursuant
to the provisions of the Constitution and pertinent laws: Provided, Thus, the Court finds it unnecessary to resolve the other issues raised by
however, That the power of eminent domain may not be exercised unless petitioners.
a valid and definite offer has been previously made to the owner, and
such offer was not accepted: Provided, further, That the local government It is well to mention however that despite our ruling in this case
unit may immediately take possession of the property upon the filing of respondent is not barred from instituting similar proceedings in the
the expropriation proceedings and upon making a deposit with the future, provided that it complies with all legal requirements. 36
proper court of at least fifteen percent (15%) of the fair market value of
the property based on the current tax declaration of the property to be WHEREFORE, the petition is GRANTED. The decision of the Court of
expropriated: Provided, finally, That, the amount to be paid for the Appeals in CA-G.R. SP No. 47052 is REVERSED and SET ASIDE. The
expropriated property shall be determined by the proper court, based on Complaint in Civil Action No. V-6958 is DISMISSED without prejudice.
the fair market value at the time of the taking of the property.

No costs.
It is clear therefore that several requisites must concur before an LGU can
exercise the power of eminent domain, to wit:
SO ORDERED.

1. An ordinance is enacted by the local legislative council authorizing the


#4 G.R. No. 175176 October 17, 2008
local chief executive, in behalf of the local government unit, to exercise
the power of eminent domain or pursue expropriation proceedings over a
particular private property. NATIONAL POWER CORPORATION, petitioner,
vs.
SANTA LORO VDA. DE CAPIN and SPS. JULITO QUIMCO and GLORIA
2. The power of eminent domain is exercised for public use, purpose or
CAPIN, respondents.
welfare, or for the benefit of the poor and the landless.

DECISION
3. There is payment of just compensation, as required under Section 9,
Article III of the Constitution, and other pertinent laws.
CHICO-NAZARIO, J.:
4. A valid and definite offer has been previously made to the owner of the
property sought to be expropriated, but said offer was not accepted. 30 Before this Court is a Petition for Review on Certiorari under Rule 45 of
the 1997 Revised Rules of Civil Procedure seeking to review, reverse, and

ProvRem Rule 67 Fulltext Page 9 of 119


set aside the Decision1 dated 21 April 2006 and Resolution2 dated 27 Transmission Lines, Damages and Other Reliefs, against the petitioner
October 2006 of the Court of Appeals in CA-G.R. CV No. 73656. In its before the RTC, where it was docketed as Civil Case No. DNA-547.
assailed Decision, the appellate court affirmed the Resolution3 dated 16
April 2001, as modified by the Order4 dated 24 August 2001, of the Petitioner, in its Answer, countered that respondents’ claim for
Regional Trial Court (RTC), 7th Judicial Region, Branch 25, Danao City, in compensation for the full value of their properties traversed by its
Civil Case No. DNA-547, awarding in favor of herein respondents Santa transmission lines was repugnant to Section 3-A14 of its Charter, according
Loro Vda. De Capin and spouses Julito Quimco and Gloria Capin (Spouses to which, petitioner is obligated only to pay the easement fee equivalent
Quimco) damages, in the total amount ₱1,434,207.67 (at the rate of to 10% of the market value of the land as just compensation, plus the cost
₱448.33 per square meter), for the 3,199-square-meter portion of their of damaged improvements.
lots taken by herein petitioner National Power Corporation (NAPOCOR).
In its assailed Resolution, the appellate court denied petitioner’s Motion
for Reconsideration. During the Pre-trial Conference, the parties conceded that there was no
dispute as to the material fact that petitioner had taken portions of
respondents’ lots, with a combined area of 3,199 square meters, for use in
The present controversy arose from the following facts: its Interconnection Project. They also agreed that the only issue for
resolution by the RTC was the determination of the amount of just
Petitioner is a government-owned and controlled corporation duly compensation due the respondents for the portions of their land taken by
organized under Philippine laws and vested with the power of eminent the petitioner. Thus, respondents assented that they would file a Motion
domain by its Charter under Republic Act No. 6395,5 as amended by for Summary Judgment.
Presidential Decree No. 938.6 Pursuant to its 230 KV Leyte-Cebu
Interconnection Project (Interconnection Project), petitioner expropriated On 4 September 2000, the RTC issued an Order15 giving the respondents
several parcels of land in the Municipality of Carmen and City of Danao in 30 days within which to file their Motion for Summary Judgment. The
the Province of Cebu, which will be traversed and affected by its petitioner was also given 20 days from receipt of a copy of respondents’
transmission towers and lines. Motion for Summary Judgment to interpose or file its Opposition thereto.

Among the lots affected by the petitioner’s Interconnection Project were In compliance with the 4 September 2000 Order of the RTC, respondents
those owned by the respondents located in Dawis Sur, Carmen, Cebu. filed their Motion for Summary Judgment, with several documentary
Respondent Santa Loro Vda. De Capin’s lot has an area of 16,193 square evidence and affidavits of witnesses attached, on 10 October 2000.
meters, covered by Tax Declaration No. 15-22196 (1994);7 while
respondent-Spouses Quimco’s lot has an area of 3,298 square meters,
covered by Tax Declaration No. 31376 (1996).8 To be able to enter the In an Order16 dated 17 November 2000, the RTC gave petitioner a 15-day
said properties, petitioner obtained from each of the respondents Santa period from receipt of the said Order to file its Opposition to or Comment
Loro Vda. De Capin and Spouses Quimco a "Permission to Enter for on respondents’ Motion for Summary Judgment.
Construction of Transmission Line Project," dated 14 June 19949 and 11
December 1996,10 respectively. The permits were signed by the On 21 December 2000, petitioner filed a Motion for Extension of Time to
respondents upon representation by the petitioner that it would pay them File Comment on Motion for Summary Judgment. It averred that (1) it was
just compensation for the intrusion into their properties. not inclined to oppose respondents’ Motion for Summary Judgment,
except that the area of 3,199 square meters of respondents’ lots alleged
Thereafter, petitioner began to construct on respondents’ properties its to have been traversed by petitioner’s transmission lines was still being
power lines and transmission towers, which were completed in 1996. verified as to its correctness by its Right of Way Officers; and (2) upon
Petitioner’s Interconnection Project affected portions of respondents’ confirmation that the area was correct, it would join respondents’ Motion
properties, with a combined area of 3,199 square meters. Upon its for Summary Judgment.17 In an Order18 dated 29 December 2000, the RTC
completion of the construction of the power lines and transmission granted petitioner’s motion and gave it an extension of 15 days within
towers, petitioner imposed several restrictions upon the respondents on which to file its Comment to respondents’ Motion for Summary
Judgment.
the use of their lands, which included the prohibition against planting or
building anything higher than three meters below the area traversed by
its transmission lines as the high tension electric current passing through Despite the extension given the petitioner, it still failed to file its
said lines pose danger to life and limbs. Additionally, respondent-Spouses Comment. Hence, in an Order19 dated 23 February 2001, the RTC deemed
Quimco, holder of a Small Scale Quarry Permit, Series of 1995, were also respondents’ Motion for Summary Judgment submitted for resolution.
prohibited from continuing their quarry business near petitioner’s
transmission towers because of the great possibility that the quarry might On 16 April 2001, the RTC rendered a Resolution in favor of the
weaken the foundation of the transmission towers. In other words, respondents, the decretal portion of which reads:
respondents lost substantial amount of income due to the restriction
imposed on their properties by the petitioner.
WHEREFORE, in view of the foregoing, judgment is hereby rendered in
favor of the [herein respondents], ordering the [herein petitioner] to pay
Petitioner then paid respondents Santa Loro Vda. De Capin and Spouses damages in the amount of FOUR HUNDRED FORTY EIGHT & 33/100
Quimco the amounts of ₱8,015.9011and ₱5,350.49,12 respectively, for the PESOS (₱448.33) PER SQUARE METER or the total amount of ONE
portions of their lots affected by the Interconnection Project. Only later MILLION FOUR HUNDRED THIRTY FOUR AND TWO HUNDRED SEVEN &
did respondents discover that in comparison to the measly sums they 67/100 PESOS (₱1,434,207.67) for the 3,199 square meters of
were paid by petitioner, the other landowners within their area who [respondents’] lots taken by the [petitioner], with interest thereon at the
resisted the expropriation of their properties in court or who entered into rate of 14% per annum computed since 1996 when the [petitioner] took
compromise agreements with the petitioner were paid by petitioner the said portions from the [respondents].20
amount of ₱448.30 to ₱450.00 per square meter as just compensation for
the portions of their properties similarly affected by the petitioner’s
Petitioner filed a Motion for Reconsideration praying that the aforesaid
Interconnection Project.
Resolution of the RTC be set aside and the amount of just compensation
be reduced to ₱25.00 per square meter. Petitioner also filed a
Accordingly, respondents filed a Complaint13 for Rescission of Agreement, Supplemental Motion for Reconsideration seeking the reduction of the
Recovery of Possession of Parcels of Land, Removal of Tower and interest rate imposed by the RTC from 14% per annum to 6% per annum.
ProvRem Rule 67 Fulltext Page 10 of 119
Acting on petitioner’s Motion for Reconsideration and Supplemental The Resolution dated 16 April 2001 of the RTC in Civil Case No. DNA-547,
Motion for Reconsideration, the RTC issued an Order21 dated 24 August fixing the fair market value for the portions of respondents’ lots affected
2001, affirming its Resolution dated 16 April 2001, with the modification by the Interconnection Project at ₱448.33 per square meter, is based on
that the imposable rate of interest was reduced to 6% per annum from the Decision dated 25 May 1998 also of the RTC in Civil Case No. DNA-
the filing of the complaint, and 12% per annum from the time the 379;26 which, petitioner contends, is based on another Decision dated 5
judgment has become final and executory until fully satisfied. According May 1998 of the same RTC in Civil Case No. DNA-373.27 In its 5 May 1998
to the dispositive portion of the RTC Order: Decision in Civil Case No. DNA-373, the RTC considered the opinion
values of the Committee on Appraisal in determining the fair market value
WHEREFORE, the resolution of this Court dated [16 April 2001] is hereby of the properties involved therein. The said Decision, however, did not
affirmed with modification that the imposable rate of interest of the contain a description of the properties involved therein and their land
monetary judgment in favor of [respondents] should be 6% per annum classification at the time of the filing of the complaint and/or their taking.
from the filing of the complaint and 12% per annum from the time the Therefore, the Decision dated 25 May 1998 in Civil Case No. DNA-379 did
judgment has become final and executory until fully satisfied, using the not provide sufficient basis for pegging the fair market value of
amount adjudged as the actual base for the computation.22 respondents’ properties at ₱448.33 per square meter in Civil Case No.
DNA-547.

Still refusing to accept the judgment of the RTC, petitioner appealed the
16 April 2001 Resolution and 24 August 2001 Order of the said trial court Petitioner maintains that the RTC did not discuss in its Resolution dated
to the Court of Appeals. Petitioner’s appeal was docketed as CA-G.R. CV 16 April 2001 its factual and legal bases for fixing the amount of damages
No. 73656. payable to respondents. Respondents likewise failed to demonstrate that
their properties, at the time of their taking, were of the same classification
as the properties belonging to other landowners which were similarly
On 21 April 2006, the appellate court rendered a Decision affirming the traversed by petitioner’s Interconnection Project and for which petitioner
Resolution dated 16 April 2001, as modified by the Order dated 24 paid more. Finally, petitioner insists that it only acquired an easement of
August 2001, both by the RTC. right of way on respondents’ properties for the construction of its
transmission lines. The respondents still retained ownership of their
Petitioner moved for the reconsideration of the appellate court’s Decision, properties despite the imposition of an easement of right of way thereon.
but it was denied by the same court in a Resolution dated 27 October Consequently, petitioner is liable only to pay respondents an easement
2006. fee, not exceeding 10% of the fair market value of the portions of their
properties actually affected by the petitioner’s Interconnection Project, in
Hence, petitioner filed the present Petition before this Court, raising the accordance with Section 3-A(b) of petitioner’s Charter, as amended.
following issues:
The Petition is bereft of merit.
I. Whether or not the Court of Appeals committed reversible error in
upholding the propriety of the trial court’s resort to summary Summary or accelerated judgment is a procedural technique aimed at
judgment in determining the amount of just compensation for the weeding out sham claims or defenses at an early stage of the litigation,
properties of respondents affected by petitioner’s transmission line thereby avoiding the expense and loss of time involved in a trial. Even if
project. the pleadings appear, on their face, to raise issues, summary judgment
may still ensue as a matter of law if the affidavits, depositions and
II. Whether or not the Court of Appeals committed reversible error in admissions show that such issues are not genuine. The presence or
affirming the finding of the trial court that the total area of absence of a genuine issue as to any material fact determines, at
respondents’ lands affected by petitioner’s transmission line project bottom, the propriety of summary judgment.28
is 3,199 square meters.
Sections 1 and 3, Rule 35 of the Revised Rules of Civil Procedure provide:
III. Whether or not the Court of Appeals committed reversible error
in ruling that the decision in Civil Case No. DNA-379 provides SECTION 1. Summary judgment for claimant. – A party seeking to recover
sufficient basis for fixing the fair market value of the affected upon a claim, counterclaim, or cross-claim or to obtain a declaratory relief
properties of respondents at ₱448.33 per square meter. may, at any time after the pleading in answer thereto has been served,
move with supporting affidavits, depositions or admissions for a summary
IV. Whether or not the Court of Appeals committed reversible error judgment in his favor upon all or any part thereof.
in not ruling that under petitioner’s Charter, R.A. No. 6395, as
amended, respondents are only entitled to simple easement fees.23 xxxx

Petitioner argues that although the Complaint filed by the respondents SEC. 3. Motion and proceedings thereon. – The motion shall be served at
before the RTC was one for rescission of agreement and/or damages, it least ten (10) days before the time specified for the hearing. The adverse
was subsequently transformed into one for "reversed eminent party may serve opposing affidavits, depositions, or admissions at least
domain"24 where the determination of the amount of just compensation three (3) days before the hearing. After the hearing, the judgment sought
was the issue. In fact, respondents’ Motion for Summary Judgment shall be rendered forthwith if the pleadings, supporting affidavits,
focused only on the payment of just compensation. Resultantly, the RTC depositions, and admissions on file, show that, except as to the amount of
erred in resolving the respondents’ Complaint on the basis of the damages, there is no genuine issue as to any material fact and that the
provisions of the Rules of Court on Summary Judgment. The rules on moving party is entitled to a judgment as a matter of law.
summary judgment apply only to ordinary taking of properties. Instead of
granting respondents’ Motion for Summary Judgment, the RTC should Under the afore-quoted procedural rules, for a summary judgment to be
have appointed commissioners who would ascertain the amount of just proper, the movant must establish two requisites: (a) there must be no
compensation for the subject properties, pursuant to Section 5, Rule 67 of genuine issue as to any material fact, except for the amount of damages;
the Revised Rules of Court.25 Thus, the determination of just and (b) the party presenting the motion for summary judgment must be
compensation by the RTC based only on the pleadings submitted, was entitled to a judgment as a matter of law. Where, on the basis of the
palpably void.
ProvRem Rule 67 Fulltext Page 11 of 119
pleadings of a moving party, including documents appended thereto, no geodetic engineer who supposedly conducted the survey and its
genuine issue as to a material fact exists, the burden to produce a preparation which makes these documents of doubtful credibility. As such
genuine issue shifts to the opposing party. If the opposing party fails, the without any comment filed by the [petitioner] and without any evidence
moving party is entitled to a summary judgment.29 to the contrary, the court a quo correctly relied on the evidence submitted
by the [respondents]. x x x. The [petitioner] cannot now raise any issue
A "genuine issue" is an issue of fact which requires the presentation of as to any material fact in the case at bar when through its own fault
evidence as distinguished from a sham, fictitious, contrived or false claim. and inaction, it chose to remain silent when the motion for summary
When the facts as pleaded appear uncontested or undisputed, then there judgment was filed with the RTC. Such an actuation speaks of a dilatory
is no real or genuine issue or question as to the facts, and summary tactic on the part of the [petitioner] in the payment of the just
judgment is called for. The party who moves for summary judgment has compensation due the [respondents].33 (Emphasis supplied.)
the burden of demonstrating clearly the absence of any genuine issue of
fact, or that the issue posed in the complaint is patently unsubstantial so In light of the foregoing, the issue on the area of respondents’ lots
as not to constitute a genuine issue for trial. Trial courts have limited actually affected by petitioner’s Interconnection Project was not timely or
authority to render summary judgments and may do so only when there validly raised as an issue before the RTC. Except for the amount of
is clearly no genuine issue as to any material fact. When the facts as damages to which the respondents were entitled to as a matter of law,
pleaded by the parties are disputed or contested, proceedings for there was no other genuine issue as to any material fact involved in Civil
summary judgment cannot take the place of trial.30 Case No. DNA-547. Hence, the RTC was justified in resorting to summary
judgment.
In this case, during the Pre-trial Conference, petitioner already admitted
that it had taken portions of respondents’ lands for the construction of its Equally futile is petitioner’s insistence that respondents’ Complaint is
power lines and transmission towers pursuant to its Interconnection actually for "reversed eminent domain," which requires the appointment
Project. However, the parties could not agree on the amount of just of commissioners for the determination of just compensation, as provided
compensation or damages that petitioner should pay respondents for the under Section 5, Rule 67 of the Revised Rules of Court, rather than the
lands taken. Respondents insist that they be paid the full market value of promulgation of a summary judgment.
the portions of their lots taken by the petitioner, while petitioner believed
that it was only bound to pay respondents easement fees, which was It should be emphasized that the present case stemmed from a Complaint
equivalent to 10% of the market value of the respondents’ lots as for Rescission of Agreement, Recovery of Possession of Parcels of Land,
indicated in their tax declarations, pursuant to Section 3-A of petitioner’s Removal of Tower and Transmission Lines, Damages and Other Reliefs
Charter. Evidently, based on the foregoing, what remained for the filed by the respondents against the petitioner. It was an ordinary civil
determination of the RTC was the proper amount of damages due the action for the rescission of respondents’ agreement with petitioner, as
respondents for the portions of their lots taken by the petitioner. well as recovery of the possession of the lots taken, for failure of
petitioner to comply with its obligation to pay just compensation for the
Accordingly, respondents filed a Motion for Summary Judgment before respondents’ properties. Payment of just compensation or damages was
the RTC, where they specifically alleged that: an alternative remedy, akin to specific performance by the petitioner of its
obligation under its agreement with respondents, which would prevent
"4. Portions of the above-described parcels of land with a total area the rescission of the agreements altogether and the return of the
of 3,199 square meters were affected by the aforesaid [petitioner’s] possession of the properties to respondents. The parties, at the Pre-Trial
230 KV Leyte-Cebu Interconnection Project and were taken by Conference, implicitly agreed to pursue the remedy for payment of
[petitioner] in 1996, is shown by a Sketch Plan hereto attached as Annex damages rather than rescission of the agreement. Clearly, the proceedings
Cwhich is also made an integral part of this motion."31 (Emphasis before the RTC were not for expropriation, but were for damages, to
supplied.) which Section 5, Rule 67 of the Revised Rules of Court is irrelevant.

Petitioner, in turn, filed its Motion for Extension of Time to File Comment, Reference may be made to National Power Corporation v. Court of
which was granted by the RTC. In its Motion, petitioner stated that it was Appeals.34 In the said case, after therein petitioner NAPOCOR withdrew its
not inclined to oppose respondents’ Motion for Summary second Petition for Expropriation, what was left for the trial court’s
Judgment, exceptthat its officers were still verifying whether the area of determination was the counterclaim of therein private respondent
respondents’ lots traversed by petitioner’s transmission lines was indeed Antonino Pobre, contained in his Motion to Dismiss, for damages. The
3,199 square meters; and the moment the area is confirmed to be correct, Court ruled therein:
petitioner will join respondents’ Motion for Summary Judgment. However,
despite the ample opportunities given to petitioner by the RTC, it never "In this case, NPC appropriated [private respondent’s] Property without
filed any Opposition to or Comment on respondents’ Motion for resort to expropriation proceedings. NPC dismissed its own complaint for
Summary Judgment. It did not submit to the RTC the results of its the second expropriation. At no point did NPC institute expropriation
supposed verification of the area of respondents’ lots actually traversed proceedings for the lots outside the 5,554 square-meter portion subject
by its transmission lines. Petitioner only raised the issue on the area of the second expropriation. The only issues that the trial court had to
actually taken after the RTC had rendered summary judgment directing settle were the amount of just compensation and damages that NPC had
petitioner to pay damages for the 3,199 square meters it took from to pay [private respondent].
respondents.
This case ceased to be an action for expropriation when NPC dismissed its
As correctly and clearly ratiocinated by the Court of Appeals in its complaint for expropriation. Since this case has been reduced to a
appealed Decision: simple case of recovery of damages, the provisions of the Rules of
Court on the ascertainment of the just compensation to be paid were
[Petitioner] did not present the alleged communication of its Project no longer applicable. A trial before commissioners, for instance, was
Manager or the sketch plans for the RTC’s perusal despite the extension dispensable." (Emphasis supplied.)
of time given by the court a quo. In view thereof, it is quite clear that the
[petitioner] was given sufficient time to verify the area affected by Petitioner herein cannot hide behind the mantle of protection of
[petitioner’s] tower and transmission lines and to inform the court of the procedural laws when it has so arbitrarily violated respondents’ right to
result thereof. Furthermore, the sketch plans32were not even signed by the just compensation for their properties taken for public use.
ProvRem Rule 67 Fulltext Page 12 of 119
Petitioner assured respondents that it will pay them just compensation for resulting in a restriction or limitation on property rights over the land
the portions of their lots needed for the Interconnection Project, on the traversed by transmission lines also falls within the ambit of the term
basis of which respondents agreed in good faith to allow petitioner to "expropriation."37
already enter their properties and build thereon. Yet, instead of paying
respondents just compensation for the portions of their lots taken, they After petitioner’s transmission lines were fully constructed on portions of
were paid negligible amounts as easements fees. respondents’ lots, petitioner imposed restrictions thereon such as the
prohibition against planting or building anything higher than three
More lopsided is the fact that the other landowners within their area who meters below the area traversed by said lines. In addition, respondent-
resisted the taking of their properties were paid by petitioner way more Spouses Quimco, holders of a Small Scale Quarry Permit, Series of
than respondents who voluntarily dealt with petitioner. Petitioner had to 1995,38 were also prohibited from continuing their quarry business near
bring some of the resisting landowners to court in expropriation petitioner’s transmission towers because of the great possibility that it
proceedings where petitioner willingly paid just compensation for the said could weaken the foundation thereof. Hence, the respondent-spouses
landowners’ properties, as determined by a panel of commissioners. Quimco suffered substantial loss of income. It is clear then that
Petitioner entered into compromise agreements with the other resisting petitioner’s acquisition of an easement of right of way on the lands of the
landowners in which it likewise paid just compensation for the latter’s respondents amounted to an expropriation of the portions of the latter’s
properties. There is no rhyme or reason why respondents were the only properties and perpetually deprived the respondents of their proprietary
ones paid with easement fees, which were of much lesser values. rights thereon and for which they are entitled to a reasonable and just
compensation. Just compensation is defined as the full and fair
The Decision dated 25 May 1998 of the RTC in Civil Case No. DNA- equivalent of the property taken from its owner by the expropriator.
37935 provides sufficient basis for the same RTC in Civil Case No. DNA-547 The measure is not the taker’s gain, but the owner’s loss. The word
to award just compensation to respondents, equivalent to the fair market "just" is used to intensify the meaning of the word "compensation" and to
value of their affected properties at a rate of P448.33 per square meter. convey thereby the idea that the equivalent to be rendered for the
property to be taken shall be real, substantial, full and ample.39

In its 25 May 1998 Decision in Civil Case No. DNA-379, the RTC therein
ordered the petitioner to pay just compensation in the amount of ₱448.33 As the Court thoroughly explained in National Power Corporation v.
per square meter for the lot owned by the heirs of Tomas Gingco, which Gutierrez,40 viz:
was similarly traversed by petitioner’s transmission lines. Said Decision
became final and executory on 3 December 1998.36 Although it is a The trial court’s observation shared by the appellate court show that "x x x
Decision in another case, the RTC in Civil Case No. DNA-547 can take While it is true that plaintiff [is] only after a right-of-way easement, it
cognizance thereof when respondents presented the same for its nevertheless perpetually deprives defendants of their proprietary
consideration. rights as manifested by the imposition by the plaintiff upon defendants
that below said transmission lines no plant higher than three (3) meters is
The lot of the heirs of Tomas Gingco and those of the herein respondents allowed. Furthermore, because of the high-tension current conveyed
are all located within the same area in Dawis Sur, Carmen, Cebu and, are through said transmission lines, danger to life and limbs that may be
in fact, separated only by a lot owned jointly by Epifanio, Edilberto and caused beneath said wires cannot altogether be discounted, and to cap it
Josefa, all surnamed Loro. The lots owned by the respondents are even all, plaintiff only pays the fee to defendants once, while the latter
more advantageously situated than the lot owned by the heirs of Tomas shall continually pay the taxes due on said affected portion of their
Gingco since respondents’ properties are traversed by a barangay road property."
and near the quarry areas of Llyons Richfield Industrial Corporation. The
lots of the heirs of Tomas Gingco and of the respondents were all affected The foregoing facts considered, the acquisition of the right-of-way
by the Interconnection Project and were taken by the petitioner at about easement falls within the purview of the power of eminent domain.
the same time. The lots of respondents were effectively taken in June Such conclusion finds support in similar cases of easement of right-of-
1996, while the lot of the heirs of Tomas Gingco was acquired only a way where the Supreme Court sustained the award of just compensation
month later, in July 1996. Since the personalities and properties in both for private property condemned for public use (See National Power
Civil Case No. DNA-379 and Civil Case No. DNA-547 were essentially in Corporation vs. Court of Appeals, 129 SCRA 665, 1984; Garcia vs. Court of
similar situations, then the just compensation awarded for the property in Appeals, 102 SCRA 597, 1981). The Supreme Court, in Republic of the
the former case was a logical and reasonable basis for fixing or Philippines vs. PLDT, thus held that:
determining the just compensation due in the latter.
"Normally, of course, the power of eminent domain results in the taking
Furthermore, petitioner attached to their Motion for Summary Judgment or appropriation of title to, and possession of, the expropriated property;
several pieces of document in support of their allegations therein, and but no cogent reason appears why said power may not be availed of to
they furnished petitioner copies of the same. The petitioner was given impose only a burden upon the owner of condemned property,
ample time to study, challenge, and controvert respondents’ evidences, without loss of title and possession. It is unquestionable that real
yet it failed to do so. The RTC only rightfully proceeded, based on its property may, through expropriation, be subjected to an easement of
evaluation of the evidence on record, to render a Decision awarding to right-of-way."
the respondents just compensation or damages for the taking of their
lots, equivalent to the fair market value thereof at the rate of ₱448.33 per In the case at bar, the easement of right-of-way is definitely a taking
square meter. under the power of eminent domain. Considering the nature and effect of
the installation of the 230 KV Mexico-Limay transmission lines,
Finally, petitioner cannot insist that it only acquired an easement of right the limitation imposed by NPC against the use of the land for an
of way on the properties of the respondents and that it was liable to pay indefinite period deprives private respondents of its ordinary
respondents only an easement fee not exceeding 10% of the fair market use.41 (Emphasis supplied.)
value of the portions of their property actually affected by the
Interconnection Project, pursuant to Section 3-A(b) of its Charter. Having established that petitioner’s acquisition of right-of-way easement
over the portions of respondents’ lots was definitely a taking under the
Expropriation is not limited to the acquisition of real property with a power of eminent domain, petitioner then is liable to pay respondents
corresponding transfer of title or possession. The right-of-way easement
ProvRem Rule 67 Fulltext Page 13 of 119
just compensation and not merely an easement fee. The Court quotes This is a special civil action for certiorari to annul, for having been issued
with affirmation the ruling of the Court of Appeals on this matter: without or in excess of jurisdiction, in violation of law and in deprivation
of petitioner's right to due process, four (4) orders successively issued by
The [herein petitioner] vehemently insists that its Charter [Section 3A (b) the respondent Judge in seven (7) eminent domain cases (1) fixing the
of R.A. 6395] obliges it to pay only a maximum of 10% of the market value provisional values of the parcels of land sought to be expropriated by the
declared by the owner or administrator or anyone having legal interest in petitioner, National Power Corporation (NAPOCOR), in amounts far
the property, or such market value as determined by the assessor, exceeding their market values, (2) increasing the provisional values of the
whichever is lower. To uphold such a contention would not only interfere parcels of land involved in two (2) of such cases without hearing and
with a judicial function but would also render as useless the protection holding in abeyance the issuance of the writ of possession in favor of
guaranteed by our Constitution in Section 9, Article III of our Constitution petitioner until deposit of the additional amount, (3) requiring the private
that no private property shall be taken for public use without payment of respondents, as defendants in said cases, to state in writing within twenty-
just compensation. four (24) hours whether or not they are amenable to accepting and
withdrawing the amount deposited by petitioner as provisional values in
full and final satisfaction of their respective properties, and directing that
Moreover, the valuation of a property in the tax declaration cannot be an the writ of possession be issued only until after the defendants shall have
absolute substitute to just compensation. Stated differently, the market so manifested in writing their acceptance and receipt of said amounts,
value stated in the tax declaration of the condemned property is no and (4) directing petitioner to release and pay within twenty-four (24)
longer conclusive.42 It is violative of due process to deny to the owner the hours, through the Court and in favor of the defendants, the amount of
opportunity to prove that the valuation in the tax documents is unfair or P43,016,960.00.
wrong. It is also repulsive to the basic concepts of justice and fairness to
allow the haphazard work of a minor bureaucrat or clerk to absolutely
prevail over the judgment of a court which is promulgated only after The antecedents of this case are not controverted.
expert commissioners have actually viewed the property, after evidence,
arguments pro and con have been presented, and after all factors and Petitioner is a government-owned and controlled corporation created and
considerations essential to a fair and just determination have been existing by virtue of Republic Act No. 6395, as amended, for the purpose
judicially evaluated.43 10% of the market value of the expropriated of undertaking the development of hydraulic power, the production of
property cannot in any way be considered as the fair and full equivalent power from any source, particularly by constructing, operating and
to the loss sustained by the owner of the property, such would be 90% maintaining power plants, auxiliary plants, dams, reservoirs, pipes, mains,
less than what is due him. Thus, we are of the conclusion that Section 3A transmission lines, power stations and other works for the purpose of
of [petitioner’s] Charter cannot prevail over the mandate of our developing hydraulic power from any river, creek, lake, spring and
Constitution on the payment of just compensation. The court a quo did waterfall in the Philippines and supplying such power to the inhabitants
not commit an error when it held that the [petitioner’s] charter thereof. In order to carry out these purposes, it is authorized to exercise
encroached on the function of the court in determining just the power of eminent domain.
compensation.44
On 30 March 1990, petitioner filed seven (7) eminent domain cases before
WHEREFORE, premises considered, the instant Petition is the Regional Trial Court of the Sixth Judicial Region in Bacolod City, to wit:
hereby DENIED. The Decision and Resolution of the Court of Appeals in
CA-G.R. CV No. 73656, dated 21 April 2006 and 27 October 2006, (1) Civil Case No. 5938 against Jesus, Fernando, Ma.
respectively, are hereby AFFIRMED. No pronouncement as to costs. Cristina and Michael, all surnamed GONZAGA; 1

SO ORDERED. (2) Civil Case No. 5939 against Louis, Dionisio,


Roberto, Gabriel, Benjamin, Ana, Alexander, Carla,
#5 G.R. Nos. 94193-99 February 25, 1992 Sofia, Daniel, all surnamed GONZAGA; 2

NATIONAL POWER CORPORATION, petitioner, (3) Civil Case No. 5940 against Rosario P. Mendoza; 3
vs.
HON. ENRIQUE T. JOCSON, in his capacity as Presiding Judge, (4) Civil Case No. 5941 against Celsoy Agro-Ind.
Regional Trial Court, 6th Judicial Region, Branch 47, Bacolod City; Corporation; 4
JESUS, FERNANDO, MARIA CRISTINA and MICHAEL, all surnamed
GONZAGA; LUIS, DIONISIO, ROBERTO, GABRIEL, BENJAMIN, ANA,
ALEXANDER, CARLA, SOFIA and DANIEL, all surnamed GONZAGA; (5) Civil Case No. 5942 against Emmanuel, Lydia,
ROSARIO P. MENDOZA; CELSOY AGRO-IND. CORP.; EMMANUEL, Harry, Noli, Clifford and Christian, Dale, all surnamed
LYDIA, HARRY, NOLI, CLIFFORD and CHRISTIAN DALE, all surnamed AÑO; 5
AÑO; MAYO L. LACSON; and LUCIA GOSIENFIAO, respondents.
(6) Civil Case No. 5943 against Mayo L. Lacson; 6
Amado B. Parreno Law Office for Gonzaga, et al.
(7) Civil Case No. 5944 against Lucia Gosiengfiao 7
Francisco B. Cruz for R. Mendoza.
for the acquisition of a right-of-way easement over portions of the parcels
Eduardo M. Casiple for Mayo Lacson. of land described in the complaints for its Negros-Panay Interconnection
Project, particularly the Bacolod-Tomonton Transmission Line.

The complaints uniformly (a) allege that petitioner urgently needs


portions of the affected land to enable it to construct its tower and
DAVIDE, JR., J.: transmission line in a manner that is compatible with the greatest good
while at the same time causing the least private injury; the purpose for
which the lands are principally devoted will not be impaired by the

ProvRem Rule 67 Fulltext Page 14 of 119


transmission lines as it will only acquire a right-of-way-easement thereon; Considering that Judge Habaradas was on sick leave, petitioner filed on 8
and it had negotiated with and offered to pay defendants for the portions May 1990 an Urgent Motion to Reraffle due to the urgent necessity for
affected by the Bacolod-Tomonton Transmission Line, but the parties the hearing of the cases and the Urgent Motion to Fix Provisional
failed to reach an agreement despite long and repeated negotiations, and Value. 12 Acting on said motion, Vice Executive Judge Bethel K. Moscardon
(b) pray that: issued on 9 May 1990 an Order granting the motion and directing the re-
raffle of the cases. 13
1. This Honorable Court fix the provisional value of
the portions of the parcel of land herein sought to be Upon re-raffle, the cases were assigned to Branch 47, presided over by
expropriated pursuant to Section 2, Rule 67 of the respondent Judge. Since the latter went on sick leave effective 16 May
Rules of Court; 1990, petitioner filed on said date an Urgent Motion for Special Re-raffle
and for Immediate Fixing of Provisional Value. 14 As a consequence
2. This Honorable Court, by proper order and writ, thereof, the cases were re-raffled to Branch 48 of the court.
authorize the plaintiff to enter or take possession of
the premises described in paragraph 3 hereof, and to On 17 May 1990, Judge Romeo Hibionada of Branch 48 issued an Order
commence and undertake the construction of the directing the defendants to appear before the court on 21 May 1990 at
Bacolod-Tomonton T/L after depositing with the 8:30 A.M. to register their comments or objections to the fixing of the
Provincial Treasurer of Negros Occidental the provisional values of the parcels of land subject of expropriation. 15
provisional value fixed by this Honorable Court, which
amount shall be held by said official subject to the On 21 May 1990, the petitioner and the defendants, through their
order and final disposition of the Court; respective lawyers, appeared and orally argued their respective positions
on the Motion to Fix Provisional Value. 16
3. This Honorable Court appoint three (3)
Commissioners to hear the parties, view the premises, Instead of ruling on the issues raised therein, Judge Hibionada, citing
assess the damages to be paid for the condemnation, Circular No. 7 of this Court dated 23 September 1974 which establishes a
and to report in full their proceedings to the Court; pairing system,17 promulgated an Order directing the return of the seven
(7) cases to Branch 47 for further disposition.
4. The plaintiff be declared to have the lawful right to
acquire portions of the properties of the defendants On 5 June 1990, Branch 47, through respondent Judge, issued an Order
affected by the condemnation; directing the petitioner:

5. After the determination of the amount of . . . to show by documents and otherwise within five
indemnity, the Court authorize the payment by the (5) days from receipt hereof the following:
plaintiff to the defendants; and

1. That it has earlier negotiated repeatedly with


6. Judgment be rendered against the defendants, defendants but failed to reach agreement;
condemning the portion of the parcels of land
referred to in paragraphs 3 and 4 hereof, including
the improvements thereof, if any, for public use and 2. That expropriation of heavily populated subdivision
for the purpose hereinabove set forth, free from all areas in order to install primary electric transmission
other liens and encumbrances whatsoever; and lines would not endanger lives and property in the
area;
thereafter, upon plaintiff's compliance with the
requirements of said judgment, a final order of
condemnation be issued and entered in favor of the 3. That such installation is of paramount public
plaintiff. interest and there is no other demonstrable
alternative.
Plaintiff further prays for such other reliefs as may be
deemed just and equitable in the premises. and warning that "no provisional order for tentative cost payment of the
land affected would be issued" pending compliance by petitioner with the
The cases were raffled to different branches of the trial court as follows: foregoing. 18
Civil Cases Nos. 5938, 5943 and 5944 to Branch 43; Civil Case No. 5939 to
Branch 54; Civil Case No. 5940 to Branch 45; Civil Case No. 5941 to Branch On 25 June 1990, respondent Judge, finding the existence of paramount
50; and Civil Case No. 5942 to Branch 46. public interest which. may be served by the expropriation, the long range
benefit of the project involved, substantial compliance with the rules
Only the defendants in Civil Cases Nos. 5938, 5939, and 5942 filed concerning efforts for negotiation and, taking into consideration the
Motions to Dismiss. 8 market value of the subject areas and the daily opportunity profit that the
petitioner allegedly admitted in open court, issued an Order fixing the
provisional values of the subject areas, to wit:
On 4 April 1990, petitioner filed a Motion to consolidate these cases for
joint trial 9 and an Urgent Motion To Fix Provisional Value.10
CIVIL CASE AFFECTED MARKET PROVISIONAL
NO. AREA(SQ. M.) VALUE
On 10 April 1990, Executive Judge Jesus V. Ramos issued an Order
granting the motion for consolidation and ordering the consolidation of
all the cases in Branch 43 of the court, then presided over by Judge 1. 5938 7,050 P 45,000.00 P 180,000.00
Romeo Habaradas.11 3,000 668,700.00 2,674,800.00
6,600 219,830.00 879,320.00
2. 5939 23,400 757,437.00 3,029,748.00
3. 5940 9,030 2,870.00 11,480.00
ProvRem Rule 67 Fulltext Page 15 of 119
4. 5941 17,430 433,130.00 1,732,520.00 movants. At that time, the Court is (sic) unaware that
5. 5942 2,700 342,900.00 1,371,600.00 the expropriation of these areas would render the
6. 5943 15,900 2,125,340.00 8,501,360.00 remaining portion practically a total loss considering
7. 5944 21,000 1,200,000.00 1,800,000.00 that it is in a subdivision and not agricultural and that
the fetching price (sic) now in the immediate vicinity
and directing the petitioner: is between P1,500.00 and P2,000.00 per square
meter. Considering that the presence of the primary
transmission lines of the property and the earlier
. . . to deposit the amount with the Philippine intrusion of the Central Negros Cooperative at the
National Bank in escrow for the benefit of the side of the areas affected for free (sic) during the
defendants pending decision on the merits. 19 Martial Law Regime, and considering further the
proximity of the Rolling Hills Memorial Park, the San
The market values mentioned in the Order are the same values appearing Miguel Corporation manufacturing complex, Jesusa
in the tax declarations of the properties and the notices of assessment Heights, Green Hills Memorial Park and other posh
issued by the Assessor. subdivisions, as well as a golf course, the Court is
convinced that that (sic), defendants Jesusa Gonzaga,
In compliance with the said Order, petitioner deposited the total sum of Fernando Gonzaga, Ma. Cristina and Michel (sic)
P23,180,828.00 with the Philippine National Bank, NAPOCOR Branch, Gonzaga are entitled to a higher valuation for the
Quezon City, under Savings Account 249-505865-7 and manifested on 3 property, not only because of the above-stated facts
July 1990 with the court below that it did so. 20 but because of the clear danger to the inhabitants in
the area and the destruction of the marketability of
the remaining portion after expropriation.
On 11 July 1990, the defendants in Civil Case No. 5938 filed a motion for
the reconsideration of the 25 June 1990 Order alleging that the
provisional value of the property involved therein "had been set much too II
low" considering the allegations therein adduced, stating that the real
compensation that should accrue to them is estimated at P29,970,000.00 In respect to the plea of defendants Louis Gonzaga,
and praying that the questioned Order be reconsidered so as to reflect et al. for re-evaluation of the areas owned by them,
"the true amount covering the properties subject to (sic) Eminent Domain the Court feels that adjustment should also be made
estimated at TWENTY NINE MILLION NINE HUNDRED SEVENTY considering that it is contiguous to the areas
THOUSAND (P29,970,000.00)." 21 belonging to Jesus Gonzaga, et al. above-stated and
it is also affected by the same conditions. Considering
It likewise appears that the defendants in "Civil Case No. 5939 filed a that the area affected is 23,000 square meters and
motion for reconsideration asking for a re-evaluation of the provisional the fetching price (sic) in the vicinity is between
value of the subject property. 22 P1,500.00 and P2,000.00 per square meter, the Court
feels that the provisional value of the property should
be P12,600,000.00.
On 12 July 1990, respondent Judge issued an Order 23 increasing the
provisional values of the properties enumerated in the motions for
reconsideration, directing the petitioner to deposit "whatever differential As to the rest of the defendants, there being no
between the amounts above fixed and those already deposited within extra-ordinary or peculiar conditions which may
twenty four (24) hours from receipt of the Order" and holding in abeyance warrant re-evaluation the amounts fixed earlier by
the issuance of the writ of possession pending compliance therewith. The this Court shall stand.
Order reads in full as follows:
WHEREFORE, (a) the Court rules that the provisional
ORDER value of 7,050 square meters aforestated should be
P6,000,000.00; the provisional value of 6,600 square
meters aforestated should be P5,000,000.00; and the
I
provisional value of 3,000 square meters aforestated
should be P3,000,000.00 instead of those in the June
Before this Court are two (2) Motions for 25, 1990 Order of this Court for these properties. (b)
Reconsideration of the Order dated June 25, 1990 The provisional value of 23,000 square meters
fixing provisional values of the lands sought to be belonging to Louis Gonzaga, et al. should be
expropriated belonging to the defendants in these rightfully valued at P12,600,000.00.
cases. The first motion was filed by the Torres
Valencia Ciocon Dabao Valencia & De La Paz Law
The plaintiff is directed to deposit whatever
Offices for the defendants Jesus, Fernando, Ma.
differential between the amounts above fixed and
Cristina and Michel (sic), all surnamed Gonzaga,
those already deposited in PNB Savings Account No.
seeking a reconsideration of the values set by this
249-5-5865-7 within 48 hours from receipt of this
Court earlier at P3,734,120.00 for the areas affected
Order. Pending such compliance hereof, action on
consisting of the following:
the Motion for Issuance of Writ of Possession will be
held in abeyance. The representative of the plaintiff
7,050 square meters; may get from the Branch Clerk of Court the
6,600 square meters; and corresponding bank book earlier attached to
3,000 square meters the expediente for the purpose of complying with this
Order.
belonging to the aforesaid persons. The Court is
aware that the Order of July 25, 1990 was not based SO ORDERED.
on ultimate factual conditions of the property of the

ProvRem Rule 67 Fulltext Page 16 of 119


In compliance with the said Order, petitioner immediately deposited the BENJAMIN, ANA
additional sum of P22,866,860.00 with the Philippine National Bank under ALEXANDER, CARLO
Savings Account No. 249-505865-7 as evidenced by the Bank's SOPHIA, DANIEL
certification dated 13 July 1990. 24 also named
GONZAGA 007-5224 398,260.00
On 16 July 1990, respondent Judge issued an Order 25 mandatorily 5. ROSARIO MENDOZA Notice of Assessment
requiring the defendants: of Real Property dated
March 23, 1990,
Lot No. 1278-B-1 860.00
. . . to state in writing within twenty-four (24) hours 6. ROSARIO MENDOZA Notice of Assessment
whether or not they are amenable to accept and of Real Property dated
withdraw (sic) the amounts already deposited by the March 23, 1990, 861,380.00
plaintiff for each of them at final and full satisfaction Lot No. 1278-C-1 429,080.00
of the value of their respective property (sic) affected 7. CEL-SOY-AGRO-
by expropriation, and this is mandatory. IND. CORPORATION 2284 179,650.00
8. LYDIA S. ANO
[t]he Writ of Possession sought for by the plaintiff will married to
be issued immediately after manifestation of EMMANUEL ANO 4047 (0854-05) 137,160.00
acceptance and receipt of said amounts. 9. PACITA LACSON
(MAYO L. LACSON) Notice of Assessment
On 18 July 1990, respondent Judge, claiming to act on the of Real Property dated
Manifestation — filed in compliance with the Order of 16 July 1990 — of March 21, 1990
defendants Jesus Gonzaga, et al. in Civil Case No. 5938, Luis Gonzaga, et Lot No. 7-G 861,380.00
al. in Civil Case No. 5939, Rosario Mendoza in Civil Case No. 5940, 10. DOLORES D.
Emmanuel Año, et al. in Civil Case No. 5942 and Mayo Lacson in Civil Case COSCOLLUELA 020-00017 487,730.00
No. 5943, issued an Order 26 directing the petitioner to pay the (LUCIA GOSIENFIAO)
defendants within twenty-four (24) hours, through the court and from
petitioner's Philippine National Bank Savings Account No. 249-505865-7 Yet, petitioner submits that in a clear display of abuse of discretion,
or from any other fund; whichever may be most expeditious, the following respondent Judge fixed, in the Order of 25 June 1990, the provisional
amounts by way of full payment for their expropriated property: valued as follows:

CIVIL CASE NO. AFFECTED AREA VALUE CIVIL CASE AFFECTED AREA MARKET PROVISIONAL
(SQ. M.) VALUE (SQ. M.) VALUE
NO.
1. 5938 7,050 P 6,000,000.00
3,000 3,000,000.00 1. 5938 7,050 P 45,000.00 P 180,000.00
6,600 5,000,000.00 3,000 668,700.00 2,674,800.00
2. 5939 23,000 12,600,000.00 6,600 219,830.00 879,320.00
3. 5940 9,030 11,480.00 2. 5939 23,400 757,437.00 3,029,748.00
4. 5941 17,430 1,732,520.00 3 5940 9,030 2,870.00 11,480.00
5. 5942 2,700 1,371,600.00 4. 5941 17,430 433,130.00 1,732,520.00
6. 5943 15,900 8,501,360.00 5. 5942 2,700 342,900.00 1,371,600.00
7. 5944 21,000 4,800,000.00 6. 5943 15,900 2,125,340.00 8,501,360.00
7. 5944 21,000 1,200,000.00 4,800,000.00
and ordering that the writ of possession be issued in these cases after the
defendants "have duly received the amounts." and that:

Unable to accept the above Orders of 25 June, 12 July, 16 July and 18 July . . . in another clear abuse (sic) of discretion, herein
1990, petitioner filed this petition on 24 July 1990 alleging therein, as respondent Judge, on the basis of the respective
grounds for its allowance, that respondent Judge acted in excess of Motion (sic) for Reconsideration of defendants in Civil
jurisdiction, in violation of laws and in dereliction of the duty to afford Cases Nos. 5938 and 5939, without affording the
respondents due process when he issued said Orders. In support thereof herein petitioner an opportunity to be heard, and
petitioner asserts that the Orders of 25 June and 12 July 1990 fixing the with evident and manifest partiality to therein
provisional values at excessive and unconscionable amounts, are utterly defendants increased the previously fixed provisional
scandalous and unreasonable. As classified under their respective tax value of their respective lands, as follows:
declarations, the several lots to be expropriated are sugarlands with the
following assessed values: a. Civil Case No. 5938:

OWNER TAX DEC. NO. ASSESSED 1. 7,050 sq. m. — From


VALUE P180,000.00 to P6,000,000.00

1. JESUS L. GONZAGA 007-000621 P18,000.00 2. 3,000 sq. m. — From


2. Estate of SOPHIA P2,674,800.00 to P3,000,000.00
Vda. de GONZAGA 007-000495 267,480.00
3. JESUS GONZAGA 005-000007 87,930.00
4. LOUIS, DIONISIO 3. 6,600 sq. m. — From
ROBERTO, GABRIEL P879,320.00 to P5,000,000.00

ProvRem Rule 67 Fulltext Page 17 of 119


b. Civil Case No. 5939 Mayo Lacson — 14 September
199028
1. 23,400 sq. m. — From Rosario P. Mendoza — 18
P3,029,748.00 to P12,600,000.00 September 199029
Jesus Gonzaga, et al.;
Emmanuel Año, et al. — 27
Nevertheless, due to its urgent need for the areas to be able to complete September 199030
the interconnection project as soon as possible, petitioner deposited the Luis Gonzaga, et al. — 20
amounts representing the provisional values fixed by the respondent September 199031
Judge. Still, petitioner laments, the latter persisted in his stubbornness by
not issuing a writ of possession, in violation of Section 2, Rule 67 of the
Rules of Court which provides that upon the filing of the complaint or at All of them, except for Rosario P. Mendoza who informed the Court that
any time thereafter, the plaintiff shall have the right to take or enter upon she filed a motion to reconsider the 18 July 1990 Order of respondent
the possession of the real or personal property involved if he deposits Judge and who agrees with petitioner that commissioners should be
with the National or Provincial Treasurer its value, as provisionally and appointed to determine the just compensation, 32 support and sustain the
promptly ascertained and fixed by the court having jurisdiction of the actions of respondent Judge and pray for the dismissal of the petition.
proceedings, to be held by such treasurer subject to the orders and final
disposition of the court; and that after such deposit to made, the court Mayo Lacson, in submitting that the procedure prescribed in Rule 67 may
shall order the sheriff or other proper officer to forthwith place the be abbreviated provided that the rights of the parties are duly protected,
plaintiff in possession of the property involved P.D. No. 42, which provides cites the case of City Government of Toledo vs. Fernandos, et al. 33 wherein
that: this Court sustained the judgment of the trial court on the basis of what
transpired in the pre-trial conference.
. . . upon filing in the proper court of the complaint in
eminent domain proceedings or at anytime Complying with the Resolution of the 25 September 1990, petitioner filed
thereafter, and after due notice to the defendant, on 6 November 1990 a Reply to the Comment of respondent Mayo
plaintiff shall have the right to take or enter upon the Lacson, 34 stressing therein that the case of City Government of Toledo City
possession of the real property involved if he vs.Fernandos, et al. 35 does not apply to the present case because a pre-
deposits with the Philippine National Bank, in its main trial was conducted in the former during which the parties were able to
office or any of its branches or agencies, an amount present their respective positions on just compensation.
equivalent to the assessed value of the property for
purposes of taxation, to be held by said bank subject On 22 January 1991, this Court resolved to consider the respondents'
to the orders and final disposition of the court. Comments as Answers to the petition, give due course to the petition and
require the parties to file simultaneously their respective Memoranda
is also alleged to have been violated by respondent Judge. within twenty (20) days from notice, which petitioner complied with on 11
March
The issuance then of the writ of possession was an unqualified ministerial 1991; 36 respondent Mendoza on 4 March 1991; 37 respondents Jesus
duty which respondent Judge failed to perform. Gonzaga, et al. and Emmanuel Año, et al. on 19 March 1991; 38 and Mayo
Lacson on 5 April 1991. 39

Moreover, the Order of 16 July 1990 surrenders the judicial prerogative to


fix the provisional value in favor of the defendants considering that We find merit in the petition.
respondent Judge's valuation may still be overruled by the latter since
they were given twenty-four (24) hours to state in writing whether or not Respondent Judge committed grave abuse of discretion amounting to
they are accepting and withdrawing the amount already deposited by lack of jurisdiction, and is otherwise either unmindful or ignorant of the
petitioner. law: when he fixed the provisional values of the properties for the purpose
of issuing a writ of possession on the basis of the market value and the
Finally, petitioner contends that the Order of 16 July 1990 partakes of the daily opportunity profit petitioner may derive in violation or in disregard
nature of a final disposition of the case should the defendants accept the of P.D. No. 42; in amending such determination in Civil Cases Nos. 5938
provisional value as "final and full satisfaction of the value of their and 5939 by increasing the same without hearing; in directing the
respective property (sic)affected by expropriation," thereby preempting defendants to manifest within twenty-four (24) hours whether or not they
and depriving the former of the right to dispute and contest the value of are accepting and withdrawing the amounts, representing the provisional
the property. Clearly, respondent Judge took a short-cut, violating in the values, deposited by the plaintiff for each of them as "final and full
process the procedure laid down in Sections 3 to 8, inclusive, of Rule 67 of satisfaction of the value of their respective property (sic); " in declaring the
the Rules of Court. provisional values as the final values and directing the release of the
amounts deposited, in full satisfaction thereof, to the defendants even if
not all of them made the manifestation; and in suspending the issuance of
In the Resolution of 31 July 1990, this court required the respondents to the writ of possession until after the suspending the amounts shall have
comment on the petition and resolved to issue a temporary restraining been released to and received by defendants.
order, effective immediately and to continue until further orders from the
Court, compelling the respondent Judge to cease and desist from
enforcing and/or executing his questioned Orders and directing him, In Municipality of Biñan vs. Hon. Jose Mar Garcia, et al., 40 this Court ruled
pending determination of this case, to place petitioner in possession of that there are two (2) stages in every action of expropriation:
the properties subject of this
petition. 27 The first is concerned with the determination of the
authority of the plaintiff to exercise the power of
The following respondents filed, through their counsels, their Answers on eminent domain and the propriety of its exercise in
various dates, as follows: the context of the facts involved in the suit. 41 It ends
with an order, if not of dismissal of the action, "of
condemnation declaring that the plaintiff has a lawful

ProvRem Rule 67 Fulltext Page 18 of 119


right to take the property sought to be condemned, . . . The statute directs that, at the very outset, "when
for the public use or purpose described in the condemnation proceedings are brought by any
complaint, upon the payment of just compensation railway corporation" the amount of the deposit is to
to be determined as of the date of the filing of the be "provisionally and promptly ascertained and fixed
complaint." 42 An order of dismissal, if this be by the court." It is very clear that it was not the
ordained, would be a final one, of course, since it intention of the legislator that before the order fixing
finally disposes of the action and leaves nothing the amount of the deposit could lawfully be entered
more to be done by the Court on the merits. 43 So, the court should finally and definitely determine who
too, would an order of condemnation be a final one, are the true owners of the land; and after doing so,
for thereafter as the Rules expressly state, in the give them a hearing as to its value, and assess the
proceedings before the Trial Court, "no objection to true value of the land accordingly. In effect, that
the exercise of the right of condemnation (or the would amount to a denial of the right of possession
propriety thereof) shall be filed or heard." of the lands involved until the conclusion of the
proceedings, when there would no need for the filing
The second phase of the eminent domain action is of the deposit. Of course, there is nothing in the
concerned with the determination by the Court of the statute which denies the right of the judge to hear all
"just compensation for the property sought to be persons claiming an interest in the land, and courts
taken." This is done by the Court with the assistance should ordinarily give all such persons an opportunity
of not more than three (3) commissioners. 44 The to be heard if that be practicable, and will cause no
order fixing the just compensation on the basis of the delay in the prompt and provisional ascertainment of
evidence before, and findings of, the commissioners the value of the land. But the scope and extent of the
would be final, too. It would finally dispose of the inquiry is left wholly in the discretion of the court,
second stage of the suit, and leave nothing more to and a failure to hear the owners and claimants of the
be done by the Court regarding the issue. . . . land, who may or may not be known at the time of
the entry of the order, in no wise effects the validity
of the order. . . .
However, upon the filing of the complaint or at any time thereafter, the
petitioner has the right to take or enter upon the possession of the
property involved upon compliance with P.D. No. 42 which requires the P.D. No. 42, however, effectively removes the discretion of the court in
petitioner, after due notice to the defendant, to deposit with the determining the provisional value. What is to be deposited is an amount
Philippine National Bank in its main office or any of its branches or equivalent to the assessed value for taxation purpose. 46 No hearing is
agencies, "an amount equivalent to the assessed value of the property for required for that purpose. All that is needed is notice to the owner of the
purposes of taxation." This assessed value is that indicated in the tax property sought to be condemned. 47
declaration.
Clearly, therefore, respondent Judge either deliberately disregarded P.D.
P.D. No. 42 repealed the "provisions of Rule 67 of the Rules of Court and No. 42 or was totally unaware of its existence and the cases applying the
of any other existing law contrary to or inconsistent" with it. Accordingly, same.
it repealed Section 2 of Rule 67 insofar as the determination of the
provisional value, the form of payment and the agency with which the In any event, petitioner deposited the provisional value fixed by the court.
deposit shall be made, are concerned. Said section reads in full as follows: As a matter of right, it was entitled to be placed in possession of the
property involved in the complaints at once, pursuant to both Section 2 of
Sec. 2. Entry of plaintiff upon depositing value with Rule 67 and P.D. No. 42. Respondent Court had the corresponding duty to
National or Provisional Treasurer. — Upon the filing order the sheriff or any other proper officer to forthwith place the
of the complaint or at any time thereafter the plaintiff petitioner in such possession. Instead of complying with the clear
shall have the right to take or enter upon the mandate of the law, respondent Judge chose to ignore and overlook it.
possession of the real or personal property involved if Moreover, upon separate motions for reconsideration filed by the
he deposits with the National or Provincial Treasurer defendants in Civil Cases Nos. 5938 and 5939, he issued a new Order
its value, as provisionally and promptly ascertained increasing the provisional values of the properties involved therein. No
and fixed by the court having jurisdiction of the hearing was held on the motions. As a matter of fact, as the records show,
proceedings, to be held by such treasurer subject to the motion for reconsideration filed by defendants Jesus Gonzaga, et al. in
the orders and final disposition of the court. Such Civil Case No. 5938 is dated 11 July 1990 48 while the Order granting both
deposit shall be in money, unless in lieu thereof the motions was issued the next day, 12 July 1990. 49 The motion for
court authorizes the deposit of a certificate of deposit reconsideration in Civil Case No. 5938 does not even contain a notice of
of a depository of the Republic of the Philippines hearing. It is then a mere scrap of paper; it presents no question which
payable on demand to the National or Provincial merits the attention and consideration of the court. It is not even a mere
Treasurer, as the case may be, in the amount directed motion for it does not comply with the rules, more particularly Sections 4
by the court to be deposited. After such deposit is and 5, Rule 15 of the Rules of Court; the Clerk of Court then had no right
made the court shall order the sheriff or other proper to receive it. 50
officer to forthwith place the plaintiff in possession of
the property involved. There was, moreover, a much stronger reason why the respondent Court
should not have issued the 12 July 1990 Order increasing the provisional
It will be noted that under the aforequoted section, the court has the values of the Gonzaga lots in Civil Cases Nos. 5938 and 5939. After having
discretion to determine the provisional value which must be deposited by fixed these provisional values, albeit erroneously, and upon deposit by
the plaintiff to enable it "to take or enter upon the possession of the petitioner of the said amounts, respondent Judge lost, as was held
property." Notice to the parties is not indispensable. In interpreting a in Manila Railroad Company vs. Paredes, 51 "plenary control over the order
similar provision of Act No. 1592, this Court, in the 1915 case of Manila fixing the amount of the deposit, and has no power to annul, amend or
Railroad Company, et al. vs. Paredes, et al., 45 held: modify it in matters of substance pending the course of the
condemnation proceedings." The reason for this is that a contrary ruling
would defeat the very purpose of the law which is to provide a speedy
ProvRem Rule 67 Fulltext Page 19 of 119
and summary procedure whereby the peaceable possession of the duties in the manner provided for in Section 6; upon the filing of their
property subject of the expropriation proceedings "may be secured report, the court may, after a period of ten (10) days which it must grant
without the delays incident to prolonged and vexatious litigation touching to the parties in order that the latter may file their objections to such
the ownership and value of such lands, which should not be permitted to report, and after hearing pursuant to Section 8, accept and render
delay the progress of the work." judgment in accordance therewith or, for cause shown, recommit the
same to the commissioners for further report of facts. The court may also
Compounding the above error and the capriciousness with which it was set aside the report and appoint new commissioners, or it may accept the
committed is respondent Judge's refusal to place the petitioner in report in part and reject it in part; and it may make such order or render
possession of the property or issue the writ of possession despite the fact such judgment as shall secure to the petitioner the property essential to
that the latter had likewise deposited the additional amount called for by the exercise of its right of condemnation, and to the defendant just
the 12 July 1990 Order. Instead, respondent Judge issued the 16 July 1990 compensation for the property so taken.
Order directing the defendants to state in writing within twenty-four (24)
hours whether or not they would accept and withdraw the amounts Not satisfied with the foregoing violations of law and insisting upon his
deposited by the petitioner for each of them " as final and full satisfaction own procedure, respondent Judge declared in his Order of 18 July 1990
of the value of their respective property (sic) affected by the that the provisional amounts he fixed, later increased with respect to the
expropriation" and stating at the same time that the writ will be issued properties of the Gonzagas, shall be considered as the full payment of the
after such manifestation and acceptance and receipt of the amounts. value of the properties after the defendants in Civil Cases Nos. 5938, 5939,
5940, 5942 and 5943 shall have filed their manifestations; he also ruled
The above Order has absolutely no legal basis even as it also unjustly, that the writ of possession will be issued only after the latter shall have
oppressively and capriciously compels the petitioner to accept the received the said amounts. This Order and the records before this Court
respondent Judge's determination of the provisional value as the just do not disclose that the defendants in Civil Cases Nos. 5941 and 5944
compensation after the defendants shall have manifested their conformity filed any manifestation; yet, in the Order, respondent Judge whimsically
thereto. He thus subordinated his own judgment to that of the and arbitrarily considered the so-called provisional values fixed therein as
defendants' because he made the latter the final authority to determine the final values. By such Order, the case was in fact terminated and the
such just compensation. This Court ruled in Export Processing Zone writ of execution then became a mere incident of an execution of a
Authority vs. Dulay, et al. 52 that the determination of just compensation in judgment. The right of the petitioner to take or enter into possession of
eminent domain cases is a judicial function; accordingly, We declared as the property upon the filing of the complaint granted by Section 2 of Rule
unconstitutional and void, for being, inter alia, impermissible 67 and P.D. No. 42 was totally negated despite compliance with the
encroachment on judicial prerogatives which tends to render the Court deposit requirement under the latter law.
inutile in a matter which, under the Constitution, is reserved to it for final
determination, the method of ascertaining just compensation prescribed Nothing can justify the acts of respondent Judge. Either by design or
in P.D. Nos. 76 464, 794 and 1533, to wit: the market value as declared by sheer ignorance, he made a mockery of the procedural law on eminent
the owner or administrator or such market value as determined by the domain by concocting a procedure which he believes to be correct.
assessor, whichever is lower in the first three (3) decrees, and the value Judges must apply the law; they are not at liberty to legislate. As Canon
declared by the owner or administrator or anyone having legal interest in 18 of the Canon of Judicial Ethics provides:
the property or the value as determined by the assessor, pursuant to the
Real Property Tax Code, whichever is lower, prior to the recommendation A judge should be mindful that his duty his the
or decision of the appropriate Government office to acquire the property, application of general law to particular instances, that
in the last mentioned decree. If the legislature or the executive ours is a government of law and not of men, and that
department cannot even impose upon the court how just compensation he violates his duty as a minister of justice under such
should be determined, it would be far more objectionable and a system if he seeks to do what he may personally
impermissible for respondent Judge to grant the defendants in an consider substantial justice in a particular case and
eminent domain case such power and authority. disregards the general law as he knows it to be
binding on him. Such action may become a
Without perhaps intending it to be so, there is not only a clear case of precedent unsettling accepted principles and may
abdication of judicial prerogative, but also a complete disregard by have detrimental consequences beyond the
respondent Judge of the provisions of Rule 67 as to the procedure to be immediate controversy. He should administer his
followed after the petitioner has deposited the provisional value of the office with a due regard to the integrity of the system
property. It must be recalled that three (3) sets of defendants filed of the law itself, remembering that he is not a
motions to dismiss 53 pursuant to Section 3, Rule 67 of the Rules of Court; depositary of arbitrary power, but a judge under the
Section 4 of the same rule provides that the court must rule on them and sanction of law.
in the event that it overrules the motions or, when any party fails to
present a defense as required in Section 3, it should enter an order of They must be reminded once more that "the demands of fair, impartial,
condemnation declaring that the petitioner has a lawful right to take the and wise administration of justice call for a faithful adherence to legal
property sought to be condemned. precepts on procedure which ensure to litigants the opportunity to
present their evidence and secure a ruling on all the issues presented in
As may be gleaned from the 25 June 1990 Order, the respondent Judge their respective pleadings. "Short-cuts" in judicial processes are to be
found that the petitioner has that right and that "there will be a (sic) avoided where they impede rather than promote a judicious disposition
paramount public interest to be served by the expropriation of the of justice." 54
defendants' properties." Accordingly, considering that the parties
submitted neither a compromise agreement as to the just compensation We agree with the petitioner that the ruling in the case of City
nor a stipulation to dispense with the appointment of commissioners and Government of Toledo City vs. Fernandos, et al., 55does not apply to the
to leave the determination of just compensation to the court on the basis instant petition because at the pre-trial conference held therein, the
of certain criteria, respondent Judge was duty bound to set in motion petitioner submitted to the discretion of the court as to the correct
Section 5 of Rule 67; said section directs the court to appoint not more valuation, private respondents stated that they have no objections and
than three (3) competent and disinterested persons as commissioners to are in conformity with the price of P30.00 per square meter as reasonable
ascertain and report to it regarding the just compensation for the compensation for their land and the City Assessor informed the court of
property sought to be taken. Such commissioners shall perform their
ProvRem Rule 67 Fulltext Page 20 of 119
the current market and appraisal values of the properties in the area and TAKENAKA CORPORATION AND ASAHIKOSAN
the factors to be considered in the determination of such. The parties CORPORATION, Petitioners,
presented their documentary exhibits. In effect, therefore, the parties vs.
themselves agreed to submit to a judicial determination on the matter of REPUBLIC OF THE PHILIPPINES, represented by Executive Secretary
just compensation and that judgment be rendered based thereon. In the Eduardo Ermita, DEPARTMENT OF TRANSPORTATION AND
instant case, no pre-trial was conducted; the proceedings were still at that COMMUNICATIONS, MANILA INTERNATIONAL AIRPORT
state where the provisional value was yet to be determined; and the AUTHORITY, AND PHILIPPINE INTERNATIONAL AIR TERMINALS
parties made no agreement on just compensation. COMPANY, INC. Respondents.

WHEREFORE, the instant petition is GRANTED and the Orders of x-----------------------x


respondent Judge of 25 June 1990, 12 July 1990, 16 July 1990 and 18 July
1990 are hereby SET ASIDE and the temporary restraining order issued by G.R. No. 209731
this Court on 31 July 1990 directing respondent Judge to cease and desist
from enforcing the questioned Orders is hereby made permanent.
PHILIPPINE INTERNATIONAL AIR TERMINALS CO., INC. Petitioner,
vs.
The respondent Judge is hereby directed to fix the provisional values of REPUBLIC OF THE PHILIPPINES, as represented by EXECUTIVE
the parcels of land in Civil Cases Nos. 5938, 5939, 5940, 5941, 5942, 5943, SECRETARY EDUARDO ERMITA, DEPARTMENT OF
and 5944 in accordance with P.D. No. 42; thereafter, the petitioner may TRANSPORTATION AND COMMUNICATIONS, MANILA
retain in Savings Account No. 249-505865-7 with the Philippine National INTERNATIONAL AIRPORT AUTHORITY, TAKENAKA CORPORATION,
Bank, NAPOCOR Branch, Diliman, Quezon City, a sum equivalent to the AND ASAHIKOSAN CORPORATION, Respondents.
provisional value as thus fixed, which the Bank shall hold subject to the
orders and final disposition of the court a quo, and withdraw the balance.
DECISION

The respondent Judge is further directed to proceed with the above


BRION, J.:
eminent domain cases without unnecessary delay pursuant to the
procedure laid down in Rule 67 of the Rules of Court.
Before the Court are the consolidated petitions for review on certiorari
Finally, respondent Judge is reminded to comply faithfully with the assailing the Decision dated August 22, 2013, and the Resolution dated
procedure provided for in the Rules of Court. Let a copy of this Decision October 29, 2013, of the Court of Appeals (CA) in CA-G.R. CV No. 98029;
be appended to his record. and the petition for certiorari assailing the May 3, 2007; May 18, 2008; and
January 7, 2008 Decision of the Regional Trial Court (RTC) of Pasay City,
Branch 117, in Civil Case No. 04-0876.1
Costs against private respondents.

