You are on page 1of 201

Ecodial 3 Technical documentation

Technical documentation

Introduction
1 A Overview
Ecodial 3

IEC UTE-C 15 500 C 15 100 NF


Ecodial 3

Word
Ecodial 3
690 Voltage

TT ; TN ; IT Neutral system
Sources
Ecodial 3 Technical documentation

1 B Ecodial 3 Start and quit


To start Ecodial 3

Ecodial 3

global characteristics
Ecodial 3 Technical documentation

OK

Ecodial 3
Global characteristics

Global characteristics

Calculation
General characteristics
Global characteristic Display

To quit Ecodial 3
File Quit

Alt + Q
Ecodial 3 Technical documentation

Alt + F4

1 C Window discription

Title bar

Menu bar

Tool bar

Display Tool bar


Symbol tool box Library
Library
Ecodial 3 Technical documentation

Library

Library
Display Symbol toolbox
Drawing tool box Decor

Display Decor
Decor
Work area

Status bar

( 2 ) Referance standards
IEC60 364 Ecodial 3
International electrotechnical commission
Norme France NFC 15100

General characteristics
Ecodial 3
Ecodial 3 Technical documentation

LV

Un ph-ph (V) LV

Earthing arrangement LV
TNS TNC IT TT
Max.permissible (CSA)(mm2)
mm2 CSA:Cross-Sectional Area

Cascading requested
Yes - No
Discrimination requested
Yes - No
CSA N / CSA Ph
CSA N : Cross-Sectional Area of Neutral N
CSA Ph : Cross-Sectional Area of Phases Ph

CSA N / CSA Ph = (1/2-1


CSA tolerance
0
Ecodial 3 Technical documentation

Standard

Target power factor

System frequency
(50 Or 60 ) HZ
Global characteristics
By default
OK

( 4 ) Ecodial 3 diagram characteristics


( 4 - A ) Source library

Library
Ecodial 3 Technical documentation

Replacement Circuit description


Ecodial 3

( 4 - B ) Normal / replacement source type diagrams


Ecodial 3 Technical documentation

Ecodial 3

( 4 - C ) Busbar library

( 4 - D ) Outgoing circuit library


Ecodial 3
Ecodial 3 Technical documentation

BTS
BTS

BTS

BTS Ecodial 3
BTS
Ecodial 3 Technical documentation

( 4 - E) Using the(no protection)option

( 4 - F ) Load library
Ecodial 3
Ecodial 3 Technical documentation

( 4 - G ) LV/LV transformer library

( 4 - H ) Other symbols library


Ecodial 3

( 4 - I ) Symbol : upstream project cross reference :


Ecodial 3 Technical documentation

Downstream Upstream
Downstream Upstream
Other symbols
( 4 - J ) Example
Other symbols library

Calculation
( 5 -A ) General priciple
Ecodial 3

Ecodial 3
Ecodial 3 Technical documentation

(5-B) Ecodial 3 calculation screen Ecodial 3


Ecodial 3

Summary
Details

See all characteristics


Ecodial 3 Technical documentation

Ecodial 3
Ecodial 3

Manual
Manual

( 6 ) Sources

6 A Transformer
KVA Ecodial3
High voltage HV

Level one input parameters

Description Contents
Power (KVA)

Earthing arrangement (TT IT TNC TNS Upstream)

Yes/No
Distributed neutral PE TNC
N

V
Un ph-ph (V)

IEC-60909
Cmax
Ecodial 3 Technical documentation

Short-circuit voltage(%)

Psc HV (MVA)
500 MVA
Source electrode Ohm
Impedance (Ohm) TT
Network electrode Ohm
Impedance (Ohm) TT
Type of application of PIM
the (PIM)

Level two input parameters

Description Contents

Connection
(Delta Star) ; (Star Star) ; (Star ZigZag)

Power factor

System frequency 50 - 60 HZ
HV operating time (ms) 500 ms
Ecodial 3 Technical documentation

Calculated values in the input table

Description Contents

Short-circuit voltage(%)
Reference of the PIM IT PIM

Calculated values in the calculation Details

Description Contents
R phase of HV network HV
(mOhm) mOhm
X phase of HV network HV
(mOhm) mOhm
R ph transfo. (mOhm) mOhm
X ph transfo. (mOhm) mOhm
Isc max per source(KA)
Ib (A) A
Ecodial 3 Technical documentation

A Generator

Level one input parameters

Description Contents
Power (KVA)

Earthing arrangement ( TT IT TNC TNS Upstream )

Yes/No
Distributed neutral PE TNC
N

Un ph-ph (V) IEC-60909


Cmax

Source electrode Ohm


Impedance (Ohm) TT
Network electrode Ohm
Impedance (Ohm) TT
Type of the (PIM) PIM
Ecodial 3 Technical documentation

Level two input parameters

Description Contnts
System frequency 50 - 60 HZ
X0 6%
Xd 30%
X 20%

Power factor

CENELEC

Xd Ecodial

Xd CENELEC
X

Calculated values visible in the input grid

Description Contents

Reference of the PIM IT PIM


Ecodial 3 Technical documentation

Calculated values in the calculation Details

Description Contents
Transient positive
mOhm
Xd (mOhm)
Zero-sequence
mOhm
Xo (mOhm)
Single- phase
mOhm
X (mOhm)
Iscmax per source (KA) KA
Ib (A) A

( 6 - C ) Any source
Any source
Other symbols

Input parameters

Description Contents

Un Ph- Ph (V) 220 230 240 380 400 415 440


500 660 690 (V) . ( Phase to Phase )

Isc max upstream


Ecodial 3 Technical documentation

Power factor
System frequency
Energy supplier
Distributed neutral
I service connection

I sc min upstream

TT-IT- TNC - TNS - Upstream


Earthing arrangement

Source electrode Ohm


Impedance (Ohm) Ohm TT
Network electrode Ohm
Impedance (Ohm) Ohm TT

( 6 - D ) The capacitor

First level input parameters

Description Contents
Power factor befor
compensation
Corrected cosphi
Power of the harmonic
sources (KVA) KVA
Ib (A) A
Ecodial 3 Technical documentation

Calculated values visible in the input grid

Description Contents

Power (Kvar)
Kvar

Standard STD
Type of compenstion Overrated H
Detuning reactors SAH

x
Step (Kvar)

(6 D 1)Determine capacitor bank power from electrical data :

Required tangent phi = 0.31


Cos phi = 0.96

(6 D 2)Determine the type of capacitor bank :

UPS
Ecodial 3 Technical documentation

STD: Standard
H : Overrated
SAH : Detuning type

(6 D 3)Harmonic-producing loads :
Power electronics equipment

UPS
Loads using the electric arc :

