Professional Documents
Culture Documents
Three (3) questions are resolved in the action of certiorari at bar. The first At the separate trial, the Fiscal, in representation of the Municipality called
is whether the special civil action of eminent domain under Rule 67 of the the Trial Court's attention to the irregularity of allowing Francisco to
Rules of Court is a case "wherein multiple appeals are allowed, 1 as present her evidence ahead of the plaintiff, "putting the cart before the
regards which 'the period of appeal shall be thirty [30] days,2 instead of horse, as it were." He argued that the motion to dismiss was in truth an
fifteen (15) days. 3 The second is whether or not the Trial Court may treat answer, citing Rural Progress Administration v. Judge de Guzman, and its
the motion to dismiss" filed by one of the defendants in the action of filing did "not mean that the order of presentation of evidence will be
eminent domain as a "motion to dismiss" under Rule 16 of the Rules of reversed," but the usual procedure should be followed; and the evidence
Court, reverse the sequence of trial in order and hear and determine said adduced should be deemed "evidence only for the motion for
motion to dismiss, and thereafter dismiss the expropriation suit as against reconsideration of the writ of possession." 10
the movant. And the third is whether or not a "locational clearance issued
by the Human Settlements Regulatory Commission relative to use of land
Nevertheless, at the hearing of March 5, and March 26, 1984, the Court
is a bar to an expropriation suit involving that land.
directed Francisco to commence the presentation of evidence. Francisco
presented the testimony of Atty. Josue L. Jorvina, Jr. and certain exhibits
The expropriation suit involved in this certiorari proceeding was the Land Use Map of the Municipality of Biñan, the Locational Clearance
commenced by complaint of the Municipality of Biñan, Laguna 4 filed in and Development Permit issued by the H.S.R.C. in favor of "Erlinda
the Regional Trial Court of Laguna and City of San Pablo, presided over by Francisco c/o Ferlins Realty & Development Corporation, and Executive
respondent Judge Jose Mar Garcia. The complaint named as defendants Order No. 648 and Letter of Instruction No. 729, etc. Thereafter, the
the owners of eleven (11) adjacent parcels of land in Biñan with an respondent Judge issued an Order dated July 24, 1984 dismissing the
aggregate area of about eleven and a half (11-1/2) hectares. The land complaint "as against defendant ERLINDA FRANCISCO," and amending
sought to be expropriated was intended for use as the new site of a the Writ of Possession dated October 18, 1983 so as to "exclude
modern public market and the acquisition was authorized by a resolution therefrom and from its force and effects said defendant .. and her
of the Sangguniang Bayan of Biñan approved on April 11, 1983. property ..." His Honor found that-
One of the defendants was Erlinda Francisco. She filed a "Motion to 1) a Locational Clearance had
Dismiss" dated August 26, 1983, on the following grounds; (a) the been issued on May 4,1983 by
allegations of the complaint are vague and conjectural; (b) the complaint the Human Settlements
violates the constitutional limitations of law and jurisprudence on eminent Regulatory Commission to the
domain; (c) it is oppressive; (d) it is barred by prior decision and "Ferlin's Realty .. owned by
disposition on the subject matter; and (e) it states no cause of defendant Erlinda Francisco to
action. 5 Now, her motion to dismiss" was filed pursuant to Section 3, Rule convert .. (her) lot to a
67 of the Rules of Court: commercial complex;"
Sec. 3. Defenses and objections within the time 2) according to the testimony of
specified in the summons, each defendant, in lieu of Atty. Jorvina of the H.S.R.C., a
an answer, shall present in a single motion to dismiss grantee of a locational clearance
or for other apppropriate relief, all of his objections acquires a vested right over the
and defenses to the right of the plaintiff to take his subject property in the sense
property for the use or purpose specified in the that .. said property may not be
complaint. All such objections and defenses not so subject of an application for
presented are waived. A copy of the motion shall be locational clearance by another
served on the plaintiffs attorney of record and filed applicant while said locational
with the court with the proof of service. clearance is subsisting;"
Her "motion to dismiss" was thus actually a pleading, taking the place of 3) such a clearance should be
an answer in an ordinary civil action; 6 it was not an ordinary motion "considered as a decision and
governed by Rule 15, or a "motion to dismiss" within the contemplation disposition of private property
of Rule 16 of the Rules of Court. co-equal with or in parity with a
2) moreover, the grant of a The first phase of a partition and/or accounting suit is taken up with the
separate trial at Francisco's determination of whether or not a co-ownership in fact exists, and a
instance had given rise "ipso partition is proper (i.e., not otherwise legally prescribed) and may be
facto to a situation where made by voluntary agreement of all the parties interested in the
property. 25 This phase may end with a declaration that plaintiff is not
ProvRem Rule 67 Fulltext Page 2 of 119
entitled to have a partition either because a co-ownership does not exist, proceedings in accordance with Rule 109 of the Rules of Court and other
or partition is legally prohibited.26 It may end, on the other hand, with an cases wherein multiple appeals are allowed, the period of appeal shall be
adjudgment that a co-ownership does in truth exist, partition is proper in thirty (30) days, a record of appeal being required. 45
the premises and an accounting of rents and profits received by the
defendant from the real estate in question is in order. 27 In the latter case, The municipality's motion for reconsideration filed on August 17, 1984
"the parties may, ff they are able to agree, make partition among was therefore timely presented, well within the thirty-day period laid
themselves by proper instruments of conveyance, and the court shall down by law therefor; and it was error for the Trial Court to have ruled
confirm the partition so agreed upon. 28, In either case i.e. either the otherwise and to have declared that the order sought to be considered
action is dismissed or partition and/or accounting is decreed the order is had become final and executory.
a final one, and may be appealed by any party aggrieved thereby. 29
Accordingly, the RTC ordered NAPOCOR to pay the respondents: (1) just The dismissal of the proceedings for expropriation at the instance of
compensation for the whole area of 14,257 square meters at the rate of NAPOCOR is proper, but, conformably with Section 4,36 Rule 67 of the
₱550.00/square meter; (2) legal rate of interest from May 5, 1995 until full Rules of Court, the dismissal or discontinuance of the proceedings must
payment; and (3) the costs of suit.27 be upon such terms as the court deems just and equitable.
NAPOCOR appealed (CA-G.R. No. 72069). Before anything more, we remind the parties about the nature of the
power of eminent domain. The right of eminent domain is "the ultimate
On April 29, 2004,28 the CA promulgated its decision, viz: right of the sovereign power to appropriate, not only the public but the
private property of all citizens within the territorial sovereignty, to public
purpose."37 But the exercise of such right is not unlimited, for two
WHEREFORE, premises considered, the Decision dated November 27, mandatory requirements should underlie the Government’s exercise of
2000 of Branch I of the Regional Trial Court of Batangas City, is hereby the power of eminent domain, namely: (1) that it is for a particular public
AFFIRMED with the MODIFICATION that plaintiff-appellant shall pay only purpose; and (2) that just compensation be paid to the property
for the occupied 6,326 square meters of the subject real property at the owner.38 These requirements partake the nature of implied conditions that
rate of ₱550.00 per square meter and to pay legal interest therefrom until should be complied with to enable the condemnor to keep the property
fully paid. expropriated.39
SO ORDERED.29 Public use, in common acceptation, means "use by the public." However,
the concept has expanded to include utility, advantage or productivity for
Hence, this appeal by NAPOCOR. the benefit of the public.40 In Asia's Emerging Dragon Corporation v.
Department of Transportation and Communications,41 Justice Corona, in
Issue his dissenting opinion said that:
On December 3, 2012, during the pendency of the appeal, NAPOCOR filed To be valid, the taking must be for public use. The meaning of the term
a Motion to Defer Proceedings stating that negotiations between the "public use" has evolved over time in response to changing public needs
and exigencies. Public use which was traditionally understood as strictly
Thus, the present petition claiming that: Respondent for its part contends that its power to acquire private
property for public use upon payment of just compensation was correctly
upheld by the trial court; that the CA was correct in finding that the
A. RESPONDENT IS WITHOUT, LACKS AND DOES NOT HAVE THE LAWFUL
petitioners were not denied due process, even though no hearing was
POWER TO ACQUIRE ANY OR ALL OF THE SUBJECT PROPERTIES
conducted in the trial court, as petitioners were still able to adduce their
THROUGH EMINENT DOMAIN, IT BEING EXERCISED BY MEANS OF A
objections and defenses therein; and that petitioners’ arguments have
MERE RESOLUTION, AND NOT THROUGH AN ORDINANCE AS REQUIRED
been passed upon by both the trial court and the CA and were all denied
BY LAW AND APPLICABLE JURISPRUDENCE;
for lack of substantial merit. 18
No costs.
It is clear therefore that several requisites must concur before an LGU can
exercise the power of eminent domain, to wit:
SO ORDERED.
DECISION
3. There is payment of just compensation, as required under Section 9,
Article III of the Constitution, and other pertinent laws.
CHICO-NAZARIO, J.:
4. A valid and definite offer has been previously made to the owner of the
property sought to be expropriated, but said offer was not accepted. 30 Before this Court is a Petition for Review on Certiorari under Rule 45 of
the 1997 Revised Rules of Civil Procedure seeking to review, reverse, and
Among the lots affected by the petitioner’s Interconnection Project were In compliance with the 4 September 2000 Order of the RTC, respondents
those owned by the respondents located in Dawis Sur, Carmen, Cebu. filed their Motion for Summary Judgment, with several documentary
Respondent Santa Loro Vda. De Capin’s lot has an area of 16,193 square evidence and affidavits of witnesses attached, on 10 October 2000.
meters, covered by Tax Declaration No. 15-22196 (1994);7 while
respondent-Spouses Quimco’s lot has an area of 3,298 square meters,
covered by Tax Declaration No. 31376 (1996).8 To be able to enter the In an Order16 dated 17 November 2000, the RTC gave petitioner a 15-day
said properties, petitioner obtained from each of the respondents Santa period from receipt of the said Order to file its Opposition to or Comment
Loro Vda. De Capin and Spouses Quimco a "Permission to Enter for on respondents’ Motion for Summary Judgment.
Construction of Transmission Line Project," dated 14 June 19949 and 11
December 1996,10 respectively. The permits were signed by the On 21 December 2000, petitioner filed a Motion for Extension of Time to
respondents upon representation by the petitioner that it would pay them File Comment on Motion for Summary Judgment. It averred that (1) it was
just compensation for the intrusion into their properties. not inclined to oppose respondents’ Motion for Summary Judgment,
except that the area of 3,199 square meters of respondents’ lots alleged
Thereafter, petitioner began to construct on respondents’ properties its to have been traversed by petitioner’s transmission lines was still being
power lines and transmission towers, which were completed in 1996. verified as to its correctness by its Right of Way Officers; and (2) upon
Petitioner’s Interconnection Project affected portions of respondents’ confirmation that the area was correct, it would join respondents’ Motion
properties, with a combined area of 3,199 square meters. Upon its for Summary Judgment.17 In an Order18 dated 29 December 2000, the RTC
completion of the construction of the power lines and transmission granted petitioner’s motion and gave it an extension of 15 days within
towers, petitioner imposed several restrictions upon the respondents on which to file its Comment to respondents’ Motion for Summary
Judgment.
the use of their lands, which included the prohibition against planting or
building anything higher than three meters below the area traversed by
its transmission lines as the high tension electric current passing through Despite the extension given the petitioner, it still failed to file its
said lines pose danger to life and limbs. Additionally, respondent-Spouses Comment. Hence, in an Order19 dated 23 February 2001, the RTC deemed
Quimco, holder of a Small Scale Quarry Permit, Series of 1995, were also respondents’ Motion for Summary Judgment submitted for resolution.
prohibited from continuing their quarry business near petitioner’s
transmission towers because of the great possibility that the quarry might On 16 April 2001, the RTC rendered a Resolution in favor of the
weaken the foundation of the transmission towers. In other words, respondents, the decretal portion of which reads:
respondents lost substantial amount of income due to the restriction
imposed on their properties by the petitioner.
WHEREFORE, in view of the foregoing, judgment is hereby rendered in
favor of the [herein respondents], ordering the [herein petitioner] to pay
Petitioner then paid respondents Santa Loro Vda. De Capin and Spouses damages in the amount of FOUR HUNDRED FORTY EIGHT & 33/100
Quimco the amounts of ₱8,015.9011and ₱5,350.49,12 respectively, for the PESOS (₱448.33) PER SQUARE METER or the total amount of ONE
portions of their lots affected by the Interconnection Project. Only later MILLION FOUR HUNDRED THIRTY FOUR AND TWO HUNDRED SEVEN &
did respondents discover that in comparison to the measly sums they 67/100 PESOS (₱1,434,207.67) for the 3,199 square meters of
were paid by petitioner, the other landowners within their area who [respondents’] lots taken by the [petitioner], with interest thereon at the
resisted the expropriation of their properties in court or who entered into rate of 14% per annum computed since 1996 when the [petitioner] took
compromise agreements with the petitioner were paid by petitioner the said portions from the [respondents].20
amount of ₱448.30 to ₱450.00 per square meter as just compensation for
the portions of their properties similarly affected by the petitioner’s
Petitioner filed a Motion for Reconsideration praying that the aforesaid
Interconnection Project.
Resolution of the RTC be set aside and the amount of just compensation
be reduced to ₱25.00 per square meter. Petitioner also filed a
Accordingly, respondents filed a Complaint13 for Rescission of Agreement, Supplemental Motion for Reconsideration seeking the reduction of the
Recovery of Possession of Parcels of Land, Removal of Tower and interest rate imposed by the RTC from 14% per annum to 6% per annum.
ProvRem Rule 67 Fulltext Page 10 of 119
Acting on petitioner’s Motion for Reconsideration and Supplemental The Resolution dated 16 April 2001 of the RTC in Civil Case No. DNA-547,
Motion for Reconsideration, the RTC issued an Order21 dated 24 August fixing the fair market value for the portions of respondents’ lots affected
2001, affirming its Resolution dated 16 April 2001, with the modification by the Interconnection Project at ₱448.33 per square meter, is based on
that the imposable rate of interest was reduced to 6% per annum from the Decision dated 25 May 1998 also of the RTC in Civil Case No. DNA-
the filing of the complaint, and 12% per annum from the time the 379;26 which, petitioner contends, is based on another Decision dated 5
judgment has become final and executory until fully satisfied. According May 1998 of the same RTC in Civil Case No. DNA-373.27 In its 5 May 1998
to the dispositive portion of the RTC Order: Decision in Civil Case No. DNA-373, the RTC considered the opinion
values of the Committee on Appraisal in determining the fair market value
WHEREFORE, the resolution of this Court dated [16 April 2001] is hereby of the properties involved therein. The said Decision, however, did not
affirmed with modification that the imposable rate of interest of the contain a description of the properties involved therein and their land
monetary judgment in favor of [respondents] should be 6% per annum classification at the time of the filing of the complaint and/or their taking.
from the filing of the complaint and 12% per annum from the time the Therefore, the Decision dated 25 May 1998 in Civil Case No. DNA-379 did
judgment has become final and executory until fully satisfied, using the not provide sufficient basis for pegging the fair market value of
amount adjudged as the actual base for the computation.22 respondents’ properties at ₱448.33 per square meter in Civil Case No.
DNA-547.
Still refusing to accept the judgment of the RTC, petitioner appealed the
16 April 2001 Resolution and 24 August 2001 Order of the said trial court Petitioner maintains that the RTC did not discuss in its Resolution dated
to the Court of Appeals. Petitioner’s appeal was docketed as CA-G.R. CV 16 April 2001 its factual and legal bases for fixing the amount of damages
No. 73656. payable to respondents. Respondents likewise failed to demonstrate that
their properties, at the time of their taking, were of the same classification
as the properties belonging to other landowners which were similarly
On 21 April 2006, the appellate court rendered a Decision affirming the traversed by petitioner’s Interconnection Project and for which petitioner
Resolution dated 16 April 2001, as modified by the Order dated 24 paid more. Finally, petitioner insists that it only acquired an easement of
August 2001, both by the RTC. right of way on respondents’ properties for the construction of its
transmission lines. The respondents still retained ownership of their
Petitioner moved for the reconsideration of the appellate court’s Decision, properties despite the imposition of an easement of right of way thereon.
but it was denied by the same court in a Resolution dated 27 October Consequently, petitioner is liable only to pay respondents an easement
2006. fee, not exceeding 10% of the fair market value of the portions of their
properties actually affected by the petitioner’s Interconnection Project, in
Hence, petitioner filed the present Petition before this Court, raising the accordance with Section 3-A(b) of petitioner’s Charter, as amended.
following issues:
The Petition is bereft of merit.
I. Whether or not the Court of Appeals committed reversible error in
upholding the propriety of the trial court’s resort to summary Summary or accelerated judgment is a procedural technique aimed at
judgment in determining the amount of just compensation for the weeding out sham claims or defenses at an early stage of the litigation,
properties of respondents affected by petitioner’s transmission line thereby avoiding the expense and loss of time involved in a trial. Even if
project. the pleadings appear, on their face, to raise issues, summary judgment
may still ensue as a matter of law if the affidavits, depositions and
II. Whether or not the Court of Appeals committed reversible error in admissions show that such issues are not genuine. The presence or
affirming the finding of the trial court that the total area of absence of a genuine issue as to any material fact determines, at
respondents’ lands affected by petitioner’s transmission line project bottom, the propriety of summary judgment.28
is 3,199 square meters.
Sections 1 and 3, Rule 35 of the Revised Rules of Civil Procedure provide:
III. Whether or not the Court of Appeals committed reversible error
in ruling that the decision in Civil Case No. DNA-379 provides SECTION 1. Summary judgment for claimant. – A party seeking to recover
sufficient basis for fixing the fair market value of the affected upon a claim, counterclaim, or cross-claim or to obtain a declaratory relief
properties of respondents at ₱448.33 per square meter. may, at any time after the pleading in answer thereto has been served,
move with supporting affidavits, depositions or admissions for a summary
IV. Whether or not the Court of Appeals committed reversible error judgment in his favor upon all or any part thereof.
in not ruling that under petitioner’s Charter, R.A. No. 6395, as
amended, respondents are only entitled to simple easement fees.23 xxxx
Petitioner argues that although the Complaint filed by the respondents SEC. 3. Motion and proceedings thereon. – The motion shall be served at
before the RTC was one for rescission of agreement and/or damages, it least ten (10) days before the time specified for the hearing. The adverse
was subsequently transformed into one for "reversed eminent party may serve opposing affidavits, depositions, or admissions at least
domain"24 where the determination of the amount of just compensation three (3) days before the hearing. After the hearing, the judgment sought
was the issue. In fact, respondents’ Motion for Summary Judgment shall be rendered forthwith if the pleadings, supporting affidavits,
focused only on the payment of just compensation. Resultantly, the RTC depositions, and admissions on file, show that, except as to the amount of
erred in resolving the respondents’ Complaint on the basis of the damages, there is no genuine issue as to any material fact and that the
provisions of the Rules of Court on Summary Judgment. The rules on moving party is entitled to a judgment as a matter of law.
summary judgment apply only to ordinary taking of properties. Instead of
granting respondents’ Motion for Summary Judgment, the RTC should Under the afore-quoted procedural rules, for a summary judgment to be
have appointed commissioners who would ascertain the amount of just proper, the movant must establish two requisites: (a) there must be no
compensation for the subject properties, pursuant to Section 5, Rule 67 of genuine issue as to any material fact, except for the amount of damages;
the Revised Rules of Court.25 Thus, the determination of just and (b) the party presenting the motion for summary judgment must be
compensation by the RTC based only on the pleadings submitted, was entitled to a judgment as a matter of law. Where, on the basis of the
palpably void.
ProvRem Rule 67 Fulltext Page 11 of 119
pleadings of a moving party, including documents appended thereto, no geodetic engineer who supposedly conducted the survey and its
genuine issue as to a material fact exists, the burden to produce a preparation which makes these documents of doubtful credibility. As such
genuine issue shifts to the opposing party. If the opposing party fails, the without any comment filed by the [petitioner] and without any evidence
moving party is entitled to a summary judgment.29 to the contrary, the court a quo correctly relied on the evidence submitted
by the [respondents]. x x x. The [petitioner] cannot now raise any issue
A "genuine issue" is an issue of fact which requires the presentation of as to any material fact in the case at bar when through its own fault
evidence as distinguished from a sham, fictitious, contrived or false claim. and inaction, it chose to remain silent when the motion for summary
When the facts as pleaded appear uncontested or undisputed, then there judgment was filed with the RTC. Such an actuation speaks of a dilatory
is no real or genuine issue or question as to the facts, and summary tactic on the part of the [petitioner] in the payment of the just
judgment is called for. The party who moves for summary judgment has compensation due the [respondents].33 (Emphasis supplied.)
the burden of demonstrating clearly the absence of any genuine issue of
fact, or that the issue posed in the complaint is patently unsubstantial so In light of the foregoing, the issue on the area of respondents’ lots
as not to constitute a genuine issue for trial. Trial courts have limited actually affected by petitioner’s Interconnection Project was not timely or
authority to render summary judgments and may do so only when there validly raised as an issue before the RTC. Except for the amount of
is clearly no genuine issue as to any material fact. When the facts as damages to which the respondents were entitled to as a matter of law,
pleaded by the parties are disputed or contested, proceedings for there was no other genuine issue as to any material fact involved in Civil
summary judgment cannot take the place of trial.30 Case No. DNA-547. Hence, the RTC was justified in resorting to summary
judgment.
In this case, during the Pre-trial Conference, petitioner already admitted
that it had taken portions of respondents’ lands for the construction of its Equally futile is petitioner’s insistence that respondents’ Complaint is
power lines and transmission towers pursuant to its Interconnection actually for "reversed eminent domain," which requires the appointment
Project. However, the parties could not agree on the amount of just of commissioners for the determination of just compensation, as provided
compensation or damages that petitioner should pay respondents for the under Section 5, Rule 67 of the Revised Rules of Court, rather than the
lands taken. Respondents insist that they be paid the full market value of promulgation of a summary judgment.
the portions of their lots taken by the petitioner, while petitioner believed
that it was only bound to pay respondents easement fees, which was It should be emphasized that the present case stemmed from a Complaint
equivalent to 10% of the market value of the respondents’ lots as for Rescission of Agreement, Recovery of Possession of Parcels of Land,
indicated in their tax declarations, pursuant to Section 3-A of petitioner’s Removal of Tower and Transmission Lines, Damages and Other Reliefs
Charter. Evidently, based on the foregoing, what remained for the filed by the respondents against the petitioner. It was an ordinary civil
determination of the RTC was the proper amount of damages due the action for the rescission of respondents’ agreement with petitioner, as
respondents for the portions of their lots taken by the petitioner. well as recovery of the possession of the lots taken, for failure of
petitioner to comply with its obligation to pay just compensation for the
Accordingly, respondents filed a Motion for Summary Judgment before respondents’ properties. Payment of just compensation or damages was
the RTC, where they specifically alleged that: an alternative remedy, akin to specific performance by the petitioner of its
obligation under its agreement with respondents, which would prevent
"4. Portions of the above-described parcels of land with a total area the rescission of the agreements altogether and the return of the
of 3,199 square meters were affected by the aforesaid [petitioner’s] possession of the properties to respondents. The parties, at the Pre-Trial
230 KV Leyte-Cebu Interconnection Project and were taken by Conference, implicitly agreed to pursue the remedy for payment of
[petitioner] in 1996, is shown by a Sketch Plan hereto attached as Annex damages rather than rescission of the agreement. Clearly, the proceedings
Cwhich is also made an integral part of this motion."31 (Emphasis before the RTC were not for expropriation, but were for damages, to
supplied.) which Section 5, Rule 67 of the Revised Rules of Court is irrelevant.
Petitioner, in turn, filed its Motion for Extension of Time to File Comment, Reference may be made to National Power Corporation v. Court of
which was granted by the RTC. In its Motion, petitioner stated that it was Appeals.34 In the said case, after therein petitioner NAPOCOR withdrew its
not inclined to oppose respondents’ Motion for Summary second Petition for Expropriation, what was left for the trial court’s
Judgment, exceptthat its officers were still verifying whether the area of determination was the counterclaim of therein private respondent
respondents’ lots traversed by petitioner’s transmission lines was indeed Antonino Pobre, contained in his Motion to Dismiss, for damages. The
3,199 square meters; and the moment the area is confirmed to be correct, Court ruled therein:
petitioner will join respondents’ Motion for Summary Judgment. However,
despite the ample opportunities given to petitioner by the RTC, it never "In this case, NPC appropriated [private respondent’s] Property without
filed any Opposition to or Comment on respondents’ Motion for resort to expropriation proceedings. NPC dismissed its own complaint for
Summary Judgment. It did not submit to the RTC the results of its the second expropriation. At no point did NPC institute expropriation
supposed verification of the area of respondents’ lots actually traversed proceedings for the lots outside the 5,554 square-meter portion subject
by its transmission lines. Petitioner only raised the issue on the area of the second expropriation. The only issues that the trial court had to
actually taken after the RTC had rendered summary judgment directing settle were the amount of just compensation and damages that NPC had
petitioner to pay damages for the 3,199 square meters it took from to pay [private respondent].
respondents.
This case ceased to be an action for expropriation when NPC dismissed its
As correctly and clearly ratiocinated by the Court of Appeals in its complaint for expropriation. Since this case has been reduced to a
appealed Decision: simple case of recovery of damages, the provisions of the Rules of
Court on the ascertainment of the just compensation to be paid were
[Petitioner] did not present the alleged communication of its Project no longer applicable. A trial before commissioners, for instance, was
Manager or the sketch plans for the RTC’s perusal despite the extension dispensable." (Emphasis supplied.)
of time given by the court a quo. In view thereof, it is quite clear that the
[petitioner] was given sufficient time to verify the area affected by Petitioner herein cannot hide behind the mantle of protection of
[petitioner’s] tower and transmission lines and to inform the court of the procedural laws when it has so arbitrarily violated respondents’ right to
result thereof. Furthermore, the sketch plans32were not even signed by the just compensation for their properties taken for public use.
ProvRem Rule 67 Fulltext Page 12 of 119
Petitioner assured respondents that it will pay them just compensation for resulting in a restriction or limitation on property rights over the land
the portions of their lots needed for the Interconnection Project, on the traversed by transmission lines also falls within the ambit of the term
basis of which respondents agreed in good faith to allow petitioner to "expropriation."37
already enter their properties and build thereon. Yet, instead of paying
respondents just compensation for the portions of their lots taken, they After petitioner’s transmission lines were fully constructed on portions of
were paid negligible amounts as easements fees. respondents’ lots, petitioner imposed restrictions thereon such as the
prohibition against planting or building anything higher than three
More lopsided is the fact that the other landowners within their area who meters below the area traversed by said lines. In addition, respondent-
resisted the taking of their properties were paid by petitioner way more Spouses Quimco, holders of a Small Scale Quarry Permit, Series of
than respondents who voluntarily dealt with petitioner. Petitioner had to 1995,38 were also prohibited from continuing their quarry business near
bring some of the resisting landowners to court in expropriation petitioner’s transmission towers because of the great possibility that it
proceedings where petitioner willingly paid just compensation for the said could weaken the foundation thereof. Hence, the respondent-spouses
landowners’ properties, as determined by a panel of commissioners. Quimco suffered substantial loss of income. It is clear then that
Petitioner entered into compromise agreements with the other resisting petitioner’s acquisition of an easement of right of way on the lands of the
landowners in which it likewise paid just compensation for the latter’s respondents amounted to an expropriation of the portions of the latter’s
properties. There is no rhyme or reason why respondents were the only properties and perpetually deprived the respondents of their proprietary
ones paid with easement fees, which were of much lesser values. rights thereon and for which they are entitled to a reasonable and just
compensation. Just compensation is defined as the full and fair
The Decision dated 25 May 1998 of the RTC in Civil Case No. DNA- equivalent of the property taken from its owner by the expropriator.
37935 provides sufficient basis for the same RTC in Civil Case No. DNA-547 The measure is not the taker’s gain, but the owner’s loss. The word
to award just compensation to respondents, equivalent to the fair market "just" is used to intensify the meaning of the word "compensation" and to
value of their affected properties at a rate of P448.33 per square meter. convey thereby the idea that the equivalent to be rendered for the
property to be taken shall be real, substantial, full and ample.39
In its 25 May 1998 Decision in Civil Case No. DNA-379, the RTC therein
ordered the petitioner to pay just compensation in the amount of ₱448.33 As the Court thoroughly explained in National Power Corporation v.
per square meter for the lot owned by the heirs of Tomas Gingco, which Gutierrez,40 viz:
was similarly traversed by petitioner’s transmission lines. Said Decision
became final and executory on 3 December 1998.36 Although it is a The trial court’s observation shared by the appellate court show that "x x x
Decision in another case, the RTC in Civil Case No. DNA-547 can take While it is true that plaintiff [is] only after a right-of-way easement, it
cognizance thereof when respondents presented the same for its nevertheless perpetually deprives defendants of their proprietary
consideration. rights as manifested by the imposition by the plaintiff upon defendants
that below said transmission lines no plant higher than three (3) meters is
The lot of the heirs of Tomas Gingco and those of the herein respondents allowed. Furthermore, because of the high-tension current conveyed
are all located within the same area in Dawis Sur, Carmen, Cebu and, are through said transmission lines, danger to life and limbs that may be
in fact, separated only by a lot owned jointly by Epifanio, Edilberto and caused beneath said wires cannot altogether be discounted, and to cap it
Josefa, all surnamed Loro. The lots owned by the respondents are even all, plaintiff only pays the fee to defendants once, while the latter
more advantageously situated than the lot owned by the heirs of Tomas shall continually pay the taxes due on said affected portion of their
Gingco since respondents’ properties are traversed by a barangay road property."
and near the quarry areas of Llyons Richfield Industrial Corporation. The
lots of the heirs of Tomas Gingco and of the respondents were all affected The foregoing facts considered, the acquisition of the right-of-way
by the Interconnection Project and were taken by the petitioner at about easement falls within the purview of the power of eminent domain.
the same time. The lots of respondents were effectively taken in June Such conclusion finds support in similar cases of easement of right-of-
1996, while the lot of the heirs of Tomas Gingco was acquired only a way where the Supreme Court sustained the award of just compensation
month later, in July 1996. Since the personalities and properties in both for private property condemned for public use (See National Power
Civil Case No. DNA-379 and Civil Case No. DNA-547 were essentially in Corporation vs. Court of Appeals, 129 SCRA 665, 1984; Garcia vs. Court of
similar situations, then the just compensation awarded for the property in Appeals, 102 SCRA 597, 1981). The Supreme Court, in Republic of the
the former case was a logical and reasonable basis for fixing or Philippines vs. PLDT, thus held that:
determining the just compensation due in the latter.
"Normally, of course, the power of eminent domain results in the taking
Furthermore, petitioner attached to their Motion for Summary Judgment or appropriation of title to, and possession of, the expropriated property;
several pieces of document in support of their allegations therein, and but no cogent reason appears why said power may not be availed of to
they furnished petitioner copies of the same. The petitioner was given impose only a burden upon the owner of condemned property,
ample time to study, challenge, and controvert respondents’ evidences, without loss of title and possession. It is unquestionable that real
yet it failed to do so. The RTC only rightfully proceeded, based on its property may, through expropriation, be subjected to an easement of
evaluation of the evidence on record, to render a Decision awarding to right-of-way."
the respondents just compensation or damages for the taking of their
lots, equivalent to the fair market value thereof at the rate of ₱448.33 per In the case at bar, the easement of right-of-way is definitely a taking
square meter. under the power of eminent domain. Considering the nature and effect of
the installation of the 230 KV Mexico-Limay transmission lines,
Finally, petitioner cannot insist that it only acquired an easement of right the limitation imposed by NPC against the use of the land for an
of way on the properties of the respondents and that it was liable to pay indefinite period deprives private respondents of its ordinary
respondents only an easement fee not exceeding 10% of the fair market use.41 (Emphasis supplied.)
value of the portions of their property actually affected by the
Interconnection Project, pursuant to Section 3-A(b) of its Charter. Having established that petitioner’s acquisition of right-of-way easement
over the portions of respondents’ lots was definitely a taking under the
Expropriation is not limited to the acquisition of real property with a power of eminent domain, petitioner then is liable to pay respondents
corresponding transfer of title or possession. The right-of-way easement
ProvRem Rule 67 Fulltext Page 13 of 119
just compensation and not merely an easement fee. The Court quotes This is a special civil action for certiorari to annul, for having been issued
with affirmation the ruling of the Court of Appeals on this matter: without or in excess of jurisdiction, in violation of law and in deprivation
of petitioner's right to due process, four (4) orders successively issued by
The [herein petitioner] vehemently insists that its Charter [Section 3A (b) the respondent Judge in seven (7) eminent domain cases (1) fixing the
of R.A. 6395] obliges it to pay only a maximum of 10% of the market value provisional values of the parcels of land sought to be expropriated by the
declared by the owner or administrator or anyone having legal interest in petitioner, National Power Corporation (NAPOCOR), in amounts far
the property, or such market value as determined by the assessor, exceeding their market values, (2) increasing the provisional values of the
whichever is lower. To uphold such a contention would not only interfere parcels of land involved in two (2) of such cases without hearing and
with a judicial function but would also render as useless the protection holding in abeyance the issuance of the writ of possession in favor of
guaranteed by our Constitution in Section 9, Article III of our Constitution petitioner until deposit of the additional amount, (3) requiring the private
that no private property shall be taken for public use without payment of respondents, as defendants in said cases, to state in writing within twenty-
just compensation. four (24) hours whether or not they are amenable to accepting and
withdrawing the amount deposited by petitioner as provisional values in
full and final satisfaction of their respective properties, and directing that
Moreover, the valuation of a property in the tax declaration cannot be an the writ of possession be issued only until after the defendants shall have
absolute substitute to just compensation. Stated differently, the market so manifested in writing their acceptance and receipt of said amounts,
value stated in the tax declaration of the condemned property is no and (4) directing petitioner to release and pay within twenty-four (24)
longer conclusive.42 It is violative of due process to deny to the owner the hours, through the Court and in favor of the defendants, the amount of
opportunity to prove that the valuation in the tax documents is unfair or P43,016,960.00.
wrong. It is also repulsive to the basic concepts of justice and fairness to
allow the haphazard work of a minor bureaucrat or clerk to absolutely
prevail over the judgment of a court which is promulgated only after The antecedents of this case are not controverted.
expert commissioners have actually viewed the property, after evidence,
arguments pro and con have been presented, and after all factors and Petitioner is a government-owned and controlled corporation created and
considerations essential to a fair and just determination have been existing by virtue of Republic Act No. 6395, as amended, for the purpose
judicially evaluated.43 10% of the market value of the expropriated of undertaking the development of hydraulic power, the production of
property cannot in any way be considered as the fair and full equivalent power from any source, particularly by constructing, operating and
to the loss sustained by the owner of the property, such would be 90% maintaining power plants, auxiliary plants, dams, reservoirs, pipes, mains,
less than what is due him. Thus, we are of the conclusion that Section 3A transmission lines, power stations and other works for the purpose of
of [petitioner’s] Charter cannot prevail over the mandate of our developing hydraulic power from any river, creek, lake, spring and
Constitution on the payment of just compensation. The court a quo did waterfall in the Philippines and supplying such power to the inhabitants
not commit an error when it held that the [petitioner’s] charter thereof. In order to carry out these purposes, it is authorized to exercise
encroached on the function of the court in determining just the power of eminent domain.
compensation.44
On 30 March 1990, petitioner filed seven (7) eminent domain cases before
WHEREFORE, premises considered, the instant Petition is the Regional Trial Court of the Sixth Judicial Region in Bacolod City, to wit:
hereby DENIED. The Decision and Resolution of the Court of Appeals in
CA-G.R. CV No. 73656, dated 21 April 2006 and 27 October 2006, (1) Civil Case No. 5938 against Jesus, Fernando, Ma.
respectively, are hereby AFFIRMED. No pronouncement as to costs. Cristina and Michael, all surnamed GONZAGA; 1
NATIONAL POWER CORPORATION, petitioner, (3) Civil Case No. 5940 against Rosario P. Mendoza; 3
vs.