In CA-G.R. CV No. 98029, the CA ordered petitioners Republic of the


IT IS SO ORDERED. Philippines, Department of Transportation and Communications, and
Manila International Airport Authority (Government for brevity) to pay the
#6 G.R. No. 181892 September 8, 2015 Philippine International Airport Terminals Co., Inc. (PIATCO) the amount of
$371,426,688.24 with interest at 6%per annum as just compensation for
THIS CASE IS TOO LONG (eats up 60 pages of the Fulltext file) the expropriation of the Ninoy Aquino International Airport Passenger
Terminal III (NAIA-IPT III).2

REPUBLIC OF THE PHILIPPINES, represented by Executive Secretary


Eduardo R. Ermita, the DEPARTMENT OF TRANSPORTATION AND In Civil Case No. 04-0876, the RTC appointed DG Jones and Partners as an
COMMUNICATIONS, AND MANILA INTERNATIONAL AIRPORT independent appraiser of the NAIA-IPT III, and ordered the Government
AUTHORITY, Petitioners, to submit a Certificate of Availability of Funds to cover DG Jones and
vs. Partners' appraisal fee of $1,900,000.00.
HON. JESUS M. MUPAS, in his capacity as Acting Presiding Judge of the
Regional Trial Court, National Capital Judicial Region, Branch 117, Pasay For ease of presentation, the Court's discussion shall be under the
City, AND PHILIPPINE INTERNATIONAL AIR TERMINALS CO., following structure:
INC., Respondents.
I. The Factual Antecedents
x-----------------------x
A. The NAIA-IPT IIII Contract and PIATCO
G.R. No. 209917
1. The NAIA-IPT III Contract
REPUBLIC OF THE PHILIPPINES, represented by Executive Secretary
Eduardo Ermita, DEPARTMENT OF TRANSPORTATION AND 2. PIATCO
COMMUNICATIONS, AND MANILA INTERNATIONAL AIRPORT
AUTHORITY, Petitioners,
vs. 3. PIATCO and the Services of Takenaka
and Asahikosan
PHILIPPINE INTERNATIONAL AIR TERMINALS COMPANY, INC.,
TAKENAKA CORPORATION AND ASAHIKOSAN
CORPORATION, Respondents. B. The Agan v. PIATCO Case, G.R. No. 155001

x-----------------------x 1. The Case and the Decision dated May 5,


2003
G.R. No. 209696
ProvRem Rule 67 Fulltext Page 21 of 119
2. The Motion for Reconsideration and the VI. The Issues
Resolution dated January 21, 2004
VII. The Court's Rulings
C. The Expropriation Case, Civil Case No. 04-0876
A. G.R. Nos. 209917, 209696, and 209731
D. The Republic v. Gingoyon Case, G.R. No. 166429
1. The parties were afforded procedural
1. The Case and the Decision dated due process despite their non-receipt of
December 19, 2005 the BOC Final Report prior to the
promulgation of the May 23, 2011 Decision
2. The Motion for Reconsideration and the in Civil Case No. 04-0876.
Resolution dated February 1, 2006
2. Framework: Eminent domain is an
E. Proceedings in Civil Case No. 04-0876 after the inherent power of the State
Finality of the Gingoyon Case
2.a. The power of eminent
1. The Appointment of DG Jones and domain is a fundamental state
Partners as an Independent Appraiser power that is inseparable from
sovereignty

2. The BOC's Expenses


2.b. Just compensation is the full
and fair equivalent of the
F. The Parties and the BOC's Appraisal of the NAIA- property taken from the owner
IPT III by the condemn or

1. The Government's Appraisal 2.b.1. Fair market value


is the general standard
2. PIATCO's Appraisal of value in
determining just
3. Takenaka and Asahikosan's Appraisal compensation

4. The BOC's Appraisal 2.b.2 Replacement cost


is a different standard
of value from fair
II. The RTC Rulings in Civil Case No. 04-0876
market value

A. The Main Decision


2.b.3. Replacement
cost is only one of the
B. The RTC's Interlocutory Order on the Validity of the standards that the
Escrow Account Court should consider
in appraising the
1. The Government and the Creation of an NAIA-IPT III
Escrow Account for the Payment of Just
Compensation 2.b.4. The use of
depreciated
2. The Omnibus Order dated October 11, replacement cost
2011 method is consistent
with the principle that
the property owner
III. The CA Rulings
should be
compensated for his
A. CA-G.R. CV No. 98029 actual loss

B. CA-G.R. SP. No. 123221 3. Construction cost of the NAIA-IPT III

IV. The Action to Enforce the London Awards, Civil Case No. 06-171 3.a. The base valuation of the
NAIA-IPT III
V. The Parties' Positions
3.b. Structural defects on the
A. The Government's Position NAIA-IPT III

B. PIATCO's Position 3.b.1. The Court


cannot consider the
additional evidence
C. Takenaka and Asahikosan's Position
submitted by
ProvRem Rule 67 Fulltext Page 22 of 119
Takenaka and 9.b. The property owner is
Asahikosan before the entitled to just compensation
Court of Appeals
9.c. A final disposition in the
3.b.2. Equiponderance eminent domain case with
of evidence on the respect to the order of payment
alleged structural to a particular person shall be
defects of the NAIA- final and executory
IPT III favors PIATCO,
Takenaka, and 9.d. The determination of
Asahikosan whether the NAIA-IPT III shall be
burdened by liens and
3.c. The unnecessary areas mortgages even after the full
payment of just compensation is
4. Attendant cost of the NAIA-IPT III premature

4.a. PIATCO's attendant cost 10. The exercise of eminent domain from
the perspective of "taking."

4.b. The BOC and the RTC's


attendant cost 10.a. The Government may take
the property for public purpose
or public use upon the issuance
4.c. The Government's attendant and effectivity of the writ of
cost possession

5. Deductions to the Replacement Cost of B. G.R. No. 181892


the NAIA-IPT III

1. The issue on the appointment of an


5.a. Depreciation should be independent appraiser is already moot and
deducted from the replacement academic
cost

I. The Factual Antecedents


5.b. Rectification for contract
compliance should not be
deducted from the replacement A. The NAIA-IPT III Contract and PIATCO
cost
1. The NAIA-IPT III Contract
6. Adjustments to the Replacement Cost
On October 5, 1994, Asia's Emerging Dragon Corp. (AEDC)
6.a. The replacement cost should submitted an unsolicited proposal to the Government - through
be adjusted to December 2004 the Department of Transportation and Communications
values (DOTC)and the Manila International Airport Authority (MIAA)-
for the construction and development of the NAIA-IPT III under
a build-operate-and-transfer (BOT) arrangement. The DOTC
7. Interests, Fruits, and Income
and the MIAA invited the public to submit competitive and
comparative proposals to AEDC's unsolicited proposal in
7.a. Computation of Interests accordance with the BOT Law3 and its implementing rules.4

7.b. PIATCO is not entitled to the 2. PIATCO


fruits and income of the NAIA-
IPT III
On September 20, 1996, Paircargo Consortium - composed of
People's Air Cargo and Warehousing Co., Inc. (Paircargo),
8. The BOC's Expenses Philippine Air and Grounds Services, Inc.(PAGS), and Security
Bank Corporation (Security Bank)- submitted its competitive
8.a. Takenaka and Asahikosan proposal to the Prequalification Bids and Awards Committee
should not share in the BOC's (PBAC).5
expenses
Both AEDC and Paircargo Consortium offered to build the
9. PIATCO as the Proper Recipient of Just NAIA-IPT III for at least $350 million at no cost to the
Compensation Government and to pay the Government: 5% share in gross
revenues for the first five years of operation, 7.5% share in
gross revenues for the next ten years of operation, and 10%
9.a. Takenaka and Asahikosan's
share in gross revenues for the last ten years of operation.
intervention in the case as
However, Paircargo Consortium offered to pay the Government
unpaid subcontractors is proper
a total of ₱17.75 billion as guaranteed payment for 27 years

ProvRem Rule 67 Fulltext Page 23 of 119


while AEDC offered to pay the Government a total of ₱135 being contrary to law. The case, entitled Agan v. PIATCO, was
million for the same period.6 docketed as G.R. No. 155001.16

After finding that Paircargo Consortium submitted a bid On May 5, 2003, the Court nullified the PIATCO contracts after
superior to the AEDC's unsolicited proposal and after the finding that Paircargo Consortium (that later incorporated into
AEDC's failure to match the competitive bid, the DOTC PIATCO) was not a duly pre-qualified bidder for failure to meet
awarded, through a notice of award, the NAIA-IPT III project to the minimum equity requirements for the NAIA-IPT III project,
the Paircargo Consortium (that later organized itself as as required under the BOT Law and the Bid Documents. The
PIATCO).7 Court also ruled that Security Bank(member of the Paircargo
Consortium) invested its entire net worth in a single
On July 12, 1997, the Government executed a Concession undertaking or enterprise in gross violation of Section 21-B of
Agreement with PIATCO for the construction, development, and the General Banking Act(which limits a commercial bank's
operation of the NAIA-IPT III under a build-operate-transfer equity investment, whether allied or non-allied, to fifteen
scheme. On November 26, 1998, the Amended and Restated percent (15%) of its net worth).17The Court further found that
Concession Agreement (ARCA) superseded the 1997 the PIATCO contracts contained provisions that substantially
Concession Agreement. The Government and PIATCO likewise departed from the draft Concession Agreement. These
entered into a series of supplemental agreements, namely: the substantial modification of the PIATCO contracts violated the
First Supplement signed on August 27, 1999; the Second public policy for being repugnant to the principle that all
Supplement signed on September 4, 2000; and the Third bidders must be on equal footing during the public bidding.18
Supplement signed on June 22, 2001.8
2. The Motion for Reconsideration and the Resolution dated
Under the 1997 Concession Agreement, the ARCA and the January 21, 2004
Supplemental Agreement (for brevity, PIATCO contracts), the
Government authorized PIATCO to build, operate, and maintain We denied PIATCO, et al.'s motion for reconsideration in our
the NAIA-IPT III during the concession period of twenty-five January 21, 2004 resolution.19 Significantly, we stated in the
(25) years.9 resolution that the Government should first pay PIATCO as a
prerequisite before taking over the NAIA-IPT III, to wit:
3. PIATCO and the Services of Takenaka and Asahikosan
This Court, however, is not unmindful of the reality that the
On March 31, 2000, PIATCO engaged the services of Takenaka, structures comprising the NAIA-IPT III facility are almost
a local branch of a foreign corporation duly organized under complete and that funds have been spent by PIATCO in their
the laws of Japan and doing business in the Philippines, for the construction. For the Government to take over the said facility,
construction of the NAIA-IPT III under an Onshore Construction it has to compensate respondent PIATCO as builder of the said
Contract.10 structures. The compensation must be just and in accordance
with law and equity for the Government cannot unjustly enrich
itself at the expense of PIATCO and its investors.20 (Underlines
On the same date, PIATCO, through an Offshore Procurement and emphases ours)
Contract,11 likewise contracted the services of Asahikosan, a
foreign corporation duly organized under the laws of Japan, for
the design, manufacture, purchase, test and delivery of the C. The Expropriation Case, Civil Case No. 04-087621
Plant12 in the NAIA-IPT III.
On December 21, 2004, the Government filed a complaint for
In May 2002, PIATCO defaulted on its obligation to pay expropriation of the NAIA-IPT III before the RTC of Pasay,
Takenaka and Asahikosan pursuant to their respective Branch 117. The Government informed the RTC that it had
contracts. To settle the problem, Takenaka and Asahikosan deposited with the Land Bank of the Philippines (Land Bank)the
agreed to defer PIATCO's payments until June 2003, amount of ₱3,002,125,000.00, representing the NAIA-IPT III's
conditioned on their receipt of adequate security from PIATCO assessed value.22
as stipulated in the Fourth Supplemental Agreement (relating to
the Onshore Construction Contract)13 and the Fourth On the same day, the RTC issued a writ of possession in favor of
Supplement Agreement (relating to the Offshore Procurement the Government. Citing City of Manila v. Serrano,23 the RTC held
Contract), respectively.14 that that it had the ministerial duty to issue a writ of possession
upon: (1) the filing of the complaint for expropriation sufficient
On November 29, 2002, President Gloria Macapagal Arroyo in form and substance, and (2) the Government's deposit of the
declared in her speech that the Government would not honor amount equivalent to the property's assessed value, pursuant to
the PIATCO contracts. On the same day, Takenaka and Rule 67 of the Rules of Court.24
Asahikosan notified PIATCO that they were suspending the
construction of the NAIA-IPT III for PIATCO's failure to provide On January 4, 2005, the RTC modified its December 21, 2004
adequate security.15 order and directed: (1) the Land Bank to immediately release to
PIATCO the amount of US$62,343,175.7725 that would be
B. The Agan v. PIATCO Case, G.R. No. 155001 deducted from the just compensation; (2) the Government to
submit to the RTC a Certificate of Availability of Funds for the
payment of just compensation; and (3) the Government to
1. The Case and the Decision dated May 5, 2003
maintain and preserve the NAIA-IPT III pending the
expropriation proceedings and the full payment of just
On September 17, 2002, petitioners Demosthenes Agan, et al., compensation. The RTC likewise prohibited the Government
asked the Court to nullify the PIATCO contracts, and to prohibit from performing acts of ownership over the NAIA-IPT III such as
the DOTC and the MIAA from implementing these contracts for

ProvRem Rule 67 Fulltext Page 24 of 119


awarding concessions or leasing any part of the NAIA-IPT III to together with interest in the sum of 2,947,564.87
other parties.26 United States dollars up to and including 18 February
2005, being a total of 11,171,800.87 United States
The Government sought reconsideration of the January 4, 2005 dollars.
Order, arguing that Rule 67 of the Rules of Court, and not RA
8974,applied to the case since the NAIA-IPT III was not a 3. Save for the costs of and caused by the
national government infrastructure project.27 amendment of the particulars of claim, which will be
the subject of a separate Order, the Defendant do
RA 8974 is otherwise known as "An Act To Facilitate The pay the First Claimant's and the Second Claimant's
Acquisition Of Right-Of-Way, Site Or Location For National costs in the action, to be subject to detailed
Government Infrastructure Projects And For Other Purposes." assessment if not agreed.

The Government argued that under Section 2, Rule 67 of the DATED this 18th day of February 2005.39
Rules of Court, it shall have the right to a writ of possession
upon deposit with the authorized government depositary of an On the other hand, the dispositive part of the judgment award
amount equivalent to the assessed value of the property for in Claim No. HT-05-269 states:
purposes of taxation, which amount shall be held by the
depositary subject to the orders of the court. In contrast, IT IS ORDERED THAT:
Section 4 of RA 8974, as a rule, requires the Government to
immediately pay the property owner the amount equivalent
to100% of the value of the property based on the BIR's relevant 1. Judgment be entered for the First Claimant in the
zonal valuation and the value of the improvements/and or sum of 21,688,012.18 United States dollars, together
structures, upon the filing of the complaint and after due notice with interest in the sum of 6,052,805.83 United States
to the defendant. dollars.

On January 7, 2005, the RTC appointed three 2. Judgment be entered for the Second Claimant in
Commissioners28 to determine just compensation without the sum of 30,319,284.36 United States dollars,
consulting the Government and PIATCO.29 Due to these together with interest in the sum of 5,442,628.26
successive adverse rulings, the Government sought to inhibit United States dollars.
Judge Henrick F. Gingoyon, the RTC's presiding judge, from
hearing the case.30 (The judge was ambushed and killed on 3. The defendant to pay the Claimants' costs in the
December 31, 2005.)31 action, to be subject to detailed assessment if not
agreed.
On January 10, 2005, the RTC denied the Government's urgent
motion for reconsideration and motion for inhibition.32 DATED this 2 (sic) day of December 2005.40

On December 14, 2005, Asahikosan filed a motion for leave to Takenaka and Asahikosan asked the RTC to: (a) hold in
intervene in Civil Case No. 04-0876 (the expropriation abeyance the release of just compensation to PIATCO until the
case).33 On the other hand, Takenaka filed a Manifestation London awards are recognized and enforced in the Philippines;
dated December 15, 2005,34 with the attached Manifestation and (b) order that the just compensation be deposited with the
and Motion dated December 14, 2005.35 Takenaka alleged that RTC for the benefit of PIATCO's creditors.41
the Government impleaded it as an additional defendant in an
amended complaint for expropriation of the NAIA-IPT III, but During the hearing of the motions, the Government clarified
was not served summons. Takenaka thus manifested its that it neither filed an amended complaint for expropriation nor
voluntary appearance before the RTC.36 impleaded Takenaka as a necessary party in the case.42

Takenaka and Asahikosan informed the RTC that they had The RTC initially denied Takenaka and Asahikosan's respective
previously filed two collection cases against PIATCO, docketed Motions43 in the August 8, 2006 Order, but subsequently
as Claim Nos. HT-04-248 and HT-05-269, before the High Court reconsidered its ruling.44 In a March 12, 2007 Order, the RTC
of Justice, Queen's Bench Division, Technology and treated Takenaka's Manifestation with the attached
Construction Court in London, England, (London Court) on Manifestation and Motion as a motion to intervene and allowed
August 9, 2004. Takenaka and Asahikosan to intervene in the case as PIATCO's
creditors.45
In both instances, the London Court ruled in their favor. The
dispositive part of the judgment award in Claim No. HT-04-248 Pending the RTC's resolution of Takenaka and Asahikosan's
provides: motions for leave to intervene in the expropriation case, the
Government went directly to the Court seeking Judge
IT IS ORDERED THAT: Gingoyon's inhibition from the case; the nullification of the
order of release of the sum of $62.3 million to PIATCO; and the
1. Judgment be entered for the First Claimant37 in the nullification as well of the appointment of the commissioners.
sum of 6,602,971.00 United States dollars, together
with interest in the sum of 116,825,365.34 Philippine D. The Republic v. Gingoyon Case, G.R. No. 166429
pesos up to and including 18 February 2005.
1. The Case and the Decision dated December 19, 2005
2. Judgment be entered for the Second Claimant38 in
the sum of 8,224,236.00 United States dollars,
ProvRem Rule 67 Fulltext Page 25 of 119
On January 12, 2005, the Government, et al., filed a infrastructure project is of utmost urgency and
petition for certiorari with the Court assailing the importance and if there is no existing valuation of the
validity of the January 4, 7, and 10, 2005 orders of the property, the implementing agency shall immediately
RTC in the expropriation case.46 The case, entitled pay the proffered value of the property.49
Republic v. Gingoyon, was docketed as G.R. No.
166429. We thus observed that Section 2, Rule 67 of the Rules
of Court is contrary to our January 21, 2004
The Government argued that the RTC should not Resolution which required the Government to make
have ordered the release of $62.3 Million since the prior payment of just compensation to PIATCO
NAIA-IPT III's assessed value was only ₱3 billion. before it could take over the NAIA-IPT III.
Moreover, the RTC's prohibition against the
Government to perform acts of ownership on the The Court at the same time qualified the applicability
NAIA-IPT III was contrary to the essence of a writ of of RA 8974 to the expropriation of the NAIA-IPT III.
possession. It47 asserted that Rule 67 of the Rules of We held that the Congress may legislate on the
Court governed the expropriation of the NAIA-IPT III valuation standards of just compensation and the
since it was not a national government infrastructure manner of its payment since these are substantive
project. The Government likewise contended that the matters. We made clear, however, that the Congress
commissioners' appointment was void. It claimed that cannot legislate on the procedural aspects of
it had been deprived of due process since it was not expropriation since this power lies with the Court. In
given the opportunity to contest the appointment of fact, Section 14 of RA 8974 IRR provides that Rule 67
the commissioners. The Government likewise sought of the Rules of Court shall apply to "all matters
Judge Gingoyon's inhibition from the case due to his regarding defenses and objections to the complaint,
alleged manifest partiality to PIATCO.48 issues on uncertain ownership and conflicting claims,
effects of appeal on the rights of the parties, and
The Court partly granted the petition and rendered such other incidents affecting the complaint."
the following rulings:
Third, we held in abeyance the implementation of the
First, under the 2004 Resolution in Agan: (a) PIATCO writ of possession until the Government directly pays
must receive payment of just compensation to PIATCO the proffered value of ₱3 billion. The zonal
determined in accordance with law and equity; and valuation method under Section 4 of RA 8974 shall
(b) the Government is barred from taking over the not apply since the Government owns the land on
NAIA-IPT III until just compensation is paid. which the NAIA-IPT III stands. Consequently, PIATCO
should only be paid the value of the improvements
Second, RA 8974 applies in the expropriation case and/or structures using the replacement cost
insofar as the law: (a) requires the Government to method.50 Pending the determination of just
immediately pay PIATCO at least the proffered value compensation, the Government shall pay the sum of
of the NAIA-IPT III; and (b) provides valuation ₱3 billion as the provisional amount of just
standards in determining the amount of just compensation because there was no expedited
compensation. means by which the Government could immediately
take possession of the NAIA-IPT III.

RA 8974 is the governing law in cases where the


national government expropriates property for the We also stated that the replacement cost method is
purpose of commencing national government only one of the factors to be considered in
infrastructure projects such as the construction of the determining just compensation. Equity should
NAIA-IPT III. However, Rule 67 of the Rules of Court likewise be considered in determining just
applies in determining the assessed value and the compensation.
mode of deposit of just compensation if the national
government initiates the expropriation complaint for Fourth, we authorized the Government to perform
purposes other than national infrastructure projects. acts essential to the operation of the NAIA-IPT III as
an international airport terminal once the writ of
Under both Rule 67 of the Rules of Court and RA possession becomes effective. This authority covers
8974, the Government initiates the expropriation by the repair, reconditioning, and improvement of the
filing an expropriation complaint. However, the rules complex; maintenance of the existing facilities and
on the mode of deposit differ because Rule 67 of the equipment; installation of new facilities and
Rules of Court merely requires the Government to equipment; provision of services and facilities
deposit the assessed value of the property sought to pertaining to the facilitation of air traffic and
be expropriated with an authorized government transport; and other services that are integral to a
depositary before the issuance of a writ of modern-day international airport. This is consistent
possession. with Section 4 of RA 8974 which provides that "the
court shall immediately issue to the implementing
agency an order to take possession of the property
In contrast, RA 8974 commands the Government to and start the implementation of the project" upon
make a direct payment to the property owner prior to fulfillment of certain conditions.
the issuance of a writ of possession. Under RA 8974,
the payment shall be based on: (a) the BIR's zonal
valuation in case of land; and (b)the value of the This ruling qualified the Court's statement in its
improvements or structures under the replacement January 21, 2004 Resolution that "[f]or the
cost method. If the completion of a government Government to take over the said facility, it has to

ProvRem Rule 67 Fulltext Page 26 of 119


compensate respondent PIATCO as builder of the determine the just compensation
said structures." Nonetheless, we clarified that the to be paid to PIATCO by the
title to the NAIA-IPT III shall pass to the Government Government.
only upon full payment of the just compensation
since the proffered value is merely a provisional The Order dated 7 January 2005 is
determination of just compensation. AFFIRMED in all respects subject to the
qualification that the parties are given ten
Fifth, we ordered the RTC to complete its (10) days from finality of this Decision to
determination of just compensation within sixty (60) file, if they so choose, objections to the
days from finality of our decision since it was no appointment of the commissioners
longer possible for the RTC to determine just decreed therein.
compensation within sixty (60) days from the filing of
the complaint under Section 4 of RA 8974. Sixth, the The Temporary Restraining Order dated 14
RTC did not gravely abuse its discretion in appointing January 2005 is hereby LIFTED.
the commissioners. Neither Rule 67 of the Rules of
Court nor RA 8974 requires the RTC to consult the
parties in the expropriation case prior to the No pronouncement as to costs.52
appointment of commissioners. We also stated that
Rule 67 of the Rules of Court shall apply insofar as it 2. The Motion for Reconsideration and the Resolution dated
is consistent with RA 8974, the IRR, and the Court's February 1, 2006
rulings in Agan.
On January 2, 2006, the Government, et al., filed a motion for
Considering that the expropriation proceedings were partial reconsideration of the Court's December 19, 2005
effectively suspended seven days after the Decision.53 Asahikosan, Takenaka, and Rep. Salacnib F. Baterina
appointment of the commissioners, the parties may also filed a motion for leave to intervene and asked the Court's
file their objections with the RTC within five days reconsideration of its December 19, 2005 Decision.54
from finality of the decision in accordance with
Section 5, Rule 67 of the Rules of Court. Seventh, The Government raised the question of who between PIATCO,
there was no ground to order Judge Gingoyon's on the one hand, and Takenaka and Asahikosan, on the other
inhibition since the Government failed to show his was the NAIAIPT III's builder. The Government informed the
alleged partiality.51 Court that Takenaka and Asahikosan, as the unpaid contractors
in the NAIA-IPT III project, claimed significant liens on the
The dispositive portion of the Decision states: NAIA-IPT III. The Government opined that it would end up
expropriating the NAIA-IPT III with liens and claims in excess of
WHEREFORE, the Petition is GRANTED in its actual value if the proffered value would be directly released
PART with respect to the orders dated 4 to PIATCO.
January 2005 and 10 January 2005 of the
lower court. Said orders are AFFIRMED with As PIATCO's unpaid creditors, Takenaka and Asahikosan
the following MODIFICATIONS: intervened in the case. They relied on Mago v. Court of
Appeals55 as basis for their intervention. In that case, the Court
1) The implementation of the took the extraordinary step of allowing the motion for
Writ of Possession dated 21 intervention even after the challenged order of the trial court
December 2005 is HELD IN had already become final. On the other hand, Rep. Baterina
ABEYANCE, pending payment by invoked his prerogative as legislator and taxpayer to curtail the
petitioners to PIATCO of the payment of just compensation without any appropriation in
amount of Three Billion Two PIATCO's favor.
Million One Hundred Twenty
Five Thousand Pesos The Court denied the motions and held that the alleged liens
(₱3,002,125,000.00), representing over the NAIA-IPT III have not been judicially
the proffered value of the NAIA- established.Takenaka and Asahikosan were not parties to
IPT III facilities; Gingoyon and did not present their claims before the Court.
The Court did not make any declaration regarding Takenaka
2) Petitioners, upon the and Asahikosan's rights to any form of compensation for the
effectivity of the Writ of construction of the NAIA-IPT III.
Possession, are authorized [to]
start the implementation of the Moreover, the Court did not recognize the London awards in
Ninoy Aquino International favor of Takenaka and Asahikosan. Under Section 48, Rule 39 of
Airport Pasenger Terminal III the Rules of Court, a foreign judgment would not bind
project by performing the acts Philippine courts unless the judgment is recognized and
that are essential to the enforced in this jurisdiction. Philippine courts may annul a
operation of the said foreign judgment for lack of jurisdiction, lack of notice to the
International Airport Passenger party, collusion, fraud, clear mistake of law or fact, or when the
Terminal project; foreign judgment is contrary to public policy. Even assuming
that PIATCO is indeed liable to other parties, the creditors have
3) RTC Branch 117 is hereby other judicial avenues to ventilate and prove their claims
directed, within sixty (60) days against PIATCO.
from finality of this Decision, to
ProvRem Rule 67 Fulltext Page 27 of 119
The Court also categorically stated that PIATCO, as builder integrity of NAIA-IPT III; (b) Ove Arup & Partners
of the NAIA-IPT III, must first receive just compensation in Massachusetts, Inc. (Ove Arup)to conduct a design and
accordance with law and equity before the Government technical review of the NAIA-IPT III and to conduct a peer
may take over the NAIA-IPT III. review of TCGI Engineer's methodology and test results; and (c)
Gleeds International to determine the value of the NAIA-IPT
The Court likewise denied the motions for intervention for III.62
serious procedural errors. Under Section 2, Rule 19 of the Rules
of Court, the motion to intervene should be filed before the On June 20, 2006, the RTC ordered Land Bank to immediately
court's rendition of judgment, and not after the resolution of release the amount of ₱3 billion to PIATCO. The RTC ruled that
the case. Moreover, Takenaka and Asahikosan failed to the collapse of a portion of the NAIA-IPT III was not a
establish their legal interest in the case since their claims supervening event that would hinder the payment of the
against PIATCO have not been conclusively established in this proffered value to PIATCO. In compliance with this order, the
jurisdiction.56 Government tendered to PIATCO a ₱3 billion check on
September 11, 2006. On the same day, the RTC reinstated the
E. Proceedings in Civil Case No. 04-0876 after the Finality of the Gingoyon writ of possession in favor of the Government.63
Case
Thereafter, the Government and PIATCO submitted their list of
1. The Appointment of DG Jones and Partners as an Independent nominees for the appointment of an independent
Appraiser appraiser.64 On May 3, 2007,the RTC appointed DG Jones and
Partners as independent appraiser.65

On April 11, 2006, the RTC ordered the BOC to resume its
duties. In compliance, the BOC submitted its Inception Report On May 18, 2007, the RTC directed the Government to submit a
and Inception Framework to the RTC. On April 24, 2007, the Certificate of Availability of Funds to cover DG Jones and
parties and the BOC conferred to set the ground rules and Partners' $1.9 Million appraisal fee.66
procedure in determining the just compensation due to the
NAIA-IPT III. The Government sought the reconsideration of the May 3 and
18, 2007 orders. The Government complained that the
On April 26, 2006, the Government asked the RTC to stop the appointment of an appraiser apart from those hired by the
payment of ₱3 billion proffered value in view of an alleged Government would result in the unnecessary depletion of its
supervening event - the collapse of the ceiling of the arrival funds since it would be compelled to pay two appraisers.67
lobby section of the north side of the NAIA-IPT III on March 27,
2006. The Government claimed that the collapse created a 100- In response, PIATCO argued that the RTC has the inherent
square foot hole in the ceiling and caused heavy asbestos pipes power to appoint an independent appraiser pursuant to Section
to fall on the floor of the NAIA-IPT III. The Government likewise 5 (g), Rule 135 of the Rules of Court. The RTC has wide
informed the Court that the MIAA requested the Association of discretion on how it shall carry its mandate under RA 8974 and
Structural Engineers of the Philippines (ASEP)to investigate the Rule67 of the Rules of Court.68
cause of the collapse.57 In its Final Report dated June2006, the
ASEP identified the following factors that contributed to the In an order dated January 7, 2008, the RTC sustained the
collapse: appointment of DG Jones and Partners. The RTC ruled that its
power to appoint the members of the BOC under Section 5,
a. Incomplete design coordination as shown by the Rule 67 of the Rules of Court includes the power to appoint an
absence of detailed shop drawings during the independent appraiser.69
construction, an absence described as "unusual" for a
BOT project of this size The Government directly challenged before the Court the May
3, May 18, and January 7, 2008 orders in a petition for certiorari
b. Wrong choice of ceiling and wall components and with prayer for the issuance of a temporary restraining order
fixing materials, e.g., use of rivets instead of clips, and/or a writ of preliminary injunction. The case was docketed
screws or wire; use of furring channels instead of as G.R. No. 181892.70
stronger C channels; use of wall angles thinner than
required; and On January 9, 2008, the Court issued a temporary restraining
order against the implementation of the May 3 and 18, 2007
c. Poor workmanship, e.g., uneven distribution and Orders as well as the January 7, 2008 Order.71
improper attachment of rivets, lack of ceiling
supports in the presence of mechanical fixtures.58 2. The BOC's Expenses

The ASEP concluded that the likely cause of the collapse was On June 15, 2006, the BOC filed a request for the release of a
the "syncretic effect of all these factors working over time since mobilization fund of ₱1,600,000.00 to support the discharge of
the construction of the ceiling."59 its functions.72 The RTC approved the request and directed the
Government and PIATCO to equally share the BOC's
Upon the BOC's request,60 on May 5, 2006, the RTC ordered the expenses.73 The Government and PIATCO complied with this
engagement of the services of an internationally accepted order and tendered the sum of ₱1,600,000.00 to the BOC.74
independent appraiser who shall conduct the valuation of the
NAIA-IPT III.61 On November 24, 2009, the BOC requested additional funds in
the amount of ₱5,250,000.00.75 On December 7, 2010, the RTC
On May 23, 2006, the Government manifested that it engaged directed the Government and PIATCO to equally defray the
the services of: (a) TCGI Engineer to determine the structural BOC's expenses.76 The Government contested this order and
ProvRem Rule 67 Fulltext Page 28 of 119
insisted that Takenaka and Asahikosan should likewise shoulder
Deductions $USD
the BOC's expenses as intervenors in the case.77

In an order dated March 11, 2011,the RTC ordered Takenaka Total CCVs $USD $186,262,649 $149,448,037
and Asahikosan to share in the BOC's expenses. The RTC thus
ordered each party to pay ₱1,750,000.00. PIATCO complied with
this order and paid the amount of ₱1,750,000.00 to the BOC.78
▪ $300,206,693.00 as base current cost
Takenaka and Asahikosan sought the partial reconsideration of valuation(CCV). Based on the Gleeds report, the
this order.1âwphi1 They argued that they should not be made construction cost of the NAIA-IPT III as of December
to pay the BOC's expenses since "their prayer to defer the 2002 was $300,206,693.00, consisting of the cost of
release of a portion of the just compensation pending the constructing the terminal building, aprons, car park,
conclusion of the enforcement proceedings was addressed to elevated roadways, and other related items.
the RTC [,] and not to the BOC."79
Gleeds appraised the NAIA-IPT III by "multiplying the
F. The Parties and the BOC's Appraisal of the NAIA-IPT III structure's dimensions (i.e., quantities) by a price (i.e.,
rate) for constructing the works at a designated time
and specific location, adding the cost of works in, on,
After the Court issued the January 9, 2008 temporary restraining
and around the structure, and then accounting for
order, the parties and the BOC conducted a preliminary conference on
inferior and nonperforming works, and rectification of
April 22, 2010, to adopt an alternative course of action to avoid further
those works."84
delay in the determination of just compensation.80

▪ Gleeds arrived at the CCV by considering the rates


The Government manifested that it was ready to present its own valuation
and prices for the third quarter of 2001, which
of the NAIA-IPT III and other supporting evidence. PIATCO, Takenaka, and
represented the midpoint of the construction period
Asahikosan did not object to this manifestation.81
from June 2000 (the commencement of construction)
to December2002 (the suspension of construction). It
On August 5, 2010, the RTC ordered the parties to submit their appraisal claimed that calculating the cost of construction
reports of NAIA-IPT III with supporting documents and affidavits.82 The based on its midpoint was a recognized standard
Government appraised the NAIA-IPT III at $149,448,037.00while PIATCO practice in the construction industry. The base CCV
concluded that its replacement cost was $905,867,549.47. On the other excluded the following items:
hand, Takenaka and Asahikosan claimed that the NAIA-IPT III's
construction cost amounted to $360,969,790.82.
1. Failed structural elements of the
Terminal, as identified in the Arup Seismic
1. The Government's Appraisal Evaluation Report and Gravity Loading and
Element Capacity Assessment;
Based on the Gleeds Report dated November 15, 2010, the
Government computed the valuation of the NAIA-IPT III as 2. The inferior quality of material used and
follows:83 works, including floor tiling, plasterboard
wall finishes and ceilings, internal and
external metal paneling;
December 2002 December 2004
CCV CCV
3. Constructed areas that are unnecessary
to the functioning of an international aiport
Base valuation $USD @3Q01 $300,206,693 $300,206,693
terminal and therefore of no benefit to the
Deterioration $USD @2Q09 $0 $1,738,318 Republic. These areas identified in the Arup
Site Observation Report include areas
Depreciation $USD 3Q01 $0 $35,076,295 where the requirements stated in the Bid
Documents have been grossly
overprovided. They also include the
Total Base CCVs $USD $300,206,693 $263,392,081 multilevel retail mall that, with its own
internal circulation, is functionally separate
from the Terminal and accessible only
Rectification for Contract through the multi-storey car park (20,465
Compliance m2), and excess retail concession space
$USD@2Q09 (1,727 m2);

Not compliant with bid -$30,670,894 -$30,670,894 4. The cost of seismic and gravity load
documents structural retrofits for the failed elements in
the terminal buildings and multi-storey car
Inferior quality -$7,702,640 -$7,702,640 park structures, as those retrofits are
described in Arup's Drawings listed in
Additional areas to be built -$75,570,510 -$75,570,510 Appendix 'B' Drawing List 2 and other
(63,490m2) rectification works required to bring the
terminal to compliance with applicable
building and airport codes (as indicated in
Total Contract Compliance -$113,944,044 -$113,944,044

ProvRem Rule 67 Fulltext Page 29 of 119


the Appendices of Arup's Site Observation
II. Attendant Costs
Report);
Engineering and Architecture 19,372,539 1.0971 21,253,613
5. The cost of completing the items listed
in the JAC project status summary report of Quality Assurance 6,923,720 1.0971 7,596,013
28 February 2003;85 and
Construction Supervision 4,302,227 1.0971 4,719,973

6. The cost of seismic and gravity load Construction Insurance 4,329,272 1.0971 4,749,644
structural retrofits for the failed elements in
the elevated roadway structures as those Site Development 8,358,169 1.0971 9,169,747
retrofits were described in Arup's Drawings
Other Costs 308,985 1.0971 338,987
listed in Appendix 'B' Drawing List 3, Arup
Review on 'TCGI Report of Civil Design
Attendant Costs exclusive of 43,594,911 1.0971 47,827,977
Review and Evaluation' - Elevated
Financing Costs
Roadway, dated March 2009, and other
rectification works required to bring the Financing Costs 26,602,890 26,602,890
elevated roadways to compliance with
applicable building and airport codes (as Total Attendant Costs 70,197,802 74,430,868
indicated in the Appendices of Arup's Site
Observation Report).86 TOTAL 431,167,593 470,450,825

▪ $263,392,081 as total base CCV as of December In US Dollars


2004. The Government asserted that the NAIA-IPT III
suffered from depreciation and deterioration in the
sum of US$36,814,612.00 from December 2002 until REPLACEMENT COST 470,450,825
December2004. The base value CCV at the time of
expropriation should be US$263,392,081.00 after Add:
deducting depreciation and deterioration.
Interest from 21 Dec 2004 to11 Sept 2006 104,014,531

▪ $113,944,044 as total contract compliance Interest from 12 Sept 2006 to 31 Dec 2010 331,402,193
deductions. The Government further deducted items
which were non-compliant with bid documents, Total Interests 435,416,724
including, among others:
Total Replacement Value 905,867,550

a. FIDS monitors not flat screen Less: Payment on 11 Sept 2006 59,438,604

b. Moving walkways under provision Amount Still Due 846,428,946

c. Sun shading to external glazing d. Lack Computation of Interest in US Dollars


of 400hz PC air to loading bridges

Period Interest No. of Days Amount in


e. Completion of testing, commissioning,
Rates USD
and operation of the facility
Replacement (a) 470,450,825
f. Provision of as-built documentation Cost

Interests
The Government likewise deducted the replacement
cost of inferior quality items and additional areas that From December 21 12% 11 1,724,986
the Government had to build to finish the NAIA-IPT takeover to December
III project.87 of NAIA T3 31, 2004
on
2. PIATCO's Appraisal 21 Dec 2004

January 1 to 12% 365 57,448,057


PIATCO claimed that the total replacement value of the
December 31,
NAIAIPT III as of December 31, 2010 amounted to
2005
$905,867,550.00.
January 1 to 12% 254 44,881,488
September 11,
Actual Inflation Base
2006
Costs @ Rate Valuation
2002 @ 2004 Total Interest from 21 December 2004 to (1) 104,014,531
11 September 2006
I. Materials, Equipment and Labor 360,969,791 1.0971 396,019,958
Engineering & Procurement TOTAL AMOUNT DUE AS OF 11 (a) + (1) 574,465,356
SEPTEMBER 2006

ProvRem Rule 67 Fulltext Page 30 of 119


range of 8.5% to 11.5% of the Construction Contract
Less: Amount Paid on 11 September 2006 (Php 59,438,604
cost.90 Financing costs are also "attendant costs"
3,002,125,000/50.508)
because loans and guarantees were obtained to
NET AMOUNT STILL DUE AS OF 11 (b) 515,026,752 finance the NAIA-IPT III project.91
SEPTEMBER 2006
▪ Conversion to 2004 values. Since the NAIA-IPT III
Additional September 12 to 12% 112 19,227,665 shall be appraised at the time of taking, the total
Interests December 31, construction cost shall be converted to December 21,
2006 2004 values by considering the inflation rate of
1.0971.92 Inflation was computed using the Consumer
January 1 to 12% 365 65,000,954
Price Index (CPI) from 2002 to 2005. The reckoning
December 31,
period was from November 29, 2002, when Takenaka
2007
and Asahikosan suspended their works in the NAIA-
January 1 to 12% 366 73,109,155 IPT III project, until December 21, 2004, when the
December 31, Government filed a complaint for expropriation.93
2008
▪ Interests on replacement cost. The twelve (12%)
January 1 to 12% 366 82,028,472 interest rate shall be added to the replacement cost
December 31, pursuant to the principles of law and equity.94 In
2009 Benguet Consolidated v. Republic of the
Philippines,95the Court ruled that the property owner
January 1 to 12% 366 92,035,946
is entitled to the payment of interest where the
December 31,
payment of compensation does not accompany the
2010
taking of property for public use but is postponed to
a later date. The interest shall compensate for the
Additional Interests up to 31 December (2) 331,402,193
Government's delay in the payment of just
2010
compensation.96
AMOUNT STILL DUE AS REPLACEMENT (b) + (2) 846,428,946
VALUE 3. Takenaka and Asahikosan's Appraisal

Replacement 470,450,825
Cost On the other hand, Takenaka and Asahikosan,
computed the NAIAIPT III's replacement cost as
Total Interests 435,416,724 follows:
(1+2)

TOTAL 905,867,550
AMOUNT OF
Total payments of PIATCO
REPLACEMENT
Add: Awards by the London Court
VALUE
Award by the Makati Court
Total Construction Cost
▪ $360,969,791 as base value. PIATCO adopted
Takenaka and Asahikosan's actual construction cost ▪ $360,969,790.82 as total construction cost. Takenaka
of $360,969,791 which is supported by As-Built and Asahikosan claimed that the initial contract price
Drawings and Bills of Quantities. PIATCO stated that for the construction of the NAIA-IPT III was
the Japanese Airport Consultants (JAC), the quality $323,753,238.11.
assurance inspector for the NAIA-IPT III project,
validated the works of Takenaka and Asahikosan.
PIATCO alleged that the Government and PIATCO Thereafter, changes were made in the course of the
entered into a Quality Assurance Agreement with construction that increased its construction contract
JAC.88 price. Pursuant to the Onshore Construction and
Offshore Procurement Contracts, PIATCO paid
Takenaka and Asahikosan the amounts of
▪ Attendant costs. Under RA 6957 IRR, the $231,312,441.28 and ₱1,796,102,030.84 (a total of
replacement cost includes the "overhead and all $275,119,807.88).
other attendant costs associated with the acquisition
and installation in place of the affected
After PIATCO defaulted on its payments, Takenaka
improvements/structures." The items under the
attendant costs correspond to these "overhead and and Asahikosan instituted Claim Nos. HT-04-248 and
other attendant costs" which are necessary to HT-05-269 in England. The London court ruled in
construct an airport project.89 their favor and awarded them the amounts of
$81,277,502.50, ₱116,825,365.34 and £65,000.00 or a
total of $ 84,035,974.44. Thereafter, they filed an
It is necessary to hire quality assurance surveyors to action to enforce Claim Nos. HT-04-248 and HT-05-
check and monitor the work of Takenaka. PIATCO 269 before the RTC of Makati which awarded them
hired Pacific Consultants, Inc. as construction the sum of $1,814,008.50.97
supervisor in the NAIA-IPT III project. PIATCO claimed
that the planning and design consultancy fees are
4. The BOC's Appraisal
even below the international norms which are in the

ProvRem Rule 67 Fulltext Page 31 of 119


On March 31, 2011, the BOC submitted its Final the time of taking of the property until actual
Report recommending the payment of just payment of just compensation. The delay in the
compensation of $376,149,742.56 with interest at the payment of just compensation is equivalent to a
rate of 12% per annum computed from the time of forbearance of money.
the taking of the property until the amount is fully
paid, plus commissioner's fees equivalent to 1% of ▪ The commissioner's fees shall be equivalent to 1%
the amount fixed as part of the costs of the of just compensation. According to the BOC, the
proceedings. commissioner's fees shall be equivalent to 1% of just
compensation, similar to the arbitrators' fees.
In arriving at the replacement cost of the NAIA-IPT III, Commissioners and arbitrators perform similar
the BOC proposed the following computation: responsibilities since both act as independent and
uninterested third parties in resolving difficult factual
issues.100
Formula In US dollars

Amount paid by PIATCO to Takenaka and Asahikosan 275,119,807.88 II. The RTC Rulings in Civil Case No. 04-0876
Add:
Award in Claim No. HT-04-248 Relating to the 14,827,207.0098 A. The Main Decision
Construction Cost of NAIA-IPT III
Award in Claim No. HT-05-269 Relating to the
In a decision dated May 23, 2011, the RTC directed the Government,
Construction Cost of NAIA-IPT III 52,007,296.5499
Takenaka, and Asahikosan to pay the commissioners' fees in the amount
Construction Cost of NAIA-IPT III 341,954,311.42
of ₱1,750,000.00 each; and ordered the Government to pay PIATCO just
Add:
compensation in the amount of $116,348,641.10. In determining the
Attendant Cost (10% of the Construction Cost) 34,195,431.14
amount of just compensation, the RTC adopted the following
Replacement Cost of NAIA-IPT III 376,149,742.56 computation:

▪ $341,954,311.42. In computing the construction Formula


cost, all actual, relevant and attendant costs for the
construction of the NAIA-IPT III, including its market Just compensation as determined by the Republic
price, shall be considered. The BOC divided the Add: Attendant cost (10% of $263,992,081.00, CCV as of
construction cost into: (a) the amount paid by December 21, 2004)
PIATCO to Takenaka and Asahikosan for the Just Compensation
construction of NAIA-IPT III; and (b) the awards by Less: Proffered value paid to PIATCO
the London Court in Claim Nos. HT-04-248 and HT- Net Just Compensation
05-269 relating solely to construction cost, excluding
interest, attorney's fees, and costs of the suit. The
BOC relied on Takenaka and Asahikosan's ▪ $149,448,037.00. The RTC adopted the Government's
construction cost since these corporations computed just compensation of $149,448,037.00, and ruled that
shouldered the actual cost of constructing the NAIA- the Government should not pay for the portions of the NAIAIPT
IPT III. III that were defective. The RTC thus excluded the following
from the computation of the CCV:

▪ $34,195,431.14. According to the BOC, PIATCO


failed to substantiate its attendant costs. In pegging (a) failed structural elements in the NAIA-IPT III;
the attendant cost at 10% of the construction cost,
the BOC relied on the Scott Wilson Report, which (b) inferior quality of material works;
states that the accepted industry range for
architecture, civil and structural, electrical and (c) constructed areas that are unnecessary to the use
mechanical, quantity surveyor and project of an international airport terminal;
management cost is 8.5% to 11.5% of the
construction cost.
(d) cost of seismic and gravity load structural retrofits
for the failed elements;
▪ Depreciation shall not be deducted from the
construction cost. The BOC explained that the
(e) cost of completing the items listed in the JAC
inventory of materials comprising the NAIA-IPT III
project status summary report of February 28, 2003;
does not reflect its replacement cost. Rather, it is the
and
actual cost of replacing an existing structure with an
identical structure that is considered in the
replacement cost method. For this reason, (f) cost of seismic and gravity load structural retrofits
depreciation shall not be deducted from the for the failed elements in the elevated roadway
construction cost; otherwise, the NAIAIPT III would structures.
have been fully depreciated since the Government
estimated that the NAIA-IPT III's useful life was only The RTC rejected PIATCO, Takenaka, Asahikosan, and the BOC's
ten years. computation for lack of factual and legal basis. The court
criticized the BOC's computation of construction cost and
▪ The replacement cost shall earn interest at 12% per stated that the BOC erroneously relied on the amounts
annum from December 21, 2004, until full payment. allegedly paid by PIATCO to Takenaka and Asahikosan. The RTC
The BOC stated that legal interests shall accrue from pointed out that PIATCO failed to present proof that it had

ProvRem Rule 67 Fulltext Page 32 of 119


indeed paid Takenaka and Asahikosan the sum of 1. The Government and the Creation of an Escrow Account for
$275,119,807.88. The RTC further posited that the BOC did not the Payment of Just Compensation
take into account the actual cost of the NAIA-IPT III at the time
of taking which was in a state of collapse and deterioration. On July 8, 2011, the Government filed a Manifestation and
Motion106 with the RTC stating that it was ready and willing to
The RTC stated that just compensation is limited to the value of pay PIATCO, through an escrow account, the amount of
the improvement at the time of the filing of the expropriation $175,787,245.10less the proffered value of ₱3 billion.
complaint. The payment of just compensation does not include
the right to be compensated of the franchise to operate the The Government expressed its desire to exercise full ownership
airport, and the increased value of improvements due to rights over the NAIA-IPT III. However, it could not directly pay
inflation rate. PIATCO who had various creditors - Takenaka, Asahikosan, and
Fraport, among them. The Government asserted that just
▪ $26,339,208.10. Similar to the BOC, the RTC pegged the compensation should only be paid to claimants who are legally
attendant cost at 10% of the CCV at the time of the filing of the entitled to receive just compensation.
expropriation complaint. The RTC agreed with the BOC that the
computation of the attendant cost based on the 10% of the The Government thus asked the RTC's leave to deposit the just
CCV was an accepted industry practice. compensation due in an escrow account that shall be subject to
the following conditions:
▪ $59,438,604.00. After deducting the proffered value of
$59,438,604.00, the RTC fixed the net compensation at 8.1. The claimant(s) shall have been held to be
$116,348,641.10, without interest. The RTC stated that no entitled to receive the sum claimed from the "Just
interest shall accrue on the net just compensation since the Compensation (NAIA Terminal 3) Fund" in
Concession Agreement was nullified by the Court in Agan. accordance with Philippine law and regulation, by a
final, binding and executory order or award of the
The dispositive portion of the decision states: expropriation court;

IN THE LIGHT OF THE FOREGOING, Plaintiffs are hereby 8.2. The claimant(s) shall have been held to have
ordered to pay respondent PIATCO the amount of accepted or otherwise become subject to the
US$175,787,245.10 less the proffered value (₱3,002,125,000.00) jurisdiction of the expropriation court and other
actually paid to and received by defendant, as the just relevant courts of the Republic of the Philippines, by
compensation for the improvements of NAIA-IPT III. Moreover, reason of or in connection with the expropriation of
both plaintiff Republic and intervenors Takenaka and NAIA Terminal 3 by the ROP, directly or indirectly;
Asahikosan Corporations are directed to pay their
proportionate shares of the Commissioners' Fees in the amount 8.3. The claimant(s) shall have executed a valid and
of ₱1,750,000.00 each with dispatch. effective quitclaim in favor of the Republic of the
Philippines acknowledging that claimant(s) against
Finally, insofar as both intervenors Takenaka and Asahikosan the ROP or any agency or instrumentality or
Corporations are concerned, resolution of their claim before corporation of the ROP, by reason of, or in
this Court is held in abeyance owing to the pendency of the connection with, the expropriation of NAIA Terminal
outcome of the appeal on certiorari before the CA, and in any 3 by the ROP, directly or indirectly, in any capacity
of their claims, as contractors are solely as against defendant whatsoever;
PIATCO.
8.4. The claimant(s) has complied within good faith
SO ORDERED.101 any condition or undertaking required from
it/him/her by the expropriation court by reason of or
PIATCO, Takenaka, and Asahikosan immediately appealed the in connection with the expropriation of NAIA
RTC's decision before the CA while the Government opted to Terminal 3 by the ROP, directly or indirectly, in any
seek partial reconsideration of the attendant costs awarded to capacity whatsoever.107
PIATCO.102
The Government thus prayed:
PIATCO, Takenaka, and Asahikosan sought to nullify the RTC
decision for alleged violation of their right to due process. They 1. Pending determination of the entitled claimants, to
complained that they were only furnished copies of the BOC allow the Government to deposit just compensation
Final Report only after the promulgation of the May 23, 2011 less the proffered value in an escrow account with a
decision.103 They averred that the RTC violated Sections 7 and 8, reputable bank whose senior unsecured obligations
Rule 67 of the Rules of Court which provide that the clerk of are rated at least 'BBB' by Standard and Poor's
court shall serve copies of the commissioners' report on all Investors Service, Inc.or 'Baa2' by Moody's Service
interested parties, with notice that they be allowed ten days Investors Service, Inc. to be designated by the RTC;
within which to file objections to the findings of the report, if
they so desire.104 2. After depositing the amount in an escrow account,
to confirm the Government's right to fully exercise
The Government subsequently partially appealed the case to any and all acts of ownership over the NAIA-IPT III;
the CA after the RTC denied its motion for partial and
reconsideration.105
3. To order the release of just compensation, or of
B. The RTC's Interlocutory Order on the Validity of the Escrow Accounts any portion thereof from the escrow account to the
ProvRem Rule 67 Fulltext Page 33 of 119
entitled claimants provided that the entitled case for the sole purpose of determining the amount of just
claimants have fully complied with all the conditions compensation to be paid to PIATCO.
and requirements set forth under paragraphs 8.1 to
8.4 of the Manifestation and Motion.108 Moreover, the Government did not raise the alleged dispute in
the ownership of the NAIA-IPT III during the expropriation
PIATCO opposed the Manifestation and Motion and argued proceedings. The RTC stated that it could not take judicial
that the Government could not vary the terms of the May 23, notice of the allegation that PIATCO was indebted to various
2011 Decision as well as the Court's rulings in Agan and creditors, apart from Takenaka and Asahikosan, since these
Gingoyon commanding the Government to make a direct alleged creditors were not impleaded in the expropriation
payment of just compensation to PIATCO. It insisted that the complaint.
offer to pay through an escrow account is not equivalent to
direct payment. PIATCO further denied the Government's The RTC likewise observed that compliance with the
allegations that there were several claimants on the just Government's conditions under 8.1 and 8.3 for the release of
compensation.109 just compensation from the escrow account pending appeal
was legally impossible. For this reason, the payment through an
On the other hand, Takenaka and Asahikosan agreed with the escrow account was not the payment that would transfer the
Government that just compensation should only be paid to title of the NAIA-IPT III to the Government.
entitled claimants. They posited that the Court's directive in
Agan (with respect to the direct payment to PIATCO) was The RTC lastly ruled that the payment of just compensation
premised on the erroneous assumption that PIATCO was the through an escrow account shall be payment of just
builder of the NAIA-IPT III. Takenaka and Asahikosan insisted compensation within a reasonable time. Consequently, the
that they were the actual builders of the NAIA-IPT III. Government may exercise full rights of ownership over the
Nonetheless, they contended that the RTC had no jurisdiction NAIA-IPT III upon the creation of an escrow account.111
over the Manifestation and Motion because the parties already
filed their respective Notices of Appeal before the CA.110
The dispositive portion of this order provides:

2. The Omnibus Order dated October 11, 2011


IN THE LIGHT OF THE FOREGOING, plaintiffs'
Manifestation and Motion is GRANTED in part:
In an Omnibus Order dated October 11, 2011, the RTC granted
the Manifestation and Motion. The RTC ruled that it has
residual jurisdiction to adjudicate the Government's 1. Plaintiffs' prayer for the court to
Manifestation and Motion considering that the motion was filed determine who is/are legally entitled to
prior to the parties' filing of the Notice of Appeal. The RTC receive just compensation is DENIED for
lack of merit.
opined that the Manifestation and Motion was akin to a motion
for execution pending appeal. The Manifestation and Motion
showed the Government's intent to voluntarily comply with the 2. Plaintiffs' prayer that they be allowed to
May 23, 2011 decision which was pending appeal before the deposit the payment of just compensation
CA. Under Section 9,Rule 41 of the Rules of Court, the RTC has (less the proffered value) to an escrow
the residual power to issue orders for the protection and account is hereby GRANTED, provided that
preservation of the parties' rights, and to order the execution of only the following conditions may be
a decision pending appeal. Furthermore, Section 6, Rule 136 of imposed for the release of the money
the Rules of Court provides that courts have incidental power to deposited:
issue orders that are necessary to effectuate their judgments.
a. PIATCO must submit a
The RTC held that the creation of an escrow account conforms Warranty that the structures and
with the Court's rulings in Gingoyon that just compensation facilities of NAIA IPT III are free
shall be paid in accordance with law and equity. Since the from all liens and encumbrances;
Government had no legal obligation to create an escrow
account, it could impose conditions for the release of just b. PIATCO must submit an
compensation in the escrow account, including: (a) PIATCO's Undertaking that it is assuming
submission of a warranty that the NAIA-IPT III shall not be sole responsibility for any claims
burdened by liens and encumbrances and an undertaking that from third persons arising from
PIATCO shall be solely liable for any claims from third persons or relating to the design or
involving the NAIA-IPT III; and (b) PIATCO's execution of a Deed construction of any structure or
of Conveyance of the NAIA-IPT III in favor of the Government. facility of NAIA IPT III structures,
Equity dictated that the Government's payment of just if any; and
compensation should free the NAIA-IPTIII from liens and
encumbrances. The Deed of Conveyance should be without
c. PIATCO must submit a duly
prejudice to the appellate court's determination of just
executed Deed transferring the
compensation.
title of the NAIA IPT III structures
and facilities to the Republic of
Conversely, PIATCO had likewise no legal obligation to accept the Philippines, without however,
or reject the Government's offer of payment. prejudice to the amount which
will finally be awarded to PIATCO
The RTC clarified that PIATCO is the sole entity entitled to by the appellate court;
receive the payment from the Government. The RTC
pointed out that the Court has remanded the Gingoyon
ProvRem Rule 67 Fulltext Page 34 of 119
The Land Bank of the Philippines and the
Replacement Cost 300,206,693.00
Development Bank of the Philippines are
Less: Proffered value paid to PIATCO (59,438,604.00)
hereby jointly appointed [a]s the Escrow
Just Compensation as of September 11, 2006 240,768,035.00
Agents for the above purpose.
Add: Interest Due as of July 31, 2013 130,658,653.24
Just Compensation as of July 31, 2013 371,426,742.24
Upon payment of the plaintiffs of the said
just compensation in an escrow account,
this court recognizes the Republic of the The CA justified its computation as follows:
Philippines' right to exercise full rights of
ownership over the NAIA IPT III structures ▪ $300,206,693.00 as Replacement Cost. Under Section 10 of RA
and facilities in accordance [with] 2 (c). 8974 IRR, replacement cost shall consist of the construction and
attendant costs.
3. Plaintiffs' Formal Offer of Evidence and
defendant PIATCO's Comment and $300,206,693.00 as construction cost. The CA relied on the
Opposition thereto are NOTED. Gleeds Report which it characterized as more "particularized,
calculable and precise."116 The Government's construction cost
4. Defendant PIATCO's motion for did not vastly differ from the BOC and PIATCO's computed
reconsideration with plaintiffs' construction costs of $341,954,311.42 and $360,969,791.00,
comment/opposition of the order of this respectively. But the BOC and PIATCO's computed construction
court denying the motion for inhibition is costs were unreliable since they lacked detailed proof that the
hereby denied. quoted amounts were directly related to the construction of
NAIA-IPT III.
SO ORDERED.112
$0 as attendant cost. The CA stated that there was no need to
award additional attendant costs since these costs had already
The RTC subsequently denied PIATCO's as well as Takenaka and
been included in the Government's computations under the
Asahikosan's respective motions for partial reconsideration of
heading "General Requirements and Conditions." The inclusion
the above-quoted order,113 opening the way for PIATCO's
of attendant cost in the construction cost was justified since the
petition for certiorari with prayer for the issuance of a
attendant cost becomes part of the total construction cost once
temporary restraining order and/or a writ of preliminary
the construction of a project is completed. Based on the Bills of
injunction, filed with the CA.114This petition was docketed as
Quantities, the Government provided the following detailed list
CA-G.R. SP. No. 123221.
of attendant costs in the construction of the NAIA-IPT III:

III. The CA Rulings

A. CA-G.R. CV No. 98029 Attendant Cost In US Dollars

Design 6,439,680
In a decision dated August 7, 2013,115 the CA upheld the validity of the Staff and labour 10,491,139.54
RTC's May 23, 2011 decision. The CA ruled that the parties did not need Insurance 925,210.78
to be furnished the BOC Final Report since RA 8974 is silent on the PI Insurance 2,200,000.00
appointment of the BOC, as held in Gingoyon. Consequential Loss 800,000.00
Setting out 364,647.00
However, the CA modified the RTC rulings and arrived at its own formula Health and safety 403,224.00
of the NAIA-IPT III's replacement cost, to wit: Enviro Management 176,490.00
Design 2,631,100.00
Staff and labour 2,590,774.19
Construction Cost
Insurance 71,109.77
Add:Attendant Cost
= Replacement Cost total 25,293,376.28117
Add: Equity
Just Compensation
The CA likewise observed that PIATCO's summarized
Substituting: computation of attendant costs was self-serving and
unsubstantiated by relevant evidence. On the other hand, the
BOC and the RTC's computation of attendant costs at 10% of
Replacement Cost = $300,206,693.00 + 0 (because the construction cost lacked factual and legal support. Pegging
attendant cost already imputed in attendant costs at 10% of the construction cost was only
construction cost) relevant during the pre-construction stage since the costs of
the construction at that time could only be estimated. This
= $300,206,693.00 + 6% interest from estimate carried no relevance at the post-construction stage
December 21, 2004 to September 11, since the total construction costs, including the attendant costs,
2006 less $59,438,604.00 + 6% could already be determined.
interest from September 12, 2006
until finality of judgment ▪ Depreciation, costs for noncompliance with contract
specifications, and unnecessary areas of NAIA-IPT III shall not
be deducted from the replacement cost. The CA reversed the
In US dollars RTC's finding that the NAIA-IPT III suffered from massive

ProvRem Rule 67 Fulltext Page 35 of 119


structural defect. The CA opined that the collapse of the portion The dispositive portion of the CA decision provides:
of the NAIA-IPT III merely relates to "finishing" rather than to
"structural" defects. In construction lingo, "finishing" pertains to WHEREFORE, the decision appealed from is
aesthetics, convenience, and functionality of a built structure MODIFIED. Just compensation is fixed at
while "structural" refers to the very integrity and stability of the US$300,206,639.00 less US $59,438,604.00 paid in
built structure. The CA disagreed with the RTC's conclusion that September 2006 or the net sum of
depreciation, costs for non-compliance with contract US$240,768,035.00 with legal interest at 6%
specifications, and unnecessary areas of the NAIA-IPTIII, shall be computed as above. The Republic is thus ordered to
excluded from the computation of construction cost. pay PIATCO just compensation as herein determined
Depreciation should not be deducted since it merely measures and which sum has reached the total of US
the book value of the property or the extent of use of the $371,426,688.24 as of 31 July 2014.
property. Depreciation is inconsistent with the replacement cost
method since the replacement cost merely measures the cost of
replacing the structure at current market price at the time of Upon finality of judgment, interest on the sum due by
taking. then shall be at 12% until fully paid.

Furthermore, the market price of a building increases over time; IT IS SO ORDERED.118


thus, if the construction cost of NAIA-IPT III in 2002 was
$300,206,693.00, its replacement cost in 2004 should be equal On August 22, 2013, the CA amended its decision in view of the
to or higher than $300,206,693.00. BSP's recent issuance, BSP Circular No. 799, series of 2013,
which took effect on July 1, 2013. BSP Circular No. 799 lowered
▪ Interest. The CA further held that interest shall be added to the legal interest rate on loan or forbearance of money, goods
just compensation as of September 11, 2006. Citing Gingoyon, or credit to 6% per annum.119 The CA amended decision
the CA explained that law and equity dictated that the provides:
Government shall be liable for legal interests as a result of the
delay in the payment of just compensation to PIATCO. Since WHEREFORE, the decision appealed from is
there was no stipulation on interests, the CA fixed the interest MODIFIED. Just compensation is fixed at US
rate at 6%. $300,206,639.00 less US $ 59,438,604.00 paid in
September 2006 or the net sum of
Upon finality of the judgment, the interest shall be 6% until fully US$240,768,035.00with legal interest at 6% computed
paid. As of July 31, 2013, the CA computed the interest as as above. The Republic is thus ordered to pay PIATCO
follows: just compensation as herein determined and which
sum has reached the total of $371,426,688.24 as of 31
July 2013.
In US Dollars
Upon finality of judgment, interest on the sum due by
Interest from December 21, 2004 18,012,401.58
then shall be at 6% per annum until fully paid
to December 21, 2005
pursuant to BSP Circular No. 799, series of 2013
$300,206,693*6%
which took effect on 01 July 2013, and which
effectively modified the interest rate rulings in
Interest from December 22, 2005 13,225,544.17
Eastern Shipping Lines, Inc. v. Court of
to September 11, 2006
Appeals.1awp++i1 Eastern Shipping was the basis of
$300,206,693*6%*268 days/365
the Court's earlier imposition of a 12% interest from
days
finality of judgment.
Interest from September 12, 2006 86,676,492.60
to September 12, 2012 IT IS SO ORDERED.120 [Emphasis supplied]
$240,768,035*6%*6 years

Interest from September 13, 2012 12,744,214.89 The CA likewise denied the Government's, PIATCO's,
Takenaka's, and Asahikosan's motions for partial
to July 31, 2013
reconsideration in a resolution dated October 29, 2013.121
$240,768,035*6%*322 days/365
days
The CA's denial of their motions cleared the way for the
Total Interest as of July 31, 130,658,653.24 elevation of CA-G.R. CV No. 98029 to this Court through a
2013 petition for review on certiorari. The Government, PIATCO, and
Takenaka and Asahikosan's consolidated petitions are docketed
as G.R. Nos. 209917, 209731, and 209696, respectively.
The CA further ordered Takenaka and Asahikosan to share in
the expenses of the BOC. Since Takenaka and Asahikosan's
inputs on the construction costs of the NAIA-IPT III were heard B. CA-G.R. SP No. 123221
by the RTC, they should share in the expenses of the BOC.
In a decision dated October 18, 2014,the CA reversed the Omnibus Order
The CA likewise denied Takenaka and Asahikosan's prayer to dated October 11, 2011, for having been issued with grave abuse of
set aside in an escrow account a portion ofthe just discretion. The dispositive portion of the decision states:
compensation corresponding to the amounts owed them by
PIATCO. RA 8974 expressly provides that the Government shall WHEREFORE, in view of the foregoing, the instant Petition is Hereby
directly pay the property owner upon the filing of the complaint GRANTED. Parenthetically, the Omnibus Order dated 11 October 2011
as a prerequisite to the issuance of a writ of possession. and Order dated 5 December 2011 of the Pasay City RTC, Branch 117, in

ProvRem Rule 67 Fulltext Page 36 of 119


Civil Case No. 04-0876-CFM for Expropriation, are hereby NULLIFIED and consolidated with the four(4) cases above and shall thus be separately
SET ASIDE for having been issued with grave abuse of discretion ruled upon by the Court.
amounting to lack or excess of jurisdiction.
V. The Parties' Positions
SO ORDERED.122
A. The Government's Position (G.R. Nos. 209917, 209731, and
IV. The Action to Enforce the London Awards, Civil Case No. 06-171 209696)

On February 27, 2006, Takenaka and Asahikosan filed an action to enforce G.R. No. 209917
the London awards in Claim Nos. HT-04-248 and HT-05-269 before the
RTC of Makati, Branch143. The case was docketed as Civil Case No. 06- In G.R. No. 209917, the Government asks the Court to partially reverse the
171.123 CA rulings and to deduct from the replacement cost of
US$300,206,693.00the following items: (a) depreciation in the amount of
In a decision dated September 6, 2010, the RTC recognized the validity of US$36,814,612.00; and (b) PIATCO's non-compliance with contract
the London awards in Claim Nos. HT-04-248 and HT-05-269 and declared specifications in the amount of US$113,944,044.00. The Government also
these awards as enforceable in the Philippine jurisdiction. The RTC thus refutes the CA's imposition of a legal interest on just compensation.
ordered PIATCO to pay Takenaka and Asahikosan the sum of $85.7
million.124 The Government asserts that the CA did not consider equity in computing
the replacement cost of the NAIA-IPT III. Contrary to the Court's
PIATCO appealed the case to the CA125 which affirmed the RTC rulings in a pronouncement in Gingoyon, the CA computed just compensation based
decision dated March 13, 2012.126 The CA likewise denied PIATCO's solely on RA 8974 and its IRR. The CCV of $300,206,639.00 only reflects
motion for reconsideration in a resolution dated May 31, 2012.127 the valuation of the NAIA-IPTIII as of November 2002 when PIATCO
stopped the construction of the terminal, and did not take into account
PIATCO responded by filing a petition for review on certiorari with this other factors that lowered its valuation as of December 2004.
Court assailing the CA's ruling. The case was docketed as G.R. No.
202166and is still pending before the Court separately from the present The Government posits that there are two standards in measuring the
petitions. replacement cost. The implementing rules of RA 8974 failed to provide a
complete formula to arrive at the replacement cost of an expropriated
To summarize, the cases pending before the Court are the consolidated property.
cases: G.R. Nos. 209917, 209696, 209731,and 181892, and G.R. No. 202166
as a separate case. The first and common standard is the depreciated replacement cost
method which measures the cost of replacing an asset at current prices
G.R. No. 209917 is the Government's petition for review on Certiorari128 to but in its actual condition, i.e., adjusted for age, wear and tear. The
partially reverse the CA's August 22, 2013 Amended Decision129 and its Chartered Institute of Public Finance and Accounting defines depreciated
October 29, 2013 Resolution130 in CA-G.R. CV No. 98029. replacement cost as "a method of valuation which provides the current
cost of replacing an asset with its modern equivalent asset less
deductions for all physical deterioration and all relevant forms of
G.R. No. 209696 is a petition for review on certiorari filed by Takenaka and obsolescence and optimization" and as "the replacement value of
Asahikosan to partially reverse the CA's August 22, 2013 Amended property minus physical depreciation and obsolescence; insurance
Decision and its October 29, 2013 Resolution in CA-G.R. CV No. 98029.131
adjusters estimate the actual cash value of property based on its
depreciated replacement cost."138
G.R. No. 209731 is PIATCO's petition for review on certiorari to reverse the
CA's August 22, 2013 Amended Decision, and October 29, 2013 In other words, depreciated replacement cost adjusts the cost of replacing
Resolution in CA-G.R. CV No. 98029.132 G.R. Nos. 209917, 209696 & the actual asset in accordance with the asset's age in order to take into
209731 originally arose from the Government's complaint for account the lower economic utility of an asset that is not brand new. As
expropriation of the NAIA-IPT III filed with the RTC of Pasay, Branch117 in an asset ages, higher economic cost is required to maintain that asset to
Civil Case No. 04-0876. The main issue before the Court in these petitions the level of utility of a brand new one.
is the valuation of the just compensation due for the Government's
expropriation of the NAIA-IPT III.
The second and less common standard is the new replacement cost
method which measures the cost of replacing an asset at current prices
G.R. No. 181892 is the Government's petition for certiorari with prayer for with no adjustment for age, wear, and tear. It refers to "the cost to replace
the issuance of a temporary restraining order,133 assailing the May 3, 2007, damaged property with like property of the same functional utility
May 18, 2008;and January 7, 2008 orders of the RTC of Pasay City, Branch without regard to depreciation (physical wear and tear) and
117 in Civil Case No. 04-0876.134 obsolescence."139

This petition likewise arose from the Government's complaint for The Government asks the Court to adopt the depreciated replacement
expropriation of the NAIA-IPT III. The main issue in this petition is the cost method where depreciation is deducted from the replacement cost.
propriety of the appointment of DG Jones and Partners as an The Government asserts that it is an internationally accepted practice to
independent appraiser of the NAIA-IPT III.1âwphi1
consider depreciation and other forms of obsolescence and optimization
in measuring the replacement cost of an asset.
G.R. No. 202166 is PIATCO's petition for review on certiorari135 to assail
the CA's March 13, 2012 decision136 and May 31, 2012 Resolution137 in CA- The Government argues that the new replacement cost method usually
G.R. CV No. 96502. The petition arose from Takenaka and Asahikosan's applies in cases where the property must be rebuilt. For example, an
action to enforce the London awards before the RTC of Makati, Branch insurance policy for a house would usually use the new replacement cost
143 in Civil Case No. 06-171. As previously mentioned, this case was not method because a house, which was destroyed by fire or other natural
disaster, must be rebuilt. On the other hand, an insurance policy for an
ProvRem Rule 67 Fulltext Page 37 of 119
automobile would use the depreciated replacement cost because it Section 3.3.37. As far as the building structure is concerned the
presupposes that a new automobile must be purchased to replace the old outstanding issues are the Taking Over Inspection Defects List,
automobile that suffered from wear and tear. outstanding Quality Observation Report issues and the Non-Compliance
Schedule x x x.142
The Government disputes the CA's opinion that the replacement cost
cannot be lower than the actual construction because market prices tend (c) The ASEP made the following observation in its
to move upward over time. The Government contends that the June 23, 2006 Report:
replacement cost may be lower than the construction cost if the price of
the materials such as steel, cement, and copper used during the ● Results of material tests carried out
construction stage decreases after the construction of the improvement. identified that the materials used were
Moreover, labor productivity and technological advancements affect the adequate and meet or exceed the ER
replacement cost since these counterbalance inflation. The depreciated specification. However, the thickness of the
replacement cost method is utilized "in setting user rates for public wall angle used (0.4 mm) does not meet
utilities precisely because this standard of value will tend to result in lower the minimum plate thickness for metals to
prices over time, not higher prices."140 be fastened by power-actuated anchors,
which requires a minimum of 0.6 mm (Hilti
The Government likewise disagrees with the CA that the depreciation Catalogue). ASEP recommended further
adjustment "would irrationally result in[a] book value which continues to tests.
be lower and lower over time." Since an asset must be maintained, the
cost of performing maintenance and repairs increases the asset's ● ASEP considered that the quality of
replacement cost. Consequently, repairs and maintenance cost counter- workmanship of the installation is not
balance depreciation. The recognition that an asset depreciates impliedly considered to be within minimum
acknowledges that the owner will spend more costs in maintaining the acceptable practice.
asset's utility than on a brand new asset.