Equipment with magnetic circuits ( saturated reactors


AC
Ecodial 3 Technical documentation

(6 D 4)Choice table according the harmonic level :

Sn
Gh
(6 D 5)Detuned capacitor bank :
Ecodial 3 Technical documentation

(6 D 6)For motor compensation :


Cos phi

Qc
Un
Io
Io

In
Coc phi
Un
Ecodial 3 Technical documentation

STD
(6 D 7)Example of anormal installation : use of standard
Capacitors :
Ecodial 3 Technical documentation

H
(6 D 8)Example of polluted istallation : use of overrated type
Capacitors :
Ecodial 3 Technical documentation

SAH
(6 D 9)Example of very polluted istallation : use of detuned
Type capacitors :
Ecodial 3 Technical documentation

( 7 ) Busbars

Busbars with calculation

Description Contents

Busbar type

Ecodial 3
In (A.)
Ecodial 3

Conductor metal

Length
Nb of bars in //
Thickness (mm.) mm mm
Width ( mm.) mm.
Power factor Cos phi

Circuit polarity
3P + N ; 3P ; 2P ; 1P ; Upstream
Ecodial 3 Technical documentation

Upstream
Ambient
temperature
T o C max perm .
on Isc.
Degree of IP 30
protection Less than IP 30 < IP 30 > Great than IP 30

Earthing
TT IT TNC TNS Upstream
arrangement
Upstream

Calculated values

Description Contents
I available (A.)
R ( mOhm ) mOhm
X ( mOhm ) mOhm
Isc max ( KA. ) KA

Busbars without calculation


Zero impedance

Busbar
Ecodial 3 Technical documentation

( 8 ) Busbar trunking system (BTS) for decentralized


Distribution :
Ecodial 3 BTS

tap - off units in Plug

Bolt - on tap - off units

Floor - rising distribution

Ecodial 3 BTS
Ecodial 3 Technical documentation

Uniformly divided load


BTS
Tap - off points

BTS

Non-uniformly divided load


BTS

( 8 A ) Calculation method : uniformly divided load

First level data

Identifier Description
( Plug in tap off units
)
Application
( Bolt on tap off units )
( Floor rising ditribution )

Calculation method

Reference BTS
Ecodial 3 Technical documentation

Ib ( A.) A. BTS
Lengh ( m.) m.
K user
Delta Umax line ( % )
TT IT TNC TNS Upstream
Earthing system
Upstream
Loaded neutral Yes / No
Installation method
BTS
Ambient temperatureoC

Safety voltage ( V.)


Support width BTS
Protection degree ( IP )
For lighting circuits only E
: (E) fixation

Calculated values

Description Contents
Ik max (A.) BTS
Ik min , Id BTS
Voltage drop (V.) BTS

BTS
BTS
Ecodial 3 Technical documentation

( 8 B ) Calculation method : Non- uniformly divided load

Outgoing circuits
BTS

Identifier Description
D ( m.) BTS
Ib ( A.)

BTS
Parameters calculated for the (BTS)

Description Contents
Ik max (A.) BTS
Ik min , Id BTS
Voltage drop (V.) BTS
Ecodial 3 Technical documentation

BTS
BTS
Parameters calculated for the outgoings of the (BTS)

Description Contents
Ik max (A.)
Ik min , Id
Voltage drop (V.)

Ecodial 3 BTS

Conductors

Busbar trunking systems (BTS


Busways
Cables
( 9 - A ) Cables

Level one input parameters

Description Contents
Length (m.)

Installation method
IEC60364-5-523
Ecodial 3 Technical documentation

Table 52-B1-and 52-B2

C0nductor metal

XLPE
Insulation
PVC
Rubber
Type of conductor

Trefoil
Flat space Flat touching
Conductor arrangement

.08
C 15-
Circuit arrangement 100

C 15-
Duct spacing 100

Safety voltage (V.)


Nb Ph user
CSA Ph user (mm2)
Nb N user N
CSA N user (mm2)
Nb PE user PE
CSA PE user (mm2)
Ecodial 3 Technical documentation

Level two input parameters

Description Contents
Yes / No
Neutral loaded
NFC 15-100

Type of (PE)
PE PE PE

Cores touching
Yes / No
Nb of circuits
Number of layers
K user K
Ambient temperature
Delta Umax circuit
K user

W Km
Table 52GJ of standard NFC 15-100
K = 0.9
10%

CSA N = CSA Ph Yes

No
Ecodial 3 Technical documentation

PE N TNC
PE N Ecodial 3

(9 B) ( BTS ) with non-uniformly distributed loads :

First level data

Identifier Description
Reference
Length
K user
Delta Umax. circuit
Conductors loaded Yes/ No

Installation Edgewise Flat


Vertical
Ambient temperature
Safety voltage (V.) V.
E fixation (m.)
IP

Calculated values for cables and busbar trunking

Maximum short circuit currents at the extremityof the conductor


Ecodial 3 Technical documentation

Description Contents
IK1 max
RboN
XboN
IK2 max
Rbo Ph Ph
Xbo Ph Ph
IK3 max
RboN
XboN
Isc max at end of circuit

Isc max at beginning of


circuit

Calculated values for cables and busbar trunking

Minimum short circuit currents

Description Contents
IK2 min
Rb Ph
Xb Ph
IK1 min
Rb Ne
Xb Ne
Ecodial 3 Technical documentation

Earth fault current


Sizing constraint

( 10 ) Loads
( 10 - A ) Circuit loads

Description of aload on adistribution circuit

Description Contents
Nb. of identical circuits
Ib (A.)

Circuit polarity 3P + N ; 3P ; 2P ; 1P ; Upstream


Upstream

Earthing arrangement TT IT TNC TNS Upstream


Upstream
Power (KW.)
Power factor Cos phi
Fixed
(Fixed / Mobile) load
Mobile
Maximum earth fault
Breaking time 5 Second or < 5 Second

3P + N
PE N TNC
3P
Ecodial 3 Technical documentation

2P
1P

Ib P
Ecodial 3

TNS TNC

10 B Motors

Description of a 3-phase motor

Level one input parameters

Description Contents
Nb of identical circuits
Mechanical power(KW)
P2
Motor efficiency
( P2 / P1 P1
Ib (A.)

I start (A.)
10 %
Power factor (cos phi )
3P + N ; 3P ; 2P ; 1P ; Upstream
Circuit polarity Upstream
Ecodial 3
Ecodial 3 Technical documentation

Earthing arrangement TT IT TNC TNS Upstream


Upstream
Power (KW.)

