RFI Summary

BORDER RAOD ORGANIZATION (BRO)

NAME OF THE PROJECT :- Rehabilitation & up-gradation of Rishikesh- Dharasu Road (nh-94) with 2-lane paved shoulder from Design chainage Km. 58.608 To Km (Existing
chainage KM. 59.420 to 59.650) from Design chainage Km. 61.630 to Km. 62.950 (Existing chainage Km. 62.630 to 65.000) and New construction qf-2 lane with paced shoulders
chamba Bypass of design length 2.035 km. including 440m Long tunnel on EPC mode under improvement to NH connectivity to Chardham in the state of uttarakhand.

Client : BORDER ROAD ORGANIZAION (BRO)


AUTHORITY ENGINEER : ARKITECHNO (I) PVT. LTD.
CONTRACTOR : M/S BHARAT CONSTRUCTION
Date of Date of
SN TIME Description of Work From To SIDE Status Remarks
Submission Inspection
Highway
1 12/10/2019 12/11/2019 10:00 AM laying of G.S.B. Layer for highway 62+570 62+735 L.H.S
2 12/10/2019 12/11/2019 12:00 PM Breast Wall , 3rd lift 1:4 58+600 58+620 R.H.S
3 12/10/2019 12/11/2019 10:00 AM Breast Wall , 2nd lift 1:4 1+610 1+630 L.H.S
Structure

Tunnel (NORTH PORTAL )

1 12/10/2019 12/11/2019 12:00 PM Excavation 1303 to 1304 HEADING


2 12/11/2019 2:00 PM Rib Erection 1304 to 1304 HEADING
Tunnel (SOUTH PORTAL )
1 12/10/2019 12/11/2019 1:00 PM Rib Erection 1043.18 to 1044.68 RD 52.68 to 54.18
2 12/10/2019 12/11/2019 3:00 PM Backfilling 1043.18 to 1044.68 RD 52.68 to 54.18
Material (LAB)
1 12/10/2019 12/11/2019 Checking Gradation & Testing of (10 mm, 20mm, sand,
10:00 AM
AIV, FI,)

12:00 AM