● Structural design of the ceiling system


The Government agrees with the CA that depreciation is a cost allocation provided by Takenaka and independently
method and not a valuation method. However, the Government stresses assessed by ASEP concluded that the factor
that depreciation is also an economic cost; depreciation thus recognizes of safety of individual components is high.
that an asset suffers from wear and tear and would require higher cost to However, ASEP stated that the overall
maintain an asset's economic utility. Depreciation, as both economic and factor of safety of the total ceiling system is
accounting concepts, represents cost adjustments to reflect the fair value expected to be lower due to poor
of the asset due to age, wear, and tear. workmanship of the connections. The
positioning of the air-conditioning ducts,
The Government adds that the premise of the replacement cost method is fire protection system pipes, and other
"to measure the cost of replacing an asset at current prices with an asset systems above the ceiling has affected the
that has the same economic utility."141 Thus, the CA erred when it held standard spacing of the ceiling hangers
that the depreciation adjustment was inconsistent with the replacement and may have contributed to the uneven
cost method for the reason that this method factors in the current market distribution of loads to the various ceiling
price to measure the cost of replacing an asset. components, although without some of the
riveted joints failing, the ceiling hangers are
For instance, if the Government would expropriate a ten-year-old still adequate.
automobile, the new replacement cost method would compensate the
owner the amount of an asset that has more economic utility than the ● ASEP concluded that a combination of
ten-year-old automobile. On the other hand, if the Government would poor workmanship and wrong choice of
use the depreciated replacement cost method, it would only pay the value system in some areas particularly if
of an asset that has economic utility of a ten-year-old automobile. repeated access is required for inspection
and maintenance.143
The Government likewise insists that the CA erred in not deducting from
the replacement cost the construction costs for deviations from the (d) In its June 23, 2006 Report, the ASEP opined that
original contract, the inappropriate and defective structures, and the NAIA-IPT III may be partially opened provided
structures that were built in violation of international standards. It asserts that retrofitting works are done prior to its full
that the operation. Thus, the MIAA initiated the structural
remediation program of the NAIA-IPT III.144
NAIA-IPT III suffers from structural defects, as evidenced by the following:
(e) TCGI documented the "heaving of homogenous
(a) In the August 2007 Site Observation Report, Ove tiles and cracks underneath the slabs in the head
Arup found that the NAIA-IPT III suffered from house airline lounges (Level 3, Sector
structural defects. 4),"145 attributable to the 5.4 magnitude earthquake
that hit Lingayen, Pangasinan, on November 27,
2008. The earthquake was felt in Pasay with a 3.0
(b) In its Scott Wilson Report, PIATCO admitted that magnitude. PIATCO failed to refute TCGI's findings.146
the NAIAIPT III suffered from structural defects. The
relevant portions of the Report provide:
The Government insists that the operation of the NAIA-IPT III is not an
implied admission of the nonexistence of structural defects. The
Section 3.3.23. The cracking noted in the 2004 report at the upper storey Government clarifies that the structurally defective sectors of the NAIA-
beam/column interface appears to have worsened particularly in the outer IPT III remain unoccupied. Out of the 10 Sectors of the NAIA-IPT III, the
faces of a number of columns at high level adjacent to the internal ramps.
ProvRem Rule 67 Fulltext Page 38 of 119
MIAA fully occupies Sectors 1, 3, 5, and 6, and partially occupies Sectors 2 The Government asserts that Takenaka and Asahikosan should share in
and 4. The MIAA did not occupy Sections7, 8, 9, and the car park due to the BOC's expenses. Under Section 12, Rule 67 of the Rules of Court, the
structural issues. rival claimants should shoulder their costs in litigating their claim while
the property owner should shoulder the costs of the appeal if he appeals
That the Court declared the PIATCO contracts as null and void should not the case and the appellate court affirms the lower court's judgment.
impede the deductibility of construction costs for deviations from the
original contract, the inappropriate and defective structures, and To divide the BOC's expenses between the Government and PIATCO
structures that were built in violation of international standards. The would result in unjust enrichment. Under Section 1, Rule 142 of the Rules
Government emphasizes that when the Court nullified the PIATCO of Court, the court shall have the power to divide the costs of an action as
contracts, the NAIAIPT III was almost complete. Consequently, the may be equitable.
Government had every reason to expect that PIATCO would build the
NAIA-IPT III according to the agreed specifications. PIATCO, however, Furthermore, Takenaka and Asahikosan actively participated in and
acted in bad faith in not complying with the nullified PIATCO contracts. benefited from the proceedings before the BOC, which included the
PIATCO should not benefit from its violation of the concession London awards in the computation of just compensation. Takenaka and
agreements and the gross deviations from the original design of the Asahikosan likewise relied on the Final Report in their Appellant's Brief
NAIA-IPT III. dated October 3, 2012, and in their Reply Brief dated January 20, 2013.

The Government maintains that the imposition of legal interest on just The Government contends that Takenaka and Asahikosan's computations
compensation is erroneous. of actual construction cost of the NAIA-IPT III are conflicting.

First, the present expropriation case is sui generis. The Government was In their Manifestation dated December 9, 2010, Takenaka and Asahikosan
forced to expropriate the NAIA-IPT III due to PIATCO's violation of the stated that the actual construction cost amounted to $360,969,790.82.
Constitution and the law. To award legal interest to PIATCO is to condone However, in his report, Mr. Gary Taylor appraised the actual construction
its illegal acts. In Hulst v. PR Builders, Inc.,147 the Court held that the cost at US$323 million, "plus other costs that were incurred by various
illegality should not be rewarded. In Valderama v. Macalde,148 the Court parties during its conception and construction plus any property
deleted the payment of interest on the ground that a person should not appreciation."153 Mr. Gary Taylor further stated that the "true value of the
be allowed to profit from an illegal act. As between two parties, he who, NAIA-IPT III facility is nearer to US$408 million, given the fact that the
by his acts, caused the loss shall bear the same. He, who comes to court Republic's expert, Gleeds, failed to recognize or include any values for
for equity must do so with clean hands. [the] design and other consultants (10%) or property inflation based on
GRP schedules (15%)."154 However, Mr. Taylor did not explain how he
Second, PIATCO itself caused the delay of the expropriation proceedings arrived at the amount of $408 million.
before the RTC. PIATCO did not produce the vouchers, purchase orders,
and as-built documents which were in its possession despite the The Government adds that Takenaka and Asahikosan's actual construction
Government's filing of a Motion for Production and Inspection of cost of $360,969,790.82 is erroneous as the London and Makati awards
Documents dated May 25,2006, before the RTC.149 include interests, attorney's fees and costs of litigation. Furthermore,
Takenaka and Asahikosan's "as-built" drawings are not truly "as-built."
Third, in Eastern Shipping Lines v. CA,150 the Court pronounced that The drawings do not reflect the quality and exact detail of the built
unliquidated claims are not subject to legal interest, such as the present portions of the NAIA-IPT III.155
case.
G.R. No. 209731
Fourth, the law and jurisprudence on the imposition of interest does not
address the peculiar situation where the NAIA-IPT III is being expropriated The Government disputes PIATCO's claim that it was denied due process
as a direct result of the nullification of the PIATCO contracts. The when it was not furnished a copy of the Final Report. The Government
application of the law and jurisprudence on the imposition of interest points out that all the parties in the case were not given a copy of the
would not result in a fair and equitable judgment for the Government. The Final Report. Furthermore, PIATCO belatedly raised this issue; it was
Court must apply equity in the absence of a specific law applicable in a brought for the first time on appeal before this Court.
particular case or when the remedy afforded by the law would be
inadequate to address the injury suffered by a party.
The Government also emphasizes that PIATCO immediately filed a notice
of appeal a day after its receipt of the RTC decision. This is contrary to
The Government additionally complains that, since November 2002, "long PIATCO's claim that it wanted to secure a copy of the Final Report and
before the institution of the expropriation [complaint] in December 2004," subject it to clarificatory hearing.
Takenaka and Asahikosan prevented it from entering the NAIA-IPT III.151

Even assuming that the RTC erred in not furnishing the parties copies of
G.R. No. 209696 the Final Report, the lapse is merely an "innocuous" technicality that
should not nullify the RTC rulings.
The Government alleges that it is willing to pay just compensation to the
lawful claimant. However, just compensation should not be set aside in The Government claims that PIATCO failed to substantiate the attendant
favor of Takenaka and Asahikosan since their claim against PIATCO has costs. The documents attached to the Compliance dated December 14,
not yet been resolved with finality. 2010, are mostly summary of payments that PIATCO allegedly paid to the
consultants. However, PIATCO failed to prove that the alleged consultants
The Government disputes the applicability of Calvo v. Zandueta152 in the rendered actual service related to the construction of the NAIAIPT III.
present case. In that case, the Court allowed Juana Ordoñez to be Reyes Tacandong & Co. merely verified the mathematical accuracy of the
subrogated to Aquilino Calvo as defendant because Ordoñez obtained a schedules, including the computation of the inflation rate. Furthermore,
final judgment in her favor which entitled her to levy the land sought to the receipts that PIATCO submitted are not enough to cover its claimed
be expropriated. Furthermore, Ordoñez was not a party to the just compensation.156
expropriation case.
ProvRem Rule 67 Fulltext Page 39 of 119
G.R. No. 181892 documents and confirmed that the attendant costs amount to
$70,197,802.00 in its Report of Factual Findings dated December 14, 2010.
The Government disputes the RTC's appointment of an independent
appraiser of the NAIA-IPT III. It claims that Section 11 of RA 8974 IRR PIATCO asserts that its submission of the summary computation is
solely authorizes the implementing agency to engage the services of an justified under Section 3 (c), Rule 130 of the Rules of Court which allows
appraiser in the valuation of the expropriated property, while under the party to submit non-original copies if the original consist of numerous
Section 10 of RA 8974 IRR, it is the implementing agency that shall accounts or other documents that the court cannot examine without
determine the valuation of the improvements and/or structures on the great loss of time; the fact sought to be established from these, after all, is
land to be acquired using the replacement cost method. Pursuant to only the general result of the whole.
these provisions, the Government engaged the services of Gleeds, Ove
Arup and Gensler for purposes of appraising the NAIA-IPT III. PIATCO likewise argues that the total construction cost of
$431,167,593.00 - which is the sum of $360,969,791.00 and
The Government also argues that the appointment of an independent $70,197,802.00 - should be converted to 2004 values since the reckoning
appraiser would only duplicate the efforts of the existing appraisers. A period of just compensation is the date of taking or the date when the
court appointed appraiser and the existing appraisers would perform the complaint was filed, whichever is earlier. It posits that the amount of
same task of determining the just compensation for the NAIA-IPT III. Thus, $431,167,593.00 should thus be multiplied by 1.0971 - the prevailing
the RTC should have relied instead on the opinion of the internationally- inflation rate from November 29, 2002, to December 21, 2004 - for a total
renowned appraisers that the Government hired. amount of $470,450,825.00.

The Government likewise avers that the appointment of an independent The sum of $470,450,825.00 should further earn an interest rate of 12%
appraiser would only render the expropriation proceedings more costly. per annum beginning December 21,2004, until full payment. PIATCO
The Government would be forced to pay for the services of two maintains that the Government's deposit in an escrow account of a
appraisers, which is not the intention of RA 8974. The court-appointed portion of just compensation is not equivalent to payment; hence, interest
appraiser, too, would render the BOC's functions useless. Under Rule 67 of on the full amount of just compensation shall continue to apply.
the Rules of Court, it is the BOC that is required to receive evidence in the
determination of just compensation. Rule 67 of the Rules of Court does PIATCO contends that the CA's reduction of interest rate to 6% is
not require the appointment of an appraiser in eminent domain cases. erroneous because the Court, in numerous cases, has consistently
imposed 12% interest per annum on just compensation. PIATCO
Lastly, the Government complains that the RTC order requiring it to emphasizes that the imposition of interest on just compensation is not
submit a Certificate of Availability of Funds is vague because the RTC did based on contract, but on the owner's right to be immediately paid just
not specify the costs of the expropriation proceeding.157 compensation.

B. PIATCO's Position Finally, PIATCO prays that it be paid all income generated from the
operations of the NAIA-IPT III, from the date of taking up to the
G.R. No. 209731 present.158

PIATCO argues that the RTC rulings are null and void for the failure of the G.R. No. 209917
RTC clerk of court to furnish them copies of the BOC Final Report.
Sections 7 and 8, Rule 67 of the Rules of Court require that the parties be PIATCO asserts that the NAIA-IPTIII does not suffer from massive
given ten days within which to file their objections to the findings of the structural defects; that the Government's reliance on the Ove Arup Report
commissioners. is self-serving. The Government would not have expropriated the NAIA-
IPT III if it truly believed that the terminal suffered from massive structural
On its base value of $360,969,790.82, PIATCO insists that its valuation is defects. Furthermore, the MIAA's Project Management Office oversaw the
supported by a preponderance of evidence, particularly by the As-Built construction of the NAIA-IPT III to ensure that the terminal complied with
Drawings and the Bills of Quantities submitted by Takenaka and the agreed specifications under the relevant contracts between PIATCO
Asahikosan. The CA should not have relied on the Government's self- and the Government.
serving evidence in computing the base value of the NAIA-IPT III.
PIATCO contends that the depreciation, deterioration, and costs for non-
PIATCO also cites the CA's failure to include the attendant costs in the compliance with contract specifications should not be deducted from the
valuation of the NAIA-IPT III as an omission; the CA merely recognized the base value of the NAIA-IPT III. The base value of $300,206,693.00 should
construction cost valuation of the terminal pursuant to the Gleeds Report. be the least amount that the Government should pay. The measure of just
PIATCO alleges that it incurred attendant costs of $70,197,802.00 apart compensation is the fair and full equivalent for the loss sustained by the
from the construction cost of $360,969,790.82. It also emphasizes that its property owner, not the gain that would accrue to the condemnor.
consultancy fees are even below the international norms, as shown in the
Scott Wilson Report. It also claims that site preparation costs, legal costs PIATCO also asks this Court to strike from the record the affidavit of
in planning and constructing the development, and financing costs form Kaczmarek and other attachments in the Government's motion for partial
part of attendant costs since these costs are indispensable in completing reconsideration dated August 22, 2013. The Government should not be
a complex infrastructure project. allowed to present new evidence on the valuation of the NAIA-IPT III
before the CA. PIATCO points out that Kaczmarek was not cross-examined
PIATCO further alleges that its attendant costs are supported by the and his identity, knowledge, and credibility were not established before
attachments in its Compliance dated December 14, 2010, including the the trial court. The Government is estopped from introducing new
summary of payments for incurred attendant costs, official receipts, evidence before the appellate court since it objected to Takenaka and
statements of account, sales invoices, endorsements, insurance policies Asahikosan's introduction of new and additional evidence before the CA.
and other related documents, acknowledgement receipts, agreements,
invoices, and bonds. It claims that Reyes Tacandong & Co examined these

ProvRem Rule 67 Fulltext Page 40 of 119


As its last point, PIATCO posits that Section 10 of RA 8974 IRR does not participated in the nomination of an independent appraiser, and in fact,
allow the deduction of depreciation, deterioration, and costs for non- submitted its own nominees before the trial court.
compliance with contract specifications from the replacement cost.
Contrary to the Government's claim, the RTC did not arbitrarily appoint
Depreciation is merely an accounting concept that facilitates the standard DG Jones and Partners as an independent appraiser. The RTC in fact
of decreasing asset values in the books of accounts. It is not a method of required the nominees to submit their written proposals and invited them
valuation, but of cost allocation; an asset may still be valuable and yet to personally appear before the commissioners and the trial court prior to
appear fully depreciated in the financial statements. If at all, depreciation the issuance of the May 3, May 18,and January 7, 2008 orders.
was only relevant after the Government took possession and operated the
NAIA-IPT III.159 PIATCO argues that the Government should solely bear the expenses of
DG Jones and Partners. Section 12, Rule 67 of the Rules of Court provides
G.R. No. 209696 that all costs, except those of rival claimants litigating their claims, shall be
paid by the plaintiff, unless an appeal is taken by the owner of the
PIATCO agrees with the CA that just compensation must be directly paid property and the judgment is affirmed, in which event the costs of the
to it as the owner of the NAIA-IPTIII. It stresses that RA 8974 and its appeal shall be paid by the owner.161
implementing rules clearly provide that the owner of the expropriated
property shall receive the entire amount of just compensation. C. Takenaka and Asahikosan's Positions

PIATCO insists that it would be erroneous to create an escrow account in G.R. No. 209696 and G.R. No. 209731
favor of Takenaka and Asahikosan since the enforceability of Claim Nos.
HT-04-248 and HT-05-269 in Philippine jurisdiction has yet to be decided Takenaka and Asahikosan argue that law and equity dictate that just
by the Court in G.R. No. 202166. It points out that the main issue in G.R. compensation of at least $85,700,000.00 should be set aside to answer for
Nos. 209731, 209917, and 209696 is the amount of just compensation, their money claims against PIATCO.RA 8974 does not prohibit the
not the determination of Takenaka and Asahikosan's money claims creation of an escrow account pending the determination of the parties'
against PIATCO. Takenaka and Asahikosan's insistence to enforce their conflicting claims on the property and on the just compensation.
money claims against PIATCO in G.R. Nos. 209731, 209917 & 209696
constitutes forum shopping and is still premature.
Takenaka and Asahikosan allege that PIATCO is a shell corporation with
no significant assets, that has repeatedly defaulted on its monetary
PIATCO contends that Takenaka and Asahikosan have no standing to obligations. They emphasize that PIATCO did not pay Takenaka and
demand the creation of an escrow account in their favor. Section 9, Rule Asahikosan despite its receipt of the ₱3 billion proffered value from the
67 of the Rules of Court does not apply in this case because there are no Government. Takenaka and Asahikosan seek the creation of an escrow
conflicting claims regarding the ownership of the NAIA-IPT III. account to preserve their property rights against PIATCO. They posit that
Furthermore, the Court categorically stated in Gingoyon that PIATCO PIATCO may abscond after its receipt of the remaining just compensation
owns the NAIA-IPT III. PIATCO further argues that the rules on preliminary from the Government.
attachment do not apply to this case. Mere apprehension that PIATCO
would abscond from its financial liabilities is not a ground for the
attachment of the creditor's assets. Moreover, an artificial entity cannot PIATCO would profit by at least $155,000,000.00 if it solely receives the
abscond. PIATCO likewise denies that it refuses to pay Takenaka and entire amount of $431,167,593,000.00 (PIATCO's claimed just
Asahikosan's money claims. PIATCO posits that the eminent domain case compensation as of December 2002). PIATCO has judicially admitted that
it has paid Takenakaand Asahikosan only $275,000,000.00.
is not the proper venue for the adjudication of Takenaka and Asahikosan's
money claims.160
Takenaka and Asahikosan assert that the interest of justice will be served
G.R. No. 181892 if the Court allows the creation of an escrow account in their favor. They
point out that the lower courts already ruled on the enforceability of
Claim Nos. HT-04-248 and HT-05-269.Furthermore, the Court, in
PIATCO agrees with the RTC's appointment of DG Jones and Partners as Gingoyon, merely ordered the direct payment of just compensation to
an independent appraiser. The determination of just compensation is PIATCO in order to ensure that the builder of the NAIA-IPT III is
essentially a judicial function. The trial court's power to appoint compensated by the Government as a matter of justice and equity.
commissioners is broad enough to include the power to appoint an Takenaka and Asahikosan underscore that they are the real builders of the
appraiser who shall assist the commissioners in ascertaining the amount NAIA-IPT III as PIATCO's subcontractors.
of just compensation. The latter power is inherent in the court's task to
receive evidence and to arrive at a fair valuation of the expropriated
property. Takenaka and Asahikosan maintain that Section 9, Rule 67 of the Rules of
Court apply with respect to the adjudication of the parties' conflicting just
compensation claims. The Court did not declare in Gingoyon that Rule 67
Section 5 (g), Rule 135 of the Rules of Court allows the court to amend of the Rules of Court shall not apply to the payment of final just
and control its processes and orders so as to make them consistent with compensation. The Court merely applied RA 8974 in Gingoyon insofar as
law and justice. Furthermore, nothing in RA 8974 IRR that prohibits the the law prescribes direct payment as a prerequisite for the issuance of a
trial court from appointing an independent appraiser. writ of possession in eminent domain cases.

Section 6, Rule 67 of the Rules of Court provides that all parties may Under Section 9, Rule 67 of the Rules of Court, if there are conflicting
introduce evidence on the valuation of the property sought to be claims on the property, the court may order the just compensation to be
expropriated. The trial court is not bound by the report of the paid to the court for the benefit of the person adjudged in the same
commissioners and of the independent appraisers, much less of the proceeding to be entitled thereto. Takenaka and Asahikosan argue that
findings of the Government-hired appraisers. they are the lawful recipients of just compensation as the real builders of
the NAIA-IPT III and as the prevailing parties in Claim Nos. HT-04-248 and
PIATCO asserts that the Government is estopped from assailing the HT-05-269.
appointment of an independent appraiser. The Government voluntarily
ProvRem Rule 67 Fulltext Page 41 of 119
Even assuming that PIATCO is the owner of the NAIA-IPT III, the owner of gap between the NAIA-IPT III's bridge and building structure had a
the expropriated property is not solely entitled to the full amount of just potential for seismic pounding.
compensation.
Takenaka and Asahikosan posit that all the structural members of the
In Republic v. Mangotara,162 citing de Knecht v. CA,163 the Court held that NAIA-IPT III have a DCR of less than 1.0based on the 1992 National
just compensation is not due to the property owner alone; the term Structural Code of the Philippines (NSCP), the code applicable when the
"owner" likewise includes those who have lawful interest in the property NAIA-IPT III was designed and constructed. Takenaka and Asahikosan
such as a mortgagee, a lessee, and a vendee in possession under an opine that Ove Arup did not use the 1992 NSCP in the August 2007 Site
executory contract. In Philippine Veterans Bank v. Bases Conversion Observation Report. Ove Arup's finding that the NAIA-IPT III has a
Development Authority,164 the Court held that just compensation may be potential for seismic pounding is baseless. The terminal is designed and
deposited with the court when there are questions regarding the built to address the possibility of seismic pounding, taking into
ownership of the expropriated property. In Calvo v. Zandueta,165 the Court consideration that the NAIA-IPT III is built on Type I soil. Takenaka and
deferred the release of just compensation pending the determination of Asahikosan claim that Ove Arup's finding was not based on the AASHTO
the ownership of the expropriated property, despite the finality of the Standard Specification for Highway Bridges (16th Ed., 1996), the code
order allowing the release of just compensation. applicable at the time the NAIA-IPT III was designed and built. Takenaka
and Asahikosan likewise argue that Scott Wilson did not admit that the
Takenaka and Asahikosan refuse to share in the expenses of the BOC. NAIA-IPT III suffered from structural defects. They clarify that the
Under Section 12, Rule 67 of the Rules of Court, the costs of the statements in the Scott Wilson report "were merely intended to
expropriation suit shall be shouldered by the Government. The accommodate [the] changes that the client wished to effect."167 They also
Government would be unjustly enriched if other parties are required to point out that the Government stated in its petition (in G.R. No. 209917)
shoulder the costs of the suit. It would also be unfair to require Takenaka that "additional work is required to complete the terminal structure to
and Asahikosan to share in the expenses of the BOC since they were not make it compliant with the standards of Takenaka and Asahikosan."168
furnished copies of the BOC Final Report, in violation of their right to due
process.166 To lay the structural issue to rest, Takenaka and Asahikosan consulted
Meinhardst (Singapore) Pte Ltd., their Structural Design Consultant, to
G.R. No. 209917 rebut TCGI's findings. They also hired disinterested American experts in
the construction industry - Mr. S.K. Ghosh of S.K. Ghosh Associates, Inc.;
Mr. Robert F. Mast, PE, SE of Berger/Abram Engineers, Inc.; and Mr. Mete
Takenaka and Asahikosan argue that deductions for depreciation and A. Sozen - to validate Meinhardst's conclusions. These experts
deterioration are inconsistent with the concept of replacement cost as a unanimously concluded that the NAIA-IPT III's design is structurally sound
measure of appraising the actual value of the NAIA-IPT III. In exercising because it complied with the 1992 NSCP, thus, effectively negating the
the power of eminent domain, the Government takes the property on "as Government's claim that the NAIA-IPT III suffers from structural defects.
is, where is" basis. Takenaka and Asahikosan point out that the Takenaka and Asahikosan impugn the ASEP Report. They reiterate that
Government has the option not to expropriate the terminal. they constructed the NAIA-IPT III in accordance with the Onshore
Consequently, the Government cannot base the value of the building on Construction and Offshore Procurement Contracts and the prevailing
whether or not the building caters to the Government's needs. building code at the time of the design and construction of the NAIA-IPT
III. The statement in the ASEP Report that "the NAIA-IPT III may be
Furthermore, RA 8974 IRR provides that only the costs necessary to partially opened provided that retrofitting works are done prior to its full
replace the expropriated property should be considered in appraising the operation" does not mean that the terminal is defective. The remediation
terminal. Statutes authorizing the deprivation of private property, as in works were solely to ensure that the NAIA-IPT III structures are compliant
expropriation cases, must be strictly complied with because these are in with the current standards, which were not yet in effect when the
derogation of private rights. The Court's intent in Agan when it declared construction of the NAIA-IPT III took place.
that equity should likewise be considered in appraising the NAIA-IPT III is
to prevent the Government from undervaluing the property and enriching Messrs. Meinhardt opined that the scope of the proposed retrofitting
itself at the expense of private parties. works shows that the structural design of the NAIA-IPT III is not defective
because the proposed retrofitting works are not related to the alleged
Takenaka and Asahikosan also insist that a multi-level retail mall is not an structural defects of the NAIA-IPT III vis-à-vis the 1992 NSCP. He also
unnecessary area. They point out that modern airports are subsidized by stated that the proposed retrofitting works are meant to reinforce the
income from retail malls and cannot operate profitably without this NAIA-IPT III which is already compliant with the 1992 NSCP.
additional income.
Takenaka and Asahikosan likewise engaged the services of AECOM
Takenaka and Asahikosan agree with the CA's finding that the NAIAIPT III Australia Pty. Ltd. to conduct a technical review of the Review on TCGI
is structurally sound. There is no clear evidence that the collapse of the Report of Civil Design Review and Evaluation (Elevated Roadway prepared
ceiling of the NAIA-IPT III was caused by the terminal's structural defects. by Ove Arup & Partners HK Ltd. Philippines Branch). AECOM criticized the
The CA correctly concluded that the ceiling's collapse is merely a finishing Ove Arup's review as follows:
and aesthetic issue.
a. Ove Arup valuated the NAIA-IPT's Elevated
They emphasize that Mr. Gary Taylor, their hired appraiser, assailed the Roadway using the AASHTO Manual of Bridge
qualifications, the methodology, and the findings of Ove Arup in its Evaluation and the FHA Bridge Inspectors Reference
August 2007 Site Observation Report. Furthermore, Ove Arup made Manual, which are irrelevant to any discussion of its
several conflicting findings on the structural soundness of the NAIA-IPT design;
III. Ove Arup concluded that the number of structural members failing the
Demand Capacity Rate (DCR)/m.1.10 criteria was more than those used b. Ove Arup evaluated the NAIA-IPT III's Elevated
for the retrofit design. The DCR measures the capacity of a portion of the Roadway using the Seismic Retrofitting Manual for
NAIANAIA-IPT III to carry the load it was designed to bear, with an Highway Structures, which is irrelevant because there
optimal rate being less than 1.0. It likewise opined that the distance of the is no need for a seismic retrofit of the NAIA-IPT III's
Elevated Roadway;

ProvRem Rule 67 Fulltext Page 42 of 119


c. Ove Arup's suggestion that an in-situ measurement structurally sound considering that majority of the terminal building share
of the geometry data of key structural components the same structural design.
be undertaken is unnecessary and irrelevant to a peer
review of the design of the NAIA-IPT III's Elevated They also deny that they employed armed guards to prevent the MIAA
Roadway; and DOTC officials from entering the premises of the NAIA-IPT III. They
point out that the Government did not raise this issue before the lower
d. Ove Arup made an incorrect assessment of the courts. They also state that they have provided the parties all
type of foundation material with respect to soil documentary evidence necessary in appraising the NAIA-IPT III, such as
bearing capacity; the Bills of Quantities.169

e. Ove Arup used inappropriate codes for the VI. The Issues
assessment of the bearings of the NAIA-IPT III's
Elevated Roadway; In G.R. Nos. 209917, 209696, and 209731, we resolve the following issues:

f. Ove Arup's analysis suggests that 36 pier columns (1) Whether the RTC's May 23, 2011 decision in Civil Case No.
of the NAIA-IPT III's Elevated Roadway are allegedly 04-0876 is null and void for violation of PIATCO, Takenaka and
under strength, but fails to quantify the ratio of the Asahikosan's right to procedural due process;
column effect to the corresponding capacity;

(2) Whether the CA legally erred in computing just


g. AECOM objects to Ove Arup's criticism that the compensation in the expropriation of the NAIA-IPT III;
value of the soil-bearing capacity used for the length
of the bridge of the NAIA-IPT III's Elevated Roadway
needs to be justified, since the design of the NAIA- (a) Whether "fair market value" and "replacement
IPT III's Elevated Roadway must be judged on the cost" are similar eminent domain standards of
property valuation;
geotechnical information available to AECOM at the
time the bridge was made. No foundation could have
been built without the foundation bearing capacity (b) Whether the depreciated replacement cost
results having been submitted to the relevant approach or the new replacement cost approach shall
overseeing authority and approved thereby; be used in the appraisal of the NAIA-IPT III;

h. Ove Arup used an incorrect site coefficient for the (c) With respect to the computation of construction
site's soil type, which resulted in seriously erroneous costs, the issues are:
input data, thus, any conclusions or
recommendations derived from these data are 1. Whether the Government's computation
rendered invalid; of construction cost is supported by a
preponderance of evidence;
i. Ove Arup's claim that there are "failures" in the
elastomeric bearings/bearing pads is based on an 2. Whether the NAIA-IPT III suffered/suffers
Australian design code which did not exist at the time from massive structural defects;
the NAIA-IPT III's Elevated Roadway was designed;

3. Whether the alleged unnecessary areas


j. Takenaka and Asahikosan were never provided a should be excluded from the computation
copy of the TCGI Report that was used as basis for of construction cost;
the ARUP Report;

(d) With respect to the computation of attendant


k. There are serious discrepancies between the Ove costs, the issues are:
Arup Report and the referenced, yet unseen TCGI
Report;
1. Whether PIATCO's claimed attendant
cost is supported by a preponderance of
l. The NAIA-IPT III's Elevated Roadway complies with evidence;
the project design codes in force at the time it was
designed; and
a) Whether the Court may accord
probative value to photocopied
m. AECOM refutes Ove Arup and TCGI's suggestion voluminous documents allegedly
that the NAIA-IPT III's Elevated Roadway requires proving PIATCO's attendant
retrofitting or any remedial work. costs;

Takenaka and Asahikosan aver that the Government would be able to b) Whether the Court may
lessen its expenses, operate the NAIA-IPT III, and earn revenues sooner as accord probative value to the
there is, in fact, no need to perform retrofitting works on the terminal. summary report prepared by
Reyes Tacandong & Co., which
Takenaka and Asahikosan point out that the design of the NAIA-IPT III is validated PIATCO's computation
bilaterally symmetrical which means the structural system of one area is of attendant costs;
virtually identical to others. Since the Government opened certain areas of
the NAIA-IPT III to the public, it follows that the unused areas are also

ProvRem Rule 67 Fulltext Page 43 of 119


2. Whether attendant cost may be pegged PIATCO, Takenaka and Asahikosan challenge the validity of the
at 10% of the construction cost; RTC's decision for alleged violation of their right to due process.
They point out that the RTC promulgated its decision in Civil
3. Whether the Government included the Case No. 04-0876 on May 23, 2011, immediately after the
attendant cost in its valuation of the NAIA- release of the BOC's Final Report
IPT III;
on March 31, 2011. They complain that since the RTC's clerk of
(e) Whether depreciation may be deducted from the court did not furnish the parties copies of the Final Report, the
replacement cost of the NAIA-IPT III; trial court violated Sections 7 and 8, Rule 67 of the Rules of
Court as they failed to object to the Final Report's contents.

(f) Whether rectification for contract compliance (for


failure to comply with bid documents; for inferior Rule 67 of the Rules of Court provides that the clerk of court
quality; and for the additional areas to be built)may shall serve copies of the commissioners' final report on all
be deducted from the replacement cost of the NAIA- interested parties upon the filing of the report. Each party shall
IPT III; have ten days within which to file their objections to the
report's findings.170

(g) Whether the replacement cost of the NAIA-IPT III


shall be adjusted to December 2004 values based on Upon the expiration of the ten-day period or after all the
inflation; parties have filed their objections and after hearing, the trial
court may: (a) accept the report and render judgment in
accordance therewith; (b) for cause shown, recommit the report
(h) Whether the CA erred in imposing an interest rate to the commissioners for further report of facts; (c) set aside the
of 6% per annum on the replacement cost of the report and appoint new commissioners; (d) partially accept the
NAIA-IPT III; report; and (e) make such order or render such judgment as
shall secure to the plaintiff the property essential to the exercise
(i) Whether PIATCO shall be entitled to the fruits and of his right of expropriation; and to the defendant, the just
income of the NAIA-IPT III; compensation for the property so taken.171

(3) Whether Takenaka and Asahikosan shall share in the We rule that the parties' failure to receive the Final Report did
expenses of the BOC; not render the May 23, 2011 Decision null and void.

(4) Whether the owner of the property sought to be The essence of procedural due process is the right to be
expropriated shall solely receive the just compensation due; heard.172 The procedural due process requirements in an
and eminent domain case are satisfied if the parties are given the
opportunity to present their evidence before the commissioners
(5) Whether the Government may take property for public whose findings (together with the pleadings, evidence of the
purpose or public use upon the issuance and the effectivity of parties, and the entire record of the case) are reviewed and
the writ of possession; considered by the expropriation court. It is the parties' total
failure to present evidence on just compensation that renders
the trial court's ruling void. The opportunity to present evidence
In G.R. No. 181892, the following issues are relevant:
during the trial remains to be the vital requirement in the
observance of due process.173
(1) Whether the appointment of an independent
appraiser issue has been rendered moot and
The record will show that the parties exhaustively discussed
academic by the RTC's promulgation of its rulings in
their positions in this case before the BOC, the trial court, the
Civil Case No. 04-0876; and
appellate court, and this Court.

(2) Whether the issue of who shall pay the


They had ample opportunity to refute and respond to each
independent appraiser's fees has been rendered
other's positions with the aid of their own appraisers and
moot and academic by the RTC's promulgation of its
experts. Each party, in fact, submitted countervailing evidence
rulings in Civil Case No. 04-0876.
on the valuation of the NAIA-IPT III. They also filed numerous
and voluminous pleadings and motions before the lower courts
VII. Our Ruling and before this Court. The mere failure of the RTC's clerk of
court to send the parties copies of the BOC Final Report is not
A. G.R. Nos. 209917, 209696 & 209731 substantial enough under the attendant circumstances to affect
and nullify the whole proceedings. Litigation is not a game of
technicalities. Strong public interests require that this Court
1. The parties were afforded procedural
judiciously and decisively settle the amount of just
due process despite their non-receipt
compensation in the expropriation of the NAIA-IPT III. We
of the BOC Final Report prior to the
cannot further delay this more-than a-decade case and let
promulgation of the RTC's May 23,
interests accrue on just compensation by remanding the case
2011 Decision.
once more to the trial court.

Before ruling on the substantive issues posed, we first resolve


2. Framework: Eminent domain is an
the issue of whether the CA erred in ruling that the RTC's May
inherent power of the State
23, 2011 decision is valid.

ProvRem Rule 67 Fulltext Page 44 of 119


2.a. The power of eminent domain is a fundamental Jurisprudence broadly defines "fair market
state power that is inseparable from sovereignty. value" as the sum of money that a person
desirous but not compelled to buy, and an
Eminent domain is a fundamental state power that is owner willing but not compelled to sell,
inseparable from sovereignty. It is the power of a would agree on as a price to be given and
sovereign state to appropriate private property within received for a property.184
its territorial sovereignty to promote public welfare.
The exercise of this power is based on the State's Fair market value is not limited to the
primary duty to serve the common need and advance assessed value of the property or to the
the general welfare.174 It is an inherent power and is schedule of market values determined by
not conferred by the Constitution.175 It is inalienable the provincial or city appraisal committee.
and no legislative act or agreement can serve to However, these values may serve as factors
abrogate the power of eminent domain when public to be considered in the judicial valuation of
necessity and convenience require its exercise.176 the property.185

The decision to exercise the power of eminent Among the factors to be considered in
domain rests with the legislature which has the arriving at the fair market value of the
exclusive power to prescribe how and by whom the property are the cost of acquisition, the
power of eminent domain is to be exercised. Thus, current value of like properties, its actual or
the Executive Department cannot condemn potential uses, and in the particular case of
properties for its own use without direct authority lands, their size, shape, location, and the
from the Congress.177 tax declarations. The measure is not the
taker's gain but the owner's loss.186 To be
The exercise of eminent domain necessarily just, the compensation must be fair not
derogates against private rights which must yield to only to the owner but also to the taker.187
demand of the public good and the common
welfare.178 However, it does not confer on the State While jurisprudence requires the "fair
the authority to wantonly disregard and violate the market value" to be the measure of
individual's fundamental rights. recovery in expropriation cases, it is not an
absolute and exclusive standard or method
2.b. Just compensation is the full and fair equivalent of of valuation.188 There are exceptional cases
the property taken from the owner by the condemnor. where the property has no fair market
value or where the fair market value of the
property is difficult to determine.
The 1987 Constitution embodies two constitutional
safeguards against the arbitrary exercise of eminent
domain: first, private property shall not be taken for Examples of properties with no or with
public use without just compensation;179 and second, scant data of their fair market values are
no person shall be deprived of life, liberty, or specialized properties or buildings
property without due process of law.180 designed for unique purposes.189 These
specialized properties bear these
characteristics because they are "rarely x x
Just compensation is defined as "the full and fair x sold in the market, except by way of sale
equivalent of the property taken from its owner by of the business or entity of which it is part,
the expropriator." The word "just" is used to qualify due to the uniqueness arising from its
the meaning of the word "compensation" and to specialized nature and design, its
convey the idea that the amount to be tendered for configuration, size, location, or
the property to be taken shall be real, substantial, full otherwise."190
and ample.181 On the other hand, the word
"compensation" means "a full indemnity or
remuneration for the loss or damage sustained by Examples of specialized properties are
the owner of property taken or injured for public churches, colleges, cemeteries, and
use."182 clubhouses.191 These also include airport
terminals that are specifically built as "a
place where aircrafts land and take off and
Simply stated, just compensation means that the where there are buildings for passengers to
former owner must be returned to the monetary wait in and for aircraft to be
equivalent of the position that the owner had when sheltered."192They are all specialized
the taking occurred.183 To achieve this monetary properties because they are not usually
equivalent, we use the standard value of "fair market sold in the ordinary course of trade or
value" of the property at the time of the filing of the business.
complaint for expropriation or at the time of the
taking of property, whichever is earlier.
In the Tengson Report dated December 1,
2010, Gary Taylor characterized the NAIA-
2.b.1. Fair market value is the general IPT III as a specialized asset.193 Tim Lunt
standard of value in determining just also stated in the Reply to Tengson
compensation.
International Ltd. Report and Response
from Takenaka & Asahikosan dated
December 7, 2010 that the market value of

ProvRem Rule 67 Fulltext Page 45 of 119


an airport will not be the same as the compensation if the expropriated property
market value of other commercial, has no market based evidence of its value.
industrial, and residential buildings within
the Metro Manila region.194 2.b.3. Replacement cost is only one of the
standards that the Court shall consider in
In cases where the fair market value of appraising the NAIA-IPT III.
the property is difficult to ascertain, the
court may use other just and equitable In using the replacement cost method to
market methods of valuation in order to ascertain the value of improvements that
estimate the fair market value of a shall be expropriated for purposes of
property. implementing national infrastructure
projects, Section 10 of RA 8974 IRR
In the United States, the methods requires the implementing agency to
employed include: (1) the cost of replacing consider the kinds and quantities of
the condemned property, less depreciation; materials/equipment used, the location,
(2) capitalization of the income the configuration and other physical features
property might reasonably have produced; of the properties, and the prevailing
(3) the fair rental value of the property construction prices, among other things.
during a temporary taking; (4) the gross
rental value of an item over its depreciable Section 5 of RA 8974 in this regard
lifetime; (5) the value which the owner's provides that the court may consider the
equity could have returned, had the owner following relevant standards in eminent
invested in monetary instruments; (6) the domain cases:
cost of repair or the capitalized cost of
inconvenience, whichever is less; and (7)
the loss of investment expenses actually (a) The classification and use for
incurred.195 The primary consideration, which the property is suited;
however, remains the same - to determine
the compensation that is just, both to the (b) The developmental costs for
owner whose property is taken and to the improving the land;
public that will shoulder the cost of
expropriation. (c) The value declared by the
owners;
2.b.2. Replacement cost is a different
standard of value from fair market value. (d) The current selling price of
similar lands in the vicinity;
In Gingoyon, we held that the construction
of the NAIA-IPT III involves the (e) The reasonable disturbance
implementation of a national infrastructure compensation for the removal
project. Thus, for purposes of determining and/or demolition of certain
the just compensation of the NAIA-IPT III, improvement on the land and for
RA 8974 and its implementing rules shall the value of improvements
be the governing law. thereon;

Under Section 10 of the RA 8974 IRR, the (f) The size, shape or location, tax
improvements and/or structures on the declaration and zonal valuation
land to be acquired for the purpose of of the land;
implementing national infrastructure
projects shall be appraised using the
(g) The price of the land as
replacement cost method.
manifested in the ocular findings,
oral as well as documentary
Replacement cost is a different standard of evidence presented; and
valuation from the fair market value. As we
previously stated, fair market value is the
(h) Such facts and events as to
price at which a property may be sold by a
enable the affected property
seller who is not compelled to sell and
owners to have sufficient funds
bought by a buyer who is not compelled to
to acquire similarly situated
buy. In contrast, replacement cost is "the
lands of approximate areas as
amount necessary to replace the
those required from them by the
improvements/structures, based on the
government, and thereby
current market prices for materials,
rehabilitate themselves as early
equipment, labor, contractor's profit and
as possible.
overhead, and all other attendant costs
associated with the acquisition and
installation in place of the affected The Court explained in Agan and Gingoyon
improvements/structures."196 We use the that the replacement cost method is only
replacement cost method to determine just one of the factors to be considered in

ProvRem Rule 67 Fulltext Page 46 of 119


determining the just compensation of the amount of just compensation,
NAIA-IPT III. The Court added that the the duty of the trial court is to
payment of just compensation should be in ensure that such amount
accordance with equity as well. conforms not only to the law,
such as RA 8974, but to
In Agan, we stated: principles of equity as
well.(Emphasis supplied)198

This Court, however, is not


unmindful of the reality that the The Court's pronouncements in Agan and
structures comprising the NAIA Gingoyon are consistent with the principle
IPT III facility are almost that "eminent domain is a concept of
complete and that funds have equity and fairness that attempts to make
been spent by PIATCO in their the landowner whole. It is not the amount
construction. For the of the owner's investment, but the 'value of
government to take over the said the interest' in land taken by eminent
facility, it has to compensate domain, that is guaranteed to the
respondent PIATCO as builder of owner."199
the said structures. The
compensation must be just and In sum, in estimating the fair market value
in accordance with law and of the NAIA-IPT III, the Court shall use(1)
equity for the government the replacement cost method and(2) the
cannot unjustly enrich itself at standards laid down in Section 5 of RA
the expense of PIATCO and its 8974 and Section 10 of RA 8974 IRR.
investors.(emphasis supplied)197 Furthermore, we shall likewise consider(3)
equity in the appraisal of NAIA-IPT III
We also declared in Gingoyon based on the Agan and Gingoyon cases.
that:
2.b.4. The use of depreciated replacement
Under RA 8974, the Government cost method is consistent with the principle
is required to "immediately pay" that the property owner shall be
the owner of the property the compensated for his actual loss.
amount equivalent to the sum of
(1) one hundred percent (100%) The present case confronts us with the
of the value of the property question of the specific replacement cost
based on the current relevant method that we should use in appraising
zonal valuation of the [BIR]; and the NAIA-IPT III. The Government
(2) the value of the advocates the depreciated replacement
improvements and/or structures cost method formula while PIATCO argues
as determined under Section 7. for the new replacement cost method
As stated above, the BIR zonal formula.
valuation cannot apply in this
case, thus the amount subject to The replacement cost method is a cost
immediate payment should be approach in appraising real estate for
limited to "the value of the purposes of expropriation. This approach is
improvements and/or structures premised on the principle of substitution
as determined under Section 7," which means that "all things being equal, a
with Section 7 referring to the rational, informed purchaser would pay no
"implementing rules and more for a property than the cost of
regulations for the equitable building an acceptable substitute with like
valuation of the improvements utility."200
and/or structures on the land."
Under the present implementing
rules in place, the valuation of The cost approach considers the principles
the improvements/structures are of substitution, supply and demand,
to be based using "the contribution and externalities.201 "The value
replacement cost method." of the land and the value of improvements
However, the replacement cost is are determined separately according to
only one of the factors to be their highest and best use."202 "Buyers
considered in determining the assess the value of a piece of property not
just compensation. only based on the existing condition of the
property, but also in terms of the cost to
alter or improve the property to make it
In addition to RA 8974, the 2004 functional specifically for the purposes of
Resolution in Agan also the buyer's use. This may include building
mandated that the payment of new structures, renovating existing
just compensation should be in structures, or changing the components of
accordance with equity as well. an existing structure to maximize its
Thus, in ascertaining the ultimate utility."203

ProvRem Rule 67 Fulltext Page 47 of 119


There are various methods of appraising a considered, for it is an element
property using the cost approach: among of value of specialty property. In
them are the reproduction cost, the figuring this cost, all overhead
replacement cost new, and the depreciated expenses are included. These
replacement cost. Reproduction cost is the expenses include engineering,
"estimated current cost to construct an construction, management fees,
exact replica of the subject building, using insurance, legal expenses, office
the same materials, construction standards, overhead, and interest during
design, layout, and quality of workmanship; construction period. Third, from
and incorporating all the deficiencies, the reproduction cost new an
superadequacies, and obsolescence of the allowance for depreciation of the
subject building."204 It is the cost of improvements must be made.
duplicating the subject property at current This depreciation is a matter of
prices205 or the current cost of reproducing opinion, formed after a physical
a new replica of the property being examination of the
appraised using the same, or closely improvements as a whole and is
similar, materials.206 generally not based on a
straight-line depreciation
In the United States, the recognized and according to age. Some
used method in eminent domain cases in authorities, however, have not
appraising specialized properties is the accepted such an item of
reproduction cost less depreciation depreciation and prefer the
approach. straight-line method, at so much
per year. Obsolescence and
functional depreciation are
According to AmJur, this valuation method sometimes deducted in addition
requires the inclusion of all expenditures to physical depreciation
that reasonably and necessarily are to be depending on the type of utility
expected in the recreation of the structure, involved.208
including not only the construction itself
but also collateral costs, such as the costs
of financing the reproduction. "Historical Replacement cost new is "the estimated
associations and architectural values may cost to construct a building with utility
enhance the market worth of a property by equivalent to the appraised building using
rendering it a specialty property; if so, the modern materials and current standards,
property may fairly be worth the market design, and layout"209 or "the current cost
price for similar properties, plus a premium of a similar new property having the
for its unique aspects. The premium value nearest equivalent utility as the property
in such a case may also be determined by being valued."210 It is the cost of acquiring
the cost of reproduction, minus a modern, functional equivalent of the
depreciation. The value assigned has also subject property and "views the building as
been described as the total of the land if reconstructed with modern methods,
value, plus the specialized value of the design and materials that would most
improvements, minus depreciation."207 closely replace the use of the appraised
building but provide the same
utility."211Replacement cost does not
Alfred Jahr explains the procedure in consider the most common forms of
appraising a specialized property using this functional obsolescence.212
method:

Depreciated replacement cost approach is


In the valuation of the the "method of valuation which provides
improvement or plant, however, the current cost of replacing an asset with
market value is no criterion its modern equivalent asset less deductions
because they have no market for all physical deterioration and all
value. It is specialty property. The relevant forms of obsolescence and
improvements are therefore optimisation."213 Depreciated replacement
valued on several properties. cost is a method of appraising assets that
First, consideration is given tothe are usually not exposed to the open
original book cost of the market.214 A general formula of this
improvements, that is, the method is as follows:
original cash expenditure paid by
the company for making the
physical structures and Cost of constructing the building
appurtenances. Its purpose is to (s) (including fees)
act as some guide; it is not value, Plus: Cost of the land (including
however, and the courts fees)
recognize the fact that it is not a = Total Costs
value of the physical structures. Less: Allowance for age and
Second, evidence of depreciation
reproduction cost new is then
ProvRem Rule 67 Fulltext Page 48 of 119
= Depreciated Replacement technology which allow for a more efficient
Cost215 delivery of services and goods from a
building of different designs and
Under this method, the appraiser assesses specifications."224 "Functional obsolescence
the current gross replacement of the arises where the design or specification of
assets, usually comprised of the land and the asset no longer fulfills the function for
the building. If the asset is an which it was originally designed."225
improvement, the appraiser assesses the
cost of its replacement with a modern It is "usually related to operational
equivalent and deducts depreciation to inefficiencies that typically involve either
reflect the differences between the inadequacies or superadequacies. An
hypothetical modern equivalent and the inadequacy occurs when the asset is not
actual asset. The appraiser has to "establish enough (e.g., the asset is too small) for it to
the size and specification that the operate efficiently. A superadequacy occurs
hypothetical buyer ideally requires at the when there is too much of an asset (e.g.,
date of valuation in order to provide the the asset is too large) for it to operate
same level of productive output or an efficiently."226 "To be feasible, the cost of
equivalent service."216 In appraising the replacing the obsolete item or design fault
improvement using the cost approach, the must be equal to or less than the
appraiser considers the construction cost, anticipated increase in value due to its
and attendant cost. cure. Curable functional obsolescence may
require abatement by adding or
Construction costs are "the costs that are remodelling or by removing a
normally and directly incurred in the superadequacy."227
purchase and installation of an asset, or
group of assets, into functional use." On Economic obsolescence results from "the
the other hand, attendant costs are "the impact of changing external macro- and
costs that are normally required to micro-economic conditions on the
purchase and install a property but that are property and should not include internal
not usually included in the vendor factors which affect the profitability of the
invoice."217 occupying business, the writing down of
such factors to reflect the profitability of
Under Section 10 of the RA 8974 IRR, the business being a matter for the
construction cost is the current market occupier. Within economic obsolescence,
price of materials, equipment, labor, the the prospect of extending the life of the
contractor's profit and overhead, while the building by capital investment should be
attendant cost is the cost associated with considered, as well as the fact that lack of
the acquisition and installation in place of maintenance can accelerate the rate of
the affected improvement. depreciation."228

Once the gross replacement cost or the In these consolidated cases, we rule that
sum of construction and attendant costs is the depreciated replacement cost method,
derived, depreciation shall be rather than the new replacement cost
deducted.218 Depreciation is classified into method, is the more appropriate method
three categories: physical depreciation, to use in appraising NAIA-IPT III.
functional obsolescence, and external
obsolescence. Injustice would result if we award PIATCO
just compensation based on the new
Physical obsolescence refers to the "wear replacement cost of the NAIA-IPT III, and
and tear over the years, which might be disregard the fact that the Government
combined with a lack of maintenance."219 expropriated a terminal that is not brand
new; the NAIAIPT III simply does not have
the full economic and functional utility of a
Physical depreciation is curable if "capital brand new airport.
investment can bring the building to a
state in which the degree of obsolescence
is mitigated (e.g., standards of finishes and Adjustments for depreciation should be
services)."220 It is incurable if "no amount of made to reflect the differences between
capital investment can rectify the the modern equivalent asset and the actual
[depreciation] (for example, building asset or the NAIA-IPT III. The reason is that
structural flexibility)."221 Curable physical depreciation involves the loss of value
depreciation is measured by the cost to caused by the property's reduced utility as
cure or retrofitting which could extend the a result of damage, advancement of
life of the building.222 Incurable technology, current trends and tastes, or
depreciation or deterioration is estimated environmental changes.229
by a variety of age-life or economic-age
calculation methods.223 Functional This conclusion is consistent with Section
obsolescence "reflects the advances in 10 of RA 8974 IRR which allows us - and

ProvRem Rule 67 Fulltext Page 49 of 119


under the NAIA-IPT-III's circumstances In using the depreciated replacement cost
effectively direct us - to consider the kinds method of valuation, we do not rely on
and quantities of materials/equipments Kaczmarek's affidavit and other documents
used, configuration and other physical not presented before the trial court, and
features of the properties, among other which were belatedly attached to the
things, in determining the replacement Government's motion for partial
cost of a building. To quote Section 10: reconsideration dated August 22, 2013.

Section 10. Valuation of Improvements This Court exercises its judicial function to
and/or Structures - Pursuant to Section 7 fix just compensation in eminent domain
of the Act, the Implementing Agency shall cases on the basis of the law, the rules, and
determine the valuation of the the evidence - including the appraisal
improvements and/or structures on the reports and the embedded formula on how
land to be acquired using the replacement the parties arrived at the amounts of just
cost method. The replacement cost of the compensation - presented by the parties
improvements/structures is defined as the before the trial court and the entire record
amount necessary to replacement of the consolidated cases.
improvements/structures, based on the
current market prices for materials, The determination of just compensation in
equipment, labor, contractor's profit and eminent domain cases is essentially and
overhead, and all other attendant costs exclusively a judicial function. Fixing the
associated with the acquisition and formula with definitiveness and
installation in place of the affected particularity in just compensation is not the
improvements/structures. In the valuation function of the executive nor of the
of the affected improvements/structures, legislative branches, much less of the
the Implementing Agency shall consider, parties in this case. Any valuation for just
among other things, the kinds and compensation laid down in the statutes
quantities of materials/equipment used, may not replace the court's own judgment
the location, configuration and other as to what amount should be awarded and
physical features of the properties, and how this amount should be arrived at.
prevailing construction prices. (Emphasis Legislative enactments, as well as executive
supplied) issuances, providing the method of
computing just compensation are treated
Depreciation should be deducted because as mere guidelines in ascertaining the
modern materials and design are assumed amount of just compensation. When acting
in the replacement cost method. In using within the parameters set by the law itself,
the depreciated replacement cost method, courts are not strictly bound to apply the
"[t]he intent is to provide a functionally formula to its minutest detail, particularly
similar improvement in order to apply a when faced with situations that do not
meaningful level of depreciation."230 warrant the formula's strict application. The
courts may, in the exercise of their
If we adopt the new replacement cost discretion, relax the formula's application
method, PIATCO would be compensated to fit the factual situations before them.233
for more than what it had actually lost. We
must remember that the concept of just We clarify, however, that this Court is not
compensation does not imply fairness to confined to the use of the depreciated
the property owner alone. In an eminent replacement cost method in determining
domain situation, compensation must the just compensation in these cases.
likewise be just to the public which Valuation is not exclusively a technical
ultimately bears the cost of expropriation. matter used in arriving at a numerical
The property owner is entitled to measure of compensation. Rather,
compensation only for what he actually valuation in eminent domain is a judicial
loses; what he loses is only the actual value question based on equitable principles.
of the property at the time of the taking.231 Thus, this Court shall likewise endeavor to
weigh the justness and fairness of
Just compensation must not extend compensation between the condemnor
beyond the property owner's loss or injury. and the condemnee, considering the
This is the only way for the compensation factual circumstances of this case.234
paid to be truly just, not only to the
individual whose property is taken, but also 3. Construction cost of the NAIA-IPT III
to the public who will shoulder the cost of
expropriation. Even as under valuation 3.a. The base valuation of the NAIA-IPT III
would deprive the owner of his property
without due process, so too would its
overvaluation unduly favor him to the The Government claims that the construction cost or
prejudice of the public.232 the base valuation of the NAIA-IPT III amounts to
$300,206,693.00, itemized as follows:235

ProvRem Rule 67 Fulltext Page 50 of 119


at ain
Total $USD designated
Manila time and specific location,
@3Q01 adding the cost of works in, on, and around
the structure, and then accounting for
General Requirements and Conditions inferior and non-performing works, and
$ 36,279,033
rectification of those works.
Site Development $ 3,293,967

Terminal North Concourse 2.2.2 I have arrived at the$CCVs by carrying


6,847,663
out the following sequence of tasks:
Terminal South Concourse $ 11,169,979

Terminal Head House 1) Understanding the project as


$ 60,763,798
bid and as eventually
Terminal Building Services constructed. $ 54,982,628

Multi Storey Car Park $ 8,791,857


2) Preparing measured quantities
Special Systems for the major $elements of the
69,321,503
completed works.
Airside Infrastructure Works $ 31,065,288

Landside Infrastructure Works 3) Establishing$ appropriate


11,496,552 rates
and prices for carrying out the
Terminal Support Facilities $ 6,194,425
works at that time in Manila,
Philippines.
Office Fit-out $0

Builder's Work in Connection with Included


4) Adjusting the quantities
and/or rates and prices to take
Services into account the extent of non-
performing and/or inferior
Total $ USD quality works,$ 300,206,693
the extent of
rectification and remediation of
the Terminal to bring it to Code
On the other hand, PIATCO, Takenaka, and and making it structurally safe,
Asahikosan argue that the construction cost amounts and 22,193 m2 of 'Unnecessary
to $360,969,791.00, viz: Areas' that was built in the
Terminal.
In US dollars
5) Making provision for the cost
total payments of piaTCO 275,119,807.88
of remediation on items which
Add: Awards by the London Court 84,035,974.44
deteriorated between December
Award by the Makati Court 1,814,008.50
2002 and December 2004.
Total Construction Cost 360,969,790.82

6) Making provision for the value


As we had earlier explained, construction cost is the amount of depreciation of Terminal 3
necessary to replace the improvements/structures, based on between December 2002 and
the current market prices for materials, equipment, labor, December 2004.
contractor's profit and overhead. Construction or direct costs is
also defined as the costs that are "normally and directly 7) Deducting the cost of
incurred in the purchase and installation of an asset or group of rectification to otherwise bring
assets into functional use." Construction costs generally take the Terminal to the standards in
into account the labor used to construct buildings; materials, the Bid Documents, including the
products, and equipment; contractor's profit and overhead, cost of building some 63,490 m2
including job supervision, workers' compensation, fire and of 'Necessary Operational Areas'
liability insurance, and unemployment insurance; performance that was not built in the
bonds, surveys, and permits; use of equipment; watchmen; Terminal.237
contractor's shack and temporary fencing; materials storage
facilities; and power-line installation and utility costs.236 We find
2.3 Understanding the Project
the Government's computation of construction cost to be more
realistic and appropriate. As the CA aptly observed, the Gleeds
Report is more "particularized, calculable and precise." Tim Lunt 2.3.1 I visited the Terminal 3 site
sufficiently explained how he arrived at the value of between May 9, 2006 and May
$300,206,693.00: 12, 2006; May 30, 2006 and June
2, 2006; and June 20 and June
25, 2006, when I held meetings
2.2 Methodology
with the Office of the Solicitor
General, White & Case, MIAA,
2.2.1 Stated simply, valuation of any given Arup, TCGI, and Gensler. I based
structure is derived by multiplying the myself at the Terminal 3 complex
structure's dimensions, i.e., quantities by a during my visits in May and June
price (i.e., rate) for constructing the works 2006 and made a number of
ProvRem Rule 67 Fulltext Page 51 of 119
visits to various areas both contractors. Those contractors
internal and external to Terminal who wish to do the work return
3 to gain a full understanding of the bill, with an extended price
the scope of the works opposite each item. This priced
performed. bill constitutes the contractors'
offer (or tender to bid) to do the
2.3.2 Members of my staff visited work.239
the Terminal 3 site between May
30, 2006 and June 25, 2006, and 2.4.5 As noted, it was apparent
based themselves in the Terminal from commencement of
3 complex to prepare quantities preparation of the CCVs that it
from construction drawings was doubtful that the set of
made available by Takenaka, drawings listed in Appendix "B"
which, as noted, are not properly that Takenaka provided were
designated 'As-built' drawings. "As-built" or approved.
To safeguard against error or Accordingly, because of
outdated dimensional uncertainty over the accuracy of
information in the drawings, my the "As-built" drawings, and to
staff checked certain major avoid preparing Bills of
dimensions against the Quantities based on potentially
structures as constructed and inaccurate information, I opted
found the dimensions to be not to produce full Bills of
substantially accurate. We did Quantities to form the basis of
not check the drawings for the CCVs. Instead, I relied on a
detailed accuracy of the contents "Principle Quantities" type
in the drawings (i.e., what is approach.240
within the dimensions).
Principle Quantities
2.3.3 Members of my staff also
visited the Terminal 3 site 2.4.6 The "Principle Quantities"
between February 26, 2008 and type approach is common in the
March 11, 2007. During that cost planning and cost
time, they gathered pricing estimating of construction
information from local projects. CESMM3 describes
construction contractors to assist Principle Quantities as "a list of
with the pricing of the CCVs. principle components of the
works with their approximated
2.3.4 I have examined all of the estimated quantities x x x given
documents listed in Appendix 'B' solely to assist surveyors and
and had discussions with each of estimators in making rapid
the Republic's airport assessment of the general scale
architectural and engineering and character of the proposed
experts on the content of their works prior to the examination of
reports to gain a full the remainder of the bills of
understanding of the main issues quantities and other contract
affecting Terminal 3 and the documents on which
CCVs.238 construction estimates or
tenders will be based." This
2.4. Preparing the Quantities methodology involves the
preparation of quantities for the
major elements of the
Bills of Quantities construction works where the
costs cannot be estimated
2.4.1 Construction projects are accurately from historical data, or
generally priced by construction for those areas which are known
contractors for the purpose of to vary in cost due to the quality
competitive tendering using a or nature of the works. The
Bill (or Bills) of quantities. Bills of quantities produced by adopting
Quantities are defined as: this approach are what I term
"Principle Quantities."241
A list of numbered items, each of
which describes the work to be 2.4.7 Given the serious concerns
done in a civil engineering or over the accuracy of the so called
building contract. Each item "As-built" drawings, and in order
shows the quantity or work to make some assessment of the
involved. When the procedure of dimensional accuracy of the
tendering is adopted (as is Takenaka drawings, we carried
usual), the Bill is sent out to out a number of checks of the
ProvRem Rule 67 Fulltext Page 52 of 119
plan dimensions against our ● Any physical
measurement of the physical restrictions that might
dimensions of the structures. impede construction
Overall dimensions (length and of the works;
width) were checked for a single
floor plate in each of the ● The duration for
Terminal North Concourse, the carrying out
Terminal South Concourse and construction;
the Terminal Head House
buildings. Our checks revealed
no major discrepancies in respect ● Database of costs;
of the physical plan dimensions
of the drawings against the ● The specification of
actual dimensions of the overall the works;
building floor plans. We
therefore decided to use the ● The quality of the
drawings provided by Takenaka works as constructed;
to produce the "Principle and
Quantities" dimensions required
for us to prepare the CCVs.
● The extent of works
requiring remediation
2.4.8 The 'Principle Quantities' and rectification
dimensions produced by Gleeds
from the drawings made
2.5.2 All of the above factors
available by Takenaka (listed in
have an effect on the CCVs and it
Appendix 'B' Drawing List 1) are
is necessary to consider the
included in Appendix "G."
implications of each to arrive at
the CCV figures. General
2.4.9 It is standard good practice guidance including a number of
for quantities produced as part the above items are referred to
of the measurement process to in the document titled "Guide to
be checked by another member Carrying Out Reinstatement Cost
of the team who is not Assessments' published by the
connected to the particular Royal Institution of Chartered
project. The quantities we Surveyors in September 1999.243
produced were technically
checked by another member of
3. CCV CALCULATIONS
Gleeds for consistency among
inter-related items, e.g.,
consistency between floors and 3.1 Calculation of Rates and
ceilings, and to identify any Prices
major items not measured.
Another member of Gleeds also 3.1.1 The CCVs have
checked the accuracy of the been calculated in £UK
gross floor area, or "GFA," costs converted to
calculations for each of the $USD in Manila. x x x
buildings and no significant
errors were identified.242
3.1.2 The basic
approach to producing
2.5. Arriving at the Rates and Prices the CCV figures entails
the following steps:
2.5.1 In order to derive the rates
by which the quantities are 1) Establish
produced to arrive at the CCV UK pricing
figures for this project, it is levels at 2nd
necessary to establish: Quarter
2006 (£UK
● The period of @ 2Q06)
construction; (the date
when the
pricing
● The geographical
exercise was
location of the works;
initially
carried out);
● Access to the site;

2) Convert
the £UK @

ProvRem Rule 67 Fulltext Page 53 of 119


2Q06 prices CCVs as £UK @ 2Q06.
into £UK at The rates used are
3rd Quarter included in Appendix
2001 prices "D." Support in respect
(£UK @ of the reference to the
3Q01) (the source derivation of
mid point of each of the rates and
construction prices included in the
) using CCVs are also included
published in Appendix 'D' in the
and column headed "Rate
recognized Source."244
indices;
3.1.4 Second, it was
3) Convert necessary to adjust the
the £UK prices to the midpoint
@3Q01 of construction. As
prices into such the "£UK @
US dollars at 3Q01" levels to align
3rd Quarter them with required
($USD base costs for
@3Q01) (the inclusion in both CCVs.
currency of This conversion is
the Termianl made by using the
3 BCIS All-in Tender
Concession Price Indices published
Contract) by the Royal
using Institution of
published Chartered surveyors.
currency These costs are shown
exchange in the CCV as "£UK @
rates; 3Q01."

