You are on page 1of 27

energies

Review
The Role of Domestic Integrated Battery Energy
Storage Systems for Electricity Network
Performance Enhancement
Corentin Jankowiak 1, * , Aggelos Zacharopoulos 1 , Caterina Brandoni 1 , Patrick Keatley 1 ,
Paul MacArtain 2 and Neil Hewitt 1
1 Centre for Sustainable Technologies (CST), University of Ulster, Shore Rd, Newtownabbey BT37 0ZQ, UK;
a.zacharopoulos@ulster.ac.uk (A.Z.); c.brandoni@ulster.ac.uk (C.B.); p.keatley@ulster.ac.uk (P.K.);
nj.hewitt@ulster.ac.uk (N.H.)
2 School of Engineering, Dundalk Institute of Technology, Dublin Road, A91 KS84 Dundalk, Ireland;
Paul.MacArtain@dkit.ie
* Correspondence: Jankowiak-c@ulster.ac.uk; Tel.: +44-7510-132673

Received: 26 September 2019; Accepted: 15 October 2019; Published: 17 October 2019 

Abstract: Low carbon technologies are necessary to address global warming issues through electricity
decabonisation, but their large-scale integration challenges the stability and security of electricity
supply. Energy storage can support this transition by bringing flexibility to the grid but since it
represents high capital investments, the right choices must be made in terms of the technology and the
location point in the network. Most of the potential for storage is achieved when connected further
from the load, and Battery Energy Storage Systems (BESS) are a strong candidate for behind-the-meter
integration. This work reviews and evaluates the state-of-the-art development of BESS, analysing the
benefits and barriers to a wider range of applications in the domestic sector. Existing modelling tools
that are key for a better assessment of the impacts of BESS to the grid are also reviewed. It is shown
that the technology exists and has potential for including Electric Vehicle battery reuse, however it is
still mostly applied to optimise domestic photovoltaic electricity utilisation. The barriers to a wider
integration are financial, economic, technical, as well as market and regulation. Increased field trials
and robust numerical modelling should be the next step to gain investment confidence and allow
BESS to reach their potential.

Keywords: batteries energy storage systems; integrated; behind-the-meter; grid services;


electricity network

1. Introduction
Three main challenges are emerging and threatening the present structure of the electricity
network. (1) Mitigation measures against climate change including greener electricity production
means, (2) significant changes in the electricity demand enhanced by the need to electrify the heat and
transport sectors, and (3) the ageing of the network, leading to substantial replacement investments.
The production of electricity by renewable energy systems is appealing when addressing climate
change, as they do not emit Greenhouse Gases (GHG) during operation. However, renewable sources
are usually weather-dependent: Wind and solar are intermittent and non-dispatchable (in contrast with
conventional fossil-fuel based systems) therefore an integration large enough to have an impact on GHG
emissions is a real challenge [1]. The capital investment of a renewable plant represents a large part of
the total expenditures as no fuel costs are involved [2], therefore enough electricity must be produced
during its lifetime to create enough revenue and become profitable [1]. Small installed capacities are
likely not to provide enough at the right moment, whereas bigger plant ratings could result in the

Energies 2019, 12, 3954; doi:10.3390/en12203954 www.mdpi.com/journal/energies


Energies 2019, 12, 3954 2 of 27

impossibility to become profitable because of too much curtailment. In addition, renewable sources
are site specific and diffuse. Their contribution to electricity generation tends to be in a larger number
of lower-rating plants, connected to lower voltage layers in the network (i.e., distribution network), as
opposed to the large-scale, centralised generation for which the network was originally developed.
Today’s electricity
Energiesnetworks
2019, 12, x FOR are theREVIEW
PEER result of continuous improvements and 2 of 32developments [3],
originating in the 19th century
capacities are likely not following the discoveries
to provide enough and developments
at the right moment, whereas bigger plant ofratings
electricity
could [4], and in the
resultelectricity
20th century, when in the impossibility
becametoaccessible
become profitableto thebecause
majority of tooofmuch
houses curtailment.
in citiesIninaddition,
developed countries.
renewable sources are site specific and diffuse. Their contribution to electricity generation tends to
The structure
be inof the networks
a larger was shaped
number of lower-rating plants,by the following:
connected When
to lower voltage the
layers number
in the networkof (i.e.aggregated load
distributioncapacity
increases, the required network), asper-customer
opposed to the large-scale,
and thecentralised
variabilitygeneration for which the
of demand network [5], leading to
decrease
was originally developed.
easier predictability. Thiselectricity
Today’s stems from networkssimilarities
are the resultin most people’s
of continuous life habits:
improvements Cooking[3],is more likely to
and developments
happen at certain timesinofthethe
originating 19thday, lights
century are the
following mostly switched
discoveries on at night
and developments times,[4],and
of electricity so on.
and in
the 20th century, when electricity became accessible to the majority of houses in cities in developed
To illustrate this,
countries.
the two extremes are represented on Figure 1. The normalised electricity
consumption of dwelling in Northern Ireland [6] is represented in red,
The structure of the networks was shaped by the following: when the number of aggregatedand that of the entire country [7]
load increases, the required capacity per-customer and the variability
in blue over the same three-day period (24 to 26 October 2018) (The data for the individual house of demand decrease [5], leading
to easier predictability. This stems from similarities in most people’s life habits: cooking is more likely
comes from onetoof the “Test
happen at certainHouses”,
times of thelocated
day, lightsatarethe University
mostly switched onof at Ulster,
night times,representing
and so on. about 28% of the
To illustrate this, the two extremes are represented on Figure
UK’s housing stock, introduced by Shah et al. [6]. The national demand data was downloaded from 1. The normalised electricity
consumption of dwelling in Northern Ireland [6] is represented in red, and that of the entire country
the Eirgrid group[7] inwebsite
blue over [7]. Forthree-day
the same each case, periodthe 15-min
(24 to 26 Octoberresolution
2018) (The data data was divided by the average
for the individual house
over the 3-day comes
period, and
from one plotted
of the Figure
“Test Houses”, 1.).at the
located The normalised
University consumption
of Ulster, representing about 28%wasof the chosen
UK’s in order to
housing stock, introduced by Shah et al. [6]. The national demand data was downloaded from the Eirgrid group
illustrate in both cases how the consumption varies, compared to its average over the considered
website [7]. For each case, the 15-min resolution data was divided by the average over the 3-day period, and
period (a valueplotted
of 1 on Figurethe vertical
1.). The axis).
normalised The national
consumption was chosendemand
in order toremains
illustrate inbetween
both cases how50% theand 150% of its
consumption varies, compared to its average over the considered period (a value of 1 on the vertical
average value, axis).
when for a single dwelling, the variation goes from 0% to nearly 800%. Additionally,
The national demand remains between 50% and 150% of its average value, when for a single
the three days of national
dwelling, demand
the variation goespresent
from 0% toanearly
repeating pattern over
800%. Additionally, the threeeach
days24-hour
of national period,
demand whereas such
present ato
a trend is impossible repeating
identify pattern
forover
theeach 24-hour
single period, whereas such a trend is impossible to identify
house.
for the single house.

Figure 1. Normalised electricity consumption of an individual house (red) in Northern Ireland [6],
Figure 1. Normalised electricity
and the entire consumption
country (dashed of anperiod
blue) for a three-day individual house
(24–26 October 2018)(red)
[7]. in Northern Ireland [6],
and the entire country (dashed blue) for a three-day period (24–26 October 2018) [7].
For this reason and due to economies of scale, the structure of the network was designed to have
large centralised generators on one end of the network, enough aggregated loads on the other end,
For this reason and due to economies of scale, the structure of the network was designed to
and a system of transmission and distribution of electricity in between, with higher voltages for long
have large centralised generators
distances, and on one
lower voltages closer end
to theof thefor
loads network, enough
shorter sections of theaggregated
grid. Therefore,loads
the on the other
electricity generation fleet could be designed optimally and perform efficiently, as short term
end, and a system of transmission and distribution of electricity in between, with higher voltages
variations are small and predictable, relative to the overall production [8].
for long distances, and lower voltages closer to the loads for shorter sections of the grid. Therefore,
the electricity generation fleet could be designed optimally and perform efficiently, as short term
variations are small and predictable, relative to the overall production [8].
In case of non-optimised and unsupervised penetration of renewable sources, problems such as
mismatch between production and demand, voltage rise, or reverse power flows at transformers [8]
are more likely to arise. Installing electricity storage—particularly on the low-voltage layers of
the network [9]—could help reduce this problem by bridging the mismatch between demand
and production.
Storage may also play a role in addressing the evolution of the demand on the electricity network.
The electrification of heat and transport sectors at different scales presents a potential for reducing
Energies 2019, 12, x FOR PEER REVIEW
Energies 2019, 12, 3954 3 of 32 3 of 27
In case of non-optimised and unsupervised penetration of renewable sources, problems such as
mismatch between production and demand, voltage rise, or reverse power flows at transformers [8]
GHG emissions
are more aslikely
theytoare currently
arise. Installingresponsible for a substantial
electricity storage—particularly onamount of pollutant
the low-voltage layers ofemission
the [10],
and draw network
the vast[9]—could
majorityhelp reduce
of their this problem
energy from the by bridging
combustion the mismatch
of gas, oilbetween demand
and other and fuels [11].
fossil
production.
However, shifting a significant part of the heat and transport demand to the electricity network is
Storage may also play a role in addressing the evolution of the demand on the electricity
extremelynetwork.
challenging. The amount
The electrification ofand
of heat energy it represents
transport would
sectors at different generate
scales presentsaasubstantial
potential for stress on
a network,reducing
whichGHG was emissions
not originally
as they designed
are currentlyfor it. Figure
responsible for 2 gives an order
a substantial amountof of magnitude
pollutant of the
emission [10], and draw the vast majority of their energy from the combustion
consumption of heat energy compared to electrical energy (in Great Britain, for the year 2016) illustrates of gas, oil and other
fossil fuels [11]. However, shifting a significant part of the heat and transport demand to the
the fact that the electricity consumption patterns would be significantly affected by a total transition
electricity network is extremely challenging. The amount of energy it represents would generate a
of heat generation
substantial from
stress onfossil fuels which
a network, to electricity [12,13]. designed
was not originally As for renewable
for it. Figure 2sources, the distribution
gives an order of
network ismagnitude
the moreoflikelythe consumption of heat energy
to be affected, compared
as systems suchto electrical
as electric energy (in Great
heaters, Britain,
heat for theor Electric
pumps,
year 2016) illustrates the fact that the electricity consumption patterns would be significantly affected
Vehicles (EVs) should connect to such layers. Once again, having storage assets on these parts of the
by a total transition of heat generation from fossil fuels to electricity [12,13]. As for renewable sources,
network would significantly
the distribution networkhelpis thethe
more electricity
likely to benetwork
affected, asby shaving
systems suchthe peaksheaters,
as electric coming heatfrom these
systems [14]. Theorlast
pumps, challenge
Electric Vehiclesconcerns
(EVs) shouldtheconnect
ageingtoofsuch infrastructures and having
layers. Once again, components. In the present
storage assets
on these parts
design strategies, of the network
components would significantly
are upgraded help the
when their electricity network
performance by shaving
decreases due to theageing
peaks or to the
coming from these systems [14]. The last challenge concerns the ageing of infrastructures and
increase of demand. Additionally, they are sized to be able to carry at least the peak demand, which
components. In the present design strategies, components are upgraded when their performance
occurs onlydecreases
a few minutes per or
due to ageing year. This
to the kindofofdemand.
increase approach represents
Additionally, theyaare
huge
sizedinvestment
to be able to [15].
carry Installing
and operating storage
at least the peakinstead
demand,could ensure
which occurs lower
only a few variations between
minutes per year. peaks
This kind and average
of approach representsvalues, thus
leading to ainfrastructures
huge investmentwith [15]. lower
Installing and operating storage
ratings—hence, cheaperinstead could ensure lower
to upgrade—and morevariations
optimally used,
between peaks and average values, thus leading to infrastructures with lower ratings—hence,
therefore ageing more slowly [16,17].
cheaper to upgrade—and more optimally used, therefore ageing more slowly [16,17].

Figure 2.Figure 2. Seasonal variation of the heat demand compared to the electrical demand [13].
Seasonal variation of the heat demand compared to the electrical demand [13].
The different types of energy storage technology have been extensively reviewed and compared
The different types [18].
in the literature of energy storage
The focus technology
usually varies from have been extensively
one publication to another:reviewed and compared in
electricity network
the literature [18]. applications
oriented The focus usually varies
[19,20], smart from
power one publication
systems [21] flexibilityto another:
[22], Electricity
the integration network oriented
of renewables
applications[23,24]. In addition,
[19,20], smart under
power their economics
systems [21]aspect [25,26], [22],
flexibility or based
theonintegration
sizing [27], placement and
of renewables [23,24].
operation strategies [28,29].
In addition, under their economics aspect [25,26], or based on sizing [27], placement and operation
Although the literature does not give a definitive answer to where exactly is the best location to
strategies [28,29].
connect energy storage, the trend seems to be that the further downstream the better for connecting
Although the
storage literature
devices doesEnergy
[9]. Battery not give a definitive
Storage System (BESS) answer
is the to where exactly
technology that best is thethis
suits best
partlocation to
of the storage,
connect energy network thanks to its seems
the trend scalability [24,30].
to be thatHowever,
the further this downstream
solution is still the
not better
developedfororconnecting
thoroughly reviewed in particular regarding the benefits that it could provide. Moreover, the
storage devices [9]. Battery Energy Storage System (BESS) is the technology that best suits this part of
the network thanks to its scalability [24,30]. However, this solution is still not developed or thoroughly
reviewed in particular regarding the benefits that it could provide. Moreover, the literature regarding
domestic integrated BESS mostly focuses on making photovoltaic (PV) self-consumption viable for the
battery owner [31,32].
The present paper focuses on integrating Battery Energy Storage System (BESS) in the domestic
sector, offering a review on the specific solution of integrating BESS straight at the loads—behind
the meter of customers—as a way to provide the flexibility necessary to respond to the challenges
faced by the electricity network presented above. The technology considered is electro-chemical
Energy Storage (ES)—more commonly referred to as batteries—and more specifically secondary (i.e.,
rechargeable) batteries.
Energies 2019, 12, 3954 4 of 27

The paper is organised as follows: First the technology is introduced in detail, then its potential
for improving grid performance is assessed, and finally the obstacles faced are reviewed. The state-
of-the-art of domestic batteries are reviewed in Section 2, including basic principles, available products
and numerical modelling, and field trials done so far. Based on that, the potential role domestic
integrated batteries can play to help enhance the electricity network’s performance through service
provision and compared with other energy storage technologies is presented in Section 3. To finish,
Section 4 reviews the barriers to domestic battery development, explaining why this solution is still
not quite present despite its potential.

2. State-of-The-Art Development of Domestic Integrated Batteries

2.1. Generalities about Batteries

2.1.1. Main Components and Working Principles


A battery is a device capable of converting electrical energy to chemical energy and vice-versa via
oxidation-reduction (redox) reactions. The base element of a battery is the cell, which is composed
of two electrodes (one positive, one negative), the electrolyte, and a separator. During the charging
process, a voltage difference is applied between the two electrodes, imposing the current to flow in a
certain direction. The consequent excess or deficit of electrons at the electrodes generates reactions
between the molecules at their surface, in the electrolyte. The latter consists in the liquid or solid
substance in which the electrodes are immerged. Its role is also to enable and facilitate the circulation
of charge carriers between electrodes. During the discharge phase, the reverse chemical reactions take
place when the circuit is connected to a load, leading to a flow of electron on the other direction until
the chemical components are all consumed [33].
The performance of a battery cell depends on the chemistry of its components, and the reactions
created: Typically, the elements enabling the highest voltage difference between the electrodes, at the
lowest weight are sought for [33]. The maximum amount of current and voltage a cell can deliver is
limited so in order to reach higher values, a number of cells may be connected together in series or
parallel. The term “Battery” or Battery Energy Storage System (BESS) are often used to refer to the
complete system composed of this group of cells, some control electronics, and the protecting packaging
around them. The electronic part is often called Battery Management System (BMS). In simpler systems,
its role may only consist in ensuring that the cells’ voltage, current and other physical quantities remain
in the range of acceptable values and shutting down the system if not. In more complex systems,
individual cell management based on State-of-Charge (SoC) calculation, voltage, temperature, and
other parameter measurements may be provided by more sophisticated BMS [34].

2.1.2. Chemistries
There are a wide variety of chemistry compounds out of which a battery cell can be made.
However, the different chemistries bring about different properties, such as the energy density (total
energy that can be stored by mass or volume unit) or the cycle-life (number of charge-discharge cycle
executed before the overall performance drops significantly). Table 1 introduces the properties of the
main cell types with a potential role in the domestic sector. The numbers provided are to be taken as
guide values considering that each chemistry type is composed of a spectrum of variations [35], since
the performance vary depending on the precise chemical composition [36].
Lead-Acid (PbA) batteries are the oldest type of rechargeable batteries and have evolved in two
main categories: Flooded and sealed batteries. They are now a very mature and established chemistry,
widely used regarding many possible applications thanks to low costs, low maintenance requirements,
and low self-discharge [37]. Despite this, other chemistries are overtaking PbA batteries, as their
applications are limited because of potential toxicity, weight, and low energy density [38], in particular
Lithium-based chemistries since the early 2000s.
Energies 2019, 12, 3954 5 of 27

Table 1. Features of the main battery chemistries.

Chemistry Voltage Power Density Energy Density Cycle life Performance Self-Discharge Cost Safety Issues
High output current can be Limited, especially if
Lead-Acid (PbA) 2V 10 s of Wh/kg low Inexpensive Toxicity of lead
achieved for their size deep-cycled
Long, if properly
High output achievable and Robust, resistant to abuse.
Nickel-Cadmium 1.2 V 10 s of Wh/kg maintained, but memory High Inexpensive
not too harmful Toxicity of Cadmium
effect
Medium, but does not
Nickel Metal Limited, especially if Relatively
1.2 V absorb high discharge rates 120 Wh/kg High Average
Hydride deep-cycled. Memory effect environmental-friendly
well.
Overcharging and
Limited, especially if Around 4 times as full-charge idling causes
Nickel Iron 1.2 V Medium 10 s of Wh/kg High
deep-cycled expensive as PbA increased temperature, gas
builds up and dry-out
No toxic component, good
Limited, due to high
Nickel Zinc 1.65 V Relatively high 100 Wh/kg High Low temperature operating
dendrite growth
range
Long, thanks to low Need for high pressure
Nickel Hydrogen 1.25 V Medium 10 s of Wh/kg minimal Expensive
corrosion hydrogen vessels
Medium to low. Higher
Li-ion NMC 3.7 V 220 Wh/kg Around 1000–2000 cycles Low Expensive
rates reduce battery life
Relatively high
Medium. High output
Lithium-Iron LFP 3.3 V 120 Wh/kg Around 1000–2000 cycles for a Li-based Expensive Very safe chemistry
pulse can be achieved
cell
More expensive than
Lithium Cobalt Medium. Higher rates
3.6 V 240 kW/kg Around 500–1000 cycles Low other Li-batteries Safety issues due to cobalt
Oxide reduce battery life
(because of Cobalt)
Lithium Manganese Medium. High output
3.7 V 150 Wh/kg Around 300–700 cycles Low Expensive Safer than Li-cobalt
Oxide pulse can be achieved
Lithium Nickel More expensive than
Medium. Higher rates
Cobalt Aluminium 3.6 V 260 Wh/kg Around 500 cycles Low other Li-batteries Safety issues due to cobalt
reduce battery life
Oxide (because of Cobalt)
Very safe. Better thermal
More expensive than
Lithium Titanate 2.4 V High rates achievable 80 Wh/kg Up to 7000 cycles Low stability than other Li-based
other Li-batteries
batteries
Energies 2019, 12, 3954 6 of 27

The five most present Nickel-based (Ni-Based) batteries, are Nickel-Cadmium (NiCd), Nickel
Metal Hydride (NiMH), Nickel Iron (Ni-Fe), Nickel Zinc (Ni-Zn), and Nickel Hydrogen (NiH2 ). NiCd
batteries rapidly developed in the 1980s as the first competitor to PbA batteries which it remained for
a few decades thanks to their robustness and long cycle-lives and good load performance for costs
comparable to those of PbA cells NiMH cells appeared in the 1990s as an alternative to the cadmium
(toxic element) present in NiCd batteries, with less memory effect, and higher capacities, at similar
costs and durability. However their self-discharge rates turned out to be even higher than the already
high ones of NiCd, and their operation more delicate [37]. The other Ni-based cells present variations
in performance—which never enable them to overtake neither PbA nor Lithium-based batteries—but
still can claim a fair share of the overall battery market, at least for some specific applications [39].
Most of the domestic batteries available and developed nowadays are equipped with
Lithium-Based (Li-based) batteries. This chemistry emerged in the late 1990s, first as expensive
products, but with rapidly decreasing costs promoted by the need for light and portable Energy Storage
(ES) solutions. The two main types of li-based cells are Lithium Nickel Manganese Cobalt Oxide
(LiNiMnCoO2 or more commonly NMC), and Lithium Iron Phosphate (LiFePO4 , referred to as LFP).
NMC batteries have higher energy and power densities but their stability is compromised by the
presence of Nickel at the cathode. LFP batteries’ market share increased in recent years, led by an
interest in their much higher stability at high currents or temperatures, with a similar cycle life, its
main disadvantage being lower energy density [40]. LFP cells are more and more used for domestic
batteries, where a moderate increase in mass or volume is acceptable if it brings about enough extra
safety. Lithium Titanate (Li4 Ti5 O12 ) is another type of Li-based cell, which provides more safety and
increased cycle-life, coming at the cost of lower energy density, and a doubled price compared to
NMC cells. Other chemistries should be mentioned: Lithium Cobalt Oxide cells present a high specific
energy (therefore very present in portable electronics) but low stability and load capabilities, as well as
a short life span. Lithium Manganese Oxide cells trade off a higher stability for lower capacity and
a still limited life time, and Nickel Cobalt Aluminium Oxide cells present a great potential in many
aspects, but remain a very expensive chemistry [40].
Flow batteries have a slightly different functioning principle to the other batteries—which makes
them difficult to be compared with the criteria used in Table 1. They present the technical advantage of
independence between energy capacity and power output and can achieve very long cycle life at full
Depth of Discharge (DoD). Still, they struggle to move away from laboratories for a few reasons, mainly
because the energy density is limited by the ion concentration in the electrolyte. Additionally, the need
for extra components such as tanks, pumps and pipes increases the costs and reduces the overall
performance [41]. Therefore, they are not likely to be part of the early models to be implemented as
domestic batteries in the short term.
For a more detailed review of the history of the chemistries, the readers are referred to Scrosati [42],
and to Linden and Reddy [33] for thoroughly detailed nuances of chemistries and operating principles
of batteries.

2.1.3. Battery Ageing and Degradation


One determining parameter when deciding the chemistry and the operation strategy of a battery
is ageing, described as the decrease of its performance over its calendar life (in years) or cycle life (in
number of cycles). Aging corresponds to the total amount of energy that a battery can store, and the
power output decreases with time and utilisation [43]. The State of Health (SOH) defines the decrease
in the maximum amount of energy that a cell can store, compared to its original capacity, and the End
of Life (EOL) defined as the time, or number of cycles after which the SOH reaches a certain value
(typically 80%, but it can vary depending on the constructor) [37].
There exist many different ageing processes depending on the chemistry considered. They stem
from either side-reactions occurring in parallel to the normal energy storage process, or from side
effects of normal operation reactions. The rate and impact of these reactions can be alleviated or worsen
Energies 2019, 12, 3954 7 of 27

depending on the voltage, current, temperature and SOC operating values. High temperatures tend to
increase the kinetics of chemical phenomenon, thus increased side-reactions, for instance the Solid
Electrolyte Interphase (SEI) in Li-based cells [43] or grid corrosion in PbA cells [44]. Low temperatures
on the other hand reduce these kinetics according to Arrhenius law, increasing the internal impedance
which limits the performance, but also favouring lithium plating for instance [45]. High and low SOC
usually correspond to less stable states. At high SOC, Ni-based cell experience crystalline formation,
reducing the performance, which can be reversed if handled early enough. Low SOCs favour the
sulphating of the negative electrode of PbA cells [44]. High rates of charge or discharge lead to higher
reaction rates in general that can enhance SEI formation in Li-based cells [43] or more generally elevate
the temperature, with risk of bringing about issues mentioned above.
For these reasons, the state of each cells in a battery pack is managed—in higher-quality models
at least—to keep voltage, current, temperature and SOC values in ranges that are as unfavourable
as possible to these unwanted phenomena. Numerical thermal models are developed by Rao and
Wang [46] and temperature-management technologies are reviewed by Al-Zareer, Dincer and Rosen
in [47]. The degradation of cells was shown to have a considerable impact on achievable revenues by
Al-Zareer, Dincer and Rosen [48], and a significant increase in potential profitability can be achievable
by optimising cell operations to decrease ageing [49].

2.2. Products Available


The present section provides an overview of different commercialised BESS suitable to be integrated
in the domestic sector.

2.2.1. Solar PV Batteries


As will be seen and developed in Section 4 of this paper, there are still barriers to a large integration
of ES—which does not only regards the domestic level. The main one to date being probably the
economic viability. The latter is highly dependent on individual context elements, but according to
Rappaport and Miles [50], and Staffell and Rustomji [51], the cost of domestic batteries is still too
high to enable the breakeven point to happen before the end of life of the systems. Still, a higher
remuneration of service provision would lead to earlier breakeven points [9,52]. Under five years is
achievable, especially if the technology costs were to decrease as stated by Neubauer and Simpson [53],
and Muenzel et al. [54] states that systems could become economically attractive “in the near future”.
Two specific cases studied and reported by Günter and Marinopoulos [55] even conclude that storage
can already be profitable, under particular conditions.
From this literature, it seems that profitability for a full system—rooftop PV panels, Electric
Vehicles (EVs), Heat Pumps (HPs), or a combination of them—associated with a battery can be
reached in the more or less near future depending on the context. A few companies started the
commercialisation of domestic batteries mostly as “Solar Batteries”: Either as retrofitting or for a
new PV installation. Elon Musk’s Tesla Powerwall and Powerwall II played a significant role in the
acknowledgement of domestic BESS as a potential future mainstream product. Tesla’s batteries are
equipped with lithium-based chemistry which also composes the majority of the other battery cells:
The German Sonnen, the South Korean LG Chem RESU, the Chinese PylonTech US200B, and the
American Simpliphi PHI. LFP and NMC are the most present chemistries in such batteries, as they
present an advantageous trade-off between cost, cyclability, safety, and energy density, as developed
previously in Section 2.1).
Still, a few others among the main models are not lithium-based, for instance the Chinese Nerada,
the German BAE which are Lead-Carbon and Gel Lead-Acid respectively [56]. This difference in
technology illustrates a preference for lithium ion batteries as previously mentioned, due to the
performance and lower volumes achievable by this technology. Table 2 summarises the characteristics
of the different products.
Energies 2019, 12, 3954 8 of 27

Table 2. Existing products and their characteristics.

Power Round-Trip
Name Chemistry Energy (Usable) Inverter Cycle Life EoL Warranty Price US$/kWh Source
(Continuous/Peak) Efficiency
DC-AC
Tesla Powerwall 2 Lithium NMC 13.2 kWh 5.8/7.2 kW 3200 70% 10 years 89% 440 [57,58]
inverter-charger
LG Chem RESU Lithium NMC 12.4 kWh 5/7 kW none - 60% 10 years 92% 510 [56,59]
PylonTech Lithium LFP 19.2 kWh 2.4/4.8 kW none 6000 80% 5 years 94% 475 [60]
Simpliphi PHI Lithium LFP 3.5 kWh 1.6/3 kW - 10,000 80% 10 years 98% 480 [60,61]
Narada Lead-Carbon 4 kWh 5/10 kW - 3000 80% 10 years 83% 440 [60]
BAE Gel Lead-Acid 14.6 kWh 5/9 kW - 3000 80% 5 years 82% 430 [60]
SonnenBatterie ECO Lithium LFP 13.5 kWh 3.3 kW DC-AC included 10,000 80% 10 years 94% 400 [62,63]
(EOL: End of Life).
Energies 2019, 12, 3954 9 of 27

2.2.2. Electric Vehicles’ Batteries Reuse


With the increased acknowledgement of the potential of domestic batteries, the reuse of batteries
from EVs or Hybrid EVs (HEVs) starts to be considered. EV and HEV manufacturers such as Nissan
and BMW [64] or independent companies such as Relectrify [65], claim they found a way to reuse
vehicle batteries that reached their End of Life (EoL), and could thus buy them from the vehicles’
owners, refurbish them, and sell them back to the domestic battery market. Reuse of such batteries has
potential, as the performance of EV or HEV batteries are usually higher than that required for domestic
applications. Thus, once a battery reaches its EoL, due to degradation processes, the performance
achievable may still be good enough for domestic applications [66].
Still, as explained by Robinson [67], EV or hybrid EV battery requires physical removal of the
battery pack from the car, followed by an electric testing of the individual cell, and finally, reconditioning
into a “new” battery pack ready for a second life. This whole process would take time, energy and
cost money so it is not guaranteed yet that car companies would not just prefer to send batteries for
recycling [67].

2.2.3. Performance and Characteristics of Available Systems


Different products available are presented by Muoio [64] and Svarc [56]. A range of performances
are available using different chemistries and technologies as already mentioned, and the selection is
made depending on the size of the habitation, energy and power requirements, available resource
(usually PV) and the budget of the owner.
Energy capacity ranges between a couple of kWh or more (usually corresponding to a single
storage unit), and up to slightly lower than 20 kWh (a stack of a number of units in some cases). Higher
capacities are expected with reused EV batteries but are not available yet. The power ratings usually
depend on the invertor, and range between slightly higher than 1 kW to up to 10 kW. The tolerance of
a power output also varies depending in how long this output is maintained. Some systems such as
the Tesla Powerwall or the Sonnen ECO are equipped with an integrated inverter/charger, and some
other models require the purchase and installation of a compatible inverter. Table 2 gives examples of
available models and their characteristics.

2.3. Numerical Modelling of BESS


Numerical models used to describe batteries as well as electricity network models have existed
for a long time but are mostly separate from one another. The present section offers to critically analyse
these models and introduces existing simulations and results of integrated BESS.