Type of coordination
Type(1) - Type(2)

Type of sarting

Maximum earth fault


Breaking time 5 Second or < 5 Second

Ecodial 3

OK

Level two input parameters

Description Contents

Starting class Class 20 Class 10


Ecodial 3 Technical documentation

( 10 - C ) Lighting

Description of a lighting load

Description Contents
Nb of identical circuits

Lighting

Lamp power (W.)


Nb of lamps per light
Number of lights
Individual lamp power
Ib (A.)

3P + N ; 3P ; 2P ; 1P ; Upstream
Circuit polarity
Upstream
Ecodial 3
TT IT TNC TNS Upstream
Earthing arrangement
Upstream
Power (KW.)
Device consumption
Coefficient
I start / In
Maximum earth fault
Breaking time Second or < 5 Second
Ecodial 3 Technical documentation

Guide

230 V.

400 V.
230 V.

( 10 - D ) LV/LV transformers LV/LV


IT LV / LV

230 V. 400 V.

First level input parameters

Description Contents

Un ph - ph secondary LV / LV
(V.) ( 220-230-240-380-400-415-440-500-525-660-
690 ) (V.)
Transformer rating
(KVA)

Circuit polarity
3P + N ; 3P ; 2P ; 1P ; Upstream
Ecodial 3 Technical documentation

Secondary earthing
TT IT TNC TNS Upstream LV / LV
arrangement
Upstream
Disributed neutral Yes / No

Short-ciruit voltage (%) Ecodial 3

Source electrode
Impedance (Ohm) TT
Network electrode
Impedance (Ohm) TT
Type of application of PIM
the ( PIM )

Calculated values

Description Contents
Reference of the (PIM) IT PIM

( 10 E ) Variable speed drive

First level input parameters

Description Contents
Ecodial 3 Technical documentation

Standard torque
Over torque

Ist = 1 - 1.2 In

Torque High torque


Over torque
Over current
Ist = 1.5-1.7 In

Calculated values

Description Contents
Nominal power (KW.)
Ib (A.)
Absorbed power (KW.)

Shape factor (K)


Ecodial 3 Technical documentation

Constant Is (A.)

Constant max. Is (A.)

60s max. Is

Ecodial 3

ALTIVAR , ATV 58E , and ATV 68E

Wall mounted
Floor standing

EMC

Buit-in

ATV 58E , ATV 68E


ATV 68 , ATV 58H

( 10 - E - 1 ) Frequency converter
Ecodial 3 Technical documentation

( 10 - E - 2 ) Frequency converter work


50 - 60 HZ AC
Rectifier DC
Inverter

(10-E - 3)Cos phi of a motor supplied by a frequency converter

Cos phi = 1 Phi = 0

P=W.C
W C P

Shape factor

( 10 - E - 4 ) Standard and high torque

( 10 - E - 5 ) Calculation principle
Ecodial 3 Technical documentation

Shape factor
( 10 - E - 6 )The motor thermal protection

( 10 E - 7 )Short-circuit protection provided downstream of


The Variable speed drive :

( 10 E - 8 ) Short-circuit protection provided upstream of the


Variable speed drive :

(11 ) Protection
Ecodial 3 Technical documentation

( 11 - A ) Circuit-breaker

Level one input parameters

Description Contents
Range Multi 9 Compact Masterpact
Designation
Trip unit / curve
xTU xP
TU = Trip Unit
4P4TU
4P3TU+Nr
Nb. Poles protected

3P3TU
2P2TU
1P1TU
Earth fault protection Yes / No
I thermal setting (A.)
I magnetic setting (A.)
Trip unit rating (A.)
Frame rating (A.)

Cascading requested
Yes / No
Discrimin. Requested Yes / No

Installation
With drawable Fixed
Ecodial 3 Technical documentation

Integrated with the RCD


protection device .
Class A-AC RCD
Earth leakage RCD
protection device
Sensitivity RCD
Delay RCD

Additional protection
RCD Yes
Against direct contacts
30mA

Fire protection RCD Yes


90 ms. 50 ms. 500 mA

Ecodial 3

Details Ecodial3
Calculations

Compact range
STR xx range Trip unit
Details
B Multi 9
Ecodial 3 Technical documentation

Level two input parameters

Description Contents
Im setting
Ir setting
Io setting
Motor mechanism

( 11 - B ) Motor control and protection

Level one input parameters

Description Contents

Range
Multi 9 Compact Masterpact GV Integral
Designation
Trip unit / curve

Contactor

Thermal relay

Earth fault protection Yes / No

Thermal protection Included


Separate
Ecodial 3 Technical documentation

Without

xTU xP
TU = Trip Unit
4P4TU
4P3TU+Nr
Nb. Poles protected

3P3TU
2P2TU
1P1TU
I thermal setting (A.)
I magnetic setting (A.)
Frame rating (A.)
Trip unit rating (A.)

Cascading requested Yes /


No
Discrimin. Requested Yes / No

Installation
With drawable Fixed
Integrated with the RCD
protection device .
Class A-AC RCD
Sensitivity RCD
Delay RCD
Earth leakage RCD
protection device
Ecodial 3 Technical documentation

Additional protection
RCD
Against direct contacts
30 mA

Fire protection 500 mA RCD


90 ms. 50 ms.
Soft starter

Level two input parameters

Description Contents
Im setting
(Ir) and (Io) settings
Motor mechanism

( 11 - C ) Switch

Description Contents
Earth fault protection
Nb. Of poles
Switch

(11 ) Upsream project cross reference


Ecodial 3 Technical documentation

Level one input parameters

Description Contents
Upstream project
Upstream circuit
Update cross referenc Yes / No

Ecodial 3
Working at program Ecodial 3

Project management
A Creat anew project
File New ( Ctrl + N )

File New
Ctrl + N
Global characteristics
OK
Ecodial 3 Technical documentation

Global characteristics
Global characteristics Calculation
Display

B Open a project

File Open ( Ctrl + O )

File Open
File open Ctrl + O
Ecodial 3 Technical documentation

File

C Save a project
File Save ( Ctrl + S )
File Save as

File Save
Ctrl + S

File Save As
Ecodial 3 Technical documentation

File Save As File Save as

Save as
D Close a project
File Close

File Close
Ecodial 3 Technical documentation

E Recover a previous version project

File Update Ecodial 3

Busbars and BTSs


Ecodial 3 Technical documentation

File Update Ecodial

F Consult and set file information

File Summary

Summary File Summary


Ecodial 3 Technical documentation

Summary
Directory File name
Date modified Date created
Summary
Author Version Title
Comments

OK

G Set the general information


File General information

General information
Ecodial 3 Technical documentation

Edit Insert field


File Front page Front page

Name
General information Company

File General information


General information
Ecodial 3 Technical documentation

OK

General information

Project
Customer
Company
Information table

Default

H Configure the printer


File Configure printer

File Configure printer


Ecodial 3 Technical documentation

OK

I Print or export a project


File Print / Export (Ctrl + P)

RTF

DXF

ECD
Ecobat Schneider

File Print / Export


Ctrl + P
Ecodial 3 Technical documentation

Print

Print and export

Directory
RTF
Equipment Front page :
Calculation results Item lists
Landscape Portrait

Language
Margins
Preview
Diagram
Diagram
Landscape Portrait

Preview
Print
Ecodial 3 Technical documentation

DXF RTF Export project


Ecobat ECD Export ECD

File Print / Export


Print and export Ctrl + P

Export Export project

OK

Front page , Equipment , Diagram,...