4) Convert 3.1.5 Third, the "£UK


the $USD @ 3Q01" costs were
@3Q01 converted from UK
prices to pounds to US dollars
reflect local using an exchange rate
levels of of UK£1 = ISD$1.4540.
pricing by This exchange rate is
applying a obtained by averaging
Location the exchange rates
Adjustment recorded for October
using 1, November 1 and
various December 3, 2001 (i.e.,
methods 3Q01) using historical
and sources data from the
of xrates.com website.
information These particular dates
to check the represent the midpoint
accuracy of of construction which I
the refer to earlier in this
conversion. report. The result of
this conversion is
Each of these steps is shown in the column
described below. marked "£UK @ 3Q01"
in Appendix "D."

3.1.3 First, the


quantities produced 3.1.6 Fourth, a
for Terminal 3 were "Location Adjustment"
priced using a mixture of the "$USD @ 3Q01"
of current data in cost is necessary to
Gleeds' Database of account for the local
costs and published cost of constructing in
cost data, including Manila. Local cost data
Spons, and are priced gathered in Manila by
at 2Q06 prices. These members of my team
costs are shown in the in February and March

ProvRem Rule 67 Fulltext Page 54 of 119


2007 was compared contracts executed
directly with UK prices and during
to establish a ratio construction and in my
between the UK and opinion this would
the Philippines. The have resulted in no
cost data gathered in material difference to
Manila was compared the pricing level of the
on a like for like basis onshore works
with 1st Quarter 2007 submitted at tender
UK prices. The results stage when compared
of this comparison of with the actual cost
rates result in the incurred.
"Location Adjustment."
The Location 3.1.8 I also have
Adjustments resulting gathered information
from this calculation from other Chartered
which are applied to Surveyors' published
the CCV are data which also
UK£1=$USD0.7576 for indicate that the
the mechanical, Location Adjustment
electrical and plant for the Philippines is in
elements. The average the region of 45%. This
conversion rate across percentage is in line
the CCVs is with the more detailed
UK£1=$USD0.5370 or results obtained as
53.70%.245 part of my own
calculations.246
3.1.7 I double-checked
my calculations of the We thus rule in favor of the Government's
Philippine prices by position and reject PIATCO's claimed
considering what the construction cost. For one, PIATCO made
conditions in the inconsistent statements with respect to the
Philippines construction cost of the NAIA-IPT III. The
construction market Scott Wilson report states that the
were at the time the construction cost of the NAIA-IPT III
project would have amounted to US$338.83 million, exclusive
been bid, and how of attorney's fees, cost of the suit, interest
these conditions rates, etc. This amount is inconsistent with
changed through to PIATCO's claimed construction cost of
the end of 2002 when $360,969,790.82 in its pleadings. The
works stopped on site. relevant portion of the Scott Wilson report
During the period of states:
1995 to 2002 the
"Construction
Materials Wholesale 2.1.4 When Scott Wilson was
Price Index" ("CMWPI") providing Lenders Technical
published by the Advice to the Asian Development
'Economic Indices and Bank in September 2002, the
Indicators Division, total value of the construction
Industry and Trade contracts, estimated by PCI at
Statistics Department, that time, was as follows:
Philippine National
Statistics Office, On-Shore Contract:
Manila, Philippines' US$132.35 million
showed an average
increase of 2.8% per Off-Shore Contract:
annum. US$190.08 million

During the periods Total US$322.43


2000 to 2001 and 2001 million, excluding
to 2002 the increases VAT
where 2.1% and 3.4%
respectively. The
2.1.5 The contract priceS under
increases are seen to
the EPC Contracts are as follows:
be at similar levels
both in the period
during which the On-Shore Contract.
works were priced, US$133,715,911

ProvRem Rule 67 Fulltext Page 55 of 119


Off-Shore Contract. reasonable. We note that the
US$190,037,328 Gleeds' estimate is close to the
figure in 2.2.13 above.
Total
US$323,753,239 2.2.16 It is noted that in the
excluding VAT Gleeds Report entitled
Construction Cost Valuation for
2.1.6 The amounts certified for NAIA IPT3 dated 15th November
the costs of construction up to 2010 the project Base Case CCV
23 June 2004 in payment is valued at a gross amount of
certificate no 35 which is the last US$334.61 million (US$300.21
payment certificate that has million + US$34.6 million
been certified by PIATCO, are as deductions).247
follows:
Furthermore, PIATCO did not present
On-Shore US$133.64 detailed supporting information on how
Million the certified construction cost of
US$338.83 million was arrived at.248

Off-Shore US$189.83
Million PIATCO's statement that the total sum of
$360,969,791.00 is evidenced by the As-
Built Drawings is misleading. Takenaka and
VAT US$11.43 Million Asahikosan's computation of construction
cost includes items which do not pertain to
ER Changes US $3.93 the construction of the NAIA-IPT III.
Million PIATCO, Takenaka, and Asahikosan
erroneously included in the construction
TOTAL US$338.83 cost the costs of the action, interest rates
Million on the judgment award of $14,827,207.00
and $52,008,296.54, attorney's fees, and
litigation expenses.
2.2.13 Based on the certified IPC
no. 35 for both Takenaka and
Asahikosan, the cost of the These items were not directly incurred in
completed and certified works the construction of the NAIA-IPT III. In
(as of IPC No. 35) are as follows: Claim No. HT-04-248, only $6,602,971.00
and $8,224,236.00 or the sum of
$14,827,207.00 can possibly relate to the
On-Shore US$133.64
construction cost of the NAIA-IPT III. On
Million
the other hand, in Claim No. HT-05-269,
only the amounts of $21, 688,012.18 and
Off-Shore US$189.83 $30,319,284.36 or the total sum of
Million $52,008,296.54 can be possibly imputed to
the construction cost of the terminal.
VAT US$11.43 Million
In any case, we cannot consider the
ER Changes US $3.93 London awards as evidence of the
Million construction cost of the NAIA-IPT III. Todo
so in this case is to recognize Claim No.
HT-04-248 and Claim No. HT-05-269 when
TOTAL US$338.83
their recognition and enforcement have yet
Million
to be decided by this Court in G.R. No.
202166. It is a basic rule that Philippine
2.2.14 The construction cost courts cannot take judicial notice of a
stated above x x x is at 2002 foreign judgment or order.249
prices (no adjustments for
inflation/escalation) and are
We can only recognize and/or enforce a
exclusive for all other attendant
foreign judgment or order after a
costs, such as the engineering
conclusive and a final finding by Philippine
and architectural service fees,
courts that: (1) the foreign court or tribunal
quality assurance service fees,
has jurisdiction over the case, (2) the
construction supervision service
parties were properly notified, and (3) there
fees, construction insurance, site
was no collusion, fraud, or clear mistake of
development costs, financing
law or fact.250
costs and other associated costs.
2.2.15 We would conclude that
the certified cost of construction PIATCO, Takenaka, and Asahikosan alleged
of US$338 million and the other that PIATCO paid Takenaka and Asahikosan
attendant costs are fair and the sum of $275,119,807.88 pursuant to the
ProvRem Rule 67 Fulltext Page 56 of 119
Onshore Construction and Offshore Evaluation" - Elevated Roadway, dated
Procurement Contracts. According to the March 2009; and other rectification works
RTC (whose ruling the CA did not reverse), required to bring the elevated roadways to
these parties failed to prove the fact of compliance with applicable building and
payment of $275,119,807.88. airport codes, as indicated in the
Appendices of Arup's Site Observation
We add that the alleged payment of Report.252
$275,119,807.88 does not support their
allegations that this amount pertains to the Scott Wilson argued that no structural elements of
construction cost of the NAIA-IPT III. the NAIA-IPT III actually failed.253 He emphasized that
Takenaka and Asahikosan's admission that there were varying opinions regarding the integrity of
the sum of $275,119,807.88 were paid by the NAIA-IPT III:
PIATCO does not bind the Government
who is not a party to the Onshore 3.3.7 The adequacy of the structural frame, individual
Construction and Offshore Procurement load bearing elements and foundations under
Contracts. If at all, the Court can only "normal" gravity loads should be able to be readily
recognize the sum of $66,834,503.54 from evaluated. However, there are clearly differences of
PIATCO, Takenaka, and Asahikosan's opinion between all 3 parties who have carried out
computation of construction cost, which is design and assessments in this regard in terms of the
much lower than the Government's extent of 'apparent failed elements' under the design
computed construction cost of appraisal which ranges from:
$300,206,693.00.

● Meinhardt - zero failures


Lastly, we note that Takenaka and
Asahikosan's claimed construction cost is
different from the amount reflected in the ● Arup reports under gravity loading - 4%
Tengson Report. In this Report, Gary Taylor of superstructure elements and less than
1% of all substructure elements
stated the "true value of the NAIA-IPT III
facility is nearer to US$408 million, given
the fact that Gleeds failed to recognize or ● Arup reports under seismic loading - less
include any values for design & other than 1% of all primary RC and composite
consultants (10%) or property inflation columns, around 3% of all primary RC
based on GRP schedules (15%)."251 beams, around 6% of all shear walls,
around 8% of piles (mostly at shearwalls)
3.b. Structural defects on the NAIA-IPT III and around 1% of mat footing locations.
Differential settlements are considered
insignificant to cause any additional
The Government contends that that the NAIA-IPT III distress in the buildings. Pounding
suffers from structural defects, as follows: between floors of adjacent sectors is not an
issue.
1. Failed structural elements of the NAIA-
IPT III, as identified in the Arup Seismic ● TCGI - extent not readily identifiable
Evaluation Report and Gravity Loading and from documents reviewed although within
Element Capacity Assessment; Section 2.0 of the TCGI July 2008 report it
states that the evaluation did not yield
2. The inferior quality of material used and results pointing to foundation instability as
works, including, for example, floor tiling, a cause for concern.
plasterboard wall finishes and ceilings, and
the internal and external metal paneling; 3.3.8 On the basis of discussion in 3.3.6 above it
would be reasonable to follow the assessment of the
3. The cost of seismic and gravity load original designer (Meinhardt) who also provided a
structural retrofits for the failed elements in Letter of Guarantee confirming the adequacy of their
the terminal buildings and multi-storey car design, (ref para 3.3.30).
park structures, as described in Arup's
Drawings listed in Appendix "B" Drawing He also disputed the Government's allegations that
List 2 and other rectification works required some portions of the NAIA-IPT III would not be able
to bring the Terminal to compliance with to sustain strong earthquakes and that some areas of
applicable building and airport codes as the NAIA-IPT III were built using materials with
indicated in the Appendices of Arup's Site inferior quality:
Observation Report; and

c. Seismic Activity (Terminal and Multi-


4. The cost of seismic and gravity load Storey Carpark)
structural retrofits for the failed elements in
the elevated roadway structures, as
described in Arup's Drawings listed in 3.3.12 It is understood from press reports
Appendix "B" Drawing List 3, Arup Review that, since substantial completion of the
on "TCGI Report of Civil Design Review and airport in 2002, Manila has been subjected
to a number of earthquakes. It has been
ProvRem Rule 67 Fulltext Page 57 of 119
reported that on25 March 2010 a strong 3.3.23 It would appear from the Arup
earthquake measuring 6.2 on the Richter documents reviewed that they have taken
scale hit Metro Manila according to the this approach in their assessment of design
government seismology institute. It was i.e., consideration of updated documents
further reported that in July 2010 "intense (NSCP 2001 and UBC 1997) whilst
seismic activity persists in the Philippines Meinhardt used the relevant codes at the
and Manila continues to be struck by time of design which was NSCP 1992.
moderate to strong earthquakes of 6.5 to Consequently any results from assessments
7.6 magnitude." We can find no record carried out to later published codes has no
relating to any damage being reported in direct bearing on the design of the facility
terms of the structure, finishes or services which was carried out prior to the issue of
associated with NAIA Terminal 3 as a result these later standards. As such any
of these occurrences. assessment and proposed
strengthening/retrofit works in this regard
xxxx is considered to be an enhancement of the
design and has no relevance on the value
of the NAIA Terminal 3 facility as
3.3.14 Inferior quality of materials used, for constructed under the original contract.
example internal finishes.

On the other hand, the relevant portions of the


3.3.15 Gleeds do (sic) not define exactly Tengson Report dated December 2010254 states:
what areas they mean by this. There is a
number of finished items where deductions
in excess of US$800,000 have been made In addition, we should note herein that
but the rational for the quantification of Takenaka's structural designer, Messrs.
the deduction is not explained. If the works Meinhardt, concluded that its check on the
were inferior to that specified then this structural ductility requirements (as
would be reflected in the payments made questioned by TCGI & Ove Arup) on
to Takenaka under the EPC contract. elements which do not resist lateral forces,
is in full compliance of the Philippine Code
NSCP 1992 and its originating design code
Scott Wilson likewise supported Takenaka and ACI-318 (1989), and this is supported by
Asahikosan position that the Government's experts several members of the American Concrete
examined the structural integrity of the NAIA-IPT III Institute (ACI). Both Takenaka and other
using the recent building codes, which were not yet parties (including Meinhardt and members
in place at the time the NAIA-IPT III was designed of the ACI), have concluded that TCGI &
and built. Ove Arup reports use several conflicting
and misunderstood mathematical models.
3.3.18 Seismic and gravity load retrofit and These include but are not limited to the
other rectification works required to bring following:
the building to compliance with applicable
building and airport codes.
(i) TCGI used larger loadings than
those specified in the "Design &
3.3.22 TCGI also provided an option titled Load Schedule Plan."
"A Government Prerogative" which states:
(ii) Their modeling for "sector 3"
Research in earthquake engineering has uses incorrect storey elevations
rapidly progressed to the extent that and the slab thickness did not
seismic design provisions for the design of match those on the "as built"
new buildings and procedures for the plans.
evaluation of existing ones have drastically
evolved. The current edition of the National (iii) Beam section sizes do not
Structural Code of the Philippines (NSCP) is match those shown on the "as
dated 2001, whereas Meinhardt used the built" plans.
1992 edition which was applicable at the
time the Terminal was designed.
(iv) TCGI used "Dynamic
Analysis" in their modeling,
There are new published guidelines for the whereas there is no requirement
structural safety assessment of existing for such an analysis in the
buildings from such organizations as the Philippine Structural Code -
Federal Emergency Management Agency NSCP 1992.
(FEMA) which have evolved into published
documents for the structural rehabilitation
of existing buildings. TCGI have therefore (v) TCGI & Ove Arup used the
suggested that MIAA and the Philippine updated NSCP 2001 (and
Government may wish to use the more UBC1997) Philipine Codes, yet
recent published documents to Takenaka's design was based
enhance/upgrade the facility. upon the NSCP 1992 code
because the 2001 updated was
ProvRem Rule 67 Fulltext Page 58 of 119
not available when the NAIA 3 habeas data, (7) anti-money laundering,
designs were completed in 2000. and (8) application for judicial
authorization under the Human Security
(vi) TCGI & Ove Arup reports Act of 2007;
were based upon a system which
incorporates frame beams and (b) In appeals in civil cases where the Court
columns as primary structural grants a new trial on the ground of newly
element, whereas the Takenaka discovered evidence, pursuant to Sec. 12,
design used a building frame Rule 53 of the Rules of Court;
system (Sheer Wall System). Two
differing design methods will (c) In appeals in criminal cases where the
lead to different results.255 Court grants a new trial on the ground of
newly discovered evidence, pursuant to
PIATCO also argued that it is not the sole entity Sec. 12, Rule 124 of the rules of Court; and
responsible for the completion of and/or compliance
with the outstanding items in the JAC project status (d) In appeals involving claims for damages
summary report dated February 28, 2003. The arising from provisional remedies.
summary report shows that some outstanding items (Emphasis supplied)
should be performed by the Government.256

This provision qualifies the CA's power to receive


While Scott Wilson stated that only retrofit works evidence in the exercise of its original and appellate
actually undertaken should be taken into jurisdiction under Section 9 of BP 129, as amended:
consideration in the valuation of the NAIA-IPT
III,257 Takenaka and Asahikosan insisted that
subsequent rectification works in the NAIA-IPT III Sec. 9. Jurisdiction. - The Court of Appeals shall
were only intended to ensure that the terminal would exercise:
be compliant with the current building laws and
standards.258 They reiterated that the design of the xxxx
NAIA-IPT III was compliant with the NSCP 1992, the
effective building code when the terminal was The Court of Appeals shall have the power to try
designed and built.259 cases and conduct hearings, receive evidence, and
perform any and all acts necessary to resolve factual
3.b.1. The Court cannot consider issues raised in cases falling within its original and
the additional evidence submitted appellate jurisdiction, including the power to grant
by Takenaka and Asahikosan and conduct new trials or further proceedings. Trials
before the Court of Appeals or hearings in the Court of Appeals must be
continuous and must be completed within three (3)
months, unless extended by the Chief Justice.
At the outset, we rule that we cannot consider
Takenaka and Asahikosan's attachments in their (1)
Motion for Submission of Additional Documents Since Takenaka and Asahikosan filed an ordinary
dated July 30, 2013;260 (2) Supplemental Motion for appeal pursuant to Rule 41 in relation to Rule 44 of
Submission of Additional Documents dated October the Rules of Court, the CA could only have admitted
3, 2012;261 and (3) Second Supplemental Motion for newly discovered evidence. Contrary to Takenaka and
Submission of Additional Documents dated April 11, Asahikosan's claim, the attachments to the motions
2013 in CA G.R. No. CV-98029.262 These attachments are not newly discovered evidence. Newly discovered
sought to refute the Government's position that the evidence is evidence that could not, with reasonable
NAIA-IPT III suffered from massive structural defects. diligence, have been discovered and produced at the
trial, and which, if presented, would probably alter
Takenaka and Asahikosan posit that they could have the result.263
submitted reports before the trial court to show that
the design of the NAIA-IPT III was structurally sound We find it hard to believe that Takenaka and
if the RTC had only furnished the parties copies of the Asahikosan could only have possibly secured the
BOC Final Report and afforded them the opportunity attachments after the trial court had rendered its
to file a Comment on decision. With the exercise of reasonable diligence,
Takenaka and Asahikosan could have produced these
the Final Report. documents before the BOC since they were fully
aware that the Government presented evidence on
the alleged structural defects of the NAIA-IPT III.
Under Section 3, Rule 6 of the Internal Rules of the
CA, the CA may receive evidence in the following
cases: In fact, in their Manifestation/Submission dated
November 3, 2009, Takenaka and Asahikosan
attached the "Report and Response from Takenaka &
(a) In actions falling within its original Asahikosan, Contactors for the NAIA 3 Facility and
jurisdiction, such as (1) certiorari, Intervenors in the Expropriation case between the
prohibition and mandamus, (2) annulment GRP and PIATCO - October 2009" to refute the
of judgment or final order, (3) quo allegations of structural defects. Moreover, Takenaka
warranto, (4) habeas corpus, (5) amparo, (6) and Asahikosan manifested that they were reserving
ProvRem Rule 67 Fulltext Page 59 of 119
their right to submit additional reports, comments, considered to be synonymous with the term "greater
and memoranda with respect to this issue. The weight of evidence" or "greater weight of credible
relevant portions of the Manifestation/Submission evidence."269
dated November 3, 2009 provides:
In determining where the preponderance of evidence
1. The record[s] of this case will show that or superior weight of evidence on the issues involved
to date, plaintiffs have submitted various lies, the court may consider all the facts and
reports prepared by TCGI Engineers, Ove circumstances of the case, the witness' manner of
Arup & Partners Massachusetts, Inc. and testifying, their intelligence, their means and
Gleeds (Bristol) Partnership to this opportunity of knowing the facts to which they are
Honorable Court. The TCGI and Ove Arup testifying, the nature of the facts to which they testify,
Reports point out alleged defects on the the probability of their testimony, their interest or
IPT 3, while Gleeds made an attempt to want of interest, and also their personal credibility in
establish the value of the IPT 3, taking into so far as the same may legitimately appear during
account the findings of the TCGI and Ove trial. The court may also consider the number of
Arup. Intervenors have not given their witnesses, although preponderance does not
comments on these reports since they have necessarily lie with the greater number.270
not been required to do so by this Court.
The Government's burden of proof to show that the
2. With the RTC's permission, intervenors NAIA-IPT III is indeed defective does not shift to its
respectfully submit the attached "Report adverse parties. The burden of proof remains
and Response from Takenaka & throughout the trial with the party upon whom it is
Asahikosan, Contactors for the NAIA 3 imposed.
Facility and Intervenors in the Expropriation
case between the GRP and PIATCO - It is the burden of evidence that shifts from party to
October 2009" prepared by Mr. Gary party during trial.271 This means that the burden of
Taylor, in response to the above mentioned going forward with the evidence is met by the
reports. Intervenors respectfully manifest countervailing evidence of PIATCO, Takenaka and
that they are reserving their right to submit Asahikosan which, in turn, balances the evidence
additional reports, comments and introduced by the Government. Thereafter, the
memoranda in support of this submission burden of evidence shifts back to the Government.
and to aid this Honorable Court in
determining the true value of the IPT 3.264
(Emphasis supplied) In the present case, the experts and consultants of
the Government, PIATCO, Takenaka and Asahikosa
arrived at conflicting findings regarding the structural
3.b.2. Equiponderance of evidence on the alleged integrity of the NAIA-IPT III. The Government's
structural defects of the NAIA-IPT III favors PIATCO, experts detailed with particularity the alleged defects
Takenaka and Asahikosan. Nonetheless, even without of the NAIA-IPT III, which allegations the experts of
considering and/or giving probative value to the PIATCO, Takenaka and Asahikosan refuted with
additional evidence presented by Takenaka and particularity.
Asahikosan before the CA, this Court finds that the
Government failed to establish by preponderance of
evidence that the NAIA-IPT III suffered from structural Under the equiponderance of evidence rule, when
defects. the scale of justice shall stand on equipoise and
nothing in the evidence inclines a conclusion to one
side or the other, the court will find for the
Under Section 3, Rule 131 of the Rules of Court, it is defendant.272
presumed that a person is innocent of wrong;265 that
a person takes ordinary care of his concerns;266 that
private transactions have been fair and regular;267 and If the facts and circumstances are capable of two or
that the ordinary course of business has been more explanations, one of which is consistent with
followed.268 the allegations of the plaintiff and the other
consistent with the defense of the defendant, the
evidence does not fulfill the requirement of
Based on these presumptions, we presume that preponderance of evidence. When the evidence of
Takenaka and Asahikosan built the NAIA-IPT III in the parties is in equipoise, or when there is a doubt
accordance with the specifications required under the as to where the preponderance of evidence lies, the
Onshore Construction Contract and Offshore party with the burden of proof fails.273
Procurement Contract. We also presume that the
NAIA-IPT III is structurally sound and compliant with
the applicable building codes and other laws at the The reason for this rule is that the plaintiff must rely
time it was designed and built. However, these on the strength of his evidence and not on the
presumptions are merely disputable presumptions weakness of the defendant's claim. Thus, even if the
and may be overcome by contradicting evidence. The evidence of the plaintiff may be stronger than that of
burden of proof lies with the Government to prove by the defendant, there is no preponderance of
preponderance of evidence that the NAIAIPT III evidence on his side when this evidence is insufficient
in itself to establish his cause of action.274
suffered from structural defects. "Preponderance of
evidence" is the weight, credit, and value of the
aggregate evidence on either side and is usually

ProvRem Rule 67 Fulltext Page 60 of 119


In the present case, PIATCO, Takenaka and On August 14, 2012, the DOTC invited construction
Asahikosan, met the Government's allegations firms to participate in the ₱212.3 million NAIA-IPT III
regarding the structural integrity of the NAIA-IPT III. structural retrofit project. The structural retrofit of the
NAIA-IPT III that was offered for bidding had eleven
A reading of the reports of the parties' respective components: shear wall thickening; slab thickening;
experts shows that each party presented an equally application of FRPs to columns, beams and slabs;
persuasive case regarding the structural soundness or thickening of flat slab drop; enlarging of column size;
defect of the NAIA-IPTIII. The Government's case on enlarging pile cap and footings; steel jacketing;
the alleged structural defect of the NAIA-IPT III has providing shear blocks to pier headstock (elevated
been met by equally persuasive refutations by the access roadway); enlarging of pier footings (elevated
experts of PIATCO, Takenaka and Asahikosan. access roadway); application of FRP to piers (elevated
access roadway); and increasing seismic gap between
the elevated access roadway and adjacent structures
As a matter of law and evidence, the Government's (sector 1, 2, car park).279 The Official Gazette further
case regarding this matter must fail. Since PIATCO, stated:
Takenaka and Asahikosan presented equally relevant
and sufficient countervailing evidence on the
structural soundness of the NAIA-IPT III, the scales of Shear wall thickening is meant to fortify the
justice tilt in their favor. Neither party successfully reinforced concrete wall to increase its capacity
established a case by preponderance of evidence in against horizontal structure movement. At the same
its favor; neither side was able to establish its cause time, thickened slabs will increase their bending
of action and prevail with the evidence it had. As a capacity and resistance against heavy superimposed
consequence, we can only leave them as they are.275 loadings.

We thus add to the construction cost the sum of Applying fiber-reinforced polymer (FRP) to columns,
$20,713,901, itemized below:276 beams, and slabs will increase their strength and
resistance against excess loads and combined forces
of elements. A thicker flat slab drop is meant to
Item In Dollars strengthen the slab-column connection.

Surface demolition 1,971,500


Bigger -sized columns will also increase their capacity
Structural retrofit 6,860,660 against combined stresses, while enlarged pile cap
and footings will increase foundation capacity under
Elevated road 2,443,276 compression. They also prevent movement of the
foundation during earthquakes.
Miscellaneous
Steel jacketing is meant to resist the additional loads.
Alarms 154,460
Shear blocks to pier headstock will provide a bridge
Defective Ceiling 479,626 interlock is meant to distribute excess load along the
carriage way.
CUTE not working 2,774,563
Enlarged pier footings will prevent foundation
Inferior FIDS 22,020
overturning during earthquake events.
BHS Inferior Screening Software 957,881
Application of FRP to piers will also increase the
Fire Protection Inferior coverage 924,851 column capacity and ductility against combined
stresses due to earthquake forces.
Civil and HV

Apron Civil 829,619 Increased seismic gap between the elevated access
roadway and adjacent structures will reduce the risk
Taxiway Civil 439,280 of pounding between the bridge and building
structure.280
Storm Water 2,604,081

HV 252,084 However, no documents regarding the retrofit project


exist as part of the record of the case. The retrofit bid
Total 20,713,901 took place in 2012, or after the promulgation of the
trial court's ruling. Hence, we have to disregard
Government claims pertaining to the retrofit project.
Admittedly, the Government did not open to the
public certain areas of the NAIA-IPT III because of
3.c. The unnecessary areas
uncertainties on their structural integrity.277 The Scott
Wilson Report also recognized that some retrofit
works should also be undertaken in some of the Gleeds excluded "unnecessary areas" from the
areas of the NAIA-IPT III. It stated that only retrofit computation of the base value. These unnecessary
works actually undertaken in the building should be areas are the multi-level retail mall that is accessible
taken into consideration in appraising the NAIA-IPT only through the multi-storey car park (20,465 m2),
III.278 and the excess retail concession space(1,727 m2).281

ProvRem Rule 67 Fulltext Page 61 of 119


We find the exclusion of the unnecessary areas from US$7.9 million to the QA Inspectors (JAC) and US$4.2 million to PCI, SOM,
the base value unjustified. Since the Government PACICON and JGC and this therefore appears not reasonable.
would expropriate the entire NAIA-IPT III, the
Government should pay for the replacement cost of 3.1.18 In summary, PIATCO have paid the following consultancy fees:
the retail mall and the excess retail concession space.
The Government cannot avoid payment simply
because it deems the retail mall and the retail ● Planning and design consultancy fees US$19.3 million
concession space as unnecessary in its operation of preconstruction
the NAIA-IPT III. To reiterate, the measure of just
compensation is not the taker's gain, but the owner's ● QA Inspectors US$7.9 Million
loss.282
● Construction supervision US$4.2 Million

Consequently, we include in the computation of Total US$31.4 million


construction costs the excess concession space in the
amount of $1,081,272.00, and the four-level retail
complex in the sum of $12,809,485.00.283 3.1.19 In our opinion these fees are in reasonable range.

4. Attendant costs of the NAIA-IPT III Site Preparation Costs

Scott Wilson criticized the Gleeds Report for excluding the attendant 3.1.20 We understand that PIATCO has incurred costs of US$10.3 million
costs in the construction cost valuation. He stated: for relocation of PAF existing facilities, removal of subterranean structures
and site preparation which the Gleeds Base Case CCV has not included.
3.1.13 Gleeds do (sic) not show any costs for planning and design
consultancy fees preconstruction. In our experience the following Legal Costs
percentage ranges of the construction cost would typically be the
international norms for these fees. 3.1.21 We assume that in addition to the above fees PIATCO has incurred
legal costs in planning and constructing the development and this is quite
● Attendant Costs Percentage Range normal on BOT concession contracts where contract agreements and
responsibilities have to be agreed between a number of different parties.
● Architecture 3.0 to 4.0 %
Overall Summary
● Civil and Structural 1.0 to 4.0 %
3.1.21 PIATCO has incurred consultancy fees and site preparation
costs of US$41.7 million (US$31.4 plusUS$10.3 million) not included
● Electrical and Mechanical 2.5 to 3.5 %
by Gleeds in the Base Case CCV.284

● Quantity Surveyor 1.0 %


In response, Tim Lunt asserted that its CCV of US$300,206,693.00 already
includes the attendant costs of US$36,279,033 under the heading
● Project Management 1.0 % "General Requirements and Conditions." The sum of US$36,279,033
represents the General Requirements Section of the Takenaka Bill of
Total 8.5 to 11.5 % Quantities. The "General Requirements and Conditions" is composed of
engineering and architectural services fees, quality assurance services
3.1.14 On the basis of a construction cost valuation of the order of fees, construction supervision services fees, construction insurance, and
US$322 million we would expect planning and design consultancy fees site. Tim Lunt, however, admitted that the "General Requirements and
preconstruction to be a minimum of US$27 million, based on typical Conditions" exclude financing costs, and other associated costs. He
international norms. likewise stated that PIATCO's attendant costs have no evidentiary support.

3.1.15 Some preliminary design was carried out by Takenaka prior to the On December 14, 2010, PIATCO attached to its Compliance documentary
EPC tender design so slight lower planning and design consultancy fees evidence of its claimed attendant costs of US$70,197,802.00. These
could be expected. It is understood that PIATCO have paid US$19.3 include photocopies of summary of payments for architecture &
million to the designers PCI, SOM, PACICON and JGC (architect of record) engineering, quality assurance, construction supervision, construction
and this therefore appears a fair and reasonable fee. insurance, site development, other costs and financing costs, official
receipts, statements of account, sales invoices, endorsements, insurance
policies and other related documents, acknowledgement receipts,
3.1.16. In addition there is also the cost of site supervision. In this case agreements, invoices, and bonds.
there was the independent QA role undertaken by Japan Airport
Consultants and construction supervision by PCI. It is noted that the Bid
Document suggested that up to 3% of the construction cost should be PIATCO claims that the following entities rendered services in the
allowed for the independent QA role. In our experience we would expect construction of the NAIA-IPT III:
QA and construction supervision to cost between 3% and 5% of the
construction cost.
Services Rendered Entities that Rendered the
Services
3.1.17 On the basis of a construction cost valuation of the order of
US$322 million we would expect the cost of construction supervision to Engineering and Architecture Pacific Consultants International
be a minimum of US$9.5 million. It is understood that PIATCO have paid Asia, Inc. Pacicon Philippines, Inc.
Architect J. G. Cheng RMJM

ProvRem Rule 67 Fulltext Page 62 of 119


finding that the "General Requirements and Conditions" in the Gleeds'
Philippines, Inc.
Appraisal Report constitutes the attendant costs. The CA stated that there
Quality Assurance Japan Airport Consultants I.A. is no need to further recognize and award separate attendant costs
Campbell & Associates because these were already included in the construction cost valuation of
US$300,206,693.00. The CA explained that the attendant cost becomes
Construction Supervision Pacific Consultants International part of the total construction cost once the construction is completed.285
Asia, Inc.
4.a. PIATCO's attendant costs
Construction Insurance Gotuaco del Rosario

Site Development Bases Conversion Development Under the best evidence rule, when the subject of inquiry relates to the
Corporation Skidmore, Owings & contents of a document, no evidence shall be admissible other than the
Merrill Pacific Consultants original document itself. In proving the terms of a written document, the
International Asia, Inc. Natural original of the document must be produced in court.
Resource Development Corporation
Serclan Enterprises Geodesy The best evidence rule ensures that the exact contents of a document are
Services, Inc. Geotechnics brought before the court. In deeds, wills, and contracts, a slight variation
Philippines, Inc. Revalu in words may mean a great difference in the rights and obligations of the
Constructions & Supply N.O. parties. A substantial hazard of inaccuracy exists in the human process of
Mercado Construction, Inc. Lopez making a copy by handwriting or typewriting. Moreover, with respect to
Drilling Enterprises Monark oral testimony purporting to give the terms of a document from memory,
Constructions Illustrious Security a special risk of error is present, greater than in the case of attempts at
and Investigation Agency, Inc. Core describing other situations generally.286
Watchmen, Security and Detective
Agency Corp.
The best evidence rule likewise acts as an insurance against fraud. If a
Other Services Laguna Lake Development party is in the possession of the best evidence and withholds it, and seeks
Authority National to substitute inferior evidence in its place, the presumption naturally
Telecommunications Commission arises that the better evidence is withheld for fraudulent purposes that its
Prudential Guarantee and production would expose and defeat. The rule likewise protects against
Assurance, Inc. Manila Electric misleading inferences resulting from the intentional or unintentional
Company, Inc. Maynilad Philippine introduction of selected portions of a larger set of writings.287
Long Distance
Telecommunications, Inc. Myrtle As exceptions to the best evidence rule, Section 3, Rule 130 of the Rules
Intergen Exchange Corp. of Court provides that non-original documents may be produced in court
in the following cases:
Financing Services Dresdner / Kfw / Helaba Banks
Fraport AG/FAG Deutsche Bank
(a) When the original has been lost or destroyed, or cannot be
produced in court, without bad faith on the part of the offeror;
Reyes Tacandong & Co. checked the mathematical accuracy of the
attendant costs. PIATCO asserts that it engaged the services of various (b) When the original is in the custody or under control of the
consultants in the construction of the NAIA-IPT III and incurred the party against whom the evidence is offered, and the latter fails
following attendant costs: to produce it after reasonable notice;

Attendant Costs Amount (c) When the original consists of numerous accounts or other
documents which cannot be examined in court without great
Engineering and Architecture US$19,372,539 loss of time and the fact sought to be established from them is
only the general result of the whole; and
Quality Assurance US$6,923,720

Construction Supervision US$4,302,227 (d) When the original is a public record in the custody of a
public officer or is recorded in a public office. (Emphasis
Construction Insurance US$4,329,272 supplied)

Site Development US$8,358,169


Secondary evidence of the contents of writings is admitted on the theory
that the original cannot be produced by the party who offers the evidence
Other Costs US$ 308,985
within a reasonable time by the exercise of reasonable diligence.288
Financing Costs US$26,602,890
PIATCO argues that its non-submission of original documents before the
Total US$70,197,802 trial court is justified under Section 3 (c), Rule 130 of the Rules of Court. It
points out that a party need not submit the original when it consists of
numerous accounts or other documents which cannot be examined in
The BOC, the RTC, and the CA uniformly found that PIATCO failed to
court without great loss of time and the fact sought to be established
substantiate its attendant costs. The CA observed that PIATCO's
from them is only the general result of the whole. PIATCO insists that the
summarized computation of attendant costs was self-serving and
lower courts erred in not giving probative value to the report prepared by
unsupported by relevant evidence.
Reyes Tacandong & Co., an auditing firm, validating PIATCO's
computation of attendant costs. Significantly, Reyes Tacandong & Co.
Unlike the BOC and the RTC which pegged the attendant cost at 10% of failed to state that it examined the original documents in validating
the construction cost as an accepted industry practice, the CA made a PIATCO's computation of attendant costs.
ProvRem Rule 67 Fulltext Page 63 of 119
We agree with PIATCO that it need not submit numerous and voluminous Rule 130 of the Rules of Court by merely invoking Section 3 (c), Rule 130
invoices, official receipts, and other relevant documents before the trial of the Rules of Court.
court to prove the attendant costs that it incurred in the construction of
the NAIA-IPT III. The trial court may admit a summary of voluminous In the present case, PIATCO attached to its Compliance dated December
original documents, in lieu of original documents, if the party has shown 14, 2010, the photocopies of numerous documents, and the validation of
that the underlying writings are numerous and that an in-court PIATCO's computation of attendant costs prepared by Reyes Tacandong
examination of these documents would be inconvenient. In other words, & Co., among others. PIATCO justifies the non-presentment of original
Section 3 (c), Rule 130 of the Rules of Court does away with the item-by- documents pursuant to Section 3 (c), Rule 130 of the Rules of Court.
item court identification and authentication of voluminous exhibits which
would only be burdensome and tedious for the parties and the court.
We affirm the lower courts' uniform findings that PIATCO failed to
establish its attendant costs. PIATCO failed to establish that the
However, as a condition precedent to the admission of a summary of photocopied documents fall under Section 3 (a), (b), and/or (d), Rule 130
numerous documents, the proponent must lay a proper foundation for of the Rules of Court. These photocopied documents are hearsay
the admission of the original documents on which the summary is based. evidence. They are mere scraps of paper and have no weight as basis for
The proponent must prove that the source documents being summarized the attendant costs of the NAIA-IPT III. We likewise cannot give weight to
are also admissible if presented in court.289 the summary prepared by Reyes Tacandong & Co. for being double
hearsay. Reyes Tacandong & Co., whose letter was addressed to PIATCO
In concrete terms, the source documents must be shown to be original, and not to the trial court, did not state in its report that it examined the
and not secondary. Furthermore, the source documents must likewise be original documents allegedly proving attendant costs. Moreover, in a
accessible to the opposing party so that the correctness of the summary letter dated December 14, 2010, Reyes Tacandong & Co stated it does
of the voluminous records may be tested on cross-examination and/or not "express any assurance on the attendant costs:"
may be refuted in pleadings. In ordinary trial-type proceedings, a proper
foundation for the introduction of a summary may be established through We have performed the procedures agreed with Philippine International
the "testimony of the person who is responsible for the summary's Air Terminals, Co., ("the Company") with respect to the Company's
preparation, or the person who supervised the preparation of the attendant costs incurred in building NAIA Terminal 3 from 1997 to 2004.
summary."290 Our engagement was undertaken in accordance with the Philippine
Standard on Related Services applicable to agreed-upon procedures
The primary reason for these procedural foundations is that the summary engagements.
of numerous documents is, in strict terms, hearsay evidence. The trial
court should not haphazardly allow a party to present a summary of xxxx
numerous documents and immediately admit and give probative value to
such summary without sufficiently laying these foundations. If the source
documents of the summary are non-original, the trial court would commit The sufficiency of the procedures is solely the responsibility of the
a grave error in admitting and/or giving probative value to the summary specified users of the report. Consequently, we make no representation
of non-original documents; the evidence admitted would be double regarding the sufficiency of the procedures either for the purpose for
hearsay.291 which this report has been requested or for any other purpose.

Furthermore, when a party invokes Section 3 (c), Rule 130 of the Rules of Because the procedures do not constitute either an audit or a review of
Court, he does not similarly invoke Section 3 (a), (b), and/or (d), Rule 130 financial statements made in accordance with Philippine Standards on
of the Rules of Court. He does not likewise claim that the original Auditing, we do not express any assurance on the attendant costs.
(Emphasis supplied)
documents have been lost or destroyed. The party merely asserts that the
numerous documents cannot be examined in court without great loss of
time and that the fact sought to be established from these documents is 4.b. The BOC and the RTC's
only the general result of the whole. Whenever a party seeks an attendant cost
exemption under the best evidence rule pursuant to Section 3 (c), Rule
130 of the Rules of Court, he asks permission from the trial court to The CA correctly disregarded the BOC and the RTC's computation of
produce a summary of numerous documents, whose originals are attendant costs, which both pegged the attendant cost at 10% of the
available to the adverse party for inspection. He does not ask permission construction cost. The BOC and the RTC relied on the mean percentage
from the trial court to present in evidence the numerous non-original range of attendant cost which appears in the Scott Wilson Report as
documents. Otherwise, the very purpose of Section 3 (c), Rule 130 of the follows:292
Rules of Court would be defeated. In that case, every exhibit of non-
original documents would be identified, authenticated, and cross-
examined, leading to a tedious and protracted litigation. Attendant Costs Percentage Range

Architecture 3.0 to 4.0 %


Thus, if a party desires to present photocopies of the original documents,
he must first establish that the presentation of photocopies is justified Civil and Structural 1.0 to 4.0 %
under Section 3 (a), (b), and/or (d), Rule 130 of the Rules of Court. He
must establish the presence of all the elements under these provisions. In Electrical and Mechanical 2.5 to 3.5 %
the case of lost or destroyed documents, the offeror of non-original
documents must first prove the following elements before secondary Quantity Surveyor 1.0 %
evidence is admitted before the court: (a) the existence or due execution
of the original; (b) the loss and destruction of the original, or the reason Project Management 1.0 %
for its non-production in court; and (c) the absence of bad faith on the
Total 8.5 to 11.5 %
part of the offeror to which the unavailability of the original can be
attributed. To conclude otherwise is to allow the party to circumvent the
best evidence rule and the requirements under Section 3 (a), (b), and (d), The BOC and the RTC computed the mean percentage range by adding
8.5% and 11.5% and dividing the result by 2, thus:

ProvRem Rule 67 Fulltext Page 64 of 119


(8.5 + 11.5)/2 = 10% Takenaka Bills of Quantities nor do they use them as documents which
they have reviewed in paragraph 1.4.1 of their report. I do not understand
The mean percentage range is highly speculative and devoid of any how Scott Wilson can ignore the items which are included in the Bills of
factual basis. As a court of law, we should only measure just Quantities under the heading General Requirements and make the
compensation using relevant and actual evidence as basis in fixing the suggestion that they are additional costs which should be considered.
value of the condemned property. Just compensation must be duly
proven by preponderance of evidence or greater weight of credible xxxx
evidence.293 Bare allegations, unsubstantiated by evidence, are not
equivalent to proof.294 36. In respect of the Engineering Consultancy Fees set out by Scott
Wilson, it is clear to me on inspection of the General Requirements
In a case for damages, we allow the party to receive temperate damages section of the On shore and Off shore Bills of Quantities that an element
in the absence of competent proof on the amount of actual damages. of design fees included as Costs has also been included in the CCVs and
Temperate or moderate damages, which are more than nominal but less should not therefore be included as an addition. Scott Wilson has not
than compensatory damages, may be recovered when the court finds that provided any specific information on the actual cost or extent of service
some pecuniary loss has been suffered but its amount cannot, from the provided in respect of engineering consultancy.
nature of the case, be proved with certainty.295
xxxx
We cannot adopt the same liberal attitude in an eminent domain case and
merely estimate the attendant cost in the total absence of evidence of 39. The cost associated with the Independent QA role referred to by Scott
construction costs. The amount of just compensation must be Wilson is included in the General Requirements section of the
substantiated by a preponderance of evidence. CCV.(Emphasis supplied)

An eminent domain case is different from a complaint for damages. A The Government's CCV already includes attendant costs which are
complaint for damages is based on tort and emanates from the incorporated in the "General Requirements and Conditions." On the basis
transgression of a right. A complaint for damages seeks to vindicate a of the Bills of Quantities, Gleeds took into account indirect costs in
legal wrong through damages, which may be actual, moral, nominal, constructing the NAIA-IPT III, summarized below:
temperate, liquidated, or exemplary. When a right is exercised in a
manner not conformable with Article 19 of the Civil Code and other
provisions on human relations in the Civil Code, and the exercise results in Attendant Costs under General Requirements and Conditions
the damage of another, a legal wrong is committed and the wrongdoer is
held responsible.296 Design $6,439,680.00297

Staff and labour $10,491,139.54298


In contrast, an eminent domain case arises from the State's exercise of its
power to expropriate private property for public use. The Constitution Insurance $925,210.78299
mandates that the property owner shall only receive just compensation
which, of course, should be based on preponderance of evidence. Professional Indemnity Insurance $2,200,000.00300
Moreover, the determination of eminent domain being a judicial function,
there is no constitutional or statutory provision giving the courts Consequential Loss Insurance $800,000.00301
unfettered discretion to determine just compensation based on estimates
Setting out $364,647.00302
and conjectures.
Health and Safety $403,224.00303
4.c. The Government's attendant cost
Environmental management $176,490.00304
We affirm the CA's factual finding that the Government's computation of Design $2,631,100.00305
construction cost valuation already includes the attendant costs. In the
Gleeds Report dated December 22, 2010, Tim Lunt sufficiently explained: Staff and labour $2,590,774.19306

Insurance $71,109.77307
9. I consider that Engineering and Architecture, Quality Assurance,
Construction Supervision, Construction Insurance and Site Development
Total $27,093,375.28
are clearly costs which are included for in the CCV. The CCV includes costs
associated with the General Requirements (see Appendix D - Summary).
The costs of Site Development are also included (see CCV Appendix D - 5. Deductions from the replacement cost of the NAIA-IPT III
Part 2, page 5 of 38).
5.a. Depreciation should be
xxxx deducted from the replacement
cost.
25. Scott Wilson states at paragraph 2.2.14 that the constructions costs
"are exclusive of all other attendant costs, such as the engineering and In eminent domain cases, it is acceptable that a "deduction should be
architectural services fees, quality assurance services fees, construction made to the extent to which the improvement or fixture has depreciated.
supervision services fees, construction insurance, site development costs, The cost of the buildings and fixtures, minus depreciation, is a reasonable
financing costs and other associated costs." This statement is incorrect. It test of the amount by which they enhance the market value of the land
is clear on the inspection of the General Requirements sections of the even where the market value of the land itself is not readily
Takenaka Bills of Quantities that some if not all of these items are quantifiable."308
included in the assessment of the construction costs made by PIATCO
with the exception of 1) financing costs and 2) other associated costs, for
which there is no definition. Scott Wilson makes no reference to the
ProvRem Rule 67 Fulltext Page 65 of 119
In order for this Court to arrive at a valid indication of the market value of 3.2.10 A depreciation value has been assessed at $USD35,076,294 in 3Q01
the NAIA-IPT III, we must consider accrued depreciation, which is the loss Manila prices. Calculation of this amount showing the various asset lives
in value of the terminal. assumed is included in Appendix "J."

Contrary to the CA's position, "depreciation" is used in different contexts 3.2.11 Based on the deductions for deterioration and depreciation
in valuation and financial accounting. As earlier discussed, in appraisal, between December 2002 and December 2004, the Base Value CCV at the
depreciation "refers to the reduction or writing down of the cost of a time of expropriation is $USD263,392,081.320
modern equivalent asset to reflect the obsolescence and relative
disabilities affecting the actual asset"309 or "loss in value from any In the Scott Wilson report, he stated:
cause."310 It is further defined as "the reduction or writing down of the
cost of a modern equivalent asset to reflect the obsolescence and relative
disabilities affecting the actual asset."311 3.7.1 We consider the question of depreciation in this instance to be a
financial and legal issue which has to be dealt with in accordance with
Philippine law.
In contrast, depreciation in accounting refers to "a charge made against
an entity's income to reflect the consumption of an asset over a particular
accounting period."312 It is the "process of allocating to expense the cost 3.7.2 We therefore do not feel qualified to comment on the legal issue
of a plant asset over its useful (service) life in a rational and systematic except that we do not understand how deterioration in section 3.6 and
manner."313 Accumulated depreciation is reported as a deduction from depreciation can both be applied as surely this means that Gleeds (sic)
plant assets and affects the income statement through depreciation have double counted the effect of any deterioration. (emphasis
expenses. Thus, the cost allocation is designed to match expenses with supplied)321
revenues.
In response, Tim Lunt argued:
In financial accounting, "depreciation is a process of cost allocation, not a
process of asset valuation. No attempt is made to measure the change in 14. With respect to PIATCO's hypothetical inclusion of inflation, I do not
an asset's market value during ownership because" it is assumed that consider that inflation should be applied to the base value as the
plant assets are not held for resale.314 Book depreciation refers to "the replacement cost method establishes the cost of construction when
amount of capital recapture written off an owner's books"; it is not market completed in December 2002.
derived.315 Thus, the book value - original cost less accumulated
depreciation - of an asset may be different from the market value. 15. The base values included in the CCVs are the same for the December
2002 and December 2004. The December 2004 base value is not adjusted
Consequently, an asset can have zero book value but still have a to account for inflation because the items which make up the construction
significant market value.316 of NAIA3, i.e., the labour, plant, materials, systems and equipment
installed should not be paid for at a higher rate (that takes into account
Simply put, book depreciation is measured against the book value or inflation) than the rate which would have been paid when they were
original cost of the property and is the amount of capital recapture purchased at the earlier date. Put simply, it makes no sense to apply
written off an owner's books.317 Accrued depreciation is measured against December 2004 prices to items bought and used in the construction of
the current market value of the property.318 NAIA3 sometime between June 2000 and December 2002.

Under the depreciated replacement cost method, accrued depreciation is 16. PIATCO do (sic) not consider depreciation. Having explained above
the difference between the "replacement cost of the improvements on why inflation should not be included, it is the application of a similar logic
the effective date of the appraisal and the market value of the which demonstrates why depreciation should be included. In the case of
improvements on the same date."319 NAIA3 the materials, systems and equipment installed are at least two
years older as at December 2004 than at the time they were incorporated
into the construction of NAIA3. Their value should therefore be less. The
In the Gleeds Report, Tim Lunt stated: method used for assessing this reduced value is that of depreciation.322

Deterioration 66. Scott Wilson provide a "Summary of Conclusions on deductions at


section 3.11 and my responses to each of the items contained in their
3.2.7 The Arup Site Observation Report identifies a number of items which "comment" column are as follows:
have deteriorated since suspension of the construction of Terminal 3 in
December 2002. xxxx

3.2.8 A provisional value has been assessed against the items identified in ● Deterioration - "Major deduction for baggage system not
the Arup report at $1,738,318. justified" - The deterioration in the baggage systems is clearly
set out in the Arup (and Gensler) Site Observation Report dated
The deterioration items have been costed with a base date of 2Q09. August 2007, at section 9.2. The cost deduction is set out in
Calculation of this amount is contained in Appendix 'E.' Further Appendix to the previous CCV report which Scott Wilson do
examination and costing of each of the identified items are required and, (sic) not appear to have reviewed.
therefore, the costs of these items will require adjustment based on the
actual date when the rectification works are carried out. ● Depreciation - Scott Wilson states" This issue appears to be a
legal issue and should be commented on by legal expert" and
Depreciation offers no technical or cost related comments relevant to the
CCV.
3.2.0 An Assessment has been made of the depreciated value of the
assets from December 2002 when construction was suspended to On the other hand, Gary Taylor commented:
December 2004 when Terminal 3 was expropriated by the Republic.
ProvRem Rule 67 Fulltext Page 66 of 119
Gleeds have (sic) assessed a depreciation value of US$35,076,294 (11.68%) specifications in the Bid Documents precisely because the concession
to conclude its 4Q04 value. This concept of depreciation is contrary to the agreement between PIATCO and the Government had already been
GRP's own statistics which shows a Consumer Price Index for Manila nullified. The Government cannot complain of contract noncompliance in
("CPI") increase from107.8 (Aug 01) to 125.1 (Nov. 04), a 16% increase an eminent domain case, whose cause of action is not based on a breach
over the period. The CPI is a conglomerate of all consumer prices in the of contract, but on the peremptory power of the State to take private
Manila region and includes property values and is published by the GRP property for public use.
on a monthly basis. In assessing such a depreciation value, Gleeds have
(sic) taken an arbitrary life cycle of the building and assumed a write off of Consequently, deductions from the base value of the cost of
asset over that period, then assessed the two (2) year depreciation over noncompliance with bid documents as well as inferior quality items have
the period 3Q01 to 4Q04. Whilst we acknowledge that an airport terminal no legal basis. Gleeds' reliance on the NAIA-IPT III bid documents is
building is something of a specialized asset and appreciation of value is misplaced.
not always in line with the area's general value assessments, it is still a
major structure and appreciation before depreciation (which should be
limited to equipment and fittings within the building) should not be As Scott Wilson correctly pointed out, the decisive factor of the
discounted. The concept of long term value of an asset on a similar deductibility of items under "noncompliance with bid documents" is
concept is proven out by NAIA Terminal 1, which since its construction whether they are functional. The Scott Wilson report shows that, except
more than 30 years ago has maintained a value to this date.323 for the nonprovision of moving walkway, the alleged noncompliant items
are functional.327 Also, the nonprovision of a moving walkway should not
be deducted from the base value. The only consequence of the failure to
We uphold the Government's computed extent of deterioration and provide a moving walkway is the need to construct one, which would only
depreciation. In the Reply to Tengson International Ltd. Report and increase the construction cost.328 The increase in the construction cost,
Response from Takenaka and Asahikosan dated December 7, 2010, Tim however, should not be included as part of just compensation as this
Lunt explained that "[t]he asset lives are taken specifically from experience Court is
in preparing Asset Revaluations for Airport properties which are used as
an input for annual published accounts, which are in turn audited by
appointed Accountants."324 Takenaka and Asahikosan should have only tasked to determine the construction cost of the NAIA-IPT III as of
provided for contrary assumptions with respect to the useful lives of the December 21, 2004.
subject assets if they did not agree with the Government's assumptions.
Instead, Gary Taylor merely referred to the valuation of the NAIA Terminal For these same reasons, we cannot allow the deduction in the amount of
I without any factual basis to support his claim. Moreover, Scott Wilson $75,570,510.00 "additional areas to be built." These are "areas where the
did not question the assumed useful life of the NAIA-IPT III, but agreed minimum requirements stated in the Bid Documents have not been met
that the question of whether depreciation should be deducted is a legal and are necessary for the operation" of the NAIA-IPT III. These areas
issue. include:

Since PIATCO, Takenaka, and Asahikosan failed to present contrary ● Departure hall 22,462 m2
assumptions or estimates with respect to the NAIA-IPT III's useful life, we
adopt Tim Lunt's computations with respect to deterioration and ● Meeter/greeter hall 14,696 m2
depreciation.

● Ramp operations 13,640 m2


5.b. Rectification for contract
compliance should not be
● Offices 4,370 m2
deducted from the replacement
cost.
● Hold rooms 3,729 m2
However, we hold that the cost for "rectification for contract compliance"
should not be deducted from the base value, as the contract, being void, ● Public toilets 2,351 m2
cannot be ratified.325
● Hardstand hold rooms 1,442 m2
In the present case, the Court already nullified the PIATCO contracts for
being contrary to public policy in Agan. A substantial amendment to a ● Delayed flight restaurant 620 m2329
contract awarded through public bidding, when such subsequent
amendment was made without a new public bidding, is null and void. The
6. Adjustments to the Replacement Cost
PIATCO contracts contain material and substantial amendments that
substantially departed from the bidded contract. If at all, the declaration
of nullity of a contract only operates to restore things to their state and 6.a. The replacement cost
condition before the contract's execution.326 should be adjusted to
December 2004 values.
Moreover, Takenaka and Asahikosan, as subcontractors in the NAIA- IPT
III project, were not bound by the nullified PIATCO contracts. Takenaka Gleeds used the Principle Quantities approach in determining the gross
and Asahikosan were only bound to perform their contractual obligations replacement cost of the NAIA-IPT III.330Gleeds calculated the cost of
under the Onshore Construction Contract and Offshore Procurement construction based on the midpoint between June 2000 and December
Contract, respectively. They were not bound by the nullified PIATCO 2002 to arrive at the December 2002 CCV. According to Gleeds, the cost
contracts. of construction based on its midpoint or the third quarter of 2001 is a
recognized standard practice in the construction industry.331
If there had indeed been variations from the Onshore Construction
Contract and Offshore Procurement Contract, the cause of action for Gleeds did not adjust the base valuation of $300,206,693.00 as of
breach of contract and damages lies with PIATCO. For purposes of December 2002 to reflect the current gross replacement cost as of
determining just compensation, the Government cannot rely on the December 2004. It merely assumed that the gross replacement cost as of

ProvRem Rule 67 Fulltext Page 67 of 119


December 2002 is the same as the gross replacement cost as of of works in the NAIA-IPT III until December 21, 2004, or the date when the
December 2004. It stated that it did not consider inflation in determining Government filed the expropriation complaint.337
the base valuation of the NAIA-IPT III as of December 2004:
7. Interests, Fruits and Income
14. With respect to PIATCO's hypothetical inclusion of inflation, I do not
consider that inflation should be applied to the base value as the 7.a. Computation of Interests
replacement cost method establishes the cost of construction when
completed in December 2002.
To avoid confusion in computing interests, we first distinguish three
interrelated concepts in just compensation: (1) the valuation period of just
15. The base values included in the CCVs are the same for December 2002 compensation under Rule 67 of the Rules of Court; (2) the reckoning
and December 2004. The December 2004 is not adjusted to account for period of interest in eminent domain cases pursuant to Section 9, Article 3
inflation because the items which make up the construction of NAIA3, i.e., of the 1987 Constitution; and (3) the initial and final payments of just
the labour, plant, materials, systems and equipment installed should not compensation under RA 8974.
be paid for at a higher rate (that takes into account inflation) than the rate
which would have been paid when they were purchased at the earlier
date. Put simply, it makes no sense to apply December 2004 prices to Under Section 4, Rule 67 of the Rules of Court, the property sought to be
items bought and used in the construction of NAIA3 sometime between expropriated shall be appraised as of the date of taking of the property or
June 2000 and December 2002.332 (Emphasis supplied) the filing of the complaint for expropriation, whichever is earlier, thus:

Section 10 of RA 8974 IRR provides that the replacement cost shall be Section 4. Order of expropriation. - If the objections to and the defenses
based on the current market prices of construction and attendant costs. against the right of the plaintiff to expropriate the property are overruled,
Under the depreciated replacement cost method, the replacement cost or when no party appears to defend as required by this Rule, the court
shall be based on the current gross replacement cost of the asset. In its may issue an order of expropriation declaring that the plaintiff has a
pleadings, the Government itself explained that the cost of replacing an lawful right to take the property sought to be expropriated, for the public
asset under both depreciated replacement cost and new replacement cost use or purpose described in the complaint, upon the payment of just
methods should be measured at its current prices. compensation to be determined as of the date of the taking of the
property or the filing of the complaint, whichever came first.

In our jurisdiction, the word "current" should be equated with the date of
the taking of the property or the filing of the complaint, whichever came A final order sustaining the right to expropriate the property may be
first. In the present case, the word "current" should necessarily refer to appealed by any party aggrieved thereby. Such appeal, however, shall not
December 21, 2004, the filing of the complaint for expropriation. prevent the court from determining the just compensation to be paid.

In National Power Corporation v. Co,333 the Court suppletorily applied After the rendition of such an order, the plaintiff shall not be permitted to
Section 4, Rule 67 of the Rules of Court in determining the value of the dismiss or discontinue the proceeding except on such terms as the court
property sought to be expropriated for purposes of implementing deems just and equitable. (4a) (Emphasis supplied)
national infrastructure projects. Under the Rules of Court, just
compensation shall be determined from the date of the taking of the On the other hand, Section 9, Article 3 of the 1987 Constitution provides
property or the filing of the complaint, whichever came first. Thus, where that "[n]o private property shall be taken for public use without just
the filing of an action precedes the taking of the property, just compensation." The 1987 Constitution thus commands the condemnor to
compensation shall be computed as of the time of the filing of the pay the property owner the full and fair equivalent of the property from
complaint.334 The relevant valuation date when we shall reckon the current the date of taking. This provision likewise presupposes that the
gross replacement cost is December 21, 2004, or the date of filing of the condemnor incurs delay if it does not pay the property owner the full
complaint for expropriation. amount of just compensation on the date of taking.338

The Government's base valuation of $300,206,693.00 is only a The reason is that just compensation would not be "just" if the State does
measurement of the current gross replacement cost as of December 2002. not pay the property owner interest on the just compensation from the
We agree with PIATCO that the gross replacement cost of the NAIA-IPT III date of the taking of the property. Without prompt payment, the property
as of December 2002 should be adjusted to its cost as of December 2004 owner suffers the immediate deprivation of both his land and its fruits or
for the plain reason that the Government's computed gross replacement income. The owner's loss, of course, is not only his property but also its
cost is not current, as required by the Rules of Court and jurisprudence. income-generating potential.339

Equity dictates that we should adjust the replacement cost at December Ideally, just compensation should be immediately made available to the
2004 values using the Consumer Price Index (CPI).335 This Court should not property owner so that he may derive income from this compensation, in
be confined and restricted by the use of the depreciated replacement cost the same manner that he would have derived income from his
method, especially in this case where the calculated base valuation as of expropriated property.
December 2004 appears to be not truly reflective of the current gross
replacement cost of the NAIA-IPT III at the time of the filing of the However, if full compensation is not paid for the property taken, then the
complaint for expropriation. State must pay for the shortfall in the earning potential immediately lost
due to the taking, and the absence of replacement property from which
In adjusting the gross replacement cost to December 2004 values, this income can be derived. Interest on the unpaid compensation becomes
Court takes cognizance of the fact that the cost of goods and services in due as compliance with the constitutional mandate on eminent domain
the Philippines increased from 2002 until 2004. This is shown by the CPI and as a basic measure of fairness.340
which is used in calculating the inflation rate and the purchasing power of
the peso.336 PIATCO correctly arrived at the inflation rate of 1.0971 using Thus, interest in eminent domain cases "runs as a matter of law and
the prevailing CPI from November 29, 2002, or the date of the suspension follows as a matter of course from the right of the landowner to be placed

ProvRem Rule 67 Fulltext Page 68 of 119


in as good a position as money can accomplish, as of the date of The initial payment scheme as a prerequisite for the issuance of the writ
taking."341 of possession under RA 8974 only provides the Government flexibility to
immediately take the property for public purpose or public use pending
Lastly, RA 8974 requires the Government to pay just compensation twice: the court's final determination of just compensation. Section 4 (a) of RA
(1) immediately upon the filing of the complaint, when the amount to be 8974 only addresses the Government's need to immediately enter the
paid is 100% of the value of the property based on the current relevant privately owned property in order to avoid delay in the implementation of
zonal valuation of the BIR, and the value of the improvements and/or national infrastructure projects.
structures sought to be expropriated (initial payment); and (2) when the
decision of the court in the determination of just compensation becomes Otherwise, Section 4 of RA 8974 would be repugnant to Section 9, Article
final and executory, in which case the implementing agency shall pay the 3 of the 1987 Constitution which mandates that private property shall not
owner the difference between the amount already paid and the just be taken for public use without just compensation. To reiterate, the
compensation as determined by the court (final payment). Constitution commands the Government to pay the property owner no
less than the full and fair equivalent of the property from the date of
In case the completion of a government infrastructure project is of utmost taking.
urgency and importance, and there is no existing valuation of the area
concerned, the initial payment shall be the proffered value of the In the present case, the Government avers that PIATCO is not entitled to
property. Section 4 of RA 8974 also states that the initial payment of just recover interest. According to the Government, PIATCO should not be
compensation is a prerequisite for the trial court's issuance of a writ of allowed to profit from the void contracts. This contention, however, stems
possession, to wit: Section 4. Guidelines for Expropriation Proceedings. - from a mistaken understanding of interest in expropriation cases.
Whenever it is necessary to acquire real property for the right-of-way or
location for any national government infrastructure project through Contrary to the Government's opinion, the interest award is not anchored
expropriation, the appropriate implementing agency shall initiate the either on the law of contracts or damages; it is based on the owner's
expropriation proceedings before the proper court under the following constitutional right to just compensation. The difference in the amount
guidelines: between the final payment and the initial payment - in the interim or
before the judgment on just compensation becomes final and executory -
(a) Upon the filing of the complaint, and after due notice to the is not unliquidated damages which do not earn interest until the amount
defendant, the implementing agency shall immediately pay the of damages is established with reasonable certainty. The difference
owner of the property the amount equivalent to the sum of (1) between final and initial payments forms part of the just compensation
one hundred percent (100%) of the value of the property based that the property owner is entitled from the date of taking of the
on the current relevant zonal valuation of the Bureau of Internal property.
Revenue (BIR); and (2) the value of the improvements and/or
structures as determined under Section 7 hereof; Thus, when the taking of the property precedes the filing of the complaint
for expropriation, the Court orders the condemnor to pay the full amount
(b) In provinces, cities, municipalities and other areas where of just compensation from the date of taking whose interest shall likewise
there is no zonal valuation, the BIR is hereby mandated within commence on the same date. The Court does not rule that the interest on
the period of sixty (60) days from the date of the expropriation just compensation shall commence the date when the amount of just
case, to come up with a zonal valuation for said area; and compensation becomes certain, e.g., from the promulgation of the Court's
decision or the finality of the eminent domain case.
(c) In case the completion of a government infrastructure
project is of utmost urgency and importance, and there is no With respect to the amount of interest on just compensation, we
existing valuation of the area concerned, the implementing decisively ruled in Republic v. Court of Appeals342that the just
agency shall immediately pay the owner of the property its compensation due to the property owner is effectively a forbearance of
proffered value taking into consideration the standards money, and not indemnity for damages.343 Citing Eastern Shipping Lines,
prescribed in Section 5 hereof. Inc. v. Court of Appeals,344 we awarded a legal interest of 12% per annum
on just compensation. The Court upheld the imposition of the 12%
Upon compliance with the guidelines abovementioned, the court shall interest rate in just compensation cases, as ruled in Republic, in Reyes v.
immediately issue to the implementing agency an order to take National Housing Authority,345 Land Bank of the Philippines v.
possession of the property and start the implementation of the project. Wycoco,346 Republic v. Court of Appeals,347 Land Bank of the Philippines v.
Imperial,348 Philippine Ports Authority v. Rosales-Bondoc,349and Curata v.
Philippine Ports Authority.350 The Court reiterated the Republic ruling in
Before the court can issue a Writ of Possession, the implementing agency Apo Fruits Corporation and Hijo Plantation, Inc. v. Land Bank of the
shall present to the court a certificate of availability of funds from the Philippines,351 Land Bank of the Philippines v. Rivera,352 Department of
proper official concerned.
Agrarian Reform v. Goduco,353 and Land Bank of the Philippines v.
Santiago, Jr.354
In the event that the owner of the property contests the implementing
agency's proffered value, the court shall determine the just compensation On June 21, 2013, the BSP issued Circular No. 799,355 pursuant to MB
to be paid the owner within sixty (60)days from the date of filing of the Resolution No. 796 dated May 16,2013, reducing the legal interest on
expropriation case. When the decision of the court becomes final and loans and forbearance of money from 12% to 6% per annum. BSP Circular
executory, the implementing agency shall pay the owner the difference No. 799 took effect on July 1, 2013.
between the amount already paid and the just compensation as
determined by the court. (Emphasis supplied)
In the present case, the Government filed a complaint for expropriation of
the NAIA-IPT III on December 21, 2004. On the same day, the RTC issued
The Government's initial payment of just compensation does not excuse it a writ of possession in favor of the Government upon the deposit of
from avoiding payment of interest on the difference between the ₱3,002,125,000.00 with the Land Bank. In Gingoyon, the Court held in
adjudged amount of just compensation and the initial payment.
abeyance the implementation of the writ of possession pending the direct
payment of the proffered value of ₱3,002,125,000.00 to PIATCO.

