You are on page 1of 35

Flixborough disaster

By:

Paradigma Carlo
Giovanni
Introduction
• Largest peacetime explosion ever to occur in the UK
• Date: Saturday, 1 June 1974
• Location: Flixborough chemical plant owned by Nypro
(UK) Ltd
• Deaths of 28 workers on the site
• Widespread damage to property within a 6 mile radius
around the plant
• 1967: 20,000 TPA caprolactam plant built by DSM at the
Flixborough site using process involving the hydrogenation
of phenol
C6H5OH + 2 H2 → (CH2)5CO

• 1972: 70,000 TPA ; new process used

• New process based on oxidation of cyclohexane

• Posed much greater hazard than phenol process


Description of the cyclohexane
process
• Process operates by injecting compressed air into
liquid cyclohexane at a working pressure of about 9
bar and temperature of 155°C
• Cyclohexanone and cyclohexanol produced
• Conversion is low and it is necessary to recirculate
the cyclohexane continuously through a train of six
large SS-lined reactors
C6H12 + O2 → (CH2)5CO + H2O
Cyclohexane Cyclohexanone

Caprolactum Nylon6
Simplified flow diagram of cyclohexane oxidation plant
before March 1974 (Whittingham, 2005)
Events leading to the accident
2. Miners overtime ban of Nov, 1973

• Resulted in the government passing legislation to restrict


the use of electricity by industry to 3 days a week

• Was not possible to operate the process on this basis

• Was decided to utilize existing emergency power


generation on-site
• Major electricity user: 6 stirrers in the cyclohexane
reactors

• Primary purpose: disperse compressed air that was


injected into each reactor via a sparger

• Also ensured that droplets of water formed within


the reactor system were dispersed into the
cyclohexane
1. The No. 5 reactor problem

• Jan, 1974:normal electricity supply resumed

• Was found that the drive mechanism for the stirrer


in the No. 4 reactor had been subject to severe
mechanical damage

• No reason was found for this. It was therefore


decided to continue to operate the plant with the
No. 4 reactor stirrer shutdown.
• Cyclohexane reactors were MS vessels fitted with an
inner SS lining to resist corrosion

• March,1974: Cyclohexane found leaking from 6 feet


long vertical crack in the MS shell of the No. 5 reactor

• Due to technical problems experienced earlier and the


effects of the 3-day week, the plant owners were keen
to make up lost production

• Therefore decided to remove No. 5 reactor for


inspection and continue operation with the remaining
five reactors
1. Installation of 20” bypass pipe

• This pipe connected together the existing 28 inch


bellows on the outlet of reactor No. 4 and the inlet of
reactor No. 6

• Dog-leg shape of pipe

• Company did not have qualified mechanical engineer


on site to oversee design and construction

• No hydraulic pressure testing of pipe carried out,


except for a leakage test using compressed air.
Simplified flow diagram of cyclohexane oxidation plant
after March 1974 (Whittingham, 2005)
1. Resumption of production
• Plant restarted and operated normally, with occasional
stoppages, up until the afternoon of Saturday, 1 June 1974

• Previous day: plant had been shut down for minor repairs

• Early hours of 1 June: plant in process of being restarted

• Start-up involved charging system with liquid cyclohexane to


normal level and then recirculating this liquid through a heat
exchanger to raise the temperature.
• The pressure in the system was maintained with nitrogen
at about 4 bar until the heating process began to raise the
pressure due to evaporation of cyclohexane.

• The pressure was then allowed to rise to about 8 or 9 bar,


venting off nitrogen to relieve any excess pressure. The
temperature in the reactors by then was about 150°C.
• On 1 June this procedure was followed except it was noted
by the morning shift that by 06.00 hours the pressure had
reached 8.5 bar even though the temperature in the No. 1
reactor had only reached 110°C

