Method Statement For Instalation of CCTV Camera and Junction Boc Foundation
Method Statement For Instalation of CCTV Camera and Junction Boc Foundation
1
TTS/HSE/HIRA/001
Project : Provision of Fencing for the GPP Gate House At Abu Tubul Block 60.
2
TTS/HSE/HIRA/001
Contract
AB/2015-041
Number :
Client
Oman Oil Company Exploration and Production LLC
:
Engineer Liaqut ali khan
:
Prepaid BY
: ASHISH AKARE
3
TTS/HSE/HIRA/001
Copy No.
HOLDERS
Contents
1. Purpose…………………………………………………………...........…………….........5
2. Scope…………………………………………………………............………………..…..5
3. References………………………………………………………............……………..….5
4. Responsibilities.................................................................................................6
5. Site Establishment............................................................................................6
6. Material Delivery................................................................................................6
7. Earthworks........................................................................................................6
4
TTS/HSE/HIRA/001
8. Tools required for the activity..............................................................................7
9. Preparation of installation of cctv camera and junction foundation..........................7
10. Casting of blinding concrete - site mix .................................................................7
11. Pre-request.................................................................................................................7
12. Procedure...................................................................................................................8
13. Records.......................................................................................................................8
14. Evalution as per risk matrix..........................................................................................9
15. Risk Register (HEMP).................................................................................................10
1.0 PURPOSE
The purpose of this document is provided to guidelines for installation of CCTV camera foundation and junction box foundation
will be installed as per OOCEP approved drawings, standards and specific as per civil work in at Abutubul block -60.
2.0 SCOPE
This method statement explains the procedure and the guideline for the installation of installation of CCTV camera foundation
and junction box foundation as per OOCEP Requirement.
3.0 REFERENCE DOCUMENTS
Engineering documents prepared as a part of the Project
4.0 RESPONSIBILITY
Permit Holder and Site Engineer:-
1. Responsibility includes preparation of permit requires for the work.
2. Safe execution of complete activity, confirming the underground utilities before start the excavation.
3. Assigning work crew, sequence of activities to be carried out as per this method statement.
5
TTS/HSE/HIRA/001
4. Receive the approved drawing for work.
5. Review the scope of work and drawing.
6. Safe execution of complete activity, identifying the location of foundation as per the approved drawings,
7. Understanding the materials required, sequence of activities to be carried out as per this method statement, ensure qualified
persons do the work.
8. HSE meeting prior to start of work, conduct tool box meeting.
7.0 Earthworks:-
Clearing areas of all grass, weeds, shrubs, debris, including grubbing up all roots and cart away all vegetation and debris to indicated spoil areas.
Once the clearing is completed the setting out will be carried out by the qualified Surveyor, according to the coordinates on the drawings prior to any
excavation commences. All excavations work will be performed in accordance with method and specification. Tipper trucks will be used to transport
the top soil to the area of the stock pile. Compaction and backfill to be carried out to the specifics according to the inspection test method.
11.0 PRE-REQUISITE
Sleeper foundation to be installed.
Availability of required cable trays & support materials at the site.
Get the Permit to work from the client.
Approved drawing.
12.0 PROCEDURE
Marking of the area with the help of drawings and check the underground utilities.
Excavation by back hoe loader, if utilities is there start the excavation by manually
Level the ground surface area with required compaction.
Make access for excavation pit for concrete procedure.
Adequate curing for concrete work.
Transportation of cctv camera foundation and junction box foundation from yard to site with the help of HAIB
Rigger need to check the all tools and tackles before lifting.
Need to be use the guide rope for direction
13.0 RECORDS
All reports confirming to check list and final acceptance.
8
TTS/HSE/HIRA/001
∆ Relevant check sheets shall completed and submitted to OOCEP.
∆ As built drawing shall be prepared and submitted to OOCEP.
*******
9
TTS/HSE/HIRA/001
10
TTS/HSE/HIRA/001
15.0 Risk Register
11
TTS/HSE/HIRA/001
Activity: Installation of CCTV foundation and junction box foundation at abutubul block -60
Significance Recovery
Significance Evaluation Existing Controls Evaluation after
controls
Sl.
Hazard Risk
Consequence
Consequence
No
Risk Level
Risk Level
Likelihood
Likelihood
01 Site preparation: Injury due to slip C P4 P4C OOCEP PtW System for Hot work C P P1C First Aid
o Such Uneven ground
trip and sharp 1
surface :- Before start the activity tool box talk conducted.
ERP
object.
o Slip trip hazards Area need to be inspected by hse and execution Medical
Electrical fire team,
o Sharp objects. Treatment
Safe systems of work such as PtW system, Job
o Open Electrical Fatal injury
Safety Analysis, Method Statements etc.
utilities
Gas Test (Continues) using Multigas detector
Provision of guard.
Use inspected equipment.
12
TTS/HSE/HIRA/001
Activity: Installation of CCTV foundation and junction box foundation at abutubul block -60
Significance Recovery
Significance Evaluation Existing Controls Evaluation after
controls
Sl.