HON. ENRIQUE T. JOCSON, in his capacity as Presiding Judge, (4) Civil Case No. 5941 against Celsoy Agro-Ind.
Regional Trial Court, 6th Judicial Region, Branch 47, Bacolod City; Corporation; 4
JESUS, FERNANDO, MARIA CRISTINA and MICHAEL, all surnamed
GONZAGA; LUIS, DIONISIO, ROBERTO, GABRIEL, BENJAMIN, ANA,
ALEXANDER, CARLA, SOFIA and DANIEL, all surnamed GONZAGA; (5) Civil Case No. 5942 against Emmanuel, Lydia,
ROSARIO P. MENDOZA; CELSOY AGRO-IND. CORP.; EMMANUEL, Harry, Noli, Clifford and Christian, Dale, all surnamed
LYDIA, HARRY, NOLI, CLIFFORD and CHRISTIAN DALE, all surnamed AÑO; 5
AÑO; MAYO L. LACSON; and LUCIA GOSIENFIAO, respondents.
(6) Civil Case No. 5943 against Mayo L. Lacson; 6
Amado B. Parreno Law Office for Gonzaga, et al.
(7) Civil Case No. 5944 against Lucia Gosiengfiao 7
Francisco B. Cruz for R. Mendoza.
for the acquisition of a right-of-way easement over portions of the parcels
Eduardo M. Casiple for Mayo Lacson. of land described in the complaints for its Negros-Panay Interconnection
Project, particularly the Bacolod-Tomonton Transmission Line.
5. After the determination of the amount of . . . to show by documents and otherwise within five
indemnity, the Court authorize the payment by the (5) days from receipt hereof the following:
plaintiff to the defendants; and
CIVIL CASE NO. AFFECTED AREA VALUE CIVIL CASE AFFECTED AREA MARKET PROVISIONAL
(SQ. M.) VALUE (SQ. M.) VALUE
NO.
1. 5938 7,050 P 6,000,000.00
3,000 3,000,000.00 1. 5938 7,050 P 45,000.00 P 180,000.00
6,600 5,000,000.00 3,000 668,700.00 2,674,800.00
2. 5939 23,000 12,600,000.00 6,600 219,830.00 879,320.00
3. 5940 9,030 11,480.00 2. 5939 23,400 757,437.00 3,029,748.00
4. 5941 17,430 1,732,520.00 3 5940 9,030 2,870.00 11,480.00
5. 5942 2,700 1,371,600.00 4. 5941 17,430 433,130.00 1,732,520.00
6. 5943 15,900 8,501,360.00 5. 5942 2,700 342,900.00 1,371,600.00
7. 5944 21,000 4,800,000.00 6. 5943 15,900 2,125,340.00 8,501,360.00
7. 5944 21,000 1,200,000.00 4,800,000.00
and ordering that the writ of possession be issued in these cases after the
defendants "have duly received the amounts." and that:
Unable to accept the above Orders of 25 June, 12 July, 16 July and 18 July . . . in another clear abuse (sic) of discretion, herein
1990, petitioner filed this petition on 24 July 1990 alleging therein, as respondent Judge, on the basis of the respective
grounds for its allowance, that respondent Judge acted in excess of Motion (sic) for Reconsideration of defendants in Civil
jurisdiction, in violation of laws and in dereliction of the duty to afford Cases Nos. 5938 and 5939, without affording the
respondents due process when he issued said Orders. In support thereof herein petitioner an opportunity to be heard, and
petitioner asserts that the Orders of 25 June and 12 July 1990 fixing the with evident and manifest partiality to therein
provisional values at excessive and unconscionable amounts, are utterly defendants increased the previously fixed provisional
scandalous and unreasonable. As classified under their respective tax value of their respective lands, as follows:
declarations, the several lots to be expropriated are sugarlands with the
following assessed values: a. Civil Case No. 5938:
IV. The Action to Enforce the London Awards, Civil Case No. 06-171 3.a. The base valuation of the
NAIA-IPT III
V. The Parties' Positions
3.b. Structural defects on the
A. The Government's Position NAIA-IPT III
4.a. PIATCO's attendant cost 10. The exercise of eminent domain from
the perspective of "taking."
After finding that Paircargo Consortium submitted a bid On May 5, 2003, the Court nullified the PIATCO contracts after
superior to the AEDC's unsolicited proposal and after the finding that Paircargo Consortium (that later incorporated into
AEDC's failure to match the competitive bid, the DOTC PIATCO) was not a duly pre-qualified bidder for failure to meet
awarded, through a notice of award, the NAIA-IPT III project to the minimum equity requirements for the NAIA-IPT III project,
the Paircargo Consortium (that later organized itself as as required under the BOT Law and the Bid Documents. The
PIATCO).7 Court also ruled that Security Bank(member of the Paircargo
Consortium) invested its entire net worth in a single
On July 12, 1997, the Government executed a Concession undertaking or enterprise in gross violation of Section 21-B of
Agreement with PIATCO for the construction, development, and the General Banking Act(which limits a commercial bank's
operation of the NAIA-IPT III under a build-operate-transfer equity investment, whether allied or non-allied, to fifteen
scheme. On November 26, 1998, the Amended and Restated percent (15%) of its net worth).17The Court further found that
Concession Agreement (ARCA) superseded the 1997 the PIATCO contracts contained provisions that substantially
Concession Agreement. The Government and PIATCO likewise departed from the draft Concession Agreement. These
entered into a series of supplemental agreements, namely: the substantial modification of the PIATCO contracts violated the
First Supplement signed on August 27, 1999; the Second public policy for being repugnant to the principle that all
Supplement signed on September 4, 2000; and the Third bidders must be on equal footing during the public bidding.18
Supplement signed on June 22, 2001.8
2. The Motion for Reconsideration and the Resolution dated
Under the 1997 Concession Agreement, the ARCA and the January 21, 2004
Supplemental Agreement (for brevity, PIATCO contracts), the
Government authorized PIATCO to build, operate, and maintain We denied PIATCO, et al.'s motion for reconsideration in our
the NAIA-IPT III during the concession period of twenty-five January 21, 2004 resolution.19 Significantly, we stated in the
(25) years.9 resolution that the Government should first pay PIATCO as a
prerequisite before taking over the NAIA-IPT III, to wit:
3. PIATCO and the Services of Takenaka and Asahikosan
This Court, however, is not unmindful of the reality that the
On March 31, 2000, PIATCO engaged the services of Takenaka, structures comprising the NAIA-IPT III facility are almost
a local branch of a foreign corporation duly organized under complete and that funds have been spent by PIATCO in their
the laws of Japan and doing business in the Philippines, for the construction. For the Government to take over the said facility,
construction of the NAIA-IPT III under an Onshore Construction it has to compensate respondent PIATCO as builder of the said
Contract.10 structures. The compensation must be just and in accordance
with law and equity for the Government cannot unjustly enrich
itself at the expense of PIATCO and its investors.20 (Underlines
On the same date, PIATCO, through an Offshore Procurement and emphases ours)
Contract,11 likewise contracted the services of Asahikosan, a
foreign corporation duly organized under the laws of Japan, for
the design, manufacture, purchase, test and delivery of the C. The Expropriation Case, Civil Case No. 04-087621
Plant12 in the NAIA-IPT III.
On December 21, 2004, the Government filed a complaint for
In May 2002, PIATCO defaulted on its obligation to pay expropriation of the NAIA-IPT III before the RTC of Pasay,
Takenaka and Asahikosan pursuant to their respective Branch 117. The Government informed the RTC that it had
contracts. To settle the problem, Takenaka and Asahikosan deposited with the Land Bank of the Philippines (Land Bank)the
agreed to defer PIATCO's payments until June 2003, amount of ₱3,002,125,000.00, representing the NAIA-IPT III's
conditioned on their receipt of adequate security from PIATCO assessed value.22
as stipulated in the Fourth Supplemental Agreement (relating to
the Onshore Construction Contract)13 and the Fourth On the same day, the RTC issued a writ of possession in favor of
Supplement Agreement (relating to the Offshore Procurement the Government. Citing City of Manila v. Serrano,23 the RTC held
Contract), respectively.14 that that it had the ministerial duty to issue a writ of possession
upon: (1) the filing of the complaint for expropriation sufficient
On November 29, 2002, President Gloria Macapagal Arroyo in form and substance, and (2) the Government's deposit of the
declared in her speech that the Government would not honor amount equivalent to the property's assessed value, pursuant to
the PIATCO contracts. On the same day, Takenaka and Rule 67 of the Rules of Court.24
Asahikosan notified PIATCO that they were suspending the
construction of the NAIA-IPT III for PIATCO's failure to provide On January 4, 2005, the RTC modified its December 21, 2004
adequate security.15 order and directed: (1) the Land Bank to immediately release to
PIATCO the amount of US$62,343,175.7725 that would be
B. The Agan v. PIATCO Case, G.R. No. 155001 deducted from the just compensation; (2) the Government to
submit to the RTC a Certificate of Availability of Funds for the
payment of just compensation; and (3) the Government to
1. The Case and the Decision dated May 5, 2003
maintain and preserve the NAIA-IPT III pending the
expropriation proceedings and the full payment of just
On September 17, 2002, petitioners Demosthenes Agan, et al., compensation. The RTC likewise prohibited the Government
asked the Court to nullify the PIATCO contracts, and to prohibit from performing acts of ownership over the NAIA-IPT III such as
the DOTC and the MIAA from implementing these contracts for
The Government argued that under Section 2, Rule 67 of the DATED this 18th day of February 2005.39
Rules of Court, it shall have the right to a writ of possession
upon deposit with the authorized government depositary of an On the other hand, the dispositive part of the judgment award
amount equivalent to the assessed value of the property for in Claim No. HT-05-269 states:
purposes of taxation, which amount shall be held by the
depositary subject to the orders of the court. In contrast, IT IS ORDERED THAT:
Section 4 of RA 8974, as a rule, requires the Government to
immediately pay the property owner the amount equivalent
to100% of the value of the property based on the BIR's relevant 1. Judgment be entered for the First Claimant in the
zonal valuation and the value of the improvements/and or sum of 21,688,012.18 United States dollars, together
structures, upon the filing of the complaint and after due notice with interest in the sum of 6,052,805.83 United States
to the defendant. dollars.
On January 7, 2005, the RTC appointed three 2. Judgment be entered for the Second Claimant in
Commissioners28 to determine just compensation without the sum of 30,319,284.36 United States dollars,
consulting the Government and PIATCO.29 Due to these together with interest in the sum of 5,442,628.26
successive adverse rulings, the Government sought to inhibit United States dollars.
Judge Henrick F. Gingoyon, the RTC's presiding judge, from
hearing the case.30 (The judge was ambushed and killed on 3. The defendant to pay the Claimants' costs in the
December 31, 2005.)31 action, to be subject to detailed assessment if not
agreed.
On January 10, 2005, the RTC denied the Government's urgent
motion for reconsideration and motion for inhibition.32 DATED this 2 (sic) day of December 2005.40
On December 14, 2005, Asahikosan filed a motion for leave to Takenaka and Asahikosan asked the RTC to: (a) hold in
intervene in Civil Case No. 04-0876 (the expropriation abeyance the release of just compensation to PIATCO until the
case).33 On the other hand, Takenaka filed a Manifestation London awards are recognized and enforced in the Philippines;
dated December 15, 2005,34 with the attached Manifestation and (b) order that the just compensation be deposited with the
and Motion dated December 14, 2005.35 Takenaka alleged that RTC for the benefit of PIATCO's creditors.41
the Government impleaded it as an additional defendant in an
amended complaint for expropriation of the NAIA-IPT III, but During the hearing of the motions, the Government clarified
was not served summons. Takenaka thus manifested its that it neither filed an amended complaint for expropriation nor
voluntary appearance before the RTC.36 impleaded Takenaka as a necessary party in the case.42
Takenaka and Asahikosan informed the RTC that they had The RTC initially denied Takenaka and Asahikosan's respective
previously filed two collection cases against PIATCO, docketed Motions43 in the August 8, 2006 Order, but subsequently
as Claim Nos. HT-04-248 and HT-05-269, before the High Court reconsidered its ruling.44 In a March 12, 2007 Order, the RTC
of Justice, Queen's Bench Division, Technology and treated Takenaka's Manifestation with the attached
Construction Court in London, England, (London Court) on Manifestation and Motion as a motion to intervene and allowed
August 9, 2004. Takenaka and Asahikosan to intervene in the case as PIATCO's
creditors.45
In both instances, the London Court ruled in their favor. The
dispositive part of the judgment award in Claim No. HT-04-248 Pending the RTC's resolution of Takenaka and Asahikosan's
provides: motions for leave to intervene in the expropriation case, the
Government went directly to the Court seeking Judge
IT IS ORDERED THAT: Gingoyon's inhibition from the case; the nullification of the
order of release of the sum of $62.3 million to PIATCO; and the
1. Judgment be entered for the First Claimant37 in the nullification as well of the appointment of the commissioners.
sum of 6,602,971.00 United States dollars, together
with interest in the sum of 116,825,365.34 Philippine D. The Republic v. Gingoyon Case, G.R. No. 166429
pesos up to and including 18 February 2005.
1. The Case and the Decision dated December 19, 2005
2. Judgment be entered for the Second Claimant38 in
the sum of 8,224,236.00 United States dollars,
ProvRem Rule 67 Fulltext Page 25 of 119
On January 12, 2005, the Government, et al., filed a infrastructure project is of utmost urgency and
petition for certiorari with the Court assailing the importance and if there is no existing valuation of the
validity of the January 4, 7, and 10, 2005 orders of the property, the implementing agency shall immediately
RTC in the expropriation case.46 The case, entitled pay the proffered value of the property.49
Republic v. Gingoyon, was docketed as G.R. No.
166429. We thus observed that Section 2, Rule 67 of the Rules
of Court is contrary to our January 21, 2004
The Government argued that the RTC should not Resolution which required the Government to make
have ordered the release of $62.3 Million since the prior payment of just compensation to PIATCO
NAIA-IPT III's assessed value was only ₱3 billion. before it could take over the NAIA-IPT III.
Moreover, the RTC's prohibition against the
Government to perform acts of ownership on the The Court at the same time qualified the applicability
NAIA-IPT III was contrary to the essence of a writ of of RA 8974 to the expropriation of the NAIA-IPT III.
possession. It47 asserted that Rule 67 of the Rules of We held that the Congress may legislate on the
Court governed the expropriation of the NAIA-IPT III valuation standards of just compensation and the
since it was not a national government infrastructure manner of its payment since these are substantive
project. The Government likewise contended that the matters. We made clear, however, that the Congress
commissioners' appointment was void. It claimed that cannot legislate on the procedural aspects of
it had been deprived of due process since it was not expropriation since this power lies with the Court. In
given the opportunity to contest the appointment of fact, Section 14 of RA 8974 IRR provides that Rule 67
the commissioners. The Government likewise sought of the Rules of Court shall apply to "all matters
Judge Gingoyon's inhibition from the case due to his regarding defenses and objections to the complaint,
alleged manifest partiality to PIATCO.48 issues on uncertain ownership and conflicting claims,
effects of appeal on the rights of the parties, and
The Court partly granted the petition and rendered such other incidents affecting the complaint."
the following rulings:
Third, we held in abeyance the implementation of the
First, under the 2004 Resolution in Agan: (a) PIATCO writ of possession until the Government directly pays
must receive payment of just compensation to PIATCO the proffered value of ₱3 billion. The zonal
determined in accordance with law and equity; and valuation method under Section 4 of RA 8974 shall
(b) the Government is barred from taking over the not apply since the Government owns the land on
NAIA-IPT III until just compensation is paid. which the NAIA-IPT III stands. Consequently, PIATCO
should only be paid the value of the improvements
Second, RA 8974 applies in the expropriation case and/or structures using the replacement cost
insofar as the law: (a) requires the Government to method.50 Pending the determination of just
immediately pay PIATCO at least the proffered value compensation, the Government shall pay the sum of
of the NAIA-IPT III; and (b) provides valuation ₱3 billion as the provisional amount of just
standards in determining the amount of just compensation because there was no expedited
compensation. means by which the Government could immediately
take possession of the NAIA-IPT III.
On April 11, 2006, the RTC ordered the BOC to resume its
duties. In compliance, the BOC submitted its Inception Report On May 18, 2007, the RTC directed the Government to submit a
and Inception Framework to the RTC. On April 24, 2007, the Certificate of Availability of Funds to cover DG Jones and
parties and the BOC conferred to set the ground rules and Partners' $1.9 Million appraisal fee.66
procedure in determining the just compensation due to the
NAIA-IPT III. The Government sought the reconsideration of the May 3 and
18, 2007 orders. The Government complained that the
On April 26, 2006, the Government asked the RTC to stop the appointment of an appraiser apart from those hired by the
payment of ₱3 billion proffered value in view of an alleged Government would result in the unnecessary depletion of its
supervening event - the collapse of the ceiling of the arrival funds since it would be compelled to pay two appraisers.67
lobby section of the north side of the NAIA-IPT III on March 27,
2006. The Government claimed that the collapse created a 100- In response, PIATCO argued that the RTC has the inherent
square foot hole in the ceiling and caused heavy asbestos pipes power to appoint an independent appraiser pursuant to Section
to fall on the floor of the NAIA-IPT III. The Government likewise 5 (g), Rule 135 of the Rules of Court. The RTC has wide
informed the Court that the MIAA requested the Association of discretion on how it shall carry its mandate under RA 8974 and
Structural Engineers of the Philippines (ASEP)to investigate the Rule67 of the Rules of Court.68
cause of the collapse.57 In its Final Report dated June2006, the
ASEP identified the following factors that contributed to the In an order dated January 7, 2008, the RTC sustained the
collapse: appointment of DG Jones and Partners. The RTC ruled that its
power to appoint the members of the BOC under Section 5,
a. Incomplete design coordination as shown by the Rule 67 of the Rules of Court includes the power to appoint an
absence of detailed shop drawings during the independent appraiser.69
construction, an absence described as "unusual" for a
BOT project of this size The Government directly challenged before the Court the May
3, May 18, and January 7, 2008 orders in a petition for certiorari
b. Wrong choice of ceiling and wall components and with prayer for the issuance of a temporary restraining order
fixing materials, e.g., use of rivets instead of clips, and/or a writ of preliminary injunction. The case was docketed
screws or wire; use of furring channels instead of as G.R. No. 181892.70
stronger C channels; use of wall angles thinner than
required; and On January 9, 2008, the Court issued a temporary restraining
order against the implementation of the May 3 and 18, 2007
c. Poor workmanship, e.g., uneven distribution and Orders as well as the January 7, 2008 Order.71
improper attachment of rivets, lack of ceiling
supports in the presence of mechanical fixtures.58 2. The BOC's Expenses
The ASEP concluded that the likely cause of the collapse was On June 15, 2006, the BOC filed a request for the release of a
the "syncretic effect of all these factors working over time since mobilization fund of ₱1,600,000.00 to support the discharge of
the construction of the ceiling."59 its functions.72 The RTC approved the request and directed the
Government and PIATCO to equally share the BOC's
Upon the BOC's request,60 on May 5, 2006, the RTC ordered the expenses.73 The Government and PIATCO complied with this
engagement of the services of an internationally accepted order and tendered the sum of ₱1,600,000.00 to the BOC.74
independent appraiser who shall conduct the valuation of the
NAIA-IPT III.61 On November 24, 2009, the BOC requested additional funds in
the amount of ₱5,250,000.00.75 On December 7, 2010, the RTC
On May 23, 2006, the Government manifested that it engaged directed the Government and PIATCO to equally defray the
the services of: (a) TCGI Engineer to determine the structural BOC's expenses.76 The Government contested this order and
ProvRem Rule 67 Fulltext Page 28 of 119
insisted that Takenaka and Asahikosan should likewise shoulder
Deductions $USD
the BOC's expenses as intervenors in the case.77
In an order dated March 11, 2011,the RTC ordered Takenaka Total CCVs $USD $186,262,649 $149,448,037
and Asahikosan to share in the BOC's expenses. The RTC thus
ordered each party to pay ₱1,750,000.00. PIATCO complied with
this order and paid the amount of ₱1,750,000.00 to the BOC.78
▪ $300,206,693.00 as base current cost
Takenaka and Asahikosan sought the partial reconsideration of valuation(CCV). Based on the Gleeds report, the
this order.1âwphi1 They argued that they should not be made construction cost of the NAIA-IPT III as of December
to pay the BOC's expenses since "their prayer to defer the 2002 was $300,206,693.00, consisting of the cost of
release of a portion of the just compensation pending the constructing the terminal building, aprons, car park,
conclusion of the enforcement proceedings was addressed to elevated roadways, and other related items.
the RTC [,] and not to the BOC."79
Gleeds appraised the NAIA-IPT III by "multiplying the
F. The Parties and the BOC's Appraisal of the NAIA-IPT III structure's dimensions (i.e., quantities) by a price (i.e.,
rate) for constructing the works at a designated time
and specific location, adding the cost of works in, on,
After the Court issued the January 9, 2008 temporary restraining
and around the structure, and then accounting for
order, the parties and the BOC conducted a preliminary conference on
inferior and nonperforming works, and rectification of
April 22, 2010, to adopt an alternative course of action to avoid further
those works."84
delay in the determination of just compensation.80
Not compliant with bid -$30,670,894 -$30,670,894 4. The cost of seismic and gravity load
documents structural retrofits for the failed elements in
the terminal buildings and multi-storey car
Inferior quality -$7,702,640 -$7,702,640 park structures, as those retrofits are
described in Arup's Drawings listed in
Additional areas to be built -$75,570,510 -$75,570,510 Appendix 'B' Drawing List 2 and other
(63,490m2) rectification works required to bring the
terminal to compliance with applicable
building and airport codes (as indicated in
Total Contract Compliance -$113,944,044 -$113,944,044
6. The cost of seismic and gravity load Construction Insurance 4,329,272 1.0971 4,749,644
structural retrofits for the failed elements in
the elevated roadway structures as those Site Development 8,358,169 1.0971 9,169,747
retrofits were described in Arup's Drawings
Other Costs 308,985 1.0971 338,987
listed in Appendix 'B' Drawing List 3, Arup
Review on 'TCGI Report of Civil Design
Attendant Costs exclusive of 43,594,911 1.0971 47,827,977
Review and Evaluation' - Elevated
Financing Costs
Roadway, dated March 2009, and other
rectification works required to bring the Financing Costs 26,602,890 26,602,890
elevated roadways to compliance with
applicable building and airport codes (as Total Attendant Costs 70,197,802 74,430,868
indicated in the Appendices of Arup's Site
Observation Report).86 TOTAL 431,167,593 470,450,825
▪ $113,944,044 as total contract compliance Interest from 12 Sept 2006 to 31 Dec 2010 331,402,193
deductions. The Government further deducted items
which were non-compliant with bid documents, Total Interests 435,416,724
including, among others:
Total Replacement Value 905,867,550
a. FIDS monitors not flat screen Less: Payment on 11 Sept 2006 59,438,604
Interests
The Government likewise deducted the replacement
cost of inferior quality items and additional areas that From December 21 12% 11 1,724,986
the Government had to build to finish the NAIA-IPT takeover to December
III project.87 of NAIA T3 31, 2004
on
2. PIATCO's Appraisal 21 Dec 2004
Replacement 470,450,825
Cost On the other hand, Takenaka and Asahikosan,
computed the NAIAIPT III's replacement cost as
Total Interests 435,416,724 follows:
(1+2)
TOTAL 905,867,550
AMOUNT OF
Total payments of PIATCO
REPLACEMENT
Add: Awards by the London Court
VALUE
Award by the Makati Court
Total Construction Cost
▪ $360,969,791 as base value. PIATCO adopted
Takenaka and Asahikosan's actual construction cost ▪ $360,969,790.82 as total construction cost. Takenaka
of $360,969,791 which is supported by As-Built and Asahikosan claimed that the initial contract price
Drawings and Bills of Quantities. PIATCO stated that for the construction of the NAIA-IPT III was
the Japanese Airport Consultants (JAC), the quality $323,753,238.11.
assurance inspector for the NAIA-IPT III project,
validated the works of Takenaka and Asahikosan.
PIATCO alleged that the Government and PIATCO Thereafter, changes were made in the course of the
entered into a Quality Assurance Agreement with construction that increased its construction contract
JAC.88 price. Pursuant to the Onshore Construction and
Offshore Procurement Contracts, PIATCO paid
Takenaka and Asahikosan the amounts of
▪ Attendant costs. Under RA 6957 IRR, the $231,312,441.28 and ₱1,796,102,030.84 (a total of
replacement cost includes the "overhead and all $275,119,807.88).
other attendant costs associated with the acquisition
and installation in place of the affected
After PIATCO defaulted on its payments, Takenaka
improvements/structures." The items under the
attendant costs correspond to these "overhead and and Asahikosan instituted Claim Nos. HT-04-248 and
other attendant costs" which are necessary to HT-05-269 in England. The London court ruled in
construct an airport project.89 their favor and awarded them the amounts of
$81,277,502.50, ₱116,825,365.34 and £65,000.00 or a
total of $ 84,035,974.44. Thereafter, they filed an
It is necessary to hire quality assurance surveyors to action to enforce Claim Nos. HT-04-248 and HT-05-
check and monitor the work of Takenaka. PIATCO 269 before the RTC of Makati which awarded them
hired Pacific Consultants, Inc. as construction the sum of $1,814,008.50.97
supervisor in the NAIA-IPT III project. PIATCO claimed
that the planning and design consultancy fees are
4. The BOC's Appraisal
even below the international norms which are in the
Amount paid by PIATCO to Takenaka and Asahikosan 275,119,807.88 II. The RTC Rulings in Civil Case No. 04-0876
Add:
Award in Claim No. HT-04-248 Relating to the 14,827,207.0098 A. The Main Decision
Construction Cost of NAIA-IPT III
Award in Claim No. HT-05-269 Relating to the
In a decision dated May 23, 2011, the RTC directed the Government,
Construction Cost of NAIA-IPT III 52,007,296.5499
Takenaka, and Asahikosan to pay the commissioners' fees in the amount
Construction Cost of NAIA-IPT III 341,954,311.42
of ₱1,750,000.00 each; and ordered the Government to pay PIATCO just
Add:
compensation in the amount of $116,348,641.10. In determining the
Attendant Cost (10% of the Construction Cost) 34,195,431.14
amount of just compensation, the RTC adopted the following
Replacement Cost of NAIA-IPT III 376,149,742.56 computation:
IN THE LIGHT OF THE FOREGOING, Plaintiffs are hereby 8.2. The claimant(s) shall have been held to have
ordered to pay respondent PIATCO the amount of accepted or otherwise become subject to the
US$175,787,245.10 less the proffered value (₱3,002,125,000.00) jurisdiction of the expropriation court and other
actually paid to and received by defendant, as the just relevant courts of the Republic of the Philippines, by
compensation for the improvements of NAIA-IPT III. Moreover, reason of or in connection with the expropriation of
both plaintiff Republic and intervenors Takenaka and NAIA Terminal 3 by the ROP, directly or indirectly;
Asahikosan Corporations are directed to pay their
proportionate shares of the Commissioners' Fees in the amount 8.3. The claimant(s) shall have executed a valid and
of ₱1,750,000.00 each with dispatch. effective quitclaim in favor of the Republic of the
Philippines acknowledging that claimant(s) against
Finally, insofar as both intervenors Takenaka and Asahikosan the ROP or any agency or instrumentality or
Corporations are concerned, resolution of their claim before corporation of the ROP, by reason of, or in
this Court is held in abeyance owing to the pendency of the connection with, the expropriation of NAIA Terminal
outcome of the appeal on certiorari before the CA, and in any 3 by the ROP, directly or indirectly, in any capacity
of their claims, as contractors are solely as against defendant whatsoever;
PIATCO.
8.4. The claimant(s) has complied within good faith
SO ORDERED.101 any condition or undertaking required from
it/him/her by the expropriation court by reason of or
PIATCO, Takenaka, and Asahikosan immediately appealed the in connection with the expropriation of NAIA
RTC's decision before the CA while the Government opted to Terminal 3 by the ROP, directly or indirectly, in any
seek partial reconsideration of the attendant costs awarded to capacity whatsoever.107
PIATCO.102
The Government thus prayed:
PIATCO, Takenaka, and Asahikosan sought to nullify the RTC
decision for alleged violation of their right to due process. They 1. Pending determination of the entitled claimants, to
complained that they were only furnished copies of the BOC allow the Government to deposit just compensation
Final Report only after the promulgation of the May 23, 2011 less the proffered value in an escrow account with a
decision.103 They averred that the RTC violated Sections 7 and 8, reputable bank whose senior unsecured obligations
Rule 67 of the Rules of Court which provide that the clerk of are rated at least 'BBB' by Standard and Poor's
court shall serve copies of the commissioners' report on all Investors Service, Inc.or 'Baa2' by Moody's Service
interested parties, with notice that they be allowed ten days Investors Service, Inc. to be designated by the RTC;
within which to file objections to the findings of the report, if
they so desire.104 2. After depositing the amount in an escrow account,
to confirm the Government's right to fully exercise
The Government subsequently partially appealed the case to any and all acts of ownership over the NAIA-IPT III;
the CA after the RTC denied its motion for partial and
reconsideration.105
3. To order the release of just compensation, or of
B. The RTC's Interlocutory Order on the Validity of the Escrow Accounts any portion thereof from the escrow account to the
ProvRem Rule 67 Fulltext Page 33 of 119
entitled claimants provided that the entitled case for the sole purpose of determining the amount of just
claimants have fully complied with all the conditions compensation to be paid to PIATCO.
and requirements set forth under paragraphs 8.1 to
8.4 of the Manifestation and Motion.108 Moreover, the Government did not raise the alleged dispute in
the ownership of the NAIA-IPT III during the expropriation
PIATCO opposed the Manifestation and Motion and argued proceedings. The RTC stated that it could not take judicial
that the Government could not vary the terms of the May 23, notice of the allegation that PIATCO was indebted to various
2011 Decision as well as the Court's rulings in Agan and creditors, apart from Takenaka and Asahikosan, since these
Gingoyon commanding the Government to make a direct alleged creditors were not impleaded in the expropriation
payment of just compensation to PIATCO. It insisted that the complaint.
offer to pay through an escrow account is not equivalent to
direct payment. PIATCO further denied the Government's The RTC likewise observed that compliance with the
allegations that there were several claimants on the just Government's conditions under 8.1 and 8.3 for the release of
compensation.109 just compensation from the escrow account pending appeal
was legally impossible. For this reason, the payment through an
On the other hand, Takenaka and Asahikosan agreed with the escrow account was not the payment that would transfer the
Government that just compensation should only be paid to title of the NAIA-IPT III to the Government.
entitled claimants. They posited that the Court's directive in
Agan (with respect to the direct payment to PIATCO) was The RTC lastly ruled that the payment of just compensation
premised on the erroneous assumption that PIATCO was the through an escrow account shall be payment of just
builder of the NAIA-IPT III. Takenaka and Asahikosan insisted compensation within a reasonable time. Consequently, the
that they were the actual builders of the NAIA-IPT III. Government may exercise full rights of ownership over the
Nonetheless, they contended that the RTC had no jurisdiction NAIA-IPT III upon the creation of an escrow account.111
over the Manifestation and Motion because the parties already
filed their respective Notices of Appeal before the CA.110
The dispositive portion of this order provides:
Design 6,439,680
In a decision dated August 7, 2013,115 the CA upheld the validity of the Staff and labour 10,491,139.54
RTC's May 23, 2011 decision. The CA ruled that the parties did not need Insurance 925,210.78
to be furnished the BOC Final Report since RA 8974 is silent on the PI Insurance 2,200,000.00
appointment of the BOC, as held in Gingoyon. Consequential Loss 800,000.00
Setting out 364,647.00
However, the CA modified the RTC rulings and arrived at its own formula Health and safety 403,224.00
of the NAIA-IPT III's replacement cost, to wit: Enviro Management 176,490.00
Design 2,631,100.00
Staff and labour 2,590,774.19
Construction Cost
Insurance 71,109.77
Add:Attendant Cost
= Replacement Cost total 25,293,376.28117
Add: Equity
Just Compensation
The CA likewise observed that PIATCO's summarized
Substituting: computation of attendant costs was self-serving and
unsubstantiated by relevant evidence. On the other hand, the
BOC and the RTC's computation of attendant costs at 10% of
Replacement Cost = $300,206,693.00 + 0 (because the construction cost lacked factual and legal support. Pegging
attendant cost already imputed in attendant costs at 10% of the construction cost was only
construction cost) relevant during the pre-construction stage since the costs of
the construction at that time could only be estimated. This
= $300,206,693.00 + 6% interest from estimate carried no relevance at the post-construction stage
December 21, 2004 to September 11, since the total construction costs, including the attendant costs,
2006 less $59,438,604.00 + 6% could already be determined.
interest from September 12, 2006
until finality of judgment ▪ Depreciation, costs for noncompliance with contract
specifications, and unnecessary areas of NAIA-IPT III shall not
be deducted from the replacement cost. The CA reversed the
In US dollars RTC's finding that the NAIA-IPT III suffered from massive
Interest from September 13, 2012 12,744,214.89 The CA likewise denied the Government's, PIATCO's,
Takenaka's, and Asahikosan's motions for partial
to July 31, 2013
reconsideration in a resolution dated October 29, 2013.121
$240,768,035*6%*322 days/365
days
The CA's denial of their motions cleared the way for the
Total Interest as of July 31, 130,658,653.24 elevation of CA-G.R. CV No. 98029 to this Court through a
2013 petition for review on certiorari. The Government, PIATCO, and
Takenaka and Asahikosan's consolidated petitions are docketed
as G.R. Nos. 209917, 209731, and 209696, respectively.
