You are on page 1of 14

electronics

Article
Technical and Economic Assessment of VSC-HVDC
Transmission Model: A Case Study of South-Western
Region in Pakistan
Mehr Gul 1,2, * , Nengling Tai 1 , Wentao Huang 1 , Muhammad Haroon Nadeem 1 ,
Muhammad Ahmad 1 and Moduo Yu 1
1 School of Electronic Information and Electrical Engineering, Shanghai Jiao Tong University,
Shanghai 200240, China; nltai@sjtu.edu.cn (N.T.); hwt8989@sjtu.edu.cn (W.H.);
haroon.nadeem@sjtu.edu.cn (M.H.N.); ahmad1406@sjtu.edu.cn (M.A.); m18817519493@163.com (M.Y.)
2 Department of Electrical Engineering, Balochistan University of Information Technology, Engineering and
Management Sciences (BUITEMS), Quetta 87300, Pakistan
* Correspondence: emehrgul@sjtu.edu.cn; Tel.: +86-13262736005

Received: 10 October 2019; Accepted: 5 November 2019; Published: 7 November 2019 

Abstract: The southwestern part of Pakistan is still not connected to the national grid, despite its
abundance in renewable energy resources. However, this area becomes more important for energy
projects due to the development of the deep-sea Gwadar port and the China Pakistan Economic
Corridor (CPEC). In this paper, a voltage source converter (VSC) based high voltage DC (HVDC)
transmission model is proposed to link this area to the national gird. A two-terminal VSC-HVDC
model is used as a case study, in which a two-level converter with standard double-loop control is
employed. The proposed model has a capacity of transferring bulk power of 3500 MW at 350 kV
from Gwadar to Matiari. Furthermore, the discounted cash flow analysis of VSC-HVDC against the
HVAC system shows that the proposed system is economically sustainable. The outcomes of this
study reveal that the implementation of this project can bring economic stability and energy security
in the southwestern region.

Keywords: technical assessment; voltage source converter; power transmission; discounted cash
flow; energy security

1. Introduction
The demand for power supply in Pakistan is growing exponentially in domestic and industrial
sectors [1], and thus, the country has faced severe energy crises in recent times. The two primary
sources for electricity production in Pakistan, i.e., hydropower and fossil fuels, have been adopted
for long, but cannot meet the increasing demands of the country. Currently, Pakistan has been taking
initiatives to utilize renewable energy to bridge the gap between demand and supply effectively.
However, the weak, old transmission system is still a significant hindrance to uphold the rapidity with
growing energy production supply [2,3].
Pakistan has five provinces, namely, Gilgit Baltistan, Khyber Pakhtunkhwa (KPK), Sindh,
Balochistan, and Punjab. Among these, Balochistan province with 347,190 km2 area is the largest one,
consisting of approximately 45% land of the country. Additionally, the tremendous renewable energy
resources, like wind and solar, are available to their vast extent and potential in the southwestern area
of Balochistan province. Monthly mean solar radiations ranged from 153.61–281.94 W/m2 throughout
the year, while the total wind power generation capacity in this area is about to 146 GW [4,5].
In this region, the population density is comparatively low due to the scarcity of natural resources,
and only 6% of the population is residing in this region. Possibly, the one most haunting reason for

Electronics 2019, 8, 1305; doi:10.3390/electronics8111305 www.mdpi.com/journal/electronics


Electronics 2019, 8, 1305 2 of 14

neglecting this high potential energy-producing area is its unstable and uncertain bordered geographical
location that is far away from the main grid. Keeping in view the power production potential of this
area along with the rapidly increasing energy crisis in Pakistan, it is indispensable to discover cheap
and high potential renewable energy sources like wind power. Whereas Punjab and Sindh provinces
are the most populated areas of the country, approximately holding 76% of the total population [6].
Moreover, to date, there is no available transmission line from these areas to the main national
grid. Figure 1 shows the existing transmission network in different regions of the country [7].
Despite substantial available power potential, still, Pakistan is depended on importing the power from
Iran to provide electricity in southwestern areas. Due to the lack of power generation projects and no
available transmission network, these areas are still not connected with the main national gird.
On the other hand, China Pakistan Economic Corridor (CPEC) projects and Saudi Arabia
investment in the oil sector this area becomes more important for the development of new power
projects and the setup of a new transmission line. Exploiting these energy resources not only helps the
CPEC and other future projects, but also fulfills the power demand of the country. Renewable energy
department authority and Pakistan national transmission and dispatch company have evaluated that
the transmission network of the country is overloaded. Therefore, new transmission lines are required
to meet the power supply demand across the country.
Generally, power is transmitted from the generation side to the main grid. There are two possible
ways to transmit the power to the national grid, i.e., high voltage alternating current (HVAC) and high
voltage direct current (HVDC). HVDC is proposed to be suitable for transmitting bulk power over long
distances in comparison to HVAC. HVDC transmission lines based on voltage source converters (VSC)
or line commutated converters (LCC) both are considered as a viable alternative than HVAC [8–10].
Furthermore, due to the advancement of technologies and cost comparison over a long distance, the
HVDC systems are considered economically sustainable. Detailed analysis includes the technical and
economic comparison of HVDC and HVAC systems that are elaborated in [8].
Additionally, the recent development in DC circuit breaker technologies and reliable protection
schemes makes the VSC-HVDC transmission links more promising [11,12]. The concept of a hybrid
DC circuit breaker with fault limiting capacity for VSC-HVDC transmission network is proposed
in [12], which can rapidly isolate the fault within permissible limits of fault current. Likewise,
a novel multi-terminal HVDC protection scheme based on artificial neural network (ANN) and
high-frequency components from fault current signals is utilized to detect, classify, and locate overhead
line faults accurately. This includes high impedance faults without compromising the accuracy of fault
location [13,14]. Based on the consecutive data window method (CDWM), another protection scheme
is introduced for the VSC-HVDC transmission system, which is capable of prompt fault detection
and isolation [15,16]. Furthermore, a new theory for locating line fault in the transmission system
is presented in [17], which has thoroughly presented the theoretical aspects, and simulations for the
line faults. With ongoing improvements in protection technology, the authors believe this will be
sufficiently supportive of the proposed transmission line.
There are various factors, such as technical considerations, economic aspects, and legal
requirements, that are critical in the planning of new transmission lines. A technical consideration
transmission line based on VSC-HVDC and economic aspects are presented in this paper. It is hoped
that the outcomes of this study can help to understand the importance of the new proposed VSC-HVDC
based transmission line in this area and provide a base for the further academic research in this field.
Electronics 2019, 8, 1305 3 of 14
Electronics 2019, 8, x FOR PEER REVIEW 3 of 15

Figure
Figure 1.
1. Transmission network in
Transmission network in Pakistan
Pakistan (dotted
(dotted lines
lines indicate
indicate the
the existing
existing networks).
networks).

2. Overview of HVDC
There are variousSystems
factors, such as technical considerations, economic aspects, and legal
requirements, that are critical
AC-based transmission networksin the planning of new transmission
were commonly used in the lines. A technical
earlier consideration
era of power system
transmission line
development, based
while DConnetworks
VSC-HVDC were and economic
rarely aspects
practiced dueare
topresented in this paper.
lack of technologies atItthat
is hoped
time.
that the outcomes of this study can help to understand the importance of the new proposed
Nevertheless, after 1945, the solid-state power electronics components penetrated into the power sector, VSC-
HVDC
and HVDCbased
gottransmission
researchers’ line in this
attention area
and andaprovide
made a base
comeback. for the
HVDC further academic
transmission networkresearch in
consists of
this field.
two types of technologies, depending upon the control of converters, i.e., voltage source converter
(VSCs) or line commutated converters (LCCs). In the initial stages, LCC-HVDC networks were
2. Overview of HVDC Systems
commonly used, but with time, HVDC transmission-related technologies became more efficient and
mature, which also
AC-based provided anetworks
transmission window for the development
were commonly used and implementation
in the earlier eraof VSC-HVDC based
of power system
transmission
development,networks
while DC[10,18–20].
networks Somewere HVDC transmission
rarely practiced duenetworks
to lack ofbased on both technologies
technologies at that time.
were installed in
Nevertheless, different
after regions
1945, the of the world
solid-state powerand are summarized
electronics componentsin Table 1, and other
penetrated intoprojects are
the power
discussed
sector, andinHVDC
[21–24].got researchers’ attention and made a comeback. HVDC transmission network
consists of two types of technologies, depending upon the control of converters, i.e., voltage source
Table 1. List of HVDC projects in different countries.
converter (VSCs) or line commutated converters (LCCs). In the initial stages, LCC-HVDC networks
were commonly used,
Project Name
but with time, HVDC
Year
transmission-related
Voltage Power technologies
Distance
Type
became more efficient
Supplier
(kV) (MW) (km)
and mature, which also provided a window for the development and implementation of VSC-HVDC
Three Gorges–Shanghai (China) 2006 500 3000 1060 Thy ABB
based transmission networks [10,18–20].
Estlink (Estonia–Finland) 2006 Some
150 HVDC 350 transmission
105 IGBnetworks based
ABB on both
NorNed
technologies (Netherland–Norway)
were installed in different 2008regions450 of the700 580 are summarized
world and Thy ABB
in Table 1, and
Yunnan–Guangdong (China) 2010 800 5000 1418 Thy Siemens
other projects areSAPEIdiscussed
(Italy) in [21–24].2011 500 1000 435 Thy ABB
BorWin1 (Germany) 2012 150 400 200 IGB ABB
Mundra–Haryana (India) 2012 500 2500 960 Thy Siemens
Zhoushan (China) Table 1. List 2014
of HVDC projects
200 in400different134
countries.
IGB NA
AL-link (Aland–Finland) 2015 80 10 158 IGB ABB
Western Alberta Transmission Line (Canada) Voltage500
2015 Power
1000 Distance
350 Thy NA
Project Name
NordBalt (Sweden–Lithuania) Year 2015 300 700 450 IGB Type Supplier
ABB
Skagerrak 4 (Denmark Norway) 2015
(kV) 500 (MW) 700
(km) IGB
244 Nexans, ABB
Three Gorges–Shanghai
Jinsha River II–East China (China) 2016 800 6400 NA Thy NA
DolWin2 (Germany) 2006 2016 500 320 3000
900 1351060 IGB Thy ABB ABB
(China)
SydVastlanken (Sweden) 2016 300 720 260 IGB Alstom
Estlink Western
(Estonia–Finland)
HVDC Link (UK) 2006 2017 150 600 350
2200 422 105 Thy IGB ABB
Prysmain Group, Siemens
NorNed Xinjiang–Anhui
(Netherland– (China) 2017 1100 10,000 3333 Thy NA
2008 450 700 580 Thy ABB
Norway)
Yunnan–Guangdong
After many years (China)
of research2010 800
and development 5000 the VSC1418
process, Thytransmission
based HVDC Siemens
systems
SAPEI (Italy) 2011 500 1000 435 Thy ABB
became an attractive option for bulk power transmitting over long distance. Recently, VSC-HVDC
BorWin1 (Germany) 2012 150 400 200 IGB ABB
is being preferred to LCC-HVDC, because VSCs offer the independent control of both reactive and
Mundra–Haryana (India) 2012 500 2500 960 Thy Siemens
active power. Also, VSCs do not need external sources to push off the switches, while LCCs needed the
Zhoushan (China) 2014 200 400 134 IGB NA
AL-link (Aland–Finland) 2015 80 10 158 IGB ABB
Electronics 2019, 8, 1305 4 of 14

external mechanical switches. VSC-HVDC based networks offer many advantages over LCC-HVDC,
and some of them are summarized in Table 2 [25,26].

Table 2. Comparison of VSC-HVDC and LCC-HVDC.