2.3.1. Main Battery Models


Batteries are complex systems, storing electricity through chemical reactions and exchanging
heat as losses with the environment. This complexity makes it a real challenge to create a numerical
model accounting for all the different phenomena and compute results in a reasonable time. Therefore,
depending on the application, simplified models can be chosen, as well as models that depict more
accurately certain types of phenomena leaving some others aside [68].
The general aim of the different models is to predict the behaviour of a battery of given
characteristics (capacity, chemistry, etc.) operating in a given environment. Depending on the very
model, the computed parameters are: The ageing of the cell, its dynamic response, the State of Charge
(SOC), the thermal behaviour, and so on. The most popular model used in the literature are presented
in the following. Figure 3 gives a schematic representation of the three types of models introduced in
the following: The Bucket model, the equivalent electrical circuit model, and a Single Particle Model
(SPM) which is a certain type of electrochemical model.
The Bucket model is presented by Reniers et al. [49] and used by Simpkins and Donnell [69].
It considers the storage unit as a “tank” (or “bucket”), in which energy is accumulated and be pumped
Energies 2019, 12, 3954 10 of 27

in and out by virtual “pipes”. The total volume of this bucket is the Energy Capacity, the size of the
pipes is the power ratings, and one could imagine self-discharge and charging/discharging efficiencies
as energy “leaking” out of the bucket or the pipes.
This model only accounts for exchanges in bulk energy and takes the system: [Cells + Inverter +
BMS] as a “black box” that can just receive energy, accumulate it to a certain extent, and discharge it.
This model itself does not provide information concerning transient response at the chemical level,
the ageing of the cells, or any thermal aspect. Such characteristics can be added to the model, for instance
a decrease in available capacity over time to simulate the ageing mechanisms, by estimation, thanks to
empirical results, or results from other models.
The main advantage of such a model is its computational efficiency thanks to basic mathematical
foundations, enabling very short calculation times. Nevertheless, some complexity must be added in
order to account for particular aspects that cannot be neglected in some contexts.
An illustration of a possible equivalent circuit model is found Figure 3B. They are broadly used
when integration to some larger electrical systems in simulation software is required. Different circuit
layout exists with different combinations of fundamental electronics components. All these components
model one or part of an electrochemical phenomenon taking place in the real battery. The Thevenin
models for instance detailed by Gao, Liu and Dougal [70] are used for their capability to provide cell
transient response, taking account of effects such as charge depletion and recovery [68]. They are
composed of:

• A voltage source (Or Equilibrium Potential) which value is a function of the SOC of the battery,
the discharge rate (current) and the temperature.
• Resistors, used to model the “potential losses”: The conductivity of the electrodes and the separator
is not infinite, in addition to the effect of concentration gradients of ions near the electrodes and
the limits in the kinetics of the chemical reactions. The value of these resistors depends on the
chemistry, the geometry, the temperature and the discharge rate of the cell.
• A capacitor in parallel to one of the abovementioned resistors, to model the capacitive effects due
to the structure of the cell, leading to electrical polarisation, and pseudo-capacitance (diffusion
limited space charges). In other words, this capacitor accounts for transient effects in the cell.
• In some models, other parallel RC circuits maybe added in series, increasing the accuracy of the
modelled transient response, adding at the same time complexity and computation time [68].

The value of all these electrical components and their evolution with other parameters of the circuit
can be determined by comparing the response to pulses of charge and discharge at different temperature
and SOC, and their value adjusted accordingly. The second category of electrical circuit equivalent
models are the Impedance models. They are based on an experimental method, the Electrochemical
Impedance Spectrum (EIS), which consists of analysing the battery response to a spectrum of low
frequency AC excitation. This method provides information on the SOC and the State of Health (SOH)
of the battery. In such models, half cells are represented as Randles circuits composed of a resistor, an
inductor, a capacitor and a non-linear impedance. Once again, the adjusting of the different parameters
is done with comparison to empirical results [68].
Electrochemical models are based on a more explicit description of the chemical processes
taking place inside of the cell, which makes them much more accurate than the previous types, and
therefore requiring substantially more computational resources or time. The lump parameter model
described by Seaman, Dao and McPhee [68] has been used since the early development of numerical
models. It assumes a uniform spatial distribution and solves differential equations that represent
time-dependent electrochemical phenomena between the electrodes. If well optimised, it can provide
accurate results in short simulation times, but only for NiMH or PbA batteries: The model is not valid
anymore to represent modern chemistries such as Lithium Ion, which is a major drawback regarding
their broad and fast expansion.
Energies 2019, 12, 3954 11 of 27

Lithium Ion models and other modern chemistries can be described by Porous Electrode Theory.
This model is developed by Newman and Tiedemann [71], and is based on solving partial differential
Energies
equations, 2019,
which 12,be
can x FOR
donePEERusingREVIEW
finite element methods. Hence, very accurate results14can of 32
be
obtained but at the cost of very high computation times. A number of simplification
obtained but at the cost of very high computation times. A number of simplification methods were methods
were developed,
developed, reviewed
reviewed by by Seaman,
Seaman, Dao
Dao andand McPhee
McPhee [68]based
[68] basedon
on mathematical
mathematical or orconceptual
conceptual
simplification,
simplification,either
eitherdecreasing
decreasingthetheaccuracy,
accuracy,ororthe
thefield
fieldofofapplication
applicationofofthe
themodel.
model.Modifications
Modifications
increasing
increasingthethe
complexity
complexity areare
alsoalso
reported, which
reported, aim toaim
which increase even more
to increase eventhe accuracy
more and quality
the accuracy and
ofquality
predictions [49]. The[49].
of predictions illustration in Figurein3C
The illustration represents
Figure a SPM, which
3C represents a SPM,iswhich
a certain
is atype of model
certain type of
developped based onbased
model developped the Porous
on theElectrode Theory. Theory.
Porous Electrode

Figure 3. Representation of the numerical models. (A) Bucket Model, (B) Equivalent Circuit Model
Figure 3. Representation of the numerical models. (A) Bucket Model, (B) Equivalent Circuit Model
and (C) Electrochemical Model [49].
and (C) Electrochemical Model [49].

2.3.2.Electricity
2.3.2. ElectricityNetwork
NetworkModelling
Modelling
Electricitynetworks
Electricity networksare areextremely
extremelycomplex
complexsystems,
systems,composed
composedofofa anumber
numberofofalready
alreadycomplex
complex
components. Additionally, considering how developed countries are dependent
components. Additionally, considering how developed countries are dependent on electricity, real-scale on electricity, real-
scale experiments that could potentially compromise the infrastructures
experiments that could potentially compromise the infrastructures and the users’ loads are not and the users’ loads are not
conceivable.Therefore,
conceivable. Therefore,robust
robustnumerical
numericalmodelsmodelsmust mustbe bedeveloped
developedand andvalidated
validatedtotopredict
predictthethe
impact of any modification on the grid prior to any large-scale implementation
impact of any modification on the grid prior to any large-scale implementation [72]. This complexity [72]. This complexity
inevitablyforces
inevitably forcesnumerical
numericalmodels
modelstotobe beeither
eithercomputationally
computationallyheavy, heavy,ororinaccurate
inaccuratetotosome someextent,
extent,
anda atrade-off
and trade-offmust
mustbebefound
foundbetween
betweenconfidence
confidenceinin results,
results, and
and a sensible
a sensible time
time ofof computation.
computation.
Powerflow
Power flowmodels
modelsconsist
consistofofa asteady-state
steady-staterepresentation
representationofofthe theelectricity
electricitynetwork,
network,solving
solving
non-linearand
non-linear and time-independent
time-independent equations
equations (usually
(usually solved solved
using using
iterativeiterative
methods).methods).
DynamicDynamic
effects
are therefore neglected, but this approximation is enough to represent a large proportion of grids’of
effects are therefore neglected, but this approximation is enough to represent a large proportion
grids’ operation
operation time.
time. Still, Still,
some somesuch
events events such as
as faults orfaults
other or other transient
transient events may events may
have have a significant
a significant impact
onimpact on theand
the network network
threatenand the threaten the safety
stability and stability and safetyThus,
of equipment. of equipment.
dynamic and Thus, dynamic
transient modelsand
are also developed, which describe such conditions, and enable the design of protection techniques andof
transient models are also developed, which describe such conditions, and enable the design
protection techniques
technologies. They mostlyandconsist
technologies. They
of solving mostly consist
differential of solving
equations, differential
leading to even equations,
more complexityleading
to even
than moreflow
the load complexity
analysisthan the load
models. Onceflow analysis
again, models.must
a decision Oncebeagain,
takena between
decision computation
must be taken
between computation time and accuracy. More details on these models,
time and accuracy. More details on these models, and solving methods can be found by referring and solving methods cantobe
found by referring
Andersson [73]. to Andersson [73].
Such analyses
Such analyses are arenow
nowbroadly
broadlycomputer
computerbased,
based,asasititwould
wouldnot notmake
makesense
sensetototry
trytotoanalytically
analytically
solve this type of problems. Software packages such as MATLAB/Simulink,
solve this type of problems. Software packages such as MATLAB/Simulink, NEPLAN, DIgSILENT NEPLAN, DIgSILENT
PowerWorld,
Power World,DYMOLA,
DYMOLA,Plexos, Plexos,andandmany
manyothers
othersoffer
offertotoimplement
implementand andrunrunsimulated
simulatednetworks
networks
with various performance in various contexts. A number of packages
with various performance in various contexts. A number of packages used by network companies, used by network companies,
researchersand
researchers and others,
others, andand their
their capabilities
capabilities for afor a wide
wide numbernumber of applications
of applications were were
reviewed reviewed
by Hay by
Hay
and and Ferguson
Ferguson [74]. [74].

2.3.3.Results
2.3.3. Resultsfrom
fromNumerical
NumericalSimulations
Simulations
Theliterature
The literature involving
involving some
some sortsort of modelling
of modelling and and simulation
simulation of BESS
of BESS used
used to to operate
operate one or one
moreor
ofmore of the applications
the applications previouslypreviously
described indescribed
this paperin this paper However,
is substantial. is substantial. However, many
many publications are
publications
still are still regarding
regarding different contexts ofdifferent contexts
utilisation, such asof utilisation, to
a connection such as a connection
renewable generationtoassets
renewable
[75],
generation assets [75], or for LV applications but not necessarily Behind the Meter (BtM) [76,77]. Even
for papers regarding BtM applications, the focus is rather on sizing and scheduling systems: The
economically optimal battery size regarding PV generation was assessed in [54,78–82]; a degradation
aspect considered by Angenendt [83], and Yoon and Kim [84] also deals with integration in
Energies 2019, 12, 3954 12 of 27

or for LV applications but not necessarily Behind the Meter (BtM) [76,77]. Even for papers regarding
BtM applications, the focus is rather on sizing and scheduling systems: The economically optimal
battery size regarding PV generation was assessed in [54,78–82]; a degradation aspect considered by
Angenendt [83], and Yoon and Kim [84] also deals with integration in households without PV resource.
Finally, Babacan et al. [85] presents a similar approach, but grid relief objectives start to appear, through
a reverse power flow diminution objective.
Most of the publications reviewed here, which address some sort of grid relief objective deal with
voltage regulation, for instance Yang et al. [86] and Aichhorn et al. [27]. With similar objectives, it is
reported by Zillmann, Yan and Saha [87] that in the context of their simulation, installing coupled
PV panels with batteries proved to be cheaper than grid reinforcement. The impact of location of
the BESS system on the voltage profiles is studied by Nazaripouya et al. [88] and by Lindstens [89]
which suggests that better results are achieved further from generation assets and closer to bigger
loads. Additionally, Marra et al. [90] and Zeh and Witzmann [91] propose a more sensible way to
operate batteries by charging when the net PV export to the grid becomes higher than a threshold
value (and study the impact of this very value on other parameters) rather than just charging as soon
as energy is available—which could potentially resulting in an peak exports in the early/middle of the
afternoon when the sun shines but the battery is already full. Finally, the compatibility of grid release
and PV self-consumption is addressed by Moshövel et al. [92], concluding forecast is a key parameter
in reaching satisfying compromise.
These publications mostly focus on one single domestic system and how to economically optimise
it for the benefit of the owner. The grid-relief aspect is introduced as a solution to the stress induced by
PV systems exporting to the grid when the energy is not needed, which reduces the exploitation of
the real domestic BESS potential developed earlier. Only a few authors look in this direction, such as
Müller et al. [30], concluding that low voltage storage is potentially beneficial for both high voltage and
medium voltage layers of the network, and that a number of smaller spread units may operate better
than a single centralised storage asset. Furthermore, “Cloud Energy Storage” [93] regard the operation
of storage assets by an aggregator, generating revenue by providing services to the electricity network.
This promising strategy is however not backed up by simulation results, and the technical benefits
provided by storage is stated as an assumption, and not a conclusion of the work.
Eventually, although these papers provide consistent conclusions, their results remain true for
the very context of modelling and simulation. Any grid section presents very specific characteristics
which cannot be easily generalised, and a strategy of sizing, locating and operating a fleet in one of
them may or may not be efficient in another.

2.4. Trials and Real-Scale Implementation


The paragraph shows an overview of trials and reals-scale implementation where BESSs have
been implemented at domestic level.
Sonnen Community—Probably the most advanced real scale demonstration of the benefits and
profitability of deployment of domestic ES is the company Sonnen and its growing community of
battery owners. Sonnen was founded as a start-up in the late 2000s in Bavaria, and now consists
of over 10,000 battery owners claimed in Germany, and 180,000 in the world [94]. Its particularity
is that it does not only sell batteries, but also acts as an aggregator and manages all its storage unit
fleet. The business started in 2015 when its status of nationwide cloud-base Virtual Power Plant was
established, enabling the members to exchange electricity with one another at different (and supposedly
cheaper) tariffs than the average German ones. In mid-2017, tariffs changed and decreased even more
as Sonnen’s Batteries started to take part in the frequency regulation market in Germany, by allowing
TenneT—the network operator—to use a small fraction of the capacity of each battery to regulate
the frequency fluctuations on the network, in exchange of revenues. If similar activities are started
in Austria, Italy and Australia [95], the American market has been harder to reach for the German
company so far.
Energies 2019, 12, 3954 13 of 27

An interesting project to follow is the Jasper project, in Arizona, in which Sonnen is partnering
the efficient builder Mandalay Hones in a 2900-house microgrid connected to a Virtual Power Plant
(VPP) of 23 MWh storage and 11.6 MW of power. The business model is based on differential tariffs
this time, and the aim is to demonstrate the integration of much renewables, as well as the decreased
dependence on fossil fuels. The first residents are residents expected during the year 2018 [94].
Network Operator Projects—A few Network Operator-lead projects took place and are currently
taking place in the UK and other countries, but due to the newness of the systems and concepts,
the necessity to record enough data from a sensibly long period of time, and consequently the time it
takes to properly analyse them, there is only so much information and conclusions available to date.
A few examples are introduced in the following:
The Sola Bristol project took place between 2011 and 2016 and was undertaken by the British
Distribution Network Operator (DNO) Western Power Distribution, in partnership with Siemens,
the University of Bath, and Knowle West Media Centre. It consisted of installing coupled PV and
battery systems in a total of 26 homes, 5 schools and an office, and implement a “smart tariff” for the
participants. The project concludes that such a set up provided benefits mostly to the suppliers and the
communities. Despite the small number of systems installed, a good argument—but not strong enough
to base economic decisions on it—was made in favour of the potential to achieve grid deferral. Services
such as self-consumption, peak shaving and voltage regulation were successfully achieved thanks to
an efficient self-managing network, although according to the final report [96], the cost-effectiveness of
the solution is questionable.
The Distributed Storage and Solar Study started in 2016 and should finish by 2019, led by another
UK DNO, Northern Powergrid, partnering Moixa and Energise Barnsley. Similarly, 40 batteries are
installed behind the meter and controlled by an aggregator to provide peak shaving and voltage
regulation, and thus investigate how they—associated with PV here as well—could avoid upgrade,
and reduce winter peak demand [97].
To finish, a few more projects should be mentioned, such as the “Econamic Grid” by SENEC in
Germany, which uses batteries for providing “negative balancing”. In other words, absorbing extra
energy from the network during over-production times as a means of balancing, and leaving the
energy in the batteries to be used by the customers. Another UK trial by North Star Solar, consisting of
22,000 social houses equipped with solar batteries, once again to study their possible economical and
technical impact for the different stakeholders [98].

3. Potential Roles of Domestic Integrated Batteries


The section focuses on the role of integrated BESS in the electricity network and compares it to
other possible ES solutions.

3.1. Behind-the-Meter Storage


First of all, a clarification on why BtM is of particular interest. Remembering that in electricity
networks, physical quantities have different span definition: The frequency of the network is, in theory,
the same everywhere, therefore any variation is measured as equal throughout the network. However,
the voltage is a local quantity, meaning that an event modifying the voltage locally may have little
impact far away on another section of the network. A consequence of this is that some services can be
achieved regardless of where the storage unit is connected to the network, but some others cannot.
Table 3 lists all the services that the grid would require in order to perform efficiently (described in
more detail in the following paragraph) and indicates how easily they could be achieved depending
on the location considered. As shown in Table 3, the large majority of the electricity network services
can be provided or contributed to by BtM units. The exceptions are services for which the storage unit
must be closer to the generation sites. Therefore, units located behind the meter would be of particular
interest for the distribution networks, by helping address the challenges of increasing the share of
Energies 2019, 12, 3954 14 of 27

Energies 2019, 12, Energies


x FOR PEER
2019,REVIEW
12, x FOR PEER REVIEW 17 of 34 17 of 34
renewable sources and implementing electrification of heat and transport. Table 3 summarises results
Energies 2019,
Energies 2019, 12,
12, xx FOR
FOR2019,
Energies PEER
PEER REVIEW
Energies
12,
REVIEW
x FOR
2019,
PEER12, REVIEW
Energies
x FOR PEER
2019,REVIEW 17 of
12, x FOR PEER REVIEW 17 of 34
34 17 of 34 17 of 34 17 of 34
that can be found for each service in journals or report cited in the “source” column.
Energies 2019, 12,
Energies
x FOR2019,
PEEREnergies
12,
REVIEW
x FOR
2019,
PEER12, REVIEW
Energies
x FOR PEER
2019,REVIEW
12, x FOR PEER
Table REVIEW 17 of
3. Likelihood of34
Table
connection17atof
the34
3. Likelihood of 17electricity
different of at
connection 34the different
network17levels.
of 34 netwo
electricity
Table
Energies Likelihood
3. 2019, Table
Table 3.of
12, Services
Energies
x FOR
3. connection
Likelihood
PEER
2019,REVIEW
Likelihood 12,
Table
of xatFOR
3. the PEER
of connection
connectiondifferent
at the
Likelihood
Table
at the electricity
different
ofREVIEW
3.connection
different
Likelihood network
electricity
electricity
at
Table
ofthe
connection levels.
network
different
3.Transmission
Likelihood
networkat levels.
electricity
the
levels.
of 17electricity
different of
connection
network 34
at
levels.network17levels.
the different of 34Behind
electricity netwo
Services Generation Generation Transmission
Distribution Distributio
Energies 2019, 12,
Energies
x FOR2019,
Energies 2019,
PEER
Services 12,
REVIEW
Services xx FOR
Energies
12, FOR PEER
2019,
PEER
T&D 12, REVIEW
REVIEW
Energies
xGeneration
TableFOR PEER
2019,REVIEW
3. Likelihood
congestion T&D
Generation 12,
Table x FOR
ofcongestion
relief connection
3. PEER
Likelihood
Table
Transmission REVIEW
Transmission
atrelief
the
of  17electricity
3.connection
different
Likelihood
Distribution of
at 34
Distribution
Table
ofthe 
connection 17
the17
different
3. Likelihood
Behindnetworkat of
~of 34
34
electricity
the
levels.
Meter of 17
Behind
different ofthe
connection
network 34 
Meter
electricity
Sourceat
levels.
~ the different of 34 
network17levels. Sourc
electricity netwo
Services Services Services
Generation Generation
Services
Transmission
Generation
Transmission
Distribution
Generation
Transmission
Distribution
Behind
Transmission
Distribution
the Meter
Behind the
Distributio
Meter
Behind
Sourc
T&D12,
Energies 2019, congestion
x FOR
T&D PEERrelief
REVIEW
congestion
T&D
Services Voltage
reliefT&D
congestion
Services relief 
support
congestion
Services T&DVoltage
relief
Generation 
congestion
Generation
Services ~relief
~support
Table
Transmission 

Generation 17 of
3. Likelihood ~ 34
Table
of
Transmission 
Distribution
at
connection
3. Likelihood
Generation theof 
different
connection
~Distribution
Transmission Behind 
[9,55] 
electricity
at
~ the
Transmission different 
network levels.
Distribution
the Meter
Behind 
electricity
the [9,55]
netwo
Distributio
Meter
Behind
Sourc
T&DVoltage support
Voltage
congestion T&D Voltage
support
relief Table
Power
support
congestion
T&D 
Energies

Energies
Voltage
relief
congestion 2019,
3. quality
Likelihood
2019,
support
T&D 12,
Table
12,
Voltage
Table
relief 3. 
xx FOR
FOR
of connection
Power3.
congestion 
PEER
Likelihood
quality
 at
PEER
support
Likelihood
Table REVIEW
the
of
REVIEW
of 
connection
different
3.connection
~reliefLikelihood 
 electricity
at
at the
Table
of
~ the  
different
network
at
connection
different
3. 
electricity
Likelihoodlevels.
electricity
~ the of network
different
connection
network 

~ the
levels.
electricity
at
levels.
[9,30,55] network17
different 
17levels.
of 34
of 
34 [9,30,5
electricity netwo
[9,55]
Services Services Generation Generation
Transmission Transmission
Distribution Distributio
Behind
Energies 2019,
Energies 2019,Voltage
12,
Energies
12, xx FOR
Power FOR
Energies 2019,
PEER
quality
2019,
ServicesPEER
support
Power Energies
12,
REVIEW
Power
12,
REVIEW
Voltage
quality Demand-Peak
xx FOR
FOR
2019,
PEER12,
quality
PEER
T&D REVIEW
Power
support
Table 
Limiting
Demand-Peak
xGeneration
FOR PEER
3. quality
REVIEW
Voltage support REVIEW
Likelihood
congestion T&D Power
Voltage 
quality
support
Limiting

Transmission
ofcongestion
relief connection at 


the different
relief 17 
of 34 
17electricity
of 34 
Distribution

 17
network
17
~of 34 
oflevels.
34 Behind 
17 of 

34
the 

~ Meter
[30,55,99]  

[30,55,9
[9,30,5
Sourc
Services Services Generation
Services Generation
Transmission Generation
Transmission
Distribution Transmission
Distribution
Behind the Distributio
Meter
Behind
Demand-Peak
T&DPower Demand-Peak
Limiting
quality Power Arbitrage
Demand-Peak
Limiting
quality Power & load
Energies 
Arbitrage
 levelling
Limiting
Demand-Peak
2019,
quality 12,
Power xx&FOR
load
 
levelling

Limiting
PEER
quality REVIEW
~
 

Table 

3. 
~ 
 

Likelihood 
of connection
connection 



at 

the different  
[9,30,5
17electricity
of 34
electricity
34 [30,55,9
netw
congestion T&D
Demand-Peak
Services relief
congestion
Limiting T&D relief
Energies
Voltage
congestion
Generation 2019,
support
T&D 12,
Voltage
relief FOR
congestion PEER
support
Transmission~relief
REVIEW ~
Table 3.
Distribution 
Likelihood
~ of 
Behind at
[9,30,55]~ the
the 17
different
Meter 
of [9,55]
netwo
Sourc
Arbitrage
Energies Demand-Peak
2019, 12, &
Energiesload
FOR
xx FOR
Voltage levelling
Arbitrage
2019,
PEER
support RE
Demand-Peak
Limiting xx&
Energies
12,
REVIEW
Voltage Capacity
Arbitrage
load
FOR2019,
PEER
support 12,firming
levelling
Demand-Peak
Limitingxx&
REVIEW
Table
Power RE
load
FOR
3. ~
Capacity

 &
PEER smoothing
Arbitrage
Likelihood
quality of firming
levelling
Limiting
Demand-Peak
REVIEW
Table
Power x& 
load

connection
3. Likelihood&
~quality 


Table
at smoothing
levelling
Limitingthe
of 

~ 17

3.connection
connection
different
Likelihood 


17electricity
of 34
electricity
atofthe
the 

connection 

~ 17

different
network
~of


17at of 

34different
electricity
the
levels. 

of~ 


17electricity
network 34
levels.~ network17levels.
 
 [9,30,5
~

34 [9,30,5

Energies 2019,
T&D 12,
Energies
Arbitrage
congestion 2019,
PEER
& Energies
load12,
REVIEWFOR2019,
levelling
relief PEER12, REVIEW
Energies
Voltage
Table FOR
3. 
PEER
2019,
support
Likelihood
~ REVIEW
12,
Voltage
Tableof FOR
connection
3. PEER
support
Likelihood
Services at
~ the
ofREVIEW
different of
at 34 
different
network
Generation 34
electricity
levels. 17
network of 
34
levels.
[9,30,55]
Transmission of
Distributio[9,55]
RE Capacity firming
RE &
Capacity smoothing
REfirming PV
Capacity &Self-consumption
smoothing
firming RE 
 &PV
Capacity 
Self-consumption
smoothing
firming & ~ smoothing

 
~ ~
 

 

~
 
~ 


~
 

~ 
 
[55,99,1

~
EnergiesArbitrage
2019,
REPower
12, &
Energies
x
Voltage load
FOR
Capacity Arbitrage
Services levelling
quality
2019,
PEER
firming Power
Energies
12, &
REVIEW
& x
support Services Arbitrage
load
FOR2019, levelling
Demand-Peak
quality
PEER
smoothing Power
12, &
REVIEW
Energies
x load
FOR
Services
Generation~Arbitrage
 levelling
Limiting
Demand-Peak
qualityT&D
PEER
2019, Power
REVIEW
12, x & load
congestion
FOR~

Generation~ levelling
Limiting
quality
PEER
Transmission relief
REVIEW~

Generation~ 17 of
Table
Table
Transmission 34 
3.
3.
Distribution ~
 17
Likelihood
Transmission
Likelihood of of
 Distribution
34
of 
connection
17 of 
Meter
at
~
34
BehindDistribution
connection at
[55,99,100]
the 
the
the different
17
different 
of 34
Behind the Meter [9,30,5
electricity
[30,55,9
 netw
[9,30,5
Behind
electricity netwo
Sourc
PV
RE Capacity Self-consumption
firming
RE PV
Capacity Black-Start
Self-consumption
& Energies
smoothing
REfirming PV
Capacity &Self-consumption
smoothing
firming RE 

capability
Black-Start
PV
Capacity
& 

Self-consumption
smoothing
of firming & 
capability
~~smoothing 
 
~of 
 
 


~ Likelihood~~of 
~ network 


 
~
~ the
~ different 
 
~[9,30]
Demand-Peak
T&DPower
R REVIEW Energies 2019, 12,
Energies
xPVFOR Limiting
Demand-Peak
quality
congestion T&D
2019,
PEER relief Arbitrage
Demand-Peak
congestion
12,
REVIEW
Self-consumptionx FOR T&D
2019,Limiting
PEERTablex&
relief
congestion
12, REVIEW
Energies
Table load
3.
FOR
3. Arbitrage

 levelling
Limiting
Demand-Peak
Likelihood
PEER Voltage
Table
relief
2019,
Likelihood
17 REVIEW
12,
Table
of of
34 x& FOR
load
connection
3. Likelihood

connection
3. levelling
PEER
Likelihood
Services 
Limiting
support
Table
at
Table
at the
ofREVIEW
the
of3. 
3.connection
connection
different
Likelihood
different
Likelihood of
at
~ 17electricity
electricity
at the
~the
Table
of 34 
connection
connection 

~ 17at
different
 network
different
3. network
Generation 
at
electricity
the
levels.
34
electricity
the
levels.
of 
different
 network
different 17
connection of 

electricity
levels.

34
electricity
[9,30]at
levels.
Transmission
network
network  34[55,99,1
levels.

17levels.
of
electricity~[9,55]

[9,30,5

[30,55,9
Distributio netwo
Black-Start
Arbitrage
PVVoltage capability
& load Black-Start
Self-consumption
PVlevelling
ArbitrageSelf-consumption Backup
capability
Black-Start
PVVoltage
RE&Capacity
Arbitrage
load Self-consumption
firming
levelling
&3. RE
load 
provision
 Backup
capability
Black-Start
~Arbitrage

 &PV
Capacity 
provision

Self-consumption
smoothing
levelling firming  & 

capability

 smoothing


 

 

~
 

 



~ the 

~
 




 

~
~ the
~ different 

 

[9,30,5
~

~[9,30]
Demand-Peak Limiting
supportVoltage support support 3.&Likelihood
load
~qualitylevelling ~~Transmission
  ~ at

 
 
[9,30,5
Black-Start
Services capability
Services Table
Energies Services Likelihood
Generation
2019, T&D
12, xPower
Tableofcongestion
connection
Generation
Services
FOR Table
at
Transmission
PEER the
of3.connection
relief different
Likelihood
Generation
REVIEW electricity
at
Table
ofthe
connection
different
3.
Distribution Likelihood
network
Generation electricity
Transmission levels.
of
different
connection
network
Distribution
Behind electricity
at
levels.
[9,30,55]~ Meter
Transmission
Distribution
the network levels.
Behind electricity
the 
[9,30,5
Distributio
Meter
Behind
17 netwo
Sourc
of 3
RE CapacityBackup provision
firming
RE
Black-Start Backup
Capacity
& smoothing
capability
Black-Start provision
firming Backup
& Reserves
smoothing
capability
Black-Start 

provision Backup
capability Reserves
Black-Start 

provision 
~
capability 


 

~ 
~
~ 


at 


 
~
~ 



 


~ 
 

[9,30,5

[55,99,1
[9,30,5
~
Arbitrage
Power & load
Backup
T&D congestion T&Dlevelling
quality Power
provision
relief
congestion
PV Self-consumption
RE Capacity
quality firming
Power
Table
T&D relief
RE
3.
congestion ~

quality
 PV
Capacity
&
Likelihood
T&D
Self-consumption
smoothing
Demand-Peak
Voltage
Table
reliefof firming 

connection
3. Likelihood
congestion 
&at
Table smoothing
Limiting
support the
of3.
~relief 

connection
different
Likelihood 
electricity
at
Table
of the 


connection 

different
3.
~ Generation 
~ the
 ~Distribution
Likelihood
network electricity
levels.
of 

different
connection
network 


electricity
at 
~ the


levels.
[9,30,55] ~ different
~ Meter network 

levels.
electricity~ netwo

[9,30,5
[30,55,9
[9,55]
Services Services Services
Generation Generation
Services
Transmission
 Generation Transmission
Distribution
Transmission Behind
Transmission
Distribution
the
 Behind the Distributio
Meter
Behind
Sourc
Table PV3.BackupReserves
Likelihood of connection
provision
Self-consumption
PVBackup Reserves atBackup
theReserves
Frequency
provision
Self-consumption
Black-Startdifferent
provision

electricity
regulation
 Frequency
Backup
capability Reserves
Black-Start 
network
regulation
provision
 
capability levels.


 

  
 


 


 

 


 


~
 
 
[9,30,5

[9,30,5

~[9,30]
RE Capacity firming
Demand-Peak
Voltage
T&D congestion
& smoothing
Demand-Peak
Limiting
supportVoltage
Reserves
T&D relief
congestion
PV Self-consumption
Demand-Peak
Limiting
supportVoltage
T&D relief
congestion 

support

PV
Limiting
Arbitrage
T&D
Self-consumption
Power
Voltage
relief &
congestion

load
quality
support ~


levelling
~relief 
 
 ~

~ Generation 
~
 
 ~Distribution 
 



[9,30,55] 

~ Meter 
 
[55,99,1

[9,30,5

[9,30,5
[9,55]
FrequencyServices
regulation Services Load Services
Generation
Following Load Generation
Services
Transmission
Following  Generation
Transmission
Distribution
Transmission
  Behind
Transmission
Distribution
the

  Behind the Distributio
Meter
Behind
Sourc

[9,30,5
Reserves
Black-Start Frequency
capability
Black-Start regulation
ReservesFrequency
Backup
capabilityReserves
Black-Start &RE 
regulation
provision
 Frequency
Backup
Capacity
capability Reserves
Black-Startfirming
 &
regulation
provision 
capabilitysmoothing

 
Table
 ~ 

3.  
 