The CA further ordered Takenaka and Asahikosan to share in
the expenses of the BOC. Since Takenaka and Asahikosan's
inputs on the construction costs of the NAIA-IPT III were heard B. CA-G.R. SP No. 123221
by the RTC, they should share in the expenses of the BOC.
In a decision dated October 18, 2014,the CA reversed the Omnibus Order
The CA likewise denied Takenaka and Asahikosan's prayer to dated October 11, 2011, for having been issued with grave abuse of
set aside in an escrow account a portion ofthe just discretion. The dispositive portion of the decision states:
compensation corresponding to the amounts owed them by
PIATCO. RA 8974 expressly provides that the Government shall WHEREFORE, in view of the foregoing, the instant Petition is Hereby
directly pay the property owner upon the filing of the complaint GRANTED. Parenthetically, the Omnibus Order dated 11 October 2011
as a prerequisite to the issuance of a writ of possession. and Order dated 5 December 2011 of the Pasay City RTC, Branch 117, in
On February 27, 2006, Takenaka and Asahikosan filed an action to enforce G.R. No. 209917
the London awards in Claim Nos. HT-04-248 and HT-05-269 before the
RTC of Makati, Branch143. The case was docketed as Civil Case No. 06- In G.R. No. 209917, the Government asks the Court to partially reverse the
171.123 CA rulings and to deduct from the replacement cost of
US$300,206,693.00the following items: (a) depreciation in the amount of
In a decision dated September 6, 2010, the RTC recognized the validity of US$36,814,612.00; and (b) PIATCO's non-compliance with contract
the London awards in Claim Nos. HT-04-248 and HT-05-269 and declared specifications in the amount of US$113,944,044.00. The Government also
these awards as enforceable in the Philippine jurisdiction. The RTC thus refutes the CA's imposition of a legal interest on just compensation.
ordered PIATCO to pay Takenaka and Asahikosan the sum of $85.7
million.124 The Government asserts that the CA did not consider equity in computing
the replacement cost of the NAIA-IPT III. Contrary to the Court's
PIATCO appealed the case to the CA125 which affirmed the RTC rulings in a pronouncement in Gingoyon, the CA computed just compensation based
decision dated March 13, 2012.126 The CA likewise denied PIATCO's solely on RA 8974 and its IRR. The CCV of $300,206,639.00 only reflects
motion for reconsideration in a resolution dated May 31, 2012.127 the valuation of the NAIA-IPTIII as of November 2002 when PIATCO
stopped the construction of the terminal, and did not take into account
PIATCO responded by filing a petition for review on certiorari with this other factors that lowered its valuation as of December 2004.
Court assailing the CA's ruling. The case was docketed as G.R. No.
202166and is still pending before the Court separately from the present The Government posits that there are two standards in measuring the
petitions. replacement cost. The implementing rules of RA 8974 failed to provide a
complete formula to arrive at the replacement cost of an expropriated
To summarize, the cases pending before the Court are the consolidated property.
cases: G.R. Nos. 209917, 209696, 209731,and 181892, and G.R. No. 202166
as a separate case. The first and common standard is the depreciated replacement cost
method which measures the cost of replacing an asset at current prices
G.R. No. 209917 is the Government's petition for review on Certiorari128 to but in its actual condition, i.e., adjusted for age, wear and tear. The
partially reverse the CA's August 22, 2013 Amended Decision129 and its Chartered Institute of Public Finance and Accounting defines depreciated
October 29, 2013 Resolution130 in CA-G.R. CV No. 98029. replacement cost as "a method of valuation which provides the current
cost of replacing an asset with its modern equivalent asset less
deductions for all physical deterioration and all relevant forms of
G.R. No. 209696 is a petition for review on certiorari filed by Takenaka and obsolescence and optimization" and as "the replacement value of
Asahikosan to partially reverse the CA's August 22, 2013 Amended property minus physical depreciation and obsolescence; insurance
Decision and its October 29, 2013 Resolution in CA-G.R. CV No. 98029.131
adjusters estimate the actual cash value of property based on its
depreciated replacement cost."138
G.R. No. 209731 is PIATCO's petition for review on certiorari to reverse the
CA's August 22, 2013 Amended Decision, and October 29, 2013 In other words, depreciated replacement cost adjusts the cost of replacing
Resolution in CA-G.R. CV No. 98029.132 G.R. Nos. 209917, 209696 & the actual asset in accordance with the asset's age in order to take into
209731 originally arose from the Government's complaint for account the lower economic utility of an asset that is not brand new. As
expropriation of the NAIA-IPT III filed with the RTC of Pasay, Branch117 in an asset ages, higher economic cost is required to maintain that asset to
Civil Case No. 04-0876. The main issue before the Court in these petitions the level of utility of a brand new one.
is the valuation of the just compensation due for the Government's
expropriation of the NAIA-IPT III.
The second and less common standard is the new replacement cost
method which measures the cost of replacing an asset at current prices
G.R. No. 181892 is the Government's petition for certiorari with prayer for with no adjustment for age, wear, and tear. It refers to "the cost to replace
the issuance of a temporary restraining order,133 assailing the May 3, 2007, damaged property with like property of the same functional utility
May 18, 2008;and January 7, 2008 orders of the RTC of Pasay City, Branch without regard to depreciation (physical wear and tear) and
117 in Civil Case No. 04-0876.134 obsolescence."139
This petition likewise arose from the Government's complaint for The Government asks the Court to adopt the depreciated replacement
expropriation of the NAIA-IPT III. The main issue in this petition is the cost method where depreciation is deducted from the replacement cost.
propriety of the appointment of DG Jones and Partners as an The Government asserts that it is an internationally accepted practice to
independent appraiser of the NAIA-IPT III.1âwphi1
consider depreciation and other forms of obsolescence and optimization
in measuring the replacement cost of an asset.
G.R. No. 202166 is PIATCO's petition for review on certiorari135 to assail
the CA's March 13, 2012 decision136 and May 31, 2012 Resolution137 in CA- The Government argues that the new replacement cost method usually
G.R. CV No. 96502. The petition arose from Takenaka and Asahikosan's applies in cases where the property must be rebuilt. For example, an
action to enforce the London awards before the RTC of Makati, Branch insurance policy for a house would usually use the new replacement cost
143 in Civil Case No. 06-171. As previously mentioned, this case was not method because a house, which was destroyed by fire or other natural
disaster, must be rebuilt. On the other hand, an insurance policy for an
ProvRem Rule 67 Fulltext Page 37 of 119
automobile would use the depreciated replacement cost because it Section 3.3.37. As far as the building structure is concerned the
presupposes that a new automobile must be purchased to replace the old outstanding issues are the Taking Over Inspection Defects List,
automobile that suffered from wear and tear. outstanding Quality Observation Report issues and the Non-Compliance
Schedule x x x.142
The Government disputes the CA's opinion that the replacement cost
cannot be lower than the actual construction because market prices tend (c) The ASEP made the following observation in its
to move upward over time. The Government contends that the June 23, 2006 Report:
replacement cost may be lower than the construction cost if the price of
the materials such as steel, cement, and copper used during the ● Results of material tests carried out
construction stage decreases after the construction of the improvement. identified that the materials used were
Moreover, labor productivity and technological advancements affect the adequate and meet or exceed the ER
replacement cost since these counterbalance inflation. The depreciated specification. However, the thickness of the
replacement cost method is utilized "in setting user rates for public wall angle used (0.4 mm) does not meet
utilities precisely because this standard of value will tend to result in lower the minimum plate thickness for metals to
prices over time, not higher prices."140 be fastened by power-actuated anchors,
which requires a minimum of 0.6 mm (Hilti
The Government likewise disagrees with the CA that the depreciation Catalogue). ASEP recommended further
adjustment "would irrationally result in[a] book value which continues to tests.
be lower and lower over time." Since an asset must be maintained, the
cost of performing maintenance and repairs increases the asset's ● ASEP considered that the quality of
replacement cost. Consequently, repairs and maintenance cost counter- workmanship of the installation is not
balance depreciation. The recognition that an asset depreciates impliedly considered to be within minimum
acknowledges that the owner will spend more costs in maintaining the acceptable practice.
asset's utility than on a brand new asset.
The Government maintains that the imposition of legal interest on just The Government contends that Takenaka and Asahikosan's computations
compensation is erroneous. of actual construction cost of the NAIA-IPT III are conflicting.
First, the present expropriation case is sui generis. The Government was In their Manifestation dated December 9, 2010, Takenaka and Asahikosan
forced to expropriate the NAIA-IPT III due to PIATCO's violation of the stated that the actual construction cost amounted to $360,969,790.82.
Constitution and the law. To award legal interest to PIATCO is to condone However, in his report, Mr. Gary Taylor appraised the actual construction
its illegal acts. In Hulst v. PR Builders, Inc.,147 the Court held that the cost at US$323 million, "plus other costs that were incurred by various
illegality should not be rewarded. In Valderama v. Macalde,148 the Court parties during its conception and construction plus any property
deleted the payment of interest on the ground that a person should not appreciation."153 Mr. Gary Taylor further stated that the "true value of the
be allowed to profit from an illegal act. As between two parties, he who, NAIA-IPT III facility is nearer to US$408 million, given the fact that the
by his acts, caused the loss shall bear the same. He, who comes to court Republic's expert, Gleeds, failed to recognize or include any values for
for equity must do so with clean hands. [the] design and other consultants (10%) or property inflation based on
GRP schedules (15%)."154 However, Mr. Taylor did not explain how he
Second, PIATCO itself caused the delay of the expropriation proceedings arrived at the amount of $408 million.
before the RTC. PIATCO did not produce the vouchers, purchase orders,
and as-built documents which were in its possession despite the The Government adds that Takenaka and Asahikosan's actual construction
Government's filing of a Motion for Production and Inspection of cost of $360,969,790.82 is erroneous as the London and Makati awards
Documents dated May 25,2006, before the RTC.149 include interests, attorney's fees and costs of litigation. Furthermore,
Takenaka and Asahikosan's "as-built" drawings are not truly "as-built."
Third, in Eastern Shipping Lines v. CA,150 the Court pronounced that The drawings do not reflect the quality and exact detail of the built
unliquidated claims are not subject to legal interest, such as the present portions of the NAIA-IPT III.155
case.
G.R. No. 209731
Fourth, the law and jurisprudence on the imposition of interest does not
address the peculiar situation where the NAIA-IPT III is being expropriated The Government disputes PIATCO's claim that it was denied due process
as a direct result of the nullification of the PIATCO contracts. The when it was not furnished a copy of the Final Report. The Government
application of the law and jurisprudence on the imposition of interest points out that all the parties in the case were not given a copy of the
would not result in a fair and equitable judgment for the Government. The Final Report. Furthermore, PIATCO belatedly raised this issue; it was
Court must apply equity in the absence of a specific law applicable in a brought for the first time on appeal before this Court.
particular case or when the remedy afforded by the law would be
inadequate to address the injury suffered by a party.
The Government also emphasizes that PIATCO immediately filed a notice
of appeal a day after its receipt of the RTC decision. This is contrary to
The Government additionally complains that, since November 2002, "long PIATCO's claim that it wanted to secure a copy of the Final Report and
before the institution of the expropriation [complaint] in December 2004," subject it to clarificatory hearing.
Takenaka and Asahikosan prevented it from entering the NAIA-IPT III.151
Even assuming that the RTC erred in not furnishing the parties copies of
G.R. No. 209696 the Final Report, the lapse is merely an "innocuous" technicality that
should not nullify the RTC rulings.
The Government alleges that it is willing to pay just compensation to the
lawful claimant. However, just compensation should not be set aside in The Government claims that PIATCO failed to substantiate the attendant
favor of Takenaka and Asahikosan since their claim against PIATCO has costs. The documents attached to the Compliance dated December 14,
not yet been resolved with finality. 2010, are mostly summary of payments that PIATCO allegedly paid to the
consultants. However, PIATCO failed to prove that the alleged consultants
The Government disputes the applicability of Calvo v. Zandueta152 in the rendered actual service related to the construction of the NAIAIPT III.
present case. In that case, the Court allowed Juana Ordoñez to be Reyes Tacandong & Co. merely verified the mathematical accuracy of the
subrogated to Aquilino Calvo as defendant because Ordoñez obtained a schedules, including the computation of the inflation rate. Furthermore,
final judgment in her favor which entitled her to levy the land sought to the receipts that PIATCO submitted are not enough to cover its claimed
be expropriated. Furthermore, Ordoñez was not a party to the just compensation.156
expropriation case.
ProvRem Rule 67 Fulltext Page 39 of 119
G.R. No. 181892 documents and confirmed that the attendant costs amount to
$70,197,802.00 in its Report of Factual Findings dated December 14, 2010.
The Government disputes the RTC's appointment of an independent
appraiser of the NAIA-IPT III. It claims that Section 11 of RA 8974 IRR PIATCO asserts that its submission of the summary computation is
solely authorizes the implementing agency to engage the services of an justified under Section 3 (c), Rule 130 of the Rules of Court which allows
appraiser in the valuation of the expropriated property, while under the party to submit non-original copies if the original consist of numerous
Section 10 of RA 8974 IRR, it is the implementing agency that shall accounts or other documents that the court cannot examine without
determine the valuation of the improvements and/or structures on the great loss of time; the fact sought to be established from these, after all, is
land to be acquired using the replacement cost method. Pursuant to only the general result of the whole.
these provisions, the Government engaged the services of Gleeds, Ove
Arup and Gensler for purposes of appraising the NAIA-IPT III. PIATCO likewise argues that the total construction cost of
$431,167,593.00 - which is the sum of $360,969,791.00 and
The Government also argues that the appointment of an independent $70,197,802.00 - should be converted to 2004 values since the reckoning
appraiser would only duplicate the efforts of the existing appraisers. A period of just compensation is the date of taking or the date when the
court appointed appraiser and the existing appraisers would perform the complaint was filed, whichever is earlier. It posits that the amount of
same task of determining the just compensation for the NAIA-IPT III. Thus, $431,167,593.00 should thus be multiplied by 1.0971 - the prevailing
the RTC should have relied instead on the opinion of the internationally- inflation rate from November 29, 2002, to December 21, 2004 - for a total
renowned appraisers that the Government hired. amount of $470,450,825.00.
The Government likewise avers that the appointment of an independent The sum of $470,450,825.00 should further earn an interest rate of 12%
appraiser would only render the expropriation proceedings more costly. per annum beginning December 21,2004, until full payment. PIATCO
The Government would be forced to pay for the services of two maintains that the Government's deposit in an escrow account of a
appraisers, which is not the intention of RA 8974. The court-appointed portion of just compensation is not equivalent to payment; hence, interest
appraiser, too, would render the BOC's functions useless. Under Rule 67 of on the full amount of just compensation shall continue to apply.
the Rules of Court, it is the BOC that is required to receive evidence in the
determination of just compensation. Rule 67 of the Rules of Court does PIATCO contends that the CA's reduction of interest rate to 6% is
not require the appointment of an appraiser in eminent domain cases. erroneous because the Court, in numerous cases, has consistently
imposed 12% interest per annum on just compensation. PIATCO
Lastly, the Government complains that the RTC order requiring it to emphasizes that the imposition of interest on just compensation is not
submit a Certificate of Availability of Funds is vague because the RTC did based on contract, but on the owner's right to be immediately paid just
not specify the costs of the expropriation proceeding.157 compensation.
B. PIATCO's Position Finally, PIATCO prays that it be paid all income generated from the
operations of the NAIA-IPT III, from the date of taking up to the
G.R. No. 209731 present.158
PIATCO argues that the RTC rulings are null and void for the failure of the G.R. No. 209917
RTC clerk of court to furnish them copies of the BOC Final Report.
Sections 7 and 8, Rule 67 of the Rules of Court require that the parties be PIATCO asserts that the NAIA-IPTIII does not suffer from massive
given ten days within which to file their objections to the findings of the structural defects; that the Government's reliance on the Ove Arup Report
commissioners. is self-serving. The Government would not have expropriated the NAIA-
IPT III if it truly believed that the terminal suffered from massive structural
On its base value of $360,969,790.82, PIATCO insists that its valuation is defects. Furthermore, the MIAA's Project Management Office oversaw the
supported by a preponderance of evidence, particularly by the As-Built construction of the NAIA-IPT III to ensure that the terminal complied with
Drawings and the Bills of Quantities submitted by Takenaka and the agreed specifications under the relevant contracts between PIATCO
Asahikosan. The CA should not have relied on the Government's self- and the Government.
serving evidence in computing the base value of the NAIA-IPT III.
PIATCO contends that the depreciation, deterioration, and costs for non-
PIATCO also cites the CA's failure to include the attendant costs in the compliance with contract specifications should not be deducted from the
valuation of the NAIA-IPT III as an omission; the CA merely recognized the base value of the NAIA-IPT III. The base value of $300,206,693.00 should
construction cost valuation of the terminal pursuant to the Gleeds Report. be the least amount that the Government should pay. The measure of just
PIATCO alleges that it incurred attendant costs of $70,197,802.00 apart compensation is the fair and full equivalent for the loss sustained by the
from the construction cost of $360,969,790.82. It also emphasizes that its property owner, not the gain that would accrue to the condemnor.
consultancy fees are even below the international norms, as shown in the
Scott Wilson Report. It also claims that site preparation costs, legal costs PIATCO also asks this Court to strike from the record the affidavit of
in planning and constructing the development, and financing costs form Kaczmarek and other attachments in the Government's motion for partial
part of attendant costs since these costs are indispensable in completing reconsideration dated August 22, 2013. The Government should not be
a complex infrastructure project. allowed to present new evidence on the valuation of the NAIA-IPT III
before the CA. PIATCO points out that Kaczmarek was not cross-examined
PIATCO further alleges that its attendant costs are supported by the and his identity, knowledge, and credibility were not established before
attachments in its Compliance dated December 14, 2010, including the the trial court. The Government is estopped from introducing new
summary of payments for incurred attendant costs, official receipts, evidence before the appellate court since it objected to Takenaka and
statements of account, sales invoices, endorsements, insurance policies Asahikosan's introduction of new and additional evidence before the CA.
and other related documents, acknowledgement receipts, agreements,
invoices, and bonds. It claims that Reyes Tacandong & Co examined these
PIATCO insists that it would be erroneous to create an escrow account in G.R. No. 209696 and G.R. No. 209731
favor of Takenaka and Asahikosan since the enforceability of Claim Nos.
HT-04-248 and HT-05-269 in Philippine jurisdiction has yet to be decided Takenaka and Asahikosan argue that law and equity dictate that just
by the Court in G.R. No. 202166. It points out that the main issue in G.R. compensation of at least $85,700,000.00 should be set aside to answer for
Nos. 209731, 209917, and 209696 is the amount of just compensation, their money claims against PIATCO.RA 8974 does not prohibit the
not the determination of Takenaka and Asahikosan's money claims creation of an escrow account pending the determination of the parties'
against PIATCO. Takenaka and Asahikosan's insistence to enforce their conflicting claims on the property and on the just compensation.
money claims against PIATCO in G.R. Nos. 209731, 209917 & 209696
constitutes forum shopping and is still premature.
Takenaka and Asahikosan allege that PIATCO is a shell corporation with
no significant assets, that has repeatedly defaulted on its monetary
PIATCO contends that Takenaka and Asahikosan have no standing to obligations. They emphasize that PIATCO did not pay Takenaka and
demand the creation of an escrow account in their favor. Section 9, Rule Asahikosan despite its receipt of the ₱3 billion proffered value from the
67 of the Rules of Court does not apply in this case because there are no Government. Takenaka and Asahikosan seek the creation of an escrow
conflicting claims regarding the ownership of the NAIA-IPT III. account to preserve their property rights against PIATCO. They posit that
Furthermore, the Court categorically stated in Gingoyon that PIATCO PIATCO may abscond after its receipt of the remaining just compensation
owns the NAIA-IPT III. PIATCO further argues that the rules on preliminary from the Government.
attachment do not apply to this case. Mere apprehension that PIATCO
would abscond from its financial liabilities is not a ground for the
attachment of the creditor's assets. Moreover, an artificial entity cannot PIATCO would profit by at least $155,000,000.00 if it solely receives the
abscond. PIATCO likewise denies that it refuses to pay Takenaka and entire amount of $431,167,593,000.00 (PIATCO's claimed just
Asahikosan's money claims. PIATCO posits that the eminent domain case compensation as of December 2002). PIATCO has judicially admitted that
it has paid Takenakaand Asahikosan only $275,000,000.00.
is not the proper venue for the adjudication of Takenaka and Asahikosan's
money claims.160
Takenaka and Asahikosan assert that the interest of justice will be served
G.R. No. 181892 if the Court allows the creation of an escrow account in their favor. They
point out that the lower courts already ruled on the enforceability of
Claim Nos. HT-04-248 and HT-05-269.Furthermore, the Court, in
PIATCO agrees with the RTC's appointment of DG Jones and Partners as Gingoyon, merely ordered the direct payment of just compensation to
an independent appraiser. The determination of just compensation is PIATCO in order to ensure that the builder of the NAIA-IPT III is
essentially a judicial function. The trial court's power to appoint compensated by the Government as a matter of justice and equity.
commissioners is broad enough to include the power to appoint an Takenaka and Asahikosan underscore that they are the real builders of the
appraiser who shall assist the commissioners in ascertaining the amount NAIA-IPT III as PIATCO's subcontractors.
of just compensation. The latter power is inherent in the court's task to
receive evidence and to arrive at a fair valuation of the expropriated
property. Takenaka and Asahikosan maintain that Section 9, Rule 67 of the Rules of
Court apply with respect to the adjudication of the parties' conflicting just
compensation claims. The Court did not declare in Gingoyon that Rule 67
Section 5 (g), Rule 135 of the Rules of Court allows the court to amend of the Rules of Court shall not apply to the payment of final just
and control its processes and orders so as to make them consistent with compensation. The Court merely applied RA 8974 in Gingoyon insofar as
law and justice. Furthermore, nothing in RA 8974 IRR that prohibits the the law prescribes direct payment as a prerequisite for the issuance of a
trial court from appointing an independent appraiser. writ of possession in eminent domain cases.
Section 6, Rule 67 of the Rules of Court provides that all parties may Under Section 9, Rule 67 of the Rules of Court, if there are conflicting
introduce evidence on the valuation of the property sought to be claims on the property, the court may order the just compensation to be
expropriated. The trial court is not bound by the report of the paid to the court for the benefit of the person adjudged in the same
commissioners and of the independent appraisers, much less of the proceeding to be entitled thereto. Takenaka and Asahikosan argue that
findings of the Government-hired appraisers. they are the lawful recipients of just compensation as the real builders of
the NAIA-IPT III and as the prevailing parties in Claim Nos. HT-04-248 and
PIATCO asserts that the Government is estopped from assailing the HT-05-269.
appointment of an independent appraiser. The Government voluntarily
ProvRem Rule 67 Fulltext Page 41 of 119
Even assuming that PIATCO is the owner of the NAIA-IPT III, the owner of gap between the NAIA-IPT III's bridge and building structure had a
the expropriated property is not solely entitled to the full amount of just potential for seismic pounding.
compensation.
Takenaka and Asahikosan posit that all the structural members of the
In Republic v. Mangotara,162 citing de Knecht v. CA,163 the Court held that NAIA-IPT III have a DCR of less than 1.0based on the 1992 National
just compensation is not due to the property owner alone; the term Structural Code of the Philippines (NSCP), the code applicable when the
"owner" likewise includes those who have lawful interest in the property NAIA-IPT III was designed and constructed. Takenaka and Asahikosan
such as a mortgagee, a lessee, and a vendee in possession under an opine that Ove Arup did not use the 1992 NSCP in the August 2007 Site
executory contract. In Philippine Veterans Bank v. Bases Conversion Observation Report. Ove Arup's finding that the NAIA-IPT III has a
Development Authority,164 the Court held that just compensation may be potential for seismic pounding is baseless. The terminal is designed and
deposited with the court when there are questions regarding the built to address the possibility of seismic pounding, taking into
ownership of the expropriated property. In Calvo v. Zandueta,165 the Court consideration that the NAIA-IPT III is built on Type I soil. Takenaka and
deferred the release of just compensation pending the determination of Asahikosan claim that Ove Arup's finding was not based on the AASHTO
the ownership of the expropriated property, despite the finality of the Standard Specification for Highway Bridges (16th Ed., 1996), the code
order allowing the release of just compensation. applicable at the time the NAIA-IPT III was designed and built. Takenaka
and Asahikosan likewise argue that Scott Wilson did not admit that the
Takenaka and Asahikosan refuse to share in the expenses of the BOC. NAIA-IPT III suffered from structural defects. They clarify that the
Under Section 12, Rule 67 of the Rules of Court, the costs of the statements in the Scott Wilson report "were merely intended to
expropriation suit shall be shouldered by the Government. The accommodate [the] changes that the client wished to effect."167 They also
Government would be unjustly enriched if other parties are required to point out that the Government stated in its petition (in G.R. No. 209917)
shoulder the costs of the suit. It would also be unfair to require Takenaka that "additional work is required to complete the terminal structure to
and Asahikosan to share in the expenses of the BOC since they were not make it compliant with the standards of Takenaka and Asahikosan."168
furnished copies of the BOC Final Report, in violation of their right to due
process.166 To lay the structural issue to rest, Takenaka and Asahikosan consulted
Meinhardst (Singapore) Pte Ltd., their Structural Design Consultant, to
G.R. No. 209917 rebut TCGI's findings. They also hired disinterested American experts in
the construction industry - Mr. S.K. Ghosh of S.K. Ghosh Associates, Inc.;
Mr. Robert F. Mast, PE, SE of Berger/Abram Engineers, Inc.; and Mr. Mete
Takenaka and Asahikosan argue that deductions for depreciation and A. Sozen - to validate Meinhardst's conclusions. These experts
deterioration are inconsistent with the concept of replacement cost as a unanimously concluded that the NAIA-IPT III's design is structurally sound
measure of appraising the actual value of the NAIA-IPT III. In exercising because it complied with the 1992 NSCP, thus, effectively negating the
the power of eminent domain, the Government takes the property on "as Government's claim that the NAIA-IPT III suffers from structural defects.
is, where is" basis. Takenaka and Asahikosan point out that the Takenaka and Asahikosan impugn the ASEP Report. They reiterate that
Government has the option not to expropriate the terminal. they constructed the NAIA-IPT III in accordance with the Onshore
Consequently, the Government cannot base the value of the building on Construction and Offshore Procurement Contracts and the prevailing
whether or not the building caters to the Government's needs. building code at the time of the design and construction of the NAIA-IPT
III. The statement in the ASEP Report that "the NAIA-IPT III may be
Furthermore, RA 8974 IRR provides that only the costs necessary to partially opened provided that retrofitting works are done prior to its full
replace the expropriated property should be considered in appraising the operation" does not mean that the terminal is defective. The remediation
terminal. Statutes authorizing the deprivation of private property, as in works were solely to ensure that the NAIA-IPT III structures are compliant
expropriation cases, must be strictly complied with because these are in with the current standards, which were not yet in effect when the
derogation of private rights. The Court's intent in Agan when it declared construction of the NAIA-IPT III took place.
that equity should likewise be considered in appraising the NAIA-IPT III is
to prevent the Government from undervaluing the property and enriching Messrs. Meinhardt opined that the scope of the proposed retrofitting
itself at the expense of private parties. works shows that the structural design of the NAIA-IPT III is not defective
because the proposed retrofitting works are not related to the alleged
Takenaka and Asahikosan also insist that a multi-level retail mall is not an structural defects of the NAIA-IPT III vis-à-vis the 1992 NSCP. He also
unnecessary area. They point out that modern airports are subsidized by stated that the proposed retrofitting works are meant to reinforce the
income from retail malls and cannot operate profitably without this NAIA-IPT III which is already compliant with the 1992 NSCP.
additional income.
Takenaka and Asahikosan likewise engaged the services of AECOM
Takenaka and Asahikosan agree with the CA's finding that the NAIAIPT III Australia Pty. Ltd. to conduct a technical review of the Review on TCGI
is structurally sound. There is no clear evidence that the collapse of the Report of Civil Design Review and Evaluation (Elevated Roadway prepared
ceiling of the NAIA-IPT III was caused by the terminal's structural defects. by Ove Arup & Partners HK Ltd. Philippines Branch). AECOM criticized the
The CA correctly concluded that the ceiling's collapse is merely a finishing Ove Arup's review as follows:
and aesthetic issue.
a. Ove Arup valuated the NAIA-IPT's Elevated
They emphasize that Mr. Gary Taylor, their hired appraiser, assailed the Roadway using the AASHTO Manual of Bridge
qualifications, the methodology, and the findings of Ove Arup in its Evaluation and the FHA Bridge Inspectors Reference
August 2007 Site Observation Report. Furthermore, Ove Arup made Manual, which are irrelevant to any discussion of its
several conflicting findings on the structural soundness of the NAIA-IPT design;
III. Ove Arup concluded that the number of structural members failing the
Demand Capacity Rate (DCR)/m.1.10 criteria was more than those used b. Ove Arup evaluated the NAIA-IPT III's Elevated
for the retrofit design. The DCR measures the capacity of a portion of the Roadway using the Seismic Retrofitting Manual for
NAIANAIA-IPT III to carry the load it was designed to bear, with an Highway Structures, which is irrelevant because there
optimal rate being less than 1.0. It likewise opined that the distance of the is no need for a seismic retrofit of the NAIA-IPT III's
Elevated Roadway;
e. Ove Arup used inappropriate codes for the VI. The Issues
assessment of the bearings of the NAIA-IPT III's
Elevated Roadway; In G.R. Nos. 209917, 209696, and 209731, we resolve the following issues:
f. Ove Arup's analysis suggests that 36 pier columns (1) Whether the RTC's May 23, 2011 decision in Civil Case No.
of the NAIA-IPT III's Elevated Roadway are allegedly 04-0876 is null and void for violation of PIATCO, Takenaka and
under strength, but fails to quantify the ratio of the Asahikosan's right to procedural due process;
column effect to the corresponding capacity;
h. Ove Arup used an incorrect site coefficient for the (c) With respect to the computation of construction
site's soil type, which resulted in seriously erroneous costs, the issues are:
input data, thus, any conclusions or
recommendations derived from these data are 1. Whether the Government's computation
rendered invalid; of construction cost is supported by a
preponderance of evidence;
i. Ove Arup's claim that there are "failures" in the
elastomeric bearings/bearing pads is based on an 2. Whether the NAIA-IPT III suffered/suffers
Australian design code which did not exist at the time from massive structural defects;
the NAIA-IPT III's Elevated Roadway was designed;
Takenaka and Asahikosan aver that the Government would be able to b) Whether the Court may
lessen its expenses, operate the NAIA-IPT III, and earn revenues sooner as accord probative value to the
there is, in fact, no need to perform retrofitting works on the terminal. summary report prepared by
Reyes Tacandong & Co., which
Takenaka and Asahikosan point out that the design of the NAIA-IPT III is validated PIATCO's computation
bilaterally symmetrical which means the structural system of one area is of attendant costs;
virtually identical to others. Since the Government opened certain areas of
the NAIA-IPT III to the public, it follows that the unused areas are also
(3) Whether Takenaka and Asahikosan shall share in the We rule that the parties' failure to receive the Final Report did
expenses of the BOC; not render the May 23, 2011 Decision null and void.
(4) Whether the owner of the property sought to be The essence of procedural due process is the right to be
expropriated shall solely receive the just compensation due; heard.172 The procedural due process requirements in an
and eminent domain case are satisfied if the parties are given the
opportunity to present their evidence before the commissioners
(5) Whether the Government may take property for public whose findings (together with the pleadings, evidence of the
purpose or public use upon the issuance and the effectivity of parties, and the entire record of the case) are reviewed and
the writ of possession; considered by the expropriation court. It is the parties' total
failure to present evidence on just compensation that renders
the trial court's ruling void. The opportunity to present evidence
In G.R. No. 181892, the following issues are relevant:
during the trial remains to be the vital requirement in the
observance of due process.173
(1) Whether the appointment of an independent
appraiser issue has been rendered moot and
The record will show that the parties exhaustively discussed
academic by the RTC's promulgation of its rulings in
their positions in this case before the BOC, the trial court, the
Civil Case No. 04-0876; and
appellate court, and this Court.
The decision to exercise the power of eminent Among the factors to be considered in
domain rests with the legislature which has the arriving at the fair market value of the
exclusive power to prescribe how and by whom the property are the cost of acquisition, the
power of eminent domain is to be exercised. Thus, current value of like properties, its actual or
the Executive Department cannot condemn potential uses, and in the particular case of
properties for its own use without direct authority lands, their size, shape, location, and the
from the Congress.177 tax declarations. The measure is not the
taker's gain but the owner's loss.186 To be
The exercise of eminent domain necessarily just, the compensation must be fair not
derogates against private rights which must yield to only to the owner but also to the taker.187
demand of the public good and the common
welfare.178 However, it does not confer on the State While jurisprudence requires the "fair
the authority to wantonly disregard and violate the market value" to be the measure of
individual's fundamental rights. recovery in expropriation cases, it is not an
absolute and exclusive standard or method
2.b. Just compensation is the full and fair equivalent of of valuation.188 There are exceptional cases
the property taken from the owner by the condemnor. where the property has no fair market
value or where the fair market value of the
property is difficult to determine.