Operation/Function VSC-HVDC LCC-HVDC


No external mechanical switches
Cannot change the current direction,
Direction reversal needed, current direction change is
need external switches
possible in the converter
Offer fault ride-through capability, No
Possibly commutation failure; short
AC influences AC disturbances, a less loss of active
circuit of the HVDC grid
power transfer
Consumes 50 percent of reactive power
Allows active and reactive
AC Voltage Control (VAR), needed AC filters for VAR
power control
compensation
Electrically can be connected to weak or Connection limited to medium and high
AC connections
black AC circuits capacity circuits.
Multi-Terminals Options No limitations Limited to 3-terminals
Delivery period 2 years 3 years

3. Deployment of Proposed Transmission Line


The proposed transmission line is based on VSC-HVDC, which can stretch approximately 815 km
from Gwadar, Balochistan, to Matiari, Sindh. A major part of the line will be in Balochistan province
for up to about 600 km, and the remaining portion will be in Sindh province. The Pakistan first-ever
LCC-HVDC transmission line project (under the vision of CPEC) from Matiari to Lahore is under
construction and can be operational at the start of 2021. This HVDC line is 878 km long, will be capable
of bulk power transmission of about 4000 MW at 660 kV, generated from various power projects in the
south part to the most populated area of Punjab province [27].
Gwadar is one of the busiest sea routes in between Southwest and South Asia on the Arabian Sea
shore due to its geographical, commercial, and strategically significant deep-sea port. It covers the
35% of global sea-trade, including 45% of China’s oil trade. It is being bordered with Iran, which has
broadened the opportunities to reach the overland business activities. With this recent development of
Gwadar Sea Port under CPEC projects, it has become the hub of global economic activities. Recently,
the memorandum of agreement [MOU] between Saudi Arabia and Pakistan has been signed to set up
a joint working group for the petrochemical complex and the state-of-the-art oil refinery in Gwadar
city. Moreover, Iran has made an agreement with Pakistan to build an oil refinery, whereas Qatar also
has shown its interest in establishing a food storage system at Gwadar port. This initiative would help
boost the economic and energy development of the region [28–30].
Owing to substantial renewable energy resources, development of port and oil refinery, and
other economic activities, the southwestern region should be connected to the national grid, which
can provide the power security and demolish the power shortages of the country. The proposed
VSC-HVDC transmission line is capable of dispatching bulk power approximately 3500 MW at 350 kV
from Gwadar to Matiari. The location of the proposed bipolar HVDC transmission line is shown in
Figure 2. The whole area is easily accessible for all types of vehicles through Makran coastal high way
in Balochistan and the national high way in the Sindh part. Most of the line will pass through the rural
areas and have a negligible effect on the social instability.
It is worth mentioning here that this kind of research is hardly carried out before for this area.
It is hoped that the implementation of this project can be a game-changer in the region, provides
employment opportunities, infrastructure development, increases land revenue, and uplifts the
socio-economic. Besides, the access amount of electricity that can be available in the national grid
ensures the energy security, which can also result in industrial development and expansion of industry
in the country.
It is worth mentioning here that this kind of research is hardly carried out before for this area. It
is hoped that the implementation of this project can be a game-changer in the region, provides
employment opportunities, infrastructure development, increases land revenue, and uplifts the
socio-economic. Besides, the access amount of electricity that can be available in the national grid
ensures the energy
Electronics 2019, 8, 1305 security, which can also result in industrial development and expansion 5 of of
14
industry in the country.

Iran

India
Matiari
Gwadar

Figure
Figure 2.
2. Proposed
Proposed HVDC
HVDC transmission
transmission line
line for
for the
the South-western
South-western part
part of
of Pakistan.
Pakistan.

4. VSC-HVDC
4. VSC-HVDC System
System Theory
Theory and
and Simulation
Simulation
Different types
Different typesofofvoltage source
voltage converters
source are used
converters are for HVDC
used for transmission; the most commonly
HVDC transmission; the most
used in thisused
commonly regard
in are
thisa regard
two-levelareconverter,
a two-levelthree-level
converter,neutral-point
three-level clamped (NPC)clamped
neutral-point converter, and
(NPC)
modular multilevel converter (MMC) [31]. In this paper, a case study with results
converter, and modular multilevel converter (MMC) [31]. In this paper, a case study with results is is incorporated
using MATLAB
incorporated simulation
using MATLAB to simulation
understandto the significate the
understand of the VSC-HVDC
significate of thesystem. In thissystem.
VSC-HVDC context,Ina
two-terminal
this context, a VSC-HVDC
two-terminalmodel is used,model
VSC-HVDC in which a two-level
is used, in whichconverter with
a two-level standard
converter double-loop
with standard
control is employed. Where terminal-I is controlling DC-voltage and active power, while
double-loop control is employed. Where terminal-I is controlling DC-voltage and active power, while terminal-II is
controlling is
terminal-II active and reactive
controlling activepower.
and reactive power.

4.1. Converter
4.1. Converter Control
Control
There are
There areseveral
severalapproaches
approachestotocontrol thethe
control converter; out out
converter; of many, vectorvector
of many, control and direct
control and power
direct
control are commonly used ones. In vector control, voltage and current vectors in reference
power control are commonly used ones. In vector control, voltage and current vectors in reference (rotating)
frame are transformed
(rotating) frame are into a two-dimensional
transformed stationary frame stationary
into a two-dimensional using Clark’s transformation
frame [32].
using Clark’s
The AC side voltage vectors are represented by Equations (1)–(3), whereas the application
transformation [32]. The AC side voltage vectors are represented by Equations (1)–(3), whereas the of Clark’s
transformations
application is given
of Clark’s in Equation (4).
transformations is given in Equation (4).

va (t) = Vm cos(θ) (1)


 
vb (t) = Vm cos θ − (2)
3

 
vc (t) = Vm cos θ − (3)
3
The details of variables attached to Equations (1), (2), and (3) are as follows. va , vb , and vc are
the respective phase voltages in the balanced AC grid, Vm represents the amplitude of phase voltage,
θ = ωt represents the phase angle measured in radians. The design of any control method in the
original/natural three-dimensional frame (or ABC frame) is complicated because of three independent
vectors concerning different state variables, e.g., voltage or current, etc. Therefore, the variables in
the original/natural three-dimensional frame are converted to a two-dimensional frame, either static
frame (or αβ-frame) using Clark’s Transformation, or a rotating frame (or dq-frame) using Park’s
Electronics 2019, 8, 1305 6 of 14

Transformation, depending on the design of the control. In this way, control schemes can be designed
based on the control of two independent vectors, simpler in design and easier to implement.

−√12 −√21
    
 vα (t)   1  va (t) 

 vβ (t)
 2
 = Tvabc (t) = 
 3 3

 vb (t)

0 2 − 2
 (4)
  3  1 1 1
 
vo (t) vc (t)
   
2 2 2
h i0
In Equation (4), “T” is the transformation matrix, vα (t) vβ (t) vo (t) represents the voltage vector
h i0
in the αβ-frame, while va (t) vb (t) vc (t) denotes the voltage vector in ABC-frame. Using similar
approaches, current in the two-dimensional stationary frame can also be obtained. Once the values
in the two-dimensional stationary frame are obtained, then these transformed into two-dimensional
rotating frame or dq-frame, by the application of Park’s t transformations, which is given in Equation (5).

cos(θ) sin(θ)
    
 vd (t)   0  vα (t) 
−sin(θ) cos(θ)
    
 vq (t)  = To vαβo (t) =  0  vβ (t)  (5)
    
vo (t) 0 0 1 vo (t)
   

h i0
In Equation (5), vd ( t )
vq (t) vo (t) represents the voltage vector in dq-frame, “To ” is the
h i0
transformation matrix, and vα (t) vβ (t) vo (t) indicates the voltage vector in αβ-frame. It should
be noted that if the d-axis of the rotating frame (dq-frame) is aligned to the AC voltage vectors, such
that vq = 0, consequently, the instantaneous active and reactive power is given in Equations (6) and (7),
respectively, which are based on the instantaneous power theory of Akagi [33].

3
P= v i (6)
2 dd
3
Q = − vd iq (7)
2
From the mathematical relationships, it is evident that the control of active and reactive power is
directly linked with controlling current and voltage in the dq-frame. Figure 3 explains the
Electronics 2019, 8, x FOR PEER REVIEW
working of
7 of 15
conventional double-loop control for two-level voltage source inverter (VSI) [34]. An outer control loop
produces the
loopreference
produces the currents Id∗ and
reference Iq∗ , and
currents I d* and I q* , and
these reference values serve
these reference values as input
serve for the
as input for inner
the control
loop. Theinner
inner control loop controls the actual values of V and V to
control loop. The inner control loop controls the actual dvalues ofq Vd and Vq to produceproduce desired reference
current, and ultimately Vd∗ and Vq∗ are transformed * into
* abc frame and then sent to the pulse width
desired reference current, and ultimately Vd and Vq are transformed into abc frame and then
modular PWM controller to directly control the firing angle of IBGTs to achieve the desired results.
sent to the pulse width modular PWM ∗ , P∗controller to directly control the firing angle of IBGTs to
Where LE is the line inductance and Vdc , Q∗ are the reference values * * of DC
* voltage, active power,
achieve the desired results. Where LE is the line inductance and Vdc , P , Q are the reference
and reactive power, respectively.
values of DC voltage, active power, and reactive power, respectively.

Outer loop Inner loop


Vd  V *
P* , Vdc* I d* d
PI PI 
 
P  Id 
 LE

Iq
 LE
*   V*
Iq q
*
Q 
PI 
PI 
Q  Vq 
Figure 3. Double loop-control for the converter.
Figure 3. Double loop-control for the converter.
4.2. Two-Terminal Model Simulation
The schematic layout used for simulation is shown in Figure 4, whereas the double-loop control
structure explaining the control aspects of VSI is given in Figure 3. For simulation, a two-terminal
system is developed with conventional 2-level VSI and double loop control.

Line
Iq Vq
*
Q 
PI 
PI 
Q  Vq 
Electronics 2019, 8, 1305 7 of 14
Figure 3. Double loop-control for the converter.

4.2.
4.2. Two-Terminal
Two-Terminal Model Simulation
The
The schematic
schematic layout
layout used
used for
for simulation
simulation is
is shown
shown inin Figure
Figure 4,
4, whereas
whereas the
the double-loop
double-loop control
control
structure
structure explaining
explaining the
the control
control aspects
aspects of
of VSI
VSI isis given
given in Figure 3. For
For simulation,
simulation, aa two-terminal
two-terminal
system
system is
is developed
developed with
with conventional
conventional 2-level
2-level VSI and double loop control.

Line
Terminal-I
Terminal-II
Phase Reactor Phase Reactor
Bus-I

Bus-II
AC-Grid
Passive Network
VSC-I Line VSC-II
Figure 4.
Figure VSC-HVDCsystem
4. VSC-HVDC systemwith
withthe
thepassive
passive network.
network.

The terminal-I
The terminal-I used
usedtotoregulate
regulate thethe
DC-voltage
DC-voltage andand
reactive power,
reactive whereas
power, for terminal-II
whereas active
for terminal-II
and reactive
active power power
and reactive is regulated. Between
is regulated. two terminals,
Between an 800 km
two terminals, an long transmission
800 km line model
long transmission line is
also used. The essential parameters for the system are given in the Appendix Table
model is also used. The essential parameters for the system are given in the Appendix Table A1; the A1; the simulation
model is also
simulation builtisunder
model theseunder
also built parameters.
these parameters.
The Figure 5a contains the AC grid
The Figure 5a contains the AC grid voltage voltage concerning
concerning terminal-I,
terminal-I, likewise,
likewise, Figure
Figure 5b
5b shows
shows the
the
terminal
terminal DC-voltage
DC-voltage at VSC-I,
at VSC-I,and it can be seen that the regulation of terminal DC voltage is achieved
Electronics 2019, 8, x FOR PEER REVIEWand it can be seen that the regulation of terminal DC voltage 8 of is
15
convincingly, and terminal DC voltage is kept at the desired level of
achieved convincingly, and terminal DC voltage is kept at the desired level of 400 kV.400 kV.

(a) (b)
Figure 5. VSC terminal-I voltages; (a) AC grid voltage, (b) DC-voltage.

The receiving voltage at DC-link


DC-link capacitors
capacitors of terminal-II
terminal-II is is depicted
depicted in
in Figure
Figure 6a.
6a. It can be
observed that DC-voltage
DC-voltage is slightly less than the rated value; this is obvious because line parameters
can influence the value
value of
of DC-voltage
DC-voltage at at the
the receiving
receiving station.
station. The remaining results concerning
concerning
terminal-II includes AC voltage and current
current in
in Figure
Figure 6b.
6b.
Figure 5. VSC terminal-I voltages; (a) AC grid voltage, (b) DC-voltage.