Likelihood
 of connection
~ 

~ 

 

~ 
 [9,30,5
at the different 
electr
~[9,30]
~
PV
T&D
Self-consumption
Generation
Arbitrage
Power
Voltage & load
Arbitrage
levelling
quality
support
Frequency
congestion T&D Power
Voltage &Arbitrage
Transmission
regulation
relief load
quality
support
congestionT&D levelling
Power
Voltage
relief
congestion
load


levelling
support
T&DDistribution
~ Demand-Peak
quality Power
Voltage
relief congestion
~quality

 
Limiting
support
~relief
~Behind


 
~ ~:the
 

 Meter

 

achievable 


~ the optimal 
Source



[9,30,55]~   
 
[9,30,5
 [30,55,9

[9,30,5
[9,55]
Load Following Load Following Load : Best 
location

Following for
Load :
that 
Best
service;
Following 
location
 ~: 
Service
for that 
achievable
service;  
although
Service
 
not  although 

location;
not  :
the optimal
Service 
location;
cannot 
be :perf
[55,100Se
Frequency
RE CapacityBackupfirming
RELoad
Black-Start regulation
Frequency
provision
Backup
Capacity
& smoothing
capability RE regulation
Frequency
provision
firming Backup
Capacity Reserves
& smoothing
firming regulation

provision&Frequency
PVBackup Reserves
smoothing 
regulation
provision
Self-consumption ~ (T&D: 

 
~  ~and
~ 
 

~ 
~RE: 

 
~ Energy).  
[9,30,5


 [55,99,1

[9,30,5
elief 
Demand-Peak
Power
Voltage Demand-Peak
Limiting
quality
support Power
Voltage
Following ~
Demand-Peak
Limiting
quality
support Power
Voltage 
Arbitrage

quality
support Services
Limiting
Demand-Peak
Power
Voltage 
& 
load

quality
support 
levelling
Limiting
 
 

Transmission 

(T&D: 
 
~Distribution;
Generation 
Transmission 
 and 



Renewable 
Transmission
[9,55]
Distribution;
[55,100] RE: 

Renewable 
 Dis
[9,30,5
[30,55,9
[9,30,5
Ener
: Best location
:Following for that service;
:Following : ~: Service achievable
~: : although not the optimal location; : Service
: cannot be performed
:beService from
: there. be:perf
Load
Backup
Best location
Reserves
provisionLoad for that
BestFrequency
Reserves service;
location
Load ~:for 
Service
Best
thatlocation
Following
Reserves service;
achievable
regulation

for
Load
Frequency 
Service
that
although
Best
service;
Following
Reserves
 
location
achievable
not
regulation
 
~: Service
the
foralthough
optimal

 
 
thatachievable
service;
location;
not ~:
 thealthough
Service

optimal

 Energy).
 
 
Service
achievable
not
 location;
cannot
the optimal


although 

~ 
performed
location;
not



cannot


the
from
optimal
Service 
be there.
performed
location;
cannot[9,30,5
 from
[55,100

[9,30,5
Se
th
PV Self-consumption
PV Self-consumption
PV Self-consumption
RE 
Capacity
 Black-Startfirming & 
capability

 smoothing 
 
  
 
 

 
  [30,55,9
 ~[9,30]
~
[9,30,5

rt Arbitrage
Demand-Peak
Power
::& load
BestArbitrage
levelling
Demand-Peak
Limiting
quality
location Power
for &that
: that 
Arbitrage
load levelling
Demand-Peak
Limiting
quality Power
service; :
&(T&D:
~: load
(T&D: ~Arbitrage

Service

levelling
Limiting
Demand-Peak
Transmission
quality
T&D Power
congestion
Transmission
achievable 
&
(T&D:
~: :
load
~quality

and
and levelling

Limiting
Distribution;
relief
Transmission
Distribution;
although
 
(T&D:
not ~and

the 
RE:Distribution;
Renewable
Transmission
RE: Renewable
optimal

(T&D:
and
location;

 
~Distribution;

Energy).
RE:
:
Transmission
Renewable
: Service

RE:
Energy).
and
cannot 
[9,30,55]
Renewable
Distribution;
:beServicebe

~
Energy).
:
RE: Renewable

[9,30,5
Ener
be:perf
Frequency Best location
regulation
Reserves
Black-Start Frequency
capability for
Black-Start Best service;
location
regulation
Load
Frequency
capability
Black-Start ~:forService
Best
thatlocation
Following
 service;
achievable
regulation

for
Load
Frequency
capability Service
that
although
Best
service;
location
achievable
Following

not

regulation
 
~: Service
the
foralthough
optimal
thatachievable

service;
location;
not ~:

thealthough
Service
 optimal
 
Service
achievable
not
 location;
cannot
the optimal
although 
performed
location;


not
 
cannot
the
from
optimal
Service
be there.
performed
location;
cannot[9,30,5
from


[9,30,5
 [55,99,1
Se
th
RE Capacity performed
Arbitrage firming
Demand-PeakRE& load from
Capacity
&
Arbitrage there.
smoothing
RE
levelling
Demand-Peak
Limiting (T&D:
firming
&Capacity
Arbitrage
load &Transmission
smoothing
firming
levelling
Demand-Peak
Limiting RE
&(T&D:
load  PV
andBackup
Capacity
& smoothing
~Arbitrage
levelling
Limiting
Demand-Peak firmingprovision
Self-consumption
Distribution;
& and
load RE:
&  Renewable
~smoothing

~ Transmission
levelling
Limiting 
~and Energy).

~ (T&D:
 ~~
 

 
~

~Distribution; ~~
 

~ 
 ~~  [9,30,5
~ Ener

[9,30,5
Following
Load Load Following  :Following
Best
Transmission
Voltage
location for : 
(T&D:
support
that 
Best
Distribution;
service; 
location
(T&D:
for 
~: Service ~:
Transmission
RE: Distribution;
Renewable
thatachievable
service;
and
 
Energy).
RE: Transmission
Renewable
achievable
although
Service  
RE:
Energy).
not the optimal
andRenewable
although
Distribution;
[30,55,99]


not 
location; the
Energy).
RE: Renewable
Service
:optimal location;be:perf

[55,100
cannot[9,30,5 Se
Frequency regulation Load
Backup 
provision Load Following
Reserves 
 
  

 
 
 

 
  
PV
RE CapacityBackup
Arbitrage RE& provision
Self-consumption
firming PVBackup
Capacity
load &
Arbitrage smoothing
RE provision
Self-consumption
firming
levelling PV
&Capacity
Arbitrage
load &Self-consumption
smoothing
firming
&RE
levelling load 
 Black-Start
PV
Capacity
& smoothing
~Arbitrage
levelling firming 

Self-consumption
~ &
& load
capability


~smoothing
levelling
(T&D:  

~ (T&D:
~ Transmission ~and
  
~
~Distribution;
Transmission 
~RE: and




~ 
Renewable ~ Energy).
Distribution; RE: Renewable ~~
[9,30,5

 [55,99,1
 [9,30]
[9,30,5
Ener
iting 
In
Load : Best location for
addition,
Following : Best
: that
theReserves
benefits 
Best service;
location
location: ~:for
for
provided Service
Best 
that
 Power
thatlocation
service;
achievable
service; ~: :
for
~:
Frequency
to 
quality
Service
although
Service
thatBest achievable
service;not
oflocation
achievable
regulation
a Self-consumption
section  the the although
optimal

~:distribution
Service
foralthough
thatachievable
service;
not 
location;
not ~:
the
the  :
although
Service
network 
optimal
Service
optimal  location;
cannot
achievable
not
by location; :beService
:
the optimal
locally although [9,30,55]
Service
performed
cannot
location;
improvingnot 
cannot
the
from
: be performed
there.
performed
optimal
Service
be from
location;
cannot[55,100
from th
be:perf
 Se
th
&     
Reserves
Black-Start capability
Black-Start capabilityReserves
Black-Start      
  
[9,30,5
PV
RE Capacity Self-consumption
firming PV
RE Capacity & Self-consumption
smoothing
REfirming PV
Capacity & smoothing
firming REcapability
Self-consumption
(T&D: 
 Backup
Black-Start
PV
Capacity
& smoothing
Transmissionfirming
(T&D:
(T&D:
provision


and 
capability
~smoothing
Transmission
Distribution;
Transmission(T&D: 
and
and 
~ (T&D:
RE:Distribution;
Distribution;
Renewable
Transmission ~~
 

Energy).
and RE:
RE: 
~
Renewable
Distribution;
Transmission
Renewable ~~
 Energy).
RE:
Energy).
and 

~ 
Renewable ~~
Distribution; Energy). 

RE: Renewable 
[9,30,5
~[9,30]
[55,99,1
~ Ener
velling power ~ quality,
Frequency : Best increasing
location
regulation
Frequency for that 
self-consumption
service;
Frequency
regulation 
Demand-Peak
~: Service
regulation

or
Load
achievable 
peak-shaving,

 
Limiting
Following
although not the

are likelylocation;
optimal
 
 
to decrease
 : 
Service
 thecannot
need
 befor 
services

[9,30,55]
performed
 there.
from  

[9,30,5
Backup
Black-Start
PV provision
Backup
capability
Black-Start
Self-consumption
PV provision
Backup
capability
Black-Start
Self-consumption
PV Self-consumption
(T&D:

provision
 Backup
capability Reserves
Black-Start
PV 
provision

Self-consumption
Transmission and

 
capability
Distribution;  RE:  

Renewable 
~ 


Energy).

  
~ 



 
~ 
 [9,30,5
 

~[9,30]
at higher voltage layers of the network.  This is: consistent
: Best
Best 
location with
for  the results

that service;
service; of
~: Service
Servicesimulations

achievable  reported
although not  by optimal
the optimal location; : Se
: Se
smoothing 
Load
Backup
Following
Reserves
Black-Start[89]provision
Load
Backup
capability
Black-Start
Following
Reserves ~ Load
provision
Backup
capability
Following
Arbitrage
Reserves
Black-Start 

provision &
Frequency
Black-Start
Backup
capability load
~
Reserves

location
levelling

regulation
provision 
 
capability
for that

 
 
~:
 (T&D: 

~



 ~achievable

 

although
 ~and Distribution; 


not
[55,99,100]

 the
 
~ RE: Renewable 
location;

 ~ 
[55,100

[9,30,5

[9,30,5
Lindstens which conclude that the further away from the generation Transmission
plants,
(T&D: the
Transmission better,
and and the
Distribution; RE: Renewable Ener
Ener
: Best
: Best location
location for: that
for
: that location:
Best service;
service; ~:for
forService
Best
thatlocation
 service;
achievable
for
Load~: Service
Service
that
although
service;
 achievable
not
 ~: Service
the although
although
optimal
 achievable
location;
not the
 the :
although
 optimal
: Service
not
location;
cannot :
the optimal
 beService
: Service 
performed
location;
cannot
 :
from
Service
be there.
there.
performed 
cannot[9,30,5
from
be perf
th
tion 
Frequency
Backup regulation
Reserves Frequency
provision
Backup
Best location

regulation
ReservesFrequency
provision
Backup
studies from Müller et al. [30] stating
~:
REReserves Service
that
Capacity  service;
achievable
regulation
Frequency
provision
(T&D:that Backup
~:
firming Following
although
Reserves
a number
Transmission(T&D:


achievable
& not

 
regulation
provision
and of spread
the
smoothing optimal

(T&D:distributed
Transmission
Distribution; and
Transmission
location;
not


RE:Distribution;
Distribution;
Renewableandstorage
Energy).
RE:
optimal

Service
 
assetsRE:
Distribution;
Renewable
location;
 
cannot

hasRenewable
be performed
a higherEnergy).
Energy).



cannot

[9,30] ~
from
be performed

from
 [9,30,5

th
(T&D: Transmission(T&D:and
: Best Transmission
Distribution; and
RE: Renewable Energy).
RE: Renewable Energy). : Se
Load Following Load FollowingLoad Frequency
Following
 Load : 
Best for
location
location
Following
 
for 
that
that
 ~:
service;
service;
 
~: Service
Service
   
achievable
 
achievable although
although 

not 

not
 the

optimal
the optimal location;
 : Se
[55,100
location;

ility  than a few centralised
Frequency regulation
Reserves
potential Frequency  and
regulation
Frequency
Reserves Reserves regulation
PV larger Reserves
scale. regulation
~Finally, units connected
Self-consumption  BtM
(T&D:
(T&D:
 have theand
Transmission
Transmission
advantage
and
[9,30,55] 
Distribution;
Distribution; RE: Renewable
RE:
[9,30,5
Renewable Ener
Ener
: Best : that
of Load: Best location
location for
Following Load
distribution-connected
Frequency
for
: that
Best Load:
Best service;
service;
location:
location
Following
systems ~:for
for
~: Service
Best
thatlocation
location
Service
Best
that

Following
since service;
achievable
for
service; ~: :
achievable
for
~:
Load
services Service
that
although
service;
Service
that achievable
although
Best
service;

not
~: Service
location
achievable
Following
such not

as~: Service
the
the although
optimal
achievable
foralthough
optimal location;
not ~:
thatachievable

increased service; the
location;
not
 the : Service
although
optimal
: Service
although
Service
optimal

self-consumption not
location;
cannot
achievable
not
location;
 cannot
the :
the optimal
optimal
beService
: Service
performed
location;
ofalthough
 be performed
location;
not

:
cannot
from
:
cannot
small-scale the

Service
be there.
from there.
performed
optimal
Service
be cannotfrom
performed from
be:perf
location;
cannot
 be

perf
th
Se
th
[55,100
on  regulation
Frequency regulation
Frequency
 (T&D: regulation
(T&D:
Frequency
Black-Start
Transmission
Transmission 
(T&D:
(T&D:
regulation
capability
and
andTransmission
Distribution;
(T&D:and
Transmission
Distribution;
(T&D: and
Transmission
Transmission
RE: 
RE:Distribution;
Distribution;
Renewable
Renewable and 
Energy).
(T&D:
andRE:
Distribution;
RenewableRE:
Energy).
RE:
Distribution;
Transmission
Renewable RE: [9,30,55]
Energy).
Renewable
Energy).
andRenewable 
Energy).
Distribution;
Energy).
[9,30,5
RE: Renewable Ener
Load:Following
renewables,Bestand
location
Load :Following
back-up
for that Load:
Bestpower
service;
location are
~:
for easier

Service
Best
that
location
Following to
service; ~: :
implement,
achievable
for
Load 
Service
that
although
Best 
service; while
location
achievable
Following not
~: 
Service
the still
foralthough
optimal
that enabling

achievable
service;
location;
not ~:
the  :
services
although
Service
optimal 
Service
achievable
not 
location;
cannot :beService
theachievable
optimal
although 
from
performed 
location;
not :
cannot
the
from
optimal
Service
be there.
performed be:perf

location;
cannot[55,100
from Se
th

distribution  (T&D: Backup
Transmission 
provision
(T&D:andTransmission
Distribution;
(T&D: and
Transmission
RE: 
Distribution;
Renewable (T&D:
and 
Energy).
RE:
Distribution;
Transmission
Renewable RE:
Energy).
and [9,30,55]
Renewable 
Distribution;
Energy).
RE: Renewable Ener
: Bestpoints. : that
location for location:
Best service; ~:for
Service
Best
thatlocation
service; ~: :
achievable
for Service
that
although
Best
service;
location
achievable
not
~: Service
the
foralthough
optimal
thatachievable
service;
location;
not ~:
the : Service
although
Service
optimal
achievable
not
location;
cannot :beService
the optimal
although
performed
location;
not :
cannot
the
from
optimal
Service
be there.
performed be:perf
location;
cannotfrom Se
th
tion   
Reserves
(T&D: Transmission
(T&D:
and
Transmission
Distribution;
(T&D:and 
Transmission
RE:Distribution;
Renewable
(T&D:
and 
Energy).
RE:
Distribution;
Transmission
RenewableRE: [9,30,55]
Energy).
and
Renewable 
Distribution;
Energy).
RE: Renewable Ener
3.2. Grid Services and Domestic BESS
g   Frequency 
regulation   
[55,100]
on for that service; ~:3.2.1. Services
Service andalthough
achievable Applications
not the optimal location;
Load : Service cannot be performed 
Following from there. 
(T&D: Transmission and Distribution; RE: Renewable Energy).
Before going further, the terms “Service”: and “Application”
Best location for that should
service; be properly
~: Service defined.
achievable Strictlynot the optimal loca
although
(T&D: Transmission
speaking, any operation undertaken by an ES unit comes down to generating an active or reactive power and Distribution; RE: Renew
flow [55]. Nevertheless, depending on the amount of power it represents and the timing regarding
other events occurring in the electricity network the effect can have drastic different consequences.
In the present paper, the terms application and service are interchangeably used, and defined as “any
electrical operation (local absorption or injection of active or reactive power) which objective is a local
or global improvement in the operating conditions”, derived from the definition of service given by
Günter and Marinopoulos [55].

3.2.2. Integrated Batteries for Grid Services Provision


The definition and description of the services as presented in Table 4 were broadly derived from
descriptions and definitions found in [9,21,22,25,28,69,101–104]. The table contains a brief description
of each service, how exactly domestic batteries could achieve them, and if an aggregator is necessary,
useful or not needed.
Energies 2019, 12, 3954 15 of 27
Energies 2019, 12, x FOR PEER REVIEW 21 of 32

Energies 2019, 12, x FOR PEER REVIEW 21 of 32

Figure 4. Illustration of voltage support on a fictive feeder.


Figure 4. Illustration of voltage support on a fictive feeder.

Services related to energy managementOriginal in the building such as peak limiting, PV self-consumption,
Demand
Power

or back up reserve are straightforward to After Peak-Limiting


provide, through managing the flows of active power and
ensuring a headroom and legroom energy capacity are available when needed. No aggregator is
needed, although one can imagine a more advanced management of all the parameters by making
batteries communicate and respond to each other. Similarly, services such as voltage or frequency
support, or power quality can also be operated independently from an aggregator, by measuring
values on the electricity network and appropriately responding. Time of the day
An aggregator could once again
improve the overall operation of services but is not strictly required. On the other hand, congestion
relief, load-following or reserve services require
Figure access
5. Illustration to information from elsewhere in the electricity
of Peak-Limiting.

network, and therefore cannot be achieved from behind the meter without the batteries receiving
signals from an aggregator. The aggregator should coordinate the response of the BESS fleet adequately
to achieve positive effects. Load levelling is in-between, as it could be argued that by increasing
self-consumption and reducing peaks on houses, the result at an aggregated level would tend to a
more levelled profile, but this is still to be demonstrated, and the coordination from an aggregator is
more likely to bring about the desired effect.
Finally, as mentioned previously, a few services are not possible to provide from behind the
meter, namely those directly linked to the generation part of the network: Output smoothing, capacity
firming, and black start capability.
Figures 4–7 illustrate some4.ofIllustration
Figure the services mentioned
of voltage supportin on
Table 4. feeder.
a fictive

Original Demand
Power

After Peak-Limiting

Time of the day

Figure 5. Illustration of Peak-Limiting.


Figure 5. Illustration of Peak-Limiting.
Energies 2019, 12, 3954 16 of 27
Energies 2019, 12, x FOR PEER REVIEW 22 of 32

Rest of the grid Rest of the grid

Energies 2019, 12, x FOR PEER REVIEW 22 of 32

Rest of the grid Rest of the grid

Demand
100% reduced
demand to 80%

Demand
100% reduced
demand to 80%
Providing
20% of
demand
Providing
20% of
demand

Figure 6. Illustration
Figure of Transmission
6. Illustration & Distribution
of Transmission congestion
& Distribution relief
congestion (from
relief Katsanevakis,
(from Stewart
Katsanevakis, andand
Stewart Lu [103]).
Lu [103]).
Figure 6. Illustration of Transmission & Distribution congestion relief (from Katsanevakis, Stewart and Lu [103]).

7. Illustration
FigureFigure ofofreserve
7. Illustration response
reserve response to unexpected
to an an unexpected eventTorrealba
event (From (From Torrealba
[105]). [105]).

Figure 7. Illustration of reserve response to an unexpected event (From Torrealba [105]).


Energies 2019, 12, 3954 17 of 27

Table 4. Role of Behind-the-Meter Battery Energy Storage Systems in providing grid services.
Service Name Service Description Role of Domestic BESS Role of Aggregator/Signal Sender
Provide correction to the voltage variations (potentially out of Using the power converter (STATCOM) to manage reactive power
the regulatory values) caused by the resistive and impedance flows and the storage unit to manage the active power flows in order Not necessary. Enable access to more data and thus broaden their
Voltagesupport
nature of the cables (non-ideal conductors) by injections of to stabilise voltage close to regulatory values. positive impact.
active or reactive power. Figure 4 provides an illustration of this service.
Supporting any electrical parameters which need to remain in a Using the power converter (STATCOM) to manage reactive power
Power quality certain range of value during operation, e.g. harmonic level, flows and compensate harmonics, and voltage or power factor Not needed.
flickering, power factor, or voltage. deviations, for instance.
The aggregation of demand profiles which peak has been limited
Making up for the demand when it reaches a certain value, so thanks to BtM batteries should result in overall demand with limited
Not necessary. Provide coordination between units of a same area
Peak Limiting that the power drawn as seen by the grid never overreaches a peaks. Regardless of the location of storage on the grid, peak limiting
leading to overall optimised service.
certain value. Figure 5 illustrates an example of peak shaving only affects upstream components, thus BtM peak limiting should
relieve a larger amount of hardware.
For buildings equipped with rooftop PV panels: Maximising Sensible charging and discharging schedule to maximise the on-site Not necessary. Could help relief stress on grid by coordinating
PV Self-consumption
the on-site used energy. utilisation of the energy produced. nearby units.
Guaranteeing operation of at least some critical appliances in Keeping a certain amount of energy in the battery and storing energy
Backup provision Not needed.
the building for a given time during grid outage. from PV in case of a grid breakdown.
Injecting or absorbing power in response to frequency variation Response to frequency variations by instantaneous injection or Not necessary, but helpful to make sure this service and others do
Frequency regulation
in order to maintain it in a between the regulatory limits. absorption of power. not interfere with each other.
Downstream a potentially congested line: Charging when the Discharging the fleet to cover part of the local demand during peak Necessary to make sure enough energy is stored downstream the
T&D congestion relief demand downstream is low and discharging to when it periods, to decrease the overall energy flowing through the lines. An congested lines and manage the flows during charging and
increases to diminish the congestion. illustration of this principle for a simple line is found Figure 5. discharging to keep the line un-congested.
Privileging charging during low demand and discharging
Arbitrage and load-levelling during peak times to flatten the overall profile seen by the grid. Charge during low-demand periods and discharge at peak demands. Necessary to access large-scale demand forecasts.
Resulting in a larger-scale version of what is seen Figure 5.
Covering the loss of some generation capacity shortly enough
Exploiting the potential very short-term response time to quickly
after the event occurs to maintain grid stability. There are Necessary to relay the information of unexpected events leading to
Reserves respond to unexpected events occurring in the network such as
different timescales in the response, a generic example is need for reserve dispatch.
faults or tripping of a generator.
illustrated Figure 6.
Following the variations of the load profile at a given base-load Adjust an individual unit’s output to reduce the need from load Necessary, to adjust a unit’s outputs and ease the effects of overall
Load Following
level. following by fossil fuel-based generators. variations on conventional generator.
Making up for short term fluctuations in renewable generation
Renewable Generation Output
due to weather instabilities (clouds on PV panels or gusts of Not achievable by BtM BESS. -
Smoothing
wind on turbines).
Firm up renewable’s capacity by guaranteeing a minimum
Renewable Generation capacity
output regardless weather fluctuations and un-forecasted Not achievable by BtM BESS. -
firming
events.
In case of grid black out, re-energising the generators to enable
Black-start Not achievable by BtM BESS. -
their re-connection to the network.
Energies 2019, 12, 3954 18 of 27

3.3. Comparison of BESS with Other Energy Storage Technologies


Now that the potential value of providing services from behind the meter rather than elsewhere
in the network is established, it should be explained why BESS is a particularly adapted technology,
by comparing it to other available options. Table 5 lists the different energy storage technologies that
could compete with BESS in achieving the previously introduced services and compares them against
their ability to provide each of these services.
Energy Storage (ES) qualifies any process that enables transfer energy from a device to another, or
an energy type to another where it can be accessed on demand for later usage. Using ES to provide grid
services enables to artificially loosen the constraint of having generation and demand synchronised
at any time. Different ES technologies all provide various performance characteristics—reviewed
in [18–21,24,36,100,101,106]—which makes them more or less capable to achieve the different services
introduced previously. Table 5 compares the capability for each technology to provide a given service.
Mechanical energy storage consists of storing energy as potential energy, by pumping water in
a higher reservoir, compressing air in a tank, or setting a flywheel in rotation. As found in Table 5,
these systems are usually suitable for services requiring large capacities such as arbitrage or reserve
provisions [100]. However, such systems are not easily down-scaled, making their integration behind
the meter unpractical [18]. Having a fleet of aggregated BtM BESS on the other hand, can allow the
provision of services that mechanical energy storage can and more, due to being connected behind
the meter.
Thermal ES technologies store energy as either sensible heat (temperature change), latent heat
(phase change) or thermochemical reactions. Therefore, they require lower volumes than mechanical
ES and are more likely to fit BtM requirements. In particular, if progress is made in latent and
thermochemical storage, a significant increase in energy density could be achieved, making this
technology a strong potential to domestic applications [107,108] if coupled with HPs for instance. Still,
many services require the ES system to inject electricity back to the grid, which is impossible from
thermal ES at this scale, and with a decent efficiency. On the other hand, services related to peak
shaving and head comfort can also be provided by domestic BESS, making them a stronger candidate.
Chemical ES regards all technologies based on using electricity to force a chemical reaction
(electrolysis of water for instance) and creating electricity back by making the chemical products react
in the reverse process. These technologies are under development, and the efficiency achieved are
still fairly low [101,106,109], which leaves both potential and uncertainty for providing most services,
especially facing other more developed technologies.
Electrical ES, consists of Electric Double Layer Capacitor (EDLC) and Superconducting Magnetic
ES (SMES) [36,101] which store electricity as electric and magnetic fields respectively. They are mostly
fit for high power and low energy application, similar to flywheels. Their limitations stem from high
self-discharge rates, in addition to not enough maturity. Consequently, they may be very specialised in
certain services related to power quality but are outperformed by other technologies regarding the rest.
From these comparisons, it appears that (a fleet of aggregated) domestic batteries would be more
capable to reach a wider range of services than each of the other ES technologies candidate for grid
performance enhancement.
Energies 2019, 12, 3954 19 of 27
Energies 2019, 12,
Energies
x FOR2019,
PEER 12,REVIEW
xEnergies
FOR PEER2019,REVIEW
12, x FOR PEER REVIEWEnergies 2019, 12,
Energies
x FOR
17 2019,
ofPEER
34 12,REVIEW
x FOR
17 ofPEER
34 REVIEW17Energiesof 34 2019,Energies
12, x FOR 2019,
PEER
Energies
12, REVIEW
x17FOR
of
2019,
34
PEER12, REVIEW
x FOR
17 ofEnergies
PEER
34 REVIEW
2019, 12, x FOR PEER REVIEW 17 of 34 17 of 34 17 of 34 17
Energies 2019, 12,
Energies
x FOR2019,
PEER 12,REVIEW
xEnergies
FOR PEER2019,REVIEW
12, x FOR PEER REVIEWEnergies 2019, 12,
Energies
x FOR
17 2019,
ofPEER
34 12,REVIEW
x FOR
17 ofPEER
34 REVIEW17Energiesof 34 2019,Energies
12, x FOR 2019,
PEER
Energies
12, REVIEW
x17FOR
of
2019,
34
PEER12, REVIEW
x FOR
17 ofEnergies
PEER
34 REVIEW
2019, 12, x FOR PEER REVIEW 17 of 34 17 of 34 17 of 34 17
Energies 2019, 12,
Energies
x FOR2019,
PEER 12,REVIEW
xEnergies
FOR PEER2019,REVIEW
12, x FOR PEER REVIEWEnergies 5. Capability
Table2019, 12,
Energies
x FOR 34of
17 2019,
ofPEER each
12,REVIEW
x FOR ES
17 of 34 technology
PEER REVIEW17Energiesto achieve
of 34 2019,Energiesgrid
12, x FOR 2019,services.
PEER
Energies
12, REVIEW
x17FOR
of
2019,
34
PEER12, REVIEW
x FOR
17 ofEnergies
PEER
34 REVIEW
2019, 12, x FOR PEER REVIEW 17 of 34 17 of 34 17 of 34 17
Table 3. Likelihood
Table
of connection
3. Likelihood
atTable
of
theconnection
different
3. Likelihood
electricity
at the of
different
connection
network
electricity
levels.
atTable
the network
different
3. Likelihood
levels.
electricity
Tableof connection
3.network
Likelihood
levels.
at of
theconnection
different electricity
at the different
network
Tableelectricity
3. levels.
Likelihood
Table
network
of
3.connection
Likelihood
levels.
Tableat
of
3.the
connection
Likelihood
differentat
of
electricity
the
connection
different
Tablenetwork
3.atelectricity
Likelihood
the levels.
different
network
of electricity
connection
levels.network
at the different
levels. el
Energies 2019, 12,
Energies
x FOR2019,
PEER 12,REVIEW
xEnergies
FOR PEER2019,REVIEW
12, x FOR PEER REVIEW Energies
17 2019,
of 34 12, x FOR 17 ofPEER
34 REVIEW17Energiesof 34 2019,Energies
12, x FOR 2019,
PEER
Energies
12, REVIEW
x FOR2019,
PEER12, REVIEW
x FOR
17 ofEnergies
PEER
34 REVIEW
2019, 12, x FOR PEER REVIEW 17 of 34 17 of 34 17 of 34 17
Table 3. Likelihood
Table
of connection
3. Likelihood
atTable
of
theconnection
different
3. Likelihood
electricity
at the of
different
connection
network
electricity
levels.
atTable
the network
different
3. Likelihood
levels.
electricity
Tableof connection
3.network
Likelihood
levels.
at of
theconnection
different electricity
Powerat the different
network
Tableelectricity
3. levels.
Likelihood
Table
network
of
3.connection
Likelihood
levels.
Tableat
of
3.the
connection
Likelihood
differentat
of
electricity
the
connection
different
Tablenetwork
3.atelectricity
Likelihood
the levels.
different
network
of electricity
connection
levels.network
at the different
levels. el
Energies 2019, 12, x FOR PEER Services
REVIEW Services
Energies 2019, Generation
RGServices
12, xEnergies
FOR PEER
Capacity 2019,Generation
RGREVIEW
12,Transmission
Energies
x FOR
Capacity 17 of 34Generation
2019,
PEER 12, Transmission
Services
Energies
REVIEW
x FOR2019,
Increased Distribution
PEER 12, Services
Energies
REVIEW Transmission
xCongestion
FOR Distribution
2019,
PEER Behind
Energies
12, Generation
REVIEW
x FOR 2019,the
17
VoltagePEERDistribution
Meter
Behind
Energies
of12,34x Generation
REVIEW
FOR 2019, Transmission
PEERthe Services
xMeter
Energies
12,17 REVIEW
of
FOR Source
Behind
2019,
34 PEER Transmission
Services
Energies
12,
Peak the
REVIEW
x17FORDistribution
of Source
Meter
2019,34
PEER 12, Services
REVIEW
x FOR
17Generation
Distribution
of 34 Source
Energies
PEER
Frequency Behind
REVIEWGeneration
2019,
17 of the
12,
Load 34Transmission
Services
xMeter
FORBehind
Generation
17PEER of 34
BackuptheTransmission
Meter
REVIEW Source
17 Distribution
of 34Transmission
Generation
Source
Distribution
17Upgrade
of 34 Behind
17 ofDistribution
Transmission
34 the Behind
Meter the Be Me
17
Grid Services
Arbitrage Table 3. Likelihood Table of connection
3. Likelihood atTable
of
theconnection
different
3. Likelihoodelectricity
at the of different
connection
network electricity
levels.
atTable
the network
different
3. Likelihood
levels.
electricity
Table of connection
3.network
Likelihood
Quality levels.
at of theconnection
different electricity
at the different
Reserves network
Tableelectricity
3. levels.
Likelihood Table
network of3.connection
Likelihood
levels. Tableat of 3.the
connection
Likelihood
differentat of
electricity
the
connection
Black-Start different
Table network
3.atelectricity
Likelihood
the levels.
different
network
of electricity
connection
levels.network
at the different
levels. el
Services Services Firming
Generation
Services Smoothing
Generation
Transmission Self-Consumption
Generation
Transmission
Services Distribution ServicesRelief
Transmission
Distribution Behind Support
Generation the Distribution
Meter
Behind
Generation Transmission
the Services
Meter Limiting
Source
Behind Transmission
Services
the Distribution
Source
Meter Services Regulation
Generation
Distribution Source Behind Following
Generation the Transmission
Services
Meter
Behind
GenerationPowertheTransmission
MeterSource Distribution
Transmission Deferral
Generation
Source
Distribution Behind Distribution
Transmission
the Behind
Meter the
T&D12,
Energies 2019, congestion
Energies T&D
x FOR2019,
PEER relief
congestion
12,
REVIEW
x FOR PEER T&D
relief
REVIEW
Table  Table
congestion
3. Likelihood relief
of  atT&D
connection
3. Likelihood ~Table
of
theconnection
different 
congestion
3. Likelihood atT&D
~ the
17electricity
of 34of 
relief
congestion
different
connection
network ~
17electricity
oflevels.
34
at the 
relief network
different  
levels.
electricity
Table  T&D
Enhancement
3. 
network 
Likelihoodcongestion
~
levels. of [9,55]
T&D
connectionrelief
congestion
at~ T&D [9,55]
the 
Energies
different relief
congestion
Table 2019,
electricity
3. 12,
Likelihood
relief
[9,55] x FOR
Table T&D
network of3. 
PEERcongestion
connection
Likelihood
levels. REVIEW
Table at~
of 3. the 

relief
connection
Likelihood
different [9,55]
~
at
of
electricity
the
connection 
different
Table ~
network
3.
at 
[9,55]
electricity
Likelihood
the 
levels.
different
network
of 
electricity
connection 
levels. ~ 17the
network
at Be
ofdifferent
34
levels.
Me
Energies 2019, 12, x FOR PEER REVIEW Energies 2019, 17 of12, 34x FOR PEER REVIEW 17el
Services
T&D congestion T&D Services T&D
relief
congestion Generation
Services
 Generation
Transmission
 Generation
Transmission
Services
 Distribution  Services
Transmission
Distribution Behind
 Generation
 the
 Distribution
Meter
Behind
Generation
 Transmission
 the
 Services
Meter Source
Behind Transmission
Services
the
 Distribution
Source
Meter  Services
Generation
Distribution
Source
 Behind Generation the
 Transmission
Services
Meter
Behind
Generation the