The 1987 Constitution embodies two constitutional
safeguards against the arbitrary exercise of eminent
domain: first, private property shall not be taken for Examples of properties with no or with
public use without just compensation;179 and second, scant data of their fair market values are
no person shall be deprived of life, liberty, or specialized properties or buildings
property without due process of law.180 designed for unique purposes.189 These
specialized properties bear these
characteristics because they are "rarely x x
Just compensation is defined as "the full and fair x sold in the market, except by way of sale
equivalent of the property taken from its owner by of the business or entity of which it is part,
the expropriator." The word "just" is used to qualify due to the uniqueness arising from its
the meaning of the word "compensation" and to specialized nature and design, its
convey the idea that the amount to be tendered for configuration, size, location, or
the property to be taken shall be real, substantial, full otherwise."190
and ample.181 On the other hand, the word
"compensation" means "a full indemnity or
remuneration for the loss or damage sustained by Examples of specialized properties are
the owner of property taken or injured for public churches, colleges, cemeteries, and
use."182 clubhouses.191 These also include airport
terminals that are specifically built as "a
place where aircrafts land and take off and
Simply stated, just compensation means that the where there are buildings for passengers to
former owner must be returned to the monetary wait in and for aircraft to be
equivalent of the position that the owner had when sheltered."192They are all specialized
the taking occurred.183 To achieve this monetary properties because they are not usually
equivalent, we use the standard value of "fair market sold in the ordinary course of trade or
value" of the property at the time of the filing of the business.
complaint for expropriation or at the time of the
taking of property, whichever is earlier.
In the Tengson Report dated December 1,
2010, Gary Taylor characterized the NAIA-
2.b.1. Fair market value is the general IPT III as a specialized asset.193 Tim Lunt
standard of value in determining just also stated in the Reply to Tengson
compensation.
International Ltd. Report and Response
from Takenaka & Asahikosan dated
December 7, 2010 that the market value of
Under Section 10 of the RA 8974 IRR, the (f) The size, shape or location, tax
improvements and/or structures on the declaration and zonal valuation
land to be acquired for the purpose of of the land;
implementing national infrastructure
projects shall be appraised using the
(g) The price of the land as
replacement cost method.
manifested in the ocular findings,
oral as well as documentary
Replacement cost is a different standard of evidence presented; and
valuation from the fair market value. As we
previously stated, fair market value is the
(h) Such facts and events as to
price at which a property may be sold by a
enable the affected property
seller who is not compelled to sell and
owners to have sufficient funds
bought by a buyer who is not compelled to
to acquire similarly situated
buy. In contrast, replacement cost is "the
lands of approximate areas as
amount necessary to replace the
those required from them by the
improvements/structures, based on the
government, and thereby
current market prices for materials,
rehabilitate themselves as early
equipment, labor, contractor's profit and
as possible.
overhead, and all other attendant costs
associated with the acquisition and
installation in place of the affected The Court explained in Agan and Gingoyon
improvements/structures."196 We use the that the replacement cost method is only
replacement cost method to determine just one of the factors to be considered in
Once the gross replacement cost or the In these consolidated cases, we rule that
sum of construction and attendant costs is the depreciated replacement cost method,
derived, depreciation shall be rather than the new replacement cost
deducted.218 Depreciation is classified into method, is the more appropriate method
three categories: physical depreciation, to use in appraising NAIA-IPT III.
functional obsolescence, and external
obsolescence. Injustice would result if we award PIATCO
just compensation based on the new
Physical obsolescence refers to the "wear replacement cost of the NAIA-IPT III, and
and tear over the years, which might be disregard the fact that the Government
combined with a lack of maintenance."219 expropriated a terminal that is not brand
new; the NAIAIPT III simply does not have
the full economic and functional utility of a
Physical depreciation is curable if "capital brand new airport.
investment can bring the building to a
state in which the degree of obsolescence
is mitigated (e.g., standards of finishes and Adjustments for depreciation should be
services)."220 It is incurable if "no amount of made to reflect the differences between
capital investment can rectify the the modern equivalent asset and the actual
[depreciation] (for example, building asset or the NAIA-IPT III. The reason is that
structural flexibility)."221 Curable physical depreciation involves the loss of value
depreciation is measured by the cost to caused by the property's reduced utility as
cure or retrofitting which could extend the a result of damage, advancement of
life of the building.222 Incurable technology, current trends and tastes, or
depreciation or deterioration is estimated environmental changes.229
by a variety of age-life or economic-age
calculation methods.223 Functional This conclusion is consistent with Section
obsolescence "reflects the advances in 10 of RA 8974 IRR which allows us - and
Section 10. Valuation of Improvements This Court exercises its judicial function to
and/or Structures - Pursuant to Section 7 fix just compensation in eminent domain
of the Act, the Implementing Agency shall cases on the basis of the law, the rules, and
determine the valuation of the the evidence - including the appraisal
improvements and/or structures on the reports and the embedded formula on how
land to be acquired using the replacement the parties arrived at the amounts of just
cost method. The replacement cost of the compensation - presented by the parties
improvements/structures is defined as the before the trial court and the entire record
amount necessary to replacement of the consolidated cases.
improvements/structures, based on the
current market prices for materials, The determination of just compensation in
equipment, labor, contractor's profit and eminent domain cases is essentially and
overhead, and all other attendant costs exclusively a judicial function. Fixing the
associated with the acquisition and formula with definitiveness and
installation in place of the affected particularity in just compensation is not the
improvements/structures. In the valuation function of the executive nor of the
of the affected improvements/structures, legislative branches, much less of the
the Implementing Agency shall consider, parties in this case. Any valuation for just
among other things, the kinds and compensation laid down in the statutes
quantities of materials/equipment used, may not replace the court's own judgment
the location, configuration and other as to what amount should be awarded and
physical features of the properties, and how this amount should be arrived at.
prevailing construction prices. (Emphasis Legislative enactments, as well as executive
supplied) issuances, providing the method of
computing just compensation are treated
Depreciation should be deducted because as mere guidelines in ascertaining the
modern materials and design are assumed amount of just compensation. When acting
in the replacement cost method. In using within the parameters set by the law itself,
the depreciated replacement cost method, courts are not strictly bound to apply the
"[t]he intent is to provide a functionally formula to its minutest detail, particularly
similar improvement in order to apply a when faced with situations that do not
meaningful level of depreciation."230 warrant the formula's strict application. The
courts may, in the exercise of their
If we adopt the new replacement cost discretion, relax the formula's application
method, PIATCO would be compensated to fit the factual situations before them.233
for more than what it had actually lost. We
must remember that the concept of just We clarify, however, that this Court is not
compensation does not imply fairness to confined to the use of the depreciated
the property owner alone. In an eminent replacement cost method in determining
domain situation, compensation must the just compensation in these cases.
likewise be just to the public which Valuation is not exclusively a technical
ultimately bears the cost of expropriation. matter used in arriving at a numerical
The property owner is entitled to measure of compensation. Rather,
compensation only for what he actually valuation in eminent domain is a judicial
loses; what he loses is only the actual value question based on equitable principles.
of the property at the time of the taking.231 Thus, this Court shall likewise endeavor to
weigh the justness and fairness of
Just compensation must not extend compensation between the condemnor
beyond the property owner's loss or injury. and the condemnee, considering the
This is the only way for the compensation factual circumstances of this case.234
paid to be truly just, not only to the
individual whose property is taken, but also 3. Construction cost of the NAIA-IPT III
to the public who will shoulder the cost of
expropriation. Even as under valuation 3.a. The base valuation of the NAIA-IPT III
would deprive the owner of his property
without due process, so too would its
overvaluation unduly favor him to the The Government claims that the construction cost or
prejudice of the public.232 the base valuation of the NAIA-IPT III amounts to
$300,206,693.00, itemized as follows:235
2) Convert
the £UK @
Off-Shore US$189.83
Million PIATCO's statement that the total sum of
$360,969,791.00 is evidenced by the As-
Built Drawings is misleading. Takenaka and
VAT US$11.43 Million Asahikosan's computation of construction
cost includes items which do not pertain to
ER Changes US $3.93 the construction of the NAIA-IPT III.
Million PIATCO, Takenaka, and Asahikosan
erroneously included in the construction
TOTAL US$338.83 cost the costs of the action, interest rates
Million on the judgment award of $14,827,207.00
and $52,008,296.54, attorney's fees, and
litigation expenses.
2.2.13 Based on the certified IPC
no. 35 for both Takenaka and
Asahikosan, the cost of the These items were not directly incurred in
completed and certified works the construction of the NAIA-IPT III. In
(as of IPC No. 35) are as follows: Claim No. HT-04-248, only $6,602,971.00
and $8,224,236.00 or the sum of
$14,827,207.00 can possibly relate to the
On-Shore US$133.64
construction cost of the NAIA-IPT III. On
Million
the other hand, in Claim No. HT-05-269,
only the amounts of $21, 688,012.18 and
Off-Shore US$189.83 $30,319,284.36 or the total sum of
Million $52,008,296.54 can be possibly imputed to
the construction cost of the terminal.
VAT US$11.43 Million
In any case, we cannot consider the
ER Changes US $3.93 London awards as evidence of the
Million construction cost of the NAIA-IPT III. Todo
so in this case is to recognize Claim No.
HT-04-248 and Claim No. HT-05-269 when
TOTAL US$338.83
their recognition and enforcement have yet
Million
to be decided by this Court in G.R. No.
202166. It is a basic rule that Philippine
2.2.14 The construction cost courts cannot take judicial notice of a
stated above x x x is at 2002 foreign judgment or order.249
prices (no adjustments for
inflation/escalation) and are
We can only recognize and/or enforce a
exclusive for all other attendant
foreign judgment or order after a
costs, such as the engineering
conclusive and a final finding by Philippine
and architectural service fees,
courts that: (1) the foreign court or tribunal
quality assurance service fees,
has jurisdiction over the case, (2) the
construction supervision service
parties were properly notified, and (3) there
fees, construction insurance, site
was no collusion, fraud, or clear mistake of
development costs, financing
law or fact.250
costs and other associated costs.
2.2.15 We would conclude that
the certified cost of construction PIATCO, Takenaka, and Asahikosan alleged
of US$338 million and the other that PIATCO paid Takenaka and Asahikosan
attendant costs are fair and the sum of $275,119,807.88 pursuant to the
ProvRem Rule 67 Fulltext Page 56 of 119
Onshore Construction and Offshore Evaluation" - Elevated Roadway, dated
Procurement Contracts. According to the March 2009; and other rectification works
RTC (whose ruling the CA did not reverse), required to bring the elevated roadways to
these parties failed to prove the fact of compliance with applicable building and
payment of $275,119,807.88. airport codes, as indicated in the
Appendices of Arup's Site Observation
We add that the alleged payment of Report.252
$275,119,807.88 does not support their
allegations that this amount pertains to the Scott Wilson argued that no structural elements of
construction cost of the NAIA-IPT III. the NAIA-IPT III actually failed.253 He emphasized that
Takenaka and Asahikosan's admission that there were varying opinions regarding the integrity of
the sum of $275,119,807.88 were paid by the NAIA-IPT III:
PIATCO does not bind the Government
who is not a party to the Onshore 3.3.7 The adequacy of the structural frame, individual
Construction and Offshore Procurement load bearing elements and foundations under
Contracts. If at all, the Court can only "normal" gravity loads should be able to be readily
recognize the sum of $66,834,503.54 from evaluated. However, there are clearly differences of
PIATCO, Takenaka, and Asahikosan's opinion between all 3 parties who have carried out
computation of construction cost, which is design and assessments in this regard in terms of the
much lower than the Government's extent of 'apparent failed elements' under the design
computed construction cost of appraisal which ranges from:
$300,206,693.00.
We thus add to the construction cost the sum of Applying fiber-reinforced polymer (FRP) to columns,
$20,713,901, itemized below:276 beams, and slabs will increase their strength and
resistance against excess loads and combined forces
of elements. A thicker flat slab drop is meant to
Item In Dollars strengthen the slab-column connection.
Apron Civil 829,619 Increased seismic gap between the elevated access
roadway and adjacent structures will reduce the risk
Taxiway Civil 439,280 of pounding between the bridge and building
structure.280
Storm Water 2,604,081
Scott Wilson criticized the Gleeds Report for excluding the attendant 3.1.20 We understand that PIATCO has incurred costs of US$10.3 million
costs in the construction cost valuation. He stated: for relocation of PAF existing facilities, removal of subterranean structures
and site preparation which the Gleeds Base Case CCV has not included.
3.1.13 Gleeds do (sic) not show any costs for planning and design
consultancy fees preconstruction. In our experience the following Legal Costs
percentage ranges of the construction cost would typically be the
international norms for these fees. 3.1.21 We assume that in addition to the above fees PIATCO has incurred
legal costs in planning and constructing the development and this is quite
● Attendant Costs Percentage Range normal on BOT concession contracts where contract agreements and
responsibilities have to be agreed between a number of different parties.
● Architecture 3.0 to 4.0 %
Overall Summary
● Civil and Structural 1.0 to 4.0 %
3.1.21 PIATCO has incurred consultancy fees and site preparation
costs of US$41.7 million (US$31.4 plusUS$10.3 million) not included
● Electrical and Mechanical 2.5 to 3.5 %
by Gleeds in the Base Case CCV.284
3.1.15 Some preliminary design was carried out by Takenaka prior to the On December 14, 2010, PIATCO attached to its Compliance documentary
EPC tender design so slight lower planning and design consultancy fees evidence of its claimed attendant costs of US$70,197,802.00. These
could be expected. It is understood that PIATCO have paid US$19.3 include photocopies of summary of payments for architecture &
million to the designers PCI, SOM, PACICON and JGC (architect of record) engineering, quality assurance, construction supervision, construction
and this therefore appears a fair and reasonable fee. insurance, site development, other costs and financing costs, official
receipts, statements of account, sales invoices, endorsements, insurance
policies and other related documents, acknowledgement receipts,
3.1.16. In addition there is also the cost of site supervision. In this case agreements, invoices, and bonds.
there was the independent QA role undertaken by Japan Airport
Consultants and construction supervision by PCI. It is noted that the Bid
Document suggested that up to 3% of the construction cost should be PIATCO claims that the following entities rendered services in the
allowed for the independent QA role. In our experience we would expect construction of the NAIA-IPT III:
QA and construction supervision to cost between 3% and 5% of the
construction cost.
Services Rendered Entities that Rendered the
Services
3.1.17 On the basis of a construction cost valuation of the order of
US$322 million we would expect the cost of construction supervision to Engineering and Architecture Pacific Consultants International
be a minimum of US$9.5 million. It is understood that PIATCO have paid Asia, Inc. Pacicon Philippines, Inc.
Architect J. G. Cheng RMJM
Site Development Bases Conversion Development Under the best evidence rule, when the subject of inquiry relates to the
Corporation Skidmore, Owings & contents of a document, no evidence shall be admissible other than the
Merrill Pacific Consultants original document itself. In proving the terms of a written document, the
International Asia, Inc. Natural original of the document must be produced in court.
Resource Development Corporation
Serclan Enterprises Geodesy The best evidence rule ensures that the exact contents of a document are
Services, Inc. Geotechnics brought before the court. In deeds, wills, and contracts, a slight variation
Philippines, Inc. Revalu in words may mean a great difference in the rights and obligations of the
Constructions & Supply N.O. parties. A substantial hazard of inaccuracy exists in the human process of
Mercado Construction, Inc. Lopez making a copy by handwriting or typewriting. Moreover, with respect to
Drilling Enterprises Monark oral testimony purporting to give the terms of a document from memory,
Constructions Illustrious Security a special risk of error is present, greater than in the case of attempts at
and Investigation Agency, Inc. Core describing other situations generally.286
Watchmen, Security and Detective
Agency Corp.
The best evidence rule likewise acts as an insurance against fraud. If a
Other Services Laguna Lake Development party is in the possession of the best evidence and withholds it, and seeks
Authority National to substitute inferior evidence in its place, the presumption naturally
Telecommunications Commission arises that the better evidence is withheld for fraudulent purposes that its
Prudential Guarantee and production would expose and defeat. The rule likewise protects against
Assurance, Inc. Manila Electric misleading inferences resulting from the intentional or unintentional
Company, Inc. Maynilad Philippine introduction of selected portions of a larger set of writings.287
Long Distance
Telecommunications, Inc. Myrtle As exceptions to the best evidence rule, Section 3, Rule 130 of the Rules
Intergen Exchange Corp. of Court provides that non-original documents may be produced in court
in the following cases:
Financing Services Dresdner / Kfw / Helaba Banks
Fraport AG/FAG Deutsche Bank
(a) When the original has been lost or destroyed, or cannot be
produced in court, without bad faith on the part of the offeror;
Reyes Tacandong & Co. checked the mathematical accuracy of the
attendant costs. PIATCO asserts that it engaged the services of various (b) When the original is in the custody or under control of the
consultants in the construction of the NAIA-IPT III and incurred the party against whom the evidence is offered, and the latter fails
following attendant costs: to produce it after reasonable notice;
Attendant Costs Amount (c) When the original consists of numerous accounts or other
documents which cannot be examined in court without great
Engineering and Architecture US$19,372,539 loss of time and the fact sought to be established from them is
only the general result of the whole; and
Quality Assurance US$6,923,720
Construction Supervision US$4,302,227 (d) When the original is a public record in the custody of a
public officer or is recorded in a public office. (Emphasis
Construction Insurance US$4,329,272 supplied)
Furthermore, when a party invokes Section 3 (c), Rule 130 of the Rules of Because the procedures do not constitute either an audit or a review of
Court, he does not similarly invoke Section 3 (a), (b), and/or (d), Rule 130 financial statements made in accordance with Philippine Standards on
of the Rules of Court. He does not likewise claim that the original Auditing, we do not express any assurance on the attendant costs.
(Emphasis supplied)
documents have been lost or destroyed. The party merely asserts that the
numerous documents cannot be examined in court without great loss of
time and that the fact sought to be established from these documents is 4.b. The BOC and the RTC's
only the general result of the whole. Whenever a party seeks an attendant cost
exemption under the best evidence rule pursuant to Section 3 (c), Rule
130 of the Rules of Court, he asks permission from the trial court to The CA correctly disregarded the BOC and the RTC's computation of
produce a summary of numerous documents, whose originals are attendant costs, which both pegged the attendant cost at 10% of the
available to the adverse party for inspection. He does not ask permission construction cost. The BOC and the RTC relied on the mean percentage
from the trial court to present in evidence the numerous non-original range of attendant cost which appears in the Scott Wilson Report as
documents. Otherwise, the very purpose of Section 3 (c), Rule 130 of the follows:292
Rules of Court would be defeated. In that case, every exhibit of non-
original documents would be identified, authenticated, and cross-
examined, leading to a tedious and protracted litigation. Attendant Costs Percentage Range
An eminent domain case is different from a complaint for damages. A The Government's CCV already includes attendant costs which are
complaint for damages is based on tort and emanates from the incorporated in the "General Requirements and Conditions." On the basis
transgression of a right. A complaint for damages seeks to vindicate a of the Bills of Quantities, Gleeds took into account indirect costs in
legal wrong through damages, which may be actual, moral, nominal, constructing the NAIA-IPT III, summarized below:
temperate, liquidated, or exemplary. When a right is exercised in a
manner not conformable with Article 19 of the Civil Code and other
provisions on human relations in the Civil Code, and the exercise results in Attendant Costs under General Requirements and Conditions
the damage of another, a legal wrong is committed and the wrongdoer is
held responsible.296 Design $6,439,680.00297
Insurance $71,109.77307
9. I consider that Engineering and Architecture, Quality Assurance,
Construction Supervision, Construction Insurance and Site Development
Total $27,093,375.28
are clearly costs which are included for in the CCV. The CCV includes costs
associated with the General Requirements (see Appendix D - Summary).
The costs of Site Development are also included (see CCV Appendix D - 5. Deductions from the replacement cost of the NAIA-IPT III
Part 2, page 5 of 38).
5.a. Depreciation should be
xxxx deducted from the replacement
cost.
25. Scott Wilson states at paragraph 2.2.14 that the constructions costs
"are exclusive of all other attendant costs, such as the engineering and In eminent domain cases, it is acceptable that a "deduction should be
architectural services fees, quality assurance services fees, construction made to the extent to which the improvement or fixture has depreciated.
supervision services fees, construction insurance, site development costs, The cost of the buildings and fixtures, minus depreciation, is a reasonable
financing costs and other associated costs." This statement is incorrect. It test of the amount by which they enhance the market value of the land
is clear on the inspection of the General Requirements sections of the even where the market value of the land itself is not readily
Takenaka Bills of Quantities that some if not all of these items are quantifiable."308
included in the assessment of the construction costs made by PIATCO
with the exception of 1) financing costs and 2) other associated costs, for
which there is no definition. Scott Wilson makes no reference to the
ProvRem Rule 67 Fulltext Page 65 of 119
In order for this Court to arrive at a valid indication of the market value of 3.2.10 A depreciation value has been assessed at $USD35,076,294 in 3Q01
the NAIA-IPT III, we must consider accrued depreciation, which is the loss Manila prices. Calculation of this amount showing the various asset lives
in value of the terminal. assumed is included in Appendix "J."
Contrary to the CA's position, "depreciation" is used in different contexts 3.2.11 Based on the deductions for deterioration and depreciation
in valuation and financial accounting. As earlier discussed, in appraisal, between December 2002 and December 2004, the Base Value CCV at the
depreciation "refers to the reduction or writing down of the cost of a time of expropriation is $USD263,392,081.320
modern equivalent asset to reflect the obsolescence and relative
disabilities affecting the actual asset"309 or "loss in value from any In the Scott Wilson report, he stated:
cause."310 It is further defined as "the reduction or writing down of the
cost of a modern equivalent asset to reflect the obsolescence and relative
disabilities affecting the actual asset."311 3.7.1 We consider the question of depreciation in this instance to be a
financial and legal issue which has to be dealt with in accordance with
Philippine law.
In contrast, depreciation in accounting refers to "a charge made against
an entity's income to reflect the consumption of an asset over a particular
accounting period."312 It is the "process of allocating to expense the cost 3.7.2 We therefore do not feel qualified to comment on the legal issue
of a plant asset over its useful (service) life in a rational and systematic except that we do not understand how deterioration in section 3.6 and
manner."313 Accumulated depreciation is reported as a deduction from depreciation can both be applied as surely this means that Gleeds (sic)
plant assets and affects the income statement through depreciation have double counted the effect of any deterioration. (emphasis
expenses. Thus, the cost allocation is designed to match expenses with supplied)321
revenues.
In response, Tim Lunt argued:
In financial accounting, "depreciation is a process of cost allocation, not a
process of asset valuation. No attempt is made to measure the change in 14. With respect to PIATCO's hypothetical inclusion of inflation, I do not
an asset's market value during ownership because" it is assumed that consider that inflation should be applied to the base value as the
plant assets are not held for resale.314 Book depreciation refers to "the replacement cost method establishes the cost of construction when
amount of capital recapture written off an owner's books"; it is not market completed in December 2002.
derived.315 Thus, the book value - original cost less accumulated
depreciation - of an asset may be different from the market value. 15. The base values included in the CCVs are the same for the December
2002 and December 2004. The December 2004 base value is not adjusted
Consequently, an asset can have zero book value but still have a to account for inflation because the items which make up the construction
significant market value.316 of NAIA3, i.e., the labour, plant, materials, systems and equipment
installed should not be paid for at a higher rate (that takes into account
Simply put, book depreciation is measured against the book value or inflation) than the rate which would have been paid when they were
original cost of the property and is the amount of capital recapture purchased at the earlier date. Put simply, it makes no sense to apply
written off an owner's books.317 Accrued depreciation is measured against December 2004 prices to items bought and used in the construction of
the current market value of the property.318 NAIA3 sometime between June 2000 and December 2002.
Under the depreciated replacement cost method, accrued depreciation is 16. PIATCO do (sic) not consider depreciation. Having explained above
the difference between the "replacement cost of the improvements on why inflation should not be included, it is the application of a similar logic
the effective date of the appraisal and the market value of the which demonstrates why depreciation should be included. In the case of
improvements on the same date."319 NAIA3 the materials, systems and equipment installed are at least two
years older as at December 2004 than at the time they were incorporated
into the construction of NAIA3. Their value should therefore be less. The
In the Gleeds Report, Tim Lunt stated: method used for assessing this reduced value is that of depreciation.322
3.2.8 A provisional value has been assessed against the items identified in ● Deterioration - "Major deduction for baggage system not
the Arup report at $1,738,318. justified" - The deterioration in the baggage systems is clearly
set out in the Arup (and Gensler) Site Observation Report dated
The deterioration items have been costed with a base date of 2Q09. August 2007, at section 9.2. The cost deduction is set out in
Calculation of this amount is contained in Appendix 'E.' Further Appendix to the previous CCV report which Scott Wilson do
examination and costing of each of the identified items are required and, (sic) not appear to have reviewed.
therefore, the costs of these items will require adjustment based on the
actual date when the rectification works are carried out. ● Depreciation - Scott Wilson states" This issue appears to be a
legal issue and should be commented on by legal expert" and
Depreciation offers no technical or cost related comments relevant to the
CCV.
3.2.0 An Assessment has been made of the depreciated value of the
assets from December 2002 when construction was suspended to On the other hand, Gary Taylor commented:
December 2004 when Terminal 3 was expropriated by the Republic.
ProvRem Rule 67 Fulltext Page 66 of 119
Gleeds have (sic) assessed a depreciation value of US$35,076,294 (11.68%) specifications in the Bid Documents precisely because the concession
to conclude its 4Q04 value. This concept of depreciation is contrary to the agreement between PIATCO and the Government had already been
GRP's own statistics which shows a Consumer Price Index for Manila nullified. The Government cannot complain of contract noncompliance in
("CPI") increase from107.8 (Aug 01) to 125.1 (Nov. 04), a 16% increase an eminent domain case, whose cause of action is not based on a breach
over the period. The CPI is a conglomerate of all consumer prices in the of contract, but on the peremptory power of the State to take private
Manila region and includes property values and is published by the GRP property for public use.
on a monthly basis. In assessing such a depreciation value, Gleeds have
(sic) taken an arbitrary life cycle of the building and assumed a write off of Consequently, deductions from the base value of the cost of
asset over that period, then assessed the two (2) year depreciation over noncompliance with bid documents as well as inferior quality items have
the period 3Q01 to 4Q04. Whilst we acknowledge that an airport terminal no legal basis. Gleeds' reliance on the NAIA-IPT III bid documents is
building is something of a specialized asset and appreciation of value is misplaced.
not always in line with the area's general value assessments, it is still a
major structure and appreciation before depreciation (which should be
limited to equipment and fittings within the building) should not be As Scott Wilson correctly pointed out, the decisive factor of the
discounted. The concept of long term value of an asset on a similar deductibility of items under "noncompliance with bid documents" is
concept is proven out by NAIA Terminal 1, which since its construction whether they are functional. The Scott Wilson report shows that, except
more than 30 years ago has maintained a value to this date.323 for the nonprovision of moving walkway, the alleged noncompliant items
are functional.327 Also, the nonprovision of a moving walkway should not
be deducted from the base value. The only consequence of the failure to
We uphold the Government's computed extent of deterioration and provide a moving walkway is the need to construct one, which would only
depreciation. In the Reply to Tengson International Ltd. Report and increase the construction cost.328 The increase in the construction cost,
Response from Takenaka and Asahikosan dated December 7, 2010, Tim however, should not be included as part of just compensation as this
Lunt explained that "[t]he asset lives are taken specifically from experience Court is
in preparing Asset Revaluations for Airport properties which are used as
an input for annual published accounts, which are in turn audited by
appointed Accountants."324 Takenaka and Asahikosan should have only tasked to determine the construction cost of the NAIA-IPT III as of
provided for contrary assumptions with respect to the useful lives of the December 21, 2004.
subject assets if they did not agree with the Government's assumptions.
Instead, Gary Taylor merely referred to the valuation of the NAIA Terminal For these same reasons, we cannot allow the deduction in the amount of
I without any factual basis to support his claim. Moreover, Scott Wilson $75,570,510.00 "additional areas to be built." These are "areas where the
did not question the assumed useful life of the NAIA-IPT III, but agreed minimum requirements stated in the Bid Documents have not been met
that the question of whether depreciation should be deducted is a legal and are necessary for the operation" of the NAIA-IPT III. These areas
issue. include:
Since PIATCO, Takenaka, and Asahikosan failed to present contrary ● Departure hall 22,462 m2
assumptions or estimates with respect to the NAIA-IPT III's useful life, we
adopt Tim Lunt's computations with respect to deterioration and ● Meeter/greeter hall 14,696 m2
depreciation.
Section 10 of RA 8974 IRR provides that the replacement cost shall be Section 4. Order of expropriation. - If the objections to and the defenses
based on the current market prices of construction and attendant costs. against the right of the plaintiff to expropriate the property are overruled,
Under the depreciated replacement cost method, the replacement cost or when no party appears to defend as required by this Rule, the court
shall be based on the current gross replacement cost of the asset. In its may issue an order of expropriation declaring that the plaintiff has a
pleadings, the Government itself explained that the cost of replacing an lawful right to take the property sought to be expropriated, for the public
asset under both depreciated replacement cost and new replacement cost use or purpose described in the complaint, upon the payment of just
methods should be measured at its current prices. compensation to be determined as of the date of the taking of the
property or the filing of the complaint, whichever came first.
In our jurisdiction, the word "current" should be equated with the date of
the taking of the property or the filing of the complaint, whichever came A final order sustaining the right to expropriate the property may be
first. In the present case, the word "current" should necessarily refer to appealed by any party aggrieved thereby. Such appeal, however, shall not
December 21, 2004, the filing of the complaint for expropriation. prevent the court from determining the just compensation to be paid.
In National Power Corporation v. Co,333 the Court suppletorily applied After the rendition of such an order, the plaintiff shall not be permitted to
Section 4, Rule 67 of the Rules of Court in determining the value of the dismiss or discontinue the proceeding except on such terms as the court
property sought to be expropriated for purposes of implementing deems just and equitable. (4a) (Emphasis supplied)
national infrastructure projects. Under the Rules of Court, just
compensation shall be determined from the date of the taking of the On the other hand, Section 9, Article 3 of the 1987 Constitution provides
property or the filing of the complaint, whichever came first. Thus, where that "[n]o private property shall be taken for public use without just
the filing of an action precedes the taking of the property, just compensation." The 1987 Constitution thus commands the condemnor to
compensation shall be computed as of the time of the filing of the pay the property owner the full and fair equivalent of the property from
complaint.334 The relevant valuation date when we shall reckon the current the date of taking. This provision likewise presupposes that the
gross replacement cost is December 21, 2004, or the date of filing of the condemnor incurs delay if it does not pay the property owner the full
complaint for expropriation. amount of just compensation on the date of taking.338
The Government's base valuation of $300,206,693.00 is only a The reason is that just compensation would not be "just" if the State does
measurement of the current gross replacement cost as of December 2002. not pay the property owner interest on the just compensation from the
We agree with PIATCO that the gross replacement cost of the NAIA-IPT III date of the taking of the property. Without prompt payment, the property
as of December 2002 should be adjusted to its cost as of December 2004 owner suffers the immediate deprivation of both his land and its fruits or
for the plain reason that the Government's computed gross replacement income. The owner's loss, of course, is not only his property but also its
cost is not current, as required by the Rules of Court and jurisprudence. income-generating potential.339
Equity dictates that we should adjust the replacement cost at December Ideally, just compensation should be immediately made available to the
2004 values using the Consumer Price Index (CPI).335 This Court should not property owner so that he may derive income from this compensation, in
be confined and restricted by the use of the depreciated replacement cost the same manner that he would have derived income from his
method, especially in this case where the calculated base valuation as of expropriated property.
December 2004 appears to be not truly reflective of the current gross
replacement cost of the NAIA-IPT III at the time of the filing of the However, if full compensation is not paid for the property taken, then the
complaint for expropriation. State must pay for the shortfall in the earning potential immediately lost
due to the taking, and the absence of replacement property from which
In adjusting the gross replacement cost to December 2004 values, this income can be derived. Interest on the unpaid compensation becomes
Court takes cognizance of the fact that the cost of goods and services in due as compliance with the constitutional mandate on eminent domain
the Philippines increased from 2002 until 2004. This is shown by the CPI and as a basic measure of fairness.340
which is used in calculating the inflation rate and the purchasing power of
the peso.336 PIATCO correctly arrived at the inflation rate of 1.0971 using Thus, interest in eminent domain cases "runs as a matter of law and
the prevailing CPI from November 29, 2002, or the date of the suspension follows as a matter of course from the right of the landowner to be placed
1. The principal amount of just compensation shall be appraised on the The Government, on the other hand, asserts that Section 1, Rule 142 of
date of the filing of the complaint for expropriation or on December 21, the Rules of Court explicitly authorizes the expropriation court to order
2004. The just compensation shall not earn interest from December 21, the parties to equally share the costs of an action. Hence, the court can
2004, until September 10, 2006, since the Government did not take require third-party intervenors, i.e., Takenaka and Asahikosan, to share in
possession of the NAIA-IPT III during this period. the expenses of the BOC. It points out that PIATCO already shared in the
expenses of the BOC and tendered the sum of ₱2,550,000.00 to the RTC.
January principal*ra 365 12% $267,493,617. $32,099,234.0 Principal $267,493,617.26 $ 242,810,918.54 $510,304,535.80
1, 2007 te days 26 7 Amount +
to Interest
Decemb
er 31,
9. PIATCO as the Lawful Recipient of Just Compensation.
2007
January principal*ra 365 12% $267,493,617. $32,099,234.0 After determining the amount of just compensation, we next resolve the
1, 2008 te days 26 7 question of who shall receive the full amount of just compensation.
to
Decemb
Takenaka and Asahikosan contend that as actual builders of the NAIA-IPT
er 31,
III, they are lawfully entitled to receive just compensation. They pray that
2008
just compensation of at least $85,700,000.00 be set aside through an
January principal*ra 365 12% $267,493,617. $32,099,234.0 escrow account or other means, in their favor, to answer for their pending
1, 2009 te days 26 7 money claims against PIATCO in G.R. No. 202166.
to
Decemb PIATCO, on the other hand, bases its claim for just compensation on its
er 31, ownership of the NAIA-IPT III and on the ruling in Agan and Gingoyon
2009 that PIATCO should be fully compensated as the builder and owner of the
NAIA-IPT III.
January principal*ra 365 12% $267,493,617. $32,099,234.0
1, 2010 te days 26 7
For its part, the Government refuses to make further payments to PIATCO.
to
Instead, it created an escrow account in favor of the "entitled claimants"
Decemb
of just compensation. The Government fears that the NAIA-IPT III would
er 31,
still be burdened with liens and mortgages - as a result of PIATCO's
2010
indebtedness to other entities - even after it pays PIATCO the full amount
January principal*ra 365 12% $267,493,617. $32,099,234.0 of just compensation.