The receiving voltage at DC-link capacitors of terminal-II is depicted in Figure 6a. It can be
observed that DC-voltage is slightly less than the rated value; this is obvious because line parameters
can influence
Electronics the value of DC-voltage at the receiving station. The remaining results concerning
2019, 8, 1305 8 of 14
terminal-II includes AC voltage and current in Figure 6b.

(a) (b)
Figure6.6.VSC
Figure VSCterminal-II
terminal-IIvoltages
voltagesand
andcurrent;
current;(a)
(a)DC-voltage,
DC-voltage,(b)
(b)Voltage
Voltageand
andcurrent
currentwaveforms.
waveforms.

Lastly,
Lastly,Figure
Figure77shows
showsthe
theactive
activepower
powertransmitted
transmittedtototerminal-II,
terminal-II,where
whereititisisapparent
apparentthat
thatthe
the
active
activepower
powerisisregulated
regulatedsuccessfully
successfullyatatterminal
terminalone,
one,which
whichisiskept
keptatatthe
thelevel
levelofof400
400MW
MWfollowing
following
the
thedesigned
Electronics 2019, 8,criteria.
designed criteria.
x FOR PEER REVIEW 9 of 15

Figure 7.
Figure Activepower
7. Active powertransmission
transmissionat
atterminal-II.
terminal-II.

5. Cost Assessment
5. Cost Assessment
Economic comparisons can usually be made by various methods, as depicted in Figure 8. However,
Economic comparisons can usually be made by various methods, as depicted in Figure 8.
the discounted cash flow method (DCF) is the commonly used method due to its time value of money.
However, the discounted cash flow method (DCF) is the commonly used method due to its time
In this context, all imminent cash flows are computed and discounted to get the net present values
value of money. In this context, all imminent cash flows are computed and discounted to get the net
(NPV) [8].
present values (NPV) [8].

Feasibility Study

Revenue Expense
Analysis Analysis

Discount Cash Flow


Economic
Internal Rate of Return
Evaluation
5. Cost Assessment
Economic comparisons can usually be made by various methods, as depicted in Figure 8.
However, the discounted cash flow method (DCF) is the commonly used method due to its time
value of2019,
Electronics money.
8, 1305In this context, all imminent cash flows are computed and discounted to get the
9 ofnet
14
present values (NPV) [8].

