Professional Documents
Culture Documents
Note: All doors and windows are pre-fabricated from local aluminum & glass and door supplies.
Area (m2) QUANTITY UNIT COST TOTAL COST
Sliding Glass Windows w/ Fixed Glass& Alum. Framing 21.96
Awning Type Glass Window w/ Alum. Framing 4.025
Fixed Glass W/ Aluminum Frame 7.41
Sliding Glass Doors w/ Fixed Glass& Alum Framing 20.82
Wooden doors 11 pcs.
UPVC Door 7 pcs. P 1,200.00 P 8,400.00
Door Knob 9 pcs. P 700/pc. P 6,300.00
Pin Hinges 30 pcs. P 40/ pc. P 1,200.00
SUM P 15,900.00
*unit cost already includes labor and installation
MATERIAL COST:
QUANTITY COST/UNIT TOTAL COST
¼” x 4’ x 8’ Marine Plywood 47 sheets P 350/sheet P 16,400.00
2” x 2” x 12’ Lumber 616 bd.ft P 1000/m3 P 14,540.00
No. 2 ½ Common Wire Nail 7.5 kgs P 42/kg P 315.00
No. 1 Common Wire Nail 7.5 kgs.. P 48/kg P 360.00
LABOR COST:
Ceiling construction (including framing)= 0.171 man hours per m2
440.88m2 x 0.171 man hours/ m2= 75.39≈76 man hrs.
76 man hrs. ÷ 8 hrs./day = 9 ½ days or 10 days
MATERIAL COST:
QUANTITY COST/UNIT TOTAL COST
50 mm Φ x 6m Stainless Pipe 2 lengths P 6,000/length P 12,000.00
Welding Rod 5 kgs P 350/kg P 1,750.00
Grinding Stone 10 pcs. P 50/pc. P 500.00
LABOR COST:
QUANTITY DAYS UNIT COST TOTAL COST
Foreman 1 5 P 500.00 P 2,500.00
Welder 2 5 P 350.00 P 3,500.00
A. ROOF SHEET
Length of Gutter 1 (Side) = 30 m Length of Gutter 2 (Side) = 16 m
Effective Covering Side Lapping = 0.70 Effective Covering Side Lapping = 0.70
30 ÷ 0.70 = 42 sheets 16 ÷ 0.70 = 23 sheets
B. RIVETS
For 12’ long roof sheet: 50 x 26 pieces/sheet = 1100 pieces
For 10’ long roof sheet: 50 x 22 pieces/sheet = 800 pieces
For 7’ long roof sheet: 50 x 18 pieces/sheet = 700 pieces
TOTAL = 2600 pieces
2600 pieces ÷ 180 pcs./ kg = 14.4 kg of G.I. Rivets
C. G.I. WASHER
2600 pieces of rivets x 2 washer/rivet = 5200 pieces of washer
5200 pieces of washer ÷ 128 pcs. / kg = 40.625 kg of G.I. Washer
D. LEAD WASHERS
No. of rivets= no. of washer
2600 pieces of washer ÷ 75 pcs. / kg = 35 kg. of Lead Washers
E. ROOF ACCESSORIES
LENGTH (m) EFFECTIVE LENGTH (m) QUANTITY*
Gutter 86.25 2.35 37
Flashing 86.5 2.30 38
Ridge Roll 4 2.20 2
Valley Roll 13.2 2.30 13.2
Hipped Roll 53.3 2.20 25
C-Purlins (2” x 4”)
*Length / Eff. Length
F. ANGLE BARS (1/4” X 2” X 2”)
MATERIAL COST:
LABOR COST:
QUANTITY DAYS UNIT COST TOTAL COST
Foreman
Laborer
XII. PAINTING WORKS
MATERIAL COST:
QUANTITY COST/UNIT TOTAL COST
Liquid Tile Primer White 27 gals. P 730/ gal P 19,710.00
Liquid Tile Top Coat Gloss White 27 gals. P 845/gal P 22,815.00
Flatwall Enamel Paint, Davies 13 gals P 535/gal P 6,955.00
Quick Dry Enamel Paint, Davies 26 gals. P 590/ gal P 15,340.00
Concrete Neutralizer 11li P 410/ li P 4,510.00
Paint Thinner 21 gals. P 245/gal P 5,145.00
P 74,475.00
LABOR COST:
QUANTITY DAYS UNIT COST TOTAL COST
Foreman
Painter
LABOR COST:
QUANTITY DAYS UNIT COST TOTAL COST
Foreman
Plumber/Helper
MATERIAL COST:
MATERIALS QUANTITY* COST/UNIT TOTAL COST
2.0 mm Φ x TW Copper Wire P 30.00 /roll P 90,000.00
5.5 mm Φ x TW Copper Wire P 45.00/roll P 183,300.00
8.0 mm Φ x TW Copper Wire P60.00/roll P1,805.00
20 mm Φ UPVC Conduit Pipe P20.00 P1,805.00
Fluorescent Lamp (40W) 19 pcs. P 95.00 P1,805.00
Incandescent Bulb (20W) 44 pcs. P70.00 P 3,080.00
Convenience Outlet 53 pcs. P 95.00 P1,805.00
One Gang Switch 25 pcs. P70.00 P1,805.00
Two Gang Switch 5 pcs. P 95.00 P1,805.00
Three Gang Switch 2 pcs. P70.00 P1,805.00
Fuse (15A) pcs. P 95.00 P1,805.00
Fuse (30A) pc. P70.00 P1,805.00
Fuse (60A) pcs. P 95.00 P1,805.00
TOTAL
*Derived using direct counting method
LABOR COST:
QUANTITY DAYS UNIT COST TOTAL COST
Electrician
Helper