ProvRem Rule 67 Fulltext Page 69 of 119


On September 11, 2006, the RTC reinstated the writ of possession after 8.a. Takenaka and
the Government tendered PIATCO a check in this amount. Asahikosan should not
share in the BOC's
On April 11, 2012, the MIAA and the Land Bank entered into an escrow expenses.
agreement in the amount of $82,157,716.73. On the same date, the MIAA
and the DBP likewise executed an escrow agreement in the amount of Takenaka and Asahikosan refuse to share in the expenses of the BOC.
$34,190,924.59. They argue that pursuant to Section 12,Rule 6 of the Rules of Court, the
Government should solely shoulder the costs incurred in the
Based on these factual circumstances, interest shall accrue as follows: expropriation case.

1. The principal amount of just compensation shall be appraised on the The Government, on the other hand, asserts that Section 1, Rule 142 of
date of the filing of the complaint for expropriation or on December 21, the Rules of Court explicitly authorizes the expropriation court to order
2004. The just compensation shall not earn interest from December 21, the parties to equally share the costs of an action. Hence, the court can
2004, until September 10, 2006, since the Government did not take require third-party intervenors, i.e., Takenaka and Asahikosan, to share in
possession of the NAIA-IPT III during this period. the expenses of the BOC. It points out that PIATCO already shared in the
expenses of the BOC and tendered the sum of ₱2,550,000.00 to the RTC.

2. The difference between the principal amount of just compensation and


the proffered value of ₱3,002,125,000.00 shall earn legal interest of 12% We find no merit in the Government's assertion.
per annum from the date of taking or September 11, 2006 until June 30,
2013. The relevant rule is found in Section 12, Rule 67 of the Rules of Court
which provides:
3. The difference between the principal amount of just compensation and
the proffered value of ₱3,002,125,000.00 shall earn legal interest of 6% SEC. 12. Costs, by whom paid. - The fees of the commissioners shall be
per annum from July 1, 2013, until the finality of the Court's ruling. taxed as a part of the costs of the proceedings. All costs, except those of
rival claimants litigating their claims, shall be paid by the plaintiff, unless
4. The total amount of just compensation shall earn legal interest of 6% an appeal is taken by the owner of the property and the judgment is
per annum from the finality of the Court's ruling until full payment. affirmed, in which event the costs of the appeal shall be paid by the
owner. [Emphasis supplied] This provision specifically deals with the costs
of eminent domain cases. Hence, we find that Section 1, Rule 142 of the
The execution of the escrow agreements shall not affect the accrual of Rules of Court, more specifically, the statement allowing the court to
interest in this case. In its Manifestation and Motion dated July 8, 2011, divide the costs of an action to either party to the case, is inapplicable to
the Government stated that the escrow accounts shall be subject to the the present case.
condition that "[t]he claimant(s) shall have been held to be entitled to
receive the sum claimed from the 'Just Compensation (NAIA Terminal 3)
Fund' in accordance with Philippine law and regulation, by a final, binding Based on the clear terms of Section 12, Rule 67, it is the plaintiff - in this
and executory order or award of the expropriation court."356 case, the Government - not the property owner or third-party intervenors,
i.e., Takenaka and Asahikosan, who shall shoulder the costs of the
expropriation before the court of origin. Since the expenses of the BOC
Clearly, the Government does not intend to pay the just compensation form part of the costs of the suit - as these are expenses necessary in
due to either PIATCO or Takenaka and Asahikosan during the pendency prosecuting or defending an action or a distinct proceeding within an
of the expropriation case or until the finality of the Court's rulings in G.R. action - the Government solely bears the expenses of the BOC. The
Nos. 209917, 209696 & 209731.
property owner shall only bear the costs of the appeal if he loses in his
appeal.
7.b. PIATCO is not entitled to
the fruits and income of the PIATCO, in its pleading, has not questioned its share in the expenses of
NAIA-IPT III. the BOC before the Court. PIATCO's voluntary sharing in the expenses of
the BOC and its non-objection to its payment amount to a waiver of its
PIATCO insists that aside from the interest on just compensation, it is also right not to share in the expenses of the BOC.
entitled to all income generated from the operations of the NAIA-IPT III,
from the date of taking up to the present. In sum, just compensation shall be computed as shown below:

PIATCO's claim is unmeritorious. The State, by way of interest, makes up


for the shortfall in the owners' earning potential and the absence of Base Current Cost Valuation (Inclusive of Attendant Cost)
replacement property from which income can be derived. This is because
ADD:
the interest awarded by the expropriation court is, in reality, the
equivalent of the fruits or income of the seized property.357 In fact, Excess Concession Space
PIATCO itself admitted in its petition in G.R. No. 209731 that the interest
on just compensation already answers for the loss of income that the Four-Level Retail Complex
owner suffered as a result of the State's deprivation of the ordinary use of
Exclusions due to Structural Issues
his property.358
LESS:
Thus, we cannot allow PIATCO to profit from the operation of the NAIA-
IPT III whose funds are sourced from the public coffers. Otherwise, Depreciation
PIATCO would be doubly compensated and unjustly enriched to the Deterioration
detriment of the taxpayers.
REPLACEMENT COST AS OF DECEMBER 2002
8. The BOC's Expenses
ProvRem Rule 67 Fulltext Page 70 of 119
MULTIPLY: 1, 2013 rate * days 2 8
to (181/365)
Inflation Rate of 1.0971
June 30,
REPLACEMENT COST AS OF DECEMBER 21, 2004 2013 $ 326,932,221.26

ADD: July 1, principal*ra 189 6% $267,493,617. $8,310,623.62


2013 to te days 26
Interests from September 11, 2006 to December 2014 Decemb *(189/365) $ 242,810,918.54
er 31,
LESS: 2013
Proffered Value $ 59,438,604.00
January principal*ra 365 6% $267,493,617. $16,049,617.0
JUST COMPENSATION AS OF DECEMBER 31, 2014 1, 2014 te days
$ 510,304,535.80 26 4
to
Decemb
Numb Intere er 31,
Principal Straight
Period Formula er of st 2014
Amount Interest
Days Rate
Total $242,810,918.
Septemb principal*ra 113 12% $267,493,617. $9,937,571.10 54
er 11, te days 26
2006 *(113/365)
to Just
Total Interest from
Decemb Principal Compensation
Formula September 11, 2006 to
er 31, Amount as of December
December 31, 2014
2006 31, 2014

January principal*ra 365 12% $267,493,617. $32,099,234.0 Principal $267,493,617.26 $ 242,810,918.54 $510,304,535.80
1, 2007 te days 26 7 Amount +
to Interest
Decemb
er 31,
9. PIATCO as the Lawful Recipient of Just Compensation.
2007

January principal*ra 365 12% $267,493,617. $32,099,234.0 After determining the amount of just compensation, we next resolve the
1, 2008 te days 26 7 question of who shall receive the full amount of just compensation.
to
Decemb
Takenaka and Asahikosan contend that as actual builders of the NAIA-IPT
er 31,
III, they are lawfully entitled to receive just compensation. They pray that
2008
just compensation of at least $85,700,000.00 be set aside through an
January principal*ra 365 12% $267,493,617. $32,099,234.0 escrow account or other means, in their favor, to answer for their pending
1, 2009 te days 26 7 money claims against PIATCO in G.R. No. 202166.
to
Decemb PIATCO, on the other hand, bases its claim for just compensation on its
er 31, ownership of the NAIA-IPT III and on the ruling in Agan and Gingoyon
2009 that PIATCO should be fully compensated as the builder and owner of the
NAIA-IPT III.
January principal*ra 365 12% $267,493,617. $32,099,234.0
1, 2010 te days 26 7
For its part, the Government refuses to make further payments to PIATCO.
to
Instead, it created an escrow account in favor of the "entitled claimants"
Decemb
of just compensation. The Government fears that the NAIA-IPT III would
er 31,
still be burdened with liens and mortgages - as a result of PIATCO's
2010
indebtedness to other entities - even after it pays PIATCO the full amount
January principal*ra 365 12% $267,493,617. $32,099,234.0 of just compensation.
1, 2011 te days 26 7
to 9.a. Takenaka and Asahikosan's
Decemb intervention in the case as
er 31, unpaid subcontractors is proper.
2011
The defendants in an expropriation case are not limited to the owners of
January principal*ra 365 12% $267,493,617. $32,099,234.0
the property condemned. They include all other persons owning,
1, 2012 te days 26 7
occupying, or claiming to own the property. Under Sections 8 and 14 of
to
RA 8974 IRR, in relation with Section 9, Rule 67 of the Rules of Court, all
Decemb
persons who claim to have lawful interest in the property to be
er 31,
condemned should be included as defendants in the complaint for
2012
expropriation:
January principal * 181 12% $267,493,617. $15,917,702.3

ProvRem Rule 67 Fulltext Page 71 of 119


Section 8 of RA 8974 IRR. Expropriation. - If the owner of a private yet parties to G.R. No. 166429 and Civil Case No. 04-0876 at that time.
property needed by the government implementing agency does not The Court denied Takenaka and Asahikosan's motions for leave to
agree to convey his property to the government by any of the foregoing intervene in our February 1, 2006 Resolution in Gingoyon for palpable
modes of acquiring and/or transferring ownership of the property, then violation of Section 2, Rule 19 of the Rules of Court which only allows
the government shall exercise its right of eminent domain by filing a intervention before the rendition of judgment by the court. Moreover,
complaint with the proper Court for the expropriation for the private Takenaka and Asahikosan had not yet instituted Civil Case No. 06-171
property. (the enforcement case) when we promulgated our rulings in Gingoyon.

The verified complaint shall state with certainty the right and purpose of The RTC's issuance of the March 12, 2007 order, which is binding on the
expropriation, describe the real or personal property sought to be parties and which allows Takenaka and Asahikosan to intervene in the
expropriated, and join as defendants all persons owning or claiming to case, changed the factual circumstances of this case. As an incident in our
own, or occupying, any part thereof or interest therein, showing as far as determination of the just compensation, we necessarily should resolve the
practicable, the interest of each defendant separately. If the title to any issue of NAIA-IPT III's ownership and the question of who the recipient of
property sought to be condemned appears to be in the name of the the just compensation should be.
Republic of the Philippines, although occupied by private individuals, or if
the title is otherwise obscure or doubtful so that the plaintiff cannot with 9.b. The property owner is
accuracy or certainty specify the real owners, averment to that effect may entitled to just compensation.
be made in the complaint.

Citing Agan, Takenaka and Asahikosan argue that the Court intended that
Section 14 of RA 8974 IRR. Trial Proceedings. - Within sixty (60)-day the real builders of the NAIA-IPT III should be paid just compensation.
period prescribed by the Act, all matters regarding defences and Takenaka and Asahikosan assert that they are the entities who actually
objections to the complaint, issues on uncertain ownership and conflicting built the NAIA-IPT III pursuant to the Onshore Construction and Offshore
claims, effects of appeal on the rights of the parties, and such other Procurement Contracts. In Agan, the Court declared that PIATCO is the
incidents affecting the complaint shall be resolved under the provisions builder of the NAIA-IPT III. The Court stated:
on expropriation of Rule 67 of the Rules of Court.

This Court, however, is not unmindful of the reality that the structures
Section 9, Rule 67 of the Rules of Court. Uncertain ownership; conflicting comprising the NAIA IPT III facility are almost complete and that funds
claims. - If the ownership of the property taken is uncertain, or there are have been spent by PIATCO in their construction. For the government to
conflicting claims to any part thereof, the court may order any sum or take over the said facility, it has to compensate respondent PIATCO as
sums awarded as compensation for the property to be paid to the court builder of the said structures. The compensation must be just and in
for the benefit of the person adjudged in the same proceeding to be accordance with law and equity for the government cannot unjustly
entitled thereto. But the judgment shall require the payment of the sum enrich itself at the expense of PIATCO and its investors.360
or sums awarded to either the defendant or the court before the plaintiff
can enter upon the property, or retain it for the public use or purpose if
entry has already been made. (9a) (Emphasis supplied) This finding is likewise affirmed in our February 1, 2006 Resolution in
Gingoyon where we declared:

All persons who have lawful interest in the property sought to be


expropriated should be impleaded in the complaint for purposes of The Court is not wont to reverse its previous rulings based on factual
determining who shall be entitled to just compensation. If a known owner premises that are not yet conclusive or judicially established. Certainly,
is not joined as defendant, he may intervene in the proceeding. If the whatever claims or purported liens Takenaka and Asahikosan against
owner is joined but not served with process and the proceeding is already PIATCO or over the NAIA 3 have not been judicially established. Neither
closed before he came to know of the condemnation, he may maintain an Takenaka nor Asahikosan are parties to the present action, and thus have
independent suit for damages. Consequently, Takenaka and Asahikosan not presented any claim which could be acted upon by this Court. The
are correct in invoking Section 9, Rule 67 of the Rules of Court for earlier adjudications in Agan v. PIATCO made no mention of either
purposes of determining who shall be entitled to just compensation in Takenaka or Asahikosan, and certainly made no declaration as to their
this case. This rule is likewise their proper basis of intervention in the rights to any form of compensation. If there is indeed any right to
RTC's March 12, 2007 order in Civil Case No. 04-0876. remuneration due to these two entities arising from NAIA 3, they have not
yet been established by the courts of the land.

Our ruling on this point does not contradict Section 4 (a) of RA 8974
which provides for a scheme of direct and immediate initial payment to It must be emphasized that the conclusive ruling in the Resolution dated
the property owner in cases involving national government infrastructure 21 January 2004 in Agan v. PIATCO (Agan 2004) is that PIATCO, as builder
projects. of the facilities, must first be justly compensated in accordance with law
and equity for the Government to take over the facilities. It is on that
premise that the Court adjudicated this case in its 19 December 2005
Section 4 (a) of RA 8974 applies only to cases where the issue of Decision.
ownership of the expropriated property is not disputed. In cases where
the ownership is contested; where conflicting claims or interests over the
expropriated property exist; or where there are other incidents affecting While the Government refers to a judgment rendered by a London court
the complaint for expropriation, the governing rule is Section 9, Rule 67 of in favor of Takenaka and Asahikosan against PIATCO in the amount of
the Rules of Court. By creating a separate provision applicable only to the US$82 Million, it should be noted that this foreign judgment is not yet
latter cases, Section 14 of RA 8974 IRR359 necessarily acknowledged that binding on Philippine courts. It is entrenched in Section 48, Rule 39 of the
the scheme of immediate and direct initial payment is not an absolute Rules of Civil Procedure that a foreign judgment on the mere strength of
and all-encompassing rule applicable in all circumstances. its promulgation is not yet conclusive, as it can be annulled on the
grounds of want of jurisdiction, want of notice to the party, collusion,
fraud, or clear mistake of law or fact. It is likewise recognized in Philippine
We are aware of our pronouncement in the December 19, 2005 Gingoyon jurisprudence and international law that a foreign judgment may be
decision directing the Government to directly and immediately pay barred from recognition if it runs counter to public policy.
PIATCO the proffered value of ₱3billion. We rendered the December 19,
2005 Decision based on the fact that Takenaka and Asahikosan were not
ProvRem Rule 67 Fulltext Page 72 of 119
Assuming that PIATCO indeed has corresponding obligations to other land. The Republic can still consistently assert, in both actions for
parties relating to NAIA 3, the Court does not see how such obligations, expropriation and reversion, that the subject parcels of land are part of
yet unproven, could serve to overturn the Decision mandating that the the public domain.
Government first pay PIATCO the amount of 3.02 Million Pesos before it
may acquire physical possession over the facilities. This directive enjoining The record of the present case show that PIATCO has been the original
payment is in accordance with Republic Act No. 8974, and under the contracting party commissioned by the Government to construct the
mechanism established by the law the amount to be initially paid is that NAIA-IPT III based on a build-operate-transfer arrangement and who, in
which is provisionally determined as just compensation. The provisional this capacity, contracted out the actual construction to Takenaka and
character of this payment means that it is not yet final, yet sufficient under Asahikosan. Thus, when the NAIA-IPT III was built, it was in PIATCO's
the law to entitle the Government to the writ of possession over the name and account, although it subsequently owed sums to
expropriated property. subcontractors, incurred in the course of the construction. From this
perspective, PIATCO has been the owner recognized as such by the
There are other judicial avenues outside of this Motion for Government although the basis of its contractual relationship with the
Reconsideration wherein all other claims relating to the airport facilities Government was later on nullified. Takenaka and Asahikosan, on the other
may be ventilated, proved and determined. Since such claims involve hand, had always been subcontractors with whom the Government did
factual issues, they must first be established by the appropriate trier of not have any formal link. These facts indubitably show that PIATCO has
facts before they can be accorded any respect by or binding force on this been the owner of the NAIA-IPT III entitled to receive the just
Court.361 [Emphasis supplied] compensation due. Takenaka and Asahikosan for their part, have not
shown that they possess legal title or colorable title to the NAIA-IPT III
Contrary to Takenaka and Asahikosan's position, in the Philippine that would defeat PIATCO's ownership.
jurisdiction, the person who is solely entitled to just compensation is the
owner of the property at the time of the taking.362 As shown below, the To recap and expound on the matter:
test of who shall receive just compensation is not who built the terminal,
but rather who its true owner is. First, Takenaka and Asahikosan were mere subcontractors in the nullified
NAIA-IPT III project. That Takenaka and Asahikosan actually built the
From the express provision of Section 4 of RA 8974, just compensation NAIA-IPT III does not make them the owner of the terminal building.
shall only be paid to the property owner. We implead persons with lawful
interests in the property in order to determine the person who shall We carefully point out that our finding in this case that Takenaka and
receive just compensation. Note that the last paragraph, Section 4 of RA Asahikosan are the actual builders of the NAIA-IPT III does not contravene
8974 states: "When the decision of the court becomes final and executory, our rulings in Agan and Gingoyon that PIATCO is the builder of the
the implementing agency shall pay the owner the difference between the NAIAIPT III. The word "builder" is broad enough to include the contractor,
amount already paid and the just compensation as determined by the PIATCO, and the subcontractors, Takenaka and Asahikosan, in the nullified
court." This provision thus envisions a situation where the court NAIA-IPT III project. Republic Act No. 4566367 defines a "builder" as
determines with finality, for purposes of payment of just compensation, follows:
the conflicting claims of the defendants and intervenors.

Section 9 (b) of RA 4566. "Contractor" is deemed synonymous with the


The cases cited by Takenaka and Asahikosan are inapplicable to justify term "builder" and, hence, any person who undertakes or offers to
their right to receive just compensation. The Court did not award just undertake or purports to have the capacity to undertake or submits a bid
compensation to a non-owner in De Knecht v. Court of Appeals.363 The to, or does himself or by or through others, construct, alter, repair, add to,
Court held in that case that a person who had no legal interest in the subtract from, improve, move, wreckor demolish any building, highway,
property at the time of the filing of a complaint for expropriation had no road, railroad, excavation or other structure, project, development or
right to intervene in the case. The Court ruled that only persons who have improvement, or to do any part thereof, including the erection of
lawful interests in the property may be impleaded as defendants or may scaffolding or other structures or works in connection therewith. The term
intervene in the expropriation case under Section 1, Rule 67 of the Rules contractor includes subcontractor and specialty contractor.
of Court. This case thus, at most, support their right to intervene.

In Gingoyon, the Court loosely used the word "builder" and "owner"
In Calvo v. Zandueta,364 the Court stayed the execution of the trial court's interchangeably. We clarify, however, that a builder is different from the
judgment ordering the provincial treasurer of Pangasinan to pay Aquilino owner of the property. As we stated above, a builder includes the
Calvo just compensation due to the pendency of the interpleader that contractor and the subcontractor. On the other hand, the "owner" who is
Juana Ordoñez brought based on her own claim of ownership of the constitutionally entitled to just compensation is the person who has legal
expropriated land. Ordoñez asserted that she acquired all rights and title to the property. Logically, a builder is not necessarily the owner of the
interests on the subject land when she purchased it during the execution property and vice-versa.
sale while the expropriation proceedings were still pending.

Second, we cannot recognize Takenaka and Asahikosan's claimed liens


Philippine Veterans Bank v. Bases Conversion Development over the NAIA-IPT III in this just compensation case. Since G.R. No. 202166
Authority365 further affirms the rule that just compensation shall only be is still pending before the Court, we cannot conclusively rule that
paid to the owner of the expropriated property at the time of taking. In Takenaka and Asahikosan are unpaid creditors of PIATCO without
that case, the Court held that the trial court may order the payment of just preempting the Court's ruling in the enforcement case.
compensation to itself pending the adjudication of the issue of ownership
in other proceedings pursuant to Section 9, Rule 67 of the Rules of Court.
Even assuming that Takenaka and Asahikosan - as unpaid contractors in
the botched NAIA-IPT III construction contract - indeed have liens over
The Court likewise did not award just compensation to a non-owner in the NAIA-IPT III, PIATCO is still the property owner who, as such, should
Republic v. Mangotara.366 The Court held that the filing of a supplemental directly receive just compensation from the Government.
complaint for expropriation impleading private parties does not
necessarily amount to an admission that the parcels of land sought to be
expropriated are privately owned. The Republic merely acknowledged We clarify that the expropriation court's determination of the lawful
that there are private persons also claiming ownership of the parcels of property owner is merely provisional. By filing an action for expropriation,

ProvRem Rule 67 Fulltext Page 73 of 119


the condemnor merely serves notice that it is taking title to and judicial proceedings and is, indeed, reversed in the subsequent case. This
possession of the property, and that the defendant is asserting title to or would be unfair to the State (and the public) that merely
interest in the property, not to prove a right to possession, but to prove a
right to compensation for the taking. The Court's disposition with respect exercised its immutable right to exercise the power of eminent domain.
to the ownership of the property is not conclusive, and it remains open to
challenge through proper actions. The court's resolution of the title to the
land at the time of taking has no legal consequences beyond the eminent Contrary to Takenaka and Asahikosan's claim, in Calvo v. Zandueta,370 the
domain proceedings. The court's decision cannot be pleaded as a defense Court did not stay the execution of a final and executory ruling in the
of res judicataor collateral estoppel in any action to determine title to the eminent domain case during the pendency of the interpleader case.
property.
A close reading of Calvo shows that the order of payment of just
As we explained in Republic of the Philippines v. Samson-Tatad:368 compensation in that case was not yet final and executory.

However, the authority to resolve ownership should be taken in the In November 1924, the municipality of San Quintin, Pangasinan filed an
proper context. The discussion in Republic was anchored on the question action for expropriation of a parcel of land owned by Aquilino Calvo and
with a Certificate of Title No. 25100.
of who among the respondents claiming ownership of the property must
be indemnified by the Government:
On November 25, 1925, the Court of First Instance (CFI) approved the
Now, to determine the person who is to be indemnified for the commissioners' valuation of the subject land in the sum of ₱6,943.25. The
expropriation of Lot 6, Block 6, Psd-2017, the court taking cognizance of municipality of San Quintin appealed the case but subsequently withdrew
the expropriation must necessarily determine if the sale to the Punzalan the appeal on June 23, 1926. The CFI approved the withdrawal of appeal
on July 20, 1926.
spouses by Antonio Feliciano is valid or not. For if valid, said spouses must
be the ones to be paid by the condemnor; but if invalid, the money will be
paid to someone else. x x x In the meantime, Juana Ordoñez levied on the subject land after she
obtained a favorable judgment against Calvo. The levy was recorded on
Thus, such findings of ownership in an expropriation proceeding should the certificate of title on December 23, 1925. Thereafter, the sheriff sold
not be construed as final and binding on the parties. By filing an action the subject land to Ordoñez inan execution sale. On January 23, 1926, the
for expropriation, the condemnor (petitioner), merely serves notice that it sale was duly entered by memorandum on the certificate of title. On the
is taking title to and possession of the property, and that the defendant is same date, Ordoñez filed a motion for substitution as a defendant in the
asserting title to or interest in the property, not to prove a right to expropriation case on the ground that she acquired all the rights and
possession, but to prove a right to compensation for the taking. interests of Calvo on the subject land.

If at all, this situation is akin to ejectment cases in which a court is On June 29, 1926, the CFI declared the November 25, 1925 decision final
temporarily authorized to determine ownership, if only to determine who and ordered the provincial treasurer of Pangasinan to pay Calvo a part of
is entitled to possession. This is not conclusive, and it remains open to just compensation. The following day, Ordoñez filed a motion praying for
challenge through proper actions. The consequences of Sec. 9, Rule 67 the revocation of the June 29, 1926 order and for the provincial treasurer
of Pangasinan to retain the award of just compensation.
cannot be avoided, as they are due to the intimate relationship of the
issue of ownership with the claim for the expropriation payment.
(Emphasis supplied) On July 20, 1926, the CFI revoked the June 29, 1926 order and ordered the
provincial treasurer of Pangasinan to retain the money until further orders
9.c. A final disposition in the eminent of the court. After the CFI denied Calvo et al.'s motion for reconsideration,
domain case with respect to the order they filed a petition for certiorari before the Court.
of payment to a particular person shall
be final and executory. The Court denied the petition. The Court ruled that "assuming that the
judgment of November 25, 1925, constituted a final determination of the
To avoid future litigation, we emphasize that a final disposition in the petitioners' right to receive the award," Ordoñez was not a party to the
eminent domain case with respect to the order to pay a particular person expropriation case and, therefore, could not be bound by the judgment.
shall be final and executory upon the lapse of relevant periods under Rule Ordoñez' claim that she stands subrogated to Calvo's right to just
39 of the Rules of Court. The recourse of the person claiming ownership compensation has the appearance of validity. The judicial determination
over the expropriated property in any subsequent case is against the of her claim may be adjudicated in an action for interpleader which was
adjudged property owner in the expropriation case. then pending when the motion for substitution was filed. Consequently,
the trial court correctly stayed the execution of the judgment in the
expropriation case. Whenever necessary to promote the ends of justice,
The principle of res judicata applies in this particular matter because the courts have the power to temporarily stay executions of judgments
issues on the amount of just compensation and the person to be paid just rendered by them."
compensation are the central issues in the second phase of expropriation.
Based on this principle, a final judgment or decree on the merits by a
court of competent jurisdiction is conclusive of the rights of the parties or Clearly, the November 25, 1925 decision in Calvo was not yet final and
their privies in all later suits on points and matters determined in the executory when the Court suspended the execution of that ruling. The
former suit.369 July 29, 1926 order revoked the June 29, 1926 order which in turn
declared the finality of the November 25, 1925 decision of the CFI.
Ordoñez filed a motion for the reversal of the June 29, 1926 order prior to
There would be no end to litigation in an eminent domain case if we rule the CFI's withdrawal of appeal on July 20, 1926. Significantly, the CFI
otherwise; we would only foment mockery of the judicial proceedings as approved the withdrawal of appeal on the same date that the CFI revoked
the order of payment in the eminent domain case would never be truly the June 29, 1926 order and ordered the provincial treasurer of
final and executory. Furthermore, to the detriment of the public, interest Pangasinan to withhold the just compensation. There is thus no basis to
would continue to accrue on just compensation if we rule that the order Takenaka and Asahikosan's claim that the execution of a final and
of payment to a particular recipient can be reversed in the subsequent executory judgment on just compensation may be suspended if there is
ProvRem Rule 67 Fulltext Page 74 of 119
still a subsisting case regarding the disputed ownership of the national infrastructure projects upon the issuance of the writ of
expropriated property. possession. When the taking of the property precedes the payment of just
compensation, the Government shall indemnify the property owner by
9.d. The determination of whether the way of interest.
NAIA-IPT III shall be burdened by liens
and mortgages even after the full "Taking" under the power of eminent domain means entering upon
payment of just compensation is still private property for more than a momentary period, and under the
premature. warrant or color of legal authority, devoting it to public use, or otherwise
informally appropriating or injuriously affecting it in such a way as
The determination of whether the NAIA-IPT III shall be burdened by liens substantially to oust the owner and deprive him of all beneficial
and mortgages even after the full payment of just compensation is still enjoyment thereof.373
premature. The enforceability of Claim Nos. HT-04-248 and HT-05-269 in
this jurisdiction has yet to be decided by the Court in G.R. No. 202166. "Taking" of property takes place when: (1) the owner is actually deprived
Furthermore, the application of Article 2242 of the Civil or dispossessed of his property;(2) there is a practical destruction or a
Code371 presupposes that PIATCO declared insolvency or has been material impairment of the value of his property; (3) the owner is deprived
declared insolvent. This, of course, should be litigated in insolvency of the ordinary use of the property, or (4) when he is deprived of the
proceedings, not in the present eminent domain case. jurisdiction, supervision and control of his property.374

The Court cannot pass upon the validity and enforceability of civil claims The taking of property is different from the transfer of the property title
against PIATCO by creditor/s in an expropriation case or the existence of from the private owner to the Government. Under Rule 67 of the Rules of
liens on the NAIA-IPT III. Section 114 of Republic Act No. Court, there are two phases of expropriation: (a) the condemnation of the
10142372 provides: property after it is determined that its acquisition will be for a public
purpose or public use; and (b) the determination of just compensation to
Section 114. Rights of Secured Creditors. - The Liquidation Order shall not be paid for the taking of private property to be made by the court with
affect the right of a secured creditor to enforce his lien in accordance with the assistance of not more than three commissioners.
the applicable contract or law. A secured creditor may:
The first phase is concerned with the determination of the Government's
(a) waive his right under the security or lien, prove his claim in authority to exercise the power of eminent domain and the propriety of
the liquidation proceedings and share in the distribution of the its exercise in the context of the facts involved in the suit. The court
assets of the debtor; or declares that the Government has a lawful right to take the property
sought to be condemned, for the public use or purpose described in the
complaint.375
(b) maintain his rights under the security or lien:

The second phase relates to the just amount that the Government shall
If the secured creditor maintains his rights under the security or lien: compensate the property owner.376

(1) the value of the property may be fixed in a manner agreed Whenever the court affirms the condemnation of private property in the
upon by the creditor and the liquidator. When the value of the first phase of the proceedings, it merely confirms the Government's lawful
property is less than the claim it secures, the liquidator may right to take the private property for public purpose or public use. The
convey the property to the secured creditor and the latter will court does not necessarily rule that the title to the private property
be admitted in the liquidation proceedings as a creditor for the likewise vests on the Government.
balance. If its value exceeds the claim secured, the liquidator
may convey the property to the creditor and waive the debtor's
right of redemption upon receiving the excess from the The transfer of property title from the property owner to the Government
creditor; is not a condition precedent to the taking of property. The State may take
private property prior to the eventual transfer of title of the expropriated
property to the State.
(2) the liquidator may sell the property and satisfy the secured
creditor's entire claim from the proceeds of the sale; or
In fact, there are instances when the State takes the property prior to the
filing of the complaint for expropriation or without involving the transfer
(3) the secure creditor may enforce the lien or foreclose on the of title.377 In People v. Fajardo,378 the Court ruled that the municipal
property pursuant to applicable laws. mayor's refusal to give the property owner the permission to build a
house on his own land on the ground that the structure would destroy
10. The exercise of eminent the beauty of the public plaza amounts to the taking of the property
domain from the perspective of requiring just compensation.
"taking."
In National Power Corporation (NPC) v. Spouses Malit,379 the NPC's
10.a. The Government may take transmission lines had to pass the Spouses Malit's property. The Court
the property for public ruled that the NPC's easement of right-of-wayon the land was equivalent
purpose or public use upon to the taking of property. The limitation imposed by the NPC against the
the issuance and effectivity use of the land for an indefinite period deprived the Spouses Malit of the
of the writ of possession. lot's ordinary use. Consequently, the NPC shall give the Spouses Malit just
compensation.
To clarify and to avoid confusion in the implementation of our judgment,
the full payment of just compensation is not a prerequisite for the The reckoning period, however, of the valuation of just compensation is
Government's effective taking of the property. As discussed above, RA the date of taking or the filing of the complaint for expropriation,
8974 allows the Government to enter the property and implement whichever is earlier. In either case, it is only after the finality of the second
ProvRem Rule 67 Fulltext Page 75 of 119
stage and after the payment of just compensation that the title shall pass enter upon the property of the defendant and appropriate the same for
to the Government. As we have ruled in Gingoyon, the title to the public use or purpose shall not be delayed by an appeal from the
property does not pass to the condemnor until just compensation is paid. judgment. But if the appellate court determines that plaintiff has no right
of expropriation, judgment shall be rendered ordering the Regional Trial
Under Section 4 of RA 8974, the Government is only entitled to a writ of Court to forthwith enforce the restoration to the defendant of the
possession upon initial payment of just compensation to the defendant, possession of the property, and to determine the damages which the
and upon presentment to the court of a certificate of availability of funds. defendant sustained and may recover by reason of the possession taken
by the plaintiff. (11a)

A writ of possession does not transfer title to the Government; it is "a writ
of execution employed to enforce a judgment to recover the possession The State's taking of the property is not based on trust or contract, but is
of land. It commands the sheriff to enter the land and give its possession founded on its inherent power to appropriate private property for public
to the person entitled under the judgment."380 Section 4 of RA 8974 use. It is also for this reason - to compensate the property owner for the
further states that the writ of possession is an order to take possession of deprivation of his right to enjoy the ordinary use of his property until the
the property and to start the implementation of the project, to wit: naked title to the property passed to the State - that the State pays
interest from the time of the taking of the property until full payment of
just compensation.
Section 4. Guidelines for Expropriation Proceedings. - Whenever it is
necessary to acquire real property for the right-of-way or location for any
national government infrastructure project through expropriation, the This conclusion is consistent with the dispositive portion of our ruling in
appropriate implementing agency shall initiate the expropriation Gingoyon where we authorized the Government to perform acts that are
proceedings before the proper court under the following guidelines: essential to the operation of the NAIA-IPT III as an international airport
terminal upon the effectivity of the writ of possession. The authority
granted to the Government encompasses "the repair, reconditioning and
(a) Upon the filing of the complaint, and after due notice to the improvement of the complex, maintenance of the existing facilities and
defendant, the implementing agency shall immediately pay the equipment, installation of new facilities and equipment, provision of
owner of the property the amount equivalent to the sum of (1) services and facilities pertaining to the facilitation of air traffic and
one hundred percent (100%) of the value of the property based transport, and other services that are integral to a modern-day
on the current relevant zonal valuation of the Bureau of Internal international airport."
Revenue (BIR); and (2) the value of the improvements and/or
structures as determined under Section 7 hereof;
The present case involves the second stage of expropriation or the
determination of replacement cost of the NAIA-IPT III. The first stage has
(b) In provinces, cities, municipalities and other areas where become final after the promulgation of the December 19, 2005 decision
there is no zonal valuation, the BIR is hereby mandated within and the February 1, 2006 resolution in Gingoyon where we affirmed the
the period of sixty (60) days from the date of the expropriation Government's power to expropriate the NAIA-IPT III and where we
case, to come up with a zonal valuation for said area; and
ordered the issuance of a writ of possession upon the Government's
direct payment of the proffered value of ₱3 billion to PIATCO. Thus, the
(c) In case the completion of a government infrastructure reinstatement of the writ of possession on September 11, 2006,
project is of utmost urgency and importance, and there is no empowered the Government to take the property for public use, and to
existing valuation of the area concerned, the implementing effectively deprive PIATCO of the ordinary use of the NAIA-IPT III.
agency shall immediately pay the owner of the property its
proffered value taking into consideration the standards B. G.R. No. 181892
prescribed in Section 5 hereof.

1. The issue on the appointment of


Upon compliance with the guidelines abovementioned, the court shall an independent appraiser is
immediately issue to the implementing agency an order to take already moot and academic.
possession of the property and start the implementation of the project.

In G.R. No. 181892, the RTC, in its order dated May 5,2006, ordered the
Before the court can issue a Writ of Possession, the implementing agency appointment of an independent appraiser to conduct the valuation of the
shall present to the court a certificate of availability of funds from the NAIA-IPT III upon the BOC's request. Thereafter, the Government and
proper official concerned. PIATCO submitted their lists of nominees to this position. On May 3, 2007,
the RTC engaged the services of DG Jones and Partners as an
In the event that the owner of the property contests the implementing independent appraiser. On May 18, 2007, the RTC directed the
agency's proffered value, the court shall determine the just compensation Government to submit a Certificate of Availability of Funds to cover DG
to be paid the owner within sixty (60)days from the date of filing of the Jones and Partners' $1.9 Million appraisal fee.
expropriation case. When the decision of the court becomes final and
executory, the implementing agency shall pay the owner the difference The Government disputed the May 3 and 18, 2007 orders and argued that
between the amount already paid and the just compensation as the RTC had no power to appoint an independent appraiser. The
determined by the court. (Emphasis supplied) Government insisted that the RTC should exclusively choose among its
nominees pursuant to Section 7 of RA 8974 as well as Sections 10 and 11
The Government is provisionally authorized to take the property for public of RA 8974 IRR.
purpose or public use whenever the court issues a writ of possession in
favor of the Government. It may take possession of the property or The RTC sustained the appointment of DG Jones and Partners in an order
effectively deprive the property owner of the ordinary use of the property. dated January 7, 2008.The RTC ruled that its power to appoint the
If the court, however, later on determines that the State has no right of members of the BOC under Section 5, Rule 67 of the Rules of Court was
expropriation, then the State shall immediately restore the defendant of broad enough as to include the appointment of an independent
the possession of the property and pay the property owner damages that appraiser.
he sustained. Section 11, Rule 67 of the Rules of Court: Section 11. Entry
not delayed by appeal; effect of reversal. - The right of the plaintiff to
ProvRem Rule 67 Fulltext Page 76 of 119
On February 6, 2008, the Government filed a petition for certiorari with not the BOC or the independent appraiser. DG Jones and Partners' rule
prayer for the issuance of a temporary restraining order and/or a writ of has simply been overtaken by events.
preliminary injunction before the Court assailing the May 3, 2007; May 18,
2007; and January 7, 2008 orders (G.R. No. 181892). As a final note, while we stated in Gingoyon that the RTC may validly
appoint commissioners in the appraisal of the NAIA-IPT III, the trial court
On January 9, 2008, the Court issued a temporary restraining order should have appointed commission members who possessed technical
against the implementation of the May 3, May 18, and January 7, 2008 expertise in the appraisal of a complex terminal building. Under Section 5,
orders. Rule 67 of the Rules of Court, the BOC's main functions are to ascertain
and report to the court the just compensation for the property sought to
On August 5, 2010, the RTC ordered the parties to submit their appraisal be taken. The appointment of technical experts as commissioners would
reports of the NAIA-IPTIII. The Government, PIATCO, Takenaka and have avoided the DG Jones aspect of the controversy as there would have
Asahikosan separately hired their own appraisers who came up with their been no need for the trial court to hire an independent appraiser. This
different valuations of the NAIA-IPT III. would have avoided the duplication of tasks and delay in the proceedings.

On March 31, 2011, the BOC submitted its Final Report recommending To summarize, we rule that:
the payment of just compensation in the amount of $376,149,742.56. On
May 23, 2011, the RTC rendered a decision ordering the Government to (1) The May 23, 2011 decision of the RTC in Civil Case No. 04-
pay PIATCO just compensation in the amount of $116,348,641.10. The CA 0876 is valid. The parties were afforded procedural due process
modified the RTC ruling and held that the just compensation as of July 31, since their respective positions, counter-positions, and evidence
2013, amounts to $371,426,742.24. were considered by the trial court in rendering the decision.

These developments render the appointment of DG Jones and Partners as (2) Replacement cost is a different standard of valuation from
an independent appraiser of the NAIA-IPT III ineffective. An appraiser is a fair market value. Fair market value is the price at which a
person selected or appointed by competent authority to ascertain and property may be sold by a seller who is not compelled to sell
state the true value of goods or real estate.381 The purpose of appointing and bought by a buyer who is not compelled to buy. In
DG Jones and Partners as an independent appraiser was to assist the BOC contrast, replacement cost is the amount necessary to replace
in appraising the NAIA-IPT III. In fact, the BOC requested the RTC to the improvements/structures, based on the current market
engage the services of an independent appraiser because the BOC had no prices for materials, equipment, labor, contractor's profit and
technical expertise to conduct the valuation of the NAIA-IPT III. In turn, overhead, and all other attendant costs associated with the
the BOC was to recommend to the RTC the replacement cost of the NAIA- acquisition and installation in place of the affected
IPT III. Under Section 8, Rule 67 of the Rules of Court, the RTC may accept improvements/structures. (3) In computing just compensation,
or reject, whether in whole or in part, the BOC's report which is merely the Court shall use the replacement cost method and the
advisory and recommendatory in character. standards laid down in Section 5 of RA 8974 as well as Section
10 of RA 8974. The Court shall likewise consider equity in the
We find, under the given circumstances, that the propriety of the determination of the just compensation due for NAIA-IPT III.
appointment of DG Jones and Partners and the corollary issue of who
should shoulder the independent appraiser's fees moot and academic. (4) The use of depreciated replacement cost method is
consistent with the principle that the property owner shall be
An actual case or controversy exists when there is a conflict of legal rights compensated for his actual loss. It is consistent as well with
or an assertion of opposite legal claims between the parties that is Section 10 of RA 8974 IRR which provides that the courts shall
susceptible or ripe for judicial resolution.382 A justiciable controversy must consider the kinds and quantities of materials/equipment used
not be moot and academic or have no practical use or value. In other and the configuration and other physical features of the
words, there must be a definite and concrete dispute touching on the property, among other things, in the valuation of the NAIAIPT
legal relations of the parties who have adverse legal interests. Otherwise, III. The Government should not compensate PIATCO based on
the Court would simply render an advisory opinion on what the law would the value of a modern equivalent asset that has the full
be on a hypothetical state of facts. The disposition of the case would not functional utility of a brand new asset.
have any practical use or value as there is no actual substantial relief to
which the applicant would be entitled to and which would be negated by (5) The amount of just compensation as of the filing of the
the dismissal or denial of the petition.383 complaint for expropriation on December 21, 2004, is
$326,932,221.26. From this sum shall be deducted the proffered
After the BOC submitted its Final Report on the replacement cost of the value of $59,438,604.00. The resulting difference of
NAIA-IPT III based on the appraisal reports and other evidence submitted $267,493,617.26 shall earn a straight interest of 12% per annum
by the parties, the appointment of DG Jones and Partners ceased to serve from September 11, 2006 until June 30, 2013, and a straight
any purpose. Any subsequent findings of DG Jones and Partners interest of 6% per annum from July 1, 2013, until full payment.
regarding the appraisal of the NAIA-IPT III would cease to have any
practical materiality since the RTC proceedings on the amount of just (6) PIATCO, as the owner of the NAIA-IPT III, shall solely receive
compensation had already been terminated. As with the BOC, the the just compensation. Based on the last paragraph, Section 4
independent appraiser's valuation of the NAIAIPT III was advisory and of RA 8974 and the prevailing jurisprudence, it is the owner of
recommendatory in character. DG Jones and Partners' valuation was only the expropriated property who is constitutionally entitled to just
preliminary and was not by any means meant to be final and conclusive compensation. Other claimants should be impleaded or may
on the parties. In the exercise of its judicial functions, it is the intervene in the eminent domain case if the ownership of the
expropriation court who has the final say on the amount of just property is uncertain or there are conflicting claims on the
compensation. Since the RTC has already made a factual finding on the property pursuant to Section 9, Rule 67 of the Rules of Court.
valuation of the NAIA-IPT III, there is no point in appointing DG Jones and
Partners as an independent appraiser. To reiterate, valuation involves a (7) The Government may deprive PIATCO of the ordinary use of
factual question that is within the province of the expropriation court, and the NAIA-IPT III upon the issuance and effectivity of the writ of

ProvRem Rule 67 Fulltext Page 77 of 119


possession on September 11, 2006. However, the Government possession5issued by the Regional Trial Court (RTC) of Cebu City, Branch
shall only have ownership of the NAIA-IPT III after it fully pays 23, allowing petitioner to take possession of respondent’s property.
PIATCO the just compensation due.
Petitioner Metropolitan Cebu Water District is a government-owned and
(8) The expenses of the BOC, which are part of the costs, shall controlled corporation created pursuant to Presidential Decree No. 198,
be shouldered by the Government as the condemn or of the as amended. Among its purposes are to acquire, install, improve, maintain
property pursuant to Section 12,Rule 67 of the Rules of Court. and operate water supply and distribution systems within the boundaries
Consequently, Takenaka and Asahikosan shall not share in the of the District.6
expenses of the BOC. PIATCO is deemed to have waived its
right not to share in the expenses of the BOC since it voluntarily Petitioner wanted to acquire a five (5)-square meter lot occupied by its
shared in the expenses of the BOC. production well. The lot is part of respondent’s property covered by TCT
No. 168605 and located in Banilad, Cebu City. Petitioner initiated
(9) The issues of the propriety of the appointment of DG Jones negotiations7 with respondent J. King and Sons Company, Inc. for the
and Partners as an independent appraiser in the valuation of voluntary sale of the latter’s property. Respondent did not acquiesce to
the NAIA-IPT III and who should shoulder DG Jones and petitioner’s proposal. After the negotiations had failed, petitioner
Partners' appraisal fee are already moot and academic. The pursuant to its charter8 initiated
purpose of appointing DG Jones and Partners as an
independent appraiser was to assist the BOC in the appraisal of expropriation proceedings through Board Resolution No. 015-
NAIA-IPT III. As with the BOC, the independent appraiser's 20049 which was duly approved by the Local Water Utilities
recommendation to the RTC was merely recommendatory and Administration (LWUA).10 On 10 November 2004, petitioner filed a
advisory in character. Since the RTC has already ruled on the complaint11 to expropriate the five (5)-square meter portion of
just compensation in Civil Case No. 04-0876, the appointment respondent’s property.
of an independent appraiser no longer serves any practical
purpose.
On 7 February 2005, petitioner filed a motion12 for the issuance of a writ
of possession. Petitioner wanted to tender the amount to respondent
WHEREFORE, premises considered, we PARTIALLY REVERSE the August 22, during a rescheduled hearing which petitioner’s counsel had failed to
2013 amended Decision and the October 19, 2013 Resolution of the Court attend.13Petitioner deposited14 with the Clerk of Court the amount of
of Appeals. ₱17,500.00 equivalent to one hundred percent (100%) of the current zonal
value of the property which the Bureau of Internal Revenue had pegged
1) The principal amount of just compensation is fixed at at ₱3,500.00 per square meter.15 Subsequently, the trial court granted the
$326,932,221.26 as of December 21, 2004. Thereafter, the motion16 and issued the writ of possession.17Respondent moved for
amount of $267,493,617.26, which is the difference between reconsideration but the motion was denied.18
$326,932,221.26 and the proffered value of $59,438,604.00,
shall earn a straight interest of 12% per annum from September Respondent filed a petition19 for certiorari under Rule 65 with the Court of
11, 2006 until June 30, 2013, and a straight interest of 6% per Appeals. It sought the issuance of a temporary restraining order (TRO)
annum from July 1, 2013 until full payment; which the Court of Appeals granted.20 Thus, petitioner was not able to
gain entry to the lot.21
2) The Government is hereby ordered to make direct payment
of the just compensation due to PIATCO; and On 26 July 2006, the Court of Appeals rendered the assailed
decision22 granting respondent’s petition. It ruled that the board
3) The Government is hereby ordered to defray the expenses of resolution which authorized the filing of the expropriation complaint
the BOC in the sum of ₱3,500,000.00. lacked exactitude and particularity which made it invalid; that there was
no genuine necessity for the expropriation of the five (5)-square meter lot
We DECLARE the issue of the appointment of DG Jones and Partners as and; that the reliance on Republic Act (R.A.) No. 8974 in fixing the value of
an independent appraiser of the Ninoy Aquino International Airport the property contravenes the judicial determination of just compensation.
Passenger Terminal III MOOT AND ACADEMIC. The temporary restraining Petitioner moved23 for reconsideration but the motion was rejected.24
order issued on January 9,2008, against the implementation of the May 3,
2007; May 18, 2007; and January 7, 2008 orders of the Regional Trial Hence, this petition.
Court of Pasay City, Branch 117 is hereby made PERMANENT.
The issues raised by petitioner can be summarized as follows:
SO ORDERED.
1. Whether there was sufficient authority from the petitioner’s
#7 G.R. No. 175983 April 16, 2009 board of directors to institute the expropriation complaint; and

METROPOLITAN CEBU WATER DISTRICT (MCWD), Petitioner, 2. Whether the procedure in obtaining a writ of possession was
vs. properly observed.
J. KING AND SONS COMPANY, INC., Respondent.
Eminent domain is the right of the state to acquire private property for
DECISION public use upon payment of just compensation.25 The power of eminent
domain is inseparable in sovereignty being essential to the existence of
TINGA, J.: the State and inherent in government. Its exercise is proscribed by only
two Constitutional requirements: first, that there must be just
compensation, and second, that no person shall be deprived of life, liberty
Before us is a Rule 45 petition1 which seeks the reversal of the or property without due process of law26 .
decision2 and resolution3 of the Court of Appeals in CA-G.R. CEB-SP No.
00810. The Court of Appeals’ decision nullified the orders4 and the writ of
ProvRem Rule 67 Fulltext Page 78 of 119
As an inherent sovereign prerogative, the power to expropriate pertains The letter not only explicitly debunks respondent’s claim that there was
to the legislature. However, Congress may, as in fact it often does, no authorization from LWUA but it also identifies the lot sought to be
delegate the exercise of the power to government agencies, public expropriated with sufficient particularity.
officials and quasi-public entities. Petitioner is one of the numerous
government offices so empowered. Under its charter, P.D. No. 198, as It is settled that the validity of a complaint may be questioned
amended,27 petitioner is explicitly granted the power of eminent domain. immediately upon its filing through a motion to dismiss or raised
thereafter as an affirmative defense. However, there is no need to further
On 7 November 2000, Congress enacted R.A. No. 8974, entitled "An Act belabor the issue since it is established that petitioner has the legal
To Facilitate The Acquisition Of Right-Of-Way, Site Or Location For capacity to institute the expropriation complaint.
National Government Infrastructure Projects And For Other Purposes."
Section 2 thereof defines national government projects as follows: Anent the second issue involving the issuance of a writ of possession, a
discussion on the various stages in an expropriation proceeding is
Sec. 2. National Government Projects.—The term "national government necessary.
projects" shall refer to all national government infrastructure, engineering
works and service contracts, including projects undertaken by The general rule is that upon filing of the expropriation complaint, the
government-owned and -controlled corporations, all projects covered by plaintiff has the right to take or enter into possession of the real property
Republic Act No. 6957, as amended by Republic Act No. 7718, otherwise involved if he deposits with the authorized government depositary an
known as the Build-Operate-and-Transfer Law, and other related and amount equivalent to the assessed value of the property for purposes of
necessary activities, such as site acquisition, supply and/or installation of taxation. An exception to this procedure is provided by R.A. No. 897434 . It
equipment and materials, implementation, construction, completion, requires the payment of one hundred percent (100%) of the zonal value
operation, maintenance, improvement, repair and rehabilitation, of the property to be expropriated to entitle the plaintiff to a writ of
regardless of source of funding." (emphasis ours) possession.

R.A. No. 8974 includes projects undertaken by government owned and In an expropriation proceeding there are two stages, first, is the
controlled corporations,28 such as petitioner. Moreover, the Implementing determination of the validity of the expropriation, and second is the
Rules and Regulations of R.A. No. 8974 explicitly includes water supply, determination of just compensation.35 In Tan v. Republic,36 we explained
sewerage, and waste management facilities among the national the two (2) stages in an expropriation proceeding to wit:
government projects covered by the law.29 It is beyond question,
therefore, that R.A. No. 8974 applies to the expropriation subject of this
case. (1) Determination of the authority of the plaintiff to exercise the
power of eminent domain and the propriety of its exercise in
the context of the facts involved in the suit. It ends with an
The Court of Appeals held that the board resolution authorizing the order, if not of dismissal of the action, with condemnation
expropriation lacked exactitude and particularity. It described the board declaring that the plaintiff has a lawful right to take the
resolution as akin to a general warrant in criminal law and as such property sought to be condemned for the public use or
declared it invalid. Respondent reiterates the same argument in its purpose described in the complaint, upon payment of just
comment and adds that petitioner’s exercise of the power of eminent compensation. An order of expropriation is final. An order of
domain was not reviewed by the LWUA. dismissal, if this be ordained, would be a final one, as it finally
disposes of the action and leaves nothing more to be done by
A corporation does not have powers beyond those expressly conferred the courts on the merits. The order of expropriation would also
upon it by its enabling law. Petitioner’s charter provides that it has the be a final one for after its issuance, no objection to the right of
powers, rights and privileges given to private corporations under existing condemnation shall be heard. The order of expropriation may
laws, in addition to the powers granted in it.30 All the powers, privileges, be appealed by any party aggrieved thereby by filing a record
and duties of the district shall be exercised and performed by and on appeal.
through the board and that any executive, administrative or ministerial
power may be delegated and redelegated by the board to any of its (2) Determination by the court of the just compensation for the
officers or agents for such property sought to be taken with the assistance of not more
than three (3) commissioners. The order fixing the just
purpose.31 Being a corporation, petitioner can exercise its powers only compensation on the basis of the evidence before the court
through its board of directors. and findings of the commissioners would likewise be a final
one, as it would leave nothing more to be done by the court
For petitioner to exercise its power of eminent domain, two requirements regarding the issue. A second and separate appeal may be
should be met, namely: first, its board of directors passed a resolution taken from this order fixing the just compensation.37
authorizing the expropriation, and; second, the exercise of the power of
eminent domain was subjected to review by the LWUA. In this case, Thus, the determination of the necessity of the expropriation is a
petitioner’s board of directors approved on 27 February 2004, Board justiciable question which can only be resolved during the first stage of an
Resolution No. 015-200432 authorizing its general manager to file expropriation proceeding. Respondent’s claim that the expropriated
expropriation and other cases. Moreover, the LWUA did review and gave property is too small to be considered for public use can only be resolved
its stamp of approval to the filing of a complaint for the expropriation of during that stage.
respondent’s lot. Specifically, the LWUA through its Administrator,
Lorenzo H. Jamora, wrote petitioner’s manager, Armando H. Paredes, a Further, the Court of Appeals ruled that Section 4 of R.A. No. 8974 runs
letter dated 28 February 200533 authorizing petitioner to file the counter to the express mandate of Section 2 of Rule 67.38 It held that the
expropriation case "against the owner of the five-square meter portion of law undermined the principle that the determination of just compensation
Lot No. 921-A covered by TCT No. 168805, pursuant to Section 25 of P.D. is a judicial function. However, this Court has already settled the issue. In
No. 198, as amended." Republic v. Gingoyon,39 this Court held that:

ProvRem Rule 67 Fulltext Page 79 of 119


It is the plain intent of Rep. Act No. 8974 to supersede the system of implementing agency an order to take possession of the property and
deposit under Rule 67 with the scheme of "immediate payment" in cases start the implementation of the project."49 Under this statutory provision,
involving national government infrastructure projects. when the government, its agencies or government-owned and controlled
corporations, make the required provisional payment, the trial court has a
xxx ministerial duty to issue a writ of possession. In Capitol Steel Corporation
v. PHIVIDEC Industrial Authority,50 we held that:

It likewise bears noting that the appropriate standard of just


compensation is a substantive matter. It is well within the province of the Upon compliance with the requirements, a petitioner in an expropriation
legislature to fix the standard, which it did through the enactment of Rep. case…is entitled to a writ of possession as a matter of right and it
Act No. 8974. Specifically, this prescribes the new standards in becomes the ministerial duty of the trial court to forthwith issue the writ
determining the amount of just compensation in expropriation cases of possession. No hearing is required and the court neither exercises its
relating to national government infrastructure projects, as well as the discretion or judgment in determining the amount of the provisional
manner of payment thereof. value of the properties to be expropriated as the legislature has fixed the
amount under Section 4 of R.A. No. 8974.51 (emphasis ours)

At the same time, Section 14 of the Implementing Rules recognizes the


continued applicability of Rule 67 on procedural aspects when it provides It is mandatory on the trial court’s part to issue the writ of possession and
"all matters regarding defenses and objections to the complaint, issues on on the sheriff’s part to deliver possession of respondent’s property to
uncertain ownership and conflicting claims, effects of appeal on the rights petitioner pursuant to the writ.
of the parties, and such other incidents affecting the complaint shall be
resolved under the provisions on expropriation of Rule 67 of the Rules of WHEREFORE, the Court of Appeals’ Decision dated 26 July 2006 and
Court.40 Resolution dated 28 September 2006 are REVERSED. The ORDERS of the
Regional Trial Court dated 01 April 2005 and 9 May 2005 are hereby
R.A. No. 8974 does not take away from the courts the power to judicially REINSTATED. The Regional Trial Court is further DIRECTED to immediately
determine the amount of just compensation. The law merely sets the REMIT the amount of ₱17,500.00 to respondent and to REQUIRE the
minimum price of the property as the provisional value. Thus, sheriff to implement the writ of possession. The case is REMANDED to the
trial court for further proceedings.

the amount of just compensation must still be determined by the courts


according to the standards set forth in Section 541 of R.A. No. 8974. SO ORDERED.

R.A. No. 8974 provides a different scheme for the obtention of a writ of
possession. The law does not require a deposit with a government bank;
instead it requires the government to immediately pay the property #8 G.R. No. 156093 February 2, 2007
owner.42 The provisional character of this payment means that it is not yet
final, yet, sufficient under the law to entitle the Government to the writ of NATIONAL POWER CORP., Petitioner,
possession over the expropriated property.43 The provisional payment is a vs.
prerequisite44 and a trigger45 for the issuance of the writ of possession. In SPOUSES NORBERTO AND JOSEFINA DELA CRUZ, METROBANK,
Gingoyon,46 we held that: Dasmariñas, Cavite Branch, REYNALDO FERRER, and S.K. DYNAMICS
MANUFACTURER CORP., Respondents.
It is the plain intent of Rep. Act No. 8974 to supersede the system of
deposit under Rule 67 with the scheme of "immediate payment" in cases DECISION
involving national government infrastructure projects.47

VELASCO, JR., J.:


xxx

The Case
Rep. Act. No. 8974 is plainly clear in imposing the requirement of
immediate prepayment, and no amount of statutory deconstruction can
evade such requisite. It enshrines a new approach towards eminent In this petition for review under Rule 45 of the Rules of Court, petitioner
domain that reconciles the inherent unease attending expropriation National Power Corporation (NAPOCOR) seeks to annul and set aside the
proceedings with a position of fundamental equity. While expropriation November 18, 2002 Decision1 of the Court of Appeals (CA) in CA-G.R. CV
proceedings have always demanded just compensation in exchange for No. 67446, which affirmed the December 28, 1999 Order2 of the Imus,
private property, the previous deposit requirement impeded immediate Cavite Regional Trial Court (RTC), Branch XX in Civil Case No. 1816-98,
compensation to the private owner, especially in cases wherein the which fixed the fair market value of the expropriated lots at PhP 10,000.00
per square meter.
determination of the final amount of compensation would prove highly
disputed. Under the new modality prescribed by Rep. Act. No. 8974, the
private owner sees immediate monetary recompense, with the same The Facts
degree of speed as the taking of his/her property.481avvphi1
Petitioner NAPOCOR is a government-owned and controlled corporation
Petitioner was supposed to tender the provisional payment directly to created under Republic Act No. 6395, as amended, with the mandate of
respondent during a hearing which it had failed to attend. Petitioner, developing hydroelectric power, producing transmission lines, and
then, deposited the provisional payment with the court. The trial court did developing hydroelectric power throughout the Philippines. NAPOCOR
not commit an error in accepting the deposit and in issuing the writ of decided to acquire an easement of right-of-way over portions of land
possession. The deposit of the provisional amount with the court is within the areas of Dasmariñas and Imus, Cavite for the construction and
equivalent to payment. maintenance of the proposed Dasmariñas-Zapote 230 kV Transmission
Line Project.3
Indeed, Section 4 of R.A. No. 8974 is emphatic to the effect that "upon
compliance with the guidelines…the court shall immediately issue to the
ProvRem Rule 67 Fulltext Page 80 of 119
On November 27, 1998, petitioner filed a Complaint4 for eminent domain Orchard Golf and Country Club
and expropriation of an easement of right-of-way against respondents as
registered owners of the parcels of land sought to be expropriated, which Golden City Subdivision
were covered by Transfer Certificates of Title (TCT) Nos. T-313327, T-
671864, and T-454278. The affected areas were 51.55, 18.25, and 14.625
square meters, respectively, or a total of 84.425 square meters. Southfield Subdivisions

After respondents filed their respective answers to petitioner’s Complaint, Arcontica Sports Complex
petitioner deposited PhP 5,788.50 to cover the provisional value of the
land in accordance with Section 2, Rule 67 of the Rules of Court.5 Then, on Max’s Restaurant
February 25, 1999, petitioner filed an Urgent Ex-Parte Motion for the
Issuance of a Writ of Possession, which the trial court granted in its March Waltermart Shopping Mall
9, 1999 Order. The trial court issued a Writ of Possession over the lots
owned by respondents spouses de la Cruz and respondent Ferrer on
UMC Medical Center
March 10, 1999 and April 12, 1999, respectively.

Several savings and Commercial Banks as


However, the trial court dropped the Dela Cruz spouses and their
well as several Gasoline stations.
mortgagee, Metrobank, as parties-defendants in its May 11, 1999
Order,6 in view of the Motion to Intervene filed by respondent/intervenor
Virgilio M. Saulog, who claimed ownership of the land sought to be Community centers such as, [sic] churches, public
expropriated from respondents spouses Dela Cruz. markets, shopping malls, banks and gasoline stations
are easily accessible from the subject real properties.
On June 24, 1999, the trial court terminated the pre-trial in so far as
respondent Ferrer was concerned, considering that the sole issue was the Convenience facilities such as electricity, telephone
amount of just compensation, and issued an Order directing the service as well as pipe potable water supply system
constitution of a Board of Commissioners with respect to the property of are all available along Gen. Emilio Aguinaldo
respondent S.K. Dynamics. The trial court designated Mr. Lamberto C. Highway.
Parra, Cavite Provincial Assessor, as chairman, while petitioner nominated
the Municipal Assessor of Dasmariñas, Mr. Regalado T. Andaya, as Public transportation consisting of passenger
member. Respondent S.K. Dynamics did not nominate any commissioner. jeepneys and buses as well taxicabs are [sic] regularly
available along Gen. E. Emilio Aguinaldo Highway
As to the just compensation for the property of Saulog, successor-in- [sic].
interest of the Dela Cruz spouses, the trial court ordered the latter and
petitioner to submit their compromise agreement. xxxx

The commissioners conducted an ocular inspection of S.K. Dynamics’ IV. HIGHEST AND MOST PROFITABLE USE
property, and on October 8, 1999, they submitted a report to the trial
court, with the following pertinent findings:
xxxx

In arriving our [sic] estimate of values our studies and analysis include the
The subject property is situated within the
following:
residential/commercial zone and considering the area affected
and taking into consideration, their location, shape, lot
I. PROPERTY LOCATION topography, accessibility and the predominant uses of
properties in the neighborhood, as well as the trend of land
As shown to us on-site during our ocular inspection, developments in the vicinity, we are on the opinion that the
the appraised property is land only, identified as the highest and most profitable use of the property is good for
area affected by the construction of the National residential and commercial purposes.
Power Corporation (NPC) Dasmariñas-Zapote 230KV
Transmission Lines Project, located within Barangay V. VALUATION OF LAND MARKET DATA
Salitran, Dasmariñas, Cavite registered in the name of
S.K. Dynamic[s] Manufacture[r], Corp., under Transfer
xxxx
Certificate of Title No. T-454278.

Based on the analysis of data gathered and making the proper


II. NEIGHBORHOOD DESCRIPTION
adjustments with respect to the location, area, shape, accessibility, and
the highest and best use of the subject properties, it is the opinion of the
The neighborhood particularly in the immediate herein commissioners that the fair market value of the subject real
vicinity is within a mixed residential and commercial properties is P10,000.00 per square meter, as of this date, October 05,
area, situated in the northern section of the 1999.7
Municipality of Dasmariñas which was transversed
[sic] by Gen. Emilio Aguinaldo Highway [where]
Thus, both commissioners recommended that the property of S.K.
several residential subdivisions and commercial
Dynamics to be expropriated by petitioner be valued at PhP 10,000.00 per
establishment[s] are located.
square meter.

Considered as some of the important improvements


The records show that the commissioners did not afford the parties the
[on] the vicinity are (within 1.5 radius)
opportunity to introduce evidence in their favor, nor did they conduct

ProvRem Rule 67 Fulltext Page 81 of 119


hearings before them. In fact, the commissioners did not issue notices to By way of opposition, [respondent] Dynamics countered that the
the parties to attend hearings nor provide the concerned parties the valuation of a lot under expropriation is reckoned at the time of its taking
opportunity to argue their respective causes. by the government. And since in the case at bar, the writ of possession
was issued on March 10, 1999, the price or value for 1999 must be the
Upon the submission of the commissioners’ report, petitioner was not one to be considered.
notified of the completion or filing of it nor given any opportunity to file
its objections to it. We find for the defendant.

On December 1, 1999, respondent Ferrer filed a motion adopting in toto The PAR Resolution alluded to by [petitioner] was passed in 1995 or four
the commissioners’ report with respect to the valuation of his (4) years [before] the lot in question was taken over by the government.
property.8 On December 28, 1999, the trial court consequently issued the This explains why the price or cost of the land has considerably increased.
Order approving the commissioners’ report, and granted respondent Besides, the valuation of P10,000.00 per sq.m. was the one recommended
Ferrer’s motion to adopt the subject report. Subsequently, the just by the commissioner designated by [petitioner] itself and concurred in by
compensation for the disparate properties to be expropriated by the Provincial Assessor of Cavite.
petitioner for its project was uniformly pegged at PhP 10,000.00 per
square meter. Be that as it may, the Motion for Reconsideration is denied.

Incidentally, on February 11, 2000, respondent S.K. Dynamics filed a SO ORDERED.10


motion informing the trial court that in addition to the portion of its
property covered by TCT No. T-454278 sought to be expropriated by
petitioner, the latter also took possession of an 8.55-square meter portion The Ruling of the Court of Appeals
of S.K. Dynamics’ property covered by TCT No. 503484 for the same
purpose––to acquire an easement of right-of-way for the construction Unsatisfied with the amount of just compensation, petitioner filed an
and maintenance of the proposed Dasmariñas-Zapote 230 kV appeal before the CA. In resolving the appeal, the CA made the following
Transmission Line Project. Respondent S.K. Dynamics prayed that said findings:
portion be included in the computation of the just compensation to be
paid by petitioner. We find nothing on record which would warrant the reversal of the Order
dated December 28, 1999 of the court a quo.
On the same date, the Imus, Cavite RTC granted S.K. Dynamics’ motion to
have the 8.55-square meter portion of its property included in the [Petitioner] submits that the order of the court a quo adopting the
computation of just compensation.1awphi1.net Commissioners [sic] Valuation Report, fixing the just compensation for the
subject lots in the amount of P10,000.00 per square meter is exhorbitant
The Ruling of the Regional Trial Court [sic], highly speculative and without any basis. In support thereto,
[petitioner] presented before the court a quo the Provincial Appraisal
As previously stated, in its December 28, 1999 Order, the trial court fixed Committee of Cavite Resolution No. 08-95 x x x which fixed the fair
the just compensation to be paid by petitioner at PhP 10,000.00 per market value of lots located along Gen. Aguinaldo Highway, Dasmariñas,
square meter. The relevant portion of the said Order reads as follows: Cavite, which incidentally includes the lots subject of this proceedings
[sic], in the amount of P3,000.00 per square meter.

On October 8, 1999, a Commissioner’s Valuation Report was submitted in


We do not agree.
Court by the Provincial Assessor of Cavite and by the Municipal Assessor
of Dasmariñas, Cavite. Quoting from said Report, thus:
"The nature and character of the land at the time of its taking is the
"Based on the analysis of data gathered and making the proper principal criterion to determine just compensation to the land owner."
(National Power Corporation vs. Henson, 300 SCRA 751-756).
adjustments with respect to location, area, shape, accessibility, and the
highest and best use of the subject properties, it is the opinion of herein
commissioners that the fair market value of the subject real properties is The CA then cited Section 4, Rule 67 of the 1997 Rules of Civil
₧10,000.00 per square meter, as of this date, October 05, 1999." Procedure11 to explain why Resolution No. 08-95 could not "be used as [a]
basis for determining the just compensation of the subject lots, which by
Finding the opinion of the Commissioners to be in order, this Court reason of the changed commercial conditions in the vicinity, could have
approves the same. Accordingly, the Motion filed by [respondent] increased its value greater than its value three (3) years ago." The said
Reynaldo Ferrer adopting said valuation report is granted. resolution, which fixed the fair market value of the lots, including that of
the disputed lots along Gen. Aguinaldo Highway, was approved on
October 25, 1995, while petitioner filed the Complaint for the
SO ORDERED. 9 expropriation of the disputed lots on November 27, 1998, or more than
three (3) years had elapsed after said resolution was approved. Reflecting
On January 20, 2000, petitioner filed a Motion for Reconsideration of the on the commissioners’ report, the CA noted that since the property
abovementioned Order, but said motion was denied in the trial court’s underwent important changes and improvements, "the highest and most
March 23, 2000 Order, which states that: profitable use of the property is good for residential and commercial
purposes."
The basis of [petitioner] in seeking to set aside the Order dated December
28, 1999 is its claim that the Commissioners’ Report fixing the just As regards the commissioners’ failure to conduct a hearing "to give the
compensation at P10,000.00 per square meter is exorbitant, unjust and parties the opportunity to present their respective evidence," as alleged
unreasonable. To support its contention, [petitioner] invoked Provincial by petitioner, the CA opined that "[t]he filing by [petitioner] of a motion
Appraisal Committee Report No. 08-95 dated October 25, 1995 which set for reconsideration accorded it ample opportunity to dispute the findings
the just compensation of lots along Gen. Aguinaldo Highway at P3,000.00 of the commissioners, so that [petitioner] was as fully heard as there
per sq.m. only. might have been hearing actually taken place x x x."