Feasibility Study

Revenue Expense
Analysis Analysis

Electronics 2019, 8, x FOR PEER REVIEW

Electronics 2019,Discount 8, x FOR PEER Cash REVIEW Flow


of China (SGCC) and Ministry of Water and Power Pakistan under th
Economic estimated cost is 1658.34 $MReturn (approximately 1.9 $M/km) [44]. Sim
of China (SGCC) Internal and Rate Ministryof of Water and Power Pakistan under
Evaluation
estimated cost of 1.7 $M/km for the proposed HVDC line, which is rea
estimated cost isElectronics 1658.342019, $M 8,(approximately
x FOR PEER REVIEW 1.9 $M/km) [44]. Sim
of previously selected Pay Back HVDC Period projects. Hence, the proposed HVDC mo
estimated cost of 1.7 $M/km for the proposed HVDC line, which is re
and a better choice for the future transmission projects in Pakistan.
of previously selected of China
Break-even HVDC (SGCC)
Point projects. andHence, Ministry theof proposed
Water and HVDC Power m
and a better choice for the future
estimated cost transmission
is 1658.34
Electronics 2019, 8, x FOR PEER REVIEW $M projects
(approximately in Pakistan. 1.9
6. Conclusions
estimated cost of 1.7 $M/km for the proposed HVDC
6. Conclusions
The southwestern of previouslyregion of of the country
selected
China (SGCC) HVDC isandexpected
projects.
Ministry to become
Hence,of Watertheapr ha
development due and to CPEC a region
better projects.
choice
estimated Conversely,
for
cost theisfuture power
transmission shortage proje an
The southwestern of the country is1658.34
expected $Mto(approxim
become ah
factors in this
Business Decision development due to CPEC projects. Conversely, power shortage area and should be
estimated solved cost promptly
of 1.7 $M/km to enhancefor the the CPE
propos a
activities. In this context, 6. Conclusions a study of previouslyof technical and economic aspectsHen of
Making factors in this area and should be solved selected promptly HVDC to enhance projects. the CP
HVDC transmission
2019, 8, x FORline PEERisREVIEW carried
and a better out. choice The simulation for the results for th
the future transmis
Electronics
activities. In this context, Theasouthwestern
study of technical region and of economic country aspects
is expe o
waveforms are found stable and reliable at the receiving end. The DC
HVDC transmission developmentline is carried due out. to CPEC The simulationprojects. Conversely, results for tp
Figure8.8.The
Figure Thegeneral
generalprocedure procedure transmission
present ofofbusiness
business
value of losses
decision
decision
the HVDC aremaking.
making. accounted
6. Conclusions
system is forlower theasannual compared cost;tohere, the HVA reliab
waveforms are found factors stable
in this and area reliable
and should at the be receiving
solved promptly end. The D t
neglected. DCF analysis
is found to be 3725 $M, while the HVDC NPV was 2599 $M. Moreove result is the difference of NPVs of mentioned
5.1. Methodology Electronics 2019,
5.1. Methodology Electronics 2019, 8, x FOR PEER REVIEW 8, x FOR PEER REVIEW present value of the HVDC
activities. In system
thisThe is
context, lower
southwestern a as
study compared of
regiontechnicalof to the
the10 and HVA
count
of 15ec
whichisalso
model relativelycomprises analogous the discounted to selectedannual existingcost HVDC (Cda)projects.
and 10 initia
of
Th
is found to be 3725 HVDC $M, while transmission the HVDC
development linedue NPV towas
is carried CPEC 2599out. $M.
TheMoreov
projects. simulaCon
The discount
The discount cash flow
cash flow (DCF) (DCF) analysis method transmission
realistic isand applied system.
feasible for The
the
transmission mathematical
economic system. comparison expressions of for the DCF met
transmission lossesanalysis are accounted method model isforappliedtherelatively
is for the
annual economic
cost;
analogous
waveforms here, are
factors comparison
reliability
to selected
found
in thisstable of HVAC
and
existing
area insurance
and
and reliablefactors
HVDC
should be the are
projects.
at solved receTp
Electronics
HVAC 2019, 8,8, xFORFOR transmission
PEERREVIEW REVIEWlossessystems. are accounted for theresearch
annual cost; here, reliability and
10byofof insurance
15 factors ar
Electronics
Electronicsand
Electronics 2019,
2019, 8,and
2019,
VSC-HVDC
8,xxFOR VSC-HVDC
FOR xPEER
PEER PEER
transmission
REVIEW
REVIEW transmission systems.
neglected. DCF analysis result is realistic This method ThisFurther method
uses
the difference andthe uses
difference
of NPVs
feasible
the should
present
difference
in
of value
transmission the
𝑇𝑜𝑡𝑎𝑙
mentioned be
activities. of
in
investment the
carried
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 10 10 investment
of
transmission
system.
the In HVDCthis
out
of 10
costs
15 15
system
context,
15
and considering
𝑐𝑜𝑠𝑡 line-technologies,
a is = 𝑆 +
lower
study of
the
𝐿techni
as + 𝑂𝑇
com
so
costs andcosts annual neglected.
costs of the DCF systems analysis result
for economic is the
projects. difference
comparison.Similarly, of
The NPVs of mentioned
maintenance
comprehensive costs
studies transmission
and
comprisingcosts line-technologie
of further tech
annual ofwhich the systems also for economic
comprises the comparison.
discounted annual
Further The cost
research ismaintenance
(Cda)
found should and
toHVDC be becosts
initial
3725 carried
$M, andwhile
investment
transmission outcosts by
the
line of
cost is (C
considering
HVDC i) NPV
carried for out. each
the
wasTs
transmission
transmission
transmission
of Electronics
transmission losses
transmission
losses 2019,are losses
losses
are
8,losses which
areare
accounted
x accounted
FOR PEER accounted
also
accounted
REVIEW
are accounted comprises
forthe
for for
for
theannual thethe
annual
for the annual
annual
the cost; discounted
cost;
annual cost;
cost;
here,
here, cost; here,
here,annual
reliability
here,
reliability reliability
cost
reliability
reliabilityand
and (Cda)
and and
insurance
and
insurance andinsurance
insurance
insuranceinitial
factors
factors factors
investment
factorsare
factors
are 10 areare
areof 15 cost (C i) for eac
transmission system. The mathematicalrequirements expressions of HVDC for systems
therelatively
DCF 𝑇𝑜𝑡𝑎𝑙 can
method be carried
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 are out
given 𝑐𝑜𝑠𝑡 for the real-time
as [8,35]; =further
𝑆reliable
+ 𝐿10tec im
+
neglected.
neglected. DCFanalysis
DCF analysis Electronics
transmission result
result 2019,isthe8, xdifference
the
system.
isdifference FOR
differencePEER
The REVIEW
of projects.
ofNPVsNPVs
mathematical of
ofof Similarly,
mentioned
expressions
mentioned model comprehensive
foristhe
transmission
transmission waveforms
DCF studies
analogous
are
line-technologies,
method
line-technologies, comprising
found
are to
given stable as of
selected and
[8,35];existing H
of
neglected.
neglected. DCFanalysis
neglected.
DCF analysis
DCF result
analysis
result isthethedifference
isresult is the difference
ofofNPVsNPVs of ofmentioned
NPVs
of mentioned mentioned transmission
transmission transmission line-technologies,
line-technologies,
line-technologies,
requirements , 𝐿𝑐𝑜𝑠𝑡
𝑆initial of 𝑂𝑇 HVDC
realistic systems
and present can
feasible be
value carried
transmission
of the out
HVDC for
system.the
systemreal-timeis low i
= 𝑆𝑄cost
Author
where, Contributions: , initial , and Core idea, are data collection, formal analysis, writing
which
which which
which
also
also
which alsocomprises
transmission
also
comprises
comprises
also comprises
comprises losses are
the
thediscounted
the thediscounted
discounted
the discounted
accounted
discounted annual
annual for annual
annualthe
𝑇𝑜𝑡𝑎𝑙
cost
cost
annual cost
annual
cost𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
(Cda)
(Cda)
cost (Cda)
(Cda)
and
and
(Cda)cost; andand
here,
initial
and reliability
initial
investment
investment
initial investment
investment
investment and
+cost +the
𝐿 insurance
(C cost
𝑂𝑇
cost
(C cost
i)for +
(C
for
)reliability
cost (C (C )of
i𝑄
)i)for
each
each for
substation,
for
factors eacheach
each are land, overhea (8)
ronics 2019, 8, x FOR PEER Electronics
REVIEW 2019, transmission
8,analysis
x FOR PEER REVIEW losses are 𝑇𝑜𝑡𝑎𝑙
accounted 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
simulations, for the
M.G.; 𝑐𝑜𝑠𝑡
annualresources, =
cost;
Further
10 𝑆
ofis 15 +
here, 𝐿
supervision,
research
found
i+ 𝑂𝑇
to i+
N.T.;
beshould 𝑄
3725 $M, and
methodology,
be insurance
ofcarried
while
10 annual 15 the factors
review
outHVDC byNP (8
& cN
transmission
neglected.
transmission
transmission system. DCFsystem.
system. The The
The
mathematical mathematical
result
mathematical isexpressions
expressions expressions
the difference
expressions for of reactive
NPVs
Author
the forforDCFthethe power
of DCFDCFmethod
mentioned
Contributions:
method compensations,
methodaregiven are
Core
given are
transmission given
given
idea,
as[8,35]; respectively.
as
data
[8,35]; collection,The
asline-technologies,
[8,35];
[8,35]; formal cost
analysis, (Ç),
writing
transmission system.
transmission The
system. mathematical
The
neglected. mathematicalDCF analysis expressions for
result the
collection,
is DCF
for
the the method
DCF
software,
difference are
method
validation,
of NPVs are as
ofgiven
M.H.N.,
mentioned as [8,35];
M.A., and M.Y.
transmission line-technologi
which
Electronics also2019, comprises
8, x FOR PEER theREVIEWdiscounted annual 𝑇𝑜𝑡𝑎𝑙 cost𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
expressed
simulations, (Cda) as; and
M.G.; 𝑐𝑜𝑠𝑡 projects.
initial
resources, Similarly,
investmentmodel
= 𝑆 supervision,
+ 𝐿 +cost is comprehensive
relatively
𝑂𝑇 (C i) for
N.T.; analogous
10each
methodology,
of 15 studies to compris
selected (9)
review(9&
nsmission losses aretransmission
accounted
transmission for losses
the 𝑇𝑜𝑡𝑎𝑙annual
are 𝑇𝑜𝑡𝑎𝑙
𝑇𝑜𝑡𝑎𝑙
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
accounted
cost; here, 𝑐𝑜𝑠𝑡 𝑐𝑜𝑠𝑡
𝑐𝑜𝑠𝑡
forreliability 𝑇𝑜𝑡𝑎𝑙
=
annual 𝑆 and 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
=𝐿
+ =𝐿 𝑆insurance
𝑆This
cost; +
+ + 𝑂𝑇 𝐿+
𝐿here, +
+𝑂𝑇 𝑐𝑜𝑠𝑡
𝑂𝑇
𝑄 +𝑄(Cda)
reliability
factors 𝑄 are
+supported =and 𝑆and +insurance
𝐿initial
+ 𝑂𝑇 (8)
factors (8)canare
system. 𝑇𝑜𝑡𝑎𝑙
which The 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
also comprises
mathematical
Total 𝑐𝑜𝑠𝑡 the
expressions = 𝑆
discounted
Funding: +
collection,
= for +the
+L 𝑂𝑇
annual
work
software,
DCF + 𝑄 wascost
requirements
validation,
method
+ OTc +Macro(s)
realistic
are of
M.H.N.,
givenin HVDC
part and
as by
M.A., (8)(8)
investment
systems
feasible
2019
[8,35]; and major
M.Y.transmission costcarried
be
scientific (C ) for
isystem.
research outea af
lected. DCF analysis transmission
result
neglected.is the DCF where,
difference analysis 𝑆of , NPVs , investement
𝐿result 𝑂𝑇system.
of
is , the
and
mentioned 𝑄Thecost
USV
differenceare HVACthe Symbol
transmission
of USV
cost
NPVs
Sc of Symbol
cMacro(s)
substation,
of line-technologies,
mentioned
Q c
land,
transmissionoverhead transmission
line-technologies, Ç = (8)
𝑀 +
line, 𝐿𝑠 and Descripti
cost of
losses transmission
where, , 𝐿 , 𝑂𝑇 , for
are 𝑆accounted andthe 𝑄 annual
mathematical
are the cost;
Education cost ofexpressions
Commission
here, substation, (Grant
reliability for land, the DCF
Further
andoverhead
number: method research are
transmission
2019-01-07-00-02-E00044).
insurance factors (9)
given
(9) should as
are line, [8,35];
beand carried
cost o
ich also comprises the which
discountedalso reactive
comprises
annual 𝑇𝑜𝑡𝑎𝑙
𝑇𝑜𝑡𝑎𝑙 power
cost 𝑇𝑜𝑡𝑎𝑙
𝑇𝑜𝑡𝑎𝑙
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
the 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
compensations,
(Cda)
discounted and 𝑐𝑜𝑠𝑡
𝑐𝑜𝑠𝑡
initial
annual 𝑐𝑜𝑠𝑡
𝑐𝑜𝑠𝑡 Funding:
=
respectively.
=
investment𝑆
cost 𝑆0241
Ɂ++ = =This
𝐿
(Cda)𝐿𝑆𝑆+mentioned
++ +
The
𝑂𝑇
cost 𝐿
work
𝑂𝑇 𝐿+
Ɂ The
and +
Author
𝑂𝑇
was
annual
(C 𝑂𝑇
initial
i)annual
for +Contributions:
supported
𝑄projects.
cost
investment
each (Ç),inNPV, part by
cost
Core
(9) 2019
(9)
Annuity(C
idea,major data
factor
(8)
i) comprehensive
for each
collection,
(Ⱥ), 𝐶LATIN
scientific form
, CAPITAL
research are
neglected. DCF reactive
analysis power
result is compensations,
the
Total investement cost difference 0241
𝑇𝑜𝑡𝑎𝑙 of respectively.
NPVs =of
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 of \textglotstopvari
+ Lc +
SCommission 𝑐𝑜𝑠𝑡OT
\textglotstopvari
transmission cost
= 𝑆number: (Ç),
+ 𝐿= +
Similarly,
NPV, Annuity
line-technologies,
𝑂𝑇conflict + of(9)
𝑄 supervision, factor (Ⱥ), 𝐶
studie , ar
Conflicts
Education
HVDC
ɂland, cInterest: simulations,
The authors
c(Grant 𝑁𝑃𝑉M.G.;
declare 𝑇𝑜𝑡𝑎𝑙
resources,
no 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
2019-01-07-00-02-E00044). interest. 𝑐𝑜𝑠𝑡N.T.; meth
/ +
(L
expressed as; 0242 are0242 asɂDCF
\textglotstopvarii \textglotstopvarii
, ,𝐿𝐿,𝑆,𝑆𝑂𝑇 ,𝐿𝐿, ,,and 𝑂𝑇𝑂𝑇 𝑄𝑄
nsmission system. The
where, transmission
where, mathematical
,𝑂𝑇 ,and system.
,𝑄expressions
,and
and
expressed The are mathematical
are
as;forthe
the the cost
cost DCF method
expressions
ofofannual
substation,
substation, given
land, for the overhead
overhead [8,35]; method transmission
transmission are
requirementsgiven line,
line, ascost
and[8,35];
and
of HVDCcost
)cost of ofsystems canLATIN SMALL
be ca
where,
where, 𝑆𝑆which also comprises 𝑄 are
are the
the
the discounted
cost
cost
𝑇𝑜𝑡𝑎𝑙 ofof substation,
substation,
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 land, cost
land,
𝑐𝑜𝑠𝑡
0243Conflicts
(Cda)
overhead
overhead
Ƀ of=overhead
0243
and
𝑆(Ç),
USV initial
transmission
collection,
transmission
Ƀ+ 𝐿 +
\textbarcapitalb 𝑂𝑇
investment
Symbol
\textbarcapitalb
line,
software,
line, Macro(s)
and
and cost
validation,
cost (Cof iof for
M.H.N., each
(9) M.A., and M.Y.
where,
reactive Spower
, Lc , OT
cpower c , and Q
compensations, c are the cost
respectively. of substation,The annual land, cost Interest: NPV, The transmission
authors
Annuity declare line,(Ⱥ),
factor no and
(Ⱥ), 𝐶𝐶cost
conflict ,− ,are
ofofinterest. LATIN CAPITAL(
are
reactive
reactive
reactive transmission
𝑇𝑜𝑡𝑎𝑙
power
power compensations,
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
compensations,
compensations, system. The
𝑐𝑜𝑠𝑡 respectively.
respectively. respectively.
mathematical
𝑇𝑜𝑡𝑎𝑙 = 𝑆𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
+ The 𝐿
The + The
expressions
𝑂𝑇
annual
annual +annual
𝑇𝑜𝑡𝑎𝑙
𝑐𝑜𝑠𝑡 𝑄 cost
Nomenclature
cost for cost
(Ç),
(Ç), =the
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 Ç\textbarcapitalu
𝑆 (Ç),
NPV,
NPV, =
DCF
+ 𝑀NPV,
𝐿 ++ \textbarcapitalu
method
𝑐𝑜𝑠𝑡
Annuity
Annuity 𝐿𝑠Annuity
𝑂𝑇 + are
𝑄 =
factor
factor
(8) factor
given
𝑆 +
(Ⱥ),
(Ⱥ), 𝐿 as𝐶+
𝐶 ,
[8,35];
,𝑂𝑇 are
are [1 (Ð
in(8) 1)by]2019
+ idea, (10)
reactive power compensations, respectively. 0244
The annualland, Ʉ
0244 Ç ),=NPV,
Ʉ
cost (overhead 0241 𝑀 + Annuity
Funding: 𝐿𝑠 Ɂ Author
This work Contributions:
\textglotstopvari
factor was (Ⱥ),and=Cdacost
supported , are Core part data collec
LATINmajor (10
CAPITAL
expressed
where,
expressed
expressedas; as; 𝑆 as;
as;, 𝐿 , 𝑂𝑇 , and 𝑄 are the cost of substation, transmission line, of Ð
expressed where, 𝑆𝑇𝑜𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
, 𝐿 ,respectively.
𝑂𝑇 , and 𝑁𝑃𝑉 0245
𝑄 The 𝑐𝑜𝑠𝑡 Ʌ
0245 =𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 Ʌ
𝑆 of+power 𝐿 Education
0242 + 𝑂𝑇𝑐𝑜𝑠𝑡
\textturnedcapitalv ɂ
+ land, simulations,
𝑄Commission
\textturnedcapitalv M.G.;
\textglotstopvarii
(Grant resources,
number: supervision,
(8) 2019-01-07-00-02- N
=𝑃𝑐𝑜𝑠𝑡
LATIN CAPITAL
expressed
reactive as;
power compensations, Nomenclature
are the Active
𝑇𝑜𝑡𝑎𝑙
annual cost cost substation,
(Ç), NPV, (9)
Annuity overhead+software,
factor 𝐶 (Ⱥ), transmission
𝐶 , are(9) line, and (11) cost
𝑇𝑜𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑠𝑡 𝑇𝑜𝑡𝑎𝑙 = 𝑆𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
+ 𝐿ÇÇ0246 + 𝑂𝑇
𝑁𝑃𝑉 =𝐿𝑠𝐿𝑠 =
𝑇𝑜𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
Ɇ Ɇ𝑆 + 𝐿 + 𝑂𝑇 𝑐𝑜𝑠𝑡cost (Ç),
Ƀ collection, / +=𝐶(10) validation, M.H.N., (11
M.A.,
+=𝐿𝑠 𝑀𝑄++ + 0246 0243
\textstrokecapitale \textstrokecapitale \textbarcapitalb
reactive power compensations, ÇÇ==𝑀𝑀 + == 𝑀𝐿𝑠
M respectively.
LsReactive The
power
Conflicts annual /𝐶 NPV, ƤȺAnnuity
(10) +(10) (10)
[Ç (10) ∗ (1factor− no ɍ) − (ɗ ∗𝐶ɍ)]
LATIN
(Ⱥ),
CAPITAL
of,in
expressed as;
𝑇𝑜𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 0247 c 𝑃 0247
𝑐𝑜𝑠𝑡 ɇ c Active = ɇpower
0244 \textstrokee
\textstrokee
𝑆 + 𝐿 + 𝑂𝑇 Ʉof Interest: The
\textbarcapitalu (9)
authors declare conflict
LATIN SMALL L
ere, 𝑆 , 𝐿 , 𝑂𝑇 , and 𝑄where, are the 𝑆 , cost 𝐿 , 𝑂𝑇 , and 𝑄 as;
ofexpressed
substation, areland, theoverhead
cost of substation, Ç
transmission Annual [1
land, −
line, (Ð
overhead
cost +\textbarcapitalj
and cost ]
1)maintenance Funding:
transmission
of This work
line, andwas supported
cost of in part
(12) by
𝑁𝑃𝑉𝑁𝑃𝑉
NPV == =𝑇𝑜𝑡𝑎𝑙
𝑇𝑜𝑡𝑎𝑙 0248 where,
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
Total𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
investement 𝑄cost Ɉ𝑐𝑜𝑠𝑡
0248
𝑐𝑜𝑠𝑡 𝑀
ȺReactive
= stands [1
Ɉ/ 0245

power
\textbarcapitalj
+
+ (Ð
for
+ 𝐶
C 𝐶 + 1)ɅEducation ] \textturnedcapitalv
cost, 𝐿𝑠 (11) denotes
(11)
(11) the cost LATIN of (12lo
CAPITAL
ctive power compensations, reactive respectively.
power 𝑁𝑃𝑉
𝑁𝑃𝑉
compensations,
The = = 𝑇𝑜𝑡𝑎𝑙
𝑇𝑜𝑡𝑎𝑙
annual 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
respectively.
cost (Ç), Ç=
NPV, 𝑐𝑜𝑠𝑡
The𝑀
𝑐𝑜𝑠𝑡
Ⱥ Annuity+ 𝐿𝑠
annual Ⱥ
HVAC/DC
/ += +
factor
cost 𝐶
/ 𝐶 (Ç),
(Ⱥ), da
Nomenclature 𝐶
NPV, , Ð
Annuity
are factor (11)
(11)
Commission (Ⱥ), 𝐶 (10) ,
(Grant are number: 2019-0
where, 𝑆 , 𝐿 , 𝑂𝑇 , and 𝑄 are the cost ofh0249 substation,
shows Ç systemɉ
0249 Annuity
/land,
Annual \textbarjfactor
overhead
ɉ 0246
Çcost = 𝑀 +ƤȺ
lifetime, \textbarj Ɇ
transmission Ð line,
𝐿𝑠 is the present cost for Ⱥ, Ƴ represents an
\textstrokecapitale and cost of LATIN SMALL
(1L
Ð
i
ressed as; expressed as;
reactive power compensations, respectively. 1 −The( + Ɋ
annual 1 ) −t
Discount Ɋ factor ɇ Conflicts of Interest: 𝐶get
The , aare
authors declare (13) c
no
𝑁𝑃𝑉 = [1 𝑇𝑜𝑡𝑎𝑙
[1 − (Ð [1[1−
024A
+− (Ð
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
(Ð 1)(Ð 𝐶+
rate ]Ⱥ+]1)
024A
1)
and 𝑐𝑜𝑠𝑡 ] cost
+ [Ç(Ç),
] depreciation
= Annuity
ƤȺ 0247
\texthtcapitalq
(1𝑃
∗factor
/ ∗+
NPV,
− 𝐶ɍ) value,−Annuity
\texthtcapitalq
Active (ɗrespectively.
∗ ɍ)]power factor (Ⱥ),
\textstrokee To(12) (12)(11) more representat LATIN CAPITAL

