MAPLE LEAF CEMENT FACTORY

GREY CEMENT DIVISION

CHECK LIST FOR INSPECTION OF MV PANELS

ID No:
Line No:

Description:

Inspected by: Signature: Date:

OK NA

1.1 All Safety Interlocks


1.2 Spring Energy Store Indicator
1.2 Visual Inspection for any traces of corrosion
1.3 Lubrication of sliding surfaces
1.4 Firm seating of all terminal connections
1.5 Smooth operation of lever mechanism
1.6 Visual check of spring operated mechanism
1.7 Visual check of circuit breaker operating mechanism
1.8 Check functionality & smooth operation of cable
compartment interlock
1.9 Visual Check of cable compartment
1.10 “OFF” operation through Under-voltage coil
1.11 “OFF” operation through “off” coil
1.12 LEDs test
1.13 Cleaning of all components