PROJECT PLAN – EVEN SEMESTER 2017


S.NO REVIEW CONTENT EVALUATION SUBMISSION OF
DATE DATE CORRECTIVE
MEASURE (BEFORE)
1 27.11.17 Discussion with Project Submission of Company Profile and Title for
Guide. Approval on or before 30.11.17
Project Approval Status by department project
committee on 05.12.17
2 08.12.17 Abstract Submission 11.12.17 15.12.17
3 15.12.17 System Study 18.12.17 22.12.17
a) Existing System with
limitations
b)Proposed System with
objectives
c) Problem description
d) Hardware configuration
e) Software configuration
4 22.12.17 System Requirement 26.12.17 29.12.17
Analysis
a) Input, Process &Output
b) Selection of Attributes
c) Requirement of Tables
d) Dependencies of
Modules
5 29.12.17 System Design 02.01.18 05.01.18
a) System Flow Diagrams
/ Control Flow Diagrams
b) E-R Diagrams / Use
Case Diagrams
c) Data Flow Diagram /
Activity Diagrams
d) Input Design
e) File / Database Design
f) Output design (includes
Report Design)
g) User Interface Design
(if Needed)
6 05.01.18 Development Stage :1 08.01.18 19.01.18
7 19.01.18 Development Stage :2 22.01.18 02.02.18
8 02.02.18 Development Stage :3 05.02.18 09.02.18
9 09.02.18 System Testing 12.02.18 16.02.18
a) Unit Testing
b) Behavioral Testing
c) Integration Testing
d) Acceptance Testing
(include the testing based
on project requirement)
10 16.02.18 Project Demo 19.02.18 02.03.18
11 02.03.18 Submission of Rough 07.03.18 09.03.18
Draft
12 09.03.18 Model Viva 12.03.18 12.03.18
13 14.03.18 Project Report Submission
Note:

 The evaluation of Project work shall be done in the respective semester and marks shall
be allotted as per the students’ performance.
 There shall be twelve assessments by the allotted guide during the project period. The
student shall make the presentation on the progress before the review committee.
 The Project Report prepared according to approved guidelines and duly signed by the
Head of the department shall be submitted to the Head of the Institution.
 The evaluation of the Project work will be based on the submitted report and a Viva Voce
examination by the team consisting of Guide, Internal Examiner and External Examiner.
 If the student fails to obtain 50 % of the internal assessment, he/she will not be permitted
to submit the final Project Report for that particular semester and need to re-enroll for the
same.
 If the student failed to submit the Project Report on the target date, he/she is deemed to
have failed in Project work and shall re-enroll for the same.
 A copy of the submitted Project Report after the successful completion of viva
examinations shall be kept in the library of the college.
 Student should maintain work diary to record the progress of the project work.
 Student should submit work diary to the guide on each scheduled review date.
 Internal mark is evaluated based on the review performance of the student.
 Student should get approval from the internal guide (College) and external guide
(Industry) for their work progress.
 Upload the review content in the Myklassroom portal.