 Transmission
MeterSource
~ DistributionTransmission
 Generation
Source
Distribution
  Behind Distribution
Transmission
the
  Behind
Meter the
 Be
Me
~ relief congestion
 relief  T&D
~ Voltage
 congestion
 T&D
~ Voltage
 relief
congestion ~ relief
     T&D   congestion
~[9,30,55]
 [9,55]
T&D relief
congestion
 ~T&D
 [9,55] ~relief
 congestion  relief
[9,55]
 T&D congestion ~PEER
 relief

 [9,55]
  ~[9,30,55]
 [9,55]
    ~
 17el
Energies 2019,Voltage supportVoltage 3.support Voltage support support support Voltage support
Voltage [9,30,55]
support Voltage support [9,30,55] Voltage support [9,30,55]
PbA Table Likelihood of connection at theEnergies
different electricity
Table 3. xLikelihood
network ofEnergies
levels.
Table connection
3. ~ at
2019,
Likelihood 12,
Table
the x connection
of FOR
different
3. PEER
Likelihood atREVIEW
electricity
Table of
the connection
3.network
different
Likelihood Table
levels.
electricity
at of
the ~
connection
3.different
Likelihood
network
Tableelectricity
at levels.
of
the
3. connection
Likelihood
different network
Table Energies
electricity
at
3.
of levels.
the
Likelihood
connection
different
Table 2019,
network 17
of
at of 12, 34
3.electricity
connection
the
Likelihood
levels. xTable
FOR
different network
at
of 3.electricity
the REVIEW
connection
Likelihood
different
levels. network
at
of ~different
electricity
the
connection
levels.
Table network
3.at
electricity
Likelihood
the levels.
different
network
of electricity
connection
levels. network
at the different
levels.
12,
Energies
x FOR
Services 2019,
PEER 12,
REVIEW
x FOR
Services T&D PEER REVIEW
Generation
Services Generation 2019,
Transmission 12,
Energies
GenerationFOR
17
Transmission2019,
of PEER
34 12,
Distribution REVIEW
x FOR
17
Services of
PEER
Transmission34Energies
Distribution REVIEW
Behind 2019, Energies
the 12, x FOR
Distribution
Meter
Behind 2019,
Generation PEER
Energies
12,
the xREVIEW
FOR
Services
Meter 2019,
SourcePEER
BehindEnergies
12, REVIEW
x17FOR
Transmissionof
Services
the 2019,34PEER
Source
Meter Energies
12, REVIEW
x FOR
17
Services 2019,
of
GenerationPEER
34
Distribution 12,
Source REVIEW
x FOR
GenerationPEER REVIEW
Transmission
Services
Behind17
Generationof 34
the 17
Transmission
Meter of 34 17 of 34 17 of 34 17 of 34
T&D congestion T&D relief
congestion ~ relief 
congestion
 relief 
 T&D
~of Voltage
 
congestion
 T&D
~ Voltage
 
relief
congestion ~  
~ relief
  
 
 T&D 
 
 congestion
~[9,30,55]
 [9,55]
T&D ~relief 
congestion
 ~T&D
 [9,55] 
~relief
 congestion 
 
relief
[9,55]
 T&D 

congestion ~PEER
 

relief ~ Distribution
[9,55] Transmission
~  
Generation
Source
Distribution
 
~[9,30,55]
[9,55] Behind Distribution
Transmission
the
  Behind
Meter
~ the
Be Me
Voltage supportVoltage support Voltage support support support Voltage support
Voltage [9,30,55]
support Voltage support [9,30,55] 17 Voltage support of  17
[9,30,55] 34   34   
 of 34
Li-based
Energies 2019,Energies
12, x FOR PEER
2019, Power
12, REVIEW
Energies
x FOR quality
2019,
PEER Power
12,REVIEW
x FOR quality
PEER Power
REVIEW
Table  quality
3. LikelihoodTable  17
Energies
of connection
3. Likelihood 
2019,
at of 34
Power
12,
Energies
theconnection 
x FOR
different 17 
quality
2019, 34 Power
ofPEER
electricity
at the 
Energies
12, REVIEW
differentx FOR
network 17 2019,
quality
ofPEER
34 12,
Energies
electricity
levels. x FOR
REVIEW
network 
2019,
PEER 12, REVIEW
Energies
levels. x FOR 2019, 
PEER
Power
Energies 
12, xREVIEW
FOR[30,55,99]
quality
2019,PEERPower
Energies 
12, REVIEW
x17FOR
of [30,55,99]
quality
2019,34PEER 
Power
Energies
12, REVIEWx FOR ofEnergies
quality
172019, PEER
34 12,
[30,55,99] 2019,
REVIEW
x FOR of 
PEER
12, 34x REVIEW
Power FOR 
quality
17 

34 REVIEW
Table 
[30,55,99]
3.ofLikelihood 17 
of of 
[30,55,99]
connection 17 at of
the34 
different  netw
17electricity 17
Electro-Chemical
Services
T&D congestion
Voltage T&D
support
Ni-based relief Generation
congestion
Voltage ~ T&D
support relief 
Services
Transmission
congestion
Voltage  support relief Services ~ Distribution
 Generation
Voltage 
Services
 T&D
~ Voltage

support 
 Behind
Services
Generation
Transmission
congestion ~ the
support 
~ relief
 Meter
Services
Generation
 
Transmission
 Distribution
Services
Generation
Source
T&D 
 
Transmission
 Services
Distribution
congestion
Voltage Table Generation
Behind
[9,55]
T&D ~relief 
Transmission
Services
the
congestion
3. Likelihood
[9,30,55]
support
Voltage  Distribution
~Generation
 Meter
T&D
of [9,55] ~Behind

connection
[9,30,55]
support Voltage Transmission
Services
relief
congestionGeneration
at the
support 
Distribution
the 
Source
Meter
Transmission
Behind
relief
[9,55]

different
[9,30,55] Generation
T&D 
Distribution
the

electricity
Voltage Transmission
Services
Meter
congestionBehind
Source
Generation

network
support 

~ Distribution
theTransmission
relief


levels. Meter
Behind
Source
~ Distribution

[9,30,55] ~ Table
Transmission
the Generation
Behind
Meter the
Source
Distribution
~[9,30,55]
3. [9,55]

Likelihood 
 Behind
Meter
of connection
 
Distribution
Source
Transmission
the Behind
Meter
~ theSource

at 
the

different Be
Meel
Energies
Energies 2019,Energies
12, x FOR 2019, Power
12,
Energies
Demand-Peak
2019,PEER12, xx FOR
Energies FOR
REVIEW quality
2019,
PEER Power
12,
REVIEW
Demand-Peak
Limiting
2019,
PEER 12, xx FOR
REVIEW FOR quality
PEER
LimitingPower
REVIEW
Demand-Peak
PEER REVIEW 
 quality
Energies Limiting
2019, 12, 

Energies
x FOR 

2019, Power
Demand-Peak
17 PEER
of 34 12,
Energies
REVIEW 

x FOR17
17 
quality

2019,
of 34 Power
PEER
Demand-Peak
of Limiting
34 

12, REVIEW
Energiesx FOR17
17quality
ofPEER
2019,
of 

34
Limiting
34 

Energies
Energies
12, REVIEW
x FOR 

2019,
2019,
Energies
PEER 12, REVIEW
Energies
12, xx FOR

FOR 2019,
2019, 

PEER
Power

Energies
Demand-Peak
PEER 
 [30,55,99]
12,17xxREVIEW
12, REVIEW
FOR
of
FOR quality
2019,
34 PEER
[9,30,55] Power
Energies
PEER 

12, REVIEW
Demand-Peak
Limiting REVIEW
x17FOR

of [30,55,99]
quality
2019,34PEER 
Power

Energies
Demand-Peak
[9,30,55] 12, REVIEW
Limiting x FOR quality
172019,
ofEnergies
PEER
34
12,
Limiting
[30,55,99]

[9,30,55] REVIEW
x FORDemand-Peak
2019,
17 

PEER
of 
Power

12, 34 x REVIEW
FOR 
quality
17
17 of 


34
Limiting
PEERof 34 REVIEW 17
[30,55,99]
 of 34
[9,30,55]
17 of 34  17 
 of
[30,55,99]

[9,30,55]34  17 of 34  
  17 of 34 17
T&D congestion PowerServices
Voltage Flowsupport
relief qualityVoltage
batteries
Power Services 
support
~ T&D
quality Table 
Generation
Voltage support
congestion
3. Likelihood
Power  T&D
Table
quality of 
~Generation
relief
connection
3. Likelihood
 
Transmission
congestion T&D
at
 of 
theconnection
different
Power 

Transmission
relief
congestion
 
Distribution
T&D
electricity
at

quality 
theVoltage
relief
congestion
different

Power network  

~Distribution
support
T&D ~Table
electricity
qualitylevels.
 
relief
Behind
congestion
network ~

T&D the
3. Likelihood
 levels.
 ~of
Meter
Behind
relief
congestion
Table  
[9,55]
T&D 
connection
3. 
the
Voltage
Likelihood
 
Power
Table
Meter
congestion
relief
at
 of
the3.
Source
[9,30,55]Likelihood

support
~[30,55,99]
T&D 
Voltage
~relief
connection
different
quality Power 
congestion
Table
  of3.connection
Source
[9,30,55]
support
~[30,55,99]
T&D
electricity
at
 the
quality 

Voltage
~relief
Likelihood
different

Power congestion
network at~
Tableelectricity
3.
of
quality
the
support 

levels.
Likelihood
different
[9,30,55]
relief
[9,55]
connection
 
[30,55,99] Services
Table T&D
network of
at~Voltage
3. 
electricity

 
congestion
connection
the
Likelihood
levels.
Power different
Table 
network
support
[9,55]
at 

levels.
~3.electricity
of

quality the relief
connection
Likelihood
different

 Table 
Generation
[9,55]
network
at
of
3.the
[30,55,99] 
Table

~different
~electricity
connection
Likelihood
levels.
 
3.at
network
of
 
Likelihood

~[9,30,55]
[9,55]
electricity
the 
connection

[30,55,99] 
Transmission
levels.
different
 network the 
ofatelectricity
connection
[9,55] 
levels.
different
  
at~ the
network
 
different
Distributi
[9,55]
electricity
levels.

el
netw
&   &                  
  3.   of17connection    17el
Demand-Peak
EnergiesArbitrage
2019, 12,Energies
x Demand-Peak
Limiting Limiting
Demand-Peak Limiting Demand-Peak Demand-Peak
Limiting Limiting Services Demand-Peak Generation
[9,30,55]
Demand-Peak
Limiting Demand-Peak
[9,30,55]
Limiting Transmission Limiting
[9,30,55] Demand-PeakDistribution
Services Limiting Behind
[9,30,55] the Generation
Meter [9,30,55] Source
Transmission
&FOR 2019,
loadPEER
Arbitrage
Aggregation
12,REVIEW
x FOR
levelling
of & 3.
Table load PEER REVIEW
Arbitrage
levelling
Likelihood
Table
Energies
~load
of3.connection
Likelihood
2019,
levelling
at the 12, ~x FOR
different PEEREnergies
Arbitrage
electricity REVIEW ~17
loadof

2019, 34
Arbitrage
network Energies

12,
levelling
levels. x&FOR17 2019,
loadofPEER34Energies
 12,
levelling x FOR
REVIEW 2019,PEER
~ Energies
12, REVIEW
x Arbitrage
FOR
of
2019, PEER
~ 12,17xREVIEW
&of
FOR
Table 343.PEER
Arbitrage
[9,30,55]
load EnergiesREVIEW
levelling
Likelihood &  2019,
Arbitrage
load 
Energies
[9,30,55]
of 12,network
levelling
connection x&FOR
17load
2019, Energies
oflevels.
at PEER
the34 12,
~levelling
[9,30,55]
different 2019,
REVIEW
x FOR 17electricity
Arbitrage of 12,

PEER~34 x&FOR
REVIEW 17
load
network PEERoflevelling
~34
 REVIEW
levels. 17  of 34Table
[9,30,55]  [9,30,55]
~ levels.
Likelihood  of
the34   
at 17the 
ofdifferent
34
Voltage T&D
support congestion
Power T&D
quality relief
congestion
Power 
quality relief
Voltage
Power 


Table
support
quality of
 connection
3. Likelihood


Voltage
12,
at

~ of
theconnection
support

different
Voltage 

electricity
at
~ the
support

different

Voltage
Power

network electricity
 levels.
support
quality 
Table
Voltage
 
network
3. Likelihood
 levels.

support

Table
Voltage  connection
3. Likelihood
[9,30,55]
support 
Voltage
Power at
 of
theconnection
different
[9,55]
support
[30,55,99]
quality 
Voltage
Power Table
electricity
at
 the
3. Likelihood
different
[9,55]
support 
Voltage
[30,55,99]
quality Power Table electricity
3.
of

T&D 
support
quality Likelihood
connection
  Table
network
congestion
[9,30,55]
[30,55,99] of
at
3.
 connection
the
Likelihood
levels.

Voltage
Power different
Table

relief at
of

[9,30,55]3.electricity
support
quality the
connection
Likelihood
different

 Table
 network
at
of
electricity
3.the
[9,30,55]connection
Likelihood
different
levels.
 network
at
of
electricity
the
connection

[9,30,55]
[30,55,99] different
 network
atelectricity
~ levels.
different

[9,30,55]  network
 electricity
levels.

[9,30,55] netw
~  
~         
        
Demand-Peak
EnergiesArbitrage
2019, 12,Energies
x Demand-Peak
Limiting Limiting
Demand-Peak Limiting Demand-Peak Demand-Peak
Limiting Limiting Services Demand-Peak Generation
[9,30,55] 
Demand-Peak
Limiting Demand-Peak
[9,30,55]
Limiting Transmission Limiting
[9,30,55] Demand-PeakDistribution
Services
 Limiting Behind
[9,30,55] the
 Generation
Meter 
[9,30,55] Source
Transmission
RE Capacity firming
RE &FOR
Services
domestic 2019,
loadPEER
Capacity
&
12,REVIEW
BESS
Arbitrage x&
levelling FOR
Services
smoothing
firming
Table load
RE
3.
PEER
Capacity
&
REVIEW
Arbitrage
levelling
smoothing
Table
Likelihood
Table of
Energies
Generation
&
~load
3.firming
3. Likelihood
connection
Likelihood
2019,
&
Table
Table
Generation
levelling
ofsmoothing
at
of
x FOR
Transmission
~RE

connection
3. Likelihood
the
connection
3.
PEEREnergies
Arbitrage
Capacity
Likelihood
different ~of
at
at of
electricity
the
REVIEW&~17
Transmission
Services
firming
theconnectionRE
connection
different
different loadof

2019,
Capacity
network
34
Arbitrage
~ the
&
electricity
at the
electricity
at
Energies
Distribution 
12,
levelling x&FOR
smoothing
levels.~ network
Table firming
different
network
different
17 2019,
Services
3. load
ofT&D
PEER
Likelihood
34
&
Energies
 12,
Distribution
~Table
electricity
levels.
electricity
levels.

levelling x FOR
Behind
congestion
REVIEW
smoothing
~Meter
network
2019,
Generation

PEER


Energies
the
3. Likelihood
network
of connection
12,
RE
levels.
REVIEW
x Arbitrage
Meter
relief
Table
levels.at of
FOR
Behind
Services
 2019,
Generation
Capacity
the ~Source
PEER

connection
3.different
12,17

 RE
Likelihood
xMeter
REVIEW
Transmission
the &of
FOR
Services

firming
34 PEER
Source
~Arbitrage
[9,30,55]
load
[55,99,100]
TableCapacity
at of
the3.
electricity
Energies
&
connectionRE
REVIEW
Transmission
Services
levelling
&

smoothing
differentfirming
Table
Likelihood
network
Table
Distribution
 Generation
Capacity
Source
~2019,
Arbitrage
load[9,30,55]
[55,99,100]
electricity
at the
levels.
of3. & 
Energies
12,
levelling
3.connection
Services
x&FOR
17Generation
load
~Transmission
Likelihood
different
Likelihood smoothing
firming
network
Table
Table
Energies
Distribution
~levels.
2019,
of PEER
34
electricity
3.
of
at
3.
of
12,Transmission

[55,99,100]
&RE
Likelihood
Behind
~levelling
[9,30,55]
smoothing
connection
the
Likelihood
connection~Table
different
2019,
Services
REVIEW
x 17 of
Generation
T&D
FOR
Arbitrage
Capacity
network of
at
of3.
at
12,

PEER
~34
the

connection
the
xMeter
FOR
Transmission
congestion
&
firming
Likelihood
levels.
electricity
Behind
REVIEW
different
connection
the Table
different
17
load
at
of
network
at
PEER
Generationof ~34



~3.electricity
&
REVIEW
Distribution
the
relief
levelling
smoothing
electricity
the
connection
Likelihood
the different
Table
different
levels.
17
Transmission
Meter  of
Generation
Source
[9,30,55]
[55,99,100]
34Transmission
Distribution
~electricity
network
at
of
network3.the
connection
Likelihood
electricity
 Behind
~ network
different
levels.
levels.
Table

network
3.at
of
Source
Distribution
~[9,30,55]

[55,99,100]
electricity
the
Transmission
the
~ levels.
connection  Behind
Meter
17 of
~ network
levels.
different
Likelihood
Distribution
34 the

[9,55]

ofatelectricity
the  Behind
Meter

~ network
levels.
different
connection at~ the
Distributi
ofSource
34 the Be

~17electricity
netw
levels.
different
17
Me
el
Services
Power Voltage
Demand-Peak
quality ServicessupportVoltage
Demand-Peak
Limiting Generation
Services 
support
Limiting
Demand-Peak
Power 

Generation

Transmission

Limiting
quality 

Power
Generation 

Transmission
 
Distribution
quality 
Energies
Power 

Transmission
Services
Energies 

Demand-Peak
2019,
quality
Distribution

2019, 
12,
Power

12, Behind
xx& FOR
Services
FOR  
the


Limiting
PEER
quality
Distribution
T&D
PEER  
Power

Services
REVIEW
Behind 
Generation
congestion
REVIEW 
quality
thePower
 
Meter
Behind 
Services
relief Generation
 
 
Demand-Peak
[30,55,99]
quality Power
Transmission
 the
 
Services
Meter

Generation
[9,30,55]
quality
Source 

Demand-Peak
Limiting
Power 
Transmission

Services
Energies  Demand-Peak
[9,30,55]
quality
Distribution
 Generation
Source
2019, 
Limiting
Power


Energies
12, 17
Services
x&FOR
17 
~
of
quality
Generation
2019,
of PEER
34 

Voltage
Limiting
34 
[9,30,55]
[30,55,99]
Distribution
12,Transmission
 Behind
Services
REVIEW 
support
Demand-Peak
Generation
T&D
xArbitrage
FOR 
Distribution

Power
the

PEER
Services

congestion 

[30,55,99]
REVIEW quality
Transmission
Meter
Behind
Generation
 


Limiting 
Distribution
the

relief
  
Behind

[30,55,99]
Transmission
MeterGeneration
Source
  the

Distribution
 
Transmission
 
Generation
Meter
 

[9,30,55]
[30,55,99]
Behind
 Source 
Distribution 17
Transmission
the
 Behind
Meter Source

[30,55,99] 
Distribution
of 34 the

[9,55]  
Transmission
 34
~17 [30,55,99]
Behind
Meter 
Distributi
ofSource
the
  Be
Me
Arbitrage
T&D
RE Capacity &
congestionload
Arbitrage
Sensible
firming
RE CapacityT&Dlevelling
relief
Heat &
congestionload
&Self-consumption
smoothing
firming Arbitrage
~ levelling
RE Capacity
&PVrelief
smoothing & ~load

3.firming levelling
&ofsmoothing ~
 Arbitrage
T&D
~
RE Capacity
~PV &
congestion

~
firming
RE load
Arbitrage
T&D
~
Capacity
~PV levelling
relief
&Table congestion
smoothing
~ network
firming load
~ &levelling
relief
Voltage
~ smoothing
~ network ~
T&D
 
support RE Arbitrage
congestion T&D
Capacity
~3.PV ~
  RE &
firmingArbitrage
congestion
relief ~ [9,30,55]
load
[9,55]
T&D
[55,99,100]
Capacity
~of[9,30] &
levelling
RE &
reliefArbitrage
congestion
smoothing
firming load
~ [9,30,55]
T&D
Capacity [9,55]
[55,99,100]
~levels. &levelling
relief
congestion
~ smoothing
firmingload
T&D ~
levelling
[9,30,55]
relief
congestion
[55,99,100]
&RE smoothing
~ network
Capacity ~ ~

Voltage &
relief
firming load ~
support levelling
~


~3.electricity
& smoothing [9,30,55]
[9,55]
~
[55,99,100]
~3.connection ~ network ~ 
[9,30,55]
~
[9,55]
[55,99,100]
~Likelihood ~
~ ofatelectricity 
[9,30,55] 
~ network
~ the [9,55]

PV Self-consumptionPV 
Table 
Likelihood
Table
Self-consumption 
connection
3. Likelihood atof
theconnection
different
Self-consumption
Services
at
electricity
the 
different 3. Likelihood
Self-consumption
Services 
electricity
levels.
  
of connection
Generation 
levels.at the
Table 
Generation  
different Table
electricity
Self-consumption
Likelihood
Transmission
3.
PV Likelihood
network 
Table 
Self-consumption
connection
 at
Transmission
Services
of
PV3.
[9,30]
the
Distribution 
connection
Likelihood Table
Self-consumption
different Services
at
3.
ofthe
electricity 
Likelihood
Distribution 
connection
different
[9,30]
Behind
Services
of
PV
Generation 
atelectricity
connection
the different
Self-consumption
levels.
the Table

at
network the 
different
levels.
Likelihood
Table 
network
electricity
[9,30]
of 
levels.
Table
Likelihood

3. 
at
of the 
levels.
[9,30]
connection
 different 
connection
the 
differentat 
different
electricity
levels. el
netw
T&D congestion
Services
Energies
Thermal
Energies Demand-Peak 2019,
Arbitrage relief
12,
PowerServices
Limiting x& FOR PEER
quality
load
Arbitrage Services
REVIEW
Power
levelling &Generation
quality
load Demand-Peak
Arbitrage
levelling 

Generation
Energies
&
~load 
2019,
Limiting
Demand-Peak
levelling 12,
~Generation
Transmission 
Energies
x FOR
~RE 
Transmission
Services Distribution
2019,
~PEER 3412,
Demand-Peak
Limiting REVIEW 
Transmission
x FOR
~17 
Distribution
of~PEER 
34 relief
Demand-Peak
Limiting
Arbitrage Behind
Generation
REVIEW
x&  T&D 

~Distribution
the
Demand-Peak
Limiting congestion
~Behind
Meter
Services  
Demand-Peak 
relief
Transmission
the Meter
Behind
Limiting 
Services [9,55]
~Source
[9,30,55]  
the
Energies
Demand-Peak 17
Limiting 
Services
Meter
Distribution
of Source
2019,
34
[30,55,99] 
Generation
Energies
12,

Demand-Peak
Limiting 
x17FOR

of Generation
Source
2019,34PEER 

Energies
[30,55,99]
~~Demand-Peak 12,
Limiting ~Behind
Transmission
REVIEW
x&FOR 
2019,
 
~the
GenerationPEER 12,
Meter
Transmission
Power
Limiting ~ REVIEW
[9,30,55] T&D
xArbitrage
FOR 
quality
Demand-Peak 
PEER xMeter
~congestion
Distribution Behind
Transmission
Services
REVIEW
 Generation


Source
[9,30,55] the

 Transmission
~relief
Distribution
Limiting MeterGeneration
Source


Behind 

~Distribution
[9,30,55] Transmission
the
 
17 Source
Distribution
Generation
Behind
Meter of ~34

~[9,30,55]
Transmission

the 17
~ Behind
Meter Distribution
of 
[9,55]
Source  Behind

Transmission
34 the ~17 of
Meter
 Distributi
the
34
Source
[9,30,55] Be
Me
3. load levelling Arbitrage ~Voltage & ~~Arbitrage
[9,30,55]
load levelling
& Arbitrage
load[9,30,55] levelling load ~levelling & load levelling
2019, 12, x FOR T&DPEER REVIEW
congestion
Latent T&D relief
Heat congestion ~& relief  17 of
~T&D Energies
congestion
 2019,
~T&D
 12,
 FOR
~congestion PEER relief
~Voltage
REVIEW T&D
 
support
 congestion T&D  
 congestion
relief [9,55]
T&D relief
congestion
  T&D [9,55] relief 17
congestion of
T&D Energies
34  relief
congestion
 2019, 12,
~connection


Voltage FOR
relief ~~3.PEER
support
 

 REVIEW
 ~[9,55]
   ~[9,30,55]
 [9,55]  ~connection
 
[9,30,55]
  [9,55]

  17
R REVIEW RE Capacity
PVVoltage firming
RE Capacity
Self-consumptionPV &
support smoothing
firming
Voltage RE
Self-consumption Capacity
support smoothing
Table
PV 3.firming
17 of
Likelihood
Self-consumption &
capability
34
Table ofsmoothing

connection
3. LikelihoodCapacity

at of Voltage firming
theconnection
PV RE
different Capacity
Self-consumptionsupport
 &Voltage
electricity
at the
PV smoothing

Table firming
different
network support
Likelihood
Self-consumption &
electricity
levels. smoothing
Power
 network quality

of connection RE
Voltage
levels. Capacity
at the
Table  support
 
different
PV REfirming
[55,99,100]
TableCapacity
 [9,30,55]
support
electricity
Self-consumption
3.Black-Start
Likelihood 3. & RE
smoothing
Voltagefirming
Likelihood
of[9,30]
PV network 
TableCapacity
[55,99,100]

Self-consumption
connection at [9,30,55]
support
levels.
of
PV3. &
Voltage

connection
Likelihood
[9,30]
the smoothing
firming
Table
Self-consumption
different 
support
at
3.
of the [55,99,100]
&RE
Voltage

Likelihoodsmoothing

connection
electricity different
[9,30] Capacity
network support
of
PVat Power

electricity
the 
firming
different
Self-consumption
levels. Table quality

network
at & smoothing

electricity
the different
levels.
Likelihood
Table [55,99,100]
[9,30,55]

network
electricity
[9,30]
of ~ network

levels.
Table
3.connection
Likelihood 3. 
at
of 
[55,99,100]

Likelihood 
levels.
[9,30]
the
connection
different ofat [30,55,99]

electricity 
the different 
~ network
at~ the
 [9,30,55]

different
electricity
levels. el
netw
Black-StartServices capability
Black-Start
Services capability
 Black-Start 
Generation 
Generation
 
Transmission
Services Black-Start 
Transmission 
capability
Black-Start
Distribution ~ Generation 
capability
Distribution ~
Behind
Services 

Transmission
the Meter
Behind
Services~ 
 
the 
Services
Meter [9,30,55]
Black-Start
capability
Distribution
Source
Generation
   [9,30,55]
Black-Start
capability
Generation
Source  ~
Behind
Transmission capability
Generation
 the [9,30,55]
~