1, 2011 te days 26 7
to 9.a. Takenaka and Asahikosan's
Decemb intervention in the case as
er 31, unpaid subcontractors is proper.
2011
The defendants in an expropriation case are not limited to the owners of
January principal*ra 365 12% $267,493,617. $32,099,234.0
the property condemned. They include all other persons owning,
1, 2012 te days 26 7
occupying, or claiming to own the property. Under Sections 8 and 14 of
to
RA 8974 IRR, in relation with Section 9, Rule 67 of the Rules of Court, all
Decemb
persons who claim to have lawful interest in the property to be
er 31,
condemned should be included as defendants in the complaint for
2012
expropriation:
January principal * 181 12% $267,493,617. $15,917,702.3
The verified complaint shall state with certainty the right and purpose of The RTC's issuance of the March 12, 2007 order, which is binding on the
expropriation, describe the real or personal property sought to be parties and which allows Takenaka and Asahikosan to intervene in the
expropriated, and join as defendants all persons owning or claiming to case, changed the factual circumstances of this case. As an incident in our
own, or occupying, any part thereof or interest therein, showing as far as determination of the just compensation, we necessarily should resolve the
practicable, the interest of each defendant separately. If the title to any issue of NAIA-IPT III's ownership and the question of who the recipient of
property sought to be condemned appears to be in the name of the the just compensation should be.
Republic of the Philippines, although occupied by private individuals, or if
the title is otherwise obscure or doubtful so that the plaintiff cannot with 9.b. The property owner is
accuracy or certainty specify the real owners, averment to that effect may entitled to just compensation.
be made in the complaint.
Citing Agan, Takenaka and Asahikosan argue that the Court intended that
Section 14 of RA 8974 IRR. Trial Proceedings. - Within sixty (60)-day the real builders of the NAIA-IPT III should be paid just compensation.
period prescribed by the Act, all matters regarding defences and Takenaka and Asahikosan assert that they are the entities who actually
objections to the complaint, issues on uncertain ownership and conflicting built the NAIA-IPT III pursuant to the Onshore Construction and Offshore
claims, effects of appeal on the rights of the parties, and such other Procurement Contracts. In Agan, the Court declared that PIATCO is the
incidents affecting the complaint shall be resolved under the provisions builder of the NAIA-IPT III. The Court stated:
on expropriation of Rule 67 of the Rules of Court.
This Court, however, is not unmindful of the reality that the structures
Section 9, Rule 67 of the Rules of Court. Uncertain ownership; conflicting comprising the NAIA IPT III facility are almost complete and that funds
claims. - If the ownership of the property taken is uncertain, or there are have been spent by PIATCO in their construction. For the government to
conflicting claims to any part thereof, the court may order any sum or take over the said facility, it has to compensate respondent PIATCO as
sums awarded as compensation for the property to be paid to the court builder of the said structures. The compensation must be just and in
for the benefit of the person adjudged in the same proceeding to be accordance with law and equity for the government cannot unjustly
entitled thereto. But the judgment shall require the payment of the sum enrich itself at the expense of PIATCO and its investors.360
or sums awarded to either the defendant or the court before the plaintiff
can enter upon the property, or retain it for the public use or purpose if
entry has already been made. (9a) (Emphasis supplied) This finding is likewise affirmed in our February 1, 2006 Resolution in
Gingoyon where we declared:
Our ruling on this point does not contradict Section 4 (a) of RA 8974
which provides for a scheme of direct and immediate initial payment to It must be emphasized that the conclusive ruling in the Resolution dated
the property owner in cases involving national government infrastructure 21 January 2004 in Agan v. PIATCO (Agan 2004) is that PIATCO, as builder
projects. of the facilities, must first be justly compensated in accordance with law
and equity for the Government to take over the facilities. It is on that
premise that the Court adjudicated this case in its 19 December 2005
Section 4 (a) of RA 8974 applies only to cases where the issue of Decision.
ownership of the expropriated property is not disputed. In cases where
the ownership is contested; where conflicting claims or interests over the
expropriated property exist; or where there are other incidents affecting While the Government refers to a judgment rendered by a London court
the complaint for expropriation, the governing rule is Section 9, Rule 67 of in favor of Takenaka and Asahikosan against PIATCO in the amount of
the Rules of Court. By creating a separate provision applicable only to the US$82 Million, it should be noted that this foreign judgment is not yet
latter cases, Section 14 of RA 8974 IRR359 necessarily acknowledged that binding on Philippine courts. It is entrenched in Section 48, Rule 39 of the
the scheme of immediate and direct initial payment is not an absolute Rules of Civil Procedure that a foreign judgment on the mere strength of
and all-encompassing rule applicable in all circumstances. its promulgation is not yet conclusive, as it can be annulled on the
grounds of want of jurisdiction, want of notice to the party, collusion,
fraud, or clear mistake of law or fact. It is likewise recognized in Philippine
We are aware of our pronouncement in the December 19, 2005 Gingoyon jurisprudence and international law that a foreign judgment may be
decision directing the Government to directly and immediately pay barred from recognition if it runs counter to public policy.
PIATCO the proffered value of ₱3billion. We rendered the December 19,
2005 Decision based on the fact that Takenaka and Asahikosan were not
ProvRem Rule 67 Fulltext Page 72 of 119
Assuming that PIATCO indeed has corresponding obligations to other land. The Republic can still consistently assert, in both actions for
parties relating to NAIA 3, the Court does not see how such obligations, expropriation and reversion, that the subject parcels of land are part of
yet unproven, could serve to overturn the Decision mandating that the the public domain.
Government first pay PIATCO the amount of 3.02 Million Pesos before it
may acquire physical possession over the facilities. This directive enjoining The record of the present case show that PIATCO has been the original
payment is in accordance with Republic Act No. 8974, and under the contracting party commissioned by the Government to construct the
mechanism established by the law the amount to be initially paid is that NAIA-IPT III based on a build-operate-transfer arrangement and who, in
which is provisionally determined as just compensation. The provisional this capacity, contracted out the actual construction to Takenaka and
character of this payment means that it is not yet final, yet sufficient under Asahikosan. Thus, when the NAIA-IPT III was built, it was in PIATCO's
the law to entitle the Government to the writ of possession over the name and account, although it subsequently owed sums to
expropriated property. subcontractors, incurred in the course of the construction. From this
perspective, PIATCO has been the owner recognized as such by the
There are other judicial avenues outside of this Motion for Government although the basis of its contractual relationship with the
Reconsideration wherein all other claims relating to the airport facilities Government was later on nullified. Takenaka and Asahikosan, on the other
may be ventilated, proved and determined. Since such claims involve hand, had always been subcontractors with whom the Government did
factual issues, they must first be established by the appropriate trier of not have any formal link. These facts indubitably show that PIATCO has
facts before they can be accorded any respect by or binding force on this been the owner of the NAIA-IPT III entitled to receive the just
Court.361 [Emphasis supplied] compensation due. Takenaka and Asahikosan for their part, have not
shown that they possess legal title or colorable title to the NAIA-IPT III
Contrary to Takenaka and Asahikosan's position, in the Philippine that would defeat PIATCO's ownership.
jurisdiction, the person who is solely entitled to just compensation is the
owner of the property at the time of the taking.362 As shown below, the To recap and expound on the matter:
test of who shall receive just compensation is not who built the terminal,
but rather who its true owner is. First, Takenaka and Asahikosan were mere subcontractors in the nullified
NAIA-IPT III project. That Takenaka and Asahikosan actually built the
From the express provision of Section 4 of RA 8974, just compensation NAIA-IPT III does not make them the owner of the terminal building.
shall only be paid to the property owner. We implead persons with lawful
interests in the property in order to determine the person who shall We carefully point out that our finding in this case that Takenaka and
receive just compensation. Note that the last paragraph, Section 4 of RA Asahikosan are the actual builders of the NAIA-IPT III does not contravene
8974 states: "When the decision of the court becomes final and executory, our rulings in Agan and Gingoyon that PIATCO is the builder of the
the implementing agency shall pay the owner the difference between the NAIAIPT III. The word "builder" is broad enough to include the contractor,
amount already paid and the just compensation as determined by the PIATCO, and the subcontractors, Takenaka and Asahikosan, in the nullified
court." This provision thus envisions a situation where the court NAIA-IPT III project. Republic Act No. 4566367 defines a "builder" as
determines with finality, for purposes of payment of just compensation, follows:
the conflicting claims of the defendants and intervenors.
In Gingoyon, the Court loosely used the word "builder" and "owner"
In Calvo v. Zandueta,364 the Court stayed the execution of the trial court's interchangeably. We clarify, however, that a builder is different from the
judgment ordering the provincial treasurer of Pangasinan to pay Aquilino owner of the property. As we stated above, a builder includes the
Calvo just compensation due to the pendency of the interpleader that contractor and the subcontractor. On the other hand, the "owner" who is
Juana Ordoñez brought based on her own claim of ownership of the constitutionally entitled to just compensation is the person who has legal
expropriated land. Ordoñez asserted that she acquired all rights and title to the property. Logically, a builder is not necessarily the owner of the
interests on the subject land when she purchased it during the execution property and vice-versa.
sale while the expropriation proceedings were still pending.
However, the authority to resolve ownership should be taken in the In November 1924, the municipality of San Quintin, Pangasinan filed an
proper context. The discussion in Republic was anchored on the question action for expropriation of a parcel of land owned by Aquilino Calvo and
with a Certificate of Title No. 25100.
of who among the respondents claiming ownership of the property must
be indemnified by the Government:
On November 25, 1925, the Court of First Instance (CFI) approved the
Now, to determine the person who is to be indemnified for the commissioners' valuation of the subject land in the sum of ₱6,943.25. The
expropriation of Lot 6, Block 6, Psd-2017, the court taking cognizance of municipality of San Quintin appealed the case but subsequently withdrew
the expropriation must necessarily determine if the sale to the Punzalan the appeal on June 23, 1926. The CFI approved the withdrawal of appeal
on July 20, 1926.
spouses by Antonio Feliciano is valid or not. For if valid, said spouses must
be the ones to be paid by the condemnor; but if invalid, the money will be
paid to someone else. x x x In the meantime, Juana Ordoñez levied on the subject land after she
obtained a favorable judgment against Calvo. The levy was recorded on
Thus, such findings of ownership in an expropriation proceeding should the certificate of title on December 23, 1925. Thereafter, the sheriff sold
not be construed as final and binding on the parties. By filing an action the subject land to Ordoñez inan execution sale. On January 23, 1926, the
for expropriation, the condemnor (petitioner), merely serves notice that it sale was duly entered by memorandum on the certificate of title. On the
is taking title to and possession of the property, and that the defendant is same date, Ordoñez filed a motion for substitution as a defendant in the
asserting title to or interest in the property, not to prove a right to expropriation case on the ground that she acquired all the rights and
possession, but to prove a right to compensation for the taking. interests of Calvo on the subject land.
If at all, this situation is akin to ejectment cases in which a court is On June 29, 1926, the CFI declared the November 25, 1925 decision final
temporarily authorized to determine ownership, if only to determine who and ordered the provincial treasurer of Pangasinan to pay Calvo a part of
is entitled to possession. This is not conclusive, and it remains open to just compensation. The following day, Ordoñez filed a motion praying for
challenge through proper actions. The consequences of Sec. 9, Rule 67 the revocation of the June 29, 1926 order and for the provincial treasurer
of Pangasinan to retain the award of just compensation.
cannot be avoided, as they are due to the intimate relationship of the
issue of ownership with the claim for the expropriation payment.
(Emphasis supplied) On July 20, 1926, the CFI revoked the June 29, 1926 order and ordered the
provincial treasurer of Pangasinan to retain the money until further orders
9.c. A final disposition in the eminent of the court. After the CFI denied Calvo et al.'s motion for reconsideration,
domain case with respect to the order they filed a petition for certiorari before the Court.
of payment to a particular person shall
be final and executory. The Court denied the petition. The Court ruled that "assuming that the
judgment of November 25, 1925, constituted a final determination of the
To avoid future litigation, we emphasize that a final disposition in the petitioners' right to receive the award," Ordoñez was not a party to the
eminent domain case with respect to the order to pay a particular person expropriation case and, therefore, could not be bound by the judgment.
shall be final and executory upon the lapse of relevant periods under Rule Ordoñez' claim that she stands subrogated to Calvo's right to just
39 of the Rules of Court. The recourse of the person claiming ownership compensation has the appearance of validity. The judicial determination
over the expropriated property in any subsequent case is against the of her claim may be adjudicated in an action for interpleader which was
adjudged property owner in the expropriation case. then pending when the motion for substitution was filed. Consequently,
the trial court correctly stayed the execution of the judgment in the
expropriation case. Whenever necessary to promote the ends of justice,
The principle of res judicata applies in this particular matter because the courts have the power to temporarily stay executions of judgments
issues on the amount of just compensation and the person to be paid just rendered by them."
compensation are the central issues in the second phase of expropriation.
Based on this principle, a final judgment or decree on the merits by a
court of competent jurisdiction is conclusive of the rights of the parties or Clearly, the November 25, 1925 decision in Calvo was not yet final and
their privies in all later suits on points and matters determined in the executory when the Court suspended the execution of that ruling. The
former suit.369 July 29, 1926 order revoked the June 29, 1926 order which in turn
declared the finality of the November 25, 1925 decision of the CFI.
Ordoñez filed a motion for the reversal of the June 29, 1926 order prior to
There would be no end to litigation in an eminent domain case if we rule the CFI's withdrawal of appeal on July 20, 1926. Significantly, the CFI
otherwise; we would only foment mockery of the judicial proceedings as approved the withdrawal of appeal on the same date that the CFI revoked
the order of payment in the eminent domain case would never be truly the June 29, 1926 order and ordered the provincial treasurer of
final and executory. Furthermore, to the detriment of the public, interest Pangasinan to withhold the just compensation. There is thus no basis to
would continue to accrue on just compensation if we rule that the order Takenaka and Asahikosan's claim that the execution of a final and
of payment to a particular recipient can be reversed in the subsequent executory judgment on just compensation may be suspended if there is
ProvRem Rule 67 Fulltext Page 74 of 119
still a subsisting case regarding the disputed ownership of the national infrastructure projects upon the issuance of the writ of
expropriated property. possession. When the taking of the property precedes the payment of just
compensation, the Government shall indemnify the property owner by
9.d. The determination of whether the way of interest.
NAIA-IPT III shall be burdened by liens
and mortgages even after the full "Taking" under the power of eminent domain means entering upon
payment of just compensation is still private property for more than a momentary period, and under the
premature. warrant or color of legal authority, devoting it to public use, or otherwise
informally appropriating or injuriously affecting it in such a way as
The determination of whether the NAIA-IPT III shall be burdened by liens substantially to oust the owner and deprive him of all beneficial
and mortgages even after the full payment of just compensation is still enjoyment thereof.373
premature. The enforceability of Claim Nos. HT-04-248 and HT-05-269 in
this jurisdiction has yet to be decided by the Court in G.R. No. 202166. "Taking" of property takes place when: (1) the owner is actually deprived
Furthermore, the application of Article 2242 of the Civil or dispossessed of his property;(2) there is a practical destruction or a
Code371 presupposes that PIATCO declared insolvency or has been material impairment of the value of his property; (3) the owner is deprived
declared insolvent. This, of course, should be litigated in insolvency of the ordinary use of the property, or (4) when he is deprived of the
proceedings, not in the present eminent domain case. jurisdiction, supervision and control of his property.374
The Court cannot pass upon the validity and enforceability of civil claims The taking of property is different from the transfer of the property title
against PIATCO by creditor/s in an expropriation case or the existence of from the private owner to the Government. Under Rule 67 of the Rules of
liens on the NAIA-IPT III. Section 114 of Republic Act No. Court, there are two phases of expropriation: (a) the condemnation of the
10142372 provides: property after it is determined that its acquisition will be for a public
purpose or public use; and (b) the determination of just compensation to
Section 114. Rights of Secured Creditors. - The Liquidation Order shall not be paid for the taking of private property to be made by the court with
affect the right of a secured creditor to enforce his lien in accordance with the assistance of not more than three commissioners.
the applicable contract or law. A secured creditor may:
The first phase is concerned with the determination of the Government's
(a) waive his right under the security or lien, prove his claim in authority to exercise the power of eminent domain and the propriety of
the liquidation proceedings and share in the distribution of the its exercise in the context of the facts involved in the suit. The court
assets of the debtor; or declares that the Government has a lawful right to take the property
sought to be condemned, for the public use or purpose described in the
complaint.375
(b) maintain his rights under the security or lien:
The second phase relates to the just amount that the Government shall
If the secured creditor maintains his rights under the security or lien: compensate the property owner.376
(1) the value of the property may be fixed in a manner agreed Whenever the court affirms the condemnation of private property in the
upon by the creditor and the liquidator. When the value of the first phase of the proceedings, it merely confirms the Government's lawful
property is less than the claim it secures, the liquidator may right to take the private property for public purpose or public use. The
convey the property to the secured creditor and the latter will court does not necessarily rule that the title to the private property
be admitted in the liquidation proceedings as a creditor for the likewise vests on the Government.
balance. If its value exceeds the claim secured, the liquidator
may convey the property to the creditor and waive the debtor's
right of redemption upon receiving the excess from the The transfer of property title from the property owner to the Government
creditor; is not a condition precedent to the taking of property. The State may take
private property prior to the eventual transfer of title of the expropriated
property to the State.
(2) the liquidator may sell the property and satisfy the secured
creditor's entire claim from the proceeds of the sale; or
In fact, there are instances when the State takes the property prior to the
filing of the complaint for expropriation or without involving the transfer
(3) the secure creditor may enforce the lien or foreclose on the of title.377 In People v. Fajardo,378 the Court ruled that the municipal
property pursuant to applicable laws. mayor's refusal to give the property owner the permission to build a
house on his own land on the ground that the structure would destroy
10. The exercise of eminent the beauty of the public plaza amounts to the taking of the property
domain from the perspective of requiring just compensation.
"taking."
In National Power Corporation (NPC) v. Spouses Malit,379 the NPC's
10.a. The Government may take transmission lines had to pass the Spouses Malit's property. The Court
the property for public ruled that the NPC's easement of right-of-wayon the land was equivalent
purpose or public use upon to the taking of property. The limitation imposed by the NPC against the
the issuance and effectivity use of the land for an indefinite period deprived the Spouses Malit of the
of the writ of possession. lot's ordinary use. Consequently, the NPC shall give the Spouses Malit just
compensation.
To clarify and to avoid confusion in the implementation of our judgment,
the full payment of just compensation is not a prerequisite for the The reckoning period, however, of the valuation of just compensation is
Government's effective taking of the property. As discussed above, RA the date of taking or the filing of the complaint for expropriation,
8974 allows the Government to enter the property and implement whichever is earlier. In either case, it is only after the finality of the second
ProvRem Rule 67 Fulltext Page 75 of 119
stage and after the payment of just compensation that the title shall pass enter upon the property of the defendant and appropriate the same for
to the Government. As we have ruled in Gingoyon, the title to the public use or purpose shall not be delayed by an appeal from the
property does not pass to the condemnor until just compensation is paid. judgment. But if the appellate court determines that plaintiff has no right
of expropriation, judgment shall be rendered ordering the Regional Trial
Under Section 4 of RA 8974, the Government is only entitled to a writ of Court to forthwith enforce the restoration to the defendant of the
possession upon initial payment of just compensation to the defendant, possession of the property, and to determine the damages which the
and upon presentment to the court of a certificate of availability of funds. defendant sustained and may recover by reason of the possession taken
by the plaintiff. (11a)
A writ of possession does not transfer title to the Government; it is "a writ
of execution employed to enforce a judgment to recover the possession The State's taking of the property is not based on trust or contract, but is
of land. It commands the sheriff to enter the land and give its possession founded on its inherent power to appropriate private property for public
to the person entitled under the judgment."380 Section 4 of RA 8974 use. It is also for this reason - to compensate the property owner for the
further states that the writ of possession is an order to take possession of deprivation of his right to enjoy the ordinary use of his property until the
the property and to start the implementation of the project, to wit: naked title to the property passed to the State - that the State pays
interest from the time of the taking of the property until full payment of
just compensation.
Section 4. Guidelines for Expropriation Proceedings. - Whenever it is
necessary to acquire real property for the right-of-way or location for any
national government infrastructure project through expropriation, the This conclusion is consistent with the dispositive portion of our ruling in
appropriate implementing agency shall initiate the expropriation Gingoyon where we authorized the Government to perform acts that are
proceedings before the proper court under the following guidelines: essential to the operation of the NAIA-IPT III as an international airport
terminal upon the effectivity of the writ of possession. The authority
granted to the Government encompasses "the repair, reconditioning and
(a) Upon the filing of the complaint, and after due notice to the improvement of the complex, maintenance of the existing facilities and
defendant, the implementing agency shall immediately pay the equipment, installation of new facilities and equipment, provision of
owner of the property the amount equivalent to the sum of (1) services and facilities pertaining to the facilitation of air traffic and
one hundred percent (100%) of the value of the property based transport, and other services that are integral to a modern-day
on the current relevant zonal valuation of the Bureau of Internal international airport."
Revenue (BIR); and (2) the value of the improvements and/or
structures as determined under Section 7 hereof;
The present case involves the second stage of expropriation or the
determination of replacement cost of the NAIA-IPT III. The first stage has
(b) In provinces, cities, municipalities and other areas where become final after the promulgation of the December 19, 2005 decision
there is no zonal valuation, the BIR is hereby mandated within and the February 1, 2006 resolution in Gingoyon where we affirmed the
the period of sixty (60) days from the date of the expropriation Government's power to expropriate the NAIA-IPT III and where we
case, to come up with a zonal valuation for said area; and
ordered the issuance of a writ of possession upon the Government's
direct payment of the proffered value of ₱3 billion to PIATCO. Thus, the
(c) In case the completion of a government infrastructure reinstatement of the writ of possession on September 11, 2006,
project is of utmost urgency and importance, and there is no empowered the Government to take the property for public use, and to
existing valuation of the area concerned, the implementing effectively deprive PIATCO of the ordinary use of the NAIA-IPT III.
agency shall immediately pay the owner of the property its
proffered value taking into consideration the standards B. G.R. No. 181892
prescribed in Section 5 hereof.
In G.R. No. 181892, the RTC, in its order dated May 5,2006, ordered the
Before the court can issue a Writ of Possession, the implementing agency appointment of an independent appraiser to conduct the valuation of the
shall present to the court a certificate of availability of funds from the NAIA-IPT III upon the BOC's request. Thereafter, the Government and
proper official concerned. PIATCO submitted their lists of nominees to this position. On May 3, 2007,
the RTC engaged the services of DG Jones and Partners as an
In the event that the owner of the property contests the implementing independent appraiser. On May 18, 2007, the RTC directed the
agency's proffered value, the court shall determine the just compensation Government to submit a Certificate of Availability of Funds to cover DG
to be paid the owner within sixty (60)days from the date of filing of the Jones and Partners' $1.9 Million appraisal fee.
expropriation case. When the decision of the court becomes final and
executory, the implementing agency shall pay the owner the difference The Government disputed the May 3 and 18, 2007 orders and argued that
between the amount already paid and the just compensation as the RTC had no power to appoint an independent appraiser. The
determined by the court. (Emphasis supplied) Government insisted that the RTC should exclusively choose among its
nominees pursuant to Section 7 of RA 8974 as well as Sections 10 and 11
The Government is provisionally authorized to take the property for public of RA 8974 IRR.
purpose or public use whenever the court issues a writ of possession in
favor of the Government. It may take possession of the property or The RTC sustained the appointment of DG Jones and Partners in an order
effectively deprive the property owner of the ordinary use of the property. dated January 7, 2008.The RTC ruled that its power to appoint the
If the court, however, later on determines that the State has no right of members of the BOC under Section 5, Rule 67 of the Rules of Court was
expropriation, then the State shall immediately restore the defendant of broad enough as to include the appointment of an independent
the possession of the property and pay the property owner damages that appraiser.
he sustained. Section 11, Rule 67 of the Rules of Court: Section 11. Entry
not delayed by appeal; effect of reversal. - The right of the plaintiff to
ProvRem Rule 67 Fulltext Page 76 of 119
On February 6, 2008, the Government filed a petition for certiorari with not the BOC or the independent appraiser. DG Jones and Partners' rule
prayer for the issuance of a temporary restraining order and/or a writ of has simply been overtaken by events.
preliminary injunction before the Court assailing the May 3, 2007; May 18,
2007; and January 7, 2008 orders (G.R. No. 181892). As a final note, while we stated in Gingoyon that the RTC may validly
appoint commissioners in the appraisal of the NAIA-IPT III, the trial court
On January 9, 2008, the Court issued a temporary restraining order should have appointed commission members who possessed technical
against the implementation of the May 3, May 18, and January 7, 2008 expertise in the appraisal of a complex terminal building. Under Section 5,
orders. Rule 67 of the Rules of Court, the BOC's main functions are to ascertain
and report to the court the just compensation for the property sought to
On August 5, 2010, the RTC ordered the parties to submit their appraisal be taken. The appointment of technical experts as commissioners would
reports of the NAIA-IPTIII. The Government, PIATCO, Takenaka and have avoided the DG Jones aspect of the controversy as there would have
Asahikosan separately hired their own appraisers who came up with their been no need for the trial court to hire an independent appraiser. This
different valuations of the NAIA-IPT III. would have avoided the duplication of tasks and delay in the proceedings.
On March 31, 2011, the BOC submitted its Final Report recommending To summarize, we rule that:
the payment of just compensation in the amount of $376,149,742.56. On
May 23, 2011, the RTC rendered a decision ordering the Government to (1) The May 23, 2011 decision of the RTC in Civil Case No. 04-
pay PIATCO just compensation in the amount of $116,348,641.10. The CA 0876 is valid. The parties were afforded procedural due process
modified the RTC ruling and held that the just compensation as of July 31, since their respective positions, counter-positions, and evidence
2013, amounts to $371,426,742.24. were considered by the trial court in rendering the decision.
These developments render the appointment of DG Jones and Partners as (2) Replacement cost is a different standard of valuation from
an independent appraiser of the NAIA-IPT III ineffective. An appraiser is a fair market value. Fair market value is the price at which a
person selected or appointed by competent authority to ascertain and property may be sold by a seller who is not compelled to sell
state the true value of goods or real estate.381 The purpose of appointing and bought by a buyer who is not compelled to buy. In
DG Jones and Partners as an independent appraiser was to assist the BOC contrast, replacement cost is the amount necessary to replace
in appraising the NAIA-IPT III. In fact, the BOC requested the RTC to the improvements/structures, based on the current market
engage the services of an independent appraiser because the BOC had no prices for materials, equipment, labor, contractor's profit and
technical expertise to conduct the valuation of the NAIA-IPT III. In turn, overhead, and all other attendant costs associated with the
the BOC was to recommend to the RTC the replacement cost of the NAIA- acquisition and installation in place of the affected
IPT III. Under Section 8, Rule 67 of the Rules of Court, the RTC may accept improvements/structures. (3) In computing just compensation,
or reject, whether in whole or in part, the BOC's report which is merely the Court shall use the replacement cost method and the
advisory and recommendatory in character. standards laid down in Section 5 of RA 8974 as well as Section
10 of RA 8974. The Court shall likewise consider equity in the
We find, under the given circumstances, that the propriety of the determination of the just compensation due for NAIA-IPT III.
appointment of DG Jones and Partners and the corollary issue of who
should shoulder the independent appraiser's fees moot and academic. (4) The use of depreciated replacement cost method is
consistent with the principle that the property owner shall be
An actual case or controversy exists when there is a conflict of legal rights compensated for his actual loss. It is consistent as well with
or an assertion of opposite legal claims between the parties that is Section 10 of RA 8974 IRR which provides that the courts shall
susceptible or ripe for judicial resolution.382 A justiciable controversy must consider the kinds and quantities of materials/equipment used
not be moot and academic or have no practical use or value. In other and the configuration and other physical features of the
words, there must be a definite and concrete dispute touching on the property, among other things, in the valuation of the NAIAIPT
legal relations of the parties who have adverse legal interests. Otherwise, III. The Government should not compensate PIATCO based on
the Court would simply render an advisory opinion on what the law would the value of a modern equivalent asset that has the full
be on a hypothetical state of facts. The disposition of the case would not functional utility of a brand new asset.
have any practical use or value as there is no actual substantial relief to
which the applicant would be entitled to and which would be negated by (5) The amount of just compensation as of the filing of the
the dismissal or denial of the petition.383 complaint for expropriation on December 21, 2004, is
$326,932,221.26. From this sum shall be deducted the proffered
After the BOC submitted its Final Report on the replacement cost of the value of $59,438,604.00. The resulting difference of
NAIA-IPT III based on the appraisal reports and other evidence submitted $267,493,617.26 shall earn a straight interest of 12% per annum
by the parties, the appointment of DG Jones and Partners ceased to serve from September 11, 2006 until June 30, 2013, and a straight
any purpose. Any subsequent findings of DG Jones and Partners interest of 6% per annum from July 1, 2013, until full payment.
regarding the appraisal of the NAIA-IPT III would cease to have any
practical materiality since the RTC proceedings on the amount of just (6) PIATCO, as the owner of the NAIA-IPT III, shall solely receive
compensation had already been terminated. As with the BOC, the the just compensation. Based on the last paragraph, Section 4
independent appraiser's valuation of the NAIAIPT III was advisory and of RA 8974 and the prevailing jurisprudence, it is the owner of
recommendatory in character. DG Jones and Partners' valuation was only the expropriated property who is constitutionally entitled to just
preliminary and was not by any means meant to be final and conclusive compensation. Other claimants should be impleaded or may
on the parties. In the exercise of its judicial functions, it is the intervene in the eminent domain case if the ownership of the
expropriation court who has the final say on the amount of just property is uncertain or there are conflicting claims on the
compensation. Since the RTC has already made a factual finding on the property pursuant to Section 9, Rule 67 of the Rules of Court.
valuation of the NAIA-IPT III, there is no point in appointing DG Jones and
Partners as an independent appraiser. To reiterate, valuation involves a (7) The Government may deprive PIATCO of the ordinary use of
factual question that is within the province of the expropriation court, and the NAIA-IPT III upon the issuance and effectivity of the writ of
METROPOLITAN CEBU WATER DISTRICT (MCWD), Petitioner, 2. Whether the procedure in obtaining a writ of possession was
vs. properly observed.
J. KING AND SONS COMPANY, INC., Respondent.
Eminent domain is the right of the state to acquire private property for
DECISION public use upon payment of just compensation.25 The power of eminent
domain is inseparable in sovereignty being essential to the existence of
TINGA, J.: the State and inherent in government. Its exercise is proscribed by only
two Constitutional requirements: first, that there must be just
compensation, and second, that no person shall be deprived of life, liberty
Before us is a Rule 45 petition1 which seeks the reversal of the or property without due process of law26 .
decision2 and resolution3 of the Court of Appeals in CA-G.R. CEB-SP No.
00810. The Court of Appeals’ decision nullified the orders4 and the writ of
ProvRem Rule 67 Fulltext Page 78 of 119
As an inherent sovereign prerogative, the power to expropriate pertains The letter not only explicitly debunks respondent’s claim that there was
to the legislature. However, Congress may, as in fact it often does, no authorization from LWUA but it also identifies the lot sought to be
delegate the exercise of the power to government agencies, public expropriated with sufficient particularity.
officials and quasi-public entities. Petitioner is one of the numerous
government offices so empowered. Under its charter, P.D. No. 198, as It is settled that the validity of a complaint may be questioned
amended,27 petitioner is explicitly granted the power of eminent domain. immediately upon its filing through a motion to dismiss or raised
thereafter as an affirmative defense. However, there is no need to further
On 7 November 2000, Congress enacted R.A. No. 8974, entitled "An Act belabor the issue since it is established that petitioner has the legal
To Facilitate The Acquisition Of Right-Of-Way, Site Or Location For capacity to institute the expropriation complaint.
National Government Infrastructure Projects And For Other Purposes."
Section 2 thereof defines national government projects as follows: Anent the second issue involving the issuance of a writ of possession, a
discussion on the various stages in an expropriation proceeding is
Sec. 2. National Government Projects.—The term "national government necessary.
projects" shall refer to all national government infrastructure, engineering
works and service contracts, including projects undertaken by The general rule is that upon filing of the expropriation complaint, the
government-owned and -controlled corporations, all projects covered by plaintiff has the right to take or enter into possession of the real property
Republic Act No. 6957, as amended by Republic Act No. 7718, otherwise involved if he deposits with the authorized government depositary an
known as the Build-Operate-and-Transfer Law, and other related and amount equivalent to the assessed value of the property for purposes of
necessary activities, such as site acquisition, supply and/or installation of taxation. An exception to this procedure is provided by R.A. No. 897434 . It
equipment and materials, implementation, construction, completion, requires the payment of one hundred percent (100%) of the zonal value
operation, maintenance, improvement, repair and rehabilitation, of the property to be expropriated to entitle the plaintiff to a writ of
regardless of source of funding." (emphasis ours) possession.