Ⱥ = Ⱥ −
Ⱥ = =
= + 1) ɍ 𝐶 = ƤȺ + [Ç (1 − ɍ) − (ɗ ∗ ɍ)] (12)
(12) (12) (13
𝐿𝑠ÐÐ 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
Ⱥ= 024B ɋ
024B Taxation ɋ
\texthtq rate
0248 \texthtq Ɉ \textbarcapitalj (1L
expressed as; Ç𝑁𝑃𝑉 =Ð𝑀Ð =Ð+ 𝑇𝑜𝑡𝑎𝑙 𝑄 is𝑐𝑜𝑠𝑡 / to+be 𝐶 30 years, whereas theSMALL LATIN
Ç = 𝑀 + 𝐿𝑠 the transmission
Discount system
factor (10)
Reactiveassumed power (10) disc
where, 𝑀 stands for maintenance h[1 −ofɗ(Ð
024C cost,Ɍ
024C 𝐿𝑠
Depreciation Ɍ
denotes
0249
\textbarcapitalr the ɉ cost
valuetheNomenclature
\textbarcapitalr of losses,
\textbarj Ð is the discount factor, t
where, 𝑀 stands for maintenance ɍ13.25%
+ cost,
1) ]𝐿𝑠 17%,
and
Taxation denotes
irate Çrespectively, Annual cost cost are set for Ð
of losses, this is
(13) the discount
study
(12)
LATIN
[36,37]. factor,
CAPITAL

𝐶 𝐶 = = ƤȺƤȺ
ƤȺ Ⱥ =
+ + [Ç
is(1 Ç
[Ç ∗= ∗(1 𝑀
(1 − − +ɍ)
ɍ ɍ)𝐿𝑠
− − (ɗ(ɗ ∗ ∗ɍ)]
ɍ ɍ)]
) Ⱥ,−Ⱥ,
024A Ƴ Ɋ \texthtcapitalq costs, ɍ(13)
(13) (13) (10)
and ɗ are taxation
𝑁𝑃𝑉 = 𝑇𝑜𝑡𝑎𝑙 shows system
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
shows 𝐶𝐶 lifetime,
system = =𝑐𝑜𝑠𝑡
𝑁𝑃𝑉 C
ƤȺƤȺda =
lifetime,+=+[Ç [Ç∗/ƤȺ
𝑇𝑜𝑡𝑎𝑙 ∗+
(1 −is−𝐶ɍ)
the
024D ∗ɍ)
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
+ the
1−−(ɗ
present
(− (ɗ)∗Depreciation
024D
ɗpresent ∗− ɍ)]
cost
ɍ)] ( cost
𝑐𝑜𝑠𝑡 Ð∗for[1
\textbarr
=Ɏfor
Ⱥ\textbarcapitaly / Ⱥ value
represents
\textbarr
(Ð+ Ƴ+𝐶Annuity
1) 𝑃
(11)
represents ] annual (13)
annualpower
factor
Active costs, ɍ(11) and ɗ are taxatio
LATIN SMALL
(1
L

rate and depreciation value, 024E


respectively.
Abbreviations Ɏ
024E To get 024B
alosses, ɋ
\textbarcapitaly
more representative Ð discount
\texthtq reflection, the lifetime (t) of LATIN CAPITAL
where,
𝑀𝑀 stands 𝑀 𝑀 standsstands for
rate maintenance
and depreciation cost,
𝐿𝑠 𝐿𝑠𝐿𝑠
value, denotes
respectively. the cost To ofget Ð 𝐶Ð Ðisdiscount
is 𝑄the factor, t t the lifetime
/ÐÐ
where,
where, where,
where, stands
M for
formaintenance
for maintenance maintenance 𝑁𝑃𝑉cost,
cost,
cost, cost,
𝐿𝑠 = 𝑇𝑜𝑡𝑎𝑙denotes
denotes
Ls denotes
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 5.2.
the
the the
Investment
cost
cost ɏ−be of cost
𝑐𝑜𝑠𝑡
of of
losses,
losses, ɏCost losses,aAnalysis
+
is more
is
isthe Ɍ representative
Discount the
discount discount
factor factor,
Reactive
factor, reflection,
factor,t (13)
tpower
t shows (11) (t) o
c stands for
the maintenance
transmission 𝐶
system = denotes
cisƤȺ +
024F
assumed [Ç ∗the(1 to cost
024F ɍ) of

30 losses,

\textbary
years, ∗024C
ɍ)] the
\textbary
whereas discount
the \textbarcapitalr
discount factor (Ð) and the tax LATIN SMALL L
rate
shows
shows system
system lifetime,
lifetime, [1
ƤȺ ƤȺ − is(Ð
is +
the
the 1) ]
present
present cost
cost for
for [1
Ⱥ, Ⱥ,− Ƴ (Ð
Ƴ + 1)
represents
represents ] annual
annual (12)
costs,
costs,
ɍ∗\textturna ɍ ɍ andand ɗ ɗ are
are taxation
taxation (12) (1
showssystem
shows lifetime,ƤȺ
systemlifetime,
system ƤȺȺthe = transmission
isisthethepresent
presentcost
present system
cost Ð forȺ,Ⱥ
for Ⱥ, Ƴ Ƴrepresents
is,0250
=assumedAbbreviations
CPEC
represents
represents ɐ to =
𝐶
0250
VSC-HVDC
be
ChinaƤȺ30ɐ+
annual
annual years,
\textturna
annual Ðstudy [Ç
Pakistan
costs,
costs,
024D costs,
system
whereas
(1 ɍ− ɍTaxation
isɍ)
Economic
ɍand
and
and−Çɗ(ɗ
based ɗ\textbarr
the are discount
∗are ɍ)]
rateCorridor
Annual
are
on taxation
taxation
ataxation cost
relatively
factor ratenew (Ð) and the
technology,
tax ra
LATIN SMALL L
w
𝑀 of 13.25% and 17%, respectively, 𝐿𝑠 are set for this [36,37].
rateand
rate andrate
rate
and anddepreciation
where,
and
depreciation
depreciation depreciation
depreciation stands value,
value, offor
value, value,
maintenance
13.25%
value,
respectively.
respectively. respectively.
and
respectively. 17%,
respectively. ToTocost,
To get
get Ⱥ
getTo
respectively,
To a a= get[1
get
more
0251
more
a more −amore
denotes
aVSC (Ðmore
are +
ɑ setthe
representative
0251
representative
representative for ]\textscripta
1)representative
cost
representative
Voltage this of
ɑ 024E losses,
ɗ
study
source
reflection,
reflection,
reflection, ɎÐthe
reflection,
[36,37].
reflection,
converter is
Depreciation
\textscripta theȺthe the the the lifetime
discount
lifetime
\textbarcapitaly
lifetime
lifetime Annuity
lifetime value
(t)(t) of
(t) of (t)(t)the
factor,
factor
of of of t
(12) LATIN SMALL L

the transmission where, ƤȺ 𝑀is the stands for maintenance DCCPEC or AC


Ⱥ,whereasƳɒthecost, China𝐿𝑠
options.Ðdiscount However,
Pakistan
denotes Economic
the this
cost choice
ɍthe ofandCorridor
losses,may Ð
ɗthe
also is depend
the discount on thefacto econ
the shows
thetransmission
the transmission
transmission system
transmission 𝐶system
system
system =system
lifetime,
system
isƤȺ
isassumed
assumed
is is
is[Ç
+assumed ∗assumed
(1toto
assumed −be be
to to

30
30
be to𝐶(ɗ
ɍ)present be be∗30
years,
years,
30 30
cost
=ɍ)]
years, years,
years,
ƤȺ0252 for
+whereas
whereas
whereas [Ç
MMC whereas (1
∗ 0252
the represents
−the ɍ)thethe
− ɒ(ɗ
discount
discount
discount discount
024F annual
∗factor
\textturnscripta
Modular ɍ)] factor
ɏ(Ð)
(13)
factorcosts,
\textturnscripta
multilevel
factor factor (Ð) Ð
and
(and ) (Ð)
(Ð) and
and
\textbary
converter
and Discount
the tax
tax
the the are
rate
rate
tax taxtax
taxation
factor
rate rate
rate of(13) LATIN SMALL L

of13.25%
13.25%
rate and and 17%,
depreciation
5.2.
5.2.
Investment
shows system
Investment
respectively,
value,
Cost
Cost
are
Analysis
lifetime,
respectively. set Analysis
for ƤȺ
this
To0253 is In
study
get
VSC
the this
present regard,
ɓ High
[36,37].
a [36,37].
more
0253
Voltage
cost a forcost
ɓvoltage
representative
\m{b} 0250 Ⱥ,
source\m{b} Ƴ
analysis converter
represents
ɐ current
reflection,
is drawn
\textturna annual to
the lifetime
compare
costs, (t) ɍof
the
and ɗ
HVDC are and
taxati H
of of
of13.25%
13.25%
13.25% and
and 17%,
and and
17%, 17%, 17%,
respectively,
respectively, respectively,
respectively, areare
are setsetare for
for
set set
𝐶 this
this
for for
=
this
study
study
this ƤȺstudy+
studyHVDC
[36,37].