Hazard Risk
Consequence
Consequence
No
Risk Level
Risk Level
Likelihood
Likelihood
02 Excavation by back hoe Electrocution C P4 P4C Underground utilities, where possible, should be C P1 P1C First Aid
loader:- Fire marked out
Permeant Before digging begins. Use facility maps/as-built Medical
Digging in to underground disability and local utilities (where practicable) to identify lines.
utilities Inhalation Observe overhead lines, tree limbs, or other Treatment
problem objects beforesetting up and raising the bucket of the
Striking overheads line or Fatal
object with bucket backhoe. Anticipate the radius of sweep going up
Critical shock
and coming down, and plan appropriately
Secondary injury Avoid moving parts of machinery. Keep fingers,
Injury to hearing from
noise.
as result of hands, and arms away from backhoe bucket and other
electrical shock. pinch points.
Inhalation hazards from Headache and Wear leather gloves when using hands for activities
dust from drilling or fever other than sampling, and steel-toed boots. Wear hard hat
excavation activities. at all times.
Personnel on the ground should keep away from the
Physical injury from work areaand backhoe unless they are required for the
moving parts of machinery. task. Ask for assistance when carrying or moving heavy
loads. Use legs to lift…not the back.
Physical hazards to Do not approach heavy equipment without first
personnel on the ground establishing eye contact with the operator.
Use standard hand signals when noise levels inhibit
Heat exhaustion or stroke auditory communication.
Ensure that all heavy machinery have audible back-up
signals.
To avoid inhalation of dust, wear a fit -tested half-face
respirator with appropriate cartridges for particles and
other potential Contaminants, including radionuclides.
The respirator must be worn whenever field instruments
13
TTS/HSE/HIRA/001
Activity: Installation of CCTV foundation and junction box foundation at abutubul block -60
Significance Recovery
Significance Evaluation Existing Controls Evaluation after
controls
Sl.
Hazard Risk
Consequence
Consequence
No
Risk Level
Risk Level
Likelihood
Likelihood
03 PPC in excavated area Personal injury C P3 P3C .Use proper PPE's. as like safety gogle, ear buds C P1 P1C First Aid
Edge may collapse of
excavated pit Waste of material Supervision over all work. Medical Attention
Reaction of cement and Skin irritation .Slope/Trench Should be provide.
chemical to workers
Respiratory Give Training before start work.
Inhalation of cement and problem
dust Provide sign boards wherever necessary
confusion
Incase of Emergency Provide proper access to the workers
14
TTS/HSE/HIRA/001
Activity: Installation of CCTV foundation and junction box foundation at abutubul block -60
Significance Recovery
Significance Evaluation Existing Controls Evaluation after
controls
Sl.
Hazard Risk
Consequence
Consequence
No
Risk Level
Risk Level
Likelihood
Likelihood
04 Shifting of foundation for Material may fall C P3 P3C Hiab lifting capacity to be identified on the crane C P1 P1C First Aid
and certification available in cab.
installation from yard to Damage the hiab Weights of loads to be established. Medical attention
installation area by Hiab:- Ground conditions confirmed.
Electrocution Radius of lift to be ascertained for load.
Overload of Static . Operator competency checks.
Permeant disability Slinger/banksman competency checks.
Overloading of Lifting Operator / user instructions available in cab.
Foundation Lifting accessories SWL requirements to be
Accessories (Chains, confirmed.
damage.
Hooks, web slings etc) Lifting accessories to be attached and used as
crush intended.
Slip, Loss of Load Pre use inspection to be undertaken by
Toppled competent person before use.
Collision. Contact Operator / User instructions to be briefed by a
Over heat competent person to all those involved in the
with Overhead Power lifting operation.
Lines Operators to be trained and competent in the
use of lifting accessories provided.
Over speed Current certification to be made available
Competent experienced and trained to be used
Overturning of Static for all lifting operations.
Manufacturers or suppliers lifting points To be
hiab used a all time
Allow when planning for adequate clearances to
avoid conflict with other plant or buildings in the
lift vicinity.
Allow when planning for adequate demarcation
15
TTS/HSE/HIRA/001
Activity: Installation of CCTV foundation and junction box foundation at abutubul block -60
Significance Recovery
Significance Evaluation Existing Controls Evaluation after
controls
Sl.
Hazard Risk
Consequence
Consequence
No
Risk Level
Risk Level
Likelihood
Likelihood
05 Heat Respiratory C P4 P4C Lifting operations will cease when ground C P1 P1C First Aid
system disorders conditions deteriorate following heavy rain, snow, ice
Weather conditions Medevac
etc.
Fatigue
Lifting operations will cease when wind speeds
Dehydration
exceed the manufacturers stated limit for the
persons
Lifting operations must cease during thunder
Musculoskeletal storms
Disorder
fluid intake
Loose clothing
Adequate rest
17