R.A. No. 8974 includes projects undertaken by government owned and In an expropriation proceeding there are two stages, first, is the
controlled corporations,28 such as petitioner. Moreover, the Implementing determination of the validity of the expropriation, and second is the
Rules and Regulations of R.A. No. 8974 explicitly includes water supply, determination of just compensation.35 In Tan v. Republic,36 we explained
sewerage, and waste management facilities among the national the two (2) stages in an expropriation proceeding to wit:
government projects covered by the law.29 It is beyond question,
therefore, that R.A. No. 8974 applies to the expropriation subject of this
case. (1) Determination of the authority of the plaintiff to exercise the
power of eminent domain and the propriety of its exercise in
the context of the facts involved in the suit. It ends with an
The Court of Appeals held that the board resolution authorizing the order, if not of dismissal of the action, with condemnation
expropriation lacked exactitude and particularity. It described the board declaring that the plaintiff has a lawful right to take the
resolution as akin to a general warrant in criminal law and as such property sought to be condemned for the public use or
declared it invalid. Respondent reiterates the same argument in its purpose described in the complaint, upon payment of just
comment and adds that petitioner’s exercise of the power of eminent compensation. An order of expropriation is final. An order of
domain was not reviewed by the LWUA. dismissal, if this be ordained, would be a final one, as it finally
disposes of the action and leaves nothing more to be done by
A corporation does not have powers beyond those expressly conferred the courts on the merits. The order of expropriation would also
upon it by its enabling law. Petitioner’s charter provides that it has the be a final one for after its issuance, no objection to the right of
powers, rights and privileges given to private corporations under existing condemnation shall be heard. The order of expropriation may
laws, in addition to the powers granted in it.30 All the powers, privileges, be appealed by any party aggrieved thereby by filing a record
and duties of the district shall be exercised and performed by and on appeal.
through the board and that any executive, administrative or ministerial
power may be delegated and redelegated by the board to any of its (2) Determination by the court of the just compensation for the
officers or agents for such property sought to be taken with the assistance of not more
than three (3) commissioners. The order fixing the just
purpose.31 Being a corporation, petitioner can exercise its powers only compensation on the basis of the evidence before the court
through its board of directors. and findings of the commissioners would likewise be a final
one, as it would leave nothing more to be done by the court
For petitioner to exercise its power of eminent domain, two requirements regarding the issue. A second and separate appeal may be
should be met, namely: first, its board of directors passed a resolution taken from this order fixing the just compensation.37
authorizing the expropriation, and; second, the exercise of the power of
eminent domain was subjected to review by the LWUA. In this case, Thus, the determination of the necessity of the expropriation is a
petitioner’s board of directors approved on 27 February 2004, Board justiciable question which can only be resolved during the first stage of an
Resolution No. 015-200432 authorizing its general manager to file expropriation proceeding. Respondent’s claim that the expropriated
expropriation and other cases. Moreover, the LWUA did review and gave property is too small to be considered for public use can only be resolved
its stamp of approval to the filing of a complaint for the expropriation of during that stage.
respondent’s lot. Specifically, the LWUA through its Administrator,
Lorenzo H. Jamora, wrote petitioner’s manager, Armando H. Paredes, a Further, the Court of Appeals ruled that Section 4 of R.A. No. 8974 runs
letter dated 28 February 200533 authorizing petitioner to file the counter to the express mandate of Section 2 of Rule 67.38 It held that the
expropriation case "against the owner of the five-square meter portion of law undermined the principle that the determination of just compensation
Lot No. 921-A covered by TCT No. 168805, pursuant to Section 25 of P.D. is a judicial function. However, this Court has already settled the issue. In
No. 198, as amended." Republic v. Gingoyon,39 this Court held that:
R.A. No. 8974 provides a different scheme for the obtention of a writ of
possession. The law does not require a deposit with a government bank;
instead it requires the government to immediately pay the property #8 G.R. No. 156093 February 2, 2007
owner.42 The provisional character of this payment means that it is not yet
final, yet, sufficient under the law to entitle the Government to the writ of NATIONAL POWER CORP., Petitioner,
possession over the expropriated property.43 The provisional payment is a vs.
prerequisite44 and a trigger45 for the issuance of the writ of possession. In SPOUSES NORBERTO AND JOSEFINA DELA CRUZ, METROBANK,
Gingoyon,46 we held that: Dasmariñas, Cavite Branch, REYNALDO FERRER, and S.K. DYNAMICS
MANUFACTURER CORP., Respondents.
It is the plain intent of Rep. Act No. 8974 to supersede the system of
deposit under Rule 67 with the scheme of "immediate payment" in cases DECISION
involving national government infrastructure projects.47
The Case
Rep. Act. No. 8974 is plainly clear in imposing the requirement of
immediate prepayment, and no amount of statutory deconstruction can
evade such requisite. It enshrines a new approach towards eminent In this petition for review under Rule 45 of the Rules of Court, petitioner
domain that reconciles the inherent unease attending expropriation National Power Corporation (NAPOCOR) seeks to annul and set aside the
proceedings with a position of fundamental equity. While expropriation November 18, 2002 Decision1 of the Court of Appeals (CA) in CA-G.R. CV
proceedings have always demanded just compensation in exchange for No. 67446, which affirmed the December 28, 1999 Order2 of the Imus,
private property, the previous deposit requirement impeded immediate Cavite Regional Trial Court (RTC), Branch XX in Civil Case No. 1816-98,
compensation to the private owner, especially in cases wherein the which fixed the fair market value of the expropriated lots at PhP 10,000.00
per square meter.
determination of the final amount of compensation would prove highly
disputed. Under the new modality prescribed by Rep. Act. No. 8974, the
private owner sees immediate monetary recompense, with the same The Facts
degree of speed as the taking of his/her property.481avvphi1
Petitioner NAPOCOR is a government-owned and controlled corporation
Petitioner was supposed to tender the provisional payment directly to created under Republic Act No. 6395, as amended, with the mandate of
respondent during a hearing which it had failed to attend. Petitioner, developing hydroelectric power, producing transmission lines, and
then, deposited the provisional payment with the court. The trial court did developing hydroelectric power throughout the Philippines. NAPOCOR
not commit an error in accepting the deposit and in issuing the writ of decided to acquire an easement of right-of-way over portions of land
possession. The deposit of the provisional amount with the court is within the areas of Dasmariñas and Imus, Cavite for the construction and
equivalent to payment. maintenance of the proposed Dasmariñas-Zapote 230 kV Transmission
Line Project.3
Indeed, Section 4 of R.A. No. 8974 is emphatic to the effect that "upon
compliance with the guidelines…the court shall immediately issue to the
ProvRem Rule 67 Fulltext Page 80 of 119
On November 27, 1998, petitioner filed a Complaint4 for eminent domain Orchard Golf and Country Club
and expropriation of an easement of right-of-way against respondents as
registered owners of the parcels of land sought to be expropriated, which Golden City Subdivision
were covered by Transfer Certificates of Title (TCT) Nos. T-313327, T-
671864, and T-454278. The affected areas were 51.55, 18.25, and 14.625
square meters, respectively, or a total of 84.425 square meters. Southfield Subdivisions
After respondents filed their respective answers to petitioner’s Complaint, Arcontica Sports Complex
petitioner deposited PhP 5,788.50 to cover the provisional value of the
land in accordance with Section 2, Rule 67 of the Rules of Court.5 Then, on Max’s Restaurant
February 25, 1999, petitioner filed an Urgent Ex-Parte Motion for the
Issuance of a Writ of Possession, which the trial court granted in its March Waltermart Shopping Mall
9, 1999 Order. The trial court issued a Writ of Possession over the lots
owned by respondents spouses de la Cruz and respondent Ferrer on
UMC Medical Center
March 10, 1999 and April 12, 1999, respectively.
The commissioners conducted an ocular inspection of S.K. Dynamics’ IV. HIGHEST AND MOST PROFITABLE USE
property, and on October 8, 1999, they submitted a report to the trial
court, with the following pertinent findings:
xxxx
In arriving our [sic] estimate of values our studies and analysis include the
The subject property is situated within the
following:
residential/commercial zone and considering the area affected
and taking into consideration, their location, shape, lot
I. PROPERTY LOCATION topography, accessibility and the predominant uses of
properties in the neighborhood, as well as the trend of land
As shown to us on-site during our ocular inspection, developments in the vicinity, we are on the opinion that the
the appraised property is land only, identified as the highest and most profitable use of the property is good for
area affected by the construction of the National residential and commercial purposes.
Power Corporation (NPC) Dasmariñas-Zapote 230KV
Transmission Lines Project, located within Barangay V. VALUATION OF LAND MARKET DATA
Salitran, Dasmariñas, Cavite registered in the name of
S.K. Dynamic[s] Manufacture[r], Corp., under Transfer
xxxx
Certificate of Title No. T-454278.
On December 1, 1999, respondent Ferrer filed a motion adopting in toto The PAR Resolution alluded to by [petitioner] was passed in 1995 or four
the commissioners’ report with respect to the valuation of his (4) years [before] the lot in question was taken over by the government.
property.8 On December 28, 1999, the trial court consequently issued the This explains why the price or cost of the land has considerably increased.
Order approving the commissioners’ report, and granted respondent Besides, the valuation of P10,000.00 per sq.m. was the one recommended
Ferrer’s motion to adopt the subject report. Subsequently, the just by the commissioner designated by [petitioner] itself and concurred in by
compensation for the disparate properties to be expropriated by the Provincial Assessor of Cavite.
petitioner for its project was uniformly pegged at PhP 10,000.00 per
square meter. Be that as it may, the Motion for Reconsideration is denied.
In ruling that petitioner was not deprived of due process because it was Second Issue: The legal basis for the determination of just compensation
able to file a Motion for Reconsideration, the CA had this to say: was insufficient
[Petitioner], further, asserts that "the appointed commissioners failed to In this case, it is not disputed that the commissioners recommended that
conduct a hearing to give the parties the opportunity to present their the just compensation be pegged at PhP 10,000.00 per square meter. The
respective evidence. According to [petitioner], the Commissioners commissioners arrived at the figure in question after their ocular
Valuation Report was submitted on October 8, 1999 in violation of the inspection of the property, wherein they considered the surrounding
appellant’s right to due process as it was deprived of the opportunity to structures, the property’s location and, allegedly, the prices of the other,
present evidence on the determination of the just compensation." contiguous real properties in the area. Furthermore, based on the
commissioners’ report, the recommended just compensation was
determined as of the time of the preparation of said report on October 5,
We are not persuaded. 1999.
The filing by [petitioner] of a motion for reconsideration accorded it In B.H. Berkenkotter & Co. v. Court of Appeals, we held, thus:
ample opportunity to dispute the findings of the commissioners, so that
[petitioner] was as fully heard as there might have been hearing actually
taken place. "Denial of due process cannot be successfully invoked by a Just compensation is defined as the full and fair equivalent of the
party who has had the opportunity to be heard on his motion for property sought to be expropriated. The measure is not the taker’s gain
reconsideration." (Vda. De Chua vs. Court of Appeals, 287 SCRA 33, 50).16 but the owner’s loss. The compensation, to be just, must be fair not only
to the owner but also to the taker. Even as undervaluation would deprive
the owner of his property without due process, so too would its
In this respect, we are constrained to disagree with the CA ruling, and overvaluation unduly favor him to the prejudice of the public.
therefore, set it aside.
To determine just compensation, the trial court should first ascertain the
While it is true that there is jurisprudence supporting the rule that the market value of the property, to which should be added the consequential
filing of a Motion for Reconsideration negates allegations of denial of due damages after deducting therefrom the consequential benefits which may
process, it is equally true that there are very specific rules for arise from the expropriation. If the consequential benefits exceed the
expropriation cases that require the strict observance of procedural and consequential damages, these items should be disregarded altogether as
substantive due process,17 because expropriation cases involve the the basic value of the property should be paid in every case.
admittedly painful deprivation of private property for public purposes and
the disbursement of public funds as just compensation for the private
property taken. Therefore, it is insufficient to hold that a Motion for The market value of the property is the price that may be agreed upon by
Reconsideration in an expropriation case cures the defect in due process. parties willing but not compelled to enter into the contract of sale. Not
unlikely, a buyer desperate to acquire a piece of property would agree to
pay more, and a seller in urgent need of funds would agree to accept less,
As a corollary, the CA’s ruling that "denial of due process cannot be than what it is actually worth. x x x
successfully invoked by a party who has had the opportunity to be heard
on his motion for reconsideration," citing Vda. de Chua v. Court of
Appeals, is not applicable to the instant case considering that the cited Among the factors to be considered in arriving at the fair market value of
case involved a lack of notice of the orders of the trial court in granting the property are the cost of acquisition, the current value of like
letters of administration. It was essentially a private dispute and therefore, properties, its actual or potential uses, and in the particular case of lands,
no public funds were involved. It is distinct from this expropriation case their size, shape, location, and the tax declarations thereon.
where grave consequences attached to the orders of the trial court when
it determined the just compensation. It is settled that just compensation is to be ascertained as of the time of
the taking, which usually coincides with the commencement of the
The Court takes this opportunity to elucidate the ruling that the expropriation proceedings. Where the institution of the action precedes
opportunity to present evidence incidental to a Motion for entry into the property, the just compensation is to be ascertained as of
Reconsideration will suffice if there was no chance to do so during the the time of the filing of the complaint.18
trial. We find such situation to be the exception and not the general rule.
The opportunity to present evidence during the trial remains a vital We note that in this case, the filing of the complaint for expropriation
requirement in the observance of due process. The trial is materially and preceded the petitioner’s entry into the property.
substantially different from a hearing on a Motion for Reconsideration. At
the trial stage, the party is usually allowed several hearing dates Therefore, it is clear that in this case, the sole basis for the determination
depending on the number of witnesses who will be presented. At the of just compensation was the commissioners’ ocular inspection of the
hearing of said motion, the trial court may not be more accommodating properties in question, as gleaned from the commissioners’ October 5,
with the grant of hearing dates even if the movant has many available 1999 report. The trial court’s reliance on the said report is a serious error
witnesses. Before the decision is rendered, a trial court has an open mind considering that the recommended compensation was highly speculative
on the merits of the parties’ positions. After the decision has been issued, and had no strong factual moorings. For one, the report did not indicate
the trial court’s view of these positions might be inclined to the side of the fair market value of the lots occupied by the Orchard Golf and
ProvRem Rule 67 Fulltext Page 84 of 119
Country Club, Golden City Subdivision, Arcontica Sports Complex, and decreasing from P10,000.00 to P3,000.00 the commissioners' fee for each
other business establishments cited. Also, the report did not show how of the three commissioners.
convenience facilities, public transportation, and the residential and
commercial zoning could have added value to the lots being On April 15, 1996, private respondent National Power Corporation
expropriated. (NAPOCOR) filed a Complaint for Eminent Domain, seeking to expropriate
a portion of petitioner Bank of the Philippine Islands' (BPI) property
Moreover, the trial court did not amply explain the nature and application located in Barrio Bucal, Dasmariñas, Cavite, for the purpose of
of the "highest and best use" method to determine the just compensation constructing and maintaining its Dasmariñas-Zapote 230 KV Transmission
in expropriation cases. No attempt was made to justify the recommended Line Project.
"just price" in the subject report through other sufficient and reliable
means such as the holding of a trial or hearing at which the parties could On August 1, 1996, pursuant to Section 2 of Rule 67 of the Rules of
have had adequate opportunity to adduce their own evidence, the Court,3 NAPOCOR deposited with the Philippine National Bank, NPC
testimony of realtors in the area concerned, the fair market value and tax Branch, in Quezon City, the amount of P3,013.60, equivalent to the
declaration, actual sales of lots in the vicinity of the lot being expropriated assessed value of the property. On August 15, 1996, NAPOCOR notified
on or about the date of the filing of the complaint for expropriation, the BPI, through registered mail, of its intention to take possession of the
pertinent zonal valuation derived from the Bureau of Internal Revenue, property. Thereafter, the trial court granted their urgent ex-parte motion
among others. for the issuance of a writ of possession and authorized them to enter and
take possession of the premises.4
More so, the commissioners did not take into account that the Asian
financial crisis in the second semester of 1997 affected the fair market Previously, petitioner BPI filed a motion for bill of particulars which the
value of the subject lots. Judicial notice can be taken of the fact that after trial court denied.5 Consequently, BPI moved for the dismissal of the case
the crisis hit the real estate market, there was a downward trend in the and the same was granted without prejudice to its reinstatement.6 Private
prices of real estate in the country. respondent NAPOCOR filed a motion for reconsideration. The trial court
granted the motion and reinstated the case.7
Furthermore, the commissioners’ report itself is flawed considering that its
recommended just compensation was pegged as of October 5, 1999, or In its Order dated November 28, 1997,8 the trial court designated three
the date when the said report was issued, and not the just compensation commissioners to determine the just value of the property subject of the
as of the date of the filing of the complaint for expropriation, or as of expropriation in this case, namely: Mr. Lamberto C. Parra, Provincial
November 27, 1998. The period between the time of the filing of the Assessor of Cavite; Mr. Regalado Andaya, Municipal Assessor of
complaint (when just compensation should have been determined), and Dasmariñas, Cavite; and Mr. Rodolfo D. Leonen, Defendant's
the time when the commissioners’ report recommending the just Representative.
compensation was issued (or almost one [1] year after the filing of the
complaint), may have distorted the correct amount of just compensation.
Accordingly, on February 26, 1999, the Commissioners submitted its
Report which assessed the sum of the area of the property taken and the
Clearly, the legal basis for the determination of just compensation in this estimated value of just compensation at 75.34 square meters x P10,000.00
case is insufficient as earlier enunciated. This being so, the trial court’s = P753,400.00, and recommended an additional payment of P524,660.00
ruling in this respect should be set aside. as severance damage, or a total of P1,278,060.00.9 Likewise, they
submitted an undated Commissioners' Valuation Report citing the
WHEREFORE, the petition is GRANTED. The December 28, 1999 and "Market Data Approach" as the method used in arriving at the amount of
March 23, 2000 Orders of the Imus, Cavite RTC and the November 18, P10,000.00 per square meter as just compensation, whereby the value of
2002 Decision of the CA are hereby SET ASIDE. This case is remanded to the land is based on sales and listing of comparable property registered
the said trial court for the proper determination of just compensation in within the immediate vicinity.10
conformity with this Decision. No costs.
On August 5, 1999, the trial court rendered judgment in favor of BPI, the
SO ORDERED. dispositive portion of which reads:
The case at bar falls under one of the exceptions, i.e., where the findings #10 G.R. No. 211666 February 25, 2015
of fact of the Court of Appeals are contrary to those of the trial court.
REPUBLIC OF THE PHILIPPINES, represented by the DEPARTMENT OF
Petitioner asserts that the finding of just compensation by the court- PUBLIC WORKS AND HIGHWAYS,Petitioners,
appointed commissioners was based on clear evidence of prior sales and vs.
acceptable market valuation methods. Petitioner likewise avers that the ARLENE R. SORIANO, Respondent.
valuation made by the commissioners must be accorded weight. Likewise
it argues that NAPOCOR is estopped from questioning the valuation of DECISION
the land considering that its own nominee concurred with the findings of
the other commissioners.
PERALTA, J.:
In another Order7 dated June 21, 2011, the RTC appointed the following Let a certified true copy of this decision be recorded in the Registry of
members of the Board of Commissioners for the determination of just Deeds of Valenzuela City.
compensation: (1) Ms. Eunice O. Josue, Officer-in-Charge, RTC, Branch
270, Valenzuela City; (2) Atty. Cecilynne R. Andrade, Acting Valenzuela City
Assessor,City Assessor’s Office, Valenzuela City; and (3) Engr. Restituto Records of this case show that the Land Bank Manager’s Check Nos.
Bautista, of Brgy. Bisig,Valenzuela City. However, the trial court 0000016913 dated January 21, 2011 in the amount of Php400,000.00 and
subsequently revoked the appointment of the Board for their failure to 0000017263 dated April 28, 2011 in the amount of Php20,000.00 issued
submit a report as to the fair market value of the property to assist the by the Department of Public Works and Highways (DPWH) are already
court in the determination of just compensation and directed the parties stale. Thus, the said Office is hereby directed to issue another Manager’s
to submit their respective position papers.8 Thereafter, the case was set Check in the total amount Php420,000.00 under the name of the Office of
for hearing giving the parties the opportunity to present and identify all the Clerk of Court, Regional Trial Court, Valenzuela City earmarked for the
instant case.10
evidence in support of their arguments therein. According to the RTC, the
records of the case reveal that petitioner adduced evidence to show that
the total amount deposited is just, fair, and equitable. Specifically, in its Petitioner filed a Motion for Reconsideration maintaining that pursuant to
Position Paper, petitioner alleged that pursuant to a Certification issued Bangko Sentral ng Pilipinas (BSP) Circular No. 799, Series of 2013, which
by the Bureau of Internal Revenue (BIR), Revenue Region No. 5, the zonal took effect on July 1, 2013, the interest rate imposed by the RTC on just
value of the subject property in the amount of ₱2,100.00 per square meter compensation should be lowered to 6% for the instant case falls under a
is reasonable, fair, and just to compensate the defendant for the taking of loan or forbearance of money.11 In its Order12 dated March 10, 2014, the
her property in the total area of 200 square meters.9 In fact, Tax RTC reduced the interest rate to 6% per annum not on the basis of the
Declaration No. C-018-07994, dated November 13, 2009 submitted by aforementioned Circular, but on Article 2209 of the Civil Code, viz.:
petitioner, shows that the value of the subject property is at a lower rate
of ₱400.00per square meter. Moreover, as testified to by Associate However, the case of National Power Corporation v. Honorable Zain B.
Solicitor III Julie P. Mercurio, and as affirmed by the photographs Angas is instructive.
submitted, the subject property is poorly maintained, covered by shrubs
and weeds, and not concretely-paved. It is located far from commercial or
In the aforementioned case law, which is similar to the instant case, the
industrial developments in an area without a proper drainage system, can
Supreme Court had the occasion to rule that it is well-settled that the
only be accessed through a narrow dirt road, and is surrounded by
aforequoted provision of Bangko Sentral ng Pilipinas Circular applies only
adjacent dwellings of sub-standard materials.
to a loan or forbearance of money, goods or credits. However, the term
"judgments" as used in Section 1 of the Usury Law and the previous
Accordingly, the RTC considered respondent to have waived her right to Central Bank Circular No. 416, should be interpreted to mean only
adduce evidence and to object to the evidence submitted by petitioner judgments involving loan or forbearance of money, goods or credits,
for her continued absence despite being given several notices to do so. following the principle of ejusdem generis. And applying said rule on
statutory construction, the general term "judgments" can refer only to
On November 15, 2013, the RTC rendered its Decision, the dispositive judgments in cases involving loans or forbearance of any money, goods,
portion of which reads: WHEREFORE, with the foregoing determination of or credits. Thus, the High Court held that, Art. 2209 of the Civil Code, and
just compensation, judgment is hereby rendered: not the Central Bank Circular, is the law applicable.
1) Declaring plaintiff to have lawful right to acquire possession Art. 2009 of the Civil Code reads:
of and title to 200 square meters of defendant Arlene R.
Soriano’s parcel of land covered by TCT V-13790 necessary for "If the obligation consists in the payment of a sum of money, and the
the construction of the NLEX – Harbor Link Project(Segment 9) debtor incurs in delay, the indemnity for damages, there being no
from NLEX to MacArthur Highway Valenzuela City; stipulation to the contrary, shall be the payment of the interest agreed
upon, and in the absence of stipulation, the legal interest, which is six per
cent per annum."
RESPONDENT IS NOT ENTITLED TO THE LEGAL INTEREST OF We subsequently upheld Republic’s 12% per annum interest rate on the
6% PER ANNUM ON THE AMOUNT OF JUST COMPENSATION unpaid expropriation compensation in the following cases: Reyes v.
OF THE SUBJECT PROPERTY AS THERE WAS NO DELAY ON THE National Housing Authority, Land Bank of the Philippines v. Wycoco,
PART OF PETITIONER. Republic v. Court of Appeals, Land Bank of the Philippines v. Imperial,
Philippine Ports Authority v. Rosales-Bondoc, and Curata v. Philippine
Ports Authority.17 Effectively, therefore, the debt incurred by the
II.
government on account of the taking of the property subject of an
expropriation constitutes a forbearance18 which runs contrary to the trial
BASED ON THE NATIONAL INTERNAL REVENUE CODE OF 1997 court’s opinion that the same is in the nature of indemnity for damages
AND THE LOCAL GOVERNMENT CODE, IT IS RESPONDENT’S calling for the application of Article 2209 of the Civil Code. Nevertheless,
OBLIGATION TO PAY THE TRANSFER TAXES. in line with the recent circular of the Monetary Board of the Bangko
Sentral ng Pilipinas (BSP-MB) No. 799, Series of 2013, effective July 1,
Petitioner maintains that if property is taken for public use before 2013, the prevailing rate of interest for loans or forbearance of money is
compensation is deposited with the court having jurisdiction over the six percent (6%) per annum, in the absence of an express contract as to
case, the final compensation must include interests on its just value such rate of interest.
computed from the time the property is taken up to the time when
compensation is actually paid or deposited with the court.14 Thus, legal Notwithstanding the foregoing, We find that the imposition of interest in
interest applies only when the property was taken prior to the deposit of this case is unwarranted in view of the fact that as evidenced by the
payment with the court and only to the extent that there is delay in acknowledgment receipt19 signed by the Branch Clerk of Court, petitioner
payment. In the instant case, petitioner posits that since it was able to was able to deposit with the trial court the amount representing the zonal
deposit with the court the amount representing the zonal value of the value of the property before its taking. As often ruled by this Court, the
property before its taking, it cannot be said to be in delay, and thus, there award of interest is imposed in the nature of damages for delay in
can be no interest due on the payment of just compensation.15 Moreover, payment which, in effect, makes the obligation on the part of the
petitioner alleges that since the entire subject property was expropriated government one of forbearance to ensure prompt payment of the value
and not merely a portion thereof, it did not suffer an impairment or of the land and limit the opportunity loss of the owner.20 However, when
decrease in value, rendering the award of consequential damages there is no delay in the payment of just compensation, We have not
nugatory. Furthermore, petitioner claims that contrary to the RTC’s hesitated in deleting the imposition of interest thereon for the same is
instruction, transfer taxes, in the nature of Capital Gains Tax and justified only in cases where delay has been sufficiently established.21
Documentary Stamp Tax, necessary for the transfer of the subject
property from the name of the respondent to that of the petitioner are The records of this case reveal that petitioner did not delay in its payment
liabilities of respondent and not petitioner. of just compensation as it had deposited the pertinent amount in full due
to respondent on January 24, 2011, or four (4) months before the taking
The petition is partly meritorious. thereof, which was when the RTC ordered the issuance of a Writ of
Possession and a Writ of Expropriation on May 27, 2011. The amount
At the outset, it must be noted that the RTC’s reliance on National Power deposited was deemed by the trial court to be just, fair, and equitable,
Corporation v. Angasis misplaced for the same has already been taking into account the well-established factors in assessing the value of
overturned by our more recent ruling in Republic v. Court of land, such as its size, condition, location, tax declaration, and zonal
Appeals,16 wherein we held that the payment of just compensation for the valuation as determined by the BIR. Considering, therefore, the prompt
expropriated property amounts to an effective forbearance on the part of payment by the petitioner of the full amount of just compensation as
the State, to wit: determined by the RTC, We find that the imposition of interest thereon is
unjustified and should be deleted.
Aside from this ruling, Republic notably overturned the Court’s previous
ruling in National Power Corporation v. Angas which held that just Similarly, the award of consequential damages should likewise be deleted
compensation due for expropriated properties is not a loan or in view of the fact that the entire area of the subject property is being
forbearance of money but indemnity for damages for the delay in expropriated, and not merely a portion thereof, wherein such remaining
payment; since the interest involved is in the nature of damages rather portion suffers an impairment or decrease in value, as enunciated in
than earnings from loans, then Art. 2209 of the Civil Code, which fixes Republic of the Philippines v. Bank of the Philippine Islands,22 thus:
legal interest at 6%, shall apply.
x x x The general rule is that the just compensation to which the owner of
In Republic, the Court recognized that the just compensation due to the the condemned property is entitled to is the market value. Market value is
landowners for their expropriated property amounted to an effective that sum of money which a person desirous but not compelled to buy,
forbearance on the part of the State. Applying the Eastern Shipping Lines and an owner willing but not compelled to sell, would agree on as a price
Section 56. Payment and Assessment of Income Tax for Individuals and
xxxx Corporations. – (A) Payment of Tax –
To determine just compensation, the trial court should first ascertain the Thus, it has been held that since capital gains is a tax on passive income, it
market value of the property, to which should be added the consequential is the seller, not the buyer, who generally would shoulder the
damages after deducting therefrom the consequential benefits which may tax.24 Accordingly, the BIR, in its BIR Ruling No. 476-2013, dated
arise from the expropriation. If the consequential benefits exceed the December 18, 2013, constituted the DPWH as a withholding agent to
consequential damages, these items should be disregarded altogether as withhold the six percent (6%) final withholding tax in the expropriation of
the basic value of the property should be paid in every case.23 real property for infrastructure projects. As far as the government is
concerned, therefore, the capital gains tax remains a liability of the seller
Considering that the subject property is being expropriated in its entirety, since it is a tax on the seller's gain from the sale of the real estate.25
there is no remaining portion which may suffer an impairment or
decrease in value as a result of the expropriation. Hence, the award of As to the documentary stamp tax, however, this Court finds inconsistent
consequential damages is improper. petitioner’s denial of liability to the same. Petitioner cites Section 196 of
the 1997 NIRC as its basis in saying that the documentary stamp tax is the
Anent petitioner’s contention that it cannot be made to pay the value of liability of the seller, viz.:
the transfer taxes in the nature of capital gains tax and documentary
stamp tax, which are necessary for the transfer of the subject property SECTION 196. Stamp Tax on Deeds of Sale and Conveyances of Real
from the name of the respondent to that of the petitioner, the same is Property. - On all conveyances, deeds, instruments, or writings, other than
partly meritorious. grants, patents or original certificates of adjudication issued by the
Government, whereby any land, tenement or other realty sold shall be
With respect to the capital gains tax, We find merit in petitioner’s posture granted, assigned, transferred or otherwise conveyed to the purchaser, or
that pursuant to Sections 24(D) and 56(A)(3) of the 1997 National Internal purchasers, or to any other person or persons designated by such
Revenue Code (NIRC), capital gains tax due on the sale of real property is purchaser or purchasers, there shall be collected a documentary stamp
a liability for the account of the seller, to wit: tax, at the rates herein below prescribed, based on the consideration
contracted to be paid for such realty or on its fair market value
determined in accordance with Section 6(E) of this Code, whichever is
Section 24. Income Tax Rates– higher: Provided, That when one of the contracting parties is the
Government, the tax herein imposed shall be based on the actual
xxxx consideration: (a) When the consideration, or value received or contracted
to be paid for such realty, after making proper allowance of any
(D) Capital Gains from Sale of Real Property. – encumbrance, does not exceed One thousand pesos (₱1,000), Fifteen
pesos (₱15.00).
3.) The plaintiff must pay defendant the sum of ₱72,279,555.68 (3,979.10
SO ORDERED.
sq. m. x ₱18,164.80) representing the value of the subject
A copy of the Order dated 2 August 2001 was served on the CSB on 3 The State’s power of eminent domain should be exercised within the
August 2001.15 bounds of fair play and justice. In the case at bar, considering that
valuable property has been taken, the compensation to be paid fixed and
the municipality is in full possession and utilizing the property for the
On 30 August 2001, petitioner submitted a manifestation before the trial public purpose, for three (3) years, the Court finds that the municipality
court requesting that she be informed by both the City and the CSB if a has had more than reasonable time to pay full compensation.
resolution had already been passed by the latter in compliance with
ProvRem Rule 67 Fulltext Page 91 of 119
The arguments of the herein respondents that passing the ordinance or Court has often judiciously treated petitions erroneously captioned as
the act of appropriating special educational fund is a discretionary act petitions for review on certiorari as special civil actions for certiorari. This
that could not be compelled by mandamus should be thrown overboard. is in line with the principle that the strict application of procedural
It must be stressed that what we have here is a final and executory technicalities should not hinder the speedy disposition of the case on the
judgment, establishing a legal right for the petitioner to demand merits.51
fulfillment which on the other hand became an imperative duty on the
part of the respondent to perform the act required. Accordingly, facial allegations of reversible error in the petition will be
treated, as they should be, as contextual averments of grave abuse of
WHEREFORE, premises considered, the petition is GRANTED, and the discretion on the part of the court a quo. Appropriately, petitioner
respondents are hereby ordered to immediately pass a resolution impleaded the RTC Presiding Judge as party-respondent in the instant
appropriating the necessary amount; and the corresponding petition.
disbursement thereof, for the full and complete payment of the remaining
balance of the court-adjudged compensation due and owing to petitioner Anent the alleged breach of the rule on hierarchy of courts, the doctrine is
Teresita M. Yujuico. not an iron-clad dictum.52 The rule may be relaxed when exceptional and
compelling circumstances warrant the exercise of this Court’s primary
SO ORDERED.37 jurisdiction.53 In this case, the judgment sought to be satisfied has long
attained finality and the expropriated property has been utilized as a
Respondents filed a motion for reconsideration, which the trial court school site for five (5) years now; yet, the awarded just compensation has
denied in an Order38 dated 13 December 2002. not been fully paid. These circumstances, in the Court’s estimation, merit
the relaxation of the technical rules of procedure to ensure that
substantial justice will be served.
With respondents not interposing an appeal, the Decision became final
and executory on 2 January 200339 and eventually, the
corresponding Entry of Judgment was issued on 15 January 2003.40 The Concerning petitioner’s alleged failure to implead the CSB or its new
court granted petitioner’s Motion for Execution41 in an Order42 dated 12 members before the trial court,54respondents argue that since there are
March 2003. five (5) new members in the CSB any decision in the case requiring the
CSB to act as a body would prove to be legally impossible. The former
members of the CSB could no longer be compelled to act according to
However, on 14 March 2003, respondents filed a Petition for Relief from the orders of the Court since they no longer have the capacity to do so.
Judgment,43 wherein they also prayed for a temporary restraining order On the other hand, respondents continue, the new members cannot be
(TRO) and a writ of preliminary injunction. Respondents invoked directed to comply with the Court’s judgment either; they have never
excusable negligence as a ground for their failure to seasonably file an been impleaded in the case; thus, the Court never acquired jurisdiction
appeal.44 While it denied the application for TRO in view of its prior order over their persons.55
granting petitioner’s Motion for Execution, the court granted the Petition
for Relief from Judgment in an Order45 dated 25 June 2004. This had the
effect of giving due course to respondents’ appeal despite the fact that The arguments were effectively neutered in our Resolution dated 8 August
the decision of the trial court had already attained finality. 2005. There, we declared:
Finding the Order unacceptable, petitioner elevated it to this Court by way Considering the arguments posited by both parties, this Court is of the
of a petition for certiorari under Rule 45. In her petition, petitioner asks view that a substitution of the original respondents by the members of
that the order of the lower court giving due course to respondents’ the CSB who replaced them is warranted. The phrase "or such time as may
appeal be reversed and set aside on a pure question of law.46 be granted by the Court" in Sec. 17, Rule 3 of the 1997 Rules of Civil
Procedure denotes that the Court before whom the motion for
substitution is filed may grant a period longer than thirty (30) days for the
Before resolving the substantive issues raised by the parties, the Court will purpose. In any event, technical rules on substitution of a party should not
first address the procedural infirmities ascribed by respondents to the be so narrowly construed as to prevent this Court from taking cognizance
petition at bar. of a case and deciding it on the merits. Moreover, petitioner did make an
attempt to implead the new members of the CSB by making the CSB itself
Respondents assail the correctness and propriety of the mode of appeal a respondent before this Court. There is also no showing that the new
resorted to by petitioner.47 According to them, the order granting the members of the CSB have deviated from the stand of their predecessors-
petition for relief from judgment is an interlocutory order which cannot in-interest; hence, there is a substantial need for continuing or
be made the subject of an appeal.48 Respondents likewise argue that maintaining petitioner’s action against them.56
petitioner failed to respect the rule on hierarchy of courts. This Court, they
aver, had consistently held that its original jurisdiction to issue a writ of In the same Resolution, the Court ordered the impleading of the new CSB
certiorari is not exclusive but is concurrent with that of the RTC and the members Roger Gernale, Manuel M. Zarcal, Benjamin Valbuena and
Court of Appeals in certain cases.49 Francesca Gernale as party respondents—the last three in substitution of
Arlene Ortiz, Percival Floriendo, Miles Roces—and the new CSB Assistant
Respondents have correctly pointed out that an interlocutory order Secretary Vicente Macarubbo in substitution of Isabelita Ching.57 Only
cannot be made subject to an appeal. However, when viewed in context, Manuel Zarcal filed a Comment58 dated 30 August 2005 through a new
the recitals of the petition clearly disclose and the Court is convinced that counsel, adopting in toto the comment of his co-respondents. Hence, the
the lower court committed grave abuse of discretion amounting to lack or other four newly impleaded party respondents are deemed to have
excess of jurisdiction when it granted respondents’ petition for relief from retained the Office of the City Legal Officer (OCLO) as their counsel and to
judgment. While this case should have been elevated to this Court not by have adopted the Commentalready filed by the OCLO in behalf of their
way of a petition for review under Rule 45 but through a special civil co-respondents.
action for certiorari under Rule 65, in the exercise of our sound discretion
and in order to write finis to this case which has needlessly dragged on Thus, the proper substitutions of some party respondents have already
for so long, we shall treat the petition as a special civil action for certiorari. taken place in this case.
