CONSTRUCTION ESTIMATE CALCULATOR

(BY HC GROUP-SIPIL DIVISION)


(JUST INPUT THE DATA INSIDE THE YELLOW CELL)
ITEM - I CONCRETING WORKS
A. DETERMINING THE VOLUME OF A CONCRETE
FOOTING FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length L (M) 0.70 M
Enter Width W (M) 0.70 M
Enter Thickness T (M) 1.00 M
W T
TOTAL VOLUME OF CONCRETE: 0.49 CU.M.
Number of Footing Units 6.00 Units
TOTAL VOLUME OF CONCRETE: 2.94 CU.M.
# OF CEMENT BAGS 27.00 BAGS
VOL. OF SAND CU.M. 1.50 CU.M.
L
VOL. OF 3/4" GRAVEL CU.M. 3.00 CU.M.
WALL FOOTING

T
L = LENGTH
W
FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length LT (M) 3.50 M
Enter Width W (M) 3.50 M
Enter Thickness T (M) 0.20 M
TOTAL VOLUME OF CONCRETE: 2.45 CU.M.
# OF CEMENT BAGS 23.00 BAGS
VOL. OF SAND CU.M. 1.30 CU.M.
LT = TOTAL LENGTH/PERIMETER VOL. OF 3/4" GRAVEL CU.M. 2.50 CU.M.

BASED ON HC GROUP INDONESIA - SIMPLIFIED CONSTRUCTION ESTIMATE HANDBOOK


FLOOR SLAB FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length L (M) 3.50 M
T Enter Width W (M) 3.50 M
W Enter Thickness T (M) 0.30 M
Enter Concrete Mix Design (CLASS) AA, A,or B A 1:2:4
9 0.5 1
TOTAL VOLUME OF CONCRETE: 3.68 CU.M.
# OF CEMENT BAGS 34.00 BAGS
L VOL. OF SAND CU.M. 1.90 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 3.70 CU.M.
HC GROUP-SIPIL CONSTRUCTION

FLOOR SLAB - BY AREA


FORMULA: VOLUME = Floor Area* T
CLASS A CONCRETE MIX
T Enter Floor Area A (SQ.M) 3.68 SQ.M
Enter Thickness T (M) 0.30 M
Enter Concrete Mix Design (CLASS) AA, A,or B A 1:2:4
TOTAL VOLUME OF CONCRETE: 1.10 CU.M.
# OF CEMENT BAGS 10.00 BAGS
Area VOL. OF SAND CU.M. 0.60 CU.M.
9 0.5 1 VOL. OF 3/4" GRAVEL CU.M. 1.20 CU.M.

CONCRETE COLUMNS COLUMN DIMENSIONS:


RECTANGULAR
W1 Width 1 0.25 M
Width 2 0.25 M

W2
FORMULA: VOLUME = H * W1 * W2
H CLASS A CONCRETE MIX
Enter Height L (M) 1.22 M

BASED ON HC GROUP INDONESIA - SIMPLIFIED CONSTRUCTION ESTIMATE HANDBOOK


VOLUME OF CONCRETE FOR EACH COLUME: 0.08 CU.M.
Number of Columns Units 10.00 Units
TOTAL VOLUME OF CONCRETE: 0.76 CU.M.
# OF CEMENT BAGS 7.00 BAGS
VOL. OF SAND CU.M. 0.40 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 0.80 CU.M.

CONCRETE COLUMNS COLUMN DIMENSIONS:


CIRCULAR
D1 Diameter 0.30 M

AreaCirc 0.07 SQ.M.

FORMULA: VOLUME = H * AreaCirc


H CLASS A CONCRETE MIX
Enter Height L (M) 3.00 M
VOLUME OF CONCRETE EACH COLUMN: 0.21 CU.M.
Number of Columns Units 6.00 Units
TOTAL VOLUME OF CONCRETE: 1.27 CU.M.
# OF CEMENT BAGS 12.00 BAGS
VOL. OF SAND CU.M. 0.70 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 1.30 CU.M.

HC GROUP-SIPIL CONSTRUCTION

BASED ON HC GROUP INDONESIA - SIMPLIFIED CONSTRUCTION ESTIMATE HANDBOOK


CONCRETE BEAMS

FORMULA: VOLUME = LT * W * D
CLASS A CONCRETE MIX
EnterTotal Length LT (M) 14.00 M
LT
Enter Width W (M) 0.30 M
BEAM DIMENSIONS: Enter Depth D (M) 0.40 M
D TOTAL VOLUME OF CONCRETE: 1.68 CU.M.
# OF CEMENT BAGS 16.00 BAGS
VOL. OF SAND CU.M. 0.90 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 1.70 CU.M.
W

CONCRETE STAIRS

Enter Riser Height RH (M) 0.20 M


TR
W Enter Tread Run TR (M) 0.30 M
Enter Stair Width W (M) 1.20 M
RH Enter # of Steps N 7.00 Steps
Enter Stringer Thickness TS (M) 0.15 M

0.25 0.45 0.71

TOTAL VOLUME OF CONCRETE: 0.71 CU.M.


# OF CEMENT BAGS 7.00 BAGS
TS VOL. OF SAND CU.M. 0.40 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 0.80 CU.M.

BASED ON HC GROUP INDONESIA - SIMPLIFIED CONSTRUCTION ESTIMATE HANDBOOK


DESKRIPSI CONCRETE SAT SEMEN SAT PASIR SAT BATU SAT
FOOTING 2.94 m3 27 SACK 1.5 m3 3 m3
FLOOR SLAB 3.68 m3 34 SACK 1.9 m3 3.7 m3
C.C 1.27 m3 12 SACK 0.7 m3 1.3 m3
SLAB BEAM 1.68 m3 16 SACK 0.9 m3 1.7 m3

TOTAL 9.57 m3 90 SACK 9 m3 9.7 m3


SEMEN 65,000 5,850,000
PASIR 660,000 5,940,000
BATU 150,000 1,455,000
TOTAL 13,245,000

BEHEL 13 30 70000 2,100,000


ASPHALT 2 700000 1,400,000

T KERJA 10 ORG 180000 HR 15 27,000,000

SUB TOTAL 43,745,000


GROSS PROF 13,123,500
56,868,500

BASED ON HC GROUP INDONESIA - SIMPLIFIED CONSTRUCTION ESTIMATE HANDBOOK