Export 2

J ) Define the margins for the printout


File Print / Export Margins
Ecodial 3 Technical documentation

Print and Export File Export Print

Margins

mm

OK

K Print preview
File Print / Export Preview

Print and Export File Export Print

Preview Print and Export


Preview
Calculations results Equipment , Item lists Front page
Ecodial 3 Technical documentation

Preview

Zoom factor

One page One page / Two pages


Two pages
Printt
Preview Close
Pg :

Calculations results Equipment , Item lists Front page

Print

Single - line

Print and Export File Export Print


Ecodial 3 Technical documentation

Diagram Preview

Next page
Previous page

One page One page / Two pages


Two pages

Zoom in
Zoom out
Print

Close

L Define header and footer


File Header and footer
Ecodial 3 Technical documentation

File Header and Footer

Header

Header and Footer Edit

Format
Font Header and Footer
Paragraph :centered , Right Left
Footer

OK

OK Default
Header and Footer
Ecodial 3 Technical documentation

Header and Footer

Edit
Edit
Insert field

Windows Bmp Insert drawing


Format
Format
Font

Paragraph
Left , Centered , Right
Header
Footer
Ecodial 3 Technical documentation

Edit
Format
Default

1 M Define the front page


File Front page

File Front page

Edit

Format
Ecodial 3 Technical documentation

OK

OK Default

Front page

Edit

RTF Insert file

Insert field

BMP Insert drawing


Windows
Insert object

Insert page break


Format

Font

Paragraph
Right , Centered , Left
Text editing area
Edit
Format
Print
Default
Ecodial 3 Technical documentation

Diagram editing
A Customizing the work area
A- 1 Define the work area
Parameters Frame Work area

A0 - A4

Parameters

Work area Frame

OK

OK Default
Ecodial 3 Technical documentation

Work area

Page format
A0 - A4
Horizontal Virtical
Page
A0-A4
Number of diagram
A0
A3 A4
A- 2 Zoom the diagram
Zoom Display Zoom in Zoom out 100%

Zoom in Display Zoom

Zoom out Display Zoom


Ecodial 3 Technical documentation

100% Display Zoom

2 A- 3 Display or hide toolbar


Display Toolbar
Display Toolbar

Toolbar

2 A- 4 Display or hide status bar


Display Status bar
Display Staus bar

Staus bar

Library
2 A- 5 Display or hide the symbol toolbox
Display Symbol toolbox
Display Symbol toolbox
Library
Symbol toolbox

Library
Ecodial 3 Technical documentation

Decor
2 A- 6 Display or hide the drawing toolbox
Display Decor
Decor Display Decor

Decor

Decor

2 A - 7 Display or hide grid

Page editor Normal grid , 2.5mm , 1mm


Ecodial 3 Technical documentation

Zoom

Grid None

2 A- 8 Select the annotation type


Display Basic annotations
Display Power sum annotations
Display Calculation annotations

Display Discrimination annotations

Basic annotation
Power sum
Calculation
Discrimination

Display

Display
Ecodial 3 Technical documentation

2 B Manipulating the graphic elements


2 B - 1) Find an item on the diagram
Edit Find ( Alt + F3 )

Alt + F3 Edit Find


Find

OK
Ecodial 3 Technical documentation

2 B - 2) Select graphic elements

Selection

Selection

Selection

Shift

2 B - 3 ) Deselect graphic elements

Shift
Ecodial 3 Technical documentation

2 B - 4 Cut data

Edit Cut (Ctrl + X )


Library Decor
Paste

Edit Cut
Ctrl + X
Clipboard

2 B - 5 Copy data to the clipboard

Edit Copy (Ctrl + C )


Library Decor
Paste

Edit Copy
Ctrl + C

Clipboard
2 B - 6 Paste contents of the clipboard

Edit Paste (Ctrl + V )


Symbol Decor
Cut Copy
Ecodial 3 Technical documentation

Edit Paste
Ctrl + V

2 B - 7 Delete elements in the diagram

Edit Paste (Ctrl + V )

Edit Delete
Delete
Library

2 B - 8 Move graphic elements

Paste Cut
Ecodial 3 Technical documentation

2 B - 9 Duplicate graphic elements

Ctrl

Ctrl
Ctrl

C12 C11 C1
Edit Paste Copy

Resize Resize XY
2 B - 10 Resize graphic elements
Decor
Ecodial 3 Technical documentation

Esc

Page Resize
editor
Resize Page editor
Decor

Page editor Ecodial 3


Set sheet parameters
Ecodial 3 Technical documentation

OK
Ecodial 3 Technical documentation

2 C Plotting the network


2 C- 1 Choose the symbol library

Libraries

LV transformers Sources

Others Busbars

Standard diagrams Outgoig circuits

Loads

Library Horizontal
Ecodial 3 Technical documentation

Library

Next
Previous

2 C - 2 Insert an electrical symbol in the diagram

Library

Library
Horizontal

2 C- 3 Define the circuit components


Network Circuit description ( F4 )
Ecodial 3 Technical documentation

F4 Network Circuit description

Name
OK

Network tree

Circuit description

Name
(Description
Ecodial 3 Technical documentation

Replacement

Earth protection
Motor mechanism

Characteristics

Calculate Network Item lists


Calculations

2 C - 4 Define the item characteristics


Network Item lists

Calculate the network step by step

Network Item lists


Ecodial 3 Technical documentation

Item type

OK

Network tree

Characteristics
Print
Ecodial 3 Technical documentation

Item lists

Table
Item type

Guide
Item type

Characteristics

2 C- 5 Renumber the network


Network Automatic numbering

Busbars
BTS
Eqipment
BTS Switchboard

Network Automatic numbering


Ecodial 3 Technical documentation

2 C- 6 View the network tree


Network Network tree (F2)

Sources + Equipment
Sorces + Equipment + Circuits

F2 Display Network tree


Ecodial 3 Technical documentation

Network tree

Tree

Display all circuits

Display all circuits

Flags
Ecodial 3 Technical documentation

Selection

Display all circuits

2 C - 7 View the equipment single-line diagrams


Network View equipment .