• Was not realized at the time that this discrepancy might


have indicated the presence of water in the system

• The start-up continued until, at about 16.50 hours, a shift


chemist working in the laboratory close to the reactors
heard the sound of escaping gas and saw a haze typically
associated with a hydrocarbon vapour cloud.
The accident
• 16.53 hours on 1 June 1974: massive aerial explosion
occurred with a force later estimated to be about 15 to
45 tonnes of TNT equivalent
• Explosion heard up to 30 miles away and damage
sustained to property over a radius of about 6 miles
around the plant
• 28 plant workers killed with no survivors from the
control room
• All records and charts for the start-up destroyed
• Following the explosion, 20 inch bypass assembly was
found in a ruptured condition
The Public Inquiry
• Following the disaster, public inquiry
conducted under the chairmanship of Roger
Parker QC
• To establish the causes and circumstances of
the disaster
• To identify lessons to be learnt from the
disaster
Conclusions of the inquiry
• The immediate cause of the main explosion
was the rupture of the 20 inch bypass
assembly between the No. 4 and No. 6 reactor
• Two main theories to explain
The 20 inch pipe theory
• The 20 inch bypass assembly failed due to its
unsatisfactory design features
• However, the assembly had survived 2 months of
normal operation.
• A number of independent pressure tests were
commissioned to determine unusual conditions
• The normal working pressure = 8 bar
• practice during start-up to allow the pressure to
build up to about 9 bar.
• The safety valves for the system, were set to
discharge at a pressure of 11 bar
• At pressure above 11 bar, squirming motion
which distorted the bellows.
• Even when the assembly squirmed, no rupture
until pressure crossed 14.5 bar, a pressure not
achievable in reactors.
• Inquiry concluded that a rupture of the 20 inch
bypass due to pressure, temperature conditions
• Report conceded ambiguity in the hypothesis
• Simulation tests could not replicate failure at
similar conditions
The 8 inch hypothesis
• Alternative theory
• 50 inch split in an 8 inch line connected to
separator below bypass
• this failure led to a smaller explosion causing
failure of the main 20 inch bypass
• Zinc embrittlement had caused the split
• Small lagging fire at a leaking flange causing zinc
to drip onto the 8 inch pipe
• Brittle failure – Vapour release – Explosion – 20
inch failure
• Inquiry Report had devoted discussion of this
two-stage theory
• Finally dismissed as being too improbable
• No other theories considered by them to explain
failure of 20 inch bypass pipe
The water theory
• Another alternative theory
• Not considered by the Inquiry
• Much of scientific work after Inquiry closed
• Examined the effects of not operating the No. 4
reactor stirrer during the start-up at a time when
water may be present
• More probable explanation
• Cyclohexane and water are normally immiscible
• Azeotrope forms due to the limited solubility of
water in cyclohexane.
• This azeotrope has lower boiling point than
either water or cyclohexane
• Unstable interfacial layer may form
• Under certain conditions can boil and erupt
violently ejecting cyclohexane and superheated
water from the reactor.
• Normally impossible for water layer to form due to
dispersion of water by air distribution
• During start-up, the air to the reactors shut off
• If stirrers running during start-up, no water layer
• If stirrer stops, a layer of water could form, together
with the unstable azeotrope.
• As temperature of reactor increases, boiling
point of azeotrope is reached
• Possibility of a sudden violent eruption from the
reactor and ejection of slugs of liquid reactant
• Slugs exert high mechanical forces on the bypass
assembly, loosely supported by scaffolding
• Causes bypass assembly to fail without the high
static pressure in the reactors
Alternative event sequence
• Most credible explanation
• Explains failure of 20 inch bypass
• Also provides an explanation for the whole
sequence of events
• Unexplained failure of drive mechanism of No. 4
reactor
• Crack developing in the lining and shell of No.
5 reactor
• Failure of the 20 inch bypass assembly.
• Any/all failures caused by violent eruption of
reactor contents due to presence of water
• Committee failed to see common thread
• Drive mechanism failure for No. 4 reactor
unexplained
• Thought to be irrelevant
• Crack in the shell of the No. 5 reactor due to
stress corrosion
• Proposed by plant owners but not credible
• The failure of the bypass concluded by Inquiry
due to reactors being over-pressurized
• Implies human error, not verifiable
• Greatest failing of Inquiry was not taking
account of all the events 6 months prior to the
disaster
• Issue of non-operation of the reactor stirrers
ignored
Conclusions
• Human error analysis
Table gives causes against the different types of
error that occurred.
• Direct cause
Failure of the 20 inch bypass pipe led to huge
release of inflammable cyclohexane vapour
which ignited
• Root causes
A badly designed 20 inch bypass pipe installed
rather than finding reasons for the crack in the
No. 5 reactor
Why bypass failed ?
(Whittingham, 2005)
Safety considerations
• Learnings
• Low inventory especially of flashing fluids
• Before modifying process, carry out systematic
search for possible cause of problem
• Carry out HAZOP analysis
• Construct modifications to same standard as
original plant
• Use blast-resistant control rooms and buildings
THANK YOU

You might also like