ProvRem Rule 67 Fulltext Page 82 of 119


The CA ultimately rendered its judgment, as follows: which oath shall be filed in court with the other proceedings in the case.
Evidence may be introduced by either party before the commissioners
WHEREFORE, premises considered, the present appeal is hereby who are authorized to administer oaths on hearings before them, and the
DISMISSED for lack of merit. The Order dated December 28, 1999 and commissioners shall, unless the parties consent to the contrary, after due
March 23, 2000 of the court a quo are hereby AFFIRMED by this Court. notice to the parties to attend, view and examine the property sought to
be expropriated and its surroundings, and may measure the same, after
which either party may, by himself or counsel, argue the case. The
SO ORDERED.12 commissioners shall assess the consequential damages to the property
not taken and deduct from such consequential damages the
Significantly, petitioner did not file a Motion for Reconsideration of the consequential benefits to be derived by the owner from the public use or
CA November 18, 2002 Decision, but it directly filed a petition for review purpose of the property taken, the operation of its franchise by the
before us. corporation or the carrying on of the business of the corporation or
person taking the property. But in no case shall the consequential benefits
The Issues assessed exceed the consequential damages assessed, or the owner be
deprived of the actual value of his property so taken.

In this petition for review, the issues are the following:


SEC. 7. Report by commissioners and judgment thereupon.—The court
may order the commissioners to report when any particular portion of the
PETITIONER WAS DENIED DUE PROCESS WHEN IT WAS NOT ALLOWED
real estate shall have been passed upon by them, and may render
TO PRESENT EVIDENCE ON THE REASONABLE VALUE OF THE
judgment upon such partial report, and direct the commissioners to
EXPROPRIATED PROPERTY BEFORE THE BOARD OF COMMISSIONERS.
proceed with their work as to subsequent portions of the property sought
to be expropriated, and may from time to time so deal with such
THE VALUATION OF JUST COMPENSATION HEREIN WAS NOT BASED property. The commissioners shall make a full and accurate report to the
FROM THE EVIDENCE ON RECORD AND OTHER AUTHENTIC court of all their proceedings, and such proceedings shall not be effectual
DOCUMENTS.13 until the court shall have accepted their report and rendered judgment in
accordance with their recommendations. Except as otherwise expressly
The Court’s Ruling ordered by the court, such report shall be filed within sixty (60) days from
the date the commissioners were notified of their appointment, which
time may be extended in the discretion of the court. Upon the filing of
We find this petition meritorious.
such report, the clerk of the court shall serve copies thereof on all
interested parties, with notice that they are allowed ten (10) days within
It is beyond question that petitions for review may only raise questions of which to file objections to the findings of the report, if they so desire.
law which must be distinctly set forth;14thus, this Court is mandated to
only consider purely legal questions in this petition, unless called for by
SEC. 8. Action upon commissioners’ report.—Upon the expiration of the
extraordinary circumstances.
period of ten (10) days referred to in the preceding section, or even
before the expiration of such period but after all the interested parties
In this case, petitioner raises the issue of denial of due process because it have filed their objections to the report or their statement of agreement
was allegedly deprived of the opportunity to present its evidence on the therewith, the court may, after hearing, accept the report and render
just compensation of properties it wanted to expropriate, and the judgment in accordance therewith; or, for cause shown, it may recommit
sufficiency of the legal basis or bases for the trial court’s Order on the the same to the commissioners for further report of facts; or it may set
matter of just compensation. Unquestionably, a petition for review under aside the report and appoint new commissioners; or it may accept the
Rule 45 of the Rules of Court is the proper vehicle to raise the issues in report in part and reject it in part; and it may make such order or render
question before this Court. such judgment as shall secure to the plaintiff the property essential to the
exercise of his right of expropriation, and to the defendant just
In view of the significance of the issues raised in this petition, because this compensation for the property so taken.
case involves the expenditure of public funds for a clear public purpose,
this Court will overlook the fact that petitioner did not file a Motion for Based on these provisions, it is clear that in addition to the ocular
Reconsideration of the CA November 18, 2002 Decision, and brush aside inspection performed by the two (2) appointed commissioners in this
this technicality in favor of resolving this case on the merits. case, they are also required to conduct a hearing or hearings to determine
just compensation; and to provide the parties the following: (1) notice of
First Issue: Petitioner was deprived of due process when it was not given the said hearings and the opportunity to attend them; (2) the opportunity
the opportunity to present evidence before the commissioners to introduce evidence in their favor during the said hearings; and (3) the
opportunity for the parties to argue their respective causes during the
said hearings.
It is undisputed that the commissioners failed to afford the parties the
opportunity to introduce evidence in their favor, conduct hearings before
them, issue notices to the parties to attend hearings, and provide the The appointment of commissioners to ascertain just compensation for the
opportunity for the parties to argue their respective causes. It is also property sought to be taken is a mandatory requirement in expropriation
undisputed that petitioner was not notified of the completion or filing of cases. In the instant expropriation case, where the principal issue is the
the commissioners’ report, and that petitioner was also not given any determination of just compensation, a hearing before the commissioners
opportunity to file its objections to the said report. is indispensable to allow the parties to present evidence on the issue of
just compensation. While it is true that the findings of commissioners may
be disregarded and the trial court may substitute its own estimate of the
A re-examination of the pertinent provisions on expropriation, under Rule
value, the latter may only do so for valid reasons, that is, where the
67 of the Rules of Court, reveals the following:
commissioners have applied illegal principles to the evidence submitted
to them, where they have disregarded a clear preponderance of evidence,
SEC. 6. Proceedings by commissioners.—Before entering upon the or where the amount allowed is either grossly inadequate or excessive.
performance of their duties, the commissioners shall take and subscribe Thus, "trial with the aid of the commissioners is a substantial right that
an oath that they will faithfully perform their duties as commissioners, may not be done away with capriciously or for no reason at all."15
ProvRem Rule 67 Fulltext Page 83 of 119
In this case, the fact that no trial or hearing was conducted to afford the the winning party and might treat the Motion for Reconsideration and the
parties the opportunity to present their own evidence should have evidence adduced during the hearing of said motion perfunctorily and in
impelled the trial court to disregard the commissioners’ findings. The a cavalier fashion. The incident might not receive the evaluation and
absence of such trial or hearing constitutes reversible error on the part of judgment of an impartial or neutral judge. In sum, the constitutional
the trial court because the parties’ (in particular, petitioner’s) right to due guarantee of due process still requires that a party should be given the
process was violated. fullest and widest opportunity to adduce evidence during trial, and the
availment of a motion for reconsideration will not satisfy a party’s right to
The Court of Appeals erred in ruling that the petitioner was not deprived procedural due process, unless his/her inability to adduce evidence during
of due process when it was able to file a motion for reconsideration trial was due to his/her own fault or negligence.

In ruling that petitioner was not deprived of due process because it was Second Issue: The legal basis for the determination of just compensation
able to file a Motion for Reconsideration, the CA had this to say: was insufficient

[Petitioner], further, asserts that "the appointed commissioners failed to In this case, it is not disputed that the commissioners recommended that
conduct a hearing to give the parties the opportunity to present their the just compensation be pegged at PhP 10,000.00 per square meter. The
respective evidence. According to [petitioner], the Commissioners commissioners arrived at the figure in question after their ocular
Valuation Report was submitted on October 8, 1999 in violation of the inspection of the property, wherein they considered the surrounding
appellant’s right to due process as it was deprived of the opportunity to structures, the property’s location and, allegedly, the prices of the other,
present evidence on the determination of the just compensation." contiguous real properties in the area. Furthermore, based on the
commissioners’ report, the recommended just compensation was
determined as of the time of the preparation of said report on October 5,
We are not persuaded. 1999.

The filing by [petitioner] of a motion for reconsideration accorded it In B.H. Berkenkotter & Co. v. Court of Appeals, we held, thus:
ample opportunity to dispute the findings of the commissioners, so that
[petitioner] was as fully heard as there might have been hearing actually
taken place. "Denial of due process cannot be successfully invoked by a Just compensation is defined as the full and fair equivalent of the
party who has had the opportunity to be heard on his motion for property sought to be expropriated. The measure is not the taker’s gain
reconsideration." (Vda. De Chua vs. Court of Appeals, 287 SCRA 33, 50).16 but the owner’s loss. The compensation, to be just, must be fair not only
to the owner but also to the taker. Even as undervaluation would deprive
the owner of his property without due process, so too would its
In this respect, we are constrained to disagree with the CA ruling, and overvaluation unduly favor him to the prejudice of the public.
therefore, set it aside.

To determine just compensation, the trial court should first ascertain the
While it is true that there is jurisprudence supporting the rule that the market value of the property, to which should be added the consequential
filing of a Motion for Reconsideration negates allegations of denial of due damages after deducting therefrom the consequential benefits which may
process, it is equally true that there are very specific rules for arise from the expropriation. If the consequential benefits exceed the
expropriation cases that require the strict observance of procedural and consequential damages, these items should be disregarded altogether as
substantive due process,17 because expropriation cases involve the the basic value of the property should be paid in every case.
admittedly painful deprivation of private property for public purposes and
the disbursement of public funds as just compensation for the private
property taken. Therefore, it is insufficient to hold that a Motion for The market value of the property is the price that may be agreed upon by
Reconsideration in an expropriation case cures the defect in due process. parties willing but not compelled to enter into the contract of sale. Not
unlikely, a buyer desperate to acquire a piece of property would agree to
pay more, and a seller in urgent need of funds would agree to accept less,
As a corollary, the CA’s ruling that "denial of due process cannot be than what it is actually worth. x x x
successfully invoked by a party who has had the opportunity to be heard
on his motion for reconsideration," citing Vda. de Chua v. Court of
Appeals, is not applicable to the instant case considering that the cited Among the factors to be considered in arriving at the fair market value of
case involved a lack of notice of the orders of the trial court in granting the property are the cost of acquisition, the current value of like
letters of administration. It was essentially a private dispute and therefore, properties, its actual or potential uses, and in the particular case of lands,
no public funds were involved. It is distinct from this expropriation case their size, shape, location, and the tax declarations thereon.
where grave consequences attached to the orders of the trial court when
it determined the just compensation. It is settled that just compensation is to be ascertained as of the time of
the taking, which usually coincides with the commencement of the
The Court takes this opportunity to elucidate the ruling that the expropriation proceedings. Where the institution of the action precedes
opportunity to present evidence incidental to a Motion for entry into the property, the just compensation is to be ascertained as of
Reconsideration will suffice if there was no chance to do so during the the time of the filing of the complaint.18
trial. We find such situation to be the exception and not the general rule.
The opportunity to present evidence during the trial remains a vital We note that in this case, the filing of the complaint for expropriation
requirement in the observance of due process. The trial is materially and preceded the petitioner’s entry into the property.
substantially different from a hearing on a Motion for Reconsideration. At
the trial stage, the party is usually allowed several hearing dates Therefore, it is clear that in this case, the sole basis for the determination
depending on the number of witnesses who will be presented. At the of just compensation was the commissioners’ ocular inspection of the
hearing of said motion, the trial court may not be more accommodating properties in question, as gleaned from the commissioners’ October 5,
with the grant of hearing dates even if the movant has many available 1999 report. The trial court’s reliance on the said report is a serious error
witnesses. Before the decision is rendered, a trial court has an open mind considering that the recommended compensation was highly speculative
on the merits of the parties’ positions. After the decision has been issued, and had no strong factual moorings. For one, the report did not indicate
the trial court’s view of these positions might be inclined to the side of the fair market value of the lots occupied by the Orchard Golf and
ProvRem Rule 67 Fulltext Page 84 of 119
Country Club, Golden City Subdivision, Arcontica Sports Complex, and decreasing from P10,000.00 to P3,000.00 the commissioners' fee for each
other business establishments cited. Also, the report did not show how of the three commissioners.
convenience facilities, public transportation, and the residential and
commercial zoning could have added value to the lots being On April 15, 1996, private respondent National Power Corporation
expropriated. (NAPOCOR) filed a Complaint for Eminent Domain, seeking to expropriate
a portion of petitioner Bank of the Philippine Islands' (BPI) property
Moreover, the trial court did not amply explain the nature and application located in Barrio Bucal, Dasmariñas, Cavite, for the purpose of
of the "highest and best use" method to determine the just compensation constructing and maintaining its Dasmariñas-Zapote 230 KV Transmission
in expropriation cases. No attempt was made to justify the recommended Line Project.
"just price" in the subject report through other sufficient and reliable
means such as the holding of a trial or hearing at which the parties could On August 1, 1996, pursuant to Section 2 of Rule 67 of the Rules of
have had adequate opportunity to adduce their own evidence, the Court,3 NAPOCOR deposited with the Philippine National Bank, NPC
testimony of realtors in the area concerned, the fair market value and tax Branch, in Quezon City, the amount of P3,013.60, equivalent to the
declaration, actual sales of lots in the vicinity of the lot being expropriated assessed value of the property. On August 15, 1996, NAPOCOR notified
on or about the date of the filing of the complaint for expropriation, the BPI, through registered mail, of its intention to take possession of the
pertinent zonal valuation derived from the Bureau of Internal Revenue, property. Thereafter, the trial court granted their urgent ex-parte motion
among others. for the issuance of a writ of possession and authorized them to enter and
take possession of the premises.4
More so, the commissioners did not take into account that the Asian
financial crisis in the second semester of 1997 affected the fair market Previously, petitioner BPI filed a motion for bill of particulars which the
value of the subject lots. Judicial notice can be taken of the fact that after trial court denied.5 Consequently, BPI moved for the dismissal of the case
the crisis hit the real estate market, there was a downward trend in the and the same was granted without prejudice to its reinstatement.6 Private
prices of real estate in the country. respondent NAPOCOR filed a motion for reconsideration. The trial court
granted the motion and reinstated the case.7
Furthermore, the commissioners’ report itself is flawed considering that its
recommended just compensation was pegged as of October 5, 1999, or In its Order dated November 28, 1997,8 the trial court designated three
the date when the said report was issued, and not the just compensation commissioners to determine the just value of the property subject of the
as of the date of the filing of the complaint for expropriation, or as of expropriation in this case, namely: Mr. Lamberto C. Parra, Provincial
November 27, 1998. The period between the time of the filing of the Assessor of Cavite; Mr. Regalado Andaya, Municipal Assessor of
complaint (when just compensation should have been determined), and Dasmariñas, Cavite; and Mr. Rodolfo D. Leonen, Defendant's
the time when the commissioners’ report recommending the just Representative.
compensation was issued (or almost one [1] year after the filing of the
complaint), may have distorted the correct amount of just compensation.
Accordingly, on February 26, 1999, the Commissioners submitted its
Report which assessed the sum of the area of the property taken and the
Clearly, the legal basis for the determination of just compensation in this estimated value of just compensation at 75.34 square meters x P10,000.00
case is insufficient as earlier enunciated. This being so, the trial court’s = P753,400.00, and recommended an additional payment of P524,660.00
ruling in this respect should be set aside. as severance damage, or a total of P1,278,060.00.9 Likewise, they
submitted an undated Commissioners' Valuation Report citing the
WHEREFORE, the petition is GRANTED. The December 28, 1999 and "Market Data Approach" as the method used in arriving at the amount of
March 23, 2000 Orders of the Imus, Cavite RTC and the November 18, P10,000.00 per square meter as just compensation, whereby the value of
2002 Decision of the CA are hereby SET ASIDE. This case is remanded to the land is based on sales and listing of comparable property registered
the said trial court for the proper determination of just compensation in within the immediate vicinity.10
conformity with this Decision. No costs.
On August 5, 1999, the trial court rendered judgment in favor of BPI, the
SO ORDERED. dispositive portion of which reads:

WHEREFORE, judgment is hereby rendered declaring that the


portion of the parcel of land situated in Bucal, Dasmariñas,
#9 G.R. No. 160890 November 10, 2004 Cavite, embraced in, and covered by, Transfer Certificate of Title
No. T-292517 of the Registry of Deed of Cavite consisting of
75.34 square meters to have been lawfully expropriated and
BANK OF THE PHILIPPINE ISLANDS, petitioner, now belongs to the plaintiff to be used for the construction and
vs. maintenance of its Dasmariñas-Zapote 230 KV Transmission
COURT OF APPEALS and NATIONAL POWER Line Project.
CORPORATION, respondents.

The plaintiff is hereby ordered to pay to the defendant, through


DECISION the Branch Clerk of this Court, the fair market value of the
property at P10,000.00 per square meter or a total sum of
YNARES-SANTIAGO, J.: P753,400.00 with legal rate of interest reckoned from the date
of possession by the plaintiff.
This is a petition for review under Rule 45 of the Rules of Court, assailing
the Decision dated August 30, 2002 of the Court of Appeals in CA-G.R. CV The commissioner's fee is hereby fixed at P10,000.00 each to be
No. 69402,1 which reversed the Decision of the Regional Trial Court of paid by the plaintiff through the Branch Clerk of this Court.
Imus, Cavite, Branch 21,2 reducing from P10,000.00 to P3,000.00 the
amount of just compensation for the expropriated land of petitioner; and

ProvRem Rule 67 Fulltext Page 85 of 119


The Clerk of this Court is ordered to have a certified copy of this that the equivalent to be rendered for the property taken shall be real,
decision be registered in the office of the Register of Deeds of substantial, full, ample.15
Cavite.
In eminent domain or expropriation proceedings, the general rule is that
SO ORDERED.11 the just compensation which the owner of condemned property is
entitled to is the market value. Market value is "that sum of money which
After the denial of its motion for reconsideration, NAPOCOR appealed to a person desirous but not compelled to buy, and an owner willing but not
the Court of Appeals, which ruled as follows: compelled to sell, would agree on as a price to be given and received
therefor."16

WHEREFORE, the appealed judgment is hereby REVERSED. A


new one is entered ordering plaintiff-appellant NAPOCOR to After a careful perusal of the records, we find no reason to disturb this
pay defendant-appellant BPI the amount of P3,000.00 per finding of fact by the Court of Appeals, sufficiently supported as it is, by
square meter as just compensation for the expropriated land; the evidence on record.17
and P3,000.00 commissioner's fee to each of the three (3)
commissioners. We find that the rate imposed by the Commissioners is unsubstantiated.
No official documents were presented to reflect the true market value of
SO ORDERED.12 the subject lots in the surrounding area. The Commissioner's Report
merely states that the value of the land is based on sales and listings of
comparable property registered within the immediate vicinity without any
Petitioner BPI moved for the reconsideration of the decision of the Court evidence to support the market data provided.
of Appeals, but the same was denied for lack of merit.

In this instance, we accord more weight to Resolution No. 08-95


Hence, this petition for review based on the sole issue of whether the promulgated by the Provincial Appraisal Committee of Cavite held at the
Court of Appeals gravely abused its discretion and seriously erred in fixing Office of the Provincial Assessor on October 25, 1995.18 Said Resolution
the just compensation for the subject property at P3,000.00 per square pegs as fair and reasonable the value of P3,000.00 per square meter of all
meter. the lots in the Municipality of Dasmariñas, specifically along General
Aguinaldo Highway.
In petitions for review on certiorari under Rule 45 of the Rules of Court,
the general rule is that only questions of law may be raised by the parties The just compensation is determined as of the date of the taking of the
and passed upon by this Court. However, this rule admits of exceptions, to property or the filing of the complaint whichever came first.19 NAPOCOR
wit:
filed the complaint on April 15, 1996. A period of 6 months has elapsed
from the valuation of the Provincial Assessors and the filing of the
(a) where there is grave abuse of discretion; (b) when the complaint. We note the considerable discrepancy between the valuation
finding is grounded entirely on speculations, surmises or of the former and that of the Commissioners. Indeed, the appellate court
conjectures; (c) when the inference made is manifestly computed the increase of the valuation to be 233%.
mistaken, absurd or impossible; (d) when the judgment of the
Court of Appeals was based on a misapprehension of facts; (e) The Court of Appeals pointed out that more than 70% of the 200 lot
when the factual findings are conflicting; (f) when the Court of owners have entered into compromise agreements and accepted the
Appeals, in making its findings, went beyond the issues of the price set by the Provincial Appraisal Committee of Cavite. It is also worthy
case and the same are contrary to the admissions of both to note that one of the Commissioners in this case, Mr. Lamberto C. Parra,
appellant and appellee; (g) when the Court of Appeals was the Chairman Provincial Assessor and signatory of the same
manifestly overlooked certain relevant facts not disputed by the Resolution.
parties and which, if properly considered, would justify a
different conclusion; and, (h) where the findings of fact of the
Court of Appeals are contrary to those of the trial court, or are WHEREFORE, the petition for review on certiorari is DENIED. The Decision
mere conclusions without citation of specific evidence, or where of the Court of Appeals in CA-G.R. CV No. 69402, which reversed the
the facts set forth by the petitioner are not disputed by the decision of the Regional Trial Court of Imus, Cavite, Branch 21 in Civil Case
respondent, or where the findings of fact of the Court of No. 1298-96, is AFFIRMED in toto.
Appeals are premised on the absence of evidence and are
contradicted by the evidence on record.13 (Emphasis provided) SO ORDERED.

The case at bar falls under one of the exceptions, i.e., where the findings #10 G.R. No. 211666 February 25, 2015
of fact of the Court of Appeals are contrary to those of the trial court.
REPUBLIC OF THE PHILIPPINES, represented by the DEPARTMENT OF
Petitioner asserts that the finding of just compensation by the court- PUBLIC WORKS AND HIGHWAYS,Petitioners,
appointed commissioners was based on clear evidence of prior sales and vs.
acceptable market valuation methods. Petitioner likewise avers that the ARLENE R. SORIANO, Respondent.
valuation made by the commissioners must be accorded weight. Likewise
it argues that NAPOCOR is estopped from questioning the valuation of DECISION
the land considering that its own nominee concurred with the findings of
the other commissioners.
PERALTA, J.:

Just compensation is defined as the full and fair equivalent of the


property taken from its owner by the expropriator. The measure is not the Before the Court is a petition for review under Rule 45 of the Rules of
taker's gain, but the owner's loss.14 To compensate is to render something Court assailing the Decision1 dated November 15, 2013 and Order2 dated
which is equal in value to that taken or received. The word "just" is used March 10, 2014 of the Regional Trial Court (RTC), Valenzuela City, Branch
to intensify the meaning of the word "compensation"; to convey the idea 270, in Civil Case No. 140-V-10.
ProvRem Rule 67 Fulltext Page 86 of 119
The antecedent facts are as follows: 2) Condemning portion to the extent of 200 square meters of
the above-described parcel of land including improvements
On October 20, 2010, petitioner Republic of the Philippines, represented thereon, if there be any, free from all liens and encumbrances;
by the Department of Public Works and Highways (DPWH), filed a
Complaint3 for expropriation against respondent Arlene R. Soriano, the 3) Ordering the plaintiff to pay defendant Arlene R. Soriano
registered owner of a parcel of land consisting of an area of 200 square Php2,100.00 per square meter or the sum of Four Hundred
meters, situated at Gen. T De Leon, Valenzuela City, and covered by Twenty Thousand Pesos (Php420,000.00) for the 200 square
Transfer Certificate of Title (TCT) No. V-13790.4 In its Complaint, petitioner meters as fair, equitable, and just compensation with legal
averred that pursuant to Republic Act (RA) No. 8974, otherwise known as interest at 12% per annum from the taking of the possession of
"An Act to Facilitate the Acquisition of Right-Of-Way, Site or Location for the property, subject to the payment of all unpaid real property
National Government Infrastructure Projects and for other Purposes," the taxes and other relevant taxes, if there be any;
property sought to be expropriated shall be used in implementing the
construction of the North Luzon Expressway (NLEX)- Harbor Link Project 4) Plaintiff is likewise ordered to pay the defendant
(Segment 9) from NLEX to MacArthur Highway, Valenzuela City.5 consequential damages which shall include the value of the
transfer tax necessary for the transfer of the subject property
Petitioner duly deposited to the Acting Branch Clerk of Court the amount from the name of the defendant to that of the plaintiff;
of ₱420,000.00 representing 100% of the zonal value of the subject
property. Consequently, in an Order6 dated May 27, 2011, the RTC 5) The Office of the Register of Deeds of Valenzuela City, Metro
ordered the issuance of a Writ of Possession and a Writ of Expropriation Manila is directed to annotate this Decision in Transfer
for failure of respondent, or any of her representatives, to appear despite Certificate of Title No. V-13790 registered under the name of
notice during the hearing called for the purpose. Arlene R. Soriano.

In another Order7 dated June 21, 2011, the RTC appointed the following Let a certified true copy of this decision be recorded in the Registry of
members of the Board of Commissioners for the determination of just Deeds of Valenzuela City.
compensation: (1) Ms. Eunice O. Josue, Officer-in-Charge, RTC, Branch
270, Valenzuela City; (2) Atty. Cecilynne R. Andrade, Acting Valenzuela City
Assessor,City Assessor’s Office, Valenzuela City; and (3) Engr. Restituto Records of this case show that the Land Bank Manager’s Check Nos.
Bautista, of Brgy. Bisig,Valenzuela City. However, the trial court 0000016913 dated January 21, 2011 in the amount of Php400,000.00 and
subsequently revoked the appointment of the Board for their failure to 0000017263 dated April 28, 2011 in the amount of Php20,000.00 issued
submit a report as to the fair market value of the property to assist the by the Department of Public Works and Highways (DPWH) are already
court in the determination of just compensation and directed the parties stale. Thus, the said Office is hereby directed to issue another Manager’s
to submit their respective position papers.8 Thereafter, the case was set Check in the total amount Php420,000.00 under the name of the Office of
for hearing giving the parties the opportunity to present and identify all the Clerk of Court, Regional Trial Court, Valenzuela City earmarked for the
instant case.10
evidence in support of their arguments therein. According to the RTC, the
records of the case reveal that petitioner adduced evidence to show that
the total amount deposited is just, fair, and equitable. Specifically, in its Petitioner filed a Motion for Reconsideration maintaining that pursuant to
Position Paper, petitioner alleged that pursuant to a Certification issued Bangko Sentral ng Pilipinas (BSP) Circular No. 799, Series of 2013, which
by the Bureau of Internal Revenue (BIR), Revenue Region No. 5, the zonal took effect on July 1, 2013, the interest rate imposed by the RTC on just
value of the subject property in the amount of ₱2,100.00 per square meter compensation should be lowered to 6% for the instant case falls under a
is reasonable, fair, and just to compensate the defendant for the taking of loan or forbearance of money.11 In its Order12 dated March 10, 2014, the
her property in the total area of 200 square meters.9 In fact, Tax RTC reduced the interest rate to 6% per annum not on the basis of the
Declaration No. C-018-07994, dated November 13, 2009 submitted by aforementioned Circular, but on Article 2209 of the Civil Code, viz.:
petitioner, shows that the value of the subject property is at a lower rate
of ₱400.00per square meter. Moreover, as testified to by Associate However, the case of National Power Corporation v. Honorable Zain B.
Solicitor III Julie P. Mercurio, and as affirmed by the photographs Angas is instructive.
submitted, the subject property is poorly maintained, covered by shrubs
and weeds, and not concretely-paved. It is located far from commercial or
In the aforementioned case law, which is similar to the instant case, the
industrial developments in an area without a proper drainage system, can
Supreme Court had the occasion to rule that it is well-settled that the
only be accessed through a narrow dirt road, and is surrounded by
aforequoted provision of Bangko Sentral ng Pilipinas Circular applies only
adjacent dwellings of sub-standard materials.
to a loan or forbearance of money, goods or credits. However, the term
"judgments" as used in Section 1 of the Usury Law and the previous
Accordingly, the RTC considered respondent to have waived her right to Central Bank Circular No. 416, should be interpreted to mean only
adduce evidence and to object to the evidence submitted by petitioner judgments involving loan or forbearance of money, goods or credits,
for her continued absence despite being given several notices to do so. following the principle of ejusdem generis. And applying said rule on
statutory construction, the general term "judgments" can refer only to
On November 15, 2013, the RTC rendered its Decision, the dispositive judgments in cases involving loans or forbearance of any money, goods,
portion of which reads: WHEREFORE, with the foregoing determination of or credits. Thus, the High Court held that, Art. 2209 of the Civil Code, and
just compensation, judgment is hereby rendered: not the Central Bank Circular, is the law applicable.

1) Declaring plaintiff to have lawful right to acquire possession Art. 2009 of the Civil Code reads:
of and title to 200 square meters of defendant Arlene R.
Soriano’s parcel of land covered by TCT V-13790 necessary for "If the obligation consists in the payment of a sum of money, and the
the construction of the NLEX – Harbor Link Project(Segment 9) debtor incurs in delay, the indemnity for damages, there being no
from NLEX to MacArthur Highway Valenzuela City; stipulation to the contrary, shall be the payment of the interest agreed
upon, and in the absence of stipulation, the legal interest, which is six per
cent per annum."

ProvRem Rule 67 Fulltext Page 87 of 119


Further in that case, the Supreme Court explained that the transaction ruling, the Court fixed the applicable interest rate at 12% per annum,
involved is clearly not a loan or forbearance of money, goods or credits computed from the time the property was taken until the full amount of
but expropriation of certain parcels of land for a public purpose, the just compensation was paid, in order to eliminate the issue of the
payment of which is without stipulation regarding interest, and the constant fluctuation and inflation of the value of the currency over time.
interest adjudged by the trial court is in the nature of indemnity for In the Court’s own words:
damages. The legal interest required to be paid on the amount of just
compensation for the properties expropriated is manifestly in the form of The Bulacan trial court, in its 1979 decision, was correct in imposing
indemnity for damages for the delay in the payment thereof. It ultimately interest[s] on the zonal value of the property to be computed from the
held that Art. 2209 of the Civil Code shall apply.13 time petitioner instituted condemnation proceedings and "took" the
property in September 1969. This allowance of interest on the amount
On May 12, 2014, petitioner filed the instant petition invoking the found to be the value of the property as of the time of the taking
following arguments: computed, being an effective forbearance, at 12% per annum should help
eliminate the issue of the constant fluctuation and inflation of the value of
I. the currency over time.

RESPONDENT IS NOT ENTITLED TO THE LEGAL INTEREST OF We subsequently upheld Republic’s 12% per annum interest rate on the
6% PER ANNUM ON THE AMOUNT OF JUST COMPENSATION unpaid expropriation compensation in the following cases: Reyes v.
OF THE SUBJECT PROPERTY AS THERE WAS NO DELAY ON THE National Housing Authority, Land Bank of the Philippines v. Wycoco,
PART OF PETITIONER. Republic v. Court of Appeals, Land Bank of the Philippines v. Imperial,
Philippine Ports Authority v. Rosales-Bondoc, and Curata v. Philippine
Ports Authority.17 Effectively, therefore, the debt incurred by the
II.
government on account of the taking of the property subject of an
expropriation constitutes a forbearance18 which runs contrary to the trial
BASED ON THE NATIONAL INTERNAL REVENUE CODE OF 1997 court’s opinion that the same is in the nature of indemnity for damages
AND THE LOCAL GOVERNMENT CODE, IT IS RESPONDENT’S calling for the application of Article 2209 of the Civil Code. Nevertheless,
OBLIGATION TO PAY THE TRANSFER TAXES. in line with the recent circular of the Monetary Board of the Bangko
Sentral ng Pilipinas (BSP-MB) No. 799, Series of 2013, effective July 1,
Petitioner maintains that if property is taken for public use before 2013, the prevailing rate of interest for loans or forbearance of money is
compensation is deposited with the court having jurisdiction over the six percent (6%) per annum, in the absence of an express contract as to
case, the final compensation must include interests on its just value such rate of interest.
computed from the time the property is taken up to the time when
compensation is actually paid or deposited with the court.14 Thus, legal Notwithstanding the foregoing, We find that the imposition of interest in
interest applies only when the property was taken prior to the deposit of this case is unwarranted in view of the fact that as evidenced by the
payment with the court and only to the extent that there is delay in acknowledgment receipt19 signed by the Branch Clerk of Court, petitioner
payment. In the instant case, petitioner posits that since it was able to was able to deposit with the trial court the amount representing the zonal
deposit with the court the amount representing the zonal value of the value of the property before its taking. As often ruled by this Court, the
property before its taking, it cannot be said to be in delay, and thus, there award of interest is imposed in the nature of damages for delay in
can be no interest due on the payment of just compensation.15 Moreover, payment which, in effect, makes the obligation on the part of the
petitioner alleges that since the entire subject property was expropriated government one of forbearance to ensure prompt payment of the value
and not merely a portion thereof, it did not suffer an impairment or of the land and limit the opportunity loss of the owner.20 However, when
decrease in value, rendering the award of consequential damages there is no delay in the payment of just compensation, We have not
nugatory. Furthermore, petitioner claims that contrary to the RTC’s hesitated in deleting the imposition of interest thereon for the same is
instruction, transfer taxes, in the nature of Capital Gains Tax and justified only in cases where delay has been sufficiently established.21
Documentary Stamp Tax, necessary for the transfer of the subject
property from the name of the respondent to that of the petitioner are The records of this case reveal that petitioner did not delay in its payment
liabilities of respondent and not petitioner. of just compensation as it had deposited the pertinent amount in full due
to respondent on January 24, 2011, or four (4) months before the taking
The petition is partly meritorious. thereof, which was when the RTC ordered the issuance of a Writ of
Possession and a Writ of Expropriation on May 27, 2011. The amount
At the outset, it must be noted that the RTC’s reliance on National Power deposited was deemed by the trial court to be just, fair, and equitable,
Corporation v. Angasis misplaced for the same has already been taking into account the well-established factors in assessing the value of
overturned by our more recent ruling in Republic v. Court of land, such as its size, condition, location, tax declaration, and zonal
Appeals,16 wherein we held that the payment of just compensation for the valuation as determined by the BIR. Considering, therefore, the prompt
expropriated property amounts to an effective forbearance on the part of payment by the petitioner of the full amount of just compensation as
the State, to wit: determined by the RTC, We find that the imposition of interest thereon is
unjustified and should be deleted.

Aside from this ruling, Republic notably overturned the Court’s previous
ruling in National Power Corporation v. Angas which held that just Similarly, the award of consequential damages should likewise be deleted
compensation due for expropriated properties is not a loan or in view of the fact that the entire area of the subject property is being
forbearance of money but indemnity for damages for the delay in expropriated, and not merely a portion thereof, wherein such remaining
payment; since the interest involved is in the nature of damages rather portion suffers an impairment or decrease in value, as enunciated in
than earnings from loans, then Art. 2209 of the Civil Code, which fixes Republic of the Philippines v. Bank of the Philippine Islands,22 thus:
legal interest at 6%, shall apply.
x x x The general rule is that the just compensation to which the owner of
In Republic, the Court recognized that the just compensation due to the the condemned property is entitled to is the market value. Market value is
landowners for their expropriated property amounted to an effective that sum of money which a person desirous but not compelled to buy,
forbearance on the part of the State. Applying the Eastern Shipping Lines and an owner willing but not compelled to sell, would agree on as a price

ProvRem Rule 67 Fulltext Page 88 of 119


to be paid by the buyer and received by the seller. The general rule, controlled corporations shall be determined either under Section 24(A)or
however, is modified where only a part of a certain property is under this Subsection, at the option of the taxpayer.
expropriated. In such a case, the owner is not restricted to compensation
for the portion actually taken, he is also entitled to recover the xxxx
consequential damage, if any, to the remaining part of the property.

Section 56. Payment and Assessment of Income Tax for Individuals and
xxxx Corporations. – (A) Payment of Tax –

No actual taking of the building is necessary to grant consequential xxxx


damages. Consequential damages are awarded if as a result of the
expropriation, the remaining property of the owner suffers from an
impairment or decrease in value. The rules on expropriation clearly (3) Payment of Capital Gains Tax. - The total amount of tax imposed and
provide a legal basis for the award of consequential damages. Section 6 prescribed under Section 24 (c), 24(D), 27(E)(2), 28(A)(8)(c) and 28(B)(5)(c)
of Rule 67 of the Rules of Court provides: shall be paid on the date the return prescribed therefor is filed by the
person liable thereto: Provided, That if the seller submits proof of his
intention to avail himself of the benefit of exemption of capital gains
x x x The commissioners shall assess the consequential damages to the under existing special laws, no such payments shall be required :
property not taken and deduct from such consequential damages the Provided, further, That in case of failure to qualify for exemption under
consequential benefits to be derived by the owner from the public use or such special laws and implementing rules and regulations, the tax due on
public purpose of the property taken, the operation of its franchise by the the gains realized from the original transaction shall immediately become
corporation or the carrying on of the business of the corporation or due and payable, subject to the penalties prescribed under applicable
person taking the property. But in no case shall the consequential benefits provisions of this Code: Provided, finally, That if the seller, having paid the
assessed exceed the consequential damages assessed, or the owner be tax, submits such proof of intent within six (6) months from the
deprived of the actual value of his property so taken. registration of the document transferring the real property, he shall be
entitled to a refund of such tax upon verification of his compliance with
In B.H. Berkenkotter & Co. v. Court of Appeals, we held that: the requirements for such exemption.

To determine just compensation, the trial court should first ascertain the Thus, it has been held that since capital gains is a tax on passive income, it
market value of the property, to which should be added the consequential is the seller, not the buyer, who generally would shoulder the
damages after deducting therefrom the consequential benefits which may tax.24 Accordingly, the BIR, in its BIR Ruling No. 476-2013, dated
arise from the expropriation. If the consequential benefits exceed the December 18, 2013, constituted the DPWH as a withholding agent to
consequential damages, these items should be disregarded altogether as withhold the six percent (6%) final withholding tax in the expropriation of
the basic value of the property should be paid in every case.23 real property for infrastructure projects. As far as the government is
concerned, therefore, the capital gains tax remains a liability of the seller
Considering that the subject property is being expropriated in its entirety, since it is a tax on the seller's gain from the sale of the real estate.25
there is no remaining portion which may suffer an impairment or
decrease in value as a result of the expropriation. Hence, the award of As to the documentary stamp tax, however, this Court finds inconsistent
consequential damages is improper. petitioner’s denial of liability to the same. Petitioner cites Section 196 of
the 1997 NIRC as its basis in saying that the documentary stamp tax is the
Anent petitioner’s contention that it cannot be made to pay the value of liability of the seller, viz.:
the transfer taxes in the nature of capital gains tax and documentary
stamp tax, which are necessary for the transfer of the subject property SECTION 196. Stamp Tax on Deeds of Sale and Conveyances of Real
from the name of the respondent to that of the petitioner, the same is Property. - On all conveyances, deeds, instruments, or writings, other than
partly meritorious. grants, patents or original certificates of adjudication issued by the
Government, whereby any land, tenement or other realty sold shall be
With respect to the capital gains tax, We find merit in petitioner’s posture granted, assigned, transferred or otherwise conveyed to the purchaser, or
that pursuant to Sections 24(D) and 56(A)(3) of the 1997 National Internal purchasers, or to any other person or persons designated by such
Revenue Code (NIRC), capital gains tax due on the sale of real property is purchaser or purchasers, there shall be collected a documentary stamp
a liability for the account of the seller, to wit: tax, at the rates herein below prescribed, based on the consideration
contracted to be paid for such realty or on its fair market value
determined in accordance with Section 6(E) of this Code, whichever is
Section 24. Income Tax Rates– higher: Provided, That when one of the contracting parties is the
Government, the tax herein imposed shall be based on the actual
xxxx consideration: (a) When the consideration, or value received or contracted
to be paid for such realty, after making proper allowance of any
(D) Capital Gains from Sale of Real Property. – encumbrance, does not exceed One thousand pesos (₱1,000), Fifteen
pesos (₱15.00).

(1) In General. – The provisions of Section 39(B) notwithstanding, a final


tax of six percent (6%) based on the gross selling price or current fair (b) For each additional One thousand pesos (₱1,000), or fractional part
market value as determined in accordance with Section 6(E) of this Code, thereof in excess of One thousand pesos (₱1,000) of such consideration or
whichever is higher, is hereby imposed upon capital gains presumed to value, Fifteen pesos (₱15.00).
have been realized from the sale, exchange, or other disposition of real
property located in the Philippines, classified as capital assets, including When it appears that the amount of the documentary stamp tax payable
pacto de retro sales and other forms of conditional sales, by individuals, hereunder has been reduced by an incorrect statement of the
including estates and trusts: Provided, That the tax liability, if any, on consideration in any conveyance, deed, instrument or writing subject to
gains from sales or other disposition of real property to the government such tax the Commissioner, provincial or city Treasurer, or other revenue
or any of its political subdivisions or agencies or to government-owned or officer shall, from the assessment rolls or other reliable source of

ProvRem Rule 67 Fulltext Page 89 of 119


information, assess the property of its true market value and collect the #11 G.R. No. 164282 October 12, 2005
proper tax thereon.
TERESITA M. YUJUICO, Petitioner
Yet, a perusal of the provision cited above does not explicitly impute the vs.
obligation to pay the documentary stamp tax on the seller. In fact, HON. JOSE L. ATIENZA, Chairman, City School, Board of Manila, DR.
according to the BIR, all the parties to a transaction are primarily liable for MA. LUISA S. QUIÑONES, Co-Chairman, City School Board, and
the documentary stamp tax, as provided by Section 2 of BIR Revenue Schools Division Superintendent, ROGER GERNALE, Member, City
Regulations No. 9-2000, which reads:26 School Board of Manila, HON. MANUEL M. ZARCAL, (in substitution
of ARLENE ORTIZ), Member, City School Board of Manila, BENJAMIN
SEC. 2. Nature of the Documentary Stamp Tax and Persons Liable for the VALBUENA (In substitution of MILES ROCES), Member, City School
Tax. – Board of Manila, LIBERTY TOLEDO, Member, City School Board of
Manila, HON. FRANCESCA GERNALE (In substitution of PERCIVAL
FLORIENDO), Member, City School Board of Manila, ISABELITA
(a) In General. - The documentary stamp taxes under Title VII of SANTOS, Secretary, City School Board of Manila, VICENTE
the Code is a tax on certain transactions.1âwphi1It is imposed MACARUBBO (In substitution of Isabelita Ching), Assistant Secretary,
against "the person making, signing, issuing, accepting, or City School Board of Manila, CITY SCHOOL BOARD OF MANILA and
transferring" the document or facility evidencing the aforesaid JUDGE MERCEDES POSADA-LACAP, in her capacity as PRESIDING
transactions. Thus, in general, it may be imposed on the JUDGE OF THE REGIONAL TRIAL COURT OF MANILA, BRANCH
transaction itself or upon the document underlying such act. 15, Respondents.
Any of the parties thereto shall be liable for the full amount of
the tax due: Provided, however, that as between themselves, the
said parties may agree on who shall be liable or how they may DECISION
share on the cost of the tax.
Tinga, J.:
(b) Exception. - Whenever one of the parties to the taxable
transaction is exempt from the tax imposed under Title VII of This is a Petition for Review on Certiorari instituted by Teresita M. Yujuico,
the Code, the other party thereto who is not exempt shall be petitioner in the case for mandamus docketed as Civil Case No. 02-
the one directly liable for the tax.27 103748 before the Regional Trial Court (RTC) of Manila, Branch 15.
Petitioner is questioning the propriety of the Order1 dated 25 June 2004,
As a general rule, therefore, any of the parties to a transaction shall be granting respondents’ Petition for Relief from Judgment under Section 2,
liable for the full amount of the documentary stamp tax due, unless they Rule 38 of the 1997 Rules of Civil Procedure.
agree among themselves on who shall be liable for the same.
The operative facts are not disputed.
In this case, there is no agreement as to the party liable for the
documentary stamp tax due on the sale of the land to be expropriated. On 8 December 1995, the City Council of Manila enacted
But while petitioner rejects any liability for the same, this Court must take an Ordinance2 authorizing the City Mayor to acquire by negotiation or
note of petitioner’s Citizen’s Charter,28 which functions as a guide for the expropriation certain parcels of land for utilization as a site for the
procedure to be taken by the DPWH in acquiring real property through Francisco Benitez Elementary School.3 The property chosen is located
expropriation under RA 8974. The Citizen’s Charter, issued by petitioner along Solis St. near Juan Luna St. in the Second District of Manila and
DPWH itself on December 4,2013, explicitly provides that the contains an approximate area of 3,979.10 square meters. It is covered by
documentary stamp tax, transfer tax, and registration fee due on the Transfer Certificates of Title Nos. 71541, 71548, 24423, 71544 and 71546,
transfer of the title of land in the name of the Republic shall be all in the name of petitioner. The Ordinance provides that an amount not
shouldered by the implementing agency of the DPWH, while the capital to exceed the fair market value of the land then prevailing in the area will
gains tax shall be paid by the affected property owner.29 Thus, while there be allocated out of the Special Education Fund (SEF) of the City of Manila
is no specific agreement between petitioner and respondent, petitioner's (City) to defray the cost of the property’s acquisition.4
issuance of the Citizen's Charter serves as its notice to the public as to the
procedure it shall generally take in cases of expropriation under RA 8974. Failing to acquire the land by negotiation, the City filed a case for eminent
Accordingly, it will be rather unjust for this Court to blindly accede to domain against petitioner as owner of the property. Filed on 22 August
petitioner's vague rejection of liability in the face of its issuance of the 1996, the case was raffled to Branch 15, RTC of Manila and docketed as
Citizen's Charter, which contains a clear and unequivocal assumption of Civil Case No. 96-79699.5
accountability for the documentary stamp tax. Had petitioner provided
this Court with more convincing basis, apart from a mere citation of an
indefinite provision of the 1997 NIRC, showing that it should be On 30 June 2000, the RTC rendered a Decision6 in the expropriation case
in favor of the City. The dispositive portion reads:
respondent-seller who shall be liable for the documentary stamp tax due
on the sale of the subject property, its rejection of the payment of the
same could have been sustained. WHEREFORE, premises considered, the WHEREFORE, judgment is hereby rendered as follows:
instant pet1t10n 1s PARTIALLY GRANTED. The Decision and Order, dated
November 15, 2013 and March 10, 2014, respectively, of the Regional Trial 1.) The lots including the improvements therein of defendant Teresita M.
Court, Valenzuela City, Branch 270, in Civil Case No. 140-V-10 are hereby Yujuico, as described in the complaint, are declared expropriated for
MODIFIED, in that the imposition of interest on the payment of just public use;
compensation as well as the award of consequential damages are deleted.
In addition, respondent Arlene R. Soriano is ORDERED to pay for the
2.) The fair market value of the lots of defendant is fixed at ₱18,164.80 per
capital gains tax due on the transfer of the expropriated property, while
square meter. The fair market value of the improvements of lots subject of
the documentary stamp tax, transfer tax, and registration fee shall be for
this action is fixed at ₱ 978,000.00;
the account of petitioner.

3.) The plaintiff must pay defendant the sum of ₱72,279,555.68 (3,979.10
SO ORDERED.
sq. m. x ₱18,164.80) representing the value of the subject

ProvRem Rule 67 Fulltext Page 90 of 119


lots plus ₱978,000.00 representing the value of the improvements or the the Order.16Earlier, petitioner sent a letter to the Superintendent of City
total amount of ₱73,257,555.00 as just compensation for the whole Schools of Manila to verify the CSB’s compliance with the Order.17
property (including the improvements) minus the sum of ₱5,363,289.00
that plaintiff deposited in Court per Order dated April 30, 1997, hence the Not having been favored with a reply to her queries even after the lapse
balance of ₱67,894,266.00 with interest at the rate of 6% per annum from of the thirty (30)-day compliance period, petitioner sent a letter to the
July 15, 1997 (date of possession of subject property for the purpose of CSB dated 10 September 2001, demanding compliance with the Order.18
this proceedings) until the day full payment is made to defendant or
deposited in Court.7
As there was no action from the CSB, on 1 February 2002, petitioner filed
a petition for contempt of court against respondents Hon. Jose L. Atienza,
The judgment became final and executory, no appeal having been Jr., Dr. Ma. Luisa S. Quiñoňes, Roger Gernale, Arlene Ortiz, Miles Roces,
interposed by either party.8 Percival Floriendo, Liberty Toledo, Isabelita Santos and Isabelita Ching in
their capacities as officers and members of the CSB.19 The case was
On 6 April 2001, petitioner filed a Motion for Execution of Judgment9 which docketed as Civil Case No. 02-102837 of the Manila RTC.20
the trial court granted. Pursuant to a Writ of Execution10 dated 28 June
2001, the branch sheriff served a Notice of Garnishment on the funds of Countering the petition for contempt, respondents filed a Motion to
the City deposited with the Land Bank of the Philippines, YMCA Branch, Dismiss,21 wherein they alleged inter alia that they never disregarded
Manila (Land Bank) to satisfy the judgment amount of ₱67,894,226.00, the Order as the matter had in fact been calendared and deliberated upon
with interest at 6% per annum.11 during the meetings of the CSB.22 In their subsequent Omnibus
Reply,23 respondents argued that petitioner’s failure to avail of the proper
Invoking jurisprudence holding that public funds cannot be made subject recourse to enforce the final and executory judgment24 should not be a
to garnishment, the City filed a motion to quash the Notice of ground to hold them in contempt of court. Citing the case of Municipality
Garnishment.12 Acting on the motion, the trial court issued an Order dated of Makati v. Court of Appeals,25 respondents asserted that petitioner
2 August 2001. should have filed a petition for mandamus to force the CSB to pass the
necessary resolution for immediate payment of the balance of the just
In the Order, the lower court recalled that during the hearing on the compensation awarded in her favor.26
motion, the counsel for the City manifested that the amount of
₱36,403,170.00 had been appropriated by the City School Board (CSB) According to respondents, petitioner took the Order as a writ of
under CSB Resolutions Nos. 613 and 623, of which ₱31,039,881.00 was mandamus when in fact it was a mere order in furtherance of the Writ of
available for release. The amount of ₱5,363,269.00, representing fifteen Execution.27 This interpretation, respondents insisted, should never be
percent (15%) of the assessed value of the property, had been deposited allowed since petitioner merely wanted to escape the payment of docket
in court at the start of the expropriation proceedings and subsequently fees in the filing of the petition for mandamus.28
received by petitioner. In line with the manifestation made by the counsel
for the City, the trial court ordered the release to petitioner of the amount In an Order29 dated 17 May 2002, the trial court denied the petition for
of ₱31,039,881.00 deposited with the Land Bank, in partial payment of the contempt of court.
just compensation adjudged in favor of petitioner.13

On 6 June 2002, petitioner filed a Petition for Mandamus30 against the


The trial court further stated in the Order: members of the CSB, the same respondents in the petition for contempt
of court, seeking to compel them to pass a resolution appropriating the
Considering that this case is on all fours with the case of the Municipality amount necessary to pay the balance of the just compensation awarded
of Makati vs. Court of Appeals (190 SCRA 206), wherein it was ruled that to petitioner in the expropriation case, Civil Case No. 96-79699. The
"x x x Public funds are not subject to levy and execution," the Court petition was docketed as Spl. Civil Action No. 02-103748 and raffled to
therefore grants plaintiff’s Motion to Quash the Notice of Garnishment Branch 51 of the RTC of Manila. 31
and the Notice of Garnishment to the Landbank of the Philippines issued
by the Branch Sheriff of this Court is hereby ordered lifted. Upon petitioner’s motion,32 Branch 51 of the Manila RTC before which the
mandamus case was pending, in an Order33 dated 23 August 2002,
There being no opposition for the release of the Thirty One Million Thirty directed its consolidation with the expropriation case before Branch 15.34
Nine Thousand Eight Hundred Eighty One Pesos (₱31,039,881.00)
deposited with the Land Bank, YMCA Branch as Special Education Fund, In a Decision35 dated 9 October 2002, the lower court (Branch 15) granted
the Manager of the Landbank of the Philippines, YMCA, Manila is hereby the petition for mandamus. Specifically, it ordered respondents to
directed to release the said amount to defendant Teresita M. Yujuico in immediately pass a resolution appropriating the necessary amount and
partial payment of the just compensation adjudged by this Court in its the corresponding disbursement thereof for the full and complete
Decision dated June 30, 2000. payment of the balance of the court-adjudged compensation still due
petitioner, ratiocinating as follows:36
Upon manifestation of the counsel for the plaintiff that it is the City
School Board which has the authority to pass a resolution allocating funds This case is on all fours with the case of Municipality of Makati v. Court of
for the full satisfaction of the just compensation fixed, the said body is Appeals (190 SCRA 206).
hereby given thirty (30) days from receipt of this Order to pass the
necessary resolution for the payments of the remaining balance due to
defendant Teresita M. Yujuico.14 ....

A copy of the Order dated 2 August 2001 was served on the CSB on 3 The State’s power of eminent domain should be exercised within the
August 2001.15 bounds of fair play and justice. In the case at bar, considering that
valuable property has been taken, the compensation to be paid fixed and
the municipality is in full possession and utilizing the property for the
On 30 August 2001, petitioner submitted a manifestation before the trial public purpose, for three (3) years, the Court finds that the municipality
court requesting that she be informed by both the City and the CSB if a has had more than reasonable time to pay full compensation.
resolution had already been passed by the latter in compliance with
ProvRem Rule 67 Fulltext Page 91 of 119
The arguments of the herein respondents that passing the ordinance or Court has often judiciously treated petitions erroneously captioned as
the act of appropriating special educational fund is a discretionary act petitions for review on certiorari as special civil actions for certiorari. This
that could not be compelled by mandamus should be thrown overboard. is in line with the principle that the strict application of procedural
It must be stressed that what we have here is a final and executory technicalities should not hinder the speedy disposition of the case on the
judgment, establishing a legal right for the petitioner to demand merits.51
fulfillment which on the other hand became an imperative duty on the
part of the respondent to perform the act required. Accordingly, facial allegations of reversible error in the petition will be
treated, as they should be, as contextual averments of grave abuse of
WHEREFORE, premises considered, the petition is GRANTED, and the discretion on the part of the court a quo. Appropriately, petitioner
respondents are hereby ordered to immediately pass a resolution impleaded the RTC Presiding Judge as party-respondent in the instant
appropriating the necessary amount; and the corresponding petition.
disbursement thereof, for the full and complete payment of the remaining
balance of the court-adjudged compensation due and owing to petitioner Anent the alleged breach of the rule on hierarchy of courts, the doctrine is
Teresita M. Yujuico. not an iron-clad dictum.52 The rule may be relaxed when exceptional and
compelling circumstances warrant the exercise of this Court’s primary
SO ORDERED.37 jurisdiction.53 In this case, the judgment sought to be satisfied has long
attained finality and the expropriated property has been utilized as a
Respondents filed a motion for reconsideration, which the trial court school site for five (5) years now; yet, the awarded just compensation has
denied in an Order38 dated 13 December 2002. not been fully paid. These circumstances, in the Court’s estimation, merit
the relaxation of the technical rules of procedure to ensure that
substantial justice will be served.
With respondents not interposing an appeal, the Decision became final
and executory on 2 January 200339 and eventually, the
corresponding Entry of Judgment was issued on 15 January 2003.40 The Concerning petitioner’s alleged failure to implead the CSB or its new
court granted petitioner’s Motion for Execution41 in an Order42 dated 12 members before the trial court,54respondents argue that since there are
March 2003. five (5) new members in the CSB any decision in the case requiring the
CSB to act as a body would prove to be legally impossible. The former
members of the CSB could no longer be compelled to act according to
However, on 14 March 2003, respondents filed a Petition for Relief from the orders of the Court since they no longer have the capacity to do so.
Judgment,43 wherein they also prayed for a temporary restraining order On the other hand, respondents continue, the new members cannot be
(TRO) and a writ of preliminary injunction. Respondents invoked directed to comply with the Court’s judgment either; they have never
excusable negligence as a ground for their failure to seasonably file an been impleaded in the case; thus, the Court never acquired jurisdiction
appeal.44 While it denied the application for TRO in view of its prior order over their persons.55
granting petitioner’s Motion for Execution, the court granted the Petition
for Relief from Judgment in an Order45 dated 25 June 2004. This had the
effect of giving due course to respondents’ appeal despite the fact that The arguments were effectively neutered in our Resolution dated 8 August
the decision of the trial court had already attained finality. 2005. There, we declared:

Finding the Order unacceptable, petitioner elevated it to this Court by way Considering the arguments posited by both parties, this Court is of the
of a petition for certiorari under Rule 45. In her petition, petitioner asks view that a substitution of the original respondents by the members of
that the order of the lower court giving due course to respondents’ the CSB who replaced them is warranted. The phrase "or such time as may
appeal be reversed and set aside on a pure question of law.46 be granted by the Court" in Sec. 17, Rule 3 of the 1997 Rules of Civil
Procedure denotes that the Court before whom the motion for
substitution is filed may grant a period longer than thirty (30) days for the
Before resolving the substantive issues raised by the parties, the Court will purpose. In any event, technical rules on substitution of a party should not
first address the procedural infirmities ascribed by respondents to the be so narrowly construed as to prevent this Court from taking cognizance
petition at bar. of a case and deciding it on the merits. Moreover, petitioner did make an
attempt to implead the new members of the CSB by making the CSB itself
Respondents assail the correctness and propriety of the mode of appeal a respondent before this Court. There is also no showing that the new
resorted to by petitioner.47 According to them, the order granting the members of the CSB have deviated from the stand of their predecessors-
petition for relief from judgment is an interlocutory order which cannot in-interest; hence, there is a substantial need for continuing or
be made the subject of an appeal.48 Respondents likewise argue that maintaining petitioner’s action against them.56
petitioner failed to respect the rule on hierarchy of courts. This Court, they
aver, had consistently held that its original jurisdiction to issue a writ of In the same Resolution, the Court ordered the impleading of the new CSB
certiorari is not exclusive but is concurrent with that of the RTC and the members Roger Gernale, Manuel M. Zarcal, Benjamin Valbuena and
Court of Appeals in certain cases.49 Francesca Gernale as party respondents—the last three in substitution of
Arlene Ortiz, Percival Floriendo, Miles Roces—and the new CSB Assistant
Respondents have correctly pointed out that an interlocutory order Secretary Vicente Macarubbo in substitution of Isabelita Ching.57 Only
cannot be made subject to an appeal. However, when viewed in context, Manuel Zarcal filed a Comment58 dated 30 August 2005 through a new
the recitals of the petition clearly disclose and the Court is convinced that counsel, adopting in toto the comment of his co-respondents. Hence, the
the lower court committed grave abuse of discretion amounting to lack or other four newly impleaded party respondents are deemed to have
excess of jurisdiction when it granted respondents’ petition for relief from retained the Office of the City Legal Officer (OCLO) as their counsel and to
judgment. While this case should have been elevated to this Court not by have adopted the Commentalready filed by the OCLO in behalf of their
way of a petition for review under Rule 45 but through a special civil co-respondents.
action for certiorari under Rule 65, in the exercise of our sound discretion
and in order to write finis to this case which has needlessly dragged on Thus, the proper substitutions of some party respondents have already
for so long, we shall treat the petition as a special civil action for certiorari. taken place in this case.
After all, it was filed within the reglementary period for the filing of a Rule
65 petition. As we held in Salinas v. NLRC,50 in the interest of justice, this

ProvRem Rule 67 Fulltext Page 92 of 119


The last procedural hurdle thrown petitioner’s way by respondents refers ....
to the supposed failure of the petition to comply with the requirements of
Section 4, Rule 7 and Section 4, Rule 45 of the 1997 Rules of Civil In the face of all these facts and circumstances, . . . the respondent judge
Procedure59as amended by Supreme Court Circular A.M. No. 00-2-10- revealed a simple-minded willingness to swallow a story patently
SC.60 Respondents claim that there was failure to include a verified concocted to delay as much as possible the satisfaction of a judgment
statement indicating the material dates relative to the receipt of the against respondent . . . .This indiscriminating credulity does not conform
judgments and the filing of the pleadings. The verification, moreover, to what is to be expected of a judicial mind.72
allegedly failed to state that petitioner has read the petition61 and that the
copies attached thereto are based on authentic records.62 The defects of
the verification allegedly render the petition without legal effect and Reiterated in numerous cases is the rule that the clerks’ faults are
constitute grounds for its dismissal. attributable to the handling lawyers.73 Thus, excuses offered based on the
former’s negligence are not deemed excusable. That the admonitions
issued out by this Court were mostly directed against lawyers in law firms
The purpose of requiring a verification is to secure an assurance that the does not exempt respondents herein from the same treatment. For all
allegations of the petition have been made in good faith; or are true and intents and purposes, the set-up at the OCLO is akin to that of a law firm,
correct, not merely speculative.63 This requirement is simply a condition the only difference being that the former serves a public entity while the
affecting the form of pleadings and non-compliance therewith does not latter caters to private clients. The following pronouncement in Negros
necessarily render it fatally defective.64Perusal of the verification in Stevedoring Co., Inc. v. Court of Appeals74 is apropos:
question shows that there was sufficient compliance with the
requirements of the Rules and the alleged defects are not so material as
to justify the dismissal of the petition. The negligence committed in the case at bar cannot be considered
excusable, nor is it unavoidable. Time and again, the Court has
admonished law firms to adopt a system of distributing pleadings and
Now, the substantial issues. notices, whereby lawyers working therein receive promptly notices and
pleadings intended for them, so that they will always be informed of the
Up for determination is the tenability of the RTC’s favorable action on status of their cases. The Court has also often repeated that the
respondents’ petition for relief from judgment. This engenders a look at negligence of clerks which adversely affect the cases handled by lawyers
the grounds and defenses relied upon by respondents in support of their is binding upon the latter.75
petition. Sections 2 and 3, Rule 38 of the 1997 Rules of Civil Procedure
provide that a petition for relief may be granted upon a showing that (1) Without doubt, it was grave abuse of discretion for the lower court to
through fraud, accident, mistake or excusable negligence, a party has have given due course to respondents’ appeal through the grant of their
been prevented from taking an appeal, and (2) the party has a good and petition for relief from judgment based on the flimsy ground they
substantial cause of action or defense. proferred.

The above requisites notwithstanding, it bears stressing that relief from Even assuming that the negligence invoked by respondents could be
judgment is premised on equity. It is an act of grace which is allowed only considered excusable, still the petition should not have been granted. It
in exceptional cases.65 must be borne in mind that two requisites must be satisfied before a
petition under Rule 38 may be granted, the other being the existence of a
In this case, according to respondents they were unable to seasonably file good and substantial cause of action or defense.
a notice of appeal due to "excusable negligence."66 One Ronald Silva
(Silva), an employee of the OCLO, allegedly failed to forward Respondents’ defense consisted of their claim that the CSB has a
the Order denying respondents’ motion for reconsideration in Civil Case personality separate and distinct from the City such that it should not be
No. 02-103748 to the handling lawyers. When the order was delivered to made to pay for the City’s obligations.76 However, the argument is
the OCLO on 17 December 2002,67 Silva was the one who received it undercut by the particular circumstances of this case.
because the employee designated to do so was out on official
business.68 Since the employees were busy preparing for the office
Christmas party that day,69 Silva forgot all about the order. He only It is worthy of note that the records of this case clearly show that the
remembered it when the order for entry of judgment in the case was same counsel, the OCLO, represented the City in the expropriation case
received on 29 January 2003. By that time, however, the order dated 17 and now, all except one of the individual respondents in the case at bar.
December 2002 had already been misplaced.70 Worthy of note are the following manifestations relied upon by the lower
court in issuing the order on the motion to quash the Notice of
Garnishment over the funds of the City, to wit:
Clearly, the situation does not present a case of excusable negligence
which would warrant relief under Rule 38. Time and again, this Court has
ruled that the inability to perfect an appeal in due time by reason of The Motion to Quash Notice of Garnishment was heard by this court this
failure of a counsel’s clerk to notify the handling lawyer is not a morning and Atty. Joseph Aquino appeared for the plaintiff (City of
pardonable oversight.71 As held in one case: Manila) and Atty. Federico Alday, for the defendant. Atty. Aquino
manifested that the amount of Thirty Six Million Four Hundred Three
Thousand One Hundred Seventy Pesos (₱36,403,170.00) had been
. . . The excuse offered by respondent . . . as reason for his failure to appropriated by the City School Board (CSB) under CSB Resolution
perfect in due time his appeal from the judgment of the Municipal Court, Nos. 613 and 623 for this purpose.
that counsel’s clerk forgot to hand him the court notice, is the most
hackneyed and habitual subterfuge employed by litigants who fail to
observe the procedural requirements prescribed by the Rules of Court. ....
The uncritical acceptance of this kind of common-place excuses, in the
face of the Supreme Court’s repeated rulings that they are neither Upon manifestation of the counsel for the plaintiff that it is the City
credible nor constitutive of excusable negligence (Gaerlan v. Bernal, L- School Board which has the authority to pass a resolution allocating
4039, 29 January 1952; Mercado v. Judge Domingo, L-19457, 17 funds for the full satisfaction of the just compensation fixed, the said
December 1966) is certainly such whimsical exercise of judgment as to be body is hereby given thirty (30) days from receipt of this Order to pass the
a grave abuse of discretion. necessary resolution for the payments of the remaining balance due to
defendant Teresita M. Yujuico. (Emphasis supplied.)77
ProvRem Rule 67 Fulltext Page 93 of 119
The manifestation was made by the same counsel now claiming that it is desires.81 The question of whether the enactment of an ordinance to
actually the City which should be made liable for the payment of its own satisfy the appropriation of a final money judgment rendered against an
obligations. This, after it trotted out the CSB as the entity with authority to LGU may be compelled by mandamus has already been settled
pass a resolution that would satisfy the obligation it had vigorously in Municipality of Makati v. Court of Appeals.82
pursued.
Nevertheless, this is not to say that private respondent and PSB are left
The above circumstances, coupled with the rule that an act performed by with no legal recourse. Where a municipality fails or refuses, without
counsel within the scope of a "general or implied authority" is regarded as justifiable reason, to effect payment of a final money judgment rendered
an act of the client,78 render the City and, through it, respondents against it, the claimant may avail of the remedy of mandamus in order to
in estoppel. By estoppel is meant that an admission or representation is compel the enactment and approval of the necessary appropriation
rendered conclusive upon the person making it and cannot be denied or ordinance, and the corresponding disbursement of municipal funds
disproved as against the person relying thereon.79 Petitioner and the therefore [SeeViuda De Tan Toco v. The Municipal Council of Iloilo, supra,
courts acted in accordance with the City’s own manifestations by running Baldivia v. Lota, 107 Phil 1099 (1960); Yuviengco v. Gonzales, 108 Phil 247
after the CSB. At this point, respondents and the OCLO can no longer turn (1960)].83
around and toss the obligation back to the City. After all, it was the legal
counsel of both the City and respondents who made a big production out Clearly, mandamus is a remedy available to a property owner when a
of showing that the liability incurred by the City will be borne by the CSB. money judgment is rendered in its favor and against a municipality or city,
as in this case.
Contrary to respondents’ claim, the law does not make the CSB an entity
independent from the City of Manila. This is evident from the provisions Moreover, the very ordinance authorizing the expropriation of petitioner’s
of the Local Government Code of 1991, the law providing for the creation property categorically states that the payment of the expropriated
of school boards. It states: property will be defrayed from the SEF. To quote:

TITLE IV.- LOCAL SCHOOL BOARDS An amount not to exceed the current fair market value, prevailing in the
area appraised in accordance with the requirements of existing laws, rules
Section 98. Creation, Composition and Compensation.- and regulations, of the property to be acquired or so much thereof as
may be necessary for the purpose shall be allocated out of the Special
(a) There shall be established in every province, city or municipality a Education Fund of the City to defray the cost of acquisition of the above-
provincial, city, or municipal school board, respectively. mentioned parcels of land.84

(b) The composition of local school boards shall be as follows: The legality of the above-quoted provision is presumed. The source of the
amount necessary to acquire petitioner’s property having in fact been
specified by the City Council of Manila, the passage of the resolution for
...
the allocation and disbursement thereof is indeed a ministerial duty of the
CSB.
(2) The city school board shall be composed of the city mayor and the city
superintendent of schools as co-chairmen; the chairman of the education Furthermore, respondents had argued in the petition for contempt filed
committee of the sangguniang panlungsod, the city treasurer, the against them by petitioner that the latter’s failure to invoke the proper
representative of the "pederasyon ng mga sangguniang kabataan" in remedy of mandamus should not be a ground to penalize them with
the sangguniang panlungsod, the duly elected president of the city contempt. In their haste to have the contempt petition dismissed,
federation of parents-teachers associations, the duly elected respondents consistently contended that what petitioner should have
representative of the non-academic personnel of public schools in the filed was a case for mandamus to compel passage of the corresponding
city, as members; resolution of the CSB if she wanted immediate payment.85 Having relied
on these representations of respondents and having filed the action they
... adverted to, petitioner cannot now be sent by respondents on another
wild goose chase to obtain ultimate recovery of what she is legally
Section 101. Compensation and Remuneration.- entitled to.