[36,37]. ∗ (1
[36,37]. − ɍ) − (ɗ ∗ Abbreviations
ɍ)] direct ɍ generation Taxation rate815 (13) LATIN SMALL L
ere, 𝑀 stands for maintenance where, 𝑀 cost, stands 𝐿𝑠
rate fordenotes
maintenance
and the cost
depreciation tocost,of 30 𝐿𝑠years,
losses, better
MMC
denotesÐ is the option Modular
the\m{b} for
discount
cost a 3500
multilevel
of a\m{b}
losses,
factor, MW Ðt is\textscripta
converter
the and discount over factor, km overhead
t lifetime (t) tra
the transmission system
VSC-HVDC is assumed system beisvalue,
based respectively.
HVACon whereas
a relativelyHigh
To
the get
0251discount
new
voltage
more ɑ factor
technology,
alternate
representative
ɗcurrent (Ð)which makes
current
Depreciation the reflection,
tax itrate
value better the than other
ws system lifetime, ƤȺ shows
is the system
present lifetime,
cost
the VSC-HVDC
for ƤȺ
Ⱥ,
transmission Ƴis system
represents
the present
system iscost
based
annual
is considered
for
assumedHVDC on Ƴatoɍrelatively
Ⱥ,
costs, High\texthtb
in
represents
and
be 30 ɗ
thisvoltage
are
years, new
work
CPEC \texthtb
annual technology,
taxation is
direct
ɒ
whereas comprised
China
costs, the ɍ which
Pakistan
and of
discount ɗbipolarmakes
Economic
are taxation
factor it(Ð)better
ground-return
Corridor than
andsystems.
the tax othe
tran r
5.2. where,
5.2.
of
5.2.Investment
5.2. Investment
Investment
13.25%
InvestmentCost 𝑀 and stands
CostAnalysis Cost
Cost 17%,
AnalysisDC or for
Analysis
Analysis AC maintenance
respectively,
options. are cost,
However,set for 𝐿𝑠 this denotes
study
choice
LCC the
[36,37].
may Line cost
also
\textbhook
0252
of
depend
commutated losses,
\textbhook on Ðthe is \textturnscripta
the
economic
converter discount aspects factor, of the t two
e and depreciation value, rate respectively.
and
shows systemIn depreciation DC To or
of 13.25%
lifetime,
AC
getvalue,
ƤȺ is a options.
more
and However,
respectively.
representative
17%, respectively, To thisthe
HVAC
get choice
cable
reflection,
a
Ⱥ,are more
ɔƳtoset
may also
cross-section
High voltage
representative
forthe depend
VSC
lifetime
0253
ɔthis study of ɓ
(t) 4
alternate on× 125
the
Voltage
reflection,
of
[36,37]. \m{b} 𝑚𝑚
economic
current
ɍ HVAC sourcethe
and ɗ are . A aspects
substation
converter
lifetime (t)of ofthe
with two system
voltage-ra
this regard, athecost present
analysis cost isfor
0254 drawn
DCF 0254 represents
\m{o}
compare
Discounted annual
the \m{o}HVDC
cash costs, and
Abbreviations
flow systems taxation to determine the L
LATIN SMALL

transmission system VSC-HVDC


VSC-HVDC is
theVSC-HVDC
VSC-HVDC
assumed system
transmission
system to system
system
beIn
is is 30this
based
system
based isis
years, based
regard,
based
onon
is a a
whereasaon
on aarelatively
cost
relatively
assumed
relatively relatively
analysis
theto new
be
discount
new 30 is
newnew
each
LCCdrawn
technology,
years,
technology, factortechnology,
technology,
of the
whereasto
(Ð) compare
proposed
Linewhich
which and
\textopenothe which
which
commutated
MMC
makes
the the
discount
makes tax
\textopeno makes
HVDC
makes
locations,it it
rate better itmethod
factor
better itand
\m{b} better
better
i.e.,
converter
Modular than
than(Ð) HVAC
Gwadar than
multilevel than
other
and
other the other
systems
other
and tax Matiari.
converterrate to determine th
rateInvestment
5.2. and depreciation Cost Analysis
better value,for
option respectively.
a 3500may MWalso Togeneration
get
NPV a moreover Netrepresentative
815
present km overhead
value reflection, the lifetime
transmission
\texthtb line. (t) of The DC system
3.25% and 17%, DCDCor orDCDC
AC ororACACoptions.
options.
respectively,
AC of 13.25%
options. options.
areHowever,
and
However, However,
better
setHowever,
17%,
for 5.2. this
this option thischoice
this
choice
Investment
respectively,
study
choice choice
formay
Cost
[36,37].
may aare 3500
may
also
also Analysis
set MWthis
also
depend
for
depend depend
generation
depend
DCF
on on
studythethe on on
Nevertheless, the
the
economic
[36,37].
economic economic
\textoopen
over economic
Discounted 815 the
HVDC \textoopen
aspects
aspects km aspects
overhead
aspects
HVAC
cash ofofflowtheof
High
CPEC
the twoof the
systems
method the
voltage
two two two
transmission
systems.
China
systems.
\textbhook are systems.
systems.
direct proposed
Pakistan line.Economic
current The
to be DC500 system
CorrikV
the transmission system
considered isinassumed
this work to isbe 30
comprised years,
0255 Cda whereas
ɕof
0255 bipolar ɕthe
\textctc
Discounted discount
ground-return
\textctc
annual factor
cost (Ð)
transmission and the tax
lines rate
at 350 kV LATIN having
In In
this In this
this
regard, regard,
VSC-HVDC
regard,
a cost a a cost
cost
analysis systemanalysis
considered
analysisis is
drawn is is
based
in drawn
this
drawnto on worka
to
compare
In this regard, a cost analysis is drawn to compare the HVDC and HVAC systems to determine the to compare
relatively
is
compare comprised
the the the
new
analyzed
NPV
HVDC HVDC
HVDC technology,
of
and bipolar
based
Net and
HVAC and
present
0254 HVAC
HVAC
onHVAC which
ground-return
the
systemsvalue systems
makes
systems
ɔ
transmission
High
to
VSC it
to to
voltage
determine
\m{o} determine
better
transmission
determine
system
Voltage than
alternate
the thethe
other
lines
components.
source at
current 350
converter kVThese
SMALL L
havin co
Electronics 2019, 8, 1305 10 of 14

5.2. Investment Cost Analysis


VSC-HVDC system is based on a relatively new technology, which makes it better than other DC
or AC options. However, this choice may also depend on the economic aspects of the two systems.
In this regard, a cost analysis is drawn to compare the HVDC and HVAC systems to determine the
better option for a 3500 MW generation over 815 km overhead transmission line. The DC system
considered in this work is comprised of bipolar ground-return transmission lines at 350 kV having the
cable cross-section of 4 × 125 mm2 . A substation with voltage-rating 350 kV is to be installed at each of
the proposed locations, i.e., Gwadar and Matiari.
Nevertheless, the HVAC systems are proposed to be 500 kV grid at both ends. The cost is analyzed
based on the transmission system components. These components are the substations, transmission
lines conductors, installation, and land expenses, as illustrated in Table 3 (cost/component is calculated
in a million US dollars “$M”). STATCOM expenses are also included in the case of HVAC. It can be
seen that despite the higher price of HVDC substations, the total price is kept low due to the cheaper
overhead transmission line equipment and absence of STATCOM. The total cost required for an 815 km
AC transmission line is 1201 $M, with a cost of 1.47 $M/km, which is 1.35 times of HVDC line cost.

Table 3. HVAC and HVDC systems investment cost comparison [8,9,38].

Transmission Systems
Components
HVAC Cost ($M) HVDC Cost ($M)
Substation 343 490
Land use 65 65
STATCOM 189 Nil
Overhead system 1201 889
Total price 1798 1445

5.3. Annual Cost


The system maintenance costs and losses each year will account for the annual cost of the system.
The annual maintenance cost is considered to be 0.5% of the total components cost. These components
are the substations costs, cable installment costs, and STATCOM costs in case of the HVAC system.
The annual maintenance costs of the HVDC and HVAC systems are found to be 4.45 $M and 3.37 $M,
respectively. The VSC based HVDC systems have comparatively higher losses, with a percentage of
1.8% for each station. In the case of two stations, 3.6% of the total power flow is considered, which is
found to be 52.02 $M. In the case of HVAC systems, 5% of total power flow is considered to be the loss.
Hence, 89.92 $M is computed to be the loss’s cost for HVAC systems. As a result, the annual costs for
HVDC and HVAC systems are calculated to be 56.48 $M and 94.3 $M, respectively.

5.4. Discounted Cash Flow (DCF) Analysis


From the perspective of transmission systems, the DCF analysis results presented in Figure 9,
are of great significance. It shall be noted that on a lifetime basis, the HVDC system is cheaper than
the HVAC system. As compared to the investment costs, the higher difference in NPV is due to the
significant difference in the annual costs. It must be stated that the VSC based HVDC systems are still
evolving and are expected to be more feasible in the future.
5.4. Discounted Cash Flow (DCF) Analysis
From the perspective of transmission systems, the DCF analysis results presented in Figure 9,
are of great significance. It shall be noted that on a lifetime basis, the HVDC system is cheaper than
the HVAC system. As compared to the investment costs, the higher difference in NPV is due to the
significant
Electronics difference
2019, 8, 1305 in the annual costs. It must be stated that the VSC based HVDC systems11are still
of 14
evolving and are expected to be more feasible in the future.

Figure DCF
9. 9.
Figure analysis
DCF comparison
analysis of of
comparison HVAC and
HVAC HVDC.
and HVDC.

5.5. HVDC Systems’ Economics Comparison


5.5. HVDC Systems’ Economics Comparison
It is difficult to determine the exact cost of an HVDC system because each project has different
It is difficult to determine the exact cost of an HVDC system because each project has different
features and circumstances, such as rated power, line distance, terrain, and used technology. However,
features and circumstances, such as rated power, line distance, terrain, and used technology.
an overall estimate can be obtained based on the knowledge from previous projects. In particular,
However, an overall estimate can be obtained based on the knowledge from previous projects. In
the Chongqing-Hubei back-to-back DC grid interconnection project in China was the first distinct
particular, the Chongqing-Hubei back-to-back DC grid interconnection project in China was the first
VSC-HVDC line with the highest voltage capacity of 420 kV and the largest power transmission capacity
distinct VSC-HVDC line with the highest voltage capacity of 420 kV and the largest power
of 5000 MW, covering the total distance of 1711 km [39,40]. The project cost was 1498.36 $M, which is
transmission capacity of 5000 MW, covering the total distance of 1711 km [39,40]. The project cost
roughly 0.9 $M/km. Accordingly, the cost of 1.3 $M/km was calculated for South Australia to Queensland
was 1498.36 $M, which is roughly 0.9 $M/km. Accordingly, the cost of 1.3 $M/km was calculated for
400 kV HVDC line in Australia with a length of 1450 km [41]. The Southern Hami-Zhengzhou (SHZ)
South Australia to Queensland 400 kV HVDC line in Australia with a length of 1450 km [41]. The
HVDC line is one of China’s large-scale HVDC projects (800 kV, 8000 MW), which is stretched from
Southern Hami-Zhengzhou (SHZ) HVDC line is one of China’s large-scale HVDC projects (800 kV,
Xinjiang province in the northwest down to Henan province in central China. The project cost reached
8000 MW), which is stretched from Xinjiang province in the northwest down to Henan province in
3500 $M and about 1.8 $M/km. Whereas a slight decrease in the cost of 1.7 $M/km was incurred for the
central China. The project cost reached 3500 $M and about 1.8 $M/km. Whereas a slight decrease in
Lingzhou-Shaoxing HVDC line (with the same ratings of SHZ line) due to its shorter line coverage of
the cost of 1.7 $M/km was incurred for the Lingzhou-Shaoxing HVDC line (with the same ratings of
1722 km as compared to SHZ line distance, which is 2200 km [42,43].
SHZ line) due to its shorter line coverage of 1722 km as compared to SHZ line distance, which is 2200
Furthermore, Pakistan’s first-ever HVDC Line Matiari to Lahore with a rated power of 4000 MW
km [42,43].
and voltage of 660 kV, spanning 878 km, is in progress by the cooperation of State Grid Corporation
Furthermore, Pakistan’s first-ever HVDC Line Matiari to Lahore with a rated power of 4000 MW
of China (SGCC) and Ministry of Water and Power Pakistan under the vision of CPEC. The project
and voltage of 660 kV, spanning 878 km, is in progress by the cooperation of State Grid Corporation
estimated cost is 1658.34 $M (approximately 1.9 $M/km) [44]. Similarly, this study provides an estimated
cost of 1.7 $M/km for the proposed HVDC line, which is reasonably comparable to the cost of previously
selected HVDC projects. Hence, the proposed HVDC model is economically sustainable and a better
choice for the future transmission projects in Pakistan.