Meter
Transmission Black-Start


Distribution
Transmission
Services 
capability
Source 



Distribution 
[9,30,55]
Behind Distribution
the~ 
Generation
Behind
Meter 
[9,30,55]
 ~

the Behind
Meter 
Source ~
 
Transmission
the Meter
 

Source 
T&DVoltage
Arbitrage RE support
Demand-Peak
congestion
T&D
&Capacity
load Thermochemical
relief
congestion
firming
levelling
PVVoltage Demand-Peak
RE Capacity Limiting
T&D
support relief
congestion
&Voltage
smoothing
firmingRE 
~Limiting
relief
Capacity
&PV smoothing
Arbitrage
support 
&
firming
load &T&D
~smoothing
Arbitrage
levelling 

congestion
& load 
~T&D

Arbitrage 
congestion
relief
levelling
Voltage RE&~ 
~T&D

~Capacity
load
Arbitrage
support 
relief
~congestion
levelling
Voltage Services
firming 
~
~T&D 
& 
relief
~Voltage
 ~congestion
smoothing ~
T&D 
support
 
relief
RE [9,30,55]
Generation

congestion
~& 
[9,55]
T&D
Capacity
~3. 
 ~Arbitrage

congestion
relief
REfirming T&D
[9,55]
[55,99,100]
Capacity 
& congestion
~relief
 RE 
Transmission

smoothing
firming ~~[30,55,99]
 T&D
Capacity [9,55]
[55,99,100] & 
~relief
congestion
Services
smoothing
firming ~
T&D
Demand-Peak
 

Distribution relief
congestion
~Services

[55,99,100]
&RE smoothing T&D
Capacity ~Voltage
 
Limiting 
relief
~congestion

firming support
Behind
Generation

[9,55] 

the

~3. Likelihood
& ~relief Meter
smoothing ~[9,55]
~ 
Generation
  

Transmission
~ [55,99,100] 
~Source
[9,55]

~[9,30,55] 
Transmission

~ at  
~[30,55,99]

[9,30,55]
Distribution
[9,55]  ~ electricity

~ network 
Distributi

[9,55]  Be
Self-consumption
Power
Black-Start PV
quality Self-consumption
Power
capability
Black-Start quality
capability
Black-Start 

Self-consumption
 capability 

 

PV Power
Energies
Black-Start 
Self-consumption
 
 PV
quality

2019,
capability 

Power
12,
Black-Start
~ x& FORload
Self-consumptionArbitrage
support
quality levelling

Demand-Peak
PEER 
capability
Power


~
&Arbitrage
REVIEW load
quality


 

levelling
Voltage
Table
Power
Table
Limiting Arbitrage
[9,30,55]
~
load
3.PV ~Voltage
support


quality

levelling

Likelihood & 

Self-consumption
Power
Likelihood

Black-Start 
load
[9,30,55]
of
ofsupport
[9,30]
PV
[30,55,99]
quality
[9,30,55]
levelling
Voltage
connection
 &Arbitrage
load


at
Self-consumption
Power
connection
Black-Start
capability  at

[9,30,55]
support
the
PV [9,30]
quality
the
[9,30,55]
levelling
Voltage

different &17load
Self-consumption
Power
different
Black-Start
capability ~
support
electricity

quality
electricity
of 34
capability
~levelling


[9,30,55]
Voltage
 

[9,30]
Power
[9,30,55]
~
Arbitrage
network
networkPVsupport

quality
Demand-Peak
Black-Start
Power


levels. &
Self-consumption
levels.
 Table [9,30,55]
load
quality



levelling



Limiting
capability 
 
Table [9,30,55]


[9,30]
[30,55,99]
of
 
3.connection
[9,30,55] 
Likelihood

~ 


~ different

[9,30]
[30,55,99]
at
of the 
connection

[9,30,55] 

~  [9,30,55]

electricity
the 

different
[9,30,55]
 ~ 

[9,30,55]

[30,55,99]
levels.
 netw
T&D Backup Services
congestionprovision
T&DBackup Services
relief
congestionprovision

Generation
Backup
relief 
provision
 T&D Generation
 

congestion 
Transmission
Services 
~PEERBackup
relief 
Transmission 
Distribution
~provision

~T&D Backup 
 Generation
Services 
provision
T&D 
Distribution 
Behind
 Services
congestion 
Transmission

T&D the relief
~
Meter
Behind 
Services
Generation
congestion
~ T&D  the

Backup
 
Services
Meter
Distribution

congestion
relief Source
Generation
[9,30,55] 
provision 
Backup
[9,55] 
Transmission
relief  Generation
Source
provision
 [9,30,55] 
Backup
[9,55] Behind
Transmission
Generation
the

provision
Services 
Distribution
~~17  
Meter
Transmission
[9,30,55]
 Services
T&D 
~~Backup
 
Distribution
 Transmission
Services

congestion 
Source
provision
Behind
Generation

[9,55] 

Distribution
the


~~3.connection
relief 
Behind Distribution
[9,30,55]
MeterGeneration
 

the


Transmission 
Generation
Behind
Meter 
[9,30,55]
 Source 
the
 Behind
Meter
Transmission
  Source 
Distribution
[9,55]  
Transmission
the
 Meter 
Source
Distributi

~~ electricity
[9,55]  Be
RE Capacity
Energies
Power
2019,Voltage
Energies
x FOR
quality
support
Voltage
Arbitrage
12,firming PV &
Black-Start
Demand-Peak
2019,
PEER x&
Pumped
REVIEW
FORsupport
load
12,smoothing Voltage
Arbitrage
Self-consumption
Power PV levelling
Hydro
quality Table
capability
Black-Start
Demand-Peak
Limiting
PEER &RE
REVIEW 3.
Energies Energ
support
load
Self-consumption
Power quality
Likelihood
capability es
levelling
Capacity
PV
Table
Black-Start
Limiting
2019, 12, x2019




connection
Energies
FOR 12
~REcapability
of3.firming Capacity
Self-consumption
Likelihood&
PEER at
2019, thex12,
~smoothing
of FOR


Voltage~firming

RE
connection
different
REVIEW
Energies
x FOR 17

support
Capacity
at

 &Voltage
the En
electricity
Black-Start
Demand-Peak
2019,
PEER
of 3412, 
smoothing
Power~firming
RE
different
REVIEW 
xnetwork
FOR
17
support
gREVIEW

 

Capacity

2019
PV
quality &
electricity
capability
of 12
levels.
Voltage


Black-Start
Demand-Peak
Limiting
PEER
34 ~
congestion
smoothing
firming
RE
Energies
REVIEW FOR 
support
Capacity
Self-consumption
Power
Table network
x 3. quality
Likelihood

&
levels.
PEER 
capability
2019, Table
Demand-Peak
Limiting
Arbitrage

Power

relief
~Voltage
smoothing

~
Energies
12, REfirming
of
REVx& 
Capacity
quality
support
connection
3. Voltage
&
Likelihood
EW
FOR 

 RE
Demand-Peak
2019,
load 17
PEERof
12, 
at
Limiting
Table
34 of
levelling
[30,55,99]
smoothing
Powerfirming
~REVIEW
the
[9,30,55]
x[55,99,100]
Capacity
~
~
FOR PV 

support
quality
connection
3. 
Voltage
&RE
different

 

Likelihood
Black-Start
Demand-Peak
Limiting
PEER
Energies
17 
smoothing
firming [9,30,55]
Capacity
~[30,55,99]
Self-consumption
Power [9,30]
electricity
at


REVIEW
of the
of PV
quality
support 
Voltage

~Energies
& RE
different
[9,30,55] ~network
connection
Black-Start
capability
Demand-Peak
2019,
34 Limiting
12, 

smoothing
firming

x17 
 support
T&D
Capacity
electricity
FOR

at
of levels.
the Voltage
[9,30,55]
~Demand-Peak
Self-consumption
Power PV
[9,30,55]&
[9,30]
[30,55,99]
quality 
Black-Start
capability
2019,34 


different
Limiting
PEER
Energies
12,
congestion
~~
Self-consumption
Power network17
REVIEW
x FOR 
T&D

Arbitrage
smoothing
firming o


support

quality Voltage


levels.
34
electricity
capability
Demand-Peak
2019, PEER
of 
relief
congestion

[55,99,100]
&RE smoothing
Power~~
[9,30]

[9,30,55]
Limiting
12, 34
&
Table
network
REVIEW
FOR
support

load
xCapacity
PVquality
3.
Demand-Peak
 

Power

Voltage
Likelihood
Black-Start
17
Arbitrage of


levels.
Limiting
PEER 
relief

~levelling
34firming
Table
&
REVIEW
quality
[55,99,100]
Self-consumption 

~[9,30,55]
support
of


capability
17
load & 


Likelihood
Limiting
of 



34 
smoothing
Table

[9,30,55]


~ [55,99,100]
~3.the
[30,55,99]
at
of


[9,30,55]  


connection
Likelihood
 

~different
~~17

Table
 3. 

at
of
 
[9,30,55]
[9,55]

[55,99,100]
~[9,30,55]
[9,30]
[30,55,99]
electricity
 the 

connection
 

~~
different
Likelihood
of ~34  network
ofat
17 

[30,55,99]
~connection
 [9,30,55]
[55,99,100]
electricity
 the
of 

~~
levels.
34different
[9,30,55]

  

network
at
 17the
of 

[9,30,55]
[55,99,100]
[30,55,99]
levels.

 
different
[9,30,55]
34 netw
el
T&D Backup
congestionprovision
Reserves
Voltage T&DBackup
support relief
congestion
Reserves
Voltage provision
support Backup
relief 
provision

Reserves T&D 
congestion

Voltage

~ Backup

support relief 

Reserves 
provision
~T&D
 Backup 


Services
Services
Reserves
congestion 
provision
 T&D 
 


relief
Voltage congestion 

T&D



support relief 
~ Generation
Generation

congestion
Voltage T&D 


support

Backup
  

congestion
Voltagerelief
Reserves

[9,30,55]
[9,55]
[9,30,55] 
provision
Backup

support  relief
Transmission

Transmission

Reserves
provision

~ [9,30,55]
T&D Backup
[9,55]
[9,30,55]  
 Reserves
congestionprovision
Services 
T&D  
Distribution
~
Distribution
 
[9,30,55]

[9,30,55]
relief Services
congestion
 T&D  
~Backup





Voltage 
congestion

Behind
Reserves
relief ~ levelling

provision
Behind
Generation
[9,55]

[9,30,55]
support


the
the


relief


 

Meter 
[9,30,55]
MeterGeneration

[9,30,55]
 
 


Transmission
 
 
Source
[9,30,55]
Source

[9,30,55]
~
 [9,55] 

Transmission

 ~

[9,30,55]

[9,55]

[9,30,55]

Distribution



~ [30,55,99]
Distributi

[9,55]

[9,30,55]

Be
Energies Demand-Peak
Mechanical
REx FOR
Power
PVEnergies
2019, 12, Capacity
qualityPower
Black-Start
Demand-Peak
Self-consumption
2019,
PEER12,
Compressed
Limiting
firming
REREVIEW
x FORquality
Capacity
& air
Power
smoothing
capability
Demand-Peak
Limiting
PEER firming
Black-Start
REVIEW
Energies 
~

quality
& smoothing
capability
Black-Start
Limiting
PV
2019, 

Self-consumption
12, xEn
FOR g PEER 


capability
PV
2019 

Power
REVIEW
12
En x g
FOR 

~
quality Power
Demand-Peak
Self-consumption
17 PV
2019
PEER
of 

~


Self-consumption
3412 REV x FOR
17EW 
quality

~
Demand-Peak
of Limiting
PV
PEER
34 
Power
Voltage
Black-Start~
~
Self-consumption
En REV g EW
quality
 PV
2019 
Demand-Peak
support 

capability
Limiting
Arbitrage En 12
Power~
~
Self-consumption
g
x & FOR
~
 

quality Power
Demand-Peak
PV
2019
load 17
PEERof
12 
Limiting

34 REV
x
levelling ~
Self-consumption
FOR quality
[9,30,55]
[30,55,99] 
 
Power

Black-Start
Demand-Peak
[9,30]
PVEW Limiting
PEER
En 17g 
REV
o [30,55,99]
quality
[55,99,100]
[9,30,55]
Self-consumption 
 

Power

Black-Start
capability
Demand-Peak
PV
2019
34 EW Limiting 
 

Self-consumption
En12
~ gx17FORo [30,55,99]
quality
[55,99,100]
[9,30,55] 
Power
Voltage
Black-Start
capability
Demand-Peak
PV
2019 34 

Limiting
PEER
En RE
Self-consumption
12 g
REV
x FOR 


Capacity
 
quality
support
capability
Demand-Peak
2019
EW PEERPower
Voltage
 

[9,30,55]
Limiting
12 ~
[9,30] firming
REV
x FOR 
quality
Demand-Peak
support

Black-Start
PV
17
Arbitrage EW o 
~


&
Power
Limiting 

smoothing

Self-consumption
PEER 34 &REV 

[30,55,99]
quality Limiting
capability
[9,30]
17
load EW o 



34
levelling 
 [30,55,99]


[9,30,55]
[9,30]  

~ 17
 

[30,55,99]

[9,30,55]
o[9,30]
~ 34 
~ 17
~ o 
[9,30,55]

[30,55,99]
[9,30]
34
[9,30,55] 
~ 


 17 o 

[9,30,55]
[9,30]
34 
~
Backup
Arbitrage provision
&Liquid
load
Services Backup
Arbitrage
levelling & provision
load Backup
~ levelling

~provision
Generation 
~Services 

Transmission Backup
Arbitrage &
Services 

~provision
load
ArbitrageBackup 

levelling
Distribution RE & provision
load
Generation
Capacity  

levelling
 Behind  
Arbitrage
Generation
firming ~
Transmission
 the Meter
&Table & 
Arbitrage
smoothing load 
 
Backup
~levelling

&
Transmission [9,30,55]
provision
Arbitrage
load
Distribution
Source 
Backup
levelling
&
 

provision
~~[9,30,55]
theBackup
Arbitrage
load
Services
Distribution
 ~

levelling
Behind provision
&Arbitrage
load
Services the
~  

[9,30,55]
~levelling
REMeter 
& Generation
Behind
Servicesload
Capacity 
Backup
the
 ~levelling
 Meter
firming 

provision
Source
~BehindGeneration &

~the 
Transmission
smoothing  

[9,30,55]
Generation
Source
 

~ Transmission 

 Transmission

[9,30,55] 
Distribution 

  

Distribution
~[55,99,100]  
Behind 
[9,30,55]
~ Distributithe
  Be
Me
L ke Services
Tab e Arbitrage
3Demand-Peak hood PV Power
Demand-Peak
&Arbitrage
load
Reserves
Voltage
olevelling
Frequency connec
Limiting
support
quality
Self-consumptionPV
Voltage
air
on
regulation
Frequency
Power
Demand-Peak
Limiting a&Generation
Reserves support
he
quality
Self-consumption dlevelling
regulation eren
Frequency
~Limiting
 eTransmission

Reserves



regulation


 y
cVoltage
ecDemand-Peak
rBlack-Start

Power



Distribution
support
ne Arbitrage
work
Frequency
quality
Demand-Peak

 Limiting
Reserves
eve
 
&
T&D
T&D
sregulation

Frequency
Demand-Peak

 Limiting


Voltage



Power
Behind
Services
congestion
Reserves
congestion 


Arbitrage

quality
the

regulation
support 



Demand-Peak
relief

relief
Voltage

Power
Limiting 


Meter 
support
~

quality
&Arbitrage
load

~
Voltage
Power
Demand-Peak



levelling

Limiting
Generation
Source
3.
[9,30,55]


Likelihood

support
Voltage

quality

 
Frequency
Power
Demand-Peak
Reserves
~Limiting




[9,30,55]
of
[30,55,99]
quality
[9,30,55]
[9,30]

support
[9,30,55] 

Transmission

connection

regulation
Frequency

Demand-Peak
Limiting
~ on

Reserves



at




[9,30,55]
T&D
[9,30,55]
regulation
[30,55,99]
Demand-Peak
[9,30,55]

different

Frequency
Voltage


Limiting
Power

Reserves
congestion Distribution

electricity
T&D



 
regulation
support
~
Demand-Peak

quality 

Limiting



[9,30,55]
relief
[9,30,55]
Voltage

Power

network
congestion
 Arbitrage




quality
&Demand-Peak





Voltage
Frequency
support ~

Power
Limiting


Services
&

Reserves
levels.relief

 load

[9,30,55]
support

regulation

[30,55,99]
quality








levelling



~
Limiting



Meter
[9,30,55]

 
[9,30,55]
[9,30,55]

 










Generation
~Source



[9,55]

[9,30,55]
[9,55]

~ 
[9,30,55]
[9,30,55]

[30,55,99]













Transmission

[9,30,55]

[30,55,99]
[9,30,55]












[9,30,55]

[30,55,99]
[9,30,55]







Black-Start capability
RE Capacity
T&D Backup provision
&flywheels
load
Reserves
firming
RE
congestion Backup
Arbitrage
levelling
Capacity
& Reserves
smoothing
firming
relief &Black-Start
provision
load Backup
smoothing 

3.Reserves
capability
~provision
T&D 
congestion capability
~Black-Start
~RE Capacity

T&D ~ 
Reserves
3.
relief firming
RE capability
load ~Black-Start
Arbitrage

~Capacity
congestion Backup
&levelling
 RE &
Reserves
smoothing
~congestion
relief firming capability
load
 Black-Start
provision
3. Capacity levelling


&  firming
smoothing
~RE Black-Start
capability


Capacity
& RE b~&
firming[9,30,55]
~
CapacityBlack-Start
capability
LBackup
Arbitrage
Tsmoothing load 
k
 levelling


& RE & 
Reserves
hood
smoothing
firming Black-Start
capability
[9,30,55]
Arbitrage
load
[9,30,55]
[55,99,100]
Capacity
~[30,55,99]
[9,55]
T&D ~
oprovision
Backup

3.onn&levelling
RE &Arbitrage
Reserves
smoothing
firmingload
 h[9,30]
Black-Start
capability
provision
[9,30,55]
Backup
[9,30,55]
Capacity
[55,99,100]
congestion T&D d& ~~
levelling &
Reserves
~relief
RE
smoothing
firming
congestion
PV
capability
provision
Arbitrage
load
nCapacity
T&D  &Self-consumption
[9,30,55]
~
~levelling
RE 
[9,30,55]
y

smoothing
~Table
relief wo
firming
congestion Black-Start
load
nCapacity ~Backup


kthe 
& ~~
~levelling
 firming
Reserves
vdifferent [9,30,55]
smoothing
relief capability
provision
 & 



~3.electricity
[9,55] ~
smoothing
 [9,30,55]

[9,30,55]
~ network
[55,99,100]
[9,55]
~3.the 
  ~
~different
 [9,30,55]

[9,30,55]
~ [55,99,100]
~ the   ~

~ network [9,30,55]
~[55,99,100]

 ~
 

~ network [9,30,55]
~~ electricity


[55,99,100]
~ netw
T&D congestion relief
Frequency
Power regulationTable
Frequency
quality Power 3. Likelihood
Table
regulation
quality of
Frequency connection
Likelihood


~
at
of
regulation the ~
connection
different

Power

atelectricity
 Table
the different
Frequency
quality
 
Likelihood
network
 T&D

regulation

Voltage
electricity
levels.
Table
of
Frequency 
Voltage

connection
network  PV
support
Likelihood 
regulation
support
  Self-consumption
relief
levels.
at Table
the 
Power

of
different 
connection
3. Likelihood
 
qualityelectricity
at
Power of
the
 
[9,55]
connection
network
different

quality 
Frequency
Power 
Table
levels.
electricity
at

the
[9,30,55]
quality ~
different
Likelihood

regulation
Frequencynetwork
Table
 
~
electricity

levels.
of3.
[9,30,55]
regulation
Frequency ~
connection
Likelihood
Voltage
[30,55,99] network at
of
 
regulation
support ~
levels.
the
connection
 different
[9,30,55]
Voltage PV
T&Dat
3.

Frequency
support 

Self-consumption
congestion
electricity
Likelihood
Power Table
 network
of

regulation
[30,55,99]
quality 
relief
connection
Likelihood

levels.

Table
 
at
of
[9,30,55]
 
connection
Likelihood

levels.
 
at
of

electricity
connection

[9,30,55] 
~ different
[9,55]  
at [9,30]
electricity

the 
levels.
different

[30,55,99]    
levels.

[30,55,99]
RE Capacity
Arbitrage REfirming
&Capacity
load
Load
Demand-Peak
Arbitrage& &Following
smoothing
levelling
Black-Start load
Reserves
firming
RE
Load&
Demand-Peak
Limiting
Arbitrage
levelling
capability
Black-Start
Capacity
&
Following
Reserves
smoothing
firming load 

capability
&
Load Following
~Limiting
levelling 
3.Reserves
smoothing Demand-Peak
~provision 
~Backup

Arbitrage  load
~ & provision
Arbitrage

Load
Limiting
3. & Following
~firming

levelling 
load
Arbitrage

Load
Demand-PeakPower

levelling
~
Services
RE & Following
Reserves
quality
Demand-Peak
load
Capacity

LArbitrage
~PV 


Limiting
 
levellingbofirming
~ ~
Demand-Peak


&Capacity
load 
Arbitrage
& 
Limiting
 & Generation
smoothing
 [55,99,100]
levelling 

h[9,30,55] 
 
~Load
Demand-Peak
Arbitrage
load Limiting


Following
levelling
& 

Reserves
[55,100]
[9,30,55]
~bArbitrage
load
[9,30,55] 
 
Transmission
Load
Limiting
L
levelling
~nRE
 & Following

Reserves



[55,100]
[9,30,55]
Arbitrage
load
~Demand-Peak
[9,30,55] 
Load
Power

levelling
 ~y~RE &
Reserves 
Following
~
quality
Arbitrage
load 
Demand-Peak 
Distribution

Black-Start

[55,100]
Power
RE
hLimiting
 
~levelling
 &
Capacity
Arbitrage
quality

Demand-Peak
load

Load



Limiting

capability &

~levelling
firming
y~


Behind
Following
dReserves


[9,30,55]


[9,30,55]
load & ~the
~ Limiting






levelling 

Meter
smoothing

[55,100]

[9,30,55]

 ~d 

k 




 


 
Source
[55,100]
[30,55,99]
h

~[9,30,55]
~onn


d 


 

 
[9,30,55]

~[55,99,100]

[9,30,55] 
 

 ~wo 
[9,30,55]
v 


[9,30,55]~~
Backup provision Backup ~RE Capacity
~PV Backup RE Capacity
~PV
provision & smoothing
Backup ~ firming provision & smoothing
Backup ~RE provision RE
Backup firming
oCapacity
provision
doBackup & REsmoothing
firming
[55,99,100]
Capacity
provision&
dBackup smoothing
firming
Capacity
[55,99,100]
provision &
vBackup smoothing
firming
Capacity
provision & smoothing
~Tfirming
[9,30,55] ~Backup& smoothing
provision ~on[55,99,100]
~ hLonn
[9,30,55] ~ onn[55,99,100]
[9,30,55] ~ nonn wo ~ n n [55,99,100]
Hydrogen &       
Voltage
Chemical Frequency
PV
support
Load regulation
Self-consumption
Voltage Table
Frequency
PV
support
Following Load
3. Likelihood
 Table
regulation
Self-consumption
Following
of
Frequency
Load 
connection
Likelihood

~

:Following
at
of

regulation the 
connection
different
Voltage

 
atelectricity

Table
the different
Frequency
support
 Voltage
Load  Likelihood
network
Self-consumption

~ 
electricity
levels.
regulation
:Following
Tof
Frequency
support
  b
connection
network
Self-consumption
Voltage
Power
Load  Se Tab

k levels.
support
vquality
~

ces
Following
at
hood

regulation

the
Black-Starte
TSelf-consumption

 3for L
different
onn 
L PV
kke


~ 
 hood

electricity
hood
on 
Self-consumption
capability  
onn 

network 
aconnec
Frequency
PV
[9,30,55]
Gene  
Load
nonT
on 

levels.

h[9,30]
[9,30,55]
Self-consumption
Following
yon
 k

regulation
Frequency
PV
[55,100]  a
wo
n
T
hood bk

Self-consumption
Voltage
~

T
Load :
ansm  heoPV d
[9,30,55]
regulation
FollowingFrequency
[9,30]
support
ss
[55,100] 

LVoltage
onnk optimal
n eren
hoodwo
Self-consumption
on
Load
~

on k
o
 
regulation
PV
support

D
Following 
v
eonn
 
dec
[9,30,55] ron
b
~Self-consumption
sVoltage

  bu
[55,100]
PV 
nBlack-Start
Frequency
onsupport

L 

yhSelf-consumption
cperformed 
k

Voltage
Load~ ne T
hood
~work
bn
Beh 

ncapability
owo
regulation
[9,30,55]

support
Following  nd
L k
onnk


~ eve
he
vT 
hood
y

bn
Me 
sfrom

o
wo
[9,30,55]
[9,30]
 

k
~

elocation;
[55,100] 

vhood
 
o
 
[9,30,55]
[9,30]

[30,55,99]
Sou 
[55,100] 

ce

y
 


d
v 
hk[9,30]
[9,30,55]
 
y
 
 
k[9,30]
 

y

n w
Generation
PV RE Demand-Peak
Services
Arbitrage
Capacity
Self-consumption
RE Capacity Reserves
firming &
:
Services
&
firming
RE
smoothing
Backup
Frequency
PV
Transmission
BestDemand-Peak
load Limiting
location
others
Arbitrage :
for
levelling
Capacity
&
provision
Backup
regulation
Self-consumptionFrequency
PV &Generation
smoothing Best
firmingthat
load Limiting
location
service;

 &
provision
Generation
~:
for
levelling
regulation
Self-consumption
Services
Service
that
smoothing
Frequency
Best
~


RE
Reserves
Distribution
Demand-Peak
Transmission
service;
achievable
location
~: Service
Arbitrage


Capacity
~ (T&D:
regulation
for Transmission
~


Services
although
that
RE& load Limiting
Distribution
achievable
service;
not
Capacity
firming
Reserves ~

PV
theGeneration
~:
levelling
&Load 

Services
although
optimal
Service Best
firming
RE
smoothing
~RE: 
Reserves
Behind
achievable
location;
not

Capacity
Self-consumption ~
Arbitrage
 &
Power
Distribution
location
T&D the
Demand-Peak  :
:
Behind
optimal
for
smoothing
Frequency
PV ~


 firming
RE &
Reserves
the
quality
Generation
althoughDemand-Peak
Transmission
Service
Best
that
congestion Arbitrage
~

load PV
Capacity
Self-consumption
the
location;
location
service;
cannot
not


&

regulation
Meter

relief
Limiting :
Behind
Meter
Services
the
~:be
smoothing
~


levellingRE & Demand-Peak
Generation
optimal
Service
that
Arbitrage
load
Capacity
Self-consumption
 firming
Reserves 
PV

Limiting
Transmission
the
performed
 &
Distribution
Meter
service;
 Services
achievable
cannot
location;
from
levelling
RE &~: be :
Source
Service
Arbitrage
firming

smoothing load
Capacity


Demand-Peak
performed
there.
although
Service


[9,30]
~[55,99,100]
Reserves
[9,30,55]
Self-consumption ~
  Source
:
Limiting
Transmission
achievable
levelling

&

Frequency
PV RE &
smoothing
firming

Reserves
[9,30,55]
Distribution
cannot
not Source
Best
from the
[9,30,55]
load
[55,99,100]
Capacity
~
 [9,30,55]
Self-consumption
Limiting
Generation
Behind
location
there.
be
although
optimal

&

performed
levelling
~

 RE for
smoothing
firming


Services
the
Best

[9,30,55]
Distribution
Generation
Meter
location;
not that
[9,30,55]
Capacity
[55,99,100]
Arbitrage

~Self-consumption

regulation
Frequency
[9,30]
PV Reserves [9,30,55]&
regulation
Power
location
the
from
service;
~~Demand-Peak
Frequency
PV[9,30] ~
  ~ :there.
RE :
BehindService
for
smoothing
firming
&
quality
Transmission
Services
Best

Capacity
Arbitrage
Reserves
Self-consumption load
the
~:Demand-Peak
that
Service
location;
 

~
regulation
PV ~

&
Power
location
cannot 
Source
Meter
service;
Limiting
levelling

RE
Backup 
[9,30,55]
:
Transmission
Behind
Services
achievable
for
be quality
Demand-Peak
Generation
Service
~: that
Arbitrage
smoothing
~ firming
&
Service


load
PV
Capacity
Self-consumption ~
provision
Frequency &


:
Distribution
the
service;
although
cannot
Limiting
 Meter
&
levelling
Self-consumption
firming
[9,30,55]
Source
Generation
achievable
 Best
from
~:
be not

[9,30,55]
load
smoothing
 
[55,99,100]
~~
Reserves ~
[9,30,55]
Service
location
regulation

Limiting

Distribution
performed
there.
the Transmission
although

 optimal
levelling
& 

~

 
~
smoothing
Behind
Generation
achievable
for
 Source
that
not
[55,99,100]
~


[9,30,55]
[9,30]

service;
there.
the
although

~
 


 ~ :
Transmission
the
optimal
 [30,55,99]

~:Behind
Meter
Service
not


Distribution
location;
~

[55,99,100]
~ 
[9,30,55]
[9,30] 
 ~


:Meter
Transmission
the
theachievable
[9,55]
[9,30,55] cannot
optimal
 

~

[9,30,55]
Service
be location;
performed
although
[9,30,55]


[9,30]
[55,99,100] 
Distribution
Source
cannot
 
~ :
Behind
not



[9,30,55]
beDistributi
Source
Service
fromthe the
performed
there.
[9,30,55]
[55,99,100]
~ [9,30,55]
[9,30]

~ Be
optimal
cannot
 


Me fb
Load
Black-Start
Power: Following
qualityLoad
capability
Black-Start: Following
capability Load 
Following
: 
(T&D: 
Transmission 
Power
and Black-Start
quality
Transmission
Distribution;Power 
: 
(T&D:
and 
Following
vquality
Distribution;
Renewable Load
capability
Transmission
Demand-Peak 
Black-Start~ :
:
Energy).
RE: and 
Following
Renewable 
Black-Start

capability
Backup 
Distribution;
Limiting ~ :  
capability

Black-Start
provision
Energy).
(T&D:
RE: 
Renewable
Transmission  :
(T&D: 


Energy).
and

Load
Black-Start
capability : 
Following
Transmission [55,100]
[9,30,55]
[30,55,99]
Distribution;  
Load
Black-Start
capability
Power
and
RE::  

Following
 [55,100]
quality
Distribution;
Renewable 
Load
[9,30,55]
Black-Start
capability
Power ~:there.
:
Energy).
RE: 
Following 
quality
Renewable
(T&D: 
Black-Start
capability 
[55,100]
Power
 ~ :
Transmission Black-Start
Energy).  