After all, it was filed within the reglementary period for the filing of a Rule
65 petition. As we held in Salinas v. NLRC,50 in the interest of justice, this
The above requisites notwithstanding, it bears stressing that relief from Even assuming that the negligence invoked by respondents could be
judgment is premised on equity. It is an act of grace which is allowed only considered excusable, still the petition should not have been granted. It
in exceptional cases.65 must be borne in mind that two requisites must be satisfied before a
petition under Rule 38 may be granted, the other being the existence of a
In this case, according to respondents they were unable to seasonably file good and substantial cause of action or defense.
a notice of appeal due to "excusable negligence."66 One Ronald Silva
(Silva), an employee of the OCLO, allegedly failed to forward Respondents’ defense consisted of their claim that the CSB has a
the Order denying respondents’ motion for reconsideration in Civil Case personality separate and distinct from the City such that it should not be
No. 02-103748 to the handling lawyers. When the order was delivered to made to pay for the City’s obligations.76 However, the argument is
the OCLO on 17 December 2002,67 Silva was the one who received it undercut by the particular circumstances of this case.
because the employee designated to do so was out on official
business.68 Since the employees were busy preparing for the office
Christmas party that day,69 Silva forgot all about the order. He only It is worthy of note that the records of this case clearly show that the
remembered it when the order for entry of judgment in the case was same counsel, the OCLO, represented the City in the expropriation case
received on 29 January 2003. By that time, however, the order dated 17 and now, all except one of the individual respondents in the case at bar.
December 2002 had already been misplaced.70 Worthy of note are the following manifestations relied upon by the lower
court in issuing the order on the motion to quash the Notice of
Garnishment over the funds of the City, to wit:
Clearly, the situation does not present a case of excusable negligence
which would warrant relief under Rule 38. Time and again, this Court has
ruled that the inability to perfect an appeal in due time by reason of The Motion to Quash Notice of Garnishment was heard by this court this
failure of a counsel’s clerk to notify the handling lawyer is not a morning and Atty. Joseph Aquino appeared for the plaintiff (City of
pardonable oversight.71 As held in one case: Manila) and Atty. Federico Alday, for the defendant. Atty. Aquino
manifested that the amount of Thirty Six Million Four Hundred Three
Thousand One Hundred Seventy Pesos (₱36,403,170.00) had been
. . . The excuse offered by respondent . . . as reason for his failure to appropriated by the City School Board (CSB) under CSB Resolution
perfect in due time his appeal from the judgment of the Municipal Court, Nos. 613 and 623 for this purpose.
that counsel’s clerk forgot to hand him the court notice, is the most
hackneyed and habitual subterfuge employed by litigants who fail to
observe the procedural requirements prescribed by the Rules of Court. ....
The uncritical acceptance of this kind of common-place excuses, in the
face of the Supreme Court’s repeated rulings that they are neither Upon manifestation of the counsel for the plaintiff that it is the City
credible nor constitutive of excusable negligence (Gaerlan v. Bernal, L- School Board which has the authority to pass a resolution allocating
4039, 29 January 1952; Mercado v. Judge Domingo, L-19457, 17 funds for the full satisfaction of the just compensation fixed, the said
December 1966) is certainly such whimsical exercise of judgment as to be body is hereby given thirty (30) days from receipt of this Order to pass the
a grave abuse of discretion. necessary resolution for the payments of the remaining balance due to
defendant Teresita M. Yujuico. (Emphasis supplied.)77
ProvRem Rule 67 Fulltext Page 93 of 119
The manifestation was made by the same counsel now claiming that it is desires.81 The question of whether the enactment of an ordinance to
actually the City which should be made liable for the payment of its own satisfy the appropriation of a final money judgment rendered against an
obligations. This, after it trotted out the CSB as the entity with authority to LGU may be compelled by mandamus has already been settled
pass a resolution that would satisfy the obligation it had vigorously in Municipality of Makati v. Court of Appeals.82
pursued.
Nevertheless, this is not to say that private respondent and PSB are left
The above circumstances, coupled with the rule that an act performed by with no legal recourse. Where a municipality fails or refuses, without
counsel within the scope of a "general or implied authority" is regarded as justifiable reason, to effect payment of a final money judgment rendered
an act of the client,78 render the City and, through it, respondents against it, the claimant may avail of the remedy of mandamus in order to
in estoppel. By estoppel is meant that an admission or representation is compel the enactment and approval of the necessary appropriation
rendered conclusive upon the person making it and cannot be denied or ordinance, and the corresponding disbursement of municipal funds
disproved as against the person relying thereon.79 Petitioner and the therefore [SeeViuda De Tan Toco v. The Municipal Council of Iloilo, supra,
courts acted in accordance with the City’s own manifestations by running Baldivia v. Lota, 107 Phil 1099 (1960); Yuviengco v. Gonzales, 108 Phil 247
after the CSB. At this point, respondents and the OCLO can no longer turn (1960)].83
around and toss the obligation back to the City. After all, it was the legal
counsel of both the City and respondents who made a big production out Clearly, mandamus is a remedy available to a property owner when a
of showing that the liability incurred by the City will be borne by the CSB. money judgment is rendered in its favor and against a municipality or city,
as in this case.
Contrary to respondents’ claim, the law does not make the CSB an entity
independent from the City of Manila. This is evident from the provisions Moreover, the very ordinance authorizing the expropriation of petitioner’s
of the Local Government Code of 1991, the law providing for the creation property categorically states that the payment of the expropriated
of school boards. It states: property will be defrayed from the SEF. To quote:
TITLE IV.- LOCAL SCHOOL BOARDS An amount not to exceed the current fair market value, prevailing in the
area appraised in accordance with the requirements of existing laws, rules
Section 98. Creation, Composition and Compensation.- and regulations, of the property to be acquired or so much thereof as
may be necessary for the purpose shall be allocated out of the Special
(a) There shall be established in every province, city or municipality a Education Fund of the City to defray the cost of acquisition of the above-
provincial, city, or municipal school board, respectively. mentioned parcels of land.84
(b) The composition of local school boards shall be as follows: The legality of the above-quoted provision is presumed. The source of the
amount necessary to acquire petitioner’s property having in fact been
specified by the City Council of Manila, the passage of the resolution for
...
the allocation and disbursement thereof is indeed a ministerial duty of the
CSB.
(2) The city school board shall be composed of the city mayor and the city
superintendent of schools as co-chairmen; the chairman of the education Furthermore, respondents had argued in the petition for contempt filed
committee of the sangguniang panlungsod, the city treasurer, the against them by petitioner that the latter’s failure to invoke the proper
representative of the "pederasyon ng mga sangguniang kabataan" in remedy of mandamus should not be a ground to penalize them with
the sangguniang panlungsod, the duly elected president of the city contempt. In their haste to have the contempt petition dismissed,
federation of parents-teachers associations, the duly elected respondents consistently contended that what petitioner should have
representative of the non-academic personnel of public schools in the filed was a case for mandamus to compel passage of the corresponding
city, as members; resolution of the CSB if she wanted immediate payment.85 Having relied
on these representations of respondents and having filed the action they
... adverted to, petitioner cannot now be sent by respondents on another
wild goose chase to obtain ultimate recovery of what she is legally
Section 101. Compensation and Remuneration.- entitled to.
The co-chairmen and members of the provincial, city or municipal school While this Court recognizes the power of LGU to expropriate private
board shall perform their duties as such without compensation or property for public use, it will not stand idly by while the expropriating
remuneration. Members thereof who are not government officials or authority maneuvers to evade the payment of just compensation of
employees shall be entitled to traveling expenses and allowances property already in its possession.
chargeable against the funds of the local school board concerned, subject
to existing accounting and auditing rules and regulations.80 The notion of expropriation is hard enough to take for a private owner.
He is compelled to give up his property for the common weal. But to give
The fact that the highest ranking official of a local government unit (LGU) it up and wait in vain for the just compensation decreed by the courts is
is designated as co-chairman of the school board negates the claim in this too much to bear. In cases like these, courts will not hesitate to step in to
case that the CSB has a personality separate and distinct from the City. ensure that justice and fair play are served. As we have already ruled:
The other fact that government officials in the school board do not
receive any compensation or remuneration while NGO representatives . . . This Court will not condone petitioner’s blatant refusal to settle its
merely receive allowances underscores the absurdity of respondents’ legal obligation arising from expropriation proceedings it had in fact
argument all the more. Indeed, such would not be the situation if the initiated. It cannot be over-emphasized that within the context of the
school board has a personality separate and distinct from the LGU. State’s inherent power of eminent domain,
Respondents also argue that the members of the CSB cannot be directed . . . (j)ust compensation means not only the correct determination of the
to decide a discretionary function in the specific manner the court amount to be paid to the owner of the land but also the payment of the
ProvRem Rule 67 Fulltext Page 94 of 119
land within a reasonable time from its taking. Without prompt payment, surnamed MACABANGKIT,
compensation cannot be considered ‘just’ for the property owner is made Respondents.
to suffer the consequence of being immediately deprived of his land while
x--------------------------------------------------------------x
being made to wait for a decade or more before actually receiving the
amount necessary to cope with his loss (Consculluela v. The Honorable
DECISION
Court of Appeals, G.R. No. 77765, August 15, 1988, 164 SCRA 393,
400. See also Provincial Government of Sorsogon v. Vda. De Villaroya, G.R.
BERSAMIN, J.:
No. 64037, August 27, 1987, 153 SCRA 291).86
Private property shall not be taken for
public use without just compensation.
The decision rendering just compensation in petitioner’s favor was Section 9, Article III, 1987 Constitution
promulgated way back in the year 2000.87 Five years have passed, yet the
award still has not been fully satisfied. Recently, in Republic v. Lim,88 this The application of this provision of the Constitution is the focus of this
Court made the following pronouncement: appeal.
. . . while the prevailing doctrine is that the non-payment of just Petitioner National Power Corporation (NPC) seeks the review
compensation does not entitle the private landowner to recover on certiorari of the decision promulgated on October 5, 2004,[1] whereby
possession of the expropriated lots, however, in cases where the the Court of Appeals (CA) affirmed the decision dated August 13, 1999
government failed to pay just compensation within five (5) years from and the supplemental decision dated August 18, 1999, ordering NPC to
the finality of judgment in the expropriation proceedings, the owners pay just compensation to the respondents, both rendered by the Regional
concerned shall have the right to recover possession of their property. Trial Court, Branch 1, in Iligan City (RTC).
This is in consonance with the principle that ‘the government cannot keep
the property and dishonor the judgment.’ To be sure, the five-year period Antecedents
limitation will encourage the government to pay just compensation
punctually. This is in keeping with justice and equity. After all, it is the duty Pursuant to its legal mandate under Republic Act No. 6395 (An Act
of the government, whenever it takes property from private persons Revising the Charter of the National Power Corporation), NPC undertook
against their will, to facilitate the payment of just the Agus River Hydroelectric Power Plant Project in the 1970s to generate
compensation.89 (Citations omitted) electricity for Mindanao. The project included the construction of several
underground tunnels to be used in diverting the water flow from the Agus
River to the hydroelectric plants.[2]
Given the above ruling, the reversion of the expropriated property to the
petitioner would prove not to be a remote prospect should respondents
On November 21, 1997, the respondents, namely: Cebu, Bangowa-an,
and the City they represent insist on trudging on their intransigent course.
Sayana, Nasser, Manta, Edgar, Putri, Mongkoy and Amir, all surnamed
Macabangkit (Heirs of Macabangkit), as the owners of land with an area
One final note. Respondents’ appeal from the Decision dated 9 October of 221,573 square meters situated in Ditucalan, Iligan City, sued NPC in
2002 of the lower court, made possible by its grant of their petition for the RTC for the recovery of damages and of the property, with the
relief, is before the Court of Appeals where it is docketed as CA-G.R. No. alternative prayer for the payment of just compensation.[3] They alleged
86692.90The court’s Decision in this case would have obvious that they had belatedly discovered that one of the underground tunnels
consequences on said appeal; hence, referral of this Decision to the Court of NPC that diverted the water flow of the Agus River for the operation of
of Appeals is in order. the Hydroelectric Project in Agus V, Agus VI and Agus VII traversed their
land; that their discovery had occurred in 1995 after Atty. Saidali C.
WHEREFORE, the petition is GRANTED. The Order of the trial court dated Gandamra, President of the Federation of Arabic Madaris School, had
25 June 2004, granting respondents’ Petition for Relief from Judgment is rejected their offer to sell the land because of the danger the
REVERSED and set aside and its Decision dated 9 October 2002, ordering underground tunnel might pose to the proposed Arabic Language
respondents to immediately pass a resolution for the payment of the Training Center and Muslims Skills Development Center; that such
balance of the court-adjudged compensation due petitioner, is reinstated. rejection had been followed by the withdrawal by Global Asia
Management and Resource Corporation from developing the land into a
housing project for the same reason; that Al-Amanah Islamic Investment
Let a copy of this Decision be furnished the Court of Appeals for its
Bank of the Philippines had also refused to accept their land as collateral
information and guidance in relation to CA-G.R. No. 86692 entitled
"Teresita M. Yujuico v. Hon. Jose L. Atienza, Jr., et al." because of the presence of the underground tunnel; that the
underground tunnel had been constructed without their knowledge and
consent; that the presence of the tunnel deprived them of the agricultural,
SO ORDERED. commercial, industrial and residential value of their land; and that their
land had also become an unsafe place for habitation because of the loud
#12 G.R. No. 165828 August 24, 2011 sound of the water rushing through the tunnel and the constant shaking
of the ground, forcing them and their workers to relocate to safer
NATIONAL POWER Present: grounds.
CORPORATION,
Petitioner, CORONA, C.J., Chairperson, In its answer with counterclaim,[4] NPC countered that the Heirs of
LEONARDO-DE CASTRO, Macabangkit had no right to compensation under section 3(f) of Republic
BERSAMIN, Act No. 6395, under which a mere legal easement on their land was
- versus - DEL CASTILLO, and established; that their cause of action, should they be entitled to
VILLARAMA, JR., JJ. compensation, already prescribed due to the tunnel having been
constructed in 1979; and that by reason of the tunnel being an apparent
HEIRS OF MACABANGKIT and continuous easement, any action arising from such easement
SANGKAY, namely: CEBU, prescribed in five years.
BATOWA-AN, SAYANA, NASSER,
MANTA, EDGAR, PUTRI , Ruling of the RTC
MONGKOY*, and AMIR, all
b. That at least three fruit bearing durian trees Upon a careful review of the original decision dated
were uprooted and as a result of the August 13, 1999, a sentence should be added to
construction by the defendant of the tunnel and paragraph 1(a) of the dispositive portion thereof, to
about one hundred coconuts planted died. bolster, harmonize, and conform to the findings of
the Court, which is quoted hereunder, to wit:
c. That underground tunnel was constructed
therein.[5] Consequently, plaintiffs land or
properties are hereby condemned in favor of
defendant National Power Corporation, upon
After trial, the RTC ruled in favor of the plaintiffs (Heirs of payment of the aforesaid sum.
Macabangkit),[6] decreeing: Therefore, paragraph 1(a) of the dispositive portion
of the original decision should read, as follows:
d) To pay plaintiffs, the sum of Earlier, on August 18, 1999, the Heirs of Macabangkit filed an
TWO HUNDRED THOUSAND (P200,000.00) urgent motion for execution of judgment pending appeal.[9] The RTC
PESOS, as exemplary damages; granted the motion and issued a writ of execution,[10] prompting NPC to
assail the writ by petition for certiorari in the CA. On September 15, 1999,
e)To pay plaintiffs, the sum equivalent to the CA issued a temporary restraining order (TRO) to enjoin the RTC from
15% of the total amount awarded, as implementing its decision. The Heirs of Macabangkit elevated the ruling
attorneys fees, and to pay the cost. of the CA (G.R. No. 141447), but the Court upheld the CA on May 4,
2006.[11]
SO ORDERED.
Ruling of the CA
NPC raised only two errors in the CA, namely:
The RTC found that NPC had concealed the construction of the tunnel in
1979 from the Heirs of Macabangkit, and had since continuously denied
its existence; that NPC had acted in bad faith by taking possession of the
subterranean portion of their land to construct the tunnel without their I
knowledge and prior consent; that the existence of the tunnel had THE COURT A QUO SERIOUSLY ERRED IN RULING
affected the entire expanse of the land, and had restricted their right to THAT NAPOCORS UNDERGROUND TUNNEL IN ITS
excavate or to construct a motorized deep well; and that they, as owners, AGUS RIVER HYDRO-ELECTRIC PLANT PROJECT
had lost the agricultural, commercial, industrial and residential value of TRAVERSED AND/OR AFFECTED APPELLEES
the land. PROPERTY AS THERE IS NO CLEAR EVIDENCE
INDUBITABLY ESTABLISHING THE SAME
g) The amount involved in the controversy Court and in the CA lacked enlightening research and were insignificant
and the benefits resulting to the client from the to the success of the clients cause. His legal service, if it can be called that,
service; manifested no depth or assiduousness, judging from the quality of the
pleadings from him. His written submissions in the case appeared either
h) The contingency or certainty of to have been lifted verbatim from the pleadings previously filed by Atty.
compensation; Dibaratun, or to have been merely quoted from the decisions and
resolutions of the RTC and the CA. Of the Heirs of Macabangkit, only
i) The character of the employment, Cebu, Batowa-an, Sayana, Nasser, Manta, Mongkoy[78] and Edgar gave
whether occasional or established; and their consent to Atty. Ballelos to appear in their behalf in the CA, which he
did despite Atty. Dibaratun not having yet filed any withdrawal of his
j) The professional standing of the lawyer. appearance. The Court did not receive any notice of appearance for the
Heirs of Macabangkit from Atty. Ballelos, but that capacity has meanwhile
In the event of a dispute as to the amount of fees between the become doubtful in the face of Amirs strong denial of having retained
attorney and his client, and the intervention of the courts is sought, the him.
determination requires that there be evidence to prove the amount of
fees and the extent and value of the services rendered, taking into In fairness and justice, the Court accords full recognition to
account the facts determinative thereof.[75] Ordinarily, therefore, the Atty. Dibaratun as the counsel de parte of the Heirs of Macabangkit who
determination of the attorneys fees on quantum meruit is remanded to discharged his responsibility in the prosecution of the clients cause to its
the lower court for the purpose. However, it will be just and equitable to successful end. It is he, not Atty. Ballelos, who was entitled to the full
now assess and fix the attorneys fees of both attorneys in order that the amount of attorneys fees that the clients ought to pay to their attorney.
resolution of a comparatively simple controversy, as Justice Regalado put Given the amount and quality of his legal work, his diligence and the time
it in Traders Royal Bank Employees Union-Independent v. NLRC,[76] would he expended in ensuring the success of his prosecution of the clients
not be needlessly prolonged, by taking into due consideration the cause, he deserves the recognition, notwithstanding that some of the
accepted guidelines and so much of the pertinent data as are extant in clients might appear to have retained Atty. Ballelos after the rendition of a
the records. favorable judgment.[79]
Atty. Dibaratun and Atty. Ballelos each claimed attorneys fees equivalent Atty. Ballelos may claim only from Cebu, Batowa-an, Sayana, Nasser,
to 15% of the principal award of P113,532,500.00, which was the amount Manta and Edgar, the only parties who engaged him. The Court considers
granted by the RTC in its decision. Considering that the attorneys fees will his work in the case as very minimal. His compensation under
be defrayed by the Heirs of Macabangkit out of their actual recovery from the quantum meruit principle is fixed at P5,000.00, and only the Heirs of
NPC, giving to each of the two attorneys 15% of the principal award as Macabangkit earlier named are liable to him.
attorneys fees would be excessive and unconscionable from the point of
view of the clients. Thus, the Court, which holds and exercises the power
to fix attorneys fees on a quantum meruit basis in the absence of an WHEREFORE, the Court AFFIRMS the decision promulgated on October
express written agreement between the attorney and the client, now fixes 5, 2004 by the Court of Appeals, subject to the
attorneys fees at 10% of the principal award of P113,532,500.00. following MODIFICATIONS, to wit:
Whether it is Atty. Dibaratun or Atty. Ballelos, or both, who
should receive attorneys fees from the Heirs of Macabangkit is a question (a) Interest at the rate of 12% per
that the Court must next determine and settle by considering the amount annum is IMPOSED on the principal amount
and quality of the work each performed and the results each obtained. of P113,532,500.00 as just compensation,
reckoned from the filing of the complaint on
Atty. Dibaratun, the attorney from the outset, unquestionably carried the November 21, 1997 until the full liability is paid;
bulk of the legal demands of the case. He diligently prepared and timely
filed in behalf of the Heirs of Macabangkit every pleading and paper (b) The awards of P30,000.00 as rental
necessary in the full resolution of the dispute, starting from the complaint fee, P200,000.00 as moral damages,
until the very last motion filed in this Court. He consistently appeared and P200,000.00 as exemplary damages
during the trial, and examined and cross-examined all the witnesses are DELETED; and
presented at that stage of the proceedings. The nature, character, and
substance of each pleading and the motions he prepared for the Heirs of (c) The award of 15% attorneys fees decreed to be
Macabangkit indicated that he devoted substantial time and energy in paid by National Power Corporation to the Heirs
researching and preparing the case for the trial. He even of Macabangkit is DELETED.
Costs of suit to be paid by the petitioner. Petitioner averred that it already paid just compensation for the
establishment of the transmission lines by virtue of its compliance with
SO ORDERED. the final and executory Decision in National Power Corporation v.
Pereyras. Furthermore, assuming that respondent spouses had not yet
received adequate compensation for the intrusion upon their property,
#13 G. R. No. 189127 April 25, 2012 NAPOCOR argued that a claim for just compensation and damages may
only be filed within five years from the date of installation of the
NATIONAL POWER CORPORATION, Present: transmission lines pursuant to the provisions of Republic Act (R.A.) No.
Petitioner, 6395.[13]
CARPIO, J., Chairperson,
BRION, Pretrial terminated without the parties having entered into a compromise
PEREZ, agreement.[14] Thereafter, the court appointed Lydia Gonzales and
- versus - SERENO, and Wilfredo Silawan as Commissioners for the purpose of determining the
REYES, JJ. valuation of the subject land.[15] NAPOCOR recommended Loreto
Monteposo as the third Commissioner,[16] but later clarified that its
conformity to the appointment of commissioners was only for the
SPOUSES BERNARDO AND purpose of determining the exact portion of the subject land, and that it
MINDALUZ SALUDARES, was not admitting its liability to pay just compensation.[17]
Respondents.
After the proceedings, the Commissioners recommended the amount
of ₱750 per square meter as the current and fair market value of the
x-------------------------------x subject property based on the Schedule of Market Values of Real
SERENO, J.: Properties within the City of Tagum effective in the year 2000.[18]
This Rule 45 Petition questions the 21 July 2009 Decision of the Trial on the merits ensued. On 10 September 2002, the Court
Court of Appeals (CA),[1] which affirmed the 10 September 2002 Decision rendered judgment in favor of respondent spouses, the dispositive
of the Regional Trial Court (RTC),[2] Branch 31, Tagum City. The RTC had portion of which reads:
ruled that respondent spouses are entitled to ₱4,920,750 as just
compensation for the exercise of the power of eminent domain by WHEREFORE, premises considered, judgment is
petitioner National Power Corporation (NAPOCOR). hereby rendered in favor of the plaintiffs, and against
Sometime in the 1970s, NAPOCOR constructed high-tension the defendant-National Power Corporation, ordering
transmission lines to implement the Davao-Manat 138 KV Transmission the latter to pay the plaintiffs the Just Compensation
Line Project.[3] These transmission lines traversed a 12,060-square meter as herein fixed which they claimed for the use,
portion of a parcel of agricultural land covered by Transfer Certificate of occupation and utilization of their land from which it
Title (TCT) No. T-15343 and owned by Esperanza Pereyras, Marciano benefited and profited since January 1982, as follows:
Pereyras, Laureano Pereyras and Mindaluz Pereyras.
First: To pay plaintiff Spouses Bernardo and Mindaluz
In 1981, NAPOCOR commenced expropriation proceedings Saludares as just compensation of their 6,561 square
covering TCT No. T-15343 in National Power Corporation v. Esperanza meters, more or less, titled land covered by TCT No.
Pereyras, Marciano Pereyras, Laureano Pereyras and Mindaluz T-109865 of the Registry of Deeds of Davao del
Pereyras.[4] These proceedings culminated in a final Decision ordering it to Norte hereby fixed in the amount of FOUR MILLION
pay the amount of ₱300,000 as just compensation for the affected NINE HUNDRED TWENTY THOUSAND SEVEN
property.[5] HUNDRED FIFTY (₱4,920,750.00) PESOS, Philippine
Currency, plus interest at the rate of 12% per annum
The trial court issued an Order[6] subrogating Tahanan Realty reckoned from January 01, 1982, until said amount is
Development Corporation to the rights of the defendants in National fully paid, or deposited in Court;
Power Corporation v. Pereyras. Pursuant to this Order, NAPOCOR paid the
corporation the judgment award of ₱300,000[7] and Tahanan Realty Second: To pay plaintiffs-spouses Bernardo and
Development Corporation executed a Deed of Absolute Sale in favor of Mindaluz Saludares attorneys fees of Fifty Thousand
the former.[8] This Deed covered Lot 481-B, Psd-11012718, which was a (₱50,000.00) Pesos, Philippine Currency, plus
portion of Lot 481, Cad. 276 of Barrio Magugpo, Municipality of Tagum, appearance fee of ₱2,000.00 per appearance and
Davao.[9] litigation expenses which shall be supported in a Bill
of Costs to be submitted for the Courts approval;
Respondent Spouses Bernardo and Mindaluz Pereyras-
Saludares are registered owners of a 6,561-square-meter parcel of land Third. To pay the costs of the suit.
covered by TCT No. T-109865,[10] more particularly described as follows:
ProvRem Rule 67 Fulltext Page 103 of 119
Fourth. For utter lack of merit, the counterclaim is Furthermore, the evidence before us supports respondent
dismissed. spouses contention that the lands involved in both cases are
different. National Power Corporation v. Pereyrasinvolved Lot 481-B, Psd-
SO ORDERED.[19] 11012718, which was a portion of Lot 481, Cad. 276 of Barrio Magugpo,
Municipality of Tagum, Davao.[24] On the other hand, the instant Petition
involves Lot 15, Pcs-11-000704, Amd., which is a portion of Lots 481-D,
NAPOCOR appealed the trial courts Decision to the CA.[20] After Psd-11-012718; 480-B, Psd-51550; H-148559 and 463-A-2 (LRC), Psd-
a review of the respective parties Briefs, the appellate court rendered the 150796, in Barrio Magugpo, Municipality of Tagum, Davao. Clearly, these
assailed Decision on 21 July 2009, denying NAPOCORs appeal and lots refer to different parcels of land.[25]
affirming the trial courts Decision, but reducing the rate of interest to 6%
per annum.[21] We rule, therefore, that NAPOCOR failed to prove its previous payment of
just compensation for its expropriation of the land in question.
Aggrieved, petitioner then filed the instant Rule 45 Petition
before this Court. II
The demand for payment of just compensation
has not prescribed
The Issues
The pivotal issues as distilled from the pleadings are as follows: Petitioner maintains that, in the event respondent spouses have not been
adequately compensated for the entry into their property, their claim for
1. Whether NAPOCOR has previously compensated the just compensation would have already prescribed,[26] pursuant to Section
spouses for establishing high-tension transmission lines 3 (i) of R.A. No. 6395, as amended by Presidential Decrees Nos. 380, 395,
over their property; 758, 938, 1360 and 1443. This provision empowers the NAPOCOR to do as
follows:
2. Whether the demand for payment of just compensation
has already prescribed; x x x [E]nter upon private property in the lawful
performance or prosecution of its business or
3. Whether petitioner is liable for only ten percent of the fair purposes, including the construction of the
market value of the property or for the full value thereof; transmission lines thereon; Provided, that the owner
and of such private property shall be paid the just
compensation therefor in accordance with the
4. Whether the trial court properly awarded the amount provisions hereinafter provided; Provided, further,
of ₱4,920,750 as just compensation, based on the that any action by any person claiming
Approved Schedule of Market Values for Real Property in compensation and/or damages shall be filed
Tagum City for the Year 2000. within five (5) years after the right-of-way,
transmission lines, substations, plants or other
The Courts Ruling facilities shall have been established; Provided,
finally, that after the said period no suit shall be
We uphold the Decisions of the CA and the RTC. brought to question the said right-of-way,
transmission lines, substations, plants or other
I facilities nor the amounts of compensation and/or
NAPOCOR failed to prove that it had adequately damages involved. (Emphasis supplied.)
compensated respondents for the establishment
of high tension transmission lines over their NAPOCORs reliance on this provision is misplaced.
property
The right to recover just compensation is enshrined in no less than our Bill
of Rights, which states in clear and categorical language that [p]rivate
NAPOCOR argues that the parcel of land involved in the instant property shall not be taken for public use without just
Petition had already been expropriated in National Power Corporation v. compensation.[27] This constitutional mandate cannot be defeated by
Pereyras.[22] In support of this argument, it alleges that one of the sources statutory prescription.[28] Thus, we have ruled that the prescriptive period
of the spouses TCT No. T-109865 is TCT No. 39660; and that TCT No. under Section 3 (i) of R.A. No. 6395 does not extend to an action to
39660 is a transfer from TCT No. T-15343, the subject land in National recover just compensation.[29] It would be a confiscatory act on the part of
Power Corporation v. Pereyras.[23] Thus, having paid just compensation to the government to take the property of respondent spouses for a public
Tahanan Realty Development Corporation, the successor-in-interest of purpose and deprive them of their right to just compensation, solely
defendants Pereyras in the aforementioned case, petitioner submits that it because they failed to institute inverse condemnation proceedings within
should no longer be made to pay just compensation in the present case. five years from the time the transmission lines were constructed. To begin
with, it was not the duty of respondent spouses to demand for just
We disagree. compensation. Rather, it was the duty of NAPOCOR to institute eminent
domain proceedings before occupying their property. In the normal
While it is true that respondent spouses TCT No. T-109865 was indeed course of events, before the expropriating power enters a private
indirectly sourced from TCT No. T-15343, the CA correctly ruled that property, it must first file an action for eminent domain[30] and deposit
NAPOCOR failed to prove that the lands involved in National Power with the authorized government depositary an amount equivalent to the
Corporation v. Pereyras and in the instant Petition are identical. One assessed value of the property.[31] Due to its omission, however,
cannot infer that the subject lands in both cases are the same, based on respondents were constrained to file inverse condemnation proceedings
the fact that one of the source titles of TCT No. T-109865 happens to be to demand the payment of just compensation before the trial court. We
TCT No. T-38660, and that TCT No. T-38660 itself was derived from T- therefore rule that NAPOCOR cannot invoke the statutory prescriptive
15343. period to defeat respondent spouses constitutional right to just
compensation.
WHEREFORE, premises considered, the petition is PARTIALLY GRANTED. We maintain our conclusions in the assailed July 1, 2013 Decision with
The Court of Appeals Decision dated July 31, 2007 in CAG.R. CV No. modification on the amount of interest awarded, as well as the additional
77997 is MODIFIED, in that the valuation of the subject property owned grant of exemplary damages and attorney's fees.
by respondents shall be P0.70 instead of ₱1,500.00 per square meter, with
interest at six percent (6%) per annum from the date of taking in 1940 At the outset, it should be stressed that the matter of the validity of the
instead of March 17, 1995, until full payment.2 State's exercise of the power of eminent domain has long been settled. In
fact, in our assailed decision, We have affirmed the ruling of the CA that
In view of the contrasting opinions of the members of the Third Division the pre-trial order issued on May 17, 2001 has limited the issues as
on the instant motion, and the transcendental importance of the issue follows: (1) whether or not the respondents-movants are entitled to just
raised herein, the members of the Third Division opted to refer the issue compensation; (2) whether or not the valuation would be based on the
to the En Banc for resolution. corresponding value at the time of the taking or at the time of the filing
of the action; and (3) whether or not the respondents-movants are
entitled to damages.8 Moreover, it was held that for failure of
For a proper perspective, we briefly state the factual background of the respondents-movants to question the lack of expropriation proceedings
case.
for a long period of time, they are deemed to have waived and are
estopped from assailing the power of the government to expropriate or
In 1940, the Department of Public Works and Highways (DPWH) took the public use for which the power was exercised.9 What is, therefore, left
respondents-movants' subject property without the benefit of for determination in the instant Motion for Reconsideration, in
expropriation proceedings for the construction of the MacArthur accordance with our Decision dated July 1, 2013, is the propriety of the
Highway. In a letter dated December 15, 1994,respondents-movants amount awarded to respondents as just compensation.
demanded the payment of the fair market value of the subject parcel of
land. Celestino R. Contreras (Contreras), then District Engineer of the First At this juncture, We hold that the reckoning date for property valuation in
Bulacan Engineering District of the DPWH, offered to pay for the subject determining the amount of just compensation had already been
land at the rate of Seventy Centavos (P0.70) per square meter, per addressed and squarely answered in the assailed decision. To be sure, the
Resolution of the Provincial Appraisal Committee (PAC) of Bulacan. justness of the award had been taken into consideration in arriving at our
Unsatisfied with the offer, respondents-movants demanded the return of earlier conclusion.
their property, or the payment of compensation at the current fair market
value.3 Hence, the complaint for recovery of possession with damages
filed by respondents-movants. Respondents-movants were able to obtain We have in the past been confronted with the same issues under similar
favorable decisions in the Regional Trial Court (RTC) and the Court of factual and procedural circumstances. We find no reason to depart from
Appeals (CA), with the subject property valued at One Thousand Five the doctrines laid down in the earlier cases as we adopted in the assailed
Hundred Pesos (₱1,500.00) per square meter, with interest at six percent decision. In this regard, we reiterate the doctrines laid down in the cases
(6%) per annum. of Forfom Development Corporation (Forfom) v. Philippine National
Railways (PNR),10 Eusebio v. Luis,11 Manila International Airport Authority v.