6. Conclusions
The southwestern region of the country is expected to become a hub for economic and industrial
development due to CPEC projects. Conversely, power shortage and energy security are critical factors
in this area and should be solved promptly to enhance the CPEC projects and other economic activities.
In this context, a study of technical and economic aspects of a proposed two-terminal VSC-HVDC
transmission line is carried out. The simulation results for the power, voltage, and current waveforms
are found stable and reliable at the receiving end. The DCF analysis shows that the net present value
of the HVDC system is lower as compared to the HVAC system. The NPV for HVAC is found to
be 3725 $M, while the HVDC NPV was 2599 $M. Moreover, the cost/km of the proposed model is
relatively analogous to selected existing HVDC projects. Therefore, HVDC proves to be a realistic and
feasible transmission system.
HVDC transmission line is carried out. The simulation results for the power, voltage, and current
waveforms are found stable and reliable at the receiving end. The DCF analysis shows that the net
present value of the HVDC system is lower as compared to the HVAC system. The NPV for HVAC
is found to be 3725 $M, while the HVDC NPV was 2599 $M. Moreover, the cost/km of the proposed
EER REVIEW model is relatively
Electronics 2019, 8, 1305 analogous to selected existing HVDC 10 projects.
of 15 Therefore, HVDC proves to be a 14
12 of
realistic and feasible transmission system. 10 of 15
re accounted for theFurther annualresearch
cost; here, reliability
should be carried and insurance
out by consideringfactors are the socio-economic impact of such
isannual
REVIEW result is cost; here,
the difference
projects. reliability
Further
of NPVs
Similarly, andofcomprehensive
research insurance
should factors
mentioned be carried
transmission areout
studies by considering
line-technologies,
comprising 10 ofof15furtherthe socio-economic impact of such
technical considerations andprojects.
legal
snce theofdiscounted
NPVs of mentioned Similarly,
annual transmission
comprehensive
cost (Cda) and line-technologies,
studies
initial comprising
investment of
cost further
(C
requirements of HVDC systems can be carried out for the real-time implementation of the project. i) fortechnical
each considerations and legal requirements
ual mathematical
ccounted
The cost (Cda)
for the and annual
of initialcost;
HVDC
expressions investment
here,
systems
for thecan DCF cost
reliability (Ci)and
be method
carried forout
areeach
insurance
for
given theas factors
[8,35]; are
real-time implementation of the project.
Author Contributions: Core idea, data collection, formal analysis, writing the original draft, software, and
pressions
sult is thefor the DCFofmethod
difference NPVs of are given as [8,35];
mentioned transmission line-technologies,
𝑇𝑜𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 Author𝑐𝑜𝑠𝑡
simulations, M.G.;=resources,
Contributions: 𝑆 + 𝐿Core + supervision,
𝑂𝑇
idea,+data 𝑄 collection,
N.T.; methodology,
formal analysis, (8)review & editing,
writing validation,
the original W.H.; data
draft, software, and
discounted USV annual
Symbol costMacro(s)
(Cda) and initial investment cost (C i) for each
Description
𝑛𝑡 𝑐𝑜𝑠𝑡 = 𝑆 +simulations,
𝐿 + 𝑂𝑇 + M.G.;
collection, 𝑄
software, validation, M.H.N.,
resources, supervision, (8)N.T.; methodology, review & editing, validation, W.H.; data collection,
M.A., and M.Y.
mathematical expressions software,𝑐𝑜𝑠𝑡 for the DCF
validation, method are and given as [8,35]; (9)
𝑇𝑜𝑡𝑎𝑙
0241 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 Ɂ
Funding: \textglotstopvari
This work was =M.H.N., + 𝐿 M.A.,
𝑆supported + 𝑂𝑇 M.Y.
in part by 2019 major scientific LATIN research and
CAPITAL LETTER innovation
GLOTTAL STOP project of Shanghai
𝑚𝑒𝑛𝑡 𝑐𝑜𝑠𝑡 (9)
𝑇𝑜𝑡𝑎𝑙 0242 =Education
𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 𝑆 Funding:
ɂ+ 𝑐𝑜𝑠𝑡𝐿 +\textglotstopvarii
𝑂𝑇 =
This 𝑆
Commissionwork+ 𝐿 was +
(Grant𝑂𝑇 +
supported 𝑄
number: in2019-01-07-00-02-E00044).
part by 2019 major scientific (8) research and STOP
innovation project of Shanghai
nd 𝑄 are the costEducation
LATIN SMALL LETTER GLOTTAL
of substation, Commissionland, overhead
(Grant number: transmission line, and cost of
2019-01-07-00-02-E00044).
0243 Ƀ \textbarcapitalb LATIN CAPITAL LETTER B WITH STROKE
substation,
ensations, land,
respectively. overhead
Conflicts The transmission
annual cost line,
(Ç), and
NPV, cost
Annuity
of Interest: The authors declare no conflict of interest. of factor (Ⱥ), (9) 𝐶 , are
𝑇𝑜𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
0244 Ʉ 𝑐𝑜𝑠𝑡
Conflicts =
\textbarcapitalu
of Interest: 𝑆 + 𝐿
The + 𝑂𝑇
authors declare no conflict of interest. LATIN CAPITAL LETTER U BAR
y. The annual cost (Ç), NPV, Annuity factor (Ⱥ), 𝐶 , are
0245 Ʌ \textturnedcapitalv LATIN CAPITAL LETTER TURNED V
are the0246 cost ofNomenclature
substation,
ɆNomenclature land,
\textstrokecapitaleoverhead transmission line, and cost of
Ç = 𝑀 + 𝐿𝑠 LATIN CAPITAL LETTER E WITH STROKE
(10)
ions, respectively.
0247 ɇ The annual
\textstrokeecost (Ç), NPV, Annuity factor (Ⱥ), 𝐶 , are
Ç = 𝑀 + 𝐿𝑠 P𝑃 Active power
Active power
(10) LATIN SMALL LETTER E WITH STROKE

𝑁𝑃𝑉 0248
= 𝑇𝑜𝑡𝑎𝑙 Ɉ 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡
\textbarcapitalj (11)
𝑐𝑜𝑠𝑡
Reactive power / + 𝐶
LATIN CAPITAL LETTER J WITH STROKE
Q𝑄 Reactive power
0249
𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑠𝑡 Ç =/ 𝑀Annual ɉ \textbarj
++𝐶𝐿𝑠 cost (11) LATIN SMALL LETTER J WITH STROKE

024A Ɋ [1 \texthtcapitalqAnnual cost (10)LATIN CAPITAL LETTER SMALL Q WITH HOOK TAIL
− (Ð + 1) ] (12)
024B ɋȺ = Annuity Annuity
\texthtq factor Ð
factor
[1 −
𝑁𝑃𝑉 (Ð= + 1)
𝑇𝑜𝑡𝑎𝑙 ]𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑠𝑡 + 𝐶 (12) (11)
LATIN SMALL LETTER Q WITH HOOK TAIL

= 024C ÐɌ Ð Discount factor


\textbarcapitalr
Discount /
factor LATIN CAPITAL LETTER R WITH STROKE

024D 𝐶 =ɍɍƤȺ +Taxation (1 −rate


[Ç ∗Taxation
\textbarr ɍ) −rate (ɗ ∗ ɍ)] (13)
LATIN SMALL LETTER R WITH STROKE
[1
Ⱥ + [Ç ∗ (1 − ɍ)Ⱥ−=(ɗɗ ∗ ɍ)]Depreciation
024E Ɏ − (Ð + 1) ]
\textbarcapitaly (13) (12)
Depreciation
Ð value value LATIN CAPITAL LETTER Y WITH STROKE
maintenance 024F cost,ɏ 𝐿𝑠 denotes \textbarythe cost of losses, Ð is the discount factor, t
LATIN SMALL LETTER Y WITH STROKE
𝑠, ƤȺ denotes
is the
0250
the cost of
presentAbbreviations
ɐ cost for losses,
\textturna
Ð
Ⱥ, Ƴ represents annual costs, ɍ and ɗ are(13)
is the discount factor, t taxation
st = ƤȺ
𝐶Ƴ represents
for Ⱥ,respectively. + [Ç ∗annual
Abbreviations (1 − ɍ)costs,
− (ɗ ∗ɍ ɍ)] and ɗ are taxation
LATIN SMALL LETTER TURNED A

value, 0251 ɑ To get a more representative


\textscripta reflection, the lifetimeLATIN (t) SMALL
of LETTER ALPHA
To get
ntenance a more
cost, 𝐿𝑠 CPEC
representative
ɒ
CPEC denotes China
the China
reflection,
Pakistan
cost of Pakistan
theEconomic
losses, Ð
Economic
lifetime is
em is assumed to be 30 years, whereas the discount factor (Ð) and the tax rate LETTER TURNED ALPHA
0252 \textturnscripta (t) Corridor
of
Corridor
the discount factor, t
LATIN SMALL

30 isyears,
spectively, whereas
0253
the present ɓVSC
setVSC
are cost theforthis
for Ⱥ,\m{b}
discount
Voltage
study Voltage
Ƴ represents
factor source
[36,37]. (Ð) source
and
converter
annual converter
the
costs,tax ɍrate and ɗ are taxation LATIN SMALL LETTER B WITH HOOK

MMC \m{b} Modular multilevel converter


ue, this study [36,37].
respectively. MMC
To get a moreModular multilevel converter
representative reflection, the lifetime (t) of
HVDC \texthtb High voltage direct current
nalysis
s assumed to be 30 HVDC High voltage
years,\textbhook
whereas direct current
the discount factor (Ð) and the tax rate
0254
HVAC
ɔ \m{o}
High voltage alternate current
tively, are set forHVAC this study High voltage alternate current
[36,37]. LATIN SMALL LETTER OPEN O
em is based on a relatively LCC \textopeno new Line technology,
commutated which makes it better than other
converter
tively new LCC which
technology, Line makes
commutated converter
wever, this choice may also
DCF \textoopen
depend on it
Discounted the bettercashthan
economic other
flowaspects
method of the two systems.
is
y also 0255 on the
depend DCFɕ
NPV economicDiscounted
\textctc aspects
Net cash
of
present the flow
two
value method
systems. LATIN SMALL LETTER C WITH CURL
analysis is drawn to compare the HVDC and HVAC systems to determine the
ompare 0256
theaHVDC ɖ
NPVCda andnew Net
\M{d}
HVAC present
Discounted
systems valueto annual
determine cost the LATIN SMALL LETTER D WITH TAIL
s00 based
MW on relatively
generation over 815 technology,
km
\textrtaild overhead which makes
transmission it better
line. than
The DC othersystem
Cda Discounted annual cost
verthis
er,
rk is815 km overhead
choice
comprised may ofCalsobipolar
i transmission
depend onInitial
ground-return
\textdtail theline.investment
The
economic DC cost
system
aspects
transmission of the at
lines two 350 systems.
kV having
C ɗS ic Initial investment
Cost of substationcost
polar
nysis of is4× 125 𝑚𝑚
0257
ground-return
drawn to compare
. A substation\m{d}
transmission
the HVDC with lines
and atHVAC
350 kVsystems
voltage-rating having
350 kV toisdetermine
to be installed the at
LATIN SMALL LETTER D WITH HOOK

substation with 𝑆 L c
voltage-rating Cost
\texthtd of
350 substation
CostkV ofisland
to be installed at
MW generation
ocations, i.e., over
Gwadar 815
and km overhead
Matiari. transmission line. The DC system
𝐿OTc \textdhook Cost ofCost landof overhead transmission line
er comprised
and
HVAC Matiari. of bipolar
systems
0258 ground-return
\textreveto betransmission
ɘare proposed 500 kV gridlines at both at 350 ends.kV having
The cost is LETTER REVERSED E
LATIN SMALL
𝑂𝑇 Q c Cost Cost
of overhead of reactive power compensations
transmission line
he4 proposed
×transmission
125 𝑚𝑚 0259to ə500 kV\schwa
. Abesubstation
system grid
withatvoltage-rating
components. bothThese ends. The
350cost
components kV isistoare be theinstalled at
substations,
LATIN SMALL LETTER SCHWA