Unit Network View equipment


Ecodial 3 Technical documentation

Equipments

Close
BTS
Equipments
Zoom
Next
Previous
Print

Unit Characteristics

Down
Remove : Add UP
OK

OK By Default
Ecodial 3 Technical documentation

Characteristics

Characteristics list

Selected characteristics
Item lists
Unit
Add
Selected characteristics
Characteristics list
Selected characteristics Add
Remove
Selected characteristics
Remove Selected characteristics
Characteristics list
Up
Selected characteristics
Up
Down
Selected characteristics
Down
2 C- 8 Network logical check
Network Logical check (F3)

Source configuration
Ecodial 3
Generator sets Trnsformer
Specific user-defined sources
Ecodial 3 Technical documentation

Normal source

Sheet cross reference coherence

Loop prblems

Equipment
BTS Switchboard
Network unicity

Network Logical check


F3
Ecodial 3 Technical documentation

2 C- 9 Print the diagram sheets


Print diagrams

Sheet model Sheet

Sheet model
A0-to-A4

2 C - 10 Search products in the data base


Tools Product guide .

Tools Product guide


Ecodial 3 Technical documentation

Products

Creteria

Results Find

Close

Schneider products

Products

Criteria

Guide

Find
Result
Creteria
down Page up
result
Ecodial 3 Technical documentation

2 C- 11 Associate circuit-breakers
Tools Association guide .

Tools Association guide

Network voltage

Down stream Upstream

Find
Solutions Schneider products Creteria
Cascading Discrimination Solutions

Close

Down Page up
Solutions
Ecodial 3 Technical documentation

D Using standard diagrams

D - 1 Creat or modify a standard diagram


Edit Creat standard diagram .
Standard diagram

Standard diagram library

Edit Creat standard diagram

Name of file

Designation

OK
Ecodial 3 Technical documentation

D- 2 Insert a standard diagram


Edit Insert standard diagram .

Edit Insert standard diagram

Name of file

OK
Ecodial 3 Technical documentation
Ecodial 3 Technical documentation

D- 3 Delete a standard diagram


Edit Delte standard diagram .

Edit Delete standard diagram

Name of file

OK

Yes
Ecodial 3 Technical documentation

D - 4 Customize the standard diagram library

Edit standard diagram library .

Library

Edit Standard diagram library

File name

Library Add

Down Up

Remove

OK
Ecodial 3 Technical documentation

Library
Library Standard diagram library

E Using the drawing tools


E - 1 Select text attributes
Parameters Frame Text

Parameters Frame
Default text Text
Ecodial 3 Technical documentation

OK

Default text

Color
Style
Italics Bold
Transparent Hatch Underlined

Oblique value
Angle
Justification
centered Right Left
Fonts
Size
E - 2 Select decor attributes
Parameters Frame Drawing
Decor
Ecodial 3 Technical documentation

Drawing Parameters Frame


Default drawing

Line

Pattern

OK

E - 3 Select arrowheads for lines of décor


Ecodial 3 Technical documentation

Parameters Frame Arrow .

Parameters Frame
Default arrows Arrow

Style

Size

OK

E - Draw graphic objects


4
Ecodial 3 Technical documentation

Segment Ellipse

Polyline Circle

Polygon Arc

Rectangle

Ellipse

Circle
Ecodial 3 Technical documentation

Arc

Rectangle

Segment
Ecodial 3 Technical documentation

Polyline

Esc

Polygon

Esc
Ecodial 3 Technical documentation

Esc

E - 5 Enter a text in the diagram

Decor

OK
Ecodial 3 Technical documentation

Esc

E - 6 Modify a text in the diagram


Ecodial 3 Technical documentation

Decor Modify text


Text modification

Ok

Network calculations

A Define the network electrical characteristics


Ecodial 3 Technical documentation

Calculation Global characteristics

Global characteristics

Calculation Global characteristics


Global characteristics Modify

OK

By default
OK Global characteristics
Ecodial 3 Technical documentation

Global characteristics

B Calculate the network power sum


Calculation Power sum
BTSs
Ks

Calculation Power sum

Power sum

Switchboard Eqipment
BTS
Ecodial 3 Technical documentation

Network

Loads of current equipment


Ecodial 3 Technical documentation

Ecodial 3
Load distribution

Phase distribution

OK
Ecodial 3 Technical documentation

Ku

Loads of current equipment


Other characteristics Power sum

Circuit description
Ecodial 3 Technical documentation

Circuit description
Switch board
Power sum Network
Circuit description

Network

Print

C Pre-size the network


Calculation Pre-sizing

Calculation Pre-sizing

Network tree
Network tree
Display

Network Logical check F3


Ecodial 3 Technical documentation

D Calculate the network step by step


Calculation Calculate ( F5 )

Ecodial 3

Calculation Calculate
Calculation
Calculation

Details Calculate
Calculation
Calculation
Summary
Ecodial 3 Technical documentation

Next circuit
Calculate
Ecodial 3 Technical documentation

Calculation OK
Calculate all
Ecodial 3 Technical documentation

Calculation

Calculations
Calculation

Guide
Ecodial 3 Technical documentation

Calculation

Network tree

Calculate

Details

Summary Calculation
Calculate all

Next circuit
Previous circuit
Details

Summary
Ecodial 3 Technical documentation

E Update network calculations


Calculation Update calculations (Shift + F5)

Calculation Update calculations


Shift + F5

Network Logical check F3


Ecodial 3 Technical documentation

F Display calculations results


Calculation Results

Calculation Results

Print

Close
Ecodial 3 Technical documentation

Tools

Compare circuit-breaker tripping curves


Tools Curve comparison ( F6 )