The co-chairmen and members of the provincial, city or municipal school While this Court recognizes the power of LGU to expropriate private
board shall perform their duties as such without compensation or property for public use, it will not stand idly by while the expropriating
remuneration. Members thereof who are not government officials or authority maneuvers to evade the payment of just compensation of
employees shall be entitled to traveling expenses and allowances property already in its possession.
chargeable against the funds of the local school board concerned, subject
to existing accounting and auditing rules and regulations.80 The notion of expropriation is hard enough to take for a private owner.
He is compelled to give up his property for the common weal. But to give
The fact that the highest ranking official of a local government unit (LGU) it up and wait in vain for the just compensation decreed by the courts is
is designated as co-chairman of the school board negates the claim in this too much to bear. In cases like these, courts will not hesitate to step in to
case that the CSB has a personality separate and distinct from the City. ensure that justice and fair play are served. As we have already ruled:
The other fact that government officials in the school board do not
receive any compensation or remuneration while NGO representatives . . . This Court will not condone petitioner’s blatant refusal to settle its
merely receive allowances underscores the absurdity of respondents’ legal obligation arising from expropriation proceedings it had in fact
argument all the more. Indeed, such would not be the situation if the initiated. It cannot be over-emphasized that within the context of the
school board has a personality separate and distinct from the LGU. State’s inherent power of eminent domain,

Respondents also argue that the members of the CSB cannot be directed . . . (j)ust compensation means not only the correct determination of the
to decide a discretionary function in the specific manner the court amount to be paid to the owner of the land but also the payment of the
ProvRem Rule 67 Fulltext Page 94 of 119
land within a reasonable time from its taking. Without prompt payment, surnamed MACABANGKIT,
compensation cannot be considered ‘just’ for the property owner is made Respondents.
to suffer the consequence of being immediately deprived of his land while
x--------------------------------------------------------------x
being made to wait for a decade or more before actually receiving the
amount necessary to cope with his loss (Consculluela v. The Honorable
DECISION
Court of Appeals, G.R. No. 77765, August 15, 1988, 164 SCRA 393,
400. See also Provincial Government of Sorsogon v. Vda. De Villaroya, G.R.
BERSAMIN, J.:
No. 64037, August 27, 1987, 153 SCRA 291).86
Private property shall not be taken for
public use without just compensation.
The decision rendering just compensation in petitioner’s favor was Section 9, Article III, 1987 Constitution
promulgated way back in the year 2000.87 Five years have passed, yet the
award still has not been fully satisfied. Recently, in Republic v. Lim,88 this The application of this provision of the Constitution is the focus of this
Court made the following pronouncement: appeal.

. . . while the prevailing doctrine is that the non-payment of just Petitioner National Power Corporation (NPC) seeks the review
compensation does not entitle the private landowner to recover on certiorari of the decision promulgated on October 5, 2004,[1] whereby
possession of the expropriated lots, however, in cases where the the Court of Appeals (CA) affirmed the decision dated August 13, 1999
government failed to pay just compensation within five (5) years from and the supplemental decision dated August 18, 1999, ordering NPC to
the finality of judgment in the expropriation proceedings, the owners pay just compensation to the respondents, both rendered by the Regional
concerned shall have the right to recover possession of their property. Trial Court, Branch 1, in Iligan City (RTC).
This is in consonance with the principle that ‘the government cannot keep
the property and dishonor the judgment.’ To be sure, the five-year period Antecedents
limitation will encourage the government to pay just compensation
punctually. This is in keeping with justice and equity. After all, it is the duty Pursuant to its legal mandate under Republic Act No. 6395 (An Act
of the government, whenever it takes property from private persons Revising the Charter of the National Power Corporation), NPC undertook
against their will, to facilitate the payment of just the Agus River Hydroelectric Power Plant Project in the 1970s to generate
compensation.89 (Citations omitted) electricity for Mindanao. The project included the construction of several
underground tunnels to be used in diverting the water flow from the Agus
River to the hydroelectric plants.[2]
Given the above ruling, the reversion of the expropriated property to the
petitioner would prove not to be a remote prospect should respondents
On November 21, 1997, the respondents, namely: Cebu, Bangowa-an,
and the City they represent insist on trudging on their intransigent course.
Sayana, Nasser, Manta, Edgar, Putri, Mongkoy and Amir, all surnamed
Macabangkit (Heirs of Macabangkit), as the owners of land with an area
One final note. Respondents’ appeal from the Decision dated 9 October of 221,573 square meters situated in Ditucalan, Iligan City, sued NPC in
2002 of the lower court, made possible by its grant of their petition for the RTC for the recovery of damages and of the property, with the
relief, is before the Court of Appeals where it is docketed as CA-G.R. No. alternative prayer for the payment of just compensation.[3] They alleged
86692.90The court’s Decision in this case would have obvious that they had belatedly discovered that one of the underground tunnels
consequences on said appeal; hence, referral of this Decision to the Court of NPC that diverted the water flow of the Agus River for the operation of
of Appeals is in order. the Hydroelectric Project in Agus V, Agus VI and Agus VII traversed their
land; that their discovery had occurred in 1995 after Atty. Saidali C.
WHEREFORE, the petition is GRANTED. The Order of the trial court dated Gandamra, President of the Federation of Arabic Madaris School, had
25 June 2004, granting respondents’ Petition for Relief from Judgment is rejected their offer to sell the land because of the danger the
REVERSED and set aside and its Decision dated 9 October 2002, ordering underground tunnel might pose to the proposed Arabic Language
respondents to immediately pass a resolution for the payment of the Training Center and Muslims Skills Development Center; that such
balance of the court-adjudged compensation due petitioner, is reinstated. rejection had been followed by the withdrawal by Global Asia
Management and Resource Corporation from developing the land into a
housing project for the same reason; that Al-Amanah Islamic Investment
Let a copy of this Decision be furnished the Court of Appeals for its
Bank of the Philippines had also refused to accept their land as collateral
information and guidance in relation to CA-G.R. No. 86692 entitled
"Teresita M. Yujuico v. Hon. Jose L. Atienza, Jr., et al." because of the presence of the underground tunnel; that the
underground tunnel had been constructed without their knowledge and
consent; that the presence of the tunnel deprived them of the agricultural,
SO ORDERED. commercial, industrial and residential value of their land; and that their
land had also become an unsafe place for habitation because of the loud
#12 G.R. No. 165828 August 24, 2011 sound of the water rushing through the tunnel and the constant shaking
of the ground, forcing them and their workers to relocate to safer
NATIONAL POWER Present: grounds.
CORPORATION,
Petitioner, CORONA, C.J., Chairperson, In its answer with counterclaim,[4] NPC countered that the Heirs of
LEONARDO-DE CASTRO, Macabangkit had no right to compensation under section 3(f) of Republic
BERSAMIN, Act No. 6395, under which a mere legal easement on their land was
- versus - DEL CASTILLO, and established; that their cause of action, should they be entitled to
VILLARAMA, JR., JJ. compensation, already prescribed due to the tunnel having been
constructed in 1979; and that by reason of the tunnel being an apparent
HEIRS OF MACABANGKIT and continuous easement, any action arising from such easement
SANGKAY, namely: CEBU, prescribed in five years.
BATOWA-AN, SAYANA, NASSER,
MANTA, EDGAR, PUTRI , Ruling of the RTC
MONGKOY*, and AMIR, all

ProvRem Rule 67 Fulltext Page 95 of 119


On July 23, 1998, an ocular inspection of the land that was The RTC fixed the just compensation at P500.00/square meter based on
conducted by RTC Judge Mamindiara P. Mangotara and the the testimony of Dionisio Banawan, OIC-City Assessor of Iligan City, to the
representatives of the parties resulted in the following observations and effect that the appraised value of the adjoining properties ranged
findings: from P700.00 to P750.00, while the appraised value of their affected land
ranged from P400.00 to P500.00. The RTC also required NPC to pay
a. That a concrete post which is about two feet in rentals from 1979 due to its bad faith in concealing the construction of
length from the ground which according to the the tunnel from the Heirs of Macabangkit.
claimants is the middle point of the tunnel. On August 18, 1999, the RTC issued a supplemental decision,[7] viz:

b. That at least three fruit bearing durian trees Upon a careful review of the original decision dated
were uprooted and as a result of the August 13, 1999, a sentence should be added to
construction by the defendant of the tunnel and paragraph 1(a) of the dispositive portion thereof, to
about one hundred coconuts planted died. bolster, harmonize, and conform to the findings of
the Court, which is quoted hereunder, to wit:
c. That underground tunnel was constructed
therein.[5] Consequently, plaintiffs land or
properties are hereby condemned in favor of
defendant National Power Corporation, upon
After trial, the RTC ruled in favor of the plaintiffs (Heirs of payment of the aforesaid sum.
Macabangkit),[6] decreeing: Therefore, paragraph 1(a) of the dispositive portion
of the original decision should read, as follows:

a) To pay plaintiffs land with a total area of


WHEREFORE, premises considered: 227,065 square meters, at the rate of
FIVE HUNDRED (P500.00) PESOS per
1. The prayer for the removal or square meter, or a total of ONE
dismantling of defendants tunnel is denied. However, HUNDRED THIRTEEN MILLION FIVE
defendant is hereby directed and ordered: HUNDRED THIRTY TWO THOUSAND
AND FIVE HUNDRED (P113,532,500.00)
a)To pay plaintiffs land with a total area PESOS, plus interest, as actual damages
of 227,065 square meters, at the rate of FIVE or just compensation; Consequently,
HUNDRED (P500.00) PESOS per square meter, plaintiffs land or properties are hereby
or a total of ONE HUNDRED THIRTEEN condemned in favor of defendant
MILLION FIVE HUNDRED THIRTY TWO National Power Corporation, upon
THOUSAND AND FIVE HUNDRED payment of the aforesaid sum;
(P113,532,500.00), PESOS, plus interest, as
actual damages or just compensation; This supplemental decision shall be considered as
part of paragraph 1(a) of the dispositive portion of
b) To pay plaintiff a monthly the original decision.
rental of their land in the amount of THIRTY
THOUSAND (P30,000.00) PESOS from 1979 Furnish copy of this supplemental decision to all
up to July 1999 with 12% interest per annum; parties immediately.

c)To pay plaintiffs the sum of TWO SO ORDERED.


HUNDRED THOUSAND (P200,000.00) PESOS,
as moral damages; On its part, NPC appealed to the CA on August 25, 1999.[8]

d) To pay plaintiffs, the sum of Earlier, on August 18, 1999, the Heirs of Macabangkit filed an
TWO HUNDRED THOUSAND (P200,000.00) urgent motion for execution of judgment pending appeal.[9] The RTC
PESOS, as exemplary damages; granted the motion and issued a writ of execution,[10] prompting NPC to
assail the writ by petition for certiorari in the CA. On September 15, 1999,
e)To pay plaintiffs, the sum equivalent to the CA issued a temporary restraining order (TRO) to enjoin the RTC from
15% of the total amount awarded, as implementing its decision. The Heirs of Macabangkit elevated the ruling
attorneys fees, and to pay the cost. of the CA (G.R. No. 141447), but the Court upheld the CA on May 4,
2006.[11]
SO ORDERED.
Ruling of the CA
NPC raised only two errors in the CA, namely:
The RTC found that NPC had concealed the construction of the tunnel in
1979 from the Heirs of Macabangkit, and had since continuously denied
its existence; that NPC had acted in bad faith by taking possession of the
subterranean portion of their land to construct the tunnel without their I
knowledge and prior consent; that the existence of the tunnel had THE COURT A QUO SERIOUSLY ERRED IN RULING
affected the entire expanse of the land, and had restricted their right to THAT NAPOCORS UNDERGROUND TUNNEL IN ITS
excavate or to construct a motorized deep well; and that they, as owners, AGUS RIVER HYDRO-ELECTRIC PLANT PROJECT
had lost the agricultural, commercial, industrial and residential value of TRAVERSED AND/OR AFFECTED APPELLEES
the land. PROPERTY AS THERE IS NO CLEAR EVIDENCE
INDUBITABLY ESTABLISHING THE SAME

ProvRem Rule 67 Fulltext Page 96 of 119


II lapse of 10 years pursuant to Article 620 of the Civil Code due to its being
THE COURT A QUO SERIOUSLY ERRED IN GRANTING a continuous and apparent legal easement under Article 634 of the Civil
APPELLEES CLAIMS IN THEIR ENTIRETY FOR Code.
GRANTING ARGUENDO THAT NAPOCORS The issues for resolution are, therefore, as follows:
UNDERGROUND TUNNEL INDEED TRAVERSED
APPELLEES PROPERTY, THEIR CAUSE OF ACTION (1) Whether the CA and the RTC erred in
HAD ALREADY BEEN BARRED BY PRESCRIPTION, holding that there was an underground tunnel
ESTOPPEL AND LACHES traversing the Heirs of Macabangkits land
On October 5, 2004, the CA affirmed the decision of the RTC, holding that constructed by NPC; and
the testimonies of NPCs witness Gregorio Enterone and of the
respondents witness Engr. Pete Sacedon, the topographic survey map, the (2) Whether the Heirs of Macabangkits right
sketch map, and the ocular inspection report sufficiently established the to claim just compensation had prescribed under
existence of the underground tunnel traversing the land of the Heirs of section 3(i) of Republic Act No. 6395, or, alternatively,
Macabangkit; that NPC did not substantiate its defense that prescription under Article 620 and Article 646 of the Civil Code.
already barred the claim of the Heirs of Macabangkit; and that Section 3(i) Ruling
of R.A. No. 6395, being silent about tunnels, did not apply, viz:
We uphold the liability of NPC for payment of just compensation.
As regard Section 3(i) of R.A. No. 6395 (An Act
Revising the Charter of the National Power 1.
Corporation), it is submitted that the same provision Factual findings of the RTC,
is not applicable. There is nothing in Section 3(i) of when affirmed by the CA, are binding
said law governing claims involving tunnels. The
same provision is applicable to those projects or The existence of the tunnel underneath the land of the Heirs of
facilities on the surface of the land, that can easily be Macabangkit, being a factual matter, cannot now be properly reviewed by
discovered, without any mention about the claims the Court, for questions of fact are beyond the pale of a petition for
involving tunnels, particularly those surreptitiously review on certiorari. Moreover, the factual findings and determinations by
constructed beneath the surface of the land, as in the the RTC as the trial court are generally binding on the Court, particularly
instant case. after the CA affirmed them.[13] Bearing these doctrines in mind, the Court
should rightly dismiss NPCs appeal.
Now, while it is true that Republic Act No. 6395
authorizes NAPOCOR to take water from any public NPC argues, however, that this appeal should not be dismissed because
stream, river, creek, lake, spring or waterfall in the the Heirs of Macabangkit essentially failed to prove the existence of the
Philippines for the realization of the purposes underground tunnel. It insists that the topographic survey map and the
specified therein for its creation; to intercept and right-of-way map presented by the Heirs of Macabangkit did not at all
divert the flow of waters from lands of riparian establish the presence of any underground tunnel.
owners (in this case, the Heirs), and from persons
owning or interested in water which are or may be NPC still fails to convince.
necessary to said purposes, the same Act expressly Even assuming, for now, that the Court may review the factual findings of
mandates the payment of just compensation. the CA and the RTC, for NPC to insist that the evidence on the existence
of the tunnel was not adequate and incompetent remains futile. On the
WHEREFORE, premises considered, the instant appeal contrary, the evidence on the tunnel was substantial, for the significance
is hereby DENIED for lack of merit. Accordingly, the of the topographic survey map and the sketch map (as indicative of the
appealed Decision dated August 13, 1999, and the extent and presence of the tunnel construction) to the question on the
supplemental Decision dated August 18, 1999, are existence of the tunnel was strong, as the CA correctly projected in its
hereby AFFIRMED in toto. assailed decision, viz:

SO ORDERED.[12] Among the pieces of documentary evidence


presented showing the existence of the said tunnel
Issue beneath the subject property is the topographic
survey map. The topographic survey map is one
NPC has come to the Court, assigning the lone error that: conducted to know about the location and elevation
of the land and all existing structures above and
THE APPELLATE COURT ERRED ON A QUESTION OF underneath it. Another is the Sketch Map which
LAW WHEN IT AFFIRMED THE DECISION AND shows the location and extent of the land traversed
SUPPLEMENTAL DECISION OF THE COURT A QUO or affected by the said tunnel. These two (2) pieces
DIRECTING AND ORDERING PETITIONER TO PAY of documentary evidence readily point the extent
JUST COMPENSATION TO RESPONDENTS. and presence of the tunnel construction coming
from the power cavern near the small man-made
NPC reiterates that witnesses Enterone and Sacedon lacked personal lake which is the inlet and approach tunnel, or at
knowledge about the construction and existence of the tunnel and were a distance of about two (2) kilometers away from
for that reason not entitled to credence; and that the topographic and the land of the plaintiffs-appellees, and then
relocation maps prepared by Sacedon should not be a basis to prove the traversing the entire and the whole length of the
existence and location of the tunnel due to being self-serving. plaintiffs-appellees property, and the outlet
NPC contends that the CA should have applied Section 3(i) of Republic channel of the tunnel is another small man-made
Act No. 6395, which provided a period of only five years from the date of lake. This is a sub-terrain construction, and
the construction within which the affected landowner could bring a claim considering that both inlet and outlet are bodies of
against it; and that even if Republic Act No. 6395 should be inapplicable, water, the tunnel can hardly be noticed. All
the action of the Heirs of Macabangkit had already prescribed due to the constructions done were beneath the surface of the
underground tunnel being susceptible to acquisitive prescription after the plaintiffs-appellees property. This explains why they

ProvRem Rule 67 Fulltext Page 97 of 119


could never obtain any knowledge of the existence of (i) To construct works across, or otherwise,
such tunnel during the period that the same was any stream, watercourse, canal, ditch,
constructed and installed beneath their property.[14] flume, street, avenue, highway or railway
of private and public ownership, as the
The power cavern and the inlet and outlet channels established the location of said works may
presence of the underground tunnel, based on the declaration in the RTC require:Provided, That said works be
by Sacedon, a former employee of the NPC.[15] It is worthy to note that constructed in such a manner as not to
NPC did not deny the existence of the power cavern, and of the inlet and endanger life or property; And provided,
outlet channels adverted to and as depicted in the topographic survey further, That the stream, watercourse,
map and the sketch map. The CA cannot be faulted for crediting the canal ditch, flume, street, avenue,
testimony of Sacedon despite the effort of NPC to discount his credit due highway or railway so crossed or
to his not being an expert witness, simply because Sacedon had personal intersected be restored as near as
knowledge based on his being NPCs principal engineer and supervisor possible to their former state, or in a
tasked at one time to lay out the tunnels and transmission lines manner not to impair unnecessarily their
specifically for the hydroelectric projects,[16] and to supervise the usefulness. Every person or entity whose
construction of the Agus 1 Hydroelectric Plant itself[17] from 1978 until his right of way or property is lawfully
retirement from NPC.[18] Besides, he declared that he personally crossed or intersected by said works
experienced the vibrations caused by the rushing currents in the tunnel, shall not obstruct any such crossings or
particularly near the outlet channel.[19] Under any circumstances, Sacedon intersection and shall grant the Board or
was a credible and competent witness. its representative, the proper authority
for the execution of such work. The
The ocular inspection actually confirmed the existence of the Corporation is hereby given the right of
tunnel underneath the land of the Heirs of Macabangkit. Thus, the CA way to locate, construct and maintain
observed: such works over and throughout the
lands owned by the Republic of the
More so, the Ocular inspection conducted on July 23, Philippines or any of its branches and
1998 further bolstered such claim of the existence political subdivisions. The Corporation or
and extent of such tunnel. This was conducted by a its representative may also enter upon
team composed of the Honorable Presiding Judge of private property in the lawful
the Regional Trial Court, Branch 01, Lanao del Norte, performance or prosecution of its
herself and the respective lawyers of both of the business and purposes, including the
parties and found that, among others, said construction of the transmission lines
underground tunnel was constructed beneath the thereon; Provided, that the owner of
subject property.[20] such property shall be indemnified for
any actual damage caused
It bears noting that NPC did not raise any issue against or thereby;Provided, further, That said
tender any contrary comment on the ocular inspection report. action for damages is filed within five
years after the rights of way,
transmission lines, substations, plants
2. or other facilities shall have been
Five-year prescriptive period under Section 3(i) of established; Provided, finally, That after
Republic Act No. 6395 does not apply to claims said period, no suit shall be brought to
for just compensation question the said rights of way,
transmission lines, substations, plants or
other facilities;
The CA held that Section 3(i) of Republic Act No. 6395 had no application
to this action because it covered facilities that could be easily discovered,
not tunnels that were inconspicuously constructed beneath the surface of A cursory reading shows that Section 3(i) covers the construction of works
the land.[21] across, or otherwise, any stream, watercourse, canal, ditch, flume, street,
avenue, highway or railway of private and public ownership, as the
NPC disagrees, and argues that because Article 635[22] of location of said works may require. It is notable that Section 3(i) includes
the Civil Code directs the application of special laws when an easement, no limitation except those enumerated after the term works. Accordingly,
such as the underground tunnel, was intended for public use, the law we consider the term works as embracing all kinds of constructions,
applicable was Section 3(i) of Republic Act No. 6395, as amended, which facilities, and other developments that can enable or help NPC to meet its
limits the action for recovery of compensation to five years from the date objectives of developing hydraulic power expressly provided under
of construction. It posits that the five-year prescriptive period already set paragraph (g) of Section 3.[23] The CAs restrictive construal of Section 3(i)
in due to the construction of the underground tunnel having been as exclusive of tunnels was obviously unwarranted, for the provision
completed in 1979 yet. applies not only to development works easily discoverable or on the
Without necessarily adopting the reasoning of the CA, we uphold its surface of the earth but also to subterranean works like tunnels. Such
conclusion that prescription did not bar the present action to recover just interpretation accords with the fundamental guideline in statutory
compensation. construction that when the law does not distinguish, so must we
not.[24] Moreover, when the language of the statute is plain and free from
Section 3 (i) of Republic Act No. 6395, the cited law, relevantly provides: ambiguity, and expresses a single, definite, and sensible meaning, that
meaning is conclusively presumed to be the meaning that the Congress
Section 3. Powers and General Functions of the intended to convey.[25]
Corporation. The powers, functions, rights and Even so, we still cannot side with NPC.
activities of the Corporation shall be the following:
We rule that the prescriptive period provided under Section 3(i)
xxx of Republic Act No. 6395 is applicable only to an action for damages, and

ProvRem Rule 67 Fulltext Page 98 of 119


does not extend to an action to recover just compensation like this case. Petitioner contends that the underground
Consequently, NPC cannot thereby bar the right of the Heirs of tunnels in this case constitute an easement upon the
Macabangkit to recover just compensation for their land. property of the respondents which does not involve
any loss of title or possession. The manner in which
The action to recover just compensation from the State or its the easement was created by petitioner, however,
expropriating agency differs from the action for damages. The former, violates the due process rights of respondents as it
also known as inverse condemnation, has the objective to recover the was without notice and indemnity to them and did
value of property taken in fact by the governmental defendant, even not go through proper expropriation proceedings.
though no formal exercise of the power of eminent domain has been Petitioner could have, at any time, validly exercised
attempted by the taking agency.[26] Just compensation is the full and fair the power of eminent domain to acquire the
equivalent of the property taken from its owner by the expropriator. The easement over respondents property as this power
measure is not the takers gain, but the owners loss. The word just is used encompasses not only the taking or appropriation of
to intensify the meaning of the word compensation in order to convey the title to and possession of the expropriated property
idea that the equivalent to be rendered for the property to be taken shall but likewise covers even the imposition of a mere
be real, substantial, full, and ample.[27] On the other hand, the latter action burden upon the owner of the condemned property.
seeks to vindicate a legal wrong through damages, which may be actual, Significantly, though, landowners cannot be deprived
moral, nominal, temperate, liquidated, or exemplary. When a right is of their right over their land until expropriation
exercised in a manner not conformable with the norms enshrined in proceedings are instituted in court. The court must
Article 19[28] and like provisions on human relations in the Civil Code,and then see to it that the taking is for public use, that
the exercise results to the damage of another, a legal wrong is committed there is payment of just compensation and that there
and the wrongdoer is held responsible.[29] is due process of law.[34]

The two actions are radically different in nature and purpose. 3.


The action to recover just compensation is based on the NPCs construction of the tunnel
Constitution[30] while the action for damages is predicated on statutory constituted taking of the land, and
enactments. Indeed, the former arises from the exercise by the State of its entitled owners to just compensation
power of eminent domain against private property for public use, but the
latter emanates from the transgression of a right. The fact that the owner
rather than the expropriator brings the former does not change the The Court held in National Power Corporation v. Ibrahim that
essential nature of the suit as an inverse condemnation,[31] for the suit is NPC was liable to pay not merely an easement fee but rather the full
not based on tort, but on the constitutional prohibition against the taking compensation for land traversed by the underground tunnels, viz:
of property without just compensation.[32] It would very well be contrary
to the clear language of the Constitution to bar the recovery of just In disregarding this procedure and failing to
compensation for private property taken for a public use solely on the recognize respondents ownership of the sub-terrain
basis of statutory prescription. portion, petitioner took a risk and exposed itself to
greater liability with the passage of time. It must be
Due to the need to construct the underground tunnel, NPC should have emphasized that the acquisition of the easement is
first moved to acquire the land from the Heirs of Macabangkit either by not without expense. The underground tunnels
voluntary tender to purchase or through formal expropriation impose limitations on respondents use of the
proceedings. In either case, NPC would have been liable to pay to the property for an indefinite period and deprive them of
owners the fair market value of the land, for Section 3(h) of Republic Act its ordinary use. Based upon the foregoing,
No. 6395 expressly requires NPC to pay the fair market value of such respondents are clearly entitled to the payment of
property at the time of the taking, thusly: just compensation. Notwithstanding the fact that
petitioner only occupies the sub-terrain portion, it
(h) To acquire, promote, hold, transfer, sell, lease, is liable to pay not merely an easement fee but
rent, mortgage, encumber and otherwise dispose rather the full compensation for land. This is so
of property incident to, or necessary, convenient because in this case, the nature of the easement
or proper to carry out the purposes for which the practically deprives the owners of its normal
Corporation was created: Provided, That in case a beneficial use. Respondents, as the owner of the
right of way is necessary for its transmission lines, property thus expropriated, are entitled to a just
easement of right of way shall only be compensation which should be neither more nor
sought: Provided, however, That in case the property less, whenever it is possible to make the
itself shall be acquired by purchase, the cost assessment, than the money equivalent of said
thereof shall be the fair market value at the time property.[35]
of the taking of such property.

Here, like in National Power Corporation v. Ibrahim, NPC constructed a


This was what NPC was ordered to do in National Power tunnel underneath the land of the Heirs of Macabangkit without going
Corporation v. Ibrahim,[33] where NPC had denied the right of the owners through formal expropriation proceedings and without procuring their
to be paid just compensation despite their land being traversed by the consent or at least informing them beforehand of the construction. NPCs
underground tunnels for siphoning water from Lake Lanao needed in the construction adversely affected the owners rights and interests because
operation of Agus II, Agus III, Agus IV, Agus VI and Agus VII Hydroelectric the subterranean intervention by NPC prevented them from introducing
Projects in Saguiran, Lanao del Sur, in Nangca and Balo-I in Lanao del any developments on the surface, and from disposing of the land or any
Norte and in Ditucalan and Fuentes in Iligan City. There, NPC similarly portion of it, either by sale or mortgage.
argued that the underground tunnels constituted a mere easement that
did not involve any loss of title or possession on the part of the property Did such consequence constitute taking of the land as to entitle the
owners, but the Court resolved against NPC, to wit: owners to just compensation?

ProvRem Rule 67 Fulltext Page 99 of 119


We agree with both the RTC and the CA that there was a full owners since then until the owners commenced the inverse condemnation
taking on the part of NPC, notwithstanding that the owners were not proceedings. The Court is more concerned with the necessity to prevent
completely and actually dispossessed. It is settled that the taking of NPC from unjustly profiting from its deliberate acts of denying due
private property for public use, to be compensable, need not be an actual process of law to the owners. As a measure of simple justice and ordinary
physical taking or appropriation.[36] Indeed, the expropriators action may fairness to them, therefore, reckoning just compensation on the value at
be short of acquisition of title, physical possession, or occupancy but may the time the owners commenced these inverse condemnation
still amount to a taking.[37] Compensable taking includes destruction, proceedings is entirely warranted.
restriction, diminution, or interruption of the rights of ownership or of the
common and necessary use and enjoyment of the property in a lawful In National Power Corporation v. Court of Appeals,[42] a case that
manner, lessening or destroying its value.[38] It is neither necessary that involved the similar construction of an underground tunnel by NPC
the owner be wholly deprived of the use of his property,[39] nor material without the prior consent and knowledge of the owners, and in which we
whether the property is removed from the possession of the owner, or in held that the basis in fixing just compensation when the initiation of the
any respect changes hands.[40] action preceded the entry into the property was the time of the filing of
the complaint, not the time of taking,[43] we pointed out that there was no
As a result, NPC should pay just compensation for the entire taking when the entry by NPC was made without intent to expropriate or
land. In that regard, the RTC pegged just compensation at P500.00/square was not made under warrant or color of legal authority.
meter based on its finding on what the prevailing market value of the 4.
property was at the time of the filing of the complaint, and the CA upheld Awards for rentals, moral damages, exemplary
the RTC. damages, and attorneys fees are deleted
for insufficiency of factual and legal bases
We affirm the CA, considering that NPC did not assail the valuation in the
CA and in this Court. NPCs silence was probably due to the correctness of
the RTCs valuation after careful consideration and weighing of the parties The CA upheld the RTCs granting to the Heirs of Macabangkit of rentals
evidence, as follows: of P 30,000.00/month from 1979 up to July 1999 with 12% interest per
annum by finding NPC guilty of bad faith in taking possession of the land
The matter of what is just compensation for to construct the tunnel without their knowledge and consent.
these parcels of land is a matter of evidence. These
parcels of land is (sic) located in the City of Iligan, the Granting rentals is legally and factually bereft of justification, in
Industrial City of the South. Witness Dionisio light of the taking of the land being already justly compensated.
Banawan, OIC- City Assessors Office, testified, Within Conformably with the ruling in Manila International Airport Authority v.
that area, that area is classified as industrial and Rodriguez,[44] in which the award of interest was held to render the grant
residential. That plaintiffs land is adjacent to many of back rentals unwarranted, we delete the award of back rentals and in
subdivisions and that is within the industrial its place prescribe interest of 12% interest per annum from November 21,
classification. He testified and identified Exhibit AA 1997, the date of the filing of the complaint, until the full liability is paid
and AA-1, a Certification, dated April 4, 1997, by NPC. The imposition of interest of 12% interest per annum follows a
showing that the appraised value of plaintiffs land long line of pertinent jurisprudence,[45] whereby the Court has fixed the
ranges from P400.00 to P500.00 per square meter rate of interest on just compensation at 12% per annumwhenever the
(see, TSN, testimony of Dionisio Banawan, pp. 51, 57, expropriator has not immediately paid just compensation.
and 71, February 9, 1999). Also, witness Banawan,
testified and identified Two (2) Deeds of Sale, marked The RTC did not state any factual and legal justifications for awarding to
as Exhibit AA-2 and AA-3,[] showing that the the Heirs of Macabangkit moral and exemplary damages each in the
appraised value of the land adjoining or adjacent to amount of P200,000.00. The awards just appeared in the fallo of its
plaintiff land ranges from P700.00 to P750.00 per decision. Neither did the CA proffer any justifications for sustaining the
square meter. As between the much lower price of RTC on the awards. We consider the omissions of the lower courts as pure
the land as testified by defendants witness Gregorio legal error that we feel bound to correct even if NPC did not submit that
Enterone, and that of the City Assessor of Iligan City, for our consideration. There was, to begin with, no factual and legal bases
the latter is more credible. Considering however, that mentioned for the awards. It is never trite to remind that moral and
the appraised value of the land in the area as exemplary damages, not by any means liquidated or assessed as a matter
determined by the City Assessors Office is not of routine, always require evidence that establish the circumstances under
uniform, this Court, is of the opinion that the which the claimant is entitled to them. Moreover, the failure of both the
reasonable amount of just compensation of plaintiffs RTC and the CA to render the factual and legal justifications for the moral
land should be fixed at FIVE HUNDRED (500.00) and exemplary damages in the body of their decisions immediately
PESOS, per square meter. xxx.[41] demands the striking out of the awards for being in violation of the
fundamental rule that the decision must clearly state the facts and the law
The RTC based its fixing of just compensation ostensibly on the prevailing on which it is based. Without the factual and legal justifications, the
market value at the time of the filing of the complaint, instead of awards are exposed as the product of conjecture and speculation, which
reckoning from the time of the taking pursuant to Section 3(h) of have no place in fair judicial adjudication.
Republic Act No. 6395. The CA did not dwell on the reckoning time,
possibly because NPC did not assign that as an error on the part of the We also reverse and set aside the decree of the RTC for NPC to pay to the
RTC. Heirs of Macabangkit the sum equivalent to 15% of the total amount
awarded, as attorneys fees, and to pay the cost. The body of the decision
We rule that the reckoning value is the value at the time of the did not state the factual and legal reasons why NPC was liable for
filing of the complaint, as the RTC provided in its decision. Compensation attorneys fees. The terse statement found at the end of the body of the
that is reckoned on the market value prevailing at the time either when RTCs decision, stating: xxx The contingent attorneys fee is hereby reduced
NPC entered or when it completed the tunnel, as NPC submits, would not from 20% to only 15% of the total amount of the claim that may be
be just, for it would compound the gross unfairness already caused to the awarded to plaintiffs, without more, did not indicate or explain
owners by NPCs entering without the intention of formally expropriating why and how the substantial liability of NPC for attorneys fees could have
the land, and without the prior knowledge and consent of the Heirs of arisen and been determined.
Macabangkit. NPCs entry denied elementary due process of law to the

ProvRem Rule 67 Fulltext Page 100 of 119


In assessing attorneys fees against NPC and in favor of the
respondents, the RTC casually disregarded the fundamental distinction Based on the pending motions of Atty. Macarupung Dibaratun
between the two concepts of attorneys fees the ordinary and the and Atty. Manuel D. Ballelos to assert their respective rights to attorneys
extraordinary. These concepts were aptly distinguished in Traders Royal fees, both contending that they represented the Heirs of Macabangkit in
Bank Employees Union-Independent v. NLRC,[46] thuswise: this case, a conflict would ensue from the finality of the judgment against
NPC.
There are two commonly accepted concepts
of attorneys fees, the so-called ordinary and A look at the history of the legal representation of the Heirs of
extraordinary. In its ordinary concept, an attorneys Macabangkit herein provides a helpful predicate for resolving the conflict.
fee is the reasonable compensation paid to a lawyer
by his client for the legal services he has rendered to Atty. Dibaratun was the original counsel of the Heirs of Macabangkit.
the latter. The basis of this compensation is the fact When the appeal was submitted for decision in the CA,[55] Atty. Ballelos
of his employment by and his agreement with the filed his entry of appearance,[56]and a motion for early decision.[57] Atty.
client. Ballelos
subsequently filed also a manifestation,[58] supplemental manifestation,[59]
In its extraordinary concept, an attorneys fee
is an indemnity for damages ordered by the court to reply,[60] and ex parte motion reiterating the motion for early decision.[61] It
be paid by the losing party in a litigation. The basis of appears that a copy of the CAs decision was furnished solely to Atty.
this is any of the cases provided by law where such Ballelos. However, shortly before the rendition of the decision, Atty.
award can be made, such as those authorized in Dibaratun filed in the CA a motion to register attorneys lien, [62] alleging
Article 2208, Civil Code, and is payable not to the that he had not withdrawn his appearance and had not been aware of the
lawyer but to the client, unless they have agreed that entry of appearance by Atty. Ballelos. A similar motion was also received
the award shall pertain to the lawyer as additional by the Court from Atty. Dibaratun a few days after the petition for review
compensation or as part thereof. was filed.[63] Thus, on February 14, 2005,[64] the Court directed Atty.
Dibaratun to enter his appearance herein. He complied upon filing the
comment.[65]
By referring to the award as contingency fees, and reducing the
award from 20% to 15%, the RTC was really referring to a supposed Amir Macabangkit confirmed Atty. Dibaratuns representation through
agreement on attorneys fees between the Heirs of Macabangkit and their an ex parte manifestation that he filed in his own behalf and on behalf of
counsel. As such, the concept of attorneys fees involved was the his siblings Mongkoy and Putri.[66]Amir reiterated his manifestation on
ordinary. Yet, the inclusion of the attorneys fees in the judgment among March 6, 2006,[67] and further imputed malpractice to Atty. Ballelos for
the liabilities of NPC converted the fees to extraordinary. We have to having filed an entry of appearance bearing Amirs forged signature and
disagree with the RTC thereon, and we express our discomfort that the for plagiarism, i.e., copying verbatim the arguments contained in the
CA did not do anything to excise the clearly erroneous and pleadings previously filed by Atty. Dibaratun.[68]
unfounded grant.
On September 11, 2008, Atty. Ballelos submitted two motions, to wit: (a) a
manifestation and motion authorizing a certain Abdulmajeed Djamla to
An award of attorneys fees has always been the exception receive his attorneys fees equivalent of 15% of the judgment
rather than the rule. To start with, attorneys fees are not awarded every award,[69] and (b) a motion to register his attorneys lien that he claimed
time a party prevails in a suit.[47] Nor should an adverse decision ipso was contingent.[70]
facto justify an award of attorneys fees to the winning party. [48] The policy
of the Court is that no premium should be placed on the right to Both Atty. Dibaratun and Atty. Ballelos posited that their entitlement to
litigate.[49] Too, such fees, as part of damages, are assessed only in the attorneys fees was contingent. Yet, a contract for a contingent fees is an
instances specified in Art. 2208, Civil Code.[50] Indeed, attorneys fees are in agreement in writing by which the fees, usually a fixed percentage of what
the nature of actual damages.[51] But even when a claimant is compelled may be recovered in the action, are made to depend upon the success in
to litigate with third persons or to incur expenses to protect his rights, the effort to enforce or defend a supposed right. Contingent fees depend
attorneys fees may still be withheld where no sufficient showing of bad upon an express contract, without which the attorney can only recover on
faith could be reflected in a partys persistence in a suit other than an the basis of quantum meruit.[71] With neither Atty. Dibaratun nor Atty.
erroneous conviction of the righteousness of his cause.[52] And, lastly, the Ballelos presenting a written agreement bearing upon their supposed
trial court must make express findings of fact and law that bring contingent fees, the only way to determine their right to appropriate
the suit within the exception. What this demands is that the factual, legal attorneys fees is to apply the principle of quantum meruit.
or equitable justifications for the award must be set forth
Quantum meruit literally meaning as much as he deserves is used as basis
for determining an attorneys professional fees in the absence of an
express agreement.[72] The recovery of attorneys fees on the basis
not only in the fallo but also in the text of the decision, or else, the award of quantum meruit is a device that prevents an unscrupulous client from
should be thrown out for being speculative and conjectural.[53] running away with the fruits of the legal services of counsel without
paying for it and also avoids unjust enrichment on the part of the attorney
Sound policy dictates that even if the NPC failed to raise the himself.[73] An attorney must show that he is entitled to reasonable
issue of attorneys fees, we are not precluded from correcting the lower compensation for the effort in pursuing the clients cause, taking into
courts patently erroneous application of the law.[54] Indeed, the Court, in account certain factors in fixing the amount of legal fees.[74]
supervising the lower courts, possesses the ample authority to
review legal matters like this one even if not specifically raised or assigned Rule 20.01 of the Code of Professional Responsibility lists the guidelines for
as error by the parties. determining the proper amount of attorney fees, to wit:

5. Rule 20.1 A lawyer shall be guided by the


Attorneys fees under quantum meruit principle following factors in determining his fees:
are fixed at 10% of the judgment award

ProvRem Rule 67 Fulltext Page 101 of 119


a) The time spent and the extent of the advancedP250,000.00 out of his own pocket to defray expenses from the
services rendered or required; time of the filing of the motion to execute pending appeal until the case
reached the Court.[77] His representation of all the Heirs of Macabangkit
b) The novelty and difficult of the was not denied by any of them.
questions involved;
We note that Atty. Dibaratun possessed some standing in the
c) The important of the subject matter; legal profession and in his local community. He formerly served as a
member of the Board of Director of the Integrated Bar of the Philippines
d) The skill demanded; (IBP), Lanao del Norte-Iligan City Chapter, and was an IBP national
awardee as Best Legal Aid Committee Chairman. He taught at Mindanao
e) The probability of losing other State University College of Law Extension. He was a Municipal Mayor of
employment as a result of acceptance of the Matungao, Lanao del Norte, and was enthroned Sultan a Gaus.
proffered case;
In contrast, not much about the character and standing of Atty. Ballelos,
f) The customary charges for similar as well as the nature and quality of the legal services he rendered
services and the schedule of fees of the IBP chapter for the Heirs of Macabangkit are in the records. The motions he filed in
to which he belongs; the

g) The amount involved in the controversy Court and in the CA lacked enlightening research and were insignificant
and the benefits resulting to the client from the to the success of the clients cause. His legal service, if it can be called that,
service; manifested no depth or assiduousness, judging from the quality of the
pleadings from him. His written submissions in the case appeared either
h) The contingency or certainty of to have been lifted verbatim from the pleadings previously filed by Atty.
compensation; Dibaratun, or to have been merely quoted from the decisions and
resolutions of the RTC and the CA. Of the Heirs of Macabangkit, only
i) The character of the employment, Cebu, Batowa-an, Sayana, Nasser, Manta, Mongkoy[78] and Edgar gave
whether occasional or established; and their consent to Atty. Ballelos to appear in their behalf in the CA, which he
did despite Atty. Dibaratun not having yet filed any withdrawal of his
j) The professional standing of the lawyer. appearance. The Court did not receive any notice of appearance for the
Heirs of Macabangkit from Atty. Ballelos, but that capacity has meanwhile
In the event of a dispute as to the amount of fees between the become doubtful in the face of Amirs strong denial of having retained
attorney and his client, and the intervention of the courts is sought, the him.
determination requires that there be evidence to prove the amount of
fees and the extent and value of the services rendered, taking into In fairness and justice, the Court accords full recognition to
account the facts determinative thereof.[75] Ordinarily, therefore, the Atty. Dibaratun as the counsel de parte of the Heirs of Macabangkit who
determination of the attorneys fees on quantum meruit is remanded to discharged his responsibility in the prosecution of the clients cause to its
the lower court for the purpose. However, it will be just and equitable to successful end. It is he, not Atty. Ballelos, who was entitled to the full
now assess and fix the attorneys fees of both attorneys in order that the amount of attorneys fees that the clients ought to pay to their attorney.
resolution of a comparatively simple controversy, as Justice Regalado put Given the amount and quality of his legal work, his diligence and the time
it in Traders Royal Bank Employees Union-Independent v. NLRC,[76] would he expended in ensuring the success of his prosecution of the clients
not be needlessly prolonged, by taking into due consideration the cause, he deserves the recognition, notwithstanding that some of the
accepted guidelines and so much of the pertinent data as are extant in clients might appear to have retained Atty. Ballelos after the rendition of a
the records. favorable judgment.[79]

Atty. Dibaratun and Atty. Ballelos each claimed attorneys fees equivalent Atty. Ballelos may claim only from Cebu, Batowa-an, Sayana, Nasser,
to 15% of the principal award of P113,532,500.00, which was the amount Manta and Edgar, the only parties who engaged him. The Court considers
granted by the RTC in its decision. Considering that the attorneys fees will his work in the case as very minimal. His compensation under
be defrayed by the Heirs of Macabangkit out of their actual recovery from the quantum meruit principle is fixed at P5,000.00, and only the Heirs of
NPC, giving to each of the two attorneys 15% of the principal award as Macabangkit earlier named are liable to him.
attorneys fees would be excessive and unconscionable from the point of
view of the clients. Thus, the Court, which holds and exercises the power
to fix attorneys fees on a quantum meruit basis in the absence of an WHEREFORE, the Court AFFIRMS the decision promulgated on October
express written agreement between the attorney and the client, now fixes 5, 2004 by the Court of Appeals, subject to the
attorneys fees at 10% of the principal award of P113,532,500.00. following MODIFICATIONS, to wit:
Whether it is Atty. Dibaratun or Atty. Ballelos, or both, who
should receive attorneys fees from the Heirs of Macabangkit is a question (a) Interest at the rate of 12% per
that the Court must next determine and settle by considering the amount annum is IMPOSED on the principal amount
and quality of the work each performed and the results each obtained. of P113,532,500.00 as just compensation,
reckoned from the filing of the complaint on
Atty. Dibaratun, the attorney from the outset, unquestionably carried the November 21, 1997 until the full liability is paid;
bulk of the legal demands of the case. He diligently prepared and timely
filed in behalf of the Heirs of Macabangkit every pleading and paper (b) The awards of P30,000.00 as rental
necessary in the full resolution of the dispute, starting from the complaint fee, P200,000.00 as moral damages,
until the very last motion filed in this Court. He consistently appeared and P200,000.00 as exemplary damages
during the trial, and examined and cross-examined all the witnesses are DELETED; and
presented at that stage of the proceedings. The nature, character, and
substance of each pleading and the motions he prepared for the Heirs of (c) The award of 15% attorneys fees decreed to be
Macabangkit indicated that he devoted substantial time and energy in paid by National Power Corporation to the Heirs
researching and preparing the case for the trial. He even of Macabangkit is DELETED.

ProvRem Rule 67 Fulltext Page 102 of 119


The Court PARTLY GRANTS the motion to register attorneys lien filed by
Atty. Macarupung Dibaratun, and FIXES Atty. Dibaratuns attorneys fees A parcel of land (Lot 15, Pcs-11-000704, Amd.), being
on the basis of quantummeruit at 10% of the principal award a portion of Lots 481-D, Psd-11-012718; 480-B, Psd-
of P113,532,500.00. 51550; H-148559 & 463-A-2 (LRC) Psd-150796,
situated in the Barrio of Magugpo, Mun. of Tagum,
The motion to register attorneys lien of Atty. Manuel D. Ballelos Province of Davao, Island of Mindanao. x x x[11]
is PARTLY GRANTED, and Atty. Ballelos is DECLARED ENTITLED TO
RECOVER from Cebu, Batowa-an, Sayana, Nasser, Manta and Edgar, all On 19 August 1999, respondents filed the instant Complaint
surnamed Macabangkit, the amount of P5,000.00 as attorneys fees on the against NAPOCOR and demanded the payment of just compensation.
basis of quantum meruit. They alleged that it had entered and occupied their property by erecting
high-tension transmission lines therein and failed to reasonably
compensate them for the intrusion.[12]

Costs of suit to be paid by the petitioner. Petitioner averred that it already paid just compensation for the
establishment of the transmission lines by virtue of its compliance with
SO ORDERED. the final and executory Decision in National Power Corporation v.
Pereyras. Furthermore, assuming that respondent spouses had not yet
received adequate compensation for the intrusion upon their property,
#13 G. R. No. 189127 April 25, 2012 NAPOCOR argued that a claim for just compensation and damages may
only be filed within five years from the date of installation of the
NATIONAL POWER CORPORATION, Present: transmission lines pursuant to the provisions of Republic Act (R.A.) No.
Petitioner, 6395.[13]
CARPIO, J., Chairperson,
BRION, Pretrial terminated without the parties having entered into a compromise
PEREZ, agreement.[14] Thereafter, the court appointed Lydia Gonzales and
- versus - SERENO, and Wilfredo Silawan as Commissioners for the purpose of determining the
REYES, JJ. valuation of the subject land.[15] NAPOCOR recommended Loreto
Monteposo as the third Commissioner,[16] but later clarified that its
conformity to the appointment of commissioners was only for the
SPOUSES BERNARDO AND purpose of determining the exact portion of the subject land, and that it
MINDALUZ SALUDARES, was not admitting its liability to pay just compensation.[17]
Respondents.
After the proceedings, the Commissioners recommended the amount
of ₱750 per square meter as the current and fair market value of the
x-------------------------------x subject property based on the Schedule of Market Values of Real
SERENO, J.: Properties within the City of Tagum effective in the year 2000.[18]

This Rule 45 Petition questions the 21 July 2009 Decision of the Trial on the merits ensued. On 10 September 2002, the Court
Court of Appeals (CA),[1] which affirmed the 10 September 2002 Decision rendered judgment in favor of respondent spouses, the dispositive
of the Regional Trial Court (RTC),[2] Branch 31, Tagum City. The RTC had portion of which reads:
ruled that respondent spouses are entitled to ₱4,920,750 as just
compensation for the exercise of the power of eminent domain by WHEREFORE, premises considered, judgment is
petitioner National Power Corporation (NAPOCOR). hereby rendered in favor of the plaintiffs, and against
Sometime in the 1970s, NAPOCOR constructed high-tension the defendant-National Power Corporation, ordering
transmission lines to implement the Davao-Manat 138 KV Transmission the latter to pay the plaintiffs the Just Compensation
Line Project.[3] These transmission lines traversed a 12,060-square meter as herein fixed which they claimed for the use,
portion of a parcel of agricultural land covered by Transfer Certificate of occupation and utilization of their land from which it
Title (TCT) No. T-15343 and owned by Esperanza Pereyras, Marciano benefited and profited since January 1982, as follows:
Pereyras, Laureano Pereyras and Mindaluz Pereyras.
First: To pay plaintiff Spouses Bernardo and Mindaluz
In 1981, NAPOCOR commenced expropriation proceedings Saludares as just compensation of their 6,561 square
covering TCT No. T-15343 in National Power Corporation v. Esperanza meters, more or less, titled land covered by TCT No.
Pereyras, Marciano Pereyras, Laureano Pereyras and Mindaluz T-109865 of the Registry of Deeds of Davao del
Pereyras.[4] These proceedings culminated in a final Decision ordering it to Norte hereby fixed in the amount of FOUR MILLION
pay the amount of ₱300,000 as just compensation for the affected NINE HUNDRED TWENTY THOUSAND SEVEN
property.[5] HUNDRED FIFTY (₱4,920,750.00) PESOS, Philippine
Currency, plus interest at the rate of 12% per annum
The trial court issued an Order[6] subrogating Tahanan Realty reckoned from January 01, 1982, until said amount is
Development Corporation to the rights of the defendants in National fully paid, or deposited in Court;
Power Corporation v. Pereyras. Pursuant to this Order, NAPOCOR paid the
corporation the judgment award of ₱300,000[7] and Tahanan Realty Second: To pay plaintiffs-spouses Bernardo and
Development Corporation executed a Deed of Absolute Sale in favor of Mindaluz Saludares attorneys fees of Fifty Thousand
the former.[8] This Deed covered Lot 481-B, Psd-11012718, which was a (₱50,000.00) Pesos, Philippine Currency, plus
portion of Lot 481, Cad. 276 of Barrio Magugpo, Municipality of Tagum, appearance fee of ₱2,000.00 per appearance and
Davao.[9] litigation expenses which shall be supported in a Bill
of Costs to be submitted for the Courts approval;
Respondent Spouses Bernardo and Mindaluz Pereyras-
Saludares are registered owners of a 6,561-square-meter parcel of land Third. To pay the costs of the suit.
covered by TCT No. T-109865,[10] more particularly described as follows:
ProvRem Rule 67 Fulltext Page 103 of 119
Fourth. For utter lack of merit, the counterclaim is Furthermore, the evidence before us supports respondent
dismissed. spouses contention that the lands involved in both cases are
different. National Power Corporation v. Pereyrasinvolved Lot 481-B, Psd-
SO ORDERED.[19] 11012718, which was a portion of Lot 481, Cad. 276 of Barrio Magugpo,
Municipality of Tagum, Davao.[24] On the other hand, the instant Petition
involves Lot 15, Pcs-11-000704, Amd., which is a portion of Lots 481-D,
NAPOCOR appealed the trial courts Decision to the CA.[20] After Psd-11-012718; 480-B, Psd-51550; H-148559 and 463-A-2 (LRC), Psd-
a review of the respective parties Briefs, the appellate court rendered the 150796, in Barrio Magugpo, Municipality of Tagum, Davao. Clearly, these
assailed Decision on 21 July 2009, denying NAPOCORs appeal and lots refer to different parcels of land.[25]
affirming the trial courts Decision, but reducing the rate of interest to 6%
per annum.[21] We rule, therefore, that NAPOCOR failed to prove its previous payment of
just compensation for its expropriation of the land in question.
Aggrieved, petitioner then filed the instant Rule 45 Petition
before this Court. II
The demand for payment of just compensation
has not prescribed
The Issues

The pivotal issues as distilled from the pleadings are as follows: Petitioner maintains that, in the event respondent spouses have not been
adequately compensated for the entry into their property, their claim for
1. Whether NAPOCOR has previously compensated the just compensation would have already prescribed,[26] pursuant to Section
spouses for establishing high-tension transmission lines 3 (i) of R.A. No. 6395, as amended by Presidential Decrees Nos. 380, 395,
over their property; 758, 938, 1360 and 1443. This provision empowers the NAPOCOR to do as
follows:
2. Whether the demand for payment of just compensation
has already prescribed; x x x [E]nter upon private property in the lawful
performance or prosecution of its business or
3. Whether petitioner is liable for only ten percent of the fair purposes, including the construction of the
market value of the property or for the full value thereof; transmission lines thereon; Provided, that the owner
and of such private property shall be paid the just
compensation therefor in accordance with the
4. Whether the trial court properly awarded the amount provisions hereinafter provided; Provided, further,
of ₱4,920,750 as just compensation, based on the that any action by any person claiming
Approved Schedule of Market Values for Real Property in compensation and/or damages shall be filed
Tagum City for the Year 2000. within five (5) years after the right-of-way,
transmission lines, substations, plants or other
The Courts Ruling facilities shall have been established; Provided,
finally, that after the said period no suit shall be
We uphold the Decisions of the CA and the RTC. brought to question the said right-of-way,
transmission lines, substations, plants or other
I facilities nor the amounts of compensation and/or
NAPOCOR failed to prove that it had adequately damages involved. (Emphasis supplied.)
compensated respondents for the establishment
of high tension transmission lines over their NAPOCORs reliance on this provision is misplaced.
property
The right to recover just compensation is enshrined in no less than our Bill
of Rights, which states in clear and categorical language that [p]rivate
NAPOCOR argues that the parcel of land involved in the instant property shall not be taken for public use without just
Petition had already been expropriated in National Power Corporation v. compensation.[27] This constitutional mandate cannot be defeated by
Pereyras.[22] In support of this argument, it alleges that one of the sources statutory prescription.[28] Thus, we have ruled that the prescriptive period
of the spouses TCT No. T-109865 is TCT No. 39660; and that TCT No. under Section 3 (i) of R.A. No. 6395 does not extend to an action to
39660 is a transfer from TCT No. T-15343, the subject land in National recover just compensation.[29] It would be a confiscatory act on the part of
Power Corporation v. Pereyras.[23] Thus, having paid just compensation to the government to take the property of respondent spouses for a public
Tahanan Realty Development Corporation, the successor-in-interest of purpose and deprive them of their right to just compensation, solely
defendants Pereyras in the aforementioned case, petitioner submits that it because they failed to institute inverse condemnation proceedings within
should no longer be made to pay just compensation in the present case. five years from the time the transmission lines were constructed. To begin
with, it was not the duty of respondent spouses to demand for just
We disagree. compensation. Rather, it was the duty of NAPOCOR to institute eminent
domain proceedings before occupying their property. In the normal
While it is true that respondent spouses TCT No. T-109865 was indeed course of events, before the expropriating power enters a private
indirectly sourced from TCT No. T-15343, the CA correctly ruled that property, it must first file an action for eminent domain[30] and deposit
NAPOCOR failed to prove that the lands involved in National Power with the authorized government depositary an amount equivalent to the
Corporation v. Pereyras and in the instant Petition are identical. One assessed value of the property.[31] Due to its omission, however,
cannot infer that the subject lands in both cases are the same, based on respondents were constrained to file inverse condemnation proceedings
the fact that one of the source titles of TCT No. T-109865 happens to be to demand the payment of just compensation before the trial court. We
TCT No. T-38660, and that TCT No. T-38660 itself was derived from T- therefore rule that NAPOCOR cannot invoke the statutory prescriptive
15343. period to defeat respondent spouses constitutional right to just
compensation.

ProvRem Rule 67 Fulltext Page 104 of 119


III must be determined from the time of the filing of the complaint or the
NAPOCOR is liable to pay the full market value time of taking of the subject property, whichever came first. [41] It therefore
of the affected property posits that since the taking of the property happened in the 1970s, the
trial court erred in fixing the amount of just compensation with reference
to real property market values in the year 2000.[42]
NAPOCOR submits that it should pay for only ten percent (10%)
of the fair market value of the landowners property because, under its Petitioners contention holds no water.
Charter,[32] it is only authorized to acquire easements of right-of-way over
agricultural lands.[33] We have ruled in National Power Corporation v. Heirs of Macabangkit
Sangkay[43] that the reckoning value of just compensation is that
Petitioners arguments fail to convince. prevailing at the time of the filing of the inverse condemnation
proceedings for the following reason:
We have ruled that when petitioner takes private property to
construct transmission lines, it is liable to pay the full market value upon [c]ompensation that is reckoned on the market value
proper determination by the courts.[34] prevailing at the time either when NPC entered x x x
would not be just, for it would compound the gross
unfairness already caused to the owners by NPC's
entering without the intention of formally
expropriating the land x x x. NPC's entry denied
In National Power Corporation v. Gutierrez,[35] the petitioner elementary due process of law to the owners since
likewise argued that it should only be made to pay easement fees instead then until the
of the full market value of the land traversed by its transmission lines. In
striking down its argument and ruling that the property owners were
entitled to the full market value of the land in question, we ruled: owners commenced the inverse condemnation
proceedings. The Court is more concerned with the
x x x While it is true that plaintiff [is] only after a necessity to prevent NPC from unjustly profiting from
right-of-way easement, it nevertheless perpetually its deliberate acts of denying due process of law to
deprives defendants of their proprietary rights as the owners. As a measure of simple justice and
manifested by the imposition by the plaintiff upon ordinary fairness to them, therefore, reckoning just
defendants that below said transmission lines no compensation on the value at the time the owners
plant higher than three (3) meters is allowed. commenced these inverse condemnation
Furthermore, because of the high-tension current proceedings is entirely warranted.
conveyed through said transmission lines, danger to
life and limbs that may be caused beneath said wires
cannot altogether be discounted, and to cap it all, Indeed, respondent spouses would be deprived of their right to
plaintiff only pays the fee to defendants once, while just compensation if the value of the property is pegged back to its value
the latter shall continually pay the taxes due on said in the 1970s. To reiterate, NAPOCOR should have instituted eminent
affected portion of their property.[36] domain proceedings before it occupied respondent spouses property.
Because it failed to comply with this duty, respondent spouses were
Similarly, in this case, while respondent spouses could still constrained to file the instant Complaint for just compensation before the
utilize the area beneath NAPOCORs transmission lines provided that the trial court. From the 1970s until the present, they were deprived of just
plants to be introduced underneath would not exceed three compensation, while NAPOCOR continuously burdened their property
meters,[37] danger is posed to the lives and limbs of respondents farm with its transmission lines. This Court cannot allow petitioner to profit
workers, such that the property is no longer suitable for agricultural from its failure to comply with the mandate of the law. We therefore rule
production.[38]Considering the nature and effect of the Davao-Manat 138 that, to adequately compensate respondent spouses from the decades of
KV transmission lines, the limitation imposed by NAPOCOR perpetually burden on their property, NAPOCOR should be made to pay the value of
deprives respondents of the ordinary use of their land. the property at the time of the filing of the instant Complaint when
respondent spouses made a judicial demand for just compensation.
Moreover, we have ruled that Section 3A of R.A. No. 6395, as
amended, is not binding upon this Court.[39] [T]he determination of just WHEREFORE, premises considered, the instant Petition for Review
compensation in eminent domain cases is a judicial function and . . . any is DENIED, and the Decision of the Court of Appeals in CA-G.R. CV No.
valuation for just compensation laid down in the statutes may serve only 81098 dated 21 July 2009 is AFFIRMED.
as a guiding principle or one of the factors in determining just
compensation but it may not substitute the court's own judgment as to SO ORDERED.
what amount should be awarded and how to arrive at such amount.[40]

We therefore rule that NAPOCOR is liable to pay respondents


the full market value of the affected property as determined by the
court a quo.
#14 G.R. No. 179334 April 21, 2015
IV
The trial court did not err in awarding just SECRETARY OF THE DEPARTMENT OF PUBLIC WORKS AND
compensation based on the Approved Schedule of HIGHWAYS and DISTRICT ENGINEER CELESTINO R.
Market Values for CONTRERAS, Petitioners,
Real Property for the Year 2000 vs.
SPOUSES HERACLEO and RAMONA TECSON, Respondents.
As its final argument, petitioner contends that the amount of just
compensation fixed by the trial court is unjust, unlawful and contrary to RESOLUTION
existing jurisprudence, because just compensation in expropriation cases

ProvRem Rule 67 Fulltext Page 105 of 119


PERALTA, J.: Opinion, respectively, respondents-movants insist that gross injustice will
result if the amount that will be awarded today will be based simply on
For resolution is the Motion for Reconsideration1 filed by respondents- the value of the property at the time of the actual taking. Hence, as
movants spouses Heracleo and Ramona Tecson imploring the Court to proposed by Justice Leonen, they suggest that a happy middle ground be
take a second look at its July 1, 2013 Decision, the dispositive portion of achieved by meeting the need for doctrinal precision and the thirst for
which reads: substantial justice.7

WHEREFORE, premises considered, the petition is PARTIALLY GRANTED. We maintain our conclusions in the assailed July 1, 2013 Decision with
The Court of Appeals Decision dated July 31, 2007 in CAG.R. CV No. modification on the amount of interest awarded, as well as the additional
77997 is MODIFIED, in that the valuation of the subject property owned grant of exemplary damages and attorney's fees.
by respondents shall be P0.70 instead of ₱1,500.00 per square meter, with
interest at six percent (6%) per annum from the date of taking in 1940 At the outset, it should be stressed that the matter of the validity of the
instead of March 17, 1995, until full payment.2 State's exercise of the power of eminent domain has long been settled. In
fact, in our assailed decision, We have affirmed the ruling of the CA that
In view of the contrasting opinions of the members of the Third Division the pre-trial order issued on May 17, 2001 has limited the issues as
on the instant motion, and the transcendental importance of the issue follows: (1) whether or not the respondents-movants are entitled to just
raised herein, the members of the Third Division opted to refer the issue compensation; (2) whether or not the valuation would be based on the
to the En Banc for resolution. corresponding value at the time of the taking or at the time of the filing
of the action; and (3) whether or not the respondents-movants are
entitled to damages.8 Moreover, it was held that for failure of
For a proper perspective, we briefly state the factual background of the respondents-movants to question the lack of expropriation proceedings
case.
for a long period of time, they are deemed to have waived and are
estopped from assailing the power of the government to expropriate or
In 1940, the Department of Public Works and Highways (DPWH) took the public use for which the power was exercised.9 What is, therefore, left
respondents-movants' subject property without the benefit of for determination in the instant Motion for Reconsideration, in
expropriation proceedings for the construction of the MacArthur accordance with our Decision dated July 1, 2013, is the propriety of the
Highway. In a letter dated December 15, 1994,respondents-movants amount awarded to respondents as just compensation.
demanded the payment of the fair market value of the subject parcel of
land. Celestino R. Contreras (Contreras), then District Engineer of the First At this juncture, We hold that the reckoning date for property valuation in
Bulacan Engineering District of the DPWH, offered to pay for the subject determining the amount of just compensation had already been
land at the rate of Seventy Centavos (P0.70) per square meter, per addressed and squarely answered in the assailed decision. To be sure, the
Resolution of the Provincial Appraisal Committee (PAC) of Bulacan. justness of the award had been taken into consideration in arriving at our
Unsatisfied with the offer, respondents-movants demanded the return of earlier conclusion.
their property, or the payment of compensation at the current fair market
value.3 Hence, the complaint for recovery of possession with damages
filed by respondents-movants. Respondents-movants were able to obtain We have in the past been confronted with the same issues under similar
favorable decisions in the Regional Trial Court (RTC) and the Court of factual and procedural circumstances. We find no reason to depart from
Appeals (CA), with the subject property valued at One Thousand Five the doctrines laid down in the earlier cases as we adopted in the assailed
Hundred Pesos (₱1,500.00) per square meter, with interest at six percent decision. In this regard, we reiterate the doctrines laid down in the cases
(6%) per annum. of Forfom Development Corporation (Forfom) v. Philippine National
Railways (PNR),10 Eusebio v. Luis,11 Manila International Airport Authority v.
Rodriguez,12 and Republic v. Sarabia.13
Petitioners thus elevated the matter to this Court in a petition for review
on certiorari. The only issue resolved by the Court in the assailed decision
is the amount of just compensation which respondents-movants are In Forfom, PNR entered the property of Forfom in January 1973 for
entitled to receive from the government for the taking of their property. railroad tracks, facilities and appurtenances for use of the Carmona
Both the RTC and the CA valued the property at One Thousand Five Commuter Service without initiating expropriation proceedings. In 1990,
Hundred Pesos (₱1,500.00) per square meter, plus six percent (6%) Forfom filed a complaint for recovery of possession of real property
interest from the time of the filing of the complaint until full payment. We, and/or damages against PNR. In Eusebio, respondent's parcel of land was
however, did not agree with both courts and ruled instead that just taken in 1980 by the City of Pasig and used as a municipal road without
compensation should be based on the value of the property at the time of the appropriate expropriation proceedings. In1996, respondent filed a
taking in 1940, which is Seventy Centavos (P0.70) per square meter.4 In complaint for reconveyance and/or damages against the city government
addition, and by way of compensation, we likewise awarded an interest of and the mayor. In MIAA, in the early 1970s, petitioner implemented
six percent (6%) per annum from 1940 until full payment.5 expansion programs for its runway, necessitating the acquisition and
occupation of some of the properties surrounding its premises. As to
respondent's property, no expropriation proceedings were initiated. In
Aggrieved, respondents-movants hereby move for the reconsideration of 1997, respondent initiated a case for accion reivindicatoriawith damages
said decision on the following grounds:
against petitioner. In Republic, sometime in 1956, the Air Transportation
Office (ATO) took possession and control of a portion of a lot situated in
A. THE HONORABLE COURT MAY LOOK INTO THE "JUSTNESS" Aklan, registered in the name of respondent, without initiating
OF THE MISERABLE AMOUNT OF COMPENSATION BEING expropriation proceedings. Several structures were erected thereon,
AWARDED TO THE HEREIN RESPONDENTS; and including the control tower, the Kalibo crash fire rescue station, the Kalibo
airport terminal, and the Headquarters of the PNP Aviation Security
B. THE HONORABLE COURT MAY SETTLE FOR A HAPPY MIDDLE Group. In 1995,several stores and restaurants were constructed on the
GROUND IN THE NAME OF DOCTRINAL PRECISION AND remaining portion of the lot. In 1997, respondent filed a complaint for
SUBSTANTIAL JUSTICE.6 recovery of possession with damages against the storeowners wherein
ATO intervened claiming that the storeowners were its lessees.