m components. 𝑄These components Cost of reactive


\textschwa power compensations
ions, i.e., Gwadar
onductors,
025A ɚ
and Matiari.
installation,
Appendix and A land are
\m{\schwa}
the
expenses, substations,
as illustrated in Table 3
LATIN SMALL LETTER SCHWA WITH HOOK
ion,
VAClculated andin land
systems are expenses,
a million proposed as be
to illustrated
US \texthookabove{\schwa}
dollars “$M”).500 kV grid
STATCOM in at Tableboth 3ends.are
expenses The alsocost is
included
The following parameters are used to build the simulation model.
US
It candollars
ansmission be seen “$M”).
system STATCOM
that despite expenses
\textrhookschwa
components.
the higher Theseprice are ofalso
components
HVDC included are the substations,
substations, the total price
uctors,
cheaper 025B
pite the overhead
higher
installation,price ɛtransmission
ofand\m{e}
HVDC land substations,
lineexpenses,
equipment the total
asand price
illustrated
absence ofin Table LATIN
STATCOM. 3used
TheSMALL LETTER OPEN E
\textepsilon Table A1. System’s parameters for simulation.
nsmission
ated
an 815 in akm line
ACequipment
million US dollars
transmission and absence
“$M”).
line
\texteopen is STATCOM
1201 of$M,STATCOM.
withexpenses
a costTheof are1.47
also$M/km,
included which
mission
nlinebe seen line
cost. thatisdespite
1201 $M, \textniepsilon
thewith
higher a costprice of of1.47 $M/km,
HVDC which
System Capacity
substations, the total price 400 MVA
025C ɜ \textrevepsilon
per overhead transmission line equipment and absence of STATCOM. The Line Current LATIN SMALL1 LETTER
kA REVERSED OPEN E
025D ɝ \texthookabove{\textrevepsilon}Line Voltage 400LETTER
LATIN SMALL kV REVERSED OPEN E WITH HOOK
e 3. HVAC
815 km ACand HVDC systems
transmission line investment
is 1201 $M,
\textrhookrevepsilon
cost
withcomparison
a cost of [8,9,38].
1.47 $M/km, which 400 MW
Active Power
systems
cost. investment
025E ɞcost comparison [8,9,38].
\textcloserevepsilon
Transmission Systems Distance 800LETTER
LATIN SMALL Km CLOSED REVERSED OPEN E
Components 025F
TransmissionHVAC ɟ \B{j}
Systems R L LATIN0.0256 Ω/Km
SMALL LETTER DOTLESS J WITH STROKE
Cost ($M) HVDC Cost ($M)
\textbardotlessj
HVAC and HVDC systems investment cost comparison [8,9,38]. LL 468 µH/Km
VAC Cost ($M) HVDC\textObardotlessj
Substation Cost
343 ($M) 490 CL 0.0124 µF/Km
Land 0260
343 use ɠ \texthookabove{g}
490
Transmission
65 Systems 65 LATIN SMALL LETTER G WITH HOOK
mponents \texthtg
65 0261 HVAC
STATCOM Cost
ɡReferences 65($M) HVDC CostNil
189
\textscriptg
($M) LATIN SMALL LETTER SCRIPT G

Overhead 189
ubstation0262 system ɢ 343\textscg Nil
1201 490 889 LATIN LETTER SMALL CAPITAL G

Land 1201
useprice
Total 0263 ɣ1. Rehman, 889
65\m{g}
1798 A.; Deyuan, 65 1445
Z. Pakistan’s energy scenario: ALATIN forecast of commercial
SMALL LETTER GAMMA energy consumption and
TATCOM 1798 189\textbabygamma
1445from different sources
supply Nil through 2030. Energ. Sustain. Soc. 2018, 8, 26. [CrossRef]
\textgammalatinsmall
head system 1201\textipagamma 889
otal price0264 ɤ 1798 \textramshorns 1445 LATIN SMALL LETTER RAMS HORN

0265 ɥ \textturnh LATIN SMALL LETTER TURNED H


Electronics 2019, 8, 1305 13 of 14

2. Gul, M.; Tai, N.; Huang, W.; Nadeem, M.H.; Yu, M. Assessment of Wind Power Potential and Economic
Analysis at Hyderabad in Pakistan: Powering to Local Communities Using Wind Power. Sustainability
2019, 11, 1391. [CrossRef]
3. Kamran, M. Current status and future success of renewable energy in Pakistan. Renew. Sustain. Energy Rev.
2018, 82, 609–617. [CrossRef]
4. Adnan, S.; Khan, A.H.; Haider, S.; Mahmood, R. Solar energy potential in Pakistan. J. Renew. Sustain. Energy
2012, 4, 032701. [CrossRef]
5. National Renewable Energy Laboratory (NREL), International Data. Available online: https://www.nrel.gov
/gis/data-international.html (accessed on 24 October 2019).
6. Province Wise Provisional Results of Census—2017. Available online: http://www.pbs.gov.pk/sites/default/f
iles/PAKISTAN%20TEHSIL%20WISE%20FOR%20WEB%20CENSUS_2017 (accessed on 20 May 2019).
7. Pakistan Transmission Lines. Available online: https://maps.nrel.gov/rede-pakistan/ (accessed on
24 October 2019).
8. Hur, D. Economic considerations underlying the adoption of HVDC and HVAC for the connection of an
offshore wind farm in Korea. J. Electr. Eng. Technol. 2012, 7, 157–162. [CrossRef]
9. Meah, K.; Sadrul, U. Comparative evaluation of HVDC and HVAC transmission systems. In Proceedings of
the 2007 IEEE Power Engineering Society General Meeting, Tampa, FL, USA, 24–28 June 2007.
10. Rudervall, R.; Charpentier, J.P.; Sharma, R. High voltage direct current (HVDC) transmission systems
technology review paper. Energy Week 2000, 2000, 1–19.
11. Candelaria, J.; Park, J.D. VSC-HVDC system protection: A review of current methods. In Proceedings of the
2011 IEEE/PES Power Systems Conference and Exposition, Phoenix, AZ, USA, 20–23 March 2011; pp. 1–7.
12. Ahmad, M.; Wang, Z. A Hybrid DC Circuit Breaker with Fault-Current-Limiting Capability for VSC-HVDC
Transmission System. Energies 2019, 12, 2388. [CrossRef]
13. Yang, Q.; Blond, S.-L.; Aggarwal, R.; Wang, Y.; Li, J. New ANN method for multi-terminal HVDC protection
relaying. Electr. Power Syst. Res. 2017, 148, 192–201. [CrossRef]
14. Li, J.; Yang, Q.; Mu, H.; Blond, S.-L.; He, H. A new fault detection and fault location method for multi-terminal
high voltage direct current of offshore wind farm. Appl. Energy 2018, 220, 13–20. [CrossRef]
15. Nadeem, M.; Zheng, X.; Tai, N.; Gul, M. Identification and Isolation of Faults in Multi-terminal High Voltage
DC Networks with Hybrid Circuit Breakers. Energies 2018, 5, 1086. [CrossRef]
16. Nadeem, M.; Zheng, X.; Tai, N.; Gul, M.; Tahir, S. Analysis of propagation delay for multi-terminal high voltage
direct current networks interconnecting the large-scale off-shore renewable energy. Energies 2018, 8, 2115.
[CrossRef]
17. Zhang, X.; Tai, N.; Wu, P.; Fan, C.; Zheng, X.; Huang, W. A New Theory for Locating Line Fault in Power
System: Theoretical Part. IEEE Access 2019, 7, 37–46. [CrossRef]
18. Bahrman, M.-P.; Johnson, B.-K. The ABCs of HVDC transmission technologies. IEEE Power Energy Mag. 2007,
5, 32–44. [CrossRef]
19. Povh, D. Use of HVDC and FACTS. IEEE 2000, 88, 235–245. [CrossRef]
20. Agelidis, V.G.; Demetriades, G.D.; Flourentzou, N. Recent advances in high-voltage direct-current power
transmission systems. In Proceedings of the 2006 IEEE International Conference on Industrial Technology
(ICIT), Mumbai, India, 15–17 December 2006; pp. 206–213.
21. Committee IT and D. HVDC Project Listing 2006. Available online: http://www.ece.uidaho.edu/hvdcfacts/P
rojects/HVDCProjectsListingDec2006.pdf (accessed on 12 May 2019).
22. List of HVDC Projects. Available online: https://ipfs.io/ipfs/QmXoypizjW3WknFiJnKLwHCnL72vedxjQkD
DP1mXWo6uco/wiki/List_of_HVDC_projects.html (accessed on 24 October 2019).
23. Rashid, M. Power Electronics Hand Book, 3rd ed.; Butterworth Heinemann, Elsevier: Waltham, MA, USA, 2011.
24. ABB. High-Voltage Direct Current Transmission. Available online: https://new.abb.com/systems/hvdc
(accessed on 24 October 2019).
25. Flourentzou, N.; Agelidis, V.-G.; Demetriades, G.-D. VSC-based HVDC power transmission systems:
An overview. IEEE Trans. Power Electron. 2009, 24, 592–602. [CrossRef]
26. Raza, A.; Xu, D.-G.; Su, X.-W.; Li, W.-X. Invasion of high voltage direct current till 2014. In Proceedings
of the 2014 IEEE International Conference on Control Science and Systems Engineering, Yantai, China,
29–30 December 2014.
27. CPEC-Projects. Available online: http://cpec.gov.pk/progress-update (accessed on 20 May 2019).
Electronics 2019, 8, 1305 14 of 14

28. Shaikh, F.; Ji, Q.; Ying, F. Prospects of Pakistan–China energy and economic corridor. Renew. Sustain.
Energy Rev. 2016, 59, 253–263. [CrossRef]
29. Pakistan, Saudi Arabia Oil Project. Available online: https://tribune.com.pk/story/1913551/1-pakistan-saudi-
arabia-agree-form-jwg-oil-projects/ (accessed on 23 May 2019).
30. Qatar Investment in CPEC Gwadar. Available online: https://tribune.com.pk/story/1889424/1-qatar-express
es-interest-cpec-investment-gwadar/ (accessed on 23 May 2019).
31. Chaudhuri, N.; Chaudhuri, B.; Majumder, R.; Yazdani, A. Multi-Terminal Direct-Current Grids: Modeling,
Analysis, and Control; Wiley-IEEE Press: Hoboken, NJ, USA, 2014.
32. Le Blond, S.; Bertho, R.; Coury, D.V.; Vieira, J.C.M. Design of protection schemes for multi-terminal HVDC
systems. Renew. Sustain. Energy Rev. 2016, 56, 965–974. [CrossRef]
33. Akagi, H.; Edson, H.-W.; Mauricio, A. Instantaneous Power Theory and Applications to Power Conditioning;
John Wiley & Sons: Hoboken, NJ, USA, 2017.
34. Jiang, B.-K.; Wang, Z.-X. The key technologies of VSC-MTDC and its application in China. Renew. Sustain.
Energy Rev. 2016, 62, 297–304.
35. Simkovic, M. The Evolution of Valuation in Bankruptcy. Am. Bankruptcy Law J. 2017, 91, 299. [CrossRef]
36. Pakistan Sales Tax Rate. Available online: https://tradingeconomics.com/pakistan/sales-tax-rate (accessed on
15 July 2019).
37. State Bank of Pakistan, Economic Data. Available online: http://www.sbp.org.pk/ecodata/index2.asp
(accessed on 18 July 2019).
38. Pletka, R.; Khangura, J.; Rawlins, A.; Waldren, E.; Wilson, D. Capital Costs for Transmission and Substations:
Updated Recommendations for WECC Transmission Expansion Planning. Black and Veatch PROJECT
181374 (2014). Available online: https://www.academia.edu/14330724/CAPITAL_COSTS_FOR_TRANSMISSI
ON_AND_SUBSTATIONS_Updated_Recommendations_for_WECC_Transmission_Expansion_Planning_
Western_Electricity_Coordinating_Council (accessed on 18 July 2019).
39. Construction of Chongqing-Hubei Back to Back DC Grid Interconnection Project. Available online: http:
//www.sgcc.com.cn/ywlm/mediacenter/corporatenews/05/340829.shtml (accessed on 27 October 2019).
40. Cai, D.; Zhou, K.; Wang, W.; Liu, H.-G.; Cao, K.; Wang, Y. Influence of back-to-back VSC-HVDC project on
the operation characteristics of Hubei power grid. J. Eng. 2017, 13, 801–805. [CrossRef]
41. Sa Energy Transformation Rit-T Cost Estimate Report. Available online: https://www.electranet.com.au/wp
-content/uploads/projects/2016/11/Cost-Estimate-Report.pdf (accessed on 27 October 2019).
42. China Building Super Highway for Clean Power. Available online: https://gigaom.com/2012/05/14/china-bu
ilding-super-highway-for-clean-power (accessed on 27 October 2019).
43. A New Energy Network: HVDC Development in China. Available online: http://cleanandsecuregrid.org/201
7/01/02/a-new-energy-network-hvdc-development-in-china (accessed on 27 October 2019).
44. CPEC Projects. Available online: http://cpec.gov.pk/energyaccesed (accessed on 26 October 2019).

© 2019 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access
article distributed under the terms and conditions of the Creative Commons Attribution
(CC BY) license (http://creativecommons.org/licenses/by/4.0/).

You might also like