F6 Tools Curve comparison


Ecodial 3 Technical documentation

Quit
Ecodial 3 Technical documentation

Curve comparison

Curve display area

Select a curve

Zoom

Zoom
Ecodial 3 Technical documentation

Adjustment area

Ctrl

Add curve
Display a curve
Ecodial 3 Technical documentation

OK

Curve comparison

Remove acurve
Remove a curve

OK
Ecodial 3 Technical documentation

Modify trip unit

OK
Ecodial 3 Technical documentation

Select a curve

OK

Print curves

Quit
Curve comparison

Software customize
A Configure the item lists
Network Item lists
Item lists

RTF
Ecodial 3 Technical documentation

Network Item lists

Item type

Characteristics
Add Remove Up Down

OK
Item lists

OK By default

B Define the default circuit characteristics


Characteristics Item lists
Ecodial 3 Technical documentation

Parameters Default circuit characteristics


Library
BTS

Parameters Default circuit characteristics

Circuit

Calculation

OK

OK By default
Ecodial 3 Technical documentation

Default circuit characteristics

Circuit
Calculation

Guide

By default

C Choose the calculation standard


Parameters Calculation standard
Ecodial 3 Technical documentation

Parameters Installation standard

D Customize the tools menu


Parameters Tools
Tools
Ecodial 3
Ecodial 3 Technical documentation

Calculator Tools
Windows

Tools

Parameters Tools

Add Delete Up Down Applications

OK

Add an application

Applications
Tools
Command line
Applications

Add
Menu text
Tools
Arguments

Add
Tools
Ecodial 3 Technical documentation

Delete
Tools
Up
Tools
Down
Tools

Tools

Add Add an application

Tools

*.exe
Calculator
Windows
C:
Windows C:
exe
calc.exe
Ecodial 3 Technical documentation

calc
Add an application Applications

Add an application
Menu text
calc
excel word
Arguments

Applications Tools
Down Up
Ecodial 3 Technical documentation

OK
Tools

Tools

Add an application Applications

Tools Applications Delete

OK
Ecodial 3 Technical documentation

Guided example

LV
Execorri Ecodial 3

LV

This document

( )

Starting the application


start the software

Ecodial 3
Ecodial 3 Technical documentation

Preparing the single line diagram

Defining the electrical characteristics of installation

TT
400 V.
Ecodial 3 Technical documentation

Discrimin.rquested
Yes or No
Yes
Cascading requested Yes
Earthing arrangement TT
OK
Ecodial 3 Technical documentation

Adding the electrical symbols

set of busbar
Busbar trunking system BTS

T1

Circuit
C1

Q1

Switchboard
B2

Q3 Q4

Circuit Circuit
C3 C4
Switchboard
B5

L3 Q6 Q7

Circuit Circuit
C6 C7

L6 L7

Library
Sources
Ecodial 3 Technical documentation
Ecodial 3 Technical documentation

busbar
Ecodial 3 Technical documentation

loads

Protection-conductor-load
Ecodial 3 Technical documentation

Protection - conductor

Busbars Switch board

Loads Protection-conductor-load

Adjusting the diagram


Ecodial 3 Technical documentation

L3 C3 Q3
Ecodial 3 Technical documentation

Entering the characteristics of the circuits elements :

Circuit description
T R1

Network
Circuit description
Name T R1
OK
Ecodial 3 Technical documentation

LVswitchboard

Circuit description F4
OK Lv switch board

Air cond.

B2
Circuit description
OK Air cond.
Ecodial 3 Technical documentation

LV switch board

Air cond.
Ecodial 3 Technical documentation

To switch. 2
Switch. 2
Offices.
Parking.

Modifiying the composition of acircuit


BTS Air cond.
Circuit description
Cable Description
BTS
OK
Ecodial 3 Technical documentation
Ecodial 3 Technical documentation

Moving and closing the circuit library toolbox

Display
Library Symbol toolbox
Ecodial 3 Technical documentation

Zooming

Zoom

Printing the diagram

Print diagrams
Ecodial 3 Technical documentation

Saving the project

File
Save as

Thabit.hil
OK

Determining the required source power

Calculation Power sum


Ecodial 3 Technical documentation

Yes
Ecodial 3 Technical documentation

General characteristics
400 V

Ecodial
Normal P chosen per source
Ecodial

Network
BTS
Loads of current equipment
Switch. 2 Offices 100 Kw
Ecodial 3 Technical documentation

Power(kw) Loads of current equipment


Offices
100
Enter

Parking 200 A.
Parking Ib(A.) Loads of current equipment
Enter 200

Ks = 0.9
Current equipment Ks 0.9

Ku = 0.8
Loads of current equipment Ku 0.8
Ecodial 3 Technical documentation

LV Switchboard
LV Switchboard
To switch. 2 Loads of current equipment
Switch. 2
Power (Kw) 400 Loads of current equipment
Enter Air cond
Current equipment Ks 0.9

TR1

750 KVA
P chosen per source Normal
Ecodial 3 Technical documentation

Power sum OK
Power sum

Display Power sum annotation


Ecodial 3 Technical documentation

Calculating the installation


Ecodial 3
Pre-sizing
step-by-step

Presizing the installation

Circuit description Parking


Length Characteristics
parking 50 m.
Ecodial 3 Technical documentation

Offices 50 m.

air conditioning 50 m.
Ecodial 3 Technical documentation

To switch. 2. 25 m.

Calculation Pre-sizing
Ecodial 3 Technical documentation

Calculation Results

Print

Calculation results Print


Ecodial 3 Technical documentation
Circuit : TR1 ( T1-C1-Q1) - Calculated
Upstream :
Downstream : LV Switchboard
Voltage : 400 V

Source : T1
Upstream
Upstream short-circuit power: 500 MVA
Upstream impedances: Resistance Rt: 0.0351 mOhm
Inductance Xt: 0.3510 mOhm
Transformer :
Number of transformers: 1 Earthing arrangement: TT
Total power: 800 kVA Unit power: 800 kVA
Connection: Delta-Star Short-circuit voltage: 6.00 %
Source impedances: Resistance Rt: 4.1013 mOhm
Inductance Xt: 12.5685 mOhm

Busbar trunking system (BTS): C1


Type: KTA12 In permissible: 1200.0 A
Length: 5.0 m U (%): 0.11 %
Calculation mode : Sub-feeder K user: 1.00
Installation method: Flat Application: Transport link
Sizing constraint: demand current
The thermal withstand was checked
Voltage drop upstream circuit downst.
U (%) 0.00 0.11 0.11

Calculation results:
Isc upstr. Ik3max Ik2max Ik1max Ik2min Ik1min I fault
(kA) 18.5904 16.0914 18.3815 14.5441 16.5963 0.0242
R (m ) 4.3264 8.6528 4.5164 8.7406 4.6042 5.7391
X (m ) 12.9945 26.0041 13.0945 26.0041 13.0945 14.3345

Results of calculations as per UTE C15-500 (CENELEC R064-003).


UTE approval 15L-506
Assumptions and choice of devices are the responsibility of the user.