Load
capability
quality
(T&D:Backup and:
Following 
capability
[30,55,99]
provision
Transmission
Distribution;
(T&D: 

and ~ 
[55,100]
[9,30,55]
[30,55,99]
Transmission
RE:
Distribution;
Renewable  
and ~:
RE:  

[55,100]
e
[9,30,55]
Distribution;
Energy).
(T&D:
Renewable 
~ :Me
Transmission
RE: 
Energy). 
[9,30,55]

[9,30,55]
Renewableand 
~ :

 

[9,30,55]
Distribution;
Energy). 
~
RE: Refb
T&DPower quality
Services
Arbitrage
congestion
T&D
RE Capacity
Services
relief& Best
congestion
firming
RE loadlocation
Arbitrage
EDLC for
levelling
Capacity relief
&Load &Generation
smoothing
Best
firming
that
load location
service;
 Generation
~:
for
levelling
T&D
&Frequency
Services
Service
that
smoothing ~ Transmission
Best
service;
congestion

RE
achievable
location
~: Service
Arbitrage
T&Drelief
~
Capacity
for Transmission

~ Se
although
that
& v ces
load
congestion
firming  Distribution
achievable
service;
not
T&D
~ theGeneration
~: 
levelling
relief
~Black-Start
Se
although
optimal
Service Best
congestion
&Self-consumption
smoothing
ces
achievable
location;
not

T&D
Demand-Peak
Arbitrage
Power
Distribution
location
the  Behind
Gene
optimal
for
conges
relief
Voltage
~Black-Start~~ RE
quality
Transmission
although
Service
Best
that

aon
T&D
support
& Capacity
load
the
one
location;
location
service;
cannot
not
Limiting
Arbitrage
~ ~
levelling
Behind
Meter
Se
theGene
~:
for
ebe
& v
optimal
Service
that
congestion
~~
REfirming
ces
T
the
aansm
performed
service;
Arbitrage
load
T&D

Capacity
achievable
cannot
location;
& RE 
levelling
&
relief [30,55,99]
Distribution
onMeter
Sefrom
~: ss
be
Source
v
Arbitrage
congestion
~
smoothing
firming
~ Capacity
on
loadces
ServiceT
performed
there.

[9,55]
ansm
although
Service
levelling

& &
reliefD
achievable
cannot
not
~ Source
BestGene
fromss
sBehind
the
[9,30,55]
~Self-consumption

smoothing
firming load on
[9,55]
T&D
[55,99,100]
bu
location
there.
be

~&  a Se
although
optimal on
levelling
~

on
the
performed
for
 v
congestion
smoothing
D
Best
~


Gene
Meter
ces
location;
not thatslocation
the
from
service;
Demand-Peak
[9,30,55]
T&D
Arbitrage
[55,99,100] 

~ 
Beh
bu
aT Seansm
on
optimal
relief on
nd
~:vDemand-Peak
Service
for
Best
congestion that

T&D
&Capacity
Arbitrage
load
ces
~

~
he
Service ss
location;
location
cannotSource
Me
on
Limiting

~RE
TBeh
service;

relief Se ansm
eService
Gene
vnd
achievable
for
be~:
Arbitrage
congestion
[9,55]
levelling
 Capacity  ~ces
& Black-Start
load
D
performed
that
Service
~Load
Power
ss


he
 saon
service;
although
cannot
Limiting

Me
& on

relief
levelling
firming
bu quality
Sou
Gene
achievable
Best
frome
~:
be not
[9,30,55]
load
[9,55]
[55,99,100]
on
~Distribution;
~(T&D:
Dce
Service
location
&
saToptimal
performed
there.
the
although


levelling
~

ansm
onbuBehGene
achievable
for

smoothing
~RE:
Sou
from
that
noton ss
nd ceon
aT
location;
[9,55]
~

service;
there.
the he
although

~ 

ansm
on
~:Beh
optimal


~~
Me [30,55,99]

Service
not

~

D ss
nd s on
location;
9

the
[9,30,55]
~ 55
[9,30,55] T hebu
ansm
achievable
cannot
optimal




on DeSou
Service
be

~

ss s 
on
location;
performed
althoughce
cannot
[9,30,55]
[9,55]
 

bu
Behnot
 on D
nd
Sou
Service
from
be the soptimal
he
performed
there.ce
cannot

[9,30,55]
[9,55]
 

bu
Be
Me
      
    ~[55,99,100]  ~ [55,99,100]
elief PV 
Black-Start
Frequency
Demand-Peak
T&D congestion
capability
Self-consumption
Electrical PV
T&D
Load
regulation
Black-Start
Backup
Demand-Peak
Reserves
Self-consumption
:Following
Limiting
relief Best
congestion
PV
capability
location
provision
SMES Backup
Limiting
Reserves
Self-consumption
Black-Start
relief:~
forFollowing
Best
that 

capability

location
service;
provision
 T&D
Load
~:
for 

:Following
(T&D: 
Service
thatBest
service;
congestion



PV
regulation
Frequency
Transmission
~: (T&D:

achievable
location 
~ Service
Demand-Peak
T&Drelief

for

Services
and

although
that
conges



Self-consumption PV
regulation
Frequency
Transmission
Distribution;

achievable
~firmingservice;
not
~T&D
~on

the 
~
RE
:
(T&D:
and
 RE:
~:although
Backup
Demand-Peak
Limitingoptimal
Service
econges


e Best


 PV
Capacity
regulation
Distribution;
Renewable Load
Frequency
capability
Transmission

achievable
location;
not
location
provision
Arbitrage
the
Backup
Limiting
Demand-Peak
Arbitrage
on Vo


Self-consumption

e

firming
:
:
optimal
for 
ealthough
&
age


Following
Energy).
RE: and
Service
Best
that PV 
&

regulation
Frequency
capability
Renewable
 Backup
location;
location
service;
provision
load
 T&D
suppo
& Capacity
load
cannot
not
Limiting


smoothing
Black-Start
Generation
Self-consumption
Distribution;
 
levelling
~Voltage


levelling
:
Energy).
the
~:
for
be(T&D: 
PV
optimal
Service
that 
capability

regulation
Frequency
Black-Start
provision
RE: 
performed
Reserves
conges T&D

service; 

Renewable
Transmission
 
achievable
cannot
location;
Backup
on


~:[9,30,55]
from
conges
e

Self-consumption
[9,30,55]
be

~~Capacity

(T&D: 
[9,30]
PV
Service 

Load
Frequency
regulation
Black-Start
:capability
Energy).
and

performed
there.
although
Service
provision
e[9,30,55]Backup

[9,55]~~on
 [9
e:

Following
Transmission
 
achievable
cannot
not
~Best
 efrom
PV
[9,30,55]
[9,30]
55]
[55,100]
Distribution; the 


provision
[9,30,55]
[9,55]
T&D 

Self-consumption

Transmission
Load
regulation
Frequency

RE
Black-Start
capability
and
RE:
location
there.
be
although
optimal

Backup
Demand-Peak

: Capacity
performed
congesfor



Following
Best
PV
~that
[9,30,55]
location;
not [9,30]
[55,100]
Distribution;
Renewable

provision
 [9,30,55]
T&D
Arbitrage

Self-consumption

Load
regulation
Frequency
Black-Start
capability
Backup
Demand-Peak 

location
the
from
service;
Limiting
on 
RE
~:firming
:
optimal
ethere.
Service
conges for
Best
~: 
PV


Following
Energy).
RE: regulation
Black-Start
capability
Renewable
(T&D:

that 
Service
location;
provision
&eCapacity
T&D
~~
Arbitrage
load 


&
Self-consumption

location
cannot smoothing

service;
Backup
Demand-Peak
Limiting
on  
~~
[55,100]
[9,30,55]
conges
firming
Distribution
Reserves
:
Transmission
 ~:PV
achievable
[9,55]
~levelling for 

Frequency
Energy).
beService
eCapacity performed
that
Service
provision
&eDemand-Peak

load ~~ on



&

capability
(T&D:
 Backup and:
service;
although
cannot
Limiting


smoothing

e
~
Self-consumption

Following
achievable
Reserves

levelling
Best
from
e~:
be 
capability

[9,30]
[9,30,55]
Transmissionregulation
provision
9
not
[9,30,55]Service
location
55 &




performed
there.
the and 

although

Limiting
~
~
optimal
achievable
for


[9,30]

Behind
[9,30,55]
Transmission
 Distribution;
Renewable

from
that
not
[9,30,55]
 55


~ 
~9location;
service;
there.
the 
and 


although

:
RE:
optimal


~: the

Service
not


[9,30]
[55,99,100]
~[55,100]


[9,30,55]
Distribution;
Energy).
(T&D:
Renewable

9location;
the
~[9,30,55]

30
~



55


Meter
~
 :
Transmission
RE:
achievable
cannot
optimal


Energy).

Service
be 
[9,30,55]

[9,30]
[9,30,55]
Renewableand
9 
location; ~~


55
performed
although
cannot
[9,30,55]
~[55,99,100]
  
:



not
 Service
fromthe 

[9,30]
be [9,30,55]
Distribution;
Energy). 

~~
RE:

55
performed
there.
9optimalSou
cannot
[9,30,55]
 
Refb
RE
Voltage Capacity
support
PV firming
RE Capacity
Voltage
Self-consumptionPV &
support smoothing
firming
Self-consumption 

& smoothing
Voltage RE


Capacity
support PV


Voltage
 support

Self-consumption
 
& smoothing
Voltage
Black-Start RE ~Black-Start
support

Capacity

capability ~ firming
Power


RE quality

 PV &


capability ~RE
 firming
smoothing Capacity
Self-consumption

support

PV 


& REsmoothing
Voltagefirming
 [9,30,55]
Self-consumption
 PV 
support


&



smoothing
firming
[55,99,100]
 [9,30,55]
Self-consumption [9,30]~&


Black-Startsmoothing
Voltage
 RE 
[55,99,100]


support
Capacity
~that Voltage
[9,30] 

Black-Start
capability RE
~ firming support


 
Black-Start
capability &

RE
Voltage
[9,30,55]
 smoothing
 ~achievable
~firming PVsupport

 &

capability firming
[55,99,100]
 ~Distribution;
smoothing
Self-consumption

~(T&D:
[9,30,55]

[9,30]
 smoothing


 ~RE: [9,30,55]

[9,30,55] 

 

~RE: ~[9,30,55]
[30,55,99]

[55,99,100]

 

[9,30,55] 
 ~ [9,30,55]
~location;


 
[9,30]
   ~ [55,99,100]
[9,30,55]
~Distribution;
~ 
 
[9,30] 
~ Refb
~
Backup
Black-Start
Load& provision
Black-Start
capability
Frequency
Following
Backup : capability
Black-Start
regulation
Best Frequency
location
provision
Backup :
for Best capability
regulation
that location
service;
provision ~:
for :
(T&D:
that
Service Transmission
Best
service;
Load Followingachievable
location
~: (T&D:
Black-Startand

Service
for Transmission
although
Load 
that Distribution;
Backup
capability
achievable
service;
not
Following the
~: 
(T&D:
and
~ RE:
although
Loadoptimal
Service  PV
Distribution;
Renewable
Transmission
Backup
achievable
location;
not
Following
provision

the
Load 
~ :
:
Self-consumption
Energy).
RE:
optimal andRenewable
although
Service
Best 
Backup
Distribution;
Black-Start
location;
Followinglocation
provision cannot
not
Load 
~

:
Energy).
thefor
be(T&D:
RE:
provision
optimal
Service
that Renewable
Transmission
Black-Start
capability
performed
Following
Reserves service;
cannot
location;
Load
Backup from
~: 
be :
(T&D:
[9,30,55]
Energy).
Serviceand

Black-Start
capability
performed
Followingthere.
[55,100] Service
Load
provision
Backup

: 
Transmission
Distribution;

achievable [9,30,55]
cannot
Best
from
Following  and
capability
~ RE:
location
there.
be
although
Load
provision
Backup

: 
performed
for 

Best
not
FollowingPV
Distribution;
Renewable
[9,30,55]
provision 
location
the
from
service;
Load
Backup :
Self-consumption
Energy).
RE:
optimal
there.
for
Best
~: PV

that 
Renewable
(T&D:
Frequency
Service
location;
Following
provision
 
location 

service;
Backup
 [55,100] :
Self-consumption
Transmission
Energy).
for (T&D:

Black-Start
Service
~: that
Service
provision 
Backup
regulation
Load
 and:
service;
although
cannot  provision
Transmission
~
achievable
Best~:
be
Following
Reserves
  
[9,30,55]
capability
not
[55,100]

Service
location


performed
the and 
Transmission
although~
optimal
achievable
for 
Distribution;
Renewable
[9,30,55]
 
from
that
not  and
location;
[55,100]
[9,30,55] service;
there.
the 
although~ :
optimal

~: 
Service
not [9,30]
Distribution;
Energy).
(T&D:
Renewable
[55,99,100]
 
location;
the
[55,100]
[9,30,55]
  :
Transmission
RE:
Energy).
 
achievable
cannot
optimal Renewable

Service
be 
and
[9,30,55]
performed
although

cannot
[55,100]
[9,30,55]

:
Energy).

notService
from
be the RE:
[9,30,55]
performed
there.
optimal
cannot
[55,100]
Arbitrage Arbitrage
load Reserves
levelling
& load Reserves
levelling 
~ 
~ 
Arbitrage & load
Arbitrage 
levelling & 
Reserves load 
levellingReserves 
~ 

Frequency 
~ 
regulation  
Reserves
[9,30,55] 
ReservesArbitrage
[9,30,55]  &
Reserves [9,30,55]
Arbitrage
load 
levelling Reserves
& Arbitrage
load  
levellingReserves
& 
load
Frequency 
~levelling [9,30,55]
regulation ~
   ~ [9,30,55]  [9,30,55]  
[9,30,55]
rt 
Voltage
PowerTechno
Reserves
:
support
PVVoltage
quality ogy
Black-Start
support
Self-consumption
Power adap PVed
quality
capability o
Self-consumption
Black-Start he  ce
serv
capability

Voltage
achievable
(T&D: 

~ :T&D
Power 


support
quality 
Transmission
Techno ogy


Vo

congestion
PV (T&D: 
and
adap
Black-Start

age
:
suppo
Self-consumption
Power
 quality

Transmission
Vo
Backup

Distribution;
ed


Power
bu
capability RE
(T&D:
and


age
RE
~: relief
RE:
may
:
 Capacity
Arbitrage
suppo

Capacity
quality
Demand-Peak
 PV
Distribution;
:Best
Renewable
Transmission
no

provision

Powe
be
Backup 

~

Black-Start

firming
&and
firming
Self-consumption
Energy).
:
RE:
he 
load
qua


 PV
Renewable
bes

&


& y smoothing
levelling
Vo 
Distribution;
provision op
Black-Start
capability ~


ageRE:
smoothing
Self-consumption
Power
Limiting Energy).
on
Reserves
:
PV
suppo




quality

Vo 

Renewable

age
Techno
Black-Start
capability 
:~:

Self-consumption
Power
suppo
PV
[30,55,99]
(T&D: 
~Self-consumption

quality
Energy).

ogy
 [9 
30
Transmission
Black-Start
capability
: 
  : 
hard
 y
[9,30,55]
Vo


55]
[9,30]
[30,55,99] 
 RE
Power

and
or
~:capability
~


Backup
: no
age
:~
 ~ suppo
Capacity
~compa
Distribution;



Vo
[9,30]
quality
PV
[9,30,55]
provision 

Power


Backup
Black-Start
 
RE
:
age
firming
Self-consumption
RE:
:bfor
~:e
suppo


Capacity
PV 
quality
 
Renewable
(T&D:

w 
provision
Vo
Black-Start
capability

& ~
[9,30,55] Arbitrage
age
smoothing
 ~firming
[30,55,99]
Power
Self-consumption

Backup

Transmission

halthough
 ~he PV
Energy).
:for
suppo


quality

(T&D:
serv 
Black-Start

provision 

&

capability
 ceand
&
 load
smoothing
Self-consumption 9[9,30]
Transmission
:
 ~
Reserves
30

[30,55,99]

Distribution;
RG (T&D:
[9,30,55]
capability
:~: 


levelling
55 




Renewab




and 

Transmission
RE:
~


9Renewable
 30 
[30,55,99]
Distribution;

[9,30,55]

:from
55and


eservice;
Genera




~

RE: ~

Distribution;
Energy).
(T&D:
~55
30[9,30]

[55,99,100]

[9,30,55]

Renewable

 on 

[9,30,55]
99


Transmission
RE: 
Energy).
9[9,30]
Renewable


30
~[30,55,99]
 
and
[9,30,55]

55


~Energy).


9[9,30]
[30,55,99]
~Distribution;
:
30

55


RE:
be [9,30,55]
~ [9
~Refb
~ 55  :  
~ 
Backup Load
provision
Backup Following Load
provision
Backup Following
provision Backup [55,100] [55,100] Load Following : Service   
RE provision Backup provision
Backup [9,30,55]
provision
Backup [9,30,55]
provision  [9,30,55]  Backup  [9,30,55]
provision   ~ [9,30,55] ~99  [9,30,55]
Best location for
Reservesthat service; ~:
ReservesService although
Best location
not for
the that
optimal
Best
service;
location
location;Service
for
Reservesthat
Service
achievable
location
service;
cannot ~:
foralthough
Service
be
Best
that
performed
location
service;
achievable
not the
~:
for
from
optimal
Service
Best
that
although
there.
location
service;
achievable
location;
not for
Best
the
Service
that
although
optimal
Service
location
service;
achievable
cannot
location;
not
for
Best that
the
Service
location
be
although
optimal
service;
performed
Service
achievable
for
Best
location;
~:
not that
Service
cannot
location
the
from
service;
although
optimal
there.
achievable
beService
performed
Bestthat
Service
location;
not location
cannot
service;
the achievable
optimal
frombeService
~: performed
there.
that
Service
not location;
service;
the
although
cannotachievable
optimal
Best
from
beService
notService
location
performed
there.
location;
the
although
cannot
optimal
achievable
for that
Service
not
be location;
performed
there.
the
although
cannot
optimal
~: Service
from
not
belocation;
performed
thethere.
achievable
cannot
optimal be
from
location;
performed
although
there.
cannot notService
fromthe
performed
there.
optimal
cannot
RE Capacity REfirming
Power Frequency
Capacity
quality& firming
smoothing
Power regulation
Frequency
&
quality smoothing 
regulation
 Power 
RE

 quality 
Capacity
~ Powe
 
firming 
qua~Frequency
Capacity

 &y Powe 
smoothing
RE 
~firming
 
regulation
Frequency
Capacity
qua PV
Demand
PV ~ Reserves

&Self-consumption
ysmoothing
 firming
Peak
Self-consumption 


Frequency

L
&
regulation
Load
m
 
smoothing
Powe ng regulation

Following
qua 

Frequency

 Powe
Reserves

y
 
[30,55,99]
 qua 

 
Frequency
~[55,99,100]regulation
 RE
y
Reserves

 [9,30,55] 

regulation
Frequency
[55,99,100]
Capacity
~[30,55,99] ~Powe

REReserves

firming
 
 [9,30,55]
regulation
Capacity
~Demand-Peak
 quaPV 
Frequency
&Powe

 ~y
RE Reserves
smoothing
firming
Self-consumption 
qua


PV 

regulation
Frequency
Capacity 
 
&
RE 

~Reserves
smoothing
[30,55,99]
Powe
yh firming Frequency
Capacity
Self-consumption 
qua

 

regulation
Load

&
 
ysmoothing regulation
Following
firming
 30 
[55,99,100]
 55& 99 


 
smoothing
 
[9,30,55]
30
[9,30,55]
[55,99,100]
 
99 

 ~[9,30,55]
 
[9,30,55]
[55,99,100]
 9[9,30] 
30Transmission

[9,30] 55

 

[9,30,55]

[55,100]
30 55
 

 
 ~ [9,30,55]
30 55 

[9,30,55]
 

~99
EDLC
Demand-Peak E Black-Start
ec ro
Demand-Peak
Backup Chem
Limiting capability
Black-Start
ca
provision Doub
Limiting
Backup capability
e
(T&D: Layer
provision Capac
Demand-Peak
Transmission andor Black-Start
SMES
Limiting
Demand-Peak
Distribution;
~:Backup  RE: capability
Superconduc
Demand-Peak
 Limiting
Renewable
provision (T&D: ng
Energy). Magne
Limiting
Arbitrage
Transmission ~

Black-Start &(T&D:
andc Black-Start
Energy
Demand-Peak
load
 ~
levelling
capability 
Distribution;
Transmission
Backup S(T&D:Black-Start
RE:capability
orage
Demand-Peak

andLimiting
RenewableThe

Transmission
provision Distribution;
Backup Black-Start
capability
background
[9,30,55]
(T&D: 
~
Limiting
Energy).
and
beprovision 
RE:
Backup
 
Transmission [9,30,55]
Distribution;
Renewable capability
(T&D:
[9,30,55] ~
provisionco
Demand-Peak
 
and or
Energy).
RE: 
grey

Transmission

[9,30,55]
Limiting

Black-Start
Distribution;
Renewable (T&D:
[9,30,55]  regard
and
Transmission
Energy).
RE: ng
Demand-Peak
  Limiting
Black-Start
capability
Distribution;
Renewable
(T&D: 
[9,30,55]
  ~ s
Transmission
and

Black-Start
ab
Energy).
RE:  e
capability
Distribution;
(T&D:
Renewable
Backupexp
Limiting
and  ~[9,30,55]
a
Transmission
RE: capability
ns
Distribution;
Energy).
(T&D: ha
Renewable
[9,30,55]
provision 




and ~he
~:
Transmission
RE: aggrega
[9,30,55]

Distribution;
Energy).
Renewable 

 
and ~
 
RE:on  o
[9,30,55]
Distribution;
Energy).
(T&D: 
Renewable
 RE: 

Energy).[9,30,55]
the
Renewable
 and
[9,30,55] ~ location;
Distribution;
Energy).  
RE:
[9,30,55]~:Re
: Best : Best      
Reserves  the Reserves
: Service    :be
     Reserves
  Reserves    Reserves
: Best      [9,30,55]     
y PV 
Frequency
Reserves
Demand-Peak
regulation
Frequency
PV
Self-consumption
domes
Arbitrage c BESSLoad
Backup
&Arbitrage
load
Reserves
s be
levelling
&
location
regulation
Frequency
Following
Self-consumption
Demand-Peak
Limiting Load
Limiting
loaderBackup
provisioncompared
levelling 
for
Reservesthat
Following
location
service; ~:
regulation

forService
Demand-Peak
~ o he(T&D:
provision
Arbitrage
that
o& 

her

service;
achievable
~load

Voltage
PV
Limiting
Demand
Energy 
Transmission

Service
although
S
Backup
Arbitrage
levelling
(T&D: 
and &
achievable
Reserves
 Peak
orage
not
support


Self-consumption PV
Demand

 L
provision
load
Arbitrage

Transmission
thealthough
Frequency
Load
m
echno
optimal



levelling
Distribution; ng
RE
and &
RE: 
Following
Self-consumption
Peak
og
~ A
loades
 L
PV
Backup
location;
not
regulation
 Frequency
Load
m
presen
b Backup
age

Black-Start


Black-Start
Capacity

optimal
levelling
Distribution;
Renewable 
ng
Self-consumption
& ed
firming
Energy).
RE:


Following
Frequency
provision
location;
Demand
oad

cannot
regulation
nLoad


capability
eve

capability
Arbitrage
~

Renewable
provision &
 Reserves
:
hsmoothing
Backup 
 &Peak
sReserves
ab
ng
regulation
Best
Service
performed

Demand
e~ L
provision
Energy).
cannot
Frequency
Following
 Load
location
m
Backup
Arbitrage
load 



from
Reserves
levelling
 &
[9,30,55]

Following
for
Peak
ng that
[9,30,55]
 [9,30]
[9,30,55]
load

performed
there.
Frequency
regulation



 L
~
provision [30

Load
service;
Backup

m
levelling


Reserves



from
[9,30,55]
55
Following
ng[55,100]
~:
[9,30,55]
Demand
[9,30,55]
there.
[9,30]
PV 



provision
Arbitrage 

regulation
Frequency
99] 
Load
Service

~ & 


Following
achievable
Self-consumption

Peak
 
~ Demand
Backup
[9,30,55]
regulation
Frequency
[55,100]
PV L 
Load



Black-Start
[9,30,55]
Arbitrage
load 
although
Self-consumption
m
levelling

Backup ~ &
provision
Peak
ng 

Following
not
PV
Demand

 

Backup
regulation
Frequency
L 
Load
Black-Start
capability
Arbitrage
load 
provision
the




[9,30,55]

Backup
m

~ ~
levelling
[9,30,55] &Peak
ng
Frequency
provision
PV 
Following
optimal
Self-consumption
~ 

load

regulation
 Load

L


location


location;
capability
 Backup
provision ~ m
Reserves
:

Self-consumption


levelling

for
:
Best
ng
9
regulation
[9,30,55]
Following 
Service
[9,30]
30

[9,30,55]
location
provision

55


that service;






~




cannot
for

 9




Service
[9,30,55]
[55,100]
that be
[9,30]
30
[9,30,55]
(T&D:



service;
55

~



performed


achievable



~:
Transmission





[9,30,55]

[9,30,55]

[55,100]
Service
from
[9,30,55]
[9,30]
9 30 and

[9,30,55]
[55,99,100]
[9,30,55]

55



although


there.
achievable


not




[9,30,55]
[55,100]
9 30
although

[9,30,55]
Distribution; 

optimal


55

~
RE:


not


9 30

[9,30,55]

[55,100]
the

[9,30,55]
Renewable

[9


optimal
55

~ 3S
Ene
Load Following
Frequency regulation
Frequency
Load Reservesregulation
Frequency
Following Load Reserves 
regulation
Following  
Frequency Reserves
 Frequency
regulationLoad  
regulation
Following Frequency
Load Reserves 
Following 
regulationLoad
Frequency  : 
Following
 
regulation
Frequency
Best Load
location Reserves
 [55,100]
[9,30,55] 
 
Frequency
regulation
Following
for that Load
service; 
Reserves
 [9,30,55]
[9,30,55]
Following 
Frequency
regulation
(T&D:
[55,100]
~: Load
Service 

Transmission [9,30,55]
regulation
[9,30,55]
Following
achievable [55,100] 
Frequency
Load
 Reserves
and
although  
regulation
Frequency
Distribution;
Following
not 
Load
the 
 Reserves
RE: 
Frequency
Renewable
Following
optimal 
regulation
Load


location; Reserves
: [9,30,55]
Following 
[9,30,55]
:
Bestregulation
Energy).
Service
location


 
cannot
for 
[9,30,55]

[55,100]
that be 

service;
performed  ~: 

(T&D: 
[9,30,55]
[55,100]
Service
from  

Transmission
there.
achievable  [9,30,55]

[55,100]
[9,30,55]
and
although
 
not 
[9,30,55]

[9,30,55]
Distribution;
[55,100]
the 

RE:
optimal Re
:&Best location : Best
for that location
service; ~: 
forService
that service;
achievable
~: Service
although
&achievable
not the :
although
optimal ~Best location;
not
location
the :
:ng
optimal
for 
Service
Best
that ~location;
location
service;
cannot :
~:
for
be 
Service
that 
performed
service; :
achievable
cannot from
~:[9,30,55]
be
Best
Service
performed
there.
although
location :
achievable
not
for
Best
from that
thelocation
there.
although:
optimal
service; for
Best
location; :achievable
:  :
:   :from  : Service : Service :  : Sfb
Black-Start
Arbitrage Black-Start
capability
&Capacity
Arbitrage
load levelling capability
load levelling 
Arbitrage
~ &
~RE
load A& b
Black-Start
levellingage A 
capability
oad~Black-Start
b& eve
age 
~ & ng capability
oad 
Black-Start
Backup
eve ~ 


Acapability
provision
b ~ age & Ahoad
b 
~ng age
eve 
~&  ng
oad 

 eve ~A 
Black-Start
[9,30,55]
ngb ~
age
~RE &A ~~:



not
that
bService
location
theservice;

Black-Start
capability
oad age optimal
~
~eve Service
& for
ABest
~:
ng that
Service
location;
 location
cannot
service;
Black-Start
capability
oad
b although
age ~~
[9,30,55]
eve 
achievable
&for
beBest
Service
~:performed
ngthat
Service
 notlocation
service;
the
although
capability
Black-Start
oad ~cannot
eve achievable
optimal
 from
for
9~:
be that
not
[9,30,55]Service
performed
there.
location;
capability
ng
30 55the
service;
although
~



optimal
achievable
 ~:9Service
not
Service
location;
[9,30,55]
30 there.
the
although
55
~ 

cannot
optimal
achievable not
belocation;
performed
the
[9,30,55]

although
cannot
optimal

~ be
from
not


location;
performed
9thethere.
30cannot
optimal

55
~ Service
from
belocation;
performed
9 there.
30cannot
 
55
~
miting RE Capacity  RE
Load
firming &
Frequency
:Following
Best locationReserves
smoothing
firming
Load:for Following
Best
&
regulation
Frequency
that service;
Loadfor
location :
Reserves
smoothing
~: RE
Following
Best
that

Capacity
regulation

Service achievable
location
service; ~:
for
firming
(T&D: 

Capacity
although
Service
that Power
service; Frequency

not
Transmission
achievable 
~smoothing
the
~: (T&D:
Load

Reserves


firming
RE
and
Service optimal

Capacity
quality

regulation

Following
although Load
location;
Transmission
Distribution;
achievable
not the 
RE
smoothing
:
and :
RE:
although
optimal

~firmingCapac



Following
Service
Best
PV Backup
&
location;
not Load
y

smoothing

cannot
Frequency
Distribution;
Renewable
location
the :
:
optimal
for
m
~ Reserves
RE
Self-consumption
 be
Energy).
RE: 
ng

provision
Capacity


Following
&

Frequency

performed
regulation
Renewable
Service
Best
that Load
location;
location
service;
cannot
smoo



REReserves
firming
:
:
~:from
for
be Best
Energy).
(T&D: 

Capacity
 


there.
Following
Service
that
&
regulation
Frequency

location
performed
service;

Reserves
smoothing
firming


:
[55,99,100]
Transmission
Load
achievable
cannot for
from
~: be
~(T&D:
Bestthat
Following
[55,100]



and
Service

&

Frequency
regulation

RE
[9Reserves
smoothing
service;
performed
there.
although
location 30
 [9,30,55]
[55,99,100]
Capacity
:Following
Transmission
Load Distribution;
achievable
not
for
Best
from

55]
[9,30,55]
(T&D: ~


~:regulation

Load
Service
[55,100]
that
the and
RE:
location
there.
although 

firming

Transmission
achievable
:
optimal
service; for
Best
[9,30,55]
Capacity
 [9,30,55]
Following &
Backup


Load
Frequency
Distribution;
Renewable (T&D:
[55,100]
location;
~:
not
that
Service  ~RE
smoothing
although
location
theservice;
firming
Reserves
and
::
Transmission
Energy).
RE:
optimal
achievable
Service
for
Best
~:

Capacity
 ~
not
provision

Distribution;

Following 
regulation
Frequency
Renewable
(T&D:
that
Service
location;

Backup


Load
the
location
cannot

[55,99,100]
& smoothing


service;
although
firming
Reserves
RE:
optimal
:
:
Transmission
and Energy).
achievable
for
beBest

provision
 
~:Frequency
Renewable

Following 

regulation
Distribution;
(T&D:
Service Load
performed
that
Service
not

~location;
&

location :
and

Reserves

 :
Transmission
service;
the
although
cannot RE:
achievable
optimal
from
for~:
be

[9,30,55]
smoothing
[55,99,100]
~Best 
[9,30,55]
regulation
Energy).