Citing the views of Justices Presbitero J. Velasco, Jr. and Marvic Mario
Victor F. Leonen in their Dissenting and Concurring Opinion and Separate
ProvRem Rule 67 Fulltext Page 106 of 119
These cases stemmed from similar background, that is, government took We recognized in Republic v. Court of Appeals the need for prompt
control and possession of the subject properties for public use without payment and the necessity of the payment of interest to compensate for
initiating expropriation proceedings and without payment of just any delay in the payment of compensation for property already taken. We
compensation; while the landowners failed for a long period of time to ruled in this case that:
question such government act and later instituted actions for recovery of
possession with damages. In these cases, the Court has uniformly ruled The constitutional limitation of "just compensation" is considered to be
that the fair market value of the property at the time of taking is the sum equivalent to the market value of the property, broadly described
controlling for purposes of computing just compensation. to be the price fixed by the seller in open market in the usual and ordinary
course of legal action and competition or the fair value of the property as
In Forfom, the payment of just compensation was reckoned from the time between one who receives, and one who desires to sell, i[f] fixed at the
of taking in 1973; in Eusebio, the Court fixed the just compensation by time of the actual taking by the government. Thus, if property is taken
determining the value of the property at the time of taking in 1980; for public use before compensation is deposited with the court having
in MIAA, the value of the lot at the time of taking in 1972 served as basis jurisdiction over the case, the final compensation must include
for the award of compensation to the owner; and, in Republic,the Court interest[s] on its just value to be computed from the time the property
was convinced that the taking occurred in 1956 and was thus the basis in is taken to the time when compensation is actually paid or deposited
fixing just compensation. with the court. In fine, between the taking of the property and the
actual payment, legal interest[s] accrue in order to place the owner in
As in the aforementioned cases, just compensation due respondents- a position as good as (but not better than) the position he was in
movants in this case should, therefore, be fixed not as of the time of before the taking occurred.[Emphasis supplied]20
payment but at the time of taking in 1940 which is Seventy Centavos
(P0.70) per square meter, and not One Thousand Five Hundred Pesos In other words, the just compensation due to the landowners amounts to
(₱1,500.00) per square meter, as valued by the RTC and CA. an effective forbearance on the part of the State-a proper subject of
interest computed from the time the property was taken until the full
While disparity in the above amounts is obvious and may appear amount of just compensation is paid-in order to eradicate the issue of the
inequitable to respondents-movants as they would be receiving such constant variability of the value of the currency over time.21 In the Court's
outdated valuation after a very long period, it should be noted that the own words:
purpose of just compensation is not to reward the owner for the property
taken but to compensate him for the loss thereof. As such, the true The Bulacan trial court, in its 1979 decision, was correct in imposing
measure of the property, as upheld by a plethora of cases, is the market interests on the zonal value of the property to be computed from the
value at the time of the taking, when the loss resulted. This principle was time petitioner instituted condemnation proceedings and "took" the
plainly laid down in Apo Fruits Corporation and Hijo Plantation, Inc. v. Land property in September 1969. This allowance of interest on the amount
Bank of the Philippines,14 to wit: found to be the value of the property as of the time of the taking
computed, being an effective forbearance, at 12% per annum should
x x x In Land Bank of the Philippines v. Orilla, a valuation case under our help eliminate the issue of the constant fluctuation and inflation of
agrarian reform law, this Court had occasion to state: the value of the currency over time x x x.22

Constitutionally, "just compensation" is the sum equivalent to the market On this score, a review of the history of the pertinent laws, rules and
value of the property, broadly described as the price fixed by the seller in regulations, as well as the issuances of the Central Bank (CB)or Bangko
open market in the usual and ordinary course of legal action and Sentral ng Pilipinas (BSP)is imperative in arriving at the proper amount of
competition, or the fair value of the property as between the one who interest to be awarded herein.
receives and the one who desires to sell, it being fixed at the time of the
actual taking by the government. Just compensation is defined as the On May 1, 1916, Act No. 265523 took effect prescribing an interest rate of
full and fair equivalent of the property taken from its owner by the six percent (6%) or such rate as may be prescribed by the Central Bank
expropriator. It has been repeatedly stressed by this Court that the Monetary Board (CB-MB)for loans or forbearance of money, in the
true measure is not the taker's gain but the owner's loss. The word absence of express stipulation as to such rate of interest, to wit:
"just" is used to modify the meaning of the word "compensation" to
convey the idea that the equivalent to be given for the property to be Section 1. The rate of interest for the loan or forbearance of any money
taken shall be real, substantial, full and ample. [Emphasis supplied.]15 goods, or credits and the rate allowed in judgments, in the absence of
express contract as to such rate of interest, shall be six per centum per
Indeed, the State is not obliged to pay premium to the property owner for annum or such rate as may be prescribed by the Monetary Board of
appropriating the latter's property; it is only bound to make good the loss the Central Bank of the Philippines for that purpose in accordance
sustained by the landowner, with due consideration of the circumstances with the authority hereby granted.
availing at the time the property was taken. More, the concept of just
compensation does not imply fairness to the property owner alone. Sec. 1-a. The Monetary Board is hereby authorized to prescribe the
Compensation must also be just to the public, which ultimately bears the maximum rate or rates of interest for the loan or renewal thereof or the
cost of expropriation.16 forbearance of any money, goods or credits, and to change such rate or
rates whenever warranted by prevailing economic and social conditions.
Notwithstanding the foregoing, we recognize that the owner's loss is not
only his property but also its income-generating potential.17 Thus, when In the exercise of the authority herein granted, the Monetary Board may
property is taken, full compensation of its value must immediately be paid prescribe higher maximum rates for loans of low priority, such as
to achieve a fair exchange for the property and the potential income consumer loans or renewals thereof as well as such loans made by
lost.18 Accordingly, in Apo, we held that the rationale for imposing the pawnshops finance companies and other similar credit institutions
interest is to compensate the petitioners for the income they would have although the rates prescribed for these institutions need not necessarily
made had they been properly compensated for their properties at the be uniform. The Monetary Board is also authorized to prescribe different
time of the taking.19 Thus: maximum rate or rates for different types of borrowings, including
deposits and deposit substitutes, or loans of financial intermediaries.24

ProvRem Rule 67 Fulltext Page 107 of 119


Under the aforesaid law, any amount of interest paid or stipulated to be It is important to note, however, that interest shall be compounded at the
paid in excess of that fixed by law is considered usurious, therefore time judicial demand is made pursuant to Article 221230 of the Civil Code
unlawful.25 of the Philippines, and sustained in Eastern Shipping Lines v. Court of
Appeals,31then later on in Nacar v. Gallery Frames,32 save for the reduction
On July 29, 1974, the CB-MB, pursuant to the authority granted to it under of interest rate to 6% for loans or forbearance of money, thus:
the aforequoted provision, issued Resolution No. 1622.1âwphi1 On even
date, Circular No. 416 was issued, implementing MB Resolution No. 1622, 1. When the obligation is breached, and it consists in the
increasing the rate of interest for loans and forbearance of money to payment of a sum of money, i.e., a loan or forbearance of
twelve percent (12%) per annum, thus: money, the interest due should be that which may have been
stipulated in writing. Furthermore, the interest due shall itself
By virtue of the authority granted to it under Section 1 of Act No. 2655, as earn legal interest from the time it is judicially
amended, otherwise known as the "Usury Law," the Monetary Board, in its demanded. In the absence of stipulation, the rate of interest
Resolution No. 1622 dated July 29, 1974, has prescribed that the rate of shall be 6% per annum to be computed from default, i.e., from
interest for the loan or forbearance of any money, goods or credits judicial or extrajudicial demand under and subject to the
and the rate allowed in judgments, in the absence of express contract provisions of Article 1169 of the Civil Code.33
as to such rate of interest, shall be twelve per cent (12%) per
annum.26 Applying the foregoing law and jurisprudence, respondents-movants are
entitled to interest in the amount of One Million Seven Hundred
The foregoing rate was sustained in CB Circular No. 90527 which took Eighteen Thousand Eight Hundred Forty-Eight Pesos and Thirty-Two
effect on December 22, 1982, particularly Section 2 thereof, which states: Centavos (₱1,718,848.32) as of September 30, 2014,34 computed as
follows:

Sec. 2. The rate of interest for the loan or forbearance of any money,
goods or credits and the rate allowed in judgments, in the absence of January 1, 194035 to July 28, 1974 P
express contract as to such rate of interest, shall continue to be twelve 10,553.4937
per cent (12%) per annum.28
July 29, 1974 to March 16, 1995 26,126.3138
Recently, the BSP Monetary Board (BSP-MB),in its Resolution No. 796
March 17, 199536to June 30, 2013 232,070.3339
dated May 16, 2013, approved the amendment of Section 2 of Circular
No. 905, Series of 1982, and accordingly, issued Circular No. 799, Series of
July 1, 2013 to September 30, 2014 250,098.1940
2013, effective July 1, 2013, the pertinent portion of which reads:

The Monetary Board, in its Resolution No. 796 dated 16 May 2013, Market Value of the Property at the time of
approved the following revisions governing the rate of interest in the taking including interest P 518,848.32
absence of stipulation in loan contracts, thereby amending Section 2 of
Circular No. 905, Series of 1982:
Market value of the property at the time of
taking including interest P 518,848.32
Section 1. The rate of interest for the loan or forbearance of any
money, goods or credits and the rate allowed in judgments, in the
Add: Exemplary damages 1,000.000.00
absence of an express contract as to such rate of interest, shall be six
percent (6%) per annum. Attorney's fees 200,000.00

Section 2. In view of the above, Subsection X305.1 of the Manual of Total Amount of Interest due to
Regulations for Banks and Sections 4305Q.1, 4305S.3 and 4303P.1 of the Respondents-
Manual of Regulations for Non-Bank Financial Institutions are hereby Movants as of September 30, 2014 ₱1,718,848.16
amended accordingly.

This Circular shall take effect on 01 July 2013.29


Considering that respondents-movants only resorted to judicial demand
for the payment of the fair market value of the land on March 17, 1995, it
Accordingly, the prevailing interest rate for loans and forbearance of is only then that the interest earned shall itself earn interest.
money is six percent (6%) per annum, in the absence of an express
contract as to such rate of interest.
Lastly, from finality of the Court's Resolution on reconsideration until full
payment, the total amount due to respondents-movants shall earn a
In summary, the interest rates applicable to loans and forbearance of straight six percent (6%) legal interest, pursuant to Circular No. 799 and
money, in the absence of an express contract as to such rate of interest, the case of Nacar. Such interest is imposed by reason of the Court's
for the period of 1940 to present are as follows: decision and takes the nature of a judicial debt.

Law, Rule and Regulations, Date of Effectivity Interest Rate Clearly, the award of interest on the value of the land at the time of taking
BSP Issuance in 1940 until full payment is adequate compensation to respondents-
movants for the deprivation of their property without the benefit of
Act No. 2655 May 1, 1916 6% expropriation proceedings. Such interest, however meager or enormous it
may be, cannot be inequitable and unconscionable because it resulted
CB Circular No. 416 July 29, 1974 12% directly from the application of law and jurisprudence-standards that have
CB Circular No. 905 December 22, 1982 12% taken into account fairness and equity insetting the interest rates due for
the use or forbearance of money.41 Thus, adding the interest computed to
CB Circular No. 799 July 1, 2013 6% the market value of the property at the time of taking signifies the real,

ProvRem Rule 67 Fulltext Page 108 of 119


substantial, full and ample value of the property. Verily, the same The Court will not award attorney's fees in light of respondent's choice
constitutes due compliance with the constitutional mandate on eminent not to appeal the CA Decision striking down the award. However, we find
domain and serves as a basic measure of fairness. In addition to the it proper to award temperate and exemplary damages in light of
foregoing interest, additional compensation shall be awarded to NIA's misuse of its power of eminent domain. Any arm of the State that
respondents-movants by way of exemplary damages and attorney's fees exercises the delegated power of eminent domain must wield that power
in view of the government's taking without the benefit of expropriation with circumspection and utmost regard for procedural requirements. A
proceedings. As held in Eusebio v. Luis,42 an irregularity in an government instrumentality that fails to observe the constitutional
expropriation proceeding cannot ensue without consequence. Thus, the guarantees of just compensation and due process abuses the authority
Court held that the government agency's illegal occupation of the owner's delegated to it, and is liable to the property owner for damages.
property for a very long period of time surely resulted in pecuniary loss to
the owner, to wit: Temperate or moderate damages may be recovered if pecuniary loss has
been suffered but the amount cannot be proved with certainty from the
However, in taking respondents' property without the benefit of nature of the case.1âwphi1 Here, the trial and appellate courts found that
expropriation proceedings and without payment of just compensation, the owners were unable to plant palay on 96,655 square meters of the
the City of Pasig clearly acted in utter disregard of respondents' Property for an unspecified period during and after NIA's construction of
proprietary rights. Such conduct cannot be countenanced by the the canals in 1972. The passage of time, however, has made it impossible
Court. For said illegal taking, the City of Pasig should definitely be to determine these losses with any certainty. NIA also deprived the
held liable for damages to respondents. Again, in Manila International owners of the Property of possession of a substantial portion of their land
Airport Authority v. Rodriguez, the Court held that the government since 1972. Considering the particular circumstances of this case, an
agency's illegal occupation of the owner's property for a very long period award of ₱150,000 as temperate damages is reasonable.
of time surely resulted in pecuniary loss to the owner. The Court held as
follows: NIA's irresponsible exercise of its eminent domain powers also deserves
censure. For more than three decades, NIA has been charging irrigation
Such pecuniary loss entitles him to adequate compensation in the fees from respondent and other landowners for the use of the canals built
form of actual or compensatory damages, which in this case should on the Property, without reimbursing respondent a single cent for the loss
be the legal interest (6%) on the value of the land at the time of and damage. NIA exhibits a disturbingly cavalier attitude towards
taking, from said point up to full payment by the MIAA. This is based respondent's property rights, rights to due process of law and to equal
on the principle that interest "runs as a matter of law and follows from the protection of the laws. Worse, this is not the first time NIA has
right of the landowner to be placed in as good position as money can disregarded the rights of private property owners by refusing to pay just
accomplish, as of the date of the taking." compensation promptly. To dissuade NIA from continuing this practice
and to set an example for other agencies exercising eminent domain
The award of interest renders unwarranted the grant of back powers, NIA is directed to pay respondent exemplary damages of
rentals as extended by the courts below. In Republic v. Lara, et al., the ₱250,000.45
Court ruled that the indemnity for rentals is inconsistent with a property
owner's right to be paid legal interest on the value of the property, for if Applying the aforequoted doctrines to the present case, considering that
the condemn or is to pay the compensation due to the owners from the respondents-movants were deprived of beneficial ownership over their
time of the actual taking of their property, the payment of such property for more than seventy (70) years without the benefit of a timely
compensation is deemed to retro act to the actual taking of the property; expropriation proceedings, and to serve as a deterrent to the State from
and, hence, there is no basis for claiming rentals from the time of actual failing to institute such proceedings within the prescribed period under
taking. More explicitly, the Court held in Republic v. Garcellano that: the law, a grant of exemplary damages in the amount of One Million
Pesos (₱1,000,000.00) is fair and reasonable. Moreover, an award for
The uniform rule of this Court, however, is that this compensation attorney's fees in the amount of Two Hundred Thousand Pesos
must be, not in the form of rentals, but by way of 'interest from the (₱200,000.00) in favor of respondents-movants is in order.
date that the company [or entity] exercising the right of eminent
domain take possession of the condemned lands, and the amounts In sum, respondents-movants shall be entitled to an aggregate amount
granted by the court shall cease to earn interest only from the of One Million Seven Hundred Eighteen Thousand Eight Hundred
moment they are paid to the owners or deposited in court x x x. Forty-Eight Pesos and Thirty-Two Centavos (₱1,718,848.32) as just
compensation as of September 30, 2014, computed as follows:
xxxx
Market value of the property at the time P 518,848.32
For more than twenty (20) years, the MIAA occupied the subject lot of taking in 1940 including interest
without the benefit of expropriation proceedings and without the MIAA
exerting efforts to ascertain ownership of the lot and negotiating with any Add: Exemplary Damages 1,000,000.00
of the owners of the property. To our mind, these are wanton and
irresponsible acts which should be suppressed and corrected. Attorney's fees 200,000.00
Hence, the award of exemplary damages and attorneys fees is in
order. However, while Rodriguez is entitled to such exemplary damages Total Amount due to Respondents-
and attorney's fees, the award granted by the courts below should be movants as of September 30, 2014 ₱1,718,848.32
equitably reduced. We hold that Rodriguez is entitled only to ₱200,000.00
as exemplary damages, and attorney's fees equivalent to one percent (1%)
This Court is not unaware that at present, stringent laws and rules are put
of the amount due.43
in place to ensure that owners of real property acquired for national
government infrastructure projects are promptly paid just compensation.
Similarly, in Republic v. CA,44 We held that the failure of the government Specifically, Section 4 of Republic Act No. 8974 (R.A. 8974),46 which took
to initiate an expropriation proceeding to the prejudice of the landowner effect on November 26, 2000, provides sufficient guidelines for
may be corrected with the awarding of exemplary damages, attorney's implementing an expropriation proceeding, to wit:
fees and costs of litigation. Thus:

ProvRem Rule 67 Fulltext Page 109 of 119


Section 4. Guidelines for Expropriation Proceedings. - Whenever it is Despite the foregoing developments, however, We emphasize that the
necessary to acquire real property for the right-of-way or location for any government's failure, to initiate the necessary expropriation proceedings
national government infrastructure project through expropriation, the prior to actual taking cannot simply invalidate the State's exercise of its
appropriate implementing agency shall initiate the expropriation eminent domain power, given that the property subject of expropriation is
proceedings before the proper court under the following guidelines: indubitably devoted for public use, and public policy imposes upon the
public utility the obligation to continue its services to the public. To
(a) Upon the filing of the complaint, and after due notice to the hastily nullify said expropriation in the guise of lack of due process would
defendant, the implementing agency shall immediately pay the certainly diminish or weaken one of the State's inherent powers, the
owner of the property the amount equivalent to the sum of (1) ultimate objective of which is to serve the greater good. Thus, the non-
one hundred percent (100%) of the value of the property based filing of the case for expropriation will not necessarily lead to the return of
on the current relevant zonal valuation of the Bureau of Internal the property to the landowner. What is left to the landowner is the right
Revenue (BIR); and (2) the value of the improvements and/or of compensation.48
structures as determined under Section 7 hereof;
All told, We hold that putting to rest the issue on the validity of the
(b) In provinces, cities, municipalities and other areas where exercise of eminent domain is neither tantamount to condoning the acts
there is no zonal valuation, the BIR is hereby mandated within of the DPWH in disregarding the property rights of respondents-movants
the period of sixty (60) days from the date of the expropriation nor giving premium to the government's failure to institute an
case, to come up with a zonal valuation for said area; and expropriation proceeding. This Court had steadfastly adhered to the
doctrine that its first and fundamental duty is the application of the law
according to its express terms, interpretation being called for only when
(c) In case the completion of a government infrastructure such literal application is impossible.49 To entertain other formula for
project is of utmost urgency and importance, and there is no computing just compensation, contrary to those established by law and
existing valuation of the area concerned, the implementing jurisprudence, would open varying interpretation of economic policies - a
agency shall immediately pay the owner of the property its matter which this Court has no competence to take cognizance of. Time
proffered value taking into consideration the standards and again, we have held that no process of interpretation or construction
prescribed in Section 5 hereof. need be resorted to where a provision of law peremptorily calls for
application.50 Equity and equitable principles only come into full play
Upon compliance with the guidelines abovementioned, the court shall when a gap exists in the law and jurisprudence.51 As we have shown
immediately issue to the implementing agency an order to take above, established rulings of this Court are in place for full application to
possession of the property and start the implementation of the project. the case at bar, hence, should be upheld.

Before the court can issue a Writ of Possession, the implementing agency WHEREFORE, the motion for reconsideration is hereby DENIED for lack of
shall present to the court a certificate of availability of funds from the merit.
proper official concerned.
SO ORDERED.
In the event that the owner of the property contests the implementing
agency's proffered value, the court shall determine the just compensation #15 G.R. No. 223366 August 1, 2017
to be paid the owner within sixty (60) days from the date of filing of the
expropriation case. When the decision of the court becomes final and
executory, the implementing agency shall pay the owner the difference NATIONAL TRANSMISSION CORPORATION, Petitioner,
between the amount already paid and the just compensation as vs.
determined by the court. OROVILLE DEVELOPMENT CORPORATION, Respondent

Failure to comply with the foregoing directives shall subject the MENDOZA, J.:
government official or employee concerned to administrative, civil and/or
criminal sanctions, thus: This is a petition for review on certiorari seeking to reverse and set aside
the September 18, 2015 Decision1 and January 25, 2016 Resolution2 of the
Section 11. Sanctions. - Violation of any provisions of this Act shall subject Court of Appeals (CA) in CA-G.R. CV No. 03571, which affirmed with
the government official or employee concerned to appropriate modification the December 12, 2012 Decision3 of the Regional Trial Court,
administrative, civil and/or criminal sanctions, including suspension Branch 17, Misamis Oriental (RTC) in Civil Case No. 2007-85, a case for
and/or dismissal from the government service and forfeiture of benefits. expropriation.
While the foregoing provisions, being substantive in nature or disturbs
substantive rights, cannot be retroactively applied to the present case, We The Antecedents
trust that this established mechanism will surely deter hasty acquisition of
private properties in the future without the benefit of immediate payment The present case involves two (2) parcels of land located in Puerto,
of the value of the property in accordance with Section 4 of R.A. 8974. Cagayan de Oro City, which originally belonged to Alfredo Reyes (Reyes)
This effectively addresses J. Velasco's concerns that sustaining our earlier and Grace Calingasan (Calingasan), covered by Original Certificate of Title
rulings on the matter would be licensing the government to dispense with (OCT) No. P-3 and OCT No. P-13, respectively.
constitutional requirements in taking private properties. Moreover, any
gap on the procedural aspect of the expropriation proceedings will be
remedied by the aforequoted provisions. In 1983, petitioner National Transmission Corporation (TransCo)
constructed a power transmission line on these properties, known as the
Tagoloan-Pulangi 138 kV transmission line.
In effect, R.A. 8974 enshrines a new approach towards eminent domain
that reconciles the inherent unease attending expropriation proceedings
with a position of fundamental equity.47 At some point, Reyes sold his land to Antonio Navarette, who later sold
the same property to respondent Oroville Development Corporation
(Oroville), which is now covered by Transfer Certificate of Title (TCT) No. T-
85121. Likewise, Calingasan sold her land to Oroville, now registered
ProvRem Rule 67 Fulltext Page 110 of 119
under TCT No. T-104365. Thus, in 1995, Oroville became the registered Valuation of the Property: ₱78.65 per square meter or a total of
owner of these properties with a total area of 13 ,904 square meters ₱5,924,772.48 inclusive of interests4
traversed by the existing Tagoloan-Pulangi 138 kV transmission line.
2. Engr. Norberto Badelles (engaged by Transco)
On November 17, 2006, Transco offered to buy these properties from
Oroville to be used for the construction of the Abaga-Kirahon 230 kV
transmission line in Mindanao. Date of 1983 per Transmission Line Data and
Taking: Information
(Tagoloan-Pulangi 138 kV Transmission
During the negotiation, Oroville, through its representative Antonio Tiu
Line)
(Tiu), requested to reroute the Abaga-Kirahon 230 kV transmission line
because the Tagoloan-Pulangi 138 kV transmission line is already
traversing its properties. Tiu also informed Transco that Oroville has not Valuation of the Property: ₱1.20 per square meter or a total of
been paid just compensation for the constn1ction of the Tagoloan- ₱45,716.35 inclusive of interests5
Pulangi 138 kV transmission line in its property. Transco, however, refused
to reroute the proposed Abaga-Kirahon 230 kV transmission line because
3. Atty. Avelino Pakino (nominated by Oroville)
it planned to construct the said transmission line parallel to the existing
Tagoloan-Pulangi 138 kV transmission line.
Date of 1983 per Transmission Line Data and
Consequently, on April 20, 2007, Oroville filed a complaint for injunction Taking: Information
and damages with prayer for issuance of a temporary restraining order (Tagoloan-Pulangi 138 kV Transmission
against Transco, seeking to enjoin the construction of the Abaga-Kirahon Line)
230 kV transmission line.

Valuation of the Property: ₱2,000.00 per square meter or a total


On May 9, 2007, Transco filed its Answer denying the allegations in
of ₱27,808,000.00 inclusive of interests6
Oroville's complaint. It also manifested that it would file the required
expropriation proceedings against Oroville in order to acquire the latter's
properties for the Abaga-Kirahon 230 kV transmission line project. The RTC Ruling

During trial, the parties agreed to have the subject properties surveyed for In its Decision, dated December 12, 2012, the RTC set aside the
purposes of fixing the just compensation. As a result, the trial court Commissioners' report and fixed the just compensation at the rate of
suspended the proceedings and directed Transco to conduct a survey of ₱1,520.00 per square meter with legal interest of 12%
the properties. per annum reckoned from April 20, 2007, the date of filing of the
complaint. It held that the said amount was based on the fair market
value of lots along the national highway of Barangay Puerto, Cagayan de
Subsequently, Oroville filed an omnibus motion to convert the
Oro City in accordance with the schedule of values under City Ordinance
proceedings into an expropriation case and to require Transco to pay the
No. 10425-2006 otherwise known as An Ordinance Prescribing the
Bureau of Internal Revenue (BIR) the zonal value of the subject properties.
Revised Schedule of Fair Market Values of Real Property in Cagayan de
Transco made no objections to the motion.
Oro and in accordance with the BIR Comparative Value of Zonal Fair
Market Values. The RTC opined that the just compensation should not be
On May 17, 2010, the trial court directed Transco to make a provisional reckoned from 1983, the time of taking, because it was established by the
deposit of ₱7,647,200.00 as just compensation for Oroville's properties landowners that entry into their property was without their knowledge.
consisting of 13,904 square meters and affected by the existing Tagoloan- The falloreads:
Pulangi 138 kV transmission line. Transco complied after the trial court
denied its objections.
WHEREFORE, in view of the foregoing premises, judgment is hereby
rendered as follows:
On February 4, 2011, the trial court directed the Land Bank of the
Philippines, NAPOCOR Branch, to release the aforesaid deposit to Tiu.
1) FIXING the just compensation of the affected area of 13,904
square meters at ₱1,520.oo per square meter reckoned from
On March 21, 2011, the trial court issued a writ of possession directing April 20, 2007, the date the complaint was filed, at interest rate
Oroville to surrender possession of the properties to Transco. of 12% per annum until the liability is fully paid

Subsequently, on August 8, 2011, per nomination of the parties, the trial 2) ORDERING defendant TRANSCO to pay plaintiff the just
court appointed three (3) Commissioners, namely, Engr. Marilyn P. compensation in the amount of ₱1,520.00 per square meter for
Legaspi, Engr. Norberto Badelles and Atty. Avelino Pakino, to determine the 13,904 square meters the affected area at the rate of
the just compensation of the properties affected by the Abaga-Kirahon 12% per annum reckoned from April 20, 2007, the data of filing
230 kV transmission line. the complaint minus the amount of ₱7,647,200.oo representing
the amount paid by TRANSCO as provisional payments
A summary of the Commissioners' report reads as follows:
3) ORDERING defendant TRANSCO to pay plaintiff the interest
1. Engr. Marilyn Legaspi (Court-appointed Commissioner) of 12% per annum based on the deficiency amount;

4) ORDERING Plaintiff and Defendant to pay the


Date of 1983 per Transmission Line Data and
Commissioners' fee in the amount of ₱10,000.00 each within 15
Taking: Information
days from receipt of this Order.
(Tagoloan-Pulangi 138 kV Transmission
Line)

ProvRem Rule 67 Fulltext Page 111 of 119


The Court will leave to the parties the correct mathematical computation should not be allowed to benefit from its failure to question such
as to what is due to plaintiff based on the foregoing premises. construction more than a decade after its completion; and that it should
not be made to pay 12% interest per annum in the nature of damages for
SO ORDERED.7 delay as it complied with the RTC's directive to make provisional deposit
for the subject property.

Aggrieved, Transco elevated an appeal before the CA.


In its Comment,10 dated August 5, 2016, Oroville averred that to sustain
the argument of Transco that the basis of the payment for just
The CA Ruling compensation is the value of the property at the time of taking would sow
immeasurable injustice; that the P78.65 per square meter valuation as
In its assailed Decision, dated September 18, 2015, the CA ruled that recommended by Commissioner Legaspi and the ₱1.20 per square meter
TransCo's entry into Oroville's lots in 1983 was made without warrant or recommended by Commissioner Badelles would not be enough to
color of authority because at the time Transco constructed the Tagoloan- reimburse Oroville for the realty taxes it paid from the year 1983 up to the
Pulangi 138 kV transmission line over the disputed properties in 1983, it present; that while it paid these annual taxes, Transco had been earning
was made without intent to expropriate. It added that Transco billions of pesos from transmission charges; that as held in Napocor v.
constructed the transmission line without bothering to negotiate with the Campos, Jr., there were instances when Transco removed transmission
owner to purchase or expropriate the disputed lots. lines from the affected properties due to diversion of its lines, thus, upon
entry, Transco did not have intent to expropriate the property because
Further, the CA adjudged that the construction of the Tagoloan-Pulangi there might be a change of plans; that Transco would initiate
138 kV transmission line did not oust or deprive Oroville or its previous expropriation proceedings only when it was certain of its transmission
owners of the beneficial enjoyment of their properties as they continued plans; that the earlier entry into and/or possession of Transco of the
to possess the same. It observed that the previous owners were able to subject properties was patently without any color of legal authority as it
sell the properties to Oroville; and that after acquiring them, Oroville did not have the slightest intention to acquire ownership of the subject
considered developing the lots for residential subdivision purposes, but properties either by voluntary purchase or by exercise of eminent domain;
the subject properties were later on classified as agricultural lands and that the delay in the payment of just compensation justified the
covered by the Comprehensive Agrarian Reform Program (CARP) of the payment of 12% interest per annum.
government.
In its Reply,11 dated November 25, 2016, Transco contended that this case
The CA concluded that there was no actual taking of the subject is not an exception to the settled rule that just compensation should be
properties in 1983 when Transco constructed the Tagoloan-Pulangi 138 based on the property's value at the time of its taking; that the value and
kV transmission line.1âwphi1 Accordingly, the computation of the just classification of the subject property at the time of its taking in 1983
compensation should be reckoned at the time of the filing of the should be the basis for the computation of just compensation; that it
complaint in 2007. The dispositive portion reads: informed Oroville of the construction of the new transmission line over its
properties and readily agreed to the conversion of its complaint for
injunctive relief into an expropriation case; and that the landowner should
WHEREFORE, the Judgment dated 12 December 2012 of the Regional
also bear the cost of being remiss in guarding against the effects of a
Trial Court, (Branch 17), 10th Judicial Region, Cagayan de Oro City, is
belated claim.
MODIFIED. Appellant National Transmission Corporation is hereby
ORDERED to pay appellee Oroville Corporation the unpaid balance of the
just compensation in the sum of P13,486,880.oo with legal interest of The Court's Ruling
TWELVE PERCENT (12%) per annum computed from 21 March 2011 to 30
June 2013 and SIX PERCENT (6%) per annum from 1 July 2013 until its full The petition is meritorious.
payment. Both parties are DIRECTED to pay the Commissioners' fee in the
amount of ₱10,000.00 each within 15 days from notice. Eminent domain is the right or power of a sovereign state to appropriate
private property to particular uses to promote public welfare. It is an
SO ORDERED.8 indispensable attribute of sovereignty; a power grounded in the primary
duty of government to serve the common need and advance the general
Transco moved for reconsideration, but the same was denied by the CA in welfare.12 The power of eminent domain is inseparable in sovereignty
its assailed Resolution, dated January 25, 2016. being essential to the existence of the State and inherent in government.
But the exercise of such right is not unlimited, for two mandatory
requirements should underlie the Government's exercise of the power of
Hence, this petition.
eminent domain, namely: (1) that it is for a particular public purpose; and
(2) that just compensation be paid to the property owner.13 These
ISSUES requirements partake the nature of implied conditions that should be
complied with to enable the condemnor to keep the property
WHETHER THE COMPUTATION OF JUST COMPENSATION FOR THE expropriated.14
EXPROPRIATED PROPERTY SHOULD BE BASED ON ITS VALUE AT THE
TIME OF THE TAKING OF THE PROPERTY Taking of Oroville's property
occurred in 1983 upon construction of
WHETHER THE IMPOSITION OF A LEGAL INTEREST OF 12% IS the transmission lines
UNJUSTIFIED9
The landmark case of Republic v. Vda. De Castellvi15 provides an
Petitioner argues that Section 4, Rule 67 of the Rules of Court and enlightening discourse on the requisites of taking.
applicable jurisprudence are explicit in saying that just compensation for
expropriated property shall be determined based on its fair market value First, The expropriator must enter a private property; Second, the entrance
at the time of its taking; that Oroville could not claim lack of knowledge into private property must be for more than a momentary period; Third,
to the construction of the transmission line since it is in plain view, the entry into the property should be under warrant or color of legal
considering its height and the huge space that it occupied; that Oroville
ProvRem Rule 67 Fulltext Page 112 of 119
authority; Fourth, the property must be devoted to a public use or without the appropriate expropriation proceedings. In 1994, respondent
otherwise informally appropriated or injuriously affected; and Fifth, the demanded payment of the value of the property, but they could not
utilization of the property for public use must be in such a way as to oust agree on its valuation prompting respondent to file a complaint for
the owner and deprive him of all beneficial enjoyment of the property.16 reconveyance and/ or damages against the city government and the
mayor. In Manila International Airport Authority v. Rodriguez, in the early
The Court rules that there is taking of the property for purposes of 1970s, petitioner implemented expansion programs for its runway
eminent domain in 1983. necessitating the acquisition and occupation of some of the properties
surrounding its premises. AB to respondent's property, no expropriation
proceedings were initiated. In 1997, respondent demanded the payment
The first and fourth requisites are present in this case. Transco took of the value of the property, but the demand remained unheeded
possession of Oroville's property in order to construct transmission lines prompting him to institute a case for accion reivindicatoria with damages
to be used in generating electricity for the benefit of the public. against petitioner. In Republic v. Sarabia, sometime in 1956, the Air
Transportation Office (ATO) took possession and control of a portion of a
The second requisite is likewise present as there can be no question that lot situated in Aldan, registered in the name of respondent, without
the construction of transmission lines meant an indefinite stay in the initiating expropriation proceedings. Several structures were erected
property of Oroville. Further, Trans Co's exercise of eminent domain is thereon including the control tower, the Kalibo crash fire rescue station,
pursuant to its authority granted under Section 8 of Republic Act (R.A.) the Kalibo airport terminal and the headquarters of the PNP Aviation
No. 9136 or the Electric Power Industry Reform Act of 2001.17 Security Group. In 1995, several stores and restaurants were constructed
on the remaining portion of the lot. In 1997, respondent filed a complaint
Finally, Oroville has been deprived of the beneficial enjoyment of its for recovery of possession with damages against the storeowners where
property. In several rulings, notably National Power Corporation v. Spouses ATO intervened claiming that the storeowners were its lessees.
Zabala,18 Republic v. Spouses Libunao,19 and National Power Corporation v.
Tuazon20 this Court has already declared that "since the high-tension The Court in the above-mentioned cases was confronted with
electric current passing through the transmission lines will perpetually common factual circumstances where the government took control
deprive the property owners of the nonnal use of their land, it is only just and possession of the subject properties for public use without
and proper to require Napocor to recompense them for the full market initiating expropriation proceedings and without payment of just
value of their property." compensation, while the landowners failed for a long period of time to
question such government act and later instituted actions for recovery of
Just compensation reckoned from the possession with damages. The Court thus determined the landowners'
date of actual taking right to the payment of just compensation and, more importantly, the
amount of just compensation. The Court has uniformly ruled that just
compensation is the value of the property at the time of taking that
The next question to be resolved is whether just compensation should be
is controlling for purposes of compensation. In Forlorn, the payment of
reckoned from 1983 when the taking took place.
just compensation was reckoned from the time of taking in 1973; in
Eusebio, the Court fixed the just compensation by determining the value
Just compensation is defined as the full and fair equivalent of the of the property at the time of taking in 1980; in MIAA, the value of the lot
property taken from its owner by the expropriator. The measure is not the at the time of taking in 1972 served as basis for the award of
taker's gain, but the owner's loss. The word "just" is used to intensify the compensation to the owner; and in Republic, the Court was convinced
meaning of the word "compensation" and to convey thereby the idea that that the taking occurred in 1956 and was thus the basis in fixing just
the equivalent to be rendered for the property to be taken shall be real, compensation.23 [Citations omitted and emphases supplied]
substantial, full, and ample.21
As further pointed out in Republic v. Lara, et al.,24 thus:
In addition, Section 4, Rule 67 of the Rules of Court provides:
x x x "The value of the property should be fixed as of the date when it was
Section 4. Order of expropriation. - If the objections to and the defenses taken and not the date of the filing of the proceedings." For where
against the right of the plaintiff to expropriate the property are overruled, property is taken ahead of the filing of the condemnation proceedings,
or when no party appears to defend as required by this Rule, the court the value thereof may be enhanced by the public purpose for which it is
may issue an order of expropriation declaring that the plaintiff has a taken; the entry by the plaintiff upon the property may have depreciated
lawful right to take the property sought to be expropriated, for the public its value thereby; or, there may have been a natural increase in the value
use or purpose described in the complaint, upon the payment of just of the property from the time it is taken to the time the complaint is filed,
compensation to be determined as of the date of the taking of the due to general economic conditions. The owner of private property
property or the filing of the complaint, whichever came first. should be compensated only for what he actually loses; it is not intended
xxxx[Emphasis supplied] that his compensation shall extend beyond his loss or injury. And what he
loses is only the actual value of his property at the time it is taken x x x.25
The case of Secretary of the Department of Public Works and Highways v.
Spouses Tecson (Tecson)22 provides a discussion of cases wherein the Indeed, the State is only obliged to make good the loss sustained by the
Court conformed to the abovementioned rule and held that payment of landowner, with due consideration of the circumstances availing at the
just compensation should be reckoned from the date of taking when such time the property was taken. The concept of just compensation does not
preceded the filing of the complaint for expropriation, to wit: imply fairness to the property owner alone. Compensation must also be
just to the public, which ultimately bears the cost of expropriation.26
In Forfom Development Corporation [Forlorn] v. Philippine National
Railways [PNR], PNR entered the property of Forfom in January 1973 for The sequence of events in all of these cited cases as well as in Tecson is
public use, that is, for railroad tracks, facilities and appurtenances for use similar to that obtaining in the case at bench, that is, the government took
of the Carmona Commuter Service without initiating expropriation possession of private properties without initiating expropriation
proceedings. In 1990, Forlorn filed a complaint for recovery of possession proceedings and later on, the property owners demanded either the
of real property and/ or damages against PNR. In Eusebio v. Luis, return of their properties or the payment of just compensation. Thus,
respondent's parcel of land was taken in 1980 by the City of Pasig and pursuant to the Rules of Court and in accordance with prevailing
used as a municipal road now known as A Sandoval Avenue in Pasig City
ProvRem Rule 67 Fulltext Page 113 of 119
jurisprudence, the Court rules that just compensation must be ascertained the property at the time of the filing of the instant Complaint when
as of the year 1983 when Transco commenced construction of the respondent spouses made a judicial demand for just compensation.32
transmission lines. Just compensation is therefore fixed at ₱78.65 per
square meter, which is the fair market value of the property at the time of These rulings, however, are exceptions to the general rule that just
taking. As will be discussed later on, the imposition of interest would compensation must be reckoned from the time of taking or filing of the
adequately compensate the property owner for the delay in the payment complaint, whichever came first. The special circumstances of the
of just compensation considering that more often than not, the amount of aforementioned cases called for the valuation of just compensation at the
interest to be paid is higher than the increase in the property's market time the landowners initiated inverse condemnation proceedings
value. notwithstanding that taking of the properties occurred first.
In Macabangkit Sangkay, NAPOCOR did not even inform the property
The rulings in Macabangkit owners of the construction of the underground tunnels. Hence, it could
Sangkay and Saludares are be said that NAPOCOR employed stealth instead of complying with the
mere exceptions legal process of expropriation. Further, considering that the tunnels were
constructed underground, the property owners came to know thereof
The Court is not unaware of the rulings in National Power Corporation v. only when the purchaser of the property refused to proceed with the sale
Heirs of Macabangkit Sangkay (Macabangkit Sangkay)27 and National upon discovery of the underground tunnels. In this case, however, the
Power Corporation v. Spouses Saludares (Saludares) 28 wherein it was held transmission lines are visible, such that Oroville could not deny
that just compensation should be reckoned from the time the property knowledge of its construction in 1983. In Saludares, NAPOCOR refused to
owners initiated inverse condemnation proceedings notwithstanding that acknowledge the respondents' claim and insisted that it already paid just
the taking of the properties occurred earlier. compensation because the respondents' property was the same one
involved in the Pereyra case. Thus, NAPOCOR had no intention to pay just
compensation. This circumstance does not exist in the case at bench.
In Macabangkit Sangkay, NAPOCOR, in the 1970s, undertook the
construction of several underground tunnels to be used in diverting the
water flow from the Agus River to the hydroelectric plants. On November The rulings in Macabangkit Sangkay and Saludares are more in
21, 1997, respondents therein sued NAPOCOR for recovery of property consonance with the rules of equity than with the Rules of Court,
and damages, alleging that they belatedly discovered that one of the specifically Rule 67 on expropriation. Indeed, the practice of construct
underground tunnels of NPC traversed their land.29 In that case, the Court first, expropriate later is reprehensible and must not be countenanced.
adjudged that the value of the property at the time the property owners The Court, however, must not lose sight of Section 4, Rule 67 which
initiated inverse condemnation proceedings should be considered for mandates that just compensation must be determined "as of the date of
purposes of just compensation for the following reasons, viz: the taking of the property or the filing of the complaint, whichever came
first." This provision is, first and foremost, part of the Rules which the
Court itself promulgated for purposes of uniformity, among others.
Compensation that is reckoned on the market value prevailing at the time
either when NPC entered or when it completed the tunnel, as NPC
submits, would not be just, for it would compound the gross unfairness Further, the doctrine of stare decisis constrains the Court to follow the
already caused to the owners by NPC's entering without the intention of ruling laid down in Tecson and similar cases. "Time and again, the court
formally expropriating the land, and without the prior knowledge and has held that it is a very desirable and necessary judicial practice that
consent of the Heirs of Macabangkit. NPC's entry denied elementary due when a court has laid down a principle of law as applicable to a certain
process of law to the owners since then until the owners commenced the state of facts, it will adhere to that principle and apply it to all future cases
inverse condemnation proceedings. The Court is more concerned with the in which the facts are substantially the same. Stare decisis et non quieta
necessity to prevent NPC from unjustly profiting from its deliberate acts movere. Stand by the decisions and disturb not what is settled. Stare
of denying due process of law to the owners. As a measure of simple decisis simply means that for the sake of certainty, a conclusion reached in
justice and ordinary fairness to them, therefore, reckoning just one case should be applied to those that follow if the facts are
compensation on the value at the time the owners commenced these substantially the same, even though the parties may be different. It
inverse condemnation proceedings is entirely warranted.30 proceeds from the first principle of justice that, absent any powerful
countervailing considerations, like cases ought to be decided alike."33

On the other hand, in Saludares, respondents therein filed a complaint for


the payment of just compensation against NAPOCOR, averring that it had To reiterate, the facts of the instant case are substantially the same
entered and occupied their property by erecting high-tension with Tecson and similar cases cited therein. A government agency took
transmission lines and failed to reasonably compensate them for the possession of private property for the benefit of the public without,
intrusion. For its part, NAPOCOR countered that it had already paid just however, initiating expropriation proceedings, which thus, constrained the
compensation for the establishment of the transmission lines by virtue of landowner to file actions to recover their properties or to demand
its compliance with the final and executory decision in National Power payment of just compensation. Hence, in the absence of any compelling
Corporation v. Pereyras.31 In ruling that the reckoning value of just reason to deviate from the rulings in the aforecited cases, the Court, in
compensation is that prevailing at the time of the filing of the inverse the case at bench, must adhere to the doctrines established therein.
condemnation proceedings, the Court declared:
Amount of interest to be paid
x x x To reiterate, NAPOCOR should have instituted eminent domain
proceedings before it occupied respondent spouses' property. Because it The owner's loss, of course, is not only his property but also its income-
failed to comply with this duty, respondent spouses were constrained to generating potential.34 Thus, when property is taken, full compensation of
file the instant Complaint for just compensation before the trial court. its value must immediately be paid to achieve a fair exchange for the
From the 1970s until the present, they were deprived of just property and the potential income lost.35 Thus, the rationale for imposing
compensation, while NAPOCOR continuously burdened their property the interest is to compensate the landowners for the income they would
with its transmission lines. This Court cannot allow petitioner to profit have made had they been properly compensated for their properties at
from its failure to comply with the mandate of the law. We therefore rule the time of the taking.36
that, to adequately compensate respondent spouses from the decades of
burden on their property, NAPOCOR should be made to pay the value of

ProvRem Rule 67 Fulltext Page 114 of 119


The Court, in Republic v. Court of Appeals,37 further enunciated on the 1983 and 12% interest per annum on the total fair market value,
necessity of the payment of interest to compensate for delay in the computed from 1983 to January 21, 2011, the date when Transco made a
payment of just compensation, viz: provisional deposit in favor of Oroville. Considering that the actual date of
taking cannot be determined from the records of the case, the date of
The constitutional limitation of "just compensation" is considered to be taking is pegged on January 1, 1983. Oroville is also awarded exemplary
the sum equivalent to the market value of the property, broadly described damages in the amount of ₱1,000,000.00 and attorney's fees in the
to be the price fixed by the seller in open market in the usual and ordinary amount of ₱200,000.00.
course of legal action and competition or the fair value of the property as
between one who receives, and one who desires to sell, if fixed at the time On a final note, there are several cases which reached this Court in which
of the actual taking by the government. Thus, if property is taken for Transco and even other government agencies constructed transmission
public use before compensation is deposited with the court having lines, tunnels and other infrastructures before it decided to expropriate
jurisdiction over the case, the final compensation must include interest the private properties upon which they built the same. The Court reminds
[s] on its just value to be computed from the time the property is the government and its agencies that it is their obligation to initiate
taken to the time when compensation is actually paid or deposited eminent domain proceedings whenever they intend to take private
with the court. In fine, between the taking of the property and the property for any public purpose. Before the expropriating power enters a
actual payment, legal interest [s] accrue in order to place the owner private property, it must first file an action for eminent domain43and
in a position as good as (but not better than) the position he was in deposit with the authorized government depositary an amount equivalent
before the taking occurred.38 [Emphasis supplied] to the assessed value of the property.44

Tecson also clarified the amount of interest due the landowners, to wit: Transco should first file an expropriation case before it proceeds to
construct transmission lines or any other infrastructure on any private
x x x In other words, the just compensation due to the landowners property. The practice of construct first, expropriate later must be put to a
amounts to an effective forbearance on the part of the State - a proper stop.
subject of interest computed from the time the property was taken until
the full amount of just compensation is paid - in order to eradicate the WHEREFORE, the petition is GRANTED. The September 18, 2015
issue of the constant variability of the value of the currency over time. Decision and January 25, 2016 Resolution of the Court of Appeals in
CAG.R. CV No. 03571, are REVERSED and SETASIDE. The valuation of the
x x xx subject property owned by respondent Oroville shall be ₱78.65 per square
meter, with interest at twelve percent (12%) per annum from January 1983
until January 21, 2011. Petitioner Transco is also ordered to pay
It is important to note, however, that interest shall be compounded at the respondent Oroville exemplary damages in the amount of ₱1,000,000.00
time judicial demand is made pursuant to Article 2212 of the Civil Code of and attorney's fees in the amount of ₱200,000.00.
the Philippines, and sustained in Eastern Shipping Lines v. Court of
Appeals, then later on in Nacar v. Gallery Frames, save for the reduction of
interest rate to 6% for loans or forbearance of money.39 x x x SO ORDERED.

In the case at bench, Transco made a provisional deposit of ₱7,647,200.00


on January 21, 2011. Consequently, from 1983 to January 21, 2011,
Oroville is entitled to twelve percent (12%) interest per annum which is #16 G.R. No. 220367, November 20, 2017
the prevailing rate during such period pursuant to Central Bank Circular
No. 905,40 effective from December 22, 1982 to June 30, 2013. NATIONAL POWER CORPORATION, Petitioner, v. APOLONIO V.
MARASIGAN, FRANCISCO V. MARASIGAN, LILIA V. MARASIGAN,
Oroville is also awarded additional compensation by way of exemplary BENITO V. MARASIGAN, JR., AND ALICIA V.
damages and attorney's fees. In Republic v. CA,41 the Court held that the MARASIGAN, Respondents.
failure of the government to initiate an expropriation proceeding to the
prejudice of the landowner may be corrected with the awarding of DECISION
exemplary damages, attorney's fees and costs of litigation. Thus:

TIJAM, J.:
x x x However, we find it proper to award temperate and exemplary
damages in light of NIA's misuse of its power of eminent
domain. Any arm of the State that exercises the delegated power of This Petition for Review1 on Certiorari under Rule 45 challenges the
eminent domain must wield that power with circumspection and utmost Decision2 dated September 1, 2015 of the Court of Appeals (CA) in CA�
regard for procedural requirements. A government instrumentality that G.R. CV No. 97640, which affirmed the Decision3 dated December 20,
fails to observe the constitutional guarantees of just compensation 2010 of the Regional Trial Court (RTC) of Pili, Camarines Sur, in the
and due process abuses the authority delegated to it, and is liable to expropriation case commenced by petitioner National Power Corporation
the property owner for damages.42 x x x (NPC) against respondents as registered owners of the subject properties.

Hence, considering that Oroville was deprived of beneficial ownership The Antecedents
over their property without the benefit of a timely expropriation
proceeding, and to serve as a deterrent to the State from failing to For purposes of constructing and maintaining its steel transmission lines
institute such proceedings, a grant of exemplary damages in the amount and wooden electric poles for its Naga-Tiwi 230 KV (Single Bundle), Naga-
of One Million Pesos (₱1,000,000.00) is fair and reasonable. Moreover, an Tiwi 230 KV (Double Bundle) and 69 KV Naga-Daraga Transmission Lines,
award for attorney's fees in the amount of Two Hundred Thousand Pesos NPC filed, on January 23, 2006, an expropriation complaint4 against
(₱200,000.00) in favor of Oroville is in order. respondents as registered owners of the following four parcels of land
located in Barangays Sagurong, San Agustin and San Jose, Pili, Camarines
Sur:
To recapitulate, Transco is liable to pay Oroville ₱78.65 per square meter
representing the fair market value of the property at the time of taking in
ProvRem Rule 67 Fulltext Page 115 of 119
respondents as "dangling" areas were classified as agricultural under the
Tax Dec. Area tax declarations and that NPC negotiated with respondents for purposes
Lot No. OCT No. Total Area
No. Affected of installing the transmission lines in 199627 and that NPC took the subject
properties in between the years 1996 to 1998.28 The right-of-way officer
97-014- further testified that the "dangling" areas could still be used for
516-B 6265 8,712 sq.m. 2,908 sq.m.
2276 agricultural purposes but nevertheless agreed that the presence of the
transmission lines may endanger the people and animals therein if in case
97-014- 861,163 they fell.29 On cross-examination, the right of way officer admitted that
4237 6277 33,196 sq.m.
3948 sq.m. the properties were classified as agro� industrial as stated in the 1998 tax
declarations. He admitted that the classification of the properties as
97-014- agricultural which was used as basis for computing its value was
2870 6289 13,462 sq.m. 5,940 sq.m.
39110 erroneous.30

97-014- The RTC rendered its Decision dated December 20, 2010 affirming the
517-B 62911 13,765 sq.m. 7,129 sq.m.
22812 recommendation of the appraisal committee for the payment of just
compensation and fixed the amount of PhP 47,064,400 for the 49,173
Total 49,173 square meters based on the BIR zonal valuation of the properties
Area: sq.m. classified as residential, commercial and industrial as of the time of the
filing of the complaint on January 23, 2006. The RTC rejected NPC's claim
that it took possession of the property in 1972 and 1974 when
The total area over which NPC sought an easement of right of way covers respondents allegedly. allowed NPC to construct the transmission lines for
49,173 square meters of the subject properties.13 Based on the tax lack of proof. In addition, the RTC held that had the properties been taken
declarations allegedly classifying the properties as agricultural and based on said years, such taking was without color of legal authority. The RTC
on the corresponding Bureau of Internal Revenue's (BIR) zoning valuation likewise adopted the recommendation of the appraisal committee for the
therefor, NPC offered to pay PhP 299,550.50.14 payment of PhP 22,227,800 as consequential damages for the 41,867
square meters portion of the properties which were rendered useless or
While interposing no objection to the expropriation, respondents no longer fit for its intended use due to the construction of the
nevertheless opposed the classification of the properties as agricultural on transmission lines.31
the ground that the same were classified as industrial, commercial and
residential since the year 1993 as shown by (1) Sangguniang Bayan In disposal, the RTC held:
Resolution No. 17; (2) Municipal Ordinance No. 7 dated February 1, 1993;
(3) annotations on the memorandum of encumbrances of the titles; (4)
Wherefore, judgment is hereby rendered:
DARCO Conversion Order No. 050301016014-(300)-00, Series of 2000
issued by the Department of Agrarian Reform; and (5) Certification issued
by the Municipal Assessor of Pili, Camarines Sur.15 Respondents thus 1. Approving and adopting the Commissioner's Report dated August 9,
claimed PhP 47,064,400 for the affected 49,173 square meters. By way of 2006 and November 24, 2008;
counterclaim, respondents sought payment of consequential damages for
the areas left in between each transmission line, like the spaces 2. The payment of the provisional value (on May 19, 2006 when plaintiff
underneath the infrastructure, commonly known as "dangling" portions in made the deposit) of P47,064,400.00 as just compensation for the 49,173
the total area of 41,869 square meters.16 square meters area directly affected by the transmission lines is the
payment for the just compensation with 12% interest per annum (Marina
After the pre-trial, the RTC issued an Order of Expropriation and further Z. Reyes, et al. vs. National Housing Authority, G.R. No. 147511, January 20,
fixed the provisional value of the properties at PhP 47,064,400, which 2003), from the date of filing of this case until paid;
amount was eventually deposited by NPC with Landbank of the
Philippines.17 Accordingly, in an Omnibus Order dated May 23, 2006, the 3. Condemning plaintiff to pay defendants the amount of P22,227,800.00
RTC issued a writ of possession in favor of NPC and ordered the LBP to as consequential damages with interest at 12% per annum from January
release to respondents the amount deposited.18 Meanwhile, an appraisal 23, 2006 until fully paid;
committee was formed by the RTC for purposes of determining just
compensation,19 which thereafter submitted a Consolidated Report dated
4. To pay P20,000.00 attorney's fees.
August 10, 2006.20 A reversed trial thereafter ensued.

SO ORDERED.32
Respondents presented the Chairman21 of the appraisal committee who
testified that the appraisal committee recommended22 the total valuation
of PhP 49,064,400 based on the assessor's data and the BIR zonal NPC's motion for reconsideration was denied by the RTC in its Order
valuations as indicated on the 1997 tax declarations.23 Also presented was dated May 2, 2011.33 However, the RTC modified the imposition of
the succeeding Chairman24 of the appraisal committee who testified that interest as follows:
the properties suffered consequential damages which the appraisal
committee recommended to be computed at 50% of the BIR zonal value Wherefore, judgment is hereby rendered:
per square meter or for a total amount of PhP 22,227,800.25 On ocular
inspection, the appraisal committee found that the existence of the 1. Approving and adopting the Commissioner's Report dated August 9,
transmission lines hampered the properties' potential use such that while 2006 and November 24, 2008;
the areas before and after the transmission lines could still be used, the
areas in between could no longer be utilized. The appraisal committee
also noted that the transmission lines produced considerable noise 2. The payment of the provisional value (on May 19, 2006 when plaintiff
making the area unsuitable for residential purposes.26 made the deposit) of P47,064,400.00 as just compensation for the 49,173
square meters area directly affected by the transmission lines is the
payment for the just compensation with interest at 6% per annum from
NPC, on the other hand, presented its right-of-way officers whose
testimonies sought to establish that the lots being claimed by
ProvRem Rule 67 Fulltext Page 116 of 119
the date of filing of the case until full payment less the interest collected The Issues
by the defendants from the bank deposit;
Reiterating its arguments before the lower courts, NPC interposes the
3. Condemning plaintiff to pay defendants the amount of P22,227,800.00 following issues for resolution: (1.) should the value of the property be
as consequential damages with interest at 6% per annum from January reckoned at the time of the taking in the 1970s; (2.) should the amount of
23, 2006 and at 12% per annum from the date of finality of this decision just compensation be based on the properties' BIR zonal valuation
until fully paid; corresponding to its classification as agricultural in the tax declarations;
and (3.) is the award of consequential damages for the "dangling" area
5. To pay P20,000.00 attorney's fees. proper.41

SO ORDERED.34 Essentially, NPC contests the amount of just compensation and the award
of consequential damages.

Consequently, NPC interposed its appeal before the CA raising as issues


the alleged erroneous award of just compensation and consequential The Ruling
damages. Specifically, NPC argued that the award was based on the
premise that it sought to acquire ownership over the properties when it We deny the petition.
merely seeks to acquire a right-of-way thus necessitating the payment of
a mere easement fee equivalent to 10% of the market value of the Reckoning point of the market value of the properties
properties. Further, it argued that the award is contrary to the zonal
valuation of the property classified as agricultural and erroneously
reckoned as of the time of the filing of the complaint instead as of the The circumstances surrounding the "taking" of property in the context of
time of taking. the State's exercise of the power of eminent domain has been
jurisprudentially listed in the seminal case of Republic v. Vda. De
Castellvi,42 thus:
On the other hand, respondents moved for the execution of the award
pending appeal which the RTC granted.35 A writ of execution and a notice
of garnishment were thereafter issued.36 First, the expropriator must enter a private property. x x x

On September 1, 2015, the CA rendered its Decision denying NPC's Second, the entrance into private property must be for more than a
appeal. Contrary to NPC's claim, the CA held that the just compensation momentary period. x x x
to be paid for an easement of a right-of-way over lands that would be
traversed by high-powered transmission lines should be the full value of xxxx
the subject property.37
Fourth, the property must be devoted to a public use or otherwise
The CA likewise found no merit in NPC's argument that the fair market informally appropriated or injuriously affected. x x x
value of the properties should have been based on the BIR zonal
valuation at the time of its supposed taking of the property in the 1970s Fifth, the utilization of the property for public use must be in such a way
and on the basis of its classification as agricultural land as stated in the as to oust the owner and deprive him of all beneficial enjoyment of the
tax declarations. The CA reasoned that NPC failed to allege the issue of property. x x x43
taking. in its complaint nor was such raised during pre-trial or proven
during trial. The CA also held that to base the fair market value of the
That there was taking of the subject properties for purposes of
property during the alleged actual taking in the 1970s is to compound the
expropriation is beyond contest. What plagues the court and the parties is
injustice caused to respondents as the expropriation complaint was filed
the date when such taking is to be reckoned because this will, in turn, be
more than 30 years after NPC allegedly took respondents' properties.38As
determinative of the value of the subject properties from which the
regards to the proper classification of the properties, the CA noted that
amount of just compensation will be based.
these were already reclassified as residential, commercial and industrial by
the municipality of Pili, Camarines Sur even prior to the filing of the
expropriation complaint.39 Sec. 4,44 Rule 67 lays down the basic rule that the value of the just
compensation is to be determined as of the date of the taking of the
property or the filing of the complaint, whichever came first.
Finally, the CA found no reason to disturb the RTC's award of
consequential damages as testimony to that effect was presented by
respondents while NPC, on the other hand, failed to prove the alleged The case of National Transmission Corporation v. Oroville Development
consequential benefits. Corporation,45 settles that just compensation should be reckoned from the
date of actual taking when such preceded the filing of the complaint for
expropriation. In Oroville, the Court explains that the State is. only obliged
The CA thus disposed:
to make good the loss sustained by the landowner and considering the
circumstances availing at the time the property was taken. Deviation from
WHEREFORE, the foregoing considered, the appeal is this general rule was permitted in the cases of National Power Corporation
hereby DENIED and the decision of the trial court [dated] December v. Heirs of Macabangkit Sangkay46 and National Power Corporation v.
20,2010, as modified by its Order dated May 2, 2011, is AFFIRMED in Spouses Saludares47 due to special circumstances48 therein obtaining
toto. which necessitated a valuation of just compensation at the time the
landowners initiated inverse condemnation proceedings notwithstanding
SO ORDERED.40 that taking of the properties occurred first.

Upon denial of its motion for reconsideration, NPC filed the present The peculiarity of the instant case is that NPC insists that it took the
petition. subject properties in the 1970s despite having initiated the expropriation
complaint only on January 23, 2006. Following the general rule, NPC thus

ProvRem Rule 67 Fulltext Page 117 of 119


reasons that the value of the properties should be reckoned in the 1970s. However, the insistence of NPC to base the value of the properties solely
However, NPC's expropriation complaint and the very testimonial on the tax declarations is misplaced considering that such is only one of
evidence it offered strongly militate against such proposition. the several factors which the court may consider to facilitate the
determination of just compensation. Indeed, courts enjoy sufficient
NPC's expropriation complaint filed on January 23, 2006 clearly sought "to judicial discretion to determine the classification of lands, because such
acquire an easement of right-of-way over portions of the [subject classification is one of the relevant standards for the assessment of the
properties]"49 to enable it "to construct and maintain its steel transmission value of lands subject of expropriation proceedings. It bears to
lines and wooden electric poles for its Naga-Tiwi 230 KV (Single Bundle), emphasize, however, that the court's discretion in classifying the
Naga-Tiwi 230 KV (Double Bundle) and 69 KV Naga-Daraga Transmission expropriated land is only for the purpose of determining just
Lines".50 NPC's action relative to the acquisition of an easement of right- compensation and is not meant to substitute that of the local
of-way made prior to the filing of its expropriation complaint was limited government's power to reclassify and convert lands through local
only to the conduct of negotiations with respondents. Even then, such ordinance.62
negotiations pertained to the construction of HVDC 350 KV transmission
lines which was not among the transmission lines subject of the The subject properties in this case had been reclassified as residential,
expropriation complaint. This, as much, was alleged by NPC itself in its commercial and industrial several years before the expropriation
expropriation complaint51 and was testified to by NPC's right-of-way complaint was filed. If NPC contests the reclassification of the subject
officer who conducted the negotiations in 1996.52 The lower courts were properties, the expropriation case is not the proper venue to do so. As
thus correct in disregarding NPC's claim of actual taking in the 1970s as such, the RTC and the CA did not err in abiding by the classification of the
such was not alleged in the expropriation complaint nor was it subject properties as residential, commercial and industrial as reclassified
successfully proven during the trial. under Sangguniang Bayan Resolution No. 17 and Municipal Ordinance
No. 7 dated February 1, 1993 and as certified to by the Municipal Assessor
There being no sufficient proof that NPC actually took the subject of Pili, Camarines Sur.
properties at a date preceding the filing of the expropriation complaint,
the time of the taking should be taken to mean as coinciding with the In any case, reliance on the tax declarations attached to NPC's
commencement of the expropriation proceedings on January 23, 2006. expropriation complaint to classify the properties as purely agricultural is
Hence, the value at the time of the filing of the complaint should be the inaccurate as these very same tax declarations reveal that portions of the
basis for the determination of the value when the taking of the property expropriated Lot No. 4237 and Lot No. 2870 are in fact classified as
involved coincides with or is subsequent to the commencement of the residential and commercial.63
proceedings.53
Award of consequential damages
Amount of just compensation
As a rule, just compensation, to which the owner of the property to be
To begin with, factual issues pertaining to the value of an expropriated expropriated is entitled, is equivalent to the market value.64 The rule is
property is beyond the scope of judicial review under a petition filed via modified where only a part of a certain property is expropriated. In such a
Rule 45.54 As such, factual findings of the trial and appellate courts will not case, the owner is not restricted to compensation for the portion actually
be disturbed by this Court unless any of the recognized exceptions is taken, he is also entitled to recover the consequential damages, if any, to
present.55 No such exception obtains in the instant case. the remaining part of the property.

The various provisions of the Constitution56 uniformly treat the payment Consequential damages is specifically enunciated under Section 6 of Rule
of just compensation as a limitation to the State's exercise of eminent 67 as follows:
domain. Just compensation likewise bears the consistent and settled
meaning as the full and fair equivalent of the property taken from its Section 6. Proceedings by Commissioners. - Before entering upon the
owner by the expropriator, the measure is not the taker's gain, but the performance of their duties, the commissioners shall take and subscribe
owner's loss. The word "just" is used to qualify the meaning of the word an oath that they will faithfully perform their duties as commissioners,
"compensation" and to convey thereby the idea that the amount to be which oath shall be filed in court with the other proceedings in the case.
tendered for the property to be taken shall be real, substantial, full and Evidence may be introduced by either party before the commissioners
ample.57 who are authorized to administer oaths on hearings before them, and the
commissioners shall, unless the parties consent to the contrary, after due
Further, the determination of just compensation in expropriation cases is notice to the parties, to attend, view and examine the property sought to
a function addressed to the discretion of the courts owing to the be expropriated and its surroundings, and may measure the same, after
constitutional mandate that no private property shall be taken for public which either party may, by himself or counsel, argue the case. The
use without payment of just compensation.58 As such, legislative commissioners shall assess the consequential damages to the
enactments, as well as executive issuances, fixing or providing for the property not taken and deduct from such consequential damages the
method of computing just compensation are tantamount to consequential benefits to be derived by the owner from the public
impermissible encroachment on judicial prerogatives. As such, they are use or purpose of the property taken, the operation of its franchise
not binding on courts and are treated as mere guidelines in ascertaining by the corporation or the carrying on of the business of the
the amount of just compensation.59 Even the enumeration of the corporation or person taking the property. But in no case shall the
standards for the assessment of the value of the land for purposes of consequential benefits assessed exceed the consequential damages
expropriation under Section 5 of Republic Act No. 897460 reflects the non- assessed, or the owner be deprived of the actual value of his property
exclusive, permissive and discretionary character thereof.61 so taken. (Emphasis supplied)

Here, NPC assails the valuation assigned to the subject properties for Thus, if as a result of expropriation, the remaining portion of the property
being contrary to its alleged classification as agricultural as appearing on suffers from impairment or decrease in value, the award of consequential
the tax declarations attached to its expropriation complaint. damages is proper.65

ProvRem Rule 67 Fulltext Page 118 of 119


Respondents in this case claim consequential damages for the areas in damages was not yet included. The total just compensation should
between the transmission lines which were rendered unfit for use. therefore be the total of PhP 47,064,400 and PhP22,227,800. Considering
"Dangling" areas, as defined under National Power Board Resolution No. that the amount of PhP 22,227,800 as consequential damages was not yet
94-313, refer to those remaining small portions of the land not traversed paid, such amount should earn interest at the rate of 12% per
by the transmission line project but which are nevertheless rendered annum from January 23, 2006 until June 30, 201374 and the interest rate of
useless in view of the presence of the transmission lines. The appraisal 6% per annum is imposed from July 1, 2013 until fully paid.75
committee determined the total dangling area to be 41,867 square
meters66 and consequently recommended the payment of consequential WHEREFORE, the Petition is DENIED. The Decision dated September 1,
damages equivalent to 50% of the BIR zonal value per square meter or for 2015 of the Court of Appeals, which affirmed the Decision dated
a total amount of PhP 22,227,800. December 20, 2010 of the Regional Trial Court of Pili, Camarines Sur,
is AFFIRMED with MODIFICATION such that the interest imposed on the
In arriving at its recommendation to pay consequential damages, the amount of PhP 47,064,409 is DELETED and that the award of
appraisal committee conducted an ocular inspection of the properties and consequential damages in the amount of PhP 22,227,800 shall earn
observed that the areas before and behind the transmission lines could interest at the rate of 12% per annum from January 23, 2006 until June 30,
no longer be used either for commercial or residential purposes. Despite 2013 and the interest rate of 6% per annum is imposed from July 1, 2013
this determination, NPC insists that the affected areas cannot be until fully paid.
considered "dangling" as these may still be used for agricultural
purposes.67 In so arguing, NPC loses sight of the undisputed fact that the SO ORDERED.
transmission lines conveying high-tension current posed danger to the
lives and limbs of respondents and to potential farm workers, making the
affected areas no longer suitable even for agricultural production. Thus,
the Court finds no reason to depart from the assessment of the appraisal
committee, as affirmed and adopted by the RTC.

NPC's contention that the consequential benefits should have canceled


the consequential damages likewise deserve no merit. It is true that if the
expropriation resulted in benefits to the remaining lot, such consequential
benefits may be deducted from the consequential damages or from the
value of the expropriated property.68 However, such consequential
benefits refer to the actual benefits derived by the landowner which are
the direct and proximate results of the improvements as a consequence
of the expropriation and not to the general benefits which the landowner
may receive in common with the community.69 Here, it was not shown by
NPC how the alleged "tremendous increase" in the value of the remaining
portions of the properties could have been directly caused by the
construction of the transmission lines.70 If at all, any appreciation in the
value of the properties is caused by the consequent increase in land value
over time and not by the mere presence of the transmission lines.

Imposition of interest

Notwithstanding the foregoing, We find the need to modify the


imposition of interest.

The award of interest is imposed in the nature of damages for delay in


payment which, in effect, makes the obligation on the part of the
government one of forbearance to ensure prompt payment of the value
of the land and limit the opportunity loss of the owner.71 Thus, the
imposition of interest is justified only in cases where delay has been
sufficiently established.72

In this case, NPC deposited the provisional value of the subject properties
in the amount of PhP 47,064,400 on May 19, 2006 which was days before
the issuance of a writ of possession. Considering NPC's prompt payment,
the imposition of interest thereon is unjustified and should therefore be
deleted.

However, interest should be imposed on the award of consequential


damages as it is a component of just compensation. To emphasize, in
order to determine just compensation, the trial court should first ascertain
the market value of the property, to which should be added the
consequential damages after deducting therefrom the consequential
benefits which may arise from the expropriation. If the consequential
benefits exceed the consequential damages, these items should be
disregarded altogether as the basic value of the property should be paid
in every case.73 Here, when the RTC pegged the amount of PhP
47,064,400 for the expropriated 49,173 square meters, the consequential
ProvRem Rule 67 Fulltext Page 119 of 119

You might also like