Circuit breaker: Q1
Name: C1251N-50.0 kA Trip unit rating: 1250 A
Frame rating (In): 1250.0 A Trip unit: STR25DE
Number of poles: 3P3TU
Discrimination limit:
BC reinforced by cascading:
Earth leakage protection: Yes
Earth leakage protection device : RH248E
Sensitivity : 10000.00
Delay : 140

Settings:
Overload: Ir = 1.00 x 0.88 x In
Magnetic: Im(Isd) = 10.0 x Ir
tm = 60 ms
Ecodial 3 Technical documentation

General characteristics
Calculation Global characteristics

Parameters Default cicuit characteristics


Ecodial 3 Technical documentation

Default cicuit characteristics

Pre-sizing

power sum Diagram


step-by-step
Ecodial 3 Technical documentation

Step-by-step istallation calculation

Calculation Calculate
Ecodial 3 Technical documentation

TR1
Items
800 KVA Power

Calculate

TR1
Summary
Details
LV switchboard busbars
Next circuit >>
Items LV switchboard
Calculate
Ecodial 3 Technical documentation

50 m. Air conditioning
BTS
Air cond.
BTS Lengh(m) 50 m.
Calculate
Ecodial 3 Technical documentation

25 m. To Switch. 2
No. 16.
To Switch. 2
Items
25 m. Length(m.)

Installation method
Guide
Ecodial 3 Technical documentation

D 16
Guide
OK
Calculation of To Switch. 2 Calculate

Calculate all

Close
Ecodial 3 Technical documentation

Displaying the calculation results

Display
Calculation annotations

Display calculation results

Close
Ecodial 3 Technical documentation

Updating calculations after modifying a circuit


BTS Offices
Offices
Circuit description
Ecodial 3 Technical documentation

Cable Description
BTS

BTS Cable OK
Ecodial 3 Technical documentation

Offices
Calculation
Update calculations

Saving the project

File Save
Ctrl + S

Preparing the item lists

Network Item lists


Ecodial 3 Technical documentation

Cable
Characteristics Cable Item type
Ecodial 3 Technical documentation

Characteristics list
Characteristics list Item lists
Insulation
Insulation Add >>
Selected characteristics
Item lists
Installation method Selected characteristics
Selected characteristics << Remove

Selected characteristics OK
Item lists
Ecodial 3 Technical documentation

Circuit-breaker
Item lists Network Item lists
Circuit breaker Item type
Characteristics

Characteristics

Add>> Characteristics list Installation


Selected characteristics
Item lists

Down Up
OK
Ecodial 3 Technical documentation

Entering the general information

File
General information

Company General information

Address
Ecodial 3 Technical documentation

By default

Project General information


Ecodial 3 Technical documentation

Printing the documents


Calculation results Item lists
File Print / Export

Item lists Calculation results Directory


Print
Single-line diagram
Preview Directory

Preview Equipment
Ecodial 3 Technical documentation

75 Zoom

Print
Close
print and export Directory
RTF
Print

Directory Print and export


Item Equipment Front page
Diagram Calculation results lists

Saving the project

File Save
Ecodial 3 Technical documentation

Comparig ( time - current ) curves

Q1
STR25DE unit trip Compact C1251N
Q4
STR23SE unit trip Compact NS400N

Tools Curve comparison


Ecodial 3 Technical documentation

Add a curve ) Curve comparison

Q1 Display a curve
Q1 OK

Q4 Q4
Q1
Ecodial 3 Technical documentation

short time Long time


Instantaneous
discrimination

Curve comparison X
File Quit
Ecodial 3 Technical documentation

Page : 1 / 2 Equipment

Switchboard 2
Designation STANDARD
Incoming To switch.2
Earthing arra. TNS
Un (V) 400 V
Ib (A) 306.0 A

Offices Parking
Q6-C6-L6 Q7-C7-L7
Outgoing
Ib (A) 180.43 200.00
Designation NS250N NS250N
Breaking capacity (kA) 36.0 36.0
Trip unit rating (A) 200.0 200.0
Trip unit / Curve TM-D TM-D
Insulation XLPE
Earth-leakage protection No No
Conductor metal
Length (m) 0.0 30.0
Installation method Flat EJ(1)
Nb Ph conductor 1
CSA Ph conductor (mm²) 70.0
Nb N conductor 1
CSA N conductor (mm²) 70.0
Nb PE conductor 1
CSA PE conductor (mm²) 70.0
Isc upstream (kA) 15.6716 15.6716
Isc downstream (kA) 15.672 11.343
I fault (kA) 10.9903 5.8937
dU circuit (%) 0.00 0.83
Cumulated dU (%) 0.53 1.36

Number : 1001 Customer :


Name : Guided example / Eng. THABIT F. SYASNEH
Schematic :Single line diagram
Site : Guided example DesignationInstallation
: network Diagram
1 /: 1

Page : 2 / 2 Equipments
Ecodial 3 Technical documentation

Switchboard2
Designation STANDARD
Incoming TR1
Earthing arra. TNS
Un (V) 400 V
Ib (A) 924.3 A

TR1 Air cond To switch.2


T1-C1-Q1 Q3-C3-L3 Q4-C4
Outgoing Switchboard2 Switchboard
Ib (A) 721.71 306.00
Designation C1251N C801N NS400N
Breaking capacity (kA) 50.0 50.0 45.0
Trip unit rating (A) 1250.0 800.0 400.0
Trip unit / Curve STR25DE STR25DE STR23SE
Insulation XLPE
Earth-leakage protection Yes No No
Conductor metal
Length (m) 5.0 50.0 25.0
Installation method Flat Flat D(16)
Nb Ph conductor 1
CSA Ph conductor (mm²) 240.0
Nb N conductor 1
CSA N conductor (mm²) 240.0
Nb PE conductor 1
CSA PE conductor (mm²) 120.0
Isc upstream (kA) 18.7690 18.5904 18.5904
Isc downstream (kA) 18.590 15.688 15.672
I fault (kA) 16.5035 11.1504 10.9903
dU circuit (%) 0.11 1.68 0.42
Cumulated dU (%) 0.11 1.79 0.53

Number : 1001 Customer :


Name : Guided example / Eng. THABIT F. SYASNEH
Schematic :Single line diagram
Site : Guided example DesignationInstallation
: network Diagram
1 /: 1