Rodriguez,12 and Republic v. Sarabia.13
Petitioners thus elevated the matter to this Court in a petition for review
on certiorari. The only issue resolved by the Court in the assailed decision
is the amount of just compensation which respondents-movants are In Forfom, PNR entered the property of Forfom in January 1973 for
entitled to receive from the government for the taking of their property. railroad tracks, facilities and appurtenances for use of the Carmona
Both the RTC and the CA valued the property at One Thousand Five Commuter Service without initiating expropriation proceedings. In 1990,
Hundred Pesos (₱1,500.00) per square meter, plus six percent (6%) Forfom filed a complaint for recovery of possession of real property
interest from the time of the filing of the complaint until full payment. We, and/or damages against PNR. In Eusebio, respondent's parcel of land was
however, did not agree with both courts and ruled instead that just taken in 1980 by the City of Pasig and used as a municipal road without
compensation should be based on the value of the property at the time of the appropriate expropriation proceedings. In1996, respondent filed a
taking in 1940, which is Seventy Centavos (P0.70) per square meter.4 In complaint for reconveyance and/or damages against the city government
addition, and by way of compensation, we likewise awarded an interest of and the mayor. In MIAA, in the early 1970s, petitioner implemented
six percent (6%) per annum from 1940 until full payment.5 expansion programs for its runway, necessitating the acquisition and
occupation of some of the properties surrounding its premises. As to
respondent's property, no expropriation proceedings were initiated. In
Aggrieved, respondents-movants hereby move for the reconsideration of 1997, respondent initiated a case for accion reivindicatoriawith damages
said decision on the following grounds:
against petitioner. In Republic, sometime in 1956, the Air Transportation
Office (ATO) took possession and control of a portion of a lot situated in
A. THE HONORABLE COURT MAY LOOK INTO THE "JUSTNESS" Aklan, registered in the name of respondent, without initiating
OF THE MISERABLE AMOUNT OF COMPENSATION BEING expropriation proceedings. Several structures were erected thereon,
AWARDED TO THE HEREIN RESPONDENTS; and including the control tower, the Kalibo crash fire rescue station, the Kalibo
airport terminal, and the Headquarters of the PNP Aviation Security
B. THE HONORABLE COURT MAY SETTLE FOR A HAPPY MIDDLE Group. In 1995,several stores and restaurants were constructed on the
GROUND IN THE NAME OF DOCTRINAL PRECISION AND remaining portion of the lot. In 1997, respondent filed a complaint for
SUBSTANTIAL JUSTICE.6 recovery of possession with damages against the storeowners wherein
ATO intervened claiming that the storeowners were its lessees.
Citing the views of Justices Presbitero J. Velasco, Jr. and Marvic Mario
Victor F. Leonen in their Dissenting and Concurring Opinion and Separate
ProvRem Rule 67 Fulltext Page 106 of 119
These cases stemmed from similar background, that is, government took We recognized in Republic v. Court of Appeals the need for prompt
control and possession of the subject properties for public use without payment and the necessity of the payment of interest to compensate for
initiating expropriation proceedings and without payment of just any delay in the payment of compensation for property already taken. We
compensation; while the landowners failed for a long period of time to ruled in this case that:
question such government act and later instituted actions for recovery of
possession with damages. In these cases, the Court has uniformly ruled The constitutional limitation of "just compensation" is considered to be
that the fair market value of the property at the time of taking is the sum equivalent to the market value of the property, broadly described
controlling for purposes of computing just compensation. to be the price fixed by the seller in open market in the usual and ordinary
course of legal action and competition or the fair value of the property as
In Forfom, the payment of just compensation was reckoned from the time between one who receives, and one who desires to sell, i[f] fixed at the
of taking in 1973; in Eusebio, the Court fixed the just compensation by time of the actual taking by the government. Thus, if property is taken
determining the value of the property at the time of taking in 1980; for public use before compensation is deposited with the court having
in MIAA, the value of the lot at the time of taking in 1972 served as basis jurisdiction over the case, the final compensation must include
for the award of compensation to the owner; and, in Republic,the Court interest[s] on its just value to be computed from the time the property
was convinced that the taking occurred in 1956 and was thus the basis in is taken to the time when compensation is actually paid or deposited
fixing just compensation. with the court. In fine, between the taking of the property and the
actual payment, legal interest[s] accrue in order to place the owner in
As in the aforementioned cases, just compensation due respondents- a position as good as (but not better than) the position he was in
movants in this case should, therefore, be fixed not as of the time of before the taking occurred.[Emphasis supplied]20
payment but at the time of taking in 1940 which is Seventy Centavos
(P0.70) per square meter, and not One Thousand Five Hundred Pesos In other words, the just compensation due to the landowners amounts to
(₱1,500.00) per square meter, as valued by the RTC and CA. an effective forbearance on the part of the State-a proper subject of
interest computed from the time the property was taken until the full
While disparity in the above amounts is obvious and may appear amount of just compensation is paid-in order to eradicate the issue of the
inequitable to respondents-movants as they would be receiving such constant variability of the value of the currency over time.21 In the Court's
outdated valuation after a very long period, it should be noted that the own words:
purpose of just compensation is not to reward the owner for the property
taken but to compensate him for the loss thereof. As such, the true The Bulacan trial court, in its 1979 decision, was correct in imposing
measure of the property, as upheld by a plethora of cases, is the market interests on the zonal value of the property to be computed from the
value at the time of the taking, when the loss resulted. This principle was time petitioner instituted condemnation proceedings and "took" the
plainly laid down in Apo Fruits Corporation and Hijo Plantation, Inc. v. Land property in September 1969. This allowance of interest on the amount
Bank of the Philippines,14 to wit: found to be the value of the property as of the time of the taking
computed, being an effective forbearance, at 12% per annum should
x x x In Land Bank of the Philippines v. Orilla, a valuation case under our help eliminate the issue of the constant fluctuation and inflation of
agrarian reform law, this Court had occasion to state: the value of the currency over time x x x.22
Constitutionally, "just compensation" is the sum equivalent to the market On this score, a review of the history of the pertinent laws, rules and
value of the property, broadly described as the price fixed by the seller in regulations, as well as the issuances of the Central Bank (CB)or Bangko
open market in the usual and ordinary course of legal action and Sentral ng Pilipinas (BSP)is imperative in arriving at the proper amount of
competition, or the fair value of the property as between the one who interest to be awarded herein.
receives and the one who desires to sell, it being fixed at the time of the
actual taking by the government. Just compensation is defined as the On May 1, 1916, Act No. 265523 took effect prescribing an interest rate of
full and fair equivalent of the property taken from its owner by the six percent (6%) or such rate as may be prescribed by the Central Bank
expropriator. It has been repeatedly stressed by this Court that the Monetary Board (CB-MB)for loans or forbearance of money, in the
true measure is not the taker's gain but the owner's loss. The word absence of express stipulation as to such rate of interest, to wit:
"just" is used to modify the meaning of the word "compensation" to
convey the idea that the equivalent to be given for the property to be Section 1. The rate of interest for the loan or forbearance of any money
taken shall be real, substantial, full and ample. [Emphasis supplied.]15 goods, or credits and the rate allowed in judgments, in the absence of
express contract as to such rate of interest, shall be six per centum per
Indeed, the State is not obliged to pay premium to the property owner for annum or such rate as may be prescribed by the Monetary Board of
appropriating the latter's property; it is only bound to make good the loss the Central Bank of the Philippines for that purpose in accordance
sustained by the landowner, with due consideration of the circumstances with the authority hereby granted.
availing at the time the property was taken. More, the concept of just
compensation does not imply fairness to the property owner alone. Sec. 1-a. The Monetary Board is hereby authorized to prescribe the
Compensation must also be just to the public, which ultimately bears the maximum rate or rates of interest for the loan or renewal thereof or the
cost of expropriation.16 forbearance of any money, goods or credits, and to change such rate or
rates whenever warranted by prevailing economic and social conditions.
Notwithstanding the foregoing, we recognize that the owner's loss is not
only his property but also its income-generating potential.17 Thus, when In the exercise of the authority herein granted, the Monetary Board may
property is taken, full compensation of its value must immediately be paid prescribe higher maximum rates for loans of low priority, such as
to achieve a fair exchange for the property and the potential income consumer loans or renewals thereof as well as such loans made by
lost.18 Accordingly, in Apo, we held that the rationale for imposing the pawnshops finance companies and other similar credit institutions
interest is to compensate the petitioners for the income they would have although the rates prescribed for these institutions need not necessarily
made had they been properly compensated for their properties at the be uniform. The Monetary Board is also authorized to prescribe different
time of the taking.19 Thus: maximum rate or rates for different types of borrowings, including
deposits and deposit substitutes, or loans of financial intermediaries.24
Sec. 2. The rate of interest for the loan or forbearance of any money,
goods or credits and the rate allowed in judgments, in the absence of January 1, 194035 to July 28, 1974 P
express contract as to such rate of interest, shall continue to be twelve 10,553.4937
per cent (12%) per annum.28
July 29, 1974 to March 16, 1995 26,126.3138
Recently, the BSP Monetary Board (BSP-MB),in its Resolution No. 796
March 17, 199536to June 30, 2013 232,070.3339
dated May 16, 2013, approved the amendment of Section 2 of Circular
No. 905, Series of 1982, and accordingly, issued Circular No. 799, Series of
July 1, 2013 to September 30, 2014 250,098.1940
2013, effective July 1, 2013, the pertinent portion of which reads:
The Monetary Board, in its Resolution No. 796 dated 16 May 2013, Market Value of the Property at the time of
approved the following revisions governing the rate of interest in the taking including interest P 518,848.32
absence of stipulation in loan contracts, thereby amending Section 2 of
Circular No. 905, Series of 1982:
Market value of the property at the time of
taking including interest P 518,848.32
Section 1. The rate of interest for the loan or forbearance of any
money, goods or credits and the rate allowed in judgments, in the
Add: Exemplary damages 1,000.000.00
absence of an express contract as to such rate of interest, shall be six
percent (6%) per annum. Attorney's fees 200,000.00
Section 2. In view of the above, Subsection X305.1 of the Manual of Total Amount of Interest due to
Regulations for Banks and Sections 4305Q.1, 4305S.3 and 4303P.1 of the Respondents-
Manual of Regulations for Non-Bank Financial Institutions are hereby Movants as of September 30, 2014 ₱1,718,848.16
amended accordingly.
Law, Rule and Regulations, Date of Effectivity Interest Rate Clearly, the award of interest on the value of the land at the time of taking
BSP Issuance in 1940 until full payment is adequate compensation to respondents-
movants for the deprivation of their property without the benefit of
Act No. 2655 May 1, 1916 6% expropriation proceedings. Such interest, however meager or enormous it
may be, cannot be inequitable and unconscionable because it resulted
CB Circular No. 416 July 29, 1974 12% directly from the application of law and jurisprudence-standards that have
CB Circular No. 905 December 22, 1982 12% taken into account fairness and equity insetting the interest rates due for
the use or forbearance of money.41 Thus, adding the interest computed to
CB Circular No. 799 July 1, 2013 6% the market value of the property at the time of taking signifies the real,
Before the court can issue a Writ of Possession, the implementing agency WHEREFORE, the motion for reconsideration is hereby DENIED for lack of
shall present to the court a certificate of availability of funds from the merit.
proper official concerned.
SO ORDERED.
In the event that the owner of the property contests the implementing
agency's proffered value, the court shall determine the just compensation #15 G.R. No. 223366 August 1, 2017
to be paid the owner within sixty (60) days from the date of filing of the
expropriation case. When the decision of the court becomes final and
executory, the implementing agency shall pay the owner the difference NATIONAL TRANSMISSION CORPORATION, Petitioner,
between the amount already paid and the just compensation as vs.
determined by the court. OROVILLE DEVELOPMENT CORPORATION, Respondent
Failure to comply with the foregoing directives shall subject the MENDOZA, J.:
government official or employee concerned to administrative, civil and/or
criminal sanctions, thus: This is a petition for review on certiorari seeking to reverse and set aside
the September 18, 2015 Decision1 and January 25, 2016 Resolution2 of the
Section 11. Sanctions. - Violation of any provisions of this Act shall subject Court of Appeals (CA) in CA-G.R. CV No. 03571, which affirmed with
the government official or employee concerned to appropriate modification the December 12, 2012 Decision3 of the Regional Trial Court,
administrative, civil and/or criminal sanctions, including suspension Branch 17, Misamis Oriental (RTC) in Civil Case No. 2007-85, a case for
and/or dismissal from the government service and forfeiture of benefits. expropriation.
While the foregoing provisions, being substantive in nature or disturbs
substantive rights, cannot be retroactively applied to the present case, We The Antecedents
trust that this established mechanism will surely deter hasty acquisition of
private properties in the future without the benefit of immediate payment The present case involves two (2) parcels of land located in Puerto,
of the value of the property in accordance with Section 4 of R.A. 8974. Cagayan de Oro City, which originally belonged to Alfredo Reyes (Reyes)
This effectively addresses J. Velasco's concerns that sustaining our earlier and Grace Calingasan (Calingasan), covered by Original Certificate of Title
rulings on the matter would be licensing the government to dispense with (OCT) No. P-3 and OCT No. P-13, respectively.
constitutional requirements in taking private properties. Moreover, any
gap on the procedural aspect of the expropriation proceedings will be
remedied by the aforequoted provisions. In 1983, petitioner National Transmission Corporation (TransCo)
constructed a power transmission line on these properties, known as the
Tagoloan-Pulangi 138 kV transmission line.
In effect, R.A. 8974 enshrines a new approach towards eminent domain
that reconciles the inherent unease attending expropriation proceedings
with a position of fundamental equity.47 At some point, Reyes sold his land to Antonio Navarette, who later sold
the same property to respondent Oroville Development Corporation
(Oroville), which is now covered by Transfer Certificate of Title (TCT) No. T-
85121. Likewise, Calingasan sold her land to Oroville, now registered
ProvRem Rule 67 Fulltext Page 110 of 119
under TCT No. T-104365. Thus, in 1995, Oroville became the registered Valuation of the Property: ₱78.65 per square meter or a total of
owner of these properties with a total area of 13 ,904 square meters ₱5,924,772.48 inclusive of interests4
traversed by the existing Tagoloan-Pulangi 138 kV transmission line.
2. Engr. Norberto Badelles (engaged by Transco)
On November 17, 2006, Transco offered to buy these properties from
Oroville to be used for the construction of the Abaga-Kirahon 230 kV
transmission line in Mindanao. Date of 1983 per Transmission Line Data and
Taking: Information
(Tagoloan-Pulangi 138 kV Transmission
During the negotiation, Oroville, through its representative Antonio Tiu
Line)
(Tiu), requested to reroute the Abaga-Kirahon 230 kV transmission line
because the Tagoloan-Pulangi 138 kV transmission line is already
traversing its properties. Tiu also informed Transco that Oroville has not Valuation of the Property: ₱1.20 per square meter or a total of
been paid just compensation for the constn1ction of the Tagoloan- ₱45,716.35 inclusive of interests5
Pulangi 138 kV transmission line in its property. Transco, however, refused
to reroute the proposed Abaga-Kirahon 230 kV transmission line because
3. Atty. Avelino Pakino (nominated by Oroville)
it planned to construct the said transmission line parallel to the existing
Tagoloan-Pulangi 138 kV transmission line.
Date of 1983 per Transmission Line Data and
Consequently, on April 20, 2007, Oroville filed a complaint for injunction Taking: Information
and damages with prayer for issuance of a temporary restraining order (Tagoloan-Pulangi 138 kV Transmission
against Transco, seeking to enjoin the construction of the Abaga-Kirahon Line)
230 kV transmission line.
During trial, the parties agreed to have the subject properties surveyed for In its Decision, dated December 12, 2012, the RTC set aside the
purposes of fixing the just compensation. As a result, the trial court Commissioners' report and fixed the just compensation at the rate of
suspended the proceedings and directed Transco to conduct a survey of ₱1,520.00 per square meter with legal interest of 12%
the properties. per annum reckoned from April 20, 2007, the date of filing of the
complaint. It held that the said amount was based on the fair market
value of lots along the national highway of Barangay Puerto, Cagayan de
Subsequently, Oroville filed an omnibus motion to convert the
Oro City in accordance with the schedule of values under City Ordinance
proceedings into an expropriation case and to require Transco to pay the
No. 10425-2006 otherwise known as An Ordinance Prescribing the
Bureau of Internal Revenue (BIR) the zonal value of the subject properties.
Revised Schedule of Fair Market Values of Real Property in Cagayan de
Transco made no objections to the motion.
Oro and in accordance with the BIR Comparative Value of Zonal Fair
Market Values. The RTC opined that the just compensation should not be
On May 17, 2010, the trial court directed Transco to make a provisional reckoned from 1983, the time of taking, because it was established by the
deposit of ₱7,647,200.00 as just compensation for Oroville's properties landowners that entry into their property was without their knowledge.
consisting of 13,904 square meters and affected by the existing Tagoloan- The falloreads:
Pulangi 138 kV transmission line. Transco complied after the trial court
denied its objections.
WHEREFORE, in view of the foregoing premises, judgment is hereby
rendered as follows:
On February 4, 2011, the trial court directed the Land Bank of the
Philippines, NAPOCOR Branch, to release the aforesaid deposit to Tiu.
1) FIXING the just compensation of the affected area of 13,904
square meters at ₱1,520.oo per square meter reckoned from
On March 21, 2011, the trial court issued a writ of possession directing April 20, 2007, the date the complaint was filed, at interest rate
Oroville to surrender possession of the properties to Transco. of 12% per annum until the liability is fully paid
Subsequently, on August 8, 2011, per nomination of the parties, the trial 2) ORDERING defendant TRANSCO to pay plaintiff the just
court appointed three (3) Commissioners, namely, Engr. Marilyn P. compensation in the amount of ₱1,520.00 per square meter for
Legaspi, Engr. Norberto Badelles and Atty. Avelino Pakino, to determine the 13,904 square meters the affected area at the rate of
the just compensation of the properties affected by the Abaga-Kirahon 12% per annum reckoned from April 20, 2007, the data of filing
230 kV transmission line. the complaint minus the amount of ₱7,647,200.oo representing
the amount paid by TRANSCO as provisional payments
A summary of the Commissioners' report reads as follows:
3) ORDERING defendant TRANSCO to pay plaintiff the interest
1. Engr. Marilyn Legaspi (Court-appointed Commissioner) of 12% per annum based on the deficiency amount;
Tecson also clarified the amount of interest due the landowners, to wit: Transco should first file an expropriation case before it proceeds to
construct transmission lines or any other infrastructure on any private
x x x In other words, the just compensation due to the landowners property. The practice of construct first, expropriate later must be put to a
amounts to an effective forbearance on the part of the State - a proper stop.
subject of interest computed from the time the property was taken until
the full amount of just compensation is paid - in order to eradicate the WHEREFORE, the petition is GRANTED. The September 18, 2015
issue of the constant variability of the value of the currency over time. Decision and January 25, 2016 Resolution of the Court of Appeals in
CAG.R. CV No. 03571, are REVERSED and SETASIDE. The valuation of the
x x xx subject property owned by respondent Oroville shall be ₱78.65 per square
meter, with interest at twelve percent (12%) per annum from January 1983
until January 21, 2011. Petitioner Transco is also ordered to pay
It is important to note, however, that interest shall be compounded at the respondent Oroville exemplary damages in the amount of ₱1,000,000.00
time judicial demand is made pursuant to Article 2212 of the Civil Code of and attorney's fees in the amount of ₱200,000.00.
the Philippines, and sustained in Eastern Shipping Lines v. Court of
Appeals, then later on in Nacar v. Gallery Frames, save for the reduction of
interest rate to 6% for loans or forbearance of money.39 x x x SO ORDERED.
TIJAM, J.:
x x x However, we find it proper to award temperate and exemplary
damages in light of NIA's misuse of its power of eminent
domain. Any arm of the State that exercises the delegated power of This Petition for Review1 on Certiorari under Rule 45 challenges the
eminent domain must wield that power with circumspection and utmost Decision2 dated September 1, 2015 of the Court of Appeals (CA) in CA�
regard for procedural requirements. A government instrumentality that G.R. CV No. 97640, which affirmed the Decision3 dated December 20,
fails to observe the constitutional guarantees of just compensation 2010 of the Regional Trial Court (RTC) of Pili, Camarines Sur, in the
and due process abuses the authority delegated to it, and is liable to expropriation case commenced by petitioner National Power Corporation
the property owner for damages.42 x x x (NPC) against respondents as registered owners of the subject properties.
Hence, considering that Oroville was deprived of beneficial ownership The Antecedents
over their property without the benefit of a timely expropriation
proceeding, and to serve as a deterrent to the State from failing to For purposes of constructing and maintaining its steel transmission lines
institute such proceedings, a grant of exemplary damages in the amount and wooden electric poles for its Naga-Tiwi 230 KV (Single Bundle), Naga-
of One Million Pesos (₱1,000,000.00) is fair and reasonable. Moreover, an Tiwi 230 KV (Double Bundle) and 69 KV Naga-Daraga Transmission Lines,
award for attorney's fees in the amount of Two Hundred Thousand Pesos NPC filed, on January 23, 2006, an expropriation complaint4 against
(₱200,000.00) in favor of Oroville is in order. respondents as registered owners of the following four parcels of land
located in Barangays Sagurong, San Agustin and San Jose, Pili, Camarines
Sur:
To recapitulate, Transco is liable to pay Oroville ₱78.65 per square meter
representing the fair market value of the property at the time of taking in
ProvRem Rule 67 Fulltext Page 115 of 119
respondents as "dangling" areas were classified as agricultural under the
Tax Dec. Area tax declarations and that NPC negotiated with respondents for purposes
Lot No. OCT No. Total Area
No. Affected of installing the transmission lines in 199627 and that NPC took the subject
properties in between the years 1996 to 1998.28 The right-of-way officer
97-014- further testified that the "dangling" areas could still be used for
516-B 6265 8,712 sq.m. 2,908 sq.m.
2276 agricultural purposes but nevertheless agreed that the presence of the
transmission lines may endanger the people and animals therein if in case
97-014- 861,163 they fell.29 On cross-examination, the right of way officer admitted that
4237 6277 33,196 sq.m.
3948 sq.m. the properties were classified as agro� industrial as stated in the 1998 tax
declarations. He admitted that the classification of the properties as
97-014- agricultural which was used as basis for computing its value was
2870 6289 13,462 sq.m. 5,940 sq.m.
39110 erroneous.30
97-014- The RTC rendered its Decision dated December 20, 2010 affirming the
517-B 62911 13,765 sq.m. 7,129 sq.m.
22812 recommendation of the appraisal committee for the payment of just
compensation and fixed the amount of PhP 47,064,400 for the 49,173
Total 49,173 square meters based on the BIR zonal valuation of the properties
Area: sq.m. classified as residential, commercial and industrial as of the time of the
filing of the complaint on January 23, 2006. The RTC rejected NPC's claim
that it took possession of the property in 1972 and 1974 when
The total area over which NPC sought an easement of right of way covers respondents allegedly. allowed NPC to construct the transmission lines for
49,173 square meters of the subject properties.13 Based on the tax lack of proof. In addition, the RTC held that had the properties been taken
declarations allegedly classifying the properties as agricultural and based on said years, such taking was without color of legal authority. The RTC
on the corresponding Bureau of Internal Revenue's (BIR) zoning valuation likewise adopted the recommendation of the appraisal committee for the
therefor, NPC offered to pay PhP 299,550.50.14 payment of PhP 22,227,800 as consequential damages for the 41,867
square meters portion of the properties which were rendered useless or
While interposing no objection to the expropriation, respondents no longer fit for its intended use due to the construction of the
nevertheless opposed the classification of the properties as agricultural on transmission lines.31
the ground that the same were classified as industrial, commercial and
residential since the year 1993 as shown by (1) Sangguniang Bayan In disposal, the RTC held:
Resolution No. 17; (2) Municipal Ordinance No. 7 dated February 1, 1993;
(3) annotations on the memorandum of encumbrances of the titles; (4)
Wherefore, judgment is hereby rendered:
DARCO Conversion Order No. 050301016014-(300)-00, Series of 2000
issued by the Department of Agrarian Reform; and (5) Certification issued
by the Municipal Assessor of Pili, Camarines Sur.15 Respondents thus 1. Approving and adopting the Commissioner's Report dated August 9,
claimed PhP 47,064,400 for the affected 49,173 square meters. By way of 2006 and November 24, 2008;
counterclaim, respondents sought payment of consequential damages for
the areas left in between each transmission line, like the spaces 2. The payment of the provisional value (on May 19, 2006 when plaintiff
underneath the infrastructure, commonly known as "dangling" portions in made the deposit) of P47,064,400.00 as just compensation for the 49,173
the total area of 41,869 square meters.16 square meters area directly affected by the transmission lines is the
payment for the just compensation with 12% interest per annum (Marina
After the pre-trial, the RTC issued an Order of Expropriation and further Z. Reyes, et al. vs. National Housing Authority, G.R. No. 147511, January 20,
fixed the provisional value of the properties at PhP 47,064,400, which 2003), from the date of filing of this case until paid;
amount was eventually deposited by NPC with Landbank of the
Philippines.17 Accordingly, in an Omnibus Order dated May 23, 2006, the 3. Condemning plaintiff to pay defendants the amount of P22,227,800.00
RTC issued a writ of possession in favor of NPC and ordered the LBP to as consequential damages with interest at 12% per annum from January
release to respondents the amount deposited.18 Meanwhile, an appraisal 23, 2006 until fully paid;
committee was formed by the RTC for purposes of determining just
compensation,19 which thereafter submitted a Consolidated Report dated
4. To pay P20,000.00 attorney's fees.
August 10, 2006.20 A reversed trial thereafter ensued.
SO ORDERED.32
Respondents presented the Chairman21 of the appraisal committee who
testified that the appraisal committee recommended22 the total valuation
of PhP 49,064,400 based on the assessor's data and the BIR zonal NPC's motion for reconsideration was denied by the RTC in its Order
valuations as indicated on the 1997 tax declarations.23 Also presented was dated May 2, 2011.33 However, the RTC modified the imposition of
the succeeding Chairman24 of the appraisal committee who testified that interest as follows:
the properties suffered consequential damages which the appraisal
committee recommended to be computed at 50% of the BIR zonal value Wherefore, judgment is hereby rendered:
per square meter or for a total amount of PhP 22,227,800.25 On ocular
inspection, the appraisal committee found that the existence of the 1. Approving and adopting the Commissioner's Report dated August 9,
transmission lines hampered the properties' potential use such that while 2006 and November 24, 2008;
the areas before and after the transmission lines could still be used, the
areas in between could no longer be utilized. The appraisal committee
also noted that the transmission lines produced considerable noise 2. The payment of the provisional value (on May 19, 2006 when plaintiff
making the area unsuitable for residential purposes.26 made the deposit) of P47,064,400.00 as just compensation for the 49,173
square meters area directly affected by the transmission lines is the
payment for the just compensation with interest at 6% per annum from
NPC, on the other hand, presented its right-of-way officers whose
testimonies sought to establish that the lots being claimed by
ProvRem Rule 67 Fulltext Page 116 of 119
the date of filing of the case until full payment less the interest collected The Issues
by the defendants from the bank deposit;
Reiterating its arguments before the lower courts, NPC interposes the
3. Condemning plaintiff to pay defendants the amount of P22,227,800.00 following issues for resolution: (1.) should the value of the property be
as consequential damages with interest at 6% per annum from January reckoned at the time of the taking in the 1970s; (2.) should the amount of
23, 2006 and at 12% per annum from the date of finality of this decision just compensation be based on the properties' BIR zonal valuation
until fully paid; corresponding to its classification as agricultural in the tax declarations;
and (3.) is the award of consequential damages for the "dangling" area
5. To pay P20,000.00 attorney's fees. proper.41
SO ORDERED.34 Essentially, NPC contests the amount of just compensation and the award
of consequential damages.
On September 1, 2015, the CA rendered its Decision denying NPC's Second, the entrance into private property must be for more than a
appeal. Contrary to NPC's claim, the CA held that the just compensation momentary period. x x x
to be paid for an easement of a right-of-way over lands that would be
traversed by high-powered transmission lines should be the full value of xxxx
the subject property.37
Fourth, the property must be devoted to a public use or otherwise
The CA likewise found no merit in NPC's argument that the fair market informally appropriated or injuriously affected. x x x
value of the properties should have been based on the BIR zonal
valuation at the time of its supposed taking of the property in the 1970s Fifth, the utilization of the property for public use must be in such a way
and on the basis of its classification as agricultural land as stated in the as to oust the owner and deprive him of all beneficial enjoyment of the
tax declarations. The CA reasoned that NPC failed to allege the issue of property. x x x43
taking. in its complaint nor was such raised during pre-trial or proven
during trial. The CA also held that to base the fair market value of the
That there was taking of the subject properties for purposes of
property during the alleged actual taking in the 1970s is to compound the
expropriation is beyond contest. What plagues the court and the parties is
injustice caused to respondents as the expropriation complaint was filed
the date when such taking is to be reckoned because this will, in turn, be
more than 30 years after NPC allegedly took respondents' properties.38As
determinative of the value of the subject properties from which the
regards to the proper classification of the properties, the CA noted that
amount of just compensation will be based.
these were already reclassified as residential, commercial and industrial by
the municipality of Pili, Camarines Sur even prior to the filing of the
expropriation complaint.39 Sec. 4,44 Rule 67 lays down the basic rule that the value of the just
compensation is to be determined as of the date of the taking of the
property or the filing of the complaint, whichever came first.
Finally, the CA found no reason to disturb the RTC's award of
consequential damages as testimony to that effect was presented by
respondents while NPC, on the other hand, failed to prove the alleged The case of National Transmission Corporation v. Oroville Development
consequential benefits. Corporation,45 settles that just compensation should be reckoned from the
date of actual taking when such preceded the filing of the complaint for
expropriation. In Oroville, the Court explains that the State is. only obliged
The CA thus disposed:
to make good the loss sustained by the landowner and considering the
circumstances availing at the time the property was taken. Deviation from
WHEREFORE, the foregoing considered, the appeal is this general rule was permitted in the cases of National Power Corporation
hereby DENIED and the decision of the trial court [dated] December v. Heirs of Macabangkit Sangkay46 and National Power Corporation v.
20,2010, as modified by its Order dated May 2, 2011, is AFFIRMED in Spouses Saludares47 due to special circumstances48 therein obtaining
toto. which necessitated a valuation of just compensation at the time the
landowners initiated inverse condemnation proceedings notwithstanding
SO ORDERED.40 that taking of the properties occurred first.
Upon denial of its motion for reconsideration, NPC filed the present The peculiarity of the instant case is that NPC insists that it took the
petition. subject properties in the 1970s despite having initiated the expropriation
complaint only on January 23, 2006. Following the general rule, NPC thus
The various provisions of the Constitution56 uniformly treat the payment Consequential damages is specifically enunciated under Section 6 of Rule
of just compensation as a limitation to the State's exercise of eminent 67 as follows:
domain. Just compensation likewise bears the consistent and settled
meaning as the full and fair equivalent of the property taken from its Section 6. Proceedings by Commissioners. - Before entering upon the
owner by the expropriator, the measure is not the taker's gain, but the performance of their duties, the commissioners shall take and subscribe
owner's loss. The word "just" is used to qualify the meaning of the word an oath that they will faithfully perform their duties as commissioners,
"compensation" and to convey thereby the idea that the amount to be which oath shall be filed in court with the other proceedings in the case.
tendered for the property to be taken shall be real, substantial, full and Evidence may be introduced by either party before the commissioners
ample.57 who are authorized to administer oaths on hearings before them, and the
commissioners shall, unless the parties consent to the contrary, after due
Further, the determination of just compensation in expropriation cases is notice to the parties, to attend, view and examine the property sought to
a function addressed to the discretion of the courts owing to the be expropriated and its surroundings, and may measure the same, after
constitutional mandate that no private property shall be taken for public which either party may, by himself or counsel, argue the case. The
use without payment of just compensation.58 As such, legislative commissioners shall assess the consequential damages to the
enactments, as well as executive issuances, fixing or providing for the property not taken and deduct from such consequential damages the
method of computing just compensation are tantamount to consequential benefits to be derived by the owner from the public
impermissible encroachment on judicial prerogatives. As such, they are use or purpose of the property taken, the operation of its franchise
not binding on courts and are treated as mere guidelines in ascertaining by the corporation or the carrying on of the business of the
the amount of just compensation.59 Even the enumeration of the corporation or person taking the property. But in no case shall the
standards for the assessment of the value of the land for purposes of consequential benefits assessed exceed the consequential damages
expropriation under Section 5 of Republic Act No. 897460 reflects the non- assessed, or the owner be deprived of the actual value of his property
exclusive, permissive and discretionary character thereof.61 so taken. (Emphasis supplied)
Here, NPC assails the valuation assigned to the subject properties for Thus, if as a result of expropriation, the remaining portion of the property
being contrary to its alleged classification as agricultural as appearing on suffers from impairment or decrease in value, the award of consequential
the tax declarations attached to its expropriation complaint. damages is proper.65
Imposition of interest
In this case, NPC deposited the provisional value of the subject properties
in the amount of PhP 47,064,400 on May 19, 2006 which was days before
the issuance of a writ of possession. Considering NPC's prompt payment,
the imposition of interest thereon is unjustified and should therefore be
deleted.