Service
location
Distribution;
Following (T&D:
[55,100]

Renewable
that
not
Service




performed
there.
location;
the



~RE:
cannot
andfor
service;
although
optimal
[55,99,100]
:that
Transmission
achievable
from
~:
~(T&D:

[55,100]
be
Distribution;
Energy).
Service
not



service;


performed
Renewable
Service
location;
there.
the and



although
cannot~:
:
optimal
55


(T&D:
Service
Transmission
RE:
achievablefrom
99

~[9,30,55]

[9,30]
[9,30,55]

[55,100]
[9,30,55]
Distribution;
Energy).
Renewable
Service
not
be
100


 ~RE:

Transmission

there.
location;achievable
and
performed
the
although
cannot :
optimal 
Service
be
from
not

[9,30,55]
~[55,99,100]
 
[9,30,55]
and

although
Distribution;
Energy).
Renewable
[55,100]
location;
performed
the


there.
cannot :
RE:
optimal



not
Energy). the
Service
from

[9,30,55]
~Distribution;
[55,99,100]

[9,30,55]
[30

RE:~ Ene
optimal
Renewable
[55,100]
belocation;
performed
there.
cannot S5
:Refb
RE Capacity RE
Backup firming
CapacityBackup
&
provision smoothing
firmingprovision
& smoothing RE 

Capacity
 

firming
RE

 Capac
& 
~
 Backup
smoothing
y RE m 
provision
Capac
ng~

 Backup
& smoo
y 
~ 
m
provision
h ngng
 PV &
Backup
Se 
smoo
~

 Reserves
RE 

Capac
h ng
provision
consump
Reserves 
 

~

 y
RE
on Capac
m 

ng


 & y 
smoo
~

 [55,99,100]
m ~ ng
h
[9,30,55]
 

ng&
 REsmoo 
 [9,30,55]
[55,99,100]
Capac
~ h 
~

 
Backup
ng

y
RE 
 
provision

Capac
m  ng &
Backup
 
 ~y
RE
smoo Capac
m
Reserves ng

h
~

provision
 Backup
ng 


[55,99,100]
&
 y smoo
 m
Reserves provision
ng

h
~ 

ng
Backup


&
 smoo

 ~ [9,30,55]
55 99
provision
 h 100
ng



 
~ 55 
[9,30,55]
~
 99 

100

 
 
~
 
[9,30,55]
 
9 30 

~ 
~

55 99 
100

 ~ 
 55 99

 
100

 ~
Frequency
PV Self-consumption
PV Load
: Best location :
:for
regulation
Self-consumption
Best Frequency
Following Load
location :
for Bestregulation
(T&D:
Following
that
:~:Best
PV
location
service; Self-consumption
Transmission
~:
for(T&D: 
Service
that and
service; Frequency
PV
Distribution;
Transmission
achievable
~: (T&D:
Load 
and
Service RE:
although
:
regulation
Self-consumption PV
Renewable

Transmission
Distribution;
Following
achievable
not Self-consumption
the :
and
although
optimalEnergy).
RE: Best
:that 
location;
not
location
the
Load
Black-Start
Frequency
Distribution;
Renewable :
:
Energy).
RE:
optimal
for
: 
Service
Best
that Frequency
PV
capability
regulation
Renewable
location;
FollowinglocationSelf-consumption
Load
service;
cannot
cannot: :
Energy).
~:
for
: (T&D:
be regulation
Frequency
PV
Following
Service
that 
performed Self-consumption
Load
service; 
:
Transmission
achievable
cannot : (T&D:
Following
from
~: be
Best 
Frequency
regulation
[9,30]and

Service 
Load
performed
there.
although
location :
Transmission [9,30,55]
Distribution;
Following
achievable
not regulation
[9,30]
PV
(T&D:
[55,100]
for
Best
from
:location; that
the 
and
RE:
location
there.
although:
optimal
service; 
Self-consumption
Transmission
for
for
Best
: Service
[9,30,55]
PV
[55,100]
location;
~:
not
that
ServiceSelf-consumption

Frequency
Distribution;
Renewable (T&D:
location
theservice;
Load
and
::
Transmission
Energy).
RE:
optimal
achievable
Service
for
Best
~: PV
Distribution;

that
beFollowing 
regulation
Frequency
Renewable
(T&D:
Service
location; 
location
cannot
not Load 
Self-consumption
[9,30]

service; ~
although :RE:
:
Transmission
and Frequency
Energy).
achievable
for
beBestRenewable

regulation
Distribution;
(T&D:
Service
~: Load
performed
that
Service
Followingnotlocation and
service;
the
although
cannot [9,30,55]
Transmission
RE:regulation
[9,30]
Energy).
Following 
Distribution;
(T&D:
[55,100]
achievable
optimal
: from
for~:
be Renewable
that
not
Service
: Service 




performed
there. and
location;
the 
service;
although
optimal:
Transmission
RE:
achievable
from
~:
for:that
[9,30]
Distribution;
Energy).
Renewable
(T&D:
Service
not
Service 

location;
there.
the 
and
although
cannot:
Transmission
RE:
optimal
achievable
: 
(T&D:

Service
not
be 
[9,30,55]
Distribution;
Energy).
Renewable Transmission
location; 
and
performed
the
[55,100] although
cannot :
RE:
optimal 

[9,30,55]
[9,30]
Distribution;
Energy).
Renewableand

[55,100]
Service
be
from
not
location;
performed
the  :
RE:
not
there.
cannot
optimal
Energy). [9,30,55]
Distribution;[9,30]
Renewable
[55,100]
Service
from
belocation;
performed
there.
RE:

cannot :Re
EneSfb
velling PV ~ Reserves
Self-consumption
Black-Start PV Load
Black-Start
capability
Best
Reserves
that
Self-consumption
:Following
location
service;for
Loadfor
Bestcapability
location

that
Service
:Following
(T&D:
Best
that
location
service;



achievable
~:
forService
thatalthough
Black-Start
Transmission
location
service; ~:
for(T&D:
Service
that
service;
achievable
Demand-Peak


PV Self-consumption
(T&D: 
~:
notService


PV

Transmission
capability
and
Transmission
service;
achievable
the
Se
although

(T&D:
Load
Black-Start
Distribution;
~: (T&D:
Service
optimal
:
and
achievable
Bestnot
Reserves

and 

consump

location
Following
although
location;
PV
Transmission
thealthough
Limiting
Distribution;
capability
optimal
Black-Start
Transmission
RE:
Distribution;
Renewable
achievable
Best not
location


for
~
andRE:
thealthough
for

Reserves
Seoptimal
on
andRE:
Service
consump
that
location;
not

service;
the
capability
Energy).
cannot
Frequency
B ack
Frequency
Distribution;
RenewableBackup
Distribution;
Renewable
location;
not Load
service;
the



optimal
~
~: Service
:
be performed
Reserves
on
SEnergy).
RE:
Energy).
RE:
optimal
~:
:

location;


provision
(T&D:Renewable
Following
Best
achievable


regulation

aService PV
capab 

regulation
Renewable Se
Load
Black-Start 
Transmission
location;
achievable
cannot
location :
from
beService
y
:
be
for
Best
consump
Energy).
(T&D:PV
performed
although
there.



Following
Energy). and
Service
Best
location



performed
although
that
cannot
Se
Load
Black-Start
capability
location
cannot
service;
not



from
:
not
on
Transmission
for
be
Best

the
that
performed
Following
from
there.
[9,30,55]
consump
(T&D:
[9,30,55]
Distribution;
for
~: be~
Best
the
that
optimal
location

[9,30]
and

service;

Load[9
capability
RE:
performed
there.
optimal
location
Service
30


on

for
Transmission
Best
from
~: that
:Following
service;
Service
location
[9,30,55]
Distribution;
[55,100]
[9,30,55]
Renewable
there.
55]
[9,30]
PV 


service;

Se

and
~:Black-Start
location;
for
achievableBest
from (T&D:
that ~
Service :
location
there.
service;

achievable

Reserves
RE: 
~:that

consump

Service
PV
Distribution;
Energy).Renewable
Service
although 
Transmission
achievable
for ~:
cannot
(T&D:
service;
[55,100] Se

Frequency
although


Black-Start
capability
(T&D:
that
not Load
Service
cannot

service;
the ~
achievable
performed
~: Service
Reserves
onconsump
Transmission
althoughEnergy).
RE:
and 
PV
 


regulation
Frequency
Renewable
Transmission(T&D:
Black-Start
capability
Distribution;
(T&D:
:Following
achievable
be
optimal performed
~:
Best Service
not
location;
the

although
Se
Load
the


 ~
achievable
optimal
from
Reserves
[9,30] on
Transmission
and

[9,30,55]
although
location
Energy).
Transmission
and :
:
there.
consump
not

 
location;
Distribution;
RE: (T&D:
Following
achievable
optimal
fromfor
Bestthere.
not
Service
that


regulation
Load
the
although



capability
Distribution;
Renewable
location;
the and
optimal

Reserves

Best
Transmission
and:
although
location
service; ~RE:
not
[9,30,55]
on
location
9Service
 30
Distribution;
Following
optimal
cannot Best
for~:
be
(T&D:
[55,100]
[9,30,55]
:
RE: not
location;
the

Renewable
Distribution;
Energy).
Renewable
location
that







cannot
optimal
and 

Transmission
location;
Servicethe
performed
RE:
~
cannot
Service


be location;
[9,30,55]

Distribution;
RE:
optimal
for
service;
Energy).
:
service;
performed
Renewable
that
achievable
(T&D:
[9,30,55]
Energy).
Renewable
Service
from
~: be



9location;
30 
cannot



and
Transmission
service;
performed
Service
there.
RE:
cannot
although

~: Service
from

be
9 
Distribution;
Energy).
:
~: Renewable

performed
[9,30,55]
 
30
[9,30,55]
[9,30,55]
Energy).
(T&D:[55,100]
Service
achievablefrom
be
not
there.
achievable
cannot be


55

and

performed
thethere.RE:
~
from



performed
although
Distribution;
Energy).
Transmission
achievable
cannot
although
optimal
Renewable

be
from
not
there.
9and

[55,100]
[9,30,55]
performed
although


30

there.
location;
the
RE:
~ 

from
Energy).
:not
optimal
thethere.
optimal
Renewable
from

[55,100][9
[9,30,55]
Distribution;
the
Servicethere.
location;



9optimal
30
 
RE:~
cannot
3Sb
Ene
:Re
Frequency
Black-Start Frequency
regulation
Black-Start
capability: regulation
capability :  Black-Start
 Backup (T&D:  
Frequency
capability
B
Transmission
 ack
(T&D: S:
and a 
regulation
Frequency
capab
B
Transmission ack
Distribution;
Backup 
S~
and y
RE:
 
a regulation
capab Load
Frequency
Backup
Distribution;
Renewable 
~
 : y
Energy).
RE: p
(T&D: 
Following
ov
Renewable
: Best 


regulation
B ack
s on
Transmission

 for thatS
:
: a
Energy). B
and


capaback 
S: a [9,30,55]
y
Distribution; ~ 

capab RE: :  [9,30,55]
y
Renewable B
(T&D:
ack
Frequency
~ : S 
Energy).a 

Transmission regulation
B
capab
(T&D:ack
Frequency ~ S
and ay
Transmission 
B 

regulation
Frequency
capab
Distribution;
(T&D: ack 

[9,30,55]S a
Transmission
and RE:y 
Frequency
capab
Distribution;
Renewable

regulation and: ~[9,30,55]
RE:y
9
:regulation
30
Distribution;
Energy). 55
Renewable
 ~
RE:: 9
[9,30,55]
Energy). 30
Renewable 
55  : 
Energy).
(T&D: 9 
[55,100]
[9,30,55]
30 
55 
~
Transmission  9 30
and 

55~  9
Distribution; 30
 

55
RE:~ Re
smoothing 
Backup provision Best
Backup provision location for Best
that
~ 
location
service; ~:
forService
that
Arbitrage service;
achievable
provision

~:

Service
although
achievable
Best
Backup provision
& load not
location
~andTransmission

the although
optimal
for
levelling

that location;
not
provision Load
service;
the

optimal
~:
Reserves 
Following
Servicelocation;

achievable
cannot
Backup
location

be Service
Best
~
performed
although
location
provision

cannot
Backup
service; 
not

from
for
be
Best
the
that
~:[9,30,55] 
performed
there.
optimal
location
provision
(T&D:
Service service; 
location;
for
Transmission
[55 achievable
99

Best
from
~: that
[9,30,55] 
Service 
location
there.
service;
Backup
and
although
100]


Service 
achievable
for ~: that
provision
Distribution;
not the Load
Service
cannot
Backup
service;
although

achievable
be
: Best
RE:
optimal 
Following
performed
~: 
Service
not
provision
Renewable Load
the
Backup
location; 
although
[9,30,55]
location achievable
optimal
from
:
:for 
Following
there.
not
provision
Energy).
Best
Service
that

location;
the
although
location
service;

cannot
optimal
Best Service
not
[9,30,55]
for~: location
(T&D:
bethatService 

location;
the
performed
service;


cannot
optimal
for
achievable 
that
Service
from
~:

be 
location;
[9,30,55]
Transmission (T&D:service;
performed
Service
there. cannot
and
although

~: 

[55,100]
Service
Transmission
achievablefrom
be
Distribution;  
performed
[9,30,55]
not the

there.
achievable
cannot
and RE:
although
optimal

be
from
not

performed
although
there.
[9,30,55]
Distribution;
Renewable
location;
the optimal

notfrom
: Service
RE:
Energy). the 
there.
optimal
[9,30,55]
Renewable
location;
[9
cannot

: Sb
Ene
3Sb
Load
Backup Following
Reserves Load
provision
Backup Following
provision
Reserves  Backup

(T&D: 

Transmission
provision
Reserves 

(T&D:
Load
Backup Distribution;
Reserves Backup
Following
p ov onand
sLoad 

RE:

Reserves
Distribution;
pRenewable
Following
ov sLoad
on
Frequency 

:
Energy).
RE:
:
Rese (T&D:Renewable
Best
Best 
Following
ves

Transmission
 Reserves
location
Backup


location
regulation
Energy).
for
for that
thatand
p 

Distribution;
service;
ovBackup
s on
service; 

~: 
[55,100]
[9,30,55]
 p ov
(T&D:
~:[9,30,55]
Reserves 
Service
Service

RE: Renewable
on 
sachievable
Transmission

achievable (T&D:
[55,100]
[9,30,55]
[9,30,55] 
LoadEnergy).

Backup
 and

Transmission
although
although 
Following

Reserves
not
p (T&D:
Distribution;
not ov s
Load
the
Backup
the 
and
Transmission
onRE:
optimal Distribution;
p(T&D:
:Following
optimal Best
Reserves 
 
location;
ov
Renewable
 Load
Backup
location; 
[9,30,55]
location on

[9,30,55]
:
sTransmission
and :RE:
: Distribution;
for Renewable

Following
Service
pthat
Energy).
Best 
Service
Reserves ov 
Load


and
cannot
scannot
location on
service; 

RE:
Distribution;
Energy).
9~:
forbe30 Renewable
[55,100]
be
Following (T&D:
that
[9,30,55] 

performed
55service;
Service 
performed

RE:
 Energy).
Transmission

achievable9Renewable

[55,100]
from

from
~: (T&D:
Service
[9,30,55] 
30there.
55

there. 
and Energy).
(T&D:
Transmission

although  9 
[55,100]
Distribution;
achievable
not 30 Transmission
the
[9,30,55] 
and
55

RE:
although
optimal 

not and
9the
Distribution;
Renewable 
30optimal
location;
[9,30,55] 55
 :
RE:
Distribution;
Energy). 9 30
Renewable
Service 

location;RE:

55

cannot
[9,30,55] :Re
Ene

tion  Reserves
Frequency regulation
Frequency
:for
: Best location
regulation
Best location
that
Reserves service;for
~: that
Service
RE
service; ~:Capacity
achievable
Frequency 
Service
although
Reserves
 
achievable

regulation 
the
Frequency
: Bestves
notfirming
although
optimal
Rese 
not
location

the :
&optimal
smoothing

location;
regulation
:
for
Rese

Frequency
Best
that

Service
ves
F 
location;
location
service; :
~:
for
cannot
equency be 
Best
:Service
that 

service;
achievable
cannot
performed
Following
regulation
Load
location
egu
 a on

Frequency
~:be
for
from
Rese that

Service 
performed
although
there.
 
achievable
not
service;
ves
 Rese
regulation
Frequency
from

(T&D:

the
 
~:[9,30,55]
Service
ves

[9,30,55]
Transmission
there.
[9location;
although
optimal  30]
not the
achievable
regulation 
: Rese
and
 :
optimal
although
[9,30,55]

[9,30,55]
Frequency ~
Distribution;
Service
Best

not
 vesthe
location;
cannot :
:
RE:
location
be
optimal

regulation
Frequency Rese Renewable


Service
for
performed
Best
that
location
cannot
ves 
location; :
Energy).
:
service;
from
for
be
[9,30,55]
 Rese

regulation
Frequency 
Best ~
Service
[9,30,55] ves
 

:
~:performed
there.
that
Service
location
service;
cannot

regulation
Best

be
30(T&D:
achievable
from
for
9~: that
[9,30,55] 
Service
there.

Transmission
location

 
55service;
although (T&D:
~:9
achievable
performed
for

not 
Service
from
that30

the
[9,30,55]
and

 
although
55

optimal
service;
there. 
(T&D: Transmission and Distribution; RE: Renewable Energy).
Transmission
Distribution;
achievable
~: not and


9location;
Service

the
30 :
RE:
Distribution;
 
although
[55,100]
Renewable
optimal
55

Service
not
achievablelocation;

the :
RE:
Energy).
30cannot
optimal
9although
55 Service [55
Renewable
 
belocation;
not performed
the
9 30
 [9,30,55]
[9,30,55]
:
9
Ene
cannot
optimal
 55 Sfb
(T&D: Transmission
(T&D: and
Transmission
Distribution;
andRE:
Distribution;
RenewableRE: Energy).
Renewable Energy).
(T&D: Transmission (T&D: andTransmission
Distribution;
(T&D: and
RE:Distribution;
Renewableand
Transmission Energy).
RE:Distribution;
Renewable Energy).
RE: Renewable Energy).(T&D: Transmission(T&D: and
Transmission
Distribution;
(T&D: and
Transmission
RE:
Distribution;
Renewable
(T&D: andRE:
Distribution;
Energy).
Renewable
Transmission RE:
Energy).
Renewable
and Distribution; RE:Ene
Re
Frequency regulation
Frequency regulation 
 Frequency 
 F
regulation
equency
 
egu
 
F equency
a on
 
eguLoad a 
on
:FoBest
ow
F 

equency
 F
ng forFollowing
 
egu
 a 
equencyon
 
[9,30,55]
 egu 
achievable
a on
 
 
[9,30,55]
F equency
 Fegu 
equency
a on
 

Fegu

 a
equency
[9,30,55]
on
: 
egu
 


a on
 55

9be30performed
  9 
55
30there.
    55 100 

 
  9 30 55 
9 30
 [55,100]  
55

ility 
Load Following
Load Following
Load Following
Load Following
 Load Following
Load 
Load Following

Load

Following
PV Self-consumption
~   
Load
location
although
that
o

Load
service; Following
~:[55,100]

Service
 vng 
[55,100]
(T&D:
Load
although


Following
not
Transmission
Load
the

and
Following
optimal

Load

[55,100]
location; Following
Distribution;
Service
 RE:
cannot

[55,100]

Renewable 
[9 30 55] 

Energy).
[55,100]
from
   
[55,100]
 h    
  55 
 [9
: Best location
:for
Best
that
location
service;for
~: that
Service
service;
achievable:Following
~: Service
although notLoad
Bestachievable
location for
the :Fo
although
that
optimal
Best ow
service;
not Load
ng
location
location;
the Fo
::
~: optimal
Service
for Best
thatow
Service ng
achievable
location;
location
service; :
cannot
~:
for Bthat
Service
be Load
onthe
performed
service; :
achievable
cannot
not ~: Fo
obe
from ow
optimal
Service
Best Load
halthough
performed
there.
location:Fo[55,100]
achievable
location;
not
from
forS:
Best
the ow
that
there. ngh cannot
voptimal
although
Service
location
service; v[55,100]
~:bthat
location;
not
for the Load
Service
be hough
:
optimal:
service; Fo
performed no
Service ow
achievable
Best hLoad
location;
~: Service
cannotng
op
:
location
from :mFo
although
there. oow
achievable
beService
for Load
performed
Best
that
not [55,100]
ngoptimal
on
location
cannot :
service;
the
althoughFo
fromS
for
beBest vow
~:performed
there.
that
Service
not ngnno
location;
location
service;
the 55
:
achievable
optimal
from
for
~: 100
bService
pthere.
that
Service
location; d:~:55
o cannot
m
service;
although om
achievable 100
Service
not
be
Service
performed
the
although
cannot
optimal
achievable
from
not
be
location;
performed
the
although
there.
optimalfrom
not 55
: Service 100
location;
the : Service
there.
cannot
optimal 100
belocation; : Sfb
performed
cannot

    onRE BT&D  
: Best location
:for : although  o: on : v  h: TmDistribution;
n cannot
m onbe nd
 DRenewable
bu vonand
RE BRvvh
nobow bdand
ShDistribution; En gy     
on Best
that
location
service;for (T&D:
~: that Transmission
Service
service; ~: (T&D:
achievable
Serviceand
Best
Black-Start
Transmission
Distribution;
achievable
location
not for
(T&D: Transmission
(T&D: and
theandRE:
although
that
optimal
Transmission
Distribution;
capability
BDistribution;
Renewable
service;
not
o
andRE:
(T&D:
location;
the
~:on RE:
Energy).
optimal
Service
Distribution;
Renewable
hRenewable
(T&D:
Transmission
BService
RE:
achievable
location;
Energy).
Renewable
T n m on
Energy).
o vcannot (T&D:
and
oalthough
Energy).
T&D
Distribution;
SService Transmission
behvperformed
cannot
not
vh the
nd DT nbum onT&D nd
R
TD
b(T&D:
from
be RE:and
optimal Renewable
Transmission
SBperformed
vthere.
hough
o
nnwmbbu on
En
Distribution;
on nd
RE
[9 30wT&D
location;
hon
no
v
from
ob
gyDR n bu
Energy).
55]
h and
RE:
there.
op
Service
ohough
bon En
RE
T gy
R
Renewable
von
n mn w
oo (T&D:
no
T&D
on
b TEn
Shon
ndnDgy
m
vopEnergy).
RE:
Transmission
hvB ov(T&D:
performed
vSm Sbofrom
nno
on Transmission
Energy).
on
hough
there.
b op no mhnnovon RE:
bDistribution;
hough
op ommp(T&D:
oB Renewable
Shnoovo hmTransmission
d hRE:
von
op Energy).
omvS(T&D:
om Renewable
Shbhvov and
Transmission
hDistribution;
hough
vonnnoEnergy).
(T&D:
bSb vpvh and
vSno Transmission
RE:
hDistribution;
mdvRenewable
ohough
opm
nno no oph hand
bbom
bu
on RE:
ohough
on onndRE
opm
D RT&D
n
buwT
noom
on
~
Distribution;
Energy).
mdSRenewable
vo h hon
b nRE
En
op
m RT&D
gy
RE:
nnoEnergy).
mSRenewable
nonwTnd
b vop oonm
b nDEn
m T&D
gy
bu
Ene
nno
on on
d Sb
TndRE
nDmR n
buon
won
bndRE
D
En R gy
n
buwon
b RE
En R gy
n w b
[9En3
  
Backup provision   [9 30 55]    [9 3
tion   
Reserves   [9 30 55]    [9 3
g   regulation
Frequency   [55 100]    [9 3
on or ha serv ce ~ Serv ce ach evab e a hough no he op ma oca
Load  Serv ce canno be per ormed rom
on Following here    [55
T&D Transm ss on and D s r bu on RE Renewab e Energy
 Bes oca on or ha serv ce ~ Serv ce ach evab e a hough no he op ma oca on  Serv ce canno be per ormed rom here
T&D Transm ss on and D s r bu on RE Renewab e Energy
Energies 2019, 12, 3954 20 of 27

4. Barriers to Domestic Battery Deployment


In spite of the different advantages presented so far, it is a fact that the penetration of domestic
integrated BESS remains low. This section focuses on the main barriers and challenges that integrated
BESSs are facing: Markets and regulations, financial and economic issues, and technical barriers.
A recurring barrier to integration of domestic BESS and any sort of storage in general is the
unclear or often non-existent definition for electricity storage in most electricity network system
regulations [25,101]. Thus, storage units may be categorised as generation assets although not capable
of generating a net flow of energy [110] making competition with conventional generation challenging.
Additionally, as storage units are both loads and generators, owners are intended to pay twice for the
connection charges [111].
More generally, the integration of domestic BESS achieving a number of services would add
more contractual complexity. Either in the US [9] or in Europe [111], markets may vary a lot, enabling
little harmonization. Each contract is too specific to its context, environment and stakeholder to be
generalised to other situations without substantial enough adaptation, which may reduce motivation
of potential investors [98,111].
The ownership and operation of storage assets is also a concern. For a full utilisation of the potential
of domestic batteries, real-time information of the state of the network is required. The transmission
or distribution network operators are the most likely to possess these information, still they are not
allowed to own and operate storage systems by most regulations [110,111]. Reports such as [9,101]
agree on the benefit that could be drawn by giving—careful, limited and regulated—freedom to
network operators on the control of such assets. Often referred to as the transition from Distribution
Network Operators to Distribution System Operators (or DNOs to DSOs) [98].
According to Ugarte et al. [111], the main challenge to the integration of batteries in the current
context is economic. Capital costs are still high and discourage investors, making it difficult for the
technology to compete with other better-established centralised generation solutions and conventional
grid reinforcements [110]. It is interesting to note that the strictly speaking storage part “only”
represents 30% to 40% of the total cost. The rest consists in all the other components necessary for the
system to operate, which leaves space for cost reductions [112].
Moreover, the capital cost challenge would have a lower impact if more and more effective
remuneration mechanisms [25] or pricing signals [111] were in place. Batteries have been traditionally
used for arbitrage and more and more for renewable self-consumption increase [113], but according to
Castagneto Gissey, Dodds and Radcliffe J [110], and Fitzgerald et al. [9] and others, they could valuably
participate in balancing and ancillary services markets thanks to their potential to provide (ultra)
fast response. Regarding the Capacity Market, BESSs still struggle to be competitive, first due to the
current requirement of 2 MW, therefore requiring the aggregation of enough assets. More importantly,
the mechanism setting no limit to the duration for which the output must be maintained, largely plays
in favour fuel-based generation and against BESS [110].
It should also be noted that even if an effective remuneration mechanism was implemented,
the deployment of domestic BESS that it would bring about may affect it retroactively, for instance
by reducing the value of a given service and then not provide as much value as expected to battery
owners [9]. This also leads to lack of confidence in investments.
A significant challenge when it comes to technical aspects, is the inherent complexity. Transforming
consumers to “prosumers”, adding intermittent, non-dispatchable renewables to the mix means a
highly increased number of sub-systems to manage, and the necessity of an optimal management.
A poor management could indeed lead to increase the stress on the network and be severely harmful
for the nearby infrastructures. For instance, a high number of customers charging and discharging
their battery units during similar periods in response to the same price tariffs, leading to peaks and
troughs at the sub-station. Or, as presented by Moshövel et al. [92] and Marra et al. [90], batteries
used to increase the self-consumption of domestic rooftop PV are used to charge as soon as the PV
panels produce electricity: After a few hours of sunlight the batteries are fully charged but the sun
Energies 2019, 12, 3954 21 of 27

still shines. The electricity produced is not used in the household and suddenly exported to the grid,
typically in the early—or mid-afternoon, leading to sudden peaks at the substation. This is avoided by
increasing the size of the batteries, but it means higher capital investments, which also represents a
barrier to integration as presented above. It is suggested by Marra et al. [90] and Moshövel et al. [92]
that for the same battery size, and while preserving good self-consumption, substantial grid relief can
be achieved by operating the batteries differently. Still, the complexity of implementation, and the fact
that the operation of the batteries (and thus the revenue generated) depends on the quality of forecast
of the production and consumption—as introduced above [92]—increase the uncertainty regarding the
achievability of profitability by the system.
Other sources of technological uncertainty stem from the evolution of the performance of the
systems. Confidence on the progress of the technology could motivate investors but it is never certain
what exact level of efficiency the technology will eventually achieve. Additionally, even if an efficient
development was certain, BESS are not established technologies yet, and implementation phases may
be challenging because of a lack of general know-how [25]: Demonstration projects could alleviate
such risks [111]. As developed earlier, the ageing mechanisms are very complex in batteries and
still not fully understood. Such projects would help understand the evolution of the performance of
installed systems and secure investments [112], reducing the risk of being the first to invest in a yet
unproven technology.

5. Conclusions
The electricity sector is facing growing challenges, coming from two main categories: The normal
ageing of the infrastructures, and the evolution of electricity sector and more generally electricity
consumption and production behaviours—largely motivated by climate change mitigation necessities.
This second category of challenges may involve a drastic change in the management of energy flows
throughout the electricity network and addressing them with conventional grid upgrades may lead to
oversized components, and huge investments to maintain energy security. On the other hand, the
alternative option consisting in adding flexibility to the network is gaining interest, as it would enable
optimal technology installation, operation and investments.
It was shown that storing electricity is the important missing piece in the present flexibility puzzle.
Many different technologies achieving many different types of performance were compared regarding
their role in providing this flexibility to the grid, and it appears that the highest amount of value can be
achieved by installing batteries (electrochemical ES) behind the meter of consumers. Furthermore,
electrochemical energy storage units could be operated to provide benefit to its owner, as well as to the
grid, by re-shaping the apparent electricity consumption profile as seen from the electricity network.
The role could be key in the transition of consumers into “prosumers”, who are willing to introduce
photovoltaic (PV) rooftop panels, Electric Vehicles (EVs), Heat Pumps (HP), or simply have a better
control on their energy consumption.
The commercialisation of such systems has already started, mostly as an upgrade to rooftop PV.
These technologies, their performance, and the numerical models used for their development were
examined and compared. Still, the deployment remains low and does not enable the full expected
potential yet. The reasons for this are based on market, regulatory, financial, economic, and technical
concerns and were developed in the last section.
The paper shows that domestic integrated battery energy storage systems are a very strong
candidate to address the challenges faced by the electricity sector. The relevant technology is now
emerging and there is still room for performance improvement and decrease in costs. However,
investments that could lead to a large deployment are held back by a number of barriers and challenges
acting as a vicious circle. The present small number of installed batteries leads to a lack of regulation
effort, as not enough systems are present in the network, which makes market regulations and
competition unfavourable to domestic BESS. The situation brings about higher risks in investments,
therefore only a small number of systems are installed every year, leading to the small fleet growing
Energies 2019, 12, 3954 22 of 27

too slowly to make regulation efforts worthy. Additionally, the lack of real-world data due to the small
amount of installed systems sustains the unfair market and competitions context and the reluctance to
Energies 2019,Figure
investment. 12, x FOR PEER REVIEW
8 illustrates this self-sustained inhibition process. 27 of 32

Small fleet

Too slow fleet Lack of


Lack of real-
increase regulation
world data

Risky investments Unfair market &


competition

Figure 8. Illustration of the vicious circle in domestic battery implementation.