Page : 1 / 2 Item lists

CABLE C4 C7
Length (m) 25.0 30.0
Installation method D(16) EJ(1)
Neutral metal Copper Copper
Insulation XLPE XLPE
Nb Ph conductor 1 1
CSA Ph conductor (mm²) 240.0 70.0
Nb N conductor 1 1
CSA N conductor (mm²) 240.0 70.0
Nb PE conductor 1 1
CSA PE conductor (mm²) 120.0 70.0
Type of conductor Single-core Multicore
Neutral loaded No No
Conductor arrangement Trefoil
Type of PE PE separate PE included
Number of additional joined circuits
Number of layers 1 1
K user 1.00 1.00
Ambient temperature (°C) 30 30
Delta U max Circuit (%) 5.00 5.00
Reference
Phase Metal Copper Copper
PE metal Copper Copper
Safety voltage (V) 50 50
Automatic calculation auto auto
Calculation mode : Load
Ecodial 3 Technical documentation

LOAD L3 L6 L7
Phase loading Automatic Automatic Automatic
Ib (A) 721.71 180.43 200.00
Circuit polarity 3P + N 3P + N 3P + N
Earthing arrangement TNS TNS TNS
Power (kW) 400.00 100.00 110.85
Number of identical circuits 1 1 1
Power factor 0.80 0.80 0.80
Fixed / Mobile Fixed Fixed Fixed

CIRCUIT-BREAKER Q1 Q3 Q4 Q6
Range Compact Compact Compact Compact
Designation C1251N C801N NS400N NS250N
Trip unit / Curve STR25DE STR25DE STR23SE TM-D
Nb poles protected 3P3TU 3P3TU 3P3TU 3P3TU
Earth-leakage protection Yes No No No
Trip unit rating (A) 1250.0 800.0 400.0 200.0
Io setting 1.00 1.00 0.80
Ir setting 0.88 0.92 0.98 1.00
Im/Isd setting 10.0 10.0 10.0 10.0
Installation Fixed Fixed Fixed Fixed
I thermal setting (A) 1100.0 736.0 313.6 200.0
I magnetic setting (A) 11000 7360 3136 2000
Frame rating (A) 1250 800 400 250
Motor mechanism Without Without Without Without
Cascading requested Yes Yes Yes Yes
Discrimination requested Yes Yes Yes Yes
Short-time delay - - - -

CIRCUIT-BREAKER Q7
Range Compact
Designation NS250N
Trip unit / Curve TM-D
Nb poles protected 3P3TU

Page : 2 / 2 Item lists

Earth-leakage protection No
Trip unit rating (A) 200.0
Io setting
Ir setting 1.00
Im/Isd setting 10.0
Installation Fixed
I thermal setting (A) 200.0
I magnetic setting (A) 2000
Frame rating (A) 250
Motor mechanism Without
Cascading requested Yes
Discrimination requested Yes
Short-time delay -

BTS C1 C3 C6
Designation KTA12 PER KVA80 PER KVA20 PER
Length (m) 5.0 50.0
Calculation mode : Load Sub-feeder Sub-feeder Sub-feeder
Installation Flat Flat Flat
Application Transport link Transport link Transport link
the source of the the source of the the source of the
Breaking capacity adjusted for an Icc at
busbar busbar busbar
Ib (A) 1099.7 721.7 180.4
IP _ _ _
E fixation _ _ _
K user 1.00 1.00 1.00
Delta U max Circuit (%) 5.00 5.00 5.00
Ecodial 3 Technical documentation
Earthing arrangement TNS TNS TNS
Neutral loaded No No No
Ambient temperature (°C) 35 35 35
Safety voltage (V) 50 50 50
Circuit polarity 3P + N 3P + N 3P + N

TRANSFORMER T1
Power (kVA) 800
Connection Delta-Star
Earthing arrangement TNS
Distributed neutral Yes
Un Ph-Ph (V) 400
System frequency (Hz) 50
Short-circuit voltage (%) 6.00
HV Psc (MVA) 500
HV operating time (ms) 500

BUSBAR B2 B5
Standardised Standardised
Busbar type
edgewise edgewise
Length (m)
In (A) 1099.7 313.6
Conductor metal
Nb of bars in // 2 1
Thickness (mm) 5.0 5.0
Width (mm) 50 32
Power factor 0.80 0.80
Circuit polarity 3P + N 3P + N
Ambient temperature (°C) 30 30
T°C max perm. on Isc (°C) 145 145
Degree of protection IP < 30 IP < 30
Earthing arrangement TNS TNS
Metal Copper Copper
Control
Automatic calculation auto auto
Page : 1 / 7 Calculation results

Project Guided example / Eng. THABIT F. SYASNEH :

Network Earthing arrangement: TNS


Voltage: 400 V
Cascading requested: Yes
Discrimin. requested: Yes
Max. permissible CSA: 300.0 mm²
CSA N / CSA Ph: 1
CSA tolerance: 5.0 %
Target power factor: 0.97
System frequency: 50 Hz

Circuit : TR1 ( T1-C1-Q1) Calculated


Upstream :
Downstream : Switchboard2
Voltage : 400 V

Source : T1
Upstream
Upstream short-circuit power: 500 MVA
Upstream impedances: Resistance Rt: 0.0351 mOhm
Inductance Xt: 0.3510 mOhm
Transformer :
Number of transformers: 1 Earthing arrangement: TNS
Total power: 800 kVA Unit power: 800 kVA
Connection: Delta-Star Short-circuit voltage: 6.00 %
Source impedances: Resistance Rt: 4.1013 mOhm
Ecodial 3 Technical documentation
Inductance Xt: 12.5685 mOhm

Busbar trunking system (BTS): C1


Type: KTA12 PER In permissible: 1200.0 A
Length: 5.0 m DU (%): 0.11 %
Calculation mode : Sub-feeder K user: 1.00
Installation method: Flat Application: Transport link
Sizing constraint: demand current
The thermal withstand was checked
Voltage drop upstream circuit downst.
U (%) 0.00 0.11 0.11
Calculation results:

Isc upstr. Ik3max Ik2max Ik1max Ik2min Ik1min I fault


(kA) 18.5904 16.0914 18.3815 14.5441 16.5963 16.5035
R (m ) 4.3264 8.6528 4.5164 8.7406 4.6042 4.6119
X (m ) 12.9945 26.0041 13.0945 26.0041 13.0945 13.1745

Results of calculations as per UTE C15-500 (CENELEC R064-003).


UTE approval 15L-506
Assumptions and choice of devices are the responsibility of the user.

Circuit breaker: Q1
Name: C1251N-50.0 kA Frame rating: 1250 A
Trip unit rating (In): 1250.0 A Trip unit: STR25DE
Number of poles: 3P3TU
Discrimination limit:
BC reinforced by cascading:
Earth leakage protection: Yes
Earth leakage protection device : RH328A
Sensitivity : 250000.00
