NATIONAL CONTRACTING CO.

LTD DPR NO : 99
DAILY PROGRESS REPORT DATE : 26-Mar-12

SEC- EOA CONTRACT No : 31131024/00


PROJECT : POWER SUPPLY TO AL- FAKHRIYAH AND AL- KHALDIYAH SUBSTATIONS.
115 kV U/G Cable Between Al- Fakhriyah 115 kV Transition Area and Al - Fakhriyah 115 / 13.8 kV S/S - Project Portion - 1

Progress
Today
Total Previous Completion
SL No. Description Unit Cumulative Bal. Remarks
Qty Qty. Section in %
Qty. Qty . Qty.
Nos.

Sec. # 6 to 18, 3 & 4 Completed - Total


A EXCAVATION Mtr 8000 2,880 4 x 5,020 34 15 sections. Sec. # 1 & 2 - under
2,980 progress

Sec. # 6 to 18 & 4 Completed - Total 14


B SAND BEDDING (15 CM) Mtr 8000 3080 18 335 3,415 4,585 21
sections.
POWER CABLE LAYING Section Sec. # 4, 6 to 18 Completed - Total 14
C 144 72 4 6 84 40 37
(24 SectionX 06Nos) /Nos. Sections.
COMMUNICATION CABLE
D Mtr 16000 x x x x x x Work not yet started.
LAYING(2X8000)
110mm PVC PIPE Sec. # 6 to 18 Completed - Total 13
E Mtr 16000 5290 18 770 10,010 5,990 30
LAYING(8000X2) Sections.
LAYING OF 32mm HDPE PIPE
F Mtr 32000 x x x x x x Work not yet started.
(8000 X 4)

i) JB # 6 to 12 & 14 - 8 Joint Bays


G CABLE JOINTING (23JBX06Nos) Nos 138 66 14 x 72 66 7 Completed.
ii) JB # 13 & 15 - under progress
THERMAL SAND BACKFILLING Sec. # 6 to 18 Completed - Total 13
H Mtr 8000 2110 15 335 2,445 5,555 26
OVER CABLE( 43 CM) Sections. Sec. # 4 under progress
Sec. # 6 to 17 Completed - Total 12
I CONCRETE TILE INSTALLATION Mtr 8,000 3015 16 335 3,350 4,550 23
Sections. Sec. # 18 under progress

THERMAL SAND BACK FILLING Sec. # 6 to 17 Completed - Total 12


J Mtr 8,000 2110 13 x 2,445 5,555 22
OVER CONCRETE TILES(15 CM) Sections.

Sec. # 6 to 17 Completed - Total 12


K INSTALLATION OF WIRE MESH Mtr 8,000 1440 10 x 1,775 6,225 22
Sections.
BACKFILLING OF SAND OVER Sec. # 6 to 16 Completed- Total 11
L Mtr 8,000 1775 12 335 2,110 5,890 26
WIREMESH(10CM) Sections.
INSTALLATION OF TERA Sec. # 6 to 14 Completed - Total 9
M Mtr 8,000 335 x x 770 7,665 4
WARNING TAPE Sections.

BACK FILLING OF SELECT FILL Sec. # 6 to 11 Completed - Total 6


N Mtr 8,000 1105 10 335 1,440 8,560 9
MATERIAL( SUBBASE) sections.

Sec. # 6 to 10 completed - Total 5


O BACK FILLING OF BASE COURSE Mtr 8,000 x x 6 x 335 1
sections.

P INSTALLATION OF ASPHALT Mtr 8,000 x x x x x x

i) DB # 05 - Completed
ii) DB # 1 - Epoxy Coating Completed.
Q CABLE DUCT BANK Nos 9 1 1 x Backfilling yet to be Started
iii) DB # 2 - Curing under progress
iv) DB # 4 - Backfilling under progress

Q COMM.HANDHOLE Nos 42 27 X 29 12 64 Hand hole grounding under progress.


1 BASE Nos Rebar binding work under progress.
2 SIDE WALL Nos

Surface preparation & Application of


3 SURFACE PREPARATION Nos 42 12 x 14 28 28 Bitumat Primer on communication
hand hole under progress.

4 CONCRETE PRIMER COATING Nos 42 8 2 10 32 19 Concrete primer coating on hand hole


under progress
Application of water proofing membrane
5 WATER PROOFING Nos 42 6 2 8 34 14
under progress.
6 HANDHOLE INSTALLATION Nos 42 4 12 1 6 36 9
7 CABLE RACK INSTALLATION Nos x x x x x
R LINK BOX HANDHOLE 46 x 1 45 1

1 BASE AND SIDE WALL Nos 46 12 x 16 30 26 Today 04 link box concrete completed.

Link box surface preparation under


2 SURFACE PREPARATION Nos 46 4 x 1 5 41 1
progress.

Primer coating on link box under


3 CONCRETE PRIMER COATING Nos 46 3 X 2 5 41 10
progress.
Application of water proofing membrane
4 WATER PROOFING Nos 46 1 x 1 2 44 1
under progress.
LINK BOX HANDHOLE Link box hand hole installed at JB-6 7,8
5 Nos 46 8 x 4 12 9
INSTALLATION & 9.
LINK BOX INSTALLATION IN Link box installed at JB-6,7,8 & 9 and
6 Nos 46 x x x 4 42 9
HAND HOLE termination completed.

i) Two spares & three Main HDPE Pipes


S HDD at Abu-Hadriyah Highway Mtr 104 x x x x x x Laid for Power Cables & one Main HDPE
pipe laid for Communication Cable.

Highlights
1) Surface preparation and application of water proofing membrane of communication hand hole & link box unit under progress.
2) 04 Link box termination completed at JB-8 & JB 9.

Page 1 of 1