Now that there is evidence concerning the potential added value of behind-the-meter BESS, a great
step forward would Figurebe8. to
Illustration
demonstrateof thequantitatively
vicious circle inthedomestic
benefitsbattery implementation.
of such a solution. Still, as real-world
implementations are expensive and risky—due to the high complexity of implementing such new
Now thatand
systems there is evidence
operating concerning
them the potential
properly—and may onlyadded value
take of behind-the-meter
place BESS, a great
once the trustworthiness of thestep
forward would
solution be to
is more demonstrate
clearly quantitatively
demonstrated. In the nearthe benefits
future, ofshould
efforts such bea solution. Still, asaccurate
made to generate real-world
implementations
and valid models that are able to provide reliable quantitative results regarding the technical viabilityand
are expensive and risky—due to the high complexity of implementing such new systems
operating
of thethem properly—and
solution. From these may only
results, take place
decisions once the
regarding fortrustworthiness
instance regulationof the solution is more
or investments couldclearly
be
demonstrated. In the near future, efforts should be made to generate accurate and
made in order to unlock the barriers to deployment and thus releasing all the potential achievable valid models that are able
to provide
without reliable quantitative
compromising results regarding
the operation the technical
of the electricity network.viability of the the
As a result, solution.
lack ofFrom these results,
data leading to
decisions
difficulties in competition and reluctance in investment (see Figure 8) could be by-passed by providing to
regarding for instance regulation or investments could be made in order to unlock the barriers
deployment and that
information thuswould
releasing all the
reverse the competition
potential achievable
and investmentwithout compromising
balance in favour ofthe operation
domestic of the
BESS.
electricity network. As a result, the lack of data leading to difficulties in competition and reluctance in
investment
Author(see Figure 8) could
Contributions: be by-passed
Writing—draft by providing
and editing, information
C.J.; Reviewing, editingthat
andwould reverse
supervision, A.Z.;theReviewing,
competition
editing and supervision,
and investment C.B.; Reviewing,
balance in favour of domesticediting and supervision, P.K.; Reviewing, P.M.; Funding acquisition and
BESS.
reviewing, N.H.
Funding:
Author This research
Contributions: and the APC
Writing—draft were funded
and editing, by the European
C.J.; Reviewing, editingUnion’s INTERREG
and supervision, VAReviewing,
A.Z.; Programme, grant and
editing
numberC.B.;
supervision, IVA5038.
Reviewing, editing and supervision, P.K.; Reviewing, P.M.; Funding acquisition and reviewing, N.H.
Acknowledgments: This work was conducted under the SPIRE 2 project, which is supported by the European
Acknowledgements:
Union’s INTERREG This VA
work was conducted
Programme, managedunder
bythethe SPIRE
Special2 EU
project, which isBody
Programmes supported by the European Union’s
(SEUPB).
INTERREG VA Programme, managed by the Special EU Programmes Body (SEUPB).
Conflicts of Interest: The authors declare no conflict of interest.
Funding: This research and the APC were funded by the European Union’s INTERREG VA Programme, grant number
IVA5038.
References
Conflicts
1. ofSpiecker,
Interest:S.;The authors
Weber, declare
C. The futurenoofconflict of interest.
the european electricity system and the impact of fluctuating renewable
energy—A scenario analysis. Energy Policy 2014, 65, 185–197. [CrossRef]
References
2. Allan, G.; Eromenko, I.; Gilmartin, M.; Kockar, I.; McGregor, P. The economics of distributed energy
1. generation:
Spiecker, S.; Weber,A C.literature
The future of theRenew.
review. european Sustain. Energysystem
electricity Rev. 2015, 42, 543–556.
and the impact of[CrossRef]
fluctuating renewable energy—
3. Ekanayake, J.; Liyanage, K.; Wu, J.; Yokoyama,
A scenario analysis. Energy Policy 2014, 65, 185–197. A.; Jenkins, N. SMART GRID—Technology and Applications;
2. Allan,Wiley: Hoboken,I.;NY,
G.; Eromenko, USA, 2012;
Gilmartin, M.; ISBN
Kockar,9780470974094.
I.; McGregor, P. The economics of distributed energy generation: A
4. Brown, M.H.; Sedano, R.P. Electricity Transmission:
literature review. Renew. Sustain. Energy Rev. 2015, 42, 543–556. A Primer; Natl Conference of State: Denver, CO, USA,
2004; ISBN 1580243525.
3. Ekanayake, J.; Liyanage, K.; Wu, J.; Yokoyama, A.; Jenkins, N. SMART GRID—Technology and Applications; Wiley:
Hoboken, NY, USA, 2012; ISBN 9780470974094.
4. Brown, M.H.; Sedano, R.P. Electricity Transmission: A Primer; Natl Conference of State: Denver, CO, USA, 2004; ISBN
1580243525.
5. Elombo, A.I.; Morstyn, T.; Apostolopoulou, D.; McCulloch, M.D. Residential load variability and diversity at different
sampling time and aggregation scales. In Proceedings of the 2017 IEEE AFRICON, Cape Town, South Africa, 8–20
September 2017; pp. 1331–1336.
Energies 2019, 12, 3954 23 of 27

5. Elombo, A.I.; Morstyn, T.; Apostolopoulou, D.; McCulloch, M.D. Residential load variability and diversity at
different sampling time and aggregation scales. In Proceedings of the 2017 IEEE AFRICON, Cape Town,
South Africa, 8–20 September 2017; pp. 1331–1336.
6. Shah, N.N.; Wilson, C.; Huang, M.J.; Hewitt, N.J. Analysis on field trial of high temperature heat pump
integrated with thermal energy storage in domestic retrofit installation. Appl. Therm. Eng. 2018, 143, 650–659.
[CrossRef]
7. EirGrid Group plc—Smart Grid Dashboard n.d. Available online: http://smartgriddashboard.eirgrid.com/
#ni/demand (accessed on 24 April 2018).
8. Mcdonald, J.D.; Wojszczyk, B.; Flynn, B.; Voloh, I. Distribution Systems, Substations, and Integration of
Ditributed Generation. In Encyclopedia of Sustainability Science and Technology; Springer: Berlin/Heidelberg,
Germany, 2012; pp. 7–68. ISBN 978-0-387-89469-0.
9. Fitzgerald, G.; Mandel, J.; Morris, J.; Touati, H. The Economics of Battery Energy Storage: How Multi-Use,
Customer-Sited Batteries Deliver the Most Services and Value to Customers and the Grid; Rocky Mountain Institute:
Boulder, CO, USA, 2015.
10. European Environment Agency. Air Quality in Europe—2017 Report; European Environment Agency:
København, Denmark, 2017; ISBN 978-92-9213-489-1.
11. Bertoldi, P.; López Lorente, J.; Labanca, N. Energy Consumption and Energy Efficiency Trends in the EU-28
2000–2014; EUR 27972 EN; Publications Office of the European Union: Luxembourg, Luxembourg, 2016;
ISBN 9789279593604.
12. Chaudry, M.; Abeysekera, M.; Reza Hosseini, S.H.; Wu, J.; Jenkins, N. UKERC Energy Strategy under
Uncertainties; UK Energy Research Center: London, UK, 2014.
13. Smith, B.D. Heat Electrification and Sub-Daily Demand Profiles: A Comparison of Great Britain and
Norway—Energy Storage Hub n.d. Available online: http://energystoragehub.org/energy-storage-
applications/grid-scale/heat-electrification-and-sub-daily-demand-profiles-a-comparison-of-great-
britain-and-norway/ (accessed on 21 January 2019).
14. Pimm, A.J.; Cockerill, T.T.; Taylor, P.G. The potential for peak shaving on low voltage distribution networks
using electricity storage. J. Energy Storage 2018, 16, 231–242. [CrossRef]
15. Jenkins, N.; Long, C.; Wu, J. An Overview of the Smart Grid in Great Britain. Engineering 2015, 1, 413–421.
[CrossRef]
16. Eyer, J. Electric Utility Transmission and Distribution Upgrade Deferral Benefits from Modular Electricity Storage;
Sandia National Laboratories: Albuquerque, New Mexico; Livermore, CA, USA, 2009.
17. Deeba, S.R.; Sharma, R.; Saha, T.K.; Chakraborty, D.; Thomas, A. Evaluation of technical and financial
benefits of battery-based energy storage systems in distribution networks. IET Renew. Power Gener. 2016, 10,
1149–1160. [CrossRef]
18. Amirante, R.; Cassone, E.; Distaso, E.; Tamburrano, P. Overview on recent developments in energy storage:
Mechanical, electrochemical and hydrogen technologies. Energy Convers. Manag. 2017, 132, 372–387.
[CrossRef]
19. Akinyele, D.O.; Rayudu, R.K. Review of energy storage technologies for sustainable power networks. Sustain.
Energy Technol. Assess. 2014. [CrossRef]
20. Beardsall, J.C.; Gould, C.A.; Al-Tai, M. Energy Storage Systems: A Review of the Technology and Its
Application in Power Systems. Power Eng. 2015. [CrossRef]
21. Koohi-Kamali, S.; Tyagi, V.V.; Rahim, N.A.; Panwar, N.L.; Mokhlis, H. Emergence of energy storage
technologies as the solution for reliable operation of smart power systems: A review. Renew. Sustain. Energy
Rev. 2013. [CrossRef]
22. Lund, P.D.; Lindgren, J.; Mikkola, J.; Salpakari, J. Review of energy system flexibility measures to enable high
levels of variable renewable electricity. Renew. Sustain. Energy Rev. 2015, 45, 785–807. [CrossRef]
23. Yekini Suberu, M.; Wazir Mustafa, M.; Bashir, N. Energy storage systems for renewable energy power sector
integration and mitigation of intermittency. Renew. Sustain. Energy Rev. 2014, 35, 499–514. [CrossRef]
24. Guney, M.S.; Tepe, Y. Classification and assessment of energy storage systems. Renew. Sustain. Energy Rev.
2017. [CrossRef]
25. Hull, R.; Jones, A. Development of Decentralised Energy and Storage Systems in the UK; A Report for the
Renewable Energy Association; KPMG: Amstelveen, The Netherlands, 2016.
26. World Energy Council World Energy Resources—E-Storage. World Energy Counc. Rep. 2016, 1, 468.
Energies 2019, 12, 3954 24 of 27

27. Aichhorn, A.; Greenleaf, M.; Li, H.; Zheng, J. A cost effective battery sizing strategy based on a detailed
battery lifetime model and an economic energy management strategy. IEEE Power Energy Soc. Gen. Meet.
2012, 1–8. [CrossRef]
28. Das, C.K.; Bass, O.; Kothapalli, G.; Mahmoud, T.S.; Habibi, D. Overview of energy storage systems in
distribution networks: Placement, sizing, operation, and power quality. Renew. Sustain. Energy Rev. 2018.
[CrossRef]
29. Johnson, R.C.; Mayfield, M.; Beck, S.B.M. Optimal placement, sizing, and dispatch of multiple BES systems
on UK low voltage residential networks. J. Energy Storage 2018, 17, 272–286. [CrossRef]
30. Müller, M.; If, T.D.; Viernstein, L.; Nam, C.; Eiting, A.; Hesse, H.C.; Witzmann, R.; Jossen, A. Evaluation of
grid-level adaptability for stationary battery energy storage system applications in Europe. J. Energy Storage
2017, 9, 1–11. [CrossRef]
31. Hoppmann, J.; Volland, J.; Schmidt, T.S.; Hoffmann, V.H. The economic viability of battery storage for
residential solar photovoltaic systems—A review and a simulation model. Renew. Sustain. Energy Rev. 2014.
[CrossRef]
32. Khalilpour, R.; Vassallo, A. Planning and operation scheduling of PV-battery systems: A novel methodology.
Renew. Sustain. Energy Rev. 2016, 53, 194–208. [CrossRef]
33. Linden, D.; Reddy, T.B. (Eds.) Handbook of Batteries, 3rd ed.; McGraw-Hill: Blackclick, OH, USA, 2002; ISBN
0071359788. [CrossRef]
34. Buchmann, I. BU-908: Battery Management System (BMS)—Battery University n.d. Available online:
https://batteryuniversity.com/learn/article/how_to_monitor_a_battery (accessed on 8 October 2019).
35. Battery IInformation Table of Contents, Basic to Advanced n.d. Available online: http://batteryuniversity.
com/learn/ (accessed on 4 December 2017).
36. Chen, H.; Cong, T.N.; Yang, W.; Tan, C.; Li, Y.; Ding, Y. Progress in electrical energy storage system: A critical
review. Prog. Nat. Sci. 2009, 19, 291–312. [CrossRef]
37. Kularatna, N. ENERGY STORAGE DEVICES FOR ELECTRONIC SYSTEMS—Rechargeable Batteries and
Supercapacitors; Hayton, J., Ed.; Elsevier: Amsterdam, The Netherlands, 2015.
38. Isidor Buchmann. How does the Lead Acid Battery Work? Battery University, 2018. Available online:
https://batteryuniversity.com/learn/article/lead_based_batteries (accessed on 15 August 2018).
39. Buchmann, I. Nickel-based Batteries—Battery University. 2018. Available online: http://batteryuniversity.
com/learn/article/nickel_based_batteries (accessed on 29 June 2018).
40. Buchmann, I. Types of Lithium-Ion Batteries—Battery University. 2018. Available online: http:
//batteryuniversity.com/learn/article/types_of_lithium_ion (accessed on 3 July 2018).
41. Garg, B. Introduction to Flow Batteries: Theory and Applications. 2011. Available online: http://large.
stanford.edu/courses/2011/ph240/garg1/ (accessed on 4 July 2018).
42. Scrosati, B. History of lithium batteries. J. Solid State Electrochem. 2011, 15, 1623–1630. [CrossRef]
43. Kabir, M.M.; Demirocak, D.E.; Dotterweich, F.H. Degradation mechanisms in Li-ion batteries: A state-of-
the-art review. Int. J. Energy Res. 2017, 41, 1963–1986. [CrossRef]
44. Isidor Buchmann. Capacity Loss and Discovering What Causes a Battery to Fade—Battery University. 2016.
Available online: http://batteryuniversity.com/learn/article/capacity_loss (accessed on 28 June 2018).
45. Vetter, J.; Novák, P.; Wagner, M.R.; Veit, C.; Möller, K.C.; Besenhard, J.O.; Winter, M.; Wohlfahrt-Mehrens, M.;
Vogler, C.; Hammouche, A. Ageing mechanisms in lithium-ion batteries. J. Power Sources 2005, 147, 269–281.
[CrossRef]
46. Rao, Z.; Wang, S. A review of power battery thermal energy management. Renew. Sustain. Energy Rev. 2011,
15, 4554–4571. [CrossRef]
47. Al-Zareer, M.; Dincer, I.; Rosen, M.A. A review of novel thermal management systems for batteries. Int. J.
Energy Res. 2018, 1–24. [CrossRef]
48. Wankmüller, F.; Thimmapuram, P.R.; Gallagher, K.G.; Botterud, A. Impact of battery degradation on energy
arbitrage revenue of grid-level energy storage. J. Energy Storage 2017, 10, 56–66. [CrossRef]
49. Reniers, J.M.; Mulder, G.; Ober-Blöbaum, S.; Howey, D.A. Improving optimal control of grid-connected
lithium-ion batteries through more accurate battery and degradation modelling. J. Power Sources 2018, 379,
91–102. [CrossRef]
50. Rappaport, R.D.; Miles, J. Cloud energy storage for grid scale applications in the UK. Energy Policy 2017, 109,
609–622. [CrossRef]
Energies 2019, 12, 3954 25 of 27

51. Staffell, I.; Rustomji, M. Maximising the value of electricity storage. J. Energy Storage 2016, 8, 212–225.
[CrossRef]
52. BEIS; Ofgem. Upgrading Our Energy System—Smart Systems and Flexibility Plan; Ofgem: London, UK, 2017;
pp. 1–32.
53. Neubauer, J.; Simpson, M. Deployment of Behind-The-Meter Energy Storage for Demand Charge Reduction;
Technical Report NREL/TP-5400-63162; National Renewable Energy Laboratory: Golden, CO, USA, 2015;
p. 30.
54. Muenzel, V.; Mareels, I.; De Hoog, J.; Vishwanath, A.; Kalyanaraman, S.; Gort, A. PV generation and demand
mismatch: Evaluating the potential of residential storage. In Proceedings of the 2015 IEEE Power & Energy
Society Innovative Smart Grid Technologies Conference (ISGT), Washington, DC, USA, 18–20 February 2015.
55. Günter, N.; Marinopoulos, A. Energy storage for grid services and applications: Classification, market review,
metrics, and methodology for evaluation of deployment cases. J. Energy Storage 2016, 8, 226–234. [CrossRef]
56. Svarc, J. Complete Solar Battery Review—Clean Energy Reviews. 2018. Available online: https://www.
cleanenergyreviews.info/blog/2015/11/19/complete-battery-storage-comparison-and-review (accessed on
8 June 2018).
57. Powerwall 2 AC Specifications n.d. Available online: https://www.energymatters.com.au/wp-content/
uploads/2016/11/tesla-powerwall-2-datasheet.pdf (accessed on 9 October 2019).
58. Powerwall 2 Full Specs Reveal Cheap Storage And Limited Warranty n.d. Available online: https:
//www.solarquotes.com.au/blog/powerwall-2-warranty/ (accessed on 9 October 2019).
59. Lg Chem Resu Datasheet n.d.:1–2. Available online: https://solarclarity.nl/wp-content/uploads/2018/07/LG-
Chem-RESU-13.pdf (accessed on 9 October 2019).
60. Svarc, J. Lithium Vs Lead-Acid Batteries—Clean Energy Reviews. 2019. Available online:
https://www.cleanenergyreviews.info/blog/simpliphi-pylontech-narada-bae-lead-acid-battery (accessed on
9 October 2019).
61. SIMPLIPHI PHI Datasheet. 2018. Available online: https://simpliphipower.com/documentation/phi-3-5/
simpliphi-power-phi-3-5-kwh-60-amp-specification-sheet.pdf (accessed on 9 October 2019).
62. Svarc, J. Sonnen Battery Review—Clean Energy Reviews. 2018. Available online: https://www.
cleanenergyreviews.info/blog/sonnen-battery-review (accessed on 9 October 2019).
63. sonnenBatterie. Technical Data sonnenBatterie. 2019, 2–3. Available online: https://sonnenbatterie.de/sites/
default/files/161018_datasheet_sonnenbatterie.pdf (accessed on 9 October 2019).
64. Muoio, D. 10 Home Batteries Competing with Tesla Powerwall 2—Business Insider. 2017. Available
online: http://uk.businessinsider.com/rechargeable-battery-options-compete-tesla-2017-5?r=US&IR=T/
#8-powervault-is-an-at-home-battery-system-that-is-sold-in-the-uk-all-units-come-with-an-inverter-
included-and-the-most-powerful-model-stores-6-kwh-of-energy-prices- (accessed on 12 January 2018).
65. Relectrify n.d. Available online: https://www.relectrify.com/ (accessed on 5 July 2018).
66. Cunningham, W. For Dead EV Batteries, Reuse comes before Recycle. CNET Road Show. 2017. Available
online: https://www.cnet.com/roadshow/news/for-dead-ev-batteries-reuse-comes-before-recycle/ (accessed
on 5 July 2018).
67. Chris Robinson. Recycle vs Reuse: Why EV Batteries May not Often Get a Second-Life as Stationary Storage
Systems. Energy Storage News. 2017. Available online: https://www.energy-storage.news/blogs/recycle-vs-
reuse-why-ev-batteries-may-not-often-get-a-second-life-as-statio (accessed on 5 July 2018).
68. Seaman, A.; Dao, T.S.; McPhee, J. A survey of mathematics-based equivalent-circuit and electrochemical
battery models for hybrid and electric vehicle simulation. J. Power Sources 2014, 256, 410–423. [CrossRef]
69. Simpkins, T.; Donnell, C.O. Optimizing Battery Sizing and Dispatching To Maximize Economic Return.
In Proceedings of the Battcon 2017 International Stationary Battery Conference, At Orlando, FL, USA,
8–10 May 2017.
70. Gao, L.; Liu, S.; Dougal, R.A. Dynamic lithium-ion battery model for system simulation. IEEE Trans.
Components Packag. Technol. 2002, 25, 495–505.
71. Newman, J.; Tiedemann, W. Porous-electrode theory with battery applications. AIChE J. 1975, 21, 25–41.
[CrossRef]
72. Banerjee, B.; Jayaweera, D.; Islam, S. Modelling and Simulation of Power Systems. In Smart Power
Systems and Renewable Energy System Integration; Springer: Berlin/Heidelberg, Germany, 2016; pp. 15–29.
ISBN 978-3-319-30425-0.
Energies 2019, 12, 3954 26 of 27

73. Andersson, G. Modelling and Analysis of Electric Power Systems; EEH—Power Systems Laboratory: Zurich,
Switzerland, 2008.
74. Hay, S.; Ferguson, A. A Review of Power System Modelling Platforms and Capabilities; IET Special Interest
Publication for the Council for Science and Technology; IET: London, UK, 2015; pp. 3–13.
75. Meneses de Quevedo, P.; Contreras, J. Optimal Placement of Energy Storage and Wind Power under
Uncertainty. Energies 2016, 9, 528. [CrossRef]
76. Sidhu, A.S.; Pollitt, M.G.; Anaya, K.L. A social cost benefit analysis of grid-scale electrical energy storage
projects: A case study. Appl. Energy 2018, 212, 881–894. [CrossRef]
77. Patsios, C.; Wu, B.; Chatzinikolaou, E.; Rogers, D.J.; Wade, N.; Brandon, N.P.; Taylor, P. An integrated
approach for the analysis and control of grid connected energy storage systems. J. Energy Storage 2016, 5,
48–61. [CrossRef]
78. Ru, Y.; Kleissl, J.; Martinez, S. Storage size determination for grid-connected photovoltaic systems. IEEE
Trans. Sustain. Energy 2013, 4, 68–81. [CrossRef]
79. Weniger, J.; Tjaden, T.; Quaschning, V. Sizing of residential PV battery systems. Energy Procedia 2014, 46,
78–87. [CrossRef]
80. Sani Hassan, A.; Cipcigan, L.; Jenkins, N. Optimal battery storage operation for PV systems with tariff
incentives. Appl. Energy 2017, 203, 422–441. [CrossRef]
81. Pena-Bello, A.; Burer, M.; Patel, M.K.; Parra, D. Optimizing PV and grid charging in combined applications
to improve the profitability of residential batteries. J. Energy Storage 2017, 13, 58–72. [CrossRef]
82. Nottrott, A.; Kleissl, J.; Washom, B. Energy dispatch schedule optimization and cost benefit analysis for
grid-connected, photovoltaic-battery storage systems. Renew. Energy 2013, 55, 230–240. [CrossRef]
83. Angenendt, G.; Zurmühlen, S.; Mir-Montazeri, R.; Magnor, D.; Sauer, D.U. Enhancing Battery Lifetime in PV
Battery Home Storage System Using Forecast Based Operating Strategies. Energy Procedia 2016, 99, 80–88.
[CrossRef]
84. Yoon, Y.; Kim, Y.H. Effective scheduling of residential energy storage systems under dynamic pricing. Renew.
Energy 2016, 87, 936–945. [CrossRef]
85. Babacan, O.; Ratnam, E.L.; Disfani, V.R.; Kleissl, J. Distributed energy storage system scheduling considering
tariff structure, energy arbitrage and solar PV penetration. Appl. Energy 2017, 1384–1393. [CrossRef]
86. Yang, Y.; Li, H.; Aichhorn, A.; Zheng, J.; Greenleaf, M. Sizing strategy of distributed battery storage system
with high penetration of photovoltaic for voltage regulation and peak load shaving. IEEE Trans. Smart Grid
2014, 5, 982–991. [CrossRef]
87. Zillmann, M.; Yan, R.; Saha, T.K. Regulation of distribution network voltage using dispersed battery storage
systems: A case study of a rural network. In Proceedings of the 2011 IEEE Power and Energy Society General
Meeting, Detroit, MI, USA, 24–28 July 2011; pp. 1–8. [CrossRef]
88. Nazaripouya, H.; Wang, Y.; Chu, P.; Pota, H.R.; Members, R.G. Optimal Sizing and Placement of Battery
Energy Storage in Distribution System Based on Solar Size for Voltage Regulation. In Proceedings of the
2015 IEEE Power & Energy Society General Meeting, Denver, CO, USA, 26–30 July 2015. [CrossRef]
89. Lindstens, J. Study of a Battery Energy Storage System in a Weak Distribution Grid Distribution Grid. Master
Thesis, UPPSALA UNIVERSITET, Uppsala, Sweden, 2017.
90. Marra, F.; Yang, G.; Træholt, C.; Østergaard, J.; Larsen, E. A decentralized storage strategy for residential
feeders with photovoltaics. IEEE Trans. Smart Grid 2014, 5, 974–981. [CrossRef]
91. Zeh, A.; Witzmann, R. Operational strategies for battery storage systems in low-voltage distribution grids to
limit the feed-in power of roof-mounted solar power systems. Energy Procedia 2014, 46, 114–123. [CrossRef]
92. Moshövel, J.; Kairies, K.P.; Magnor, D.; Leuthold, M.; Bost, M.; Gährs, S.; Szczechowicz, E.; Cramer, M.;
Sauer, D.U. Analysis of the maximal possible grid relief from PV-peak-power impacts by using storage
systems for increased self-consumption. Appl. Energy 2015, 137, 567–575. [CrossRef]
93. Liu, J.; Zhang, N.; Kang, C.; Kirschen, D.; Xia, Q. Cloud energy storage for residential and small commercial
consumers: A business case study. Appl. Energy 2017, 188, 226–236. [CrossRef]
94. Sonnen, Storage and VPPs. Grey Cells Energy n.d. Available online: https://greycellsenergy.com/examples/
sonnens-community-aggregating-domestic-battery-storage/ (accessed on 12 July 2018).
95. Williams, D. The Vanguard of Decentralized Energy for Sonnen—Decentralized Energy. 2018. Available
online: https://www.decentralized-energy.com/articles/2018/05/the-vanguard-of-decentralized-energy-for-
sonnen.html (accessed on 12 July 2018).
Energies 2019, 12, 3954 27 of 27

96. Dale, M.; Hey, R.; Turvey, N.; Swift, P. Project Sola BRISTOL—Closedown Report; University of Bristol: Bristol,
UK, 2016.
97. Northern Powergrid. Innovation Projects—Distributed Storage & Solar Study (NIA_NPG_011) n.d. Available
online: https://www.northernpowergrid.com/innovation/projects/distributed-storage-solar-study-nia-npg-
011 (accessed on 13 July 2018).
98. Puckup, D.; Greene, L.; Dunlop, S.; Barwell, P. Solar + Storage = Opportunities − Solar Trade Association Position
Paper on Energy Storage; Solar Trade Association: London, UK, 2016.
99. Teller, O.; Nicolai, J.-P.; Lafoz, M.; Laing, D.; Tamme, R.; Pedersen, A.S.; Andersson, M.; Folke, C.; Bourdil, C.;
Conte, G.; et al. Joint EASE/EERA Recommendations for a European Energy Storage Technology Development
Roadmap Towards 2030; Joint European Association for Storage of Energy (EASE); European Energy Research
Alliance (EERA): Brussels, Belgium, 2013; Available online: https://www.eera-set.eu/wp-content/uploads/
148885-EASE-recommendations-Roadmap-04.pdf (accessed on 12 September 2019).
100. Palizban, O.; Kauhaniemi, K. Energy storage systems in modern grids—Matrix of technologies and
applications. J. Energy Storage 2016, 6, 248–259. [CrossRef]
101. Becker, B.; Bardají, M.E.G.; Durand, J.-M.; Clerens, P.; Noe, M. European Energy Storage Technology
Development Roadmap—2017 Update; Joint European Association for Storage of Energy (EASE) and
European Energy Research Alliance (EERA); 2017. Available online: https://eera-es.eu/wp-content/uploads/
2016/03/EASE-EERA-Storage-Technology-Development-Roadmap-2017-HR.pdf (accessed on 12 September
2019).
102. Bray, R.; Woodman, B.; Connor, P. Policy and Regulatory Barriers to Local Energy Markets in Great Britain;
University of Exeter: Exeter, UK, 2018; pp. 1–103.
103. Katsanevakis, M.; Stewart, R.A.; Lu, J. Aggregated applications and benefits of energy storage systems with
application-specific control methods: A review. Renew. Sustain. Energy Rev. 2017, 75, 719–741. [CrossRef]
104. Hesse, H.C.; Schimpe, M.; Kucevic, D.; Jossen, A. Lithium-ion battery storage for the grid—A review of
stationary battery storage system design tailored for applications in modern power grids. Energies 2017, 10,
2107. [CrossRef]
105. Torrealba, P.J.R. The Benefits of Pumped Storage Hydro to the UK; Scottish Renewables: Glasgow, UK, 2016;
pp. 1–49.
106. Mahlia, T.M.I.; Saktisahdan, T.J.; Jannifar, A.; Hasan, M.H.; Matseelar, H.S.C. A review of available methods
and development on energy storage; Technology update. Renew. Sustain. Energy Rev. 2014, 33, 532–545.
[CrossRef]
107. Eames, P.; Loveday, D.; Haines, V.; Romanos, P. The Future Role of Thermal Energy Storage in the UK Energy
System: An Assessment of the Technical Feasibility and Factors Influencing Adoption; Research Report; UKERC:
London, UK, 2014.
108. Zhou, D.; Zhao, C.Y.; Tian, Y.; Lott, M.C.; Kim, S.-I.; Eames, P.; Loveday, D.; Haines, V.; Romanos, P. Thermal
Energy Storage—Technology Brief ; IRENA: Abu Dhabi, UAE, 2013; p. 92.
109. Dutta, S. A review on production, storage of hydrogen and its utilization as an energy resource. J. Ind. Eng.
Chem. 2014, 20, 1148–1156. [CrossRef]
110. Castagneto Gissey, G.; Dodds, P.E.; Radcliffe, J. Market and regulatory barriers to electrical energy storage
innovation. Renew. Sustain. Energy Rev. 2018, 82, 781–790. [CrossRef]
111. Ugarte, S.; Larkin, J.; van der Ree, B.; Voogt, M.; Friedrichsen, N.; Michaelis, J.; Thielmann, A.; Wietschel, M.;
Villafafila, R. Energy Storage: Which Market Design and Regulatory Incenctives Are Needed? European Parliament
Committee on Industry, Research and Energy: Brussels, Belgium, 2015; pp. 1–5.
112. Gyuk, I.; Johnson, M.; Vetrano, J.; Lynn, K.; Parks, W.; Handa, R.; Kannberg, L.D.; Hearne, S.; Waldrip, K.;
Braccio, R.; et al. Grid Energy Storage; U.S. Department of Energy: Washington, DC, USA, 2013; p. 67.
113. Zame, K.K.; Brehm, C.A.; Nitica, A.T.; Richard, C.L.; Schweitzer, G.D. Smart grid and energy storage: Policy
recommendations. Renew. Sustain. Energy Rev. 2018, 82, 1646–1654. [CrossRef]

© 2019 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access
article distributed under the terms and conditions of the Creative Commons Attribution
(CC BY) license (http://creativecommons.org/licenses/by/4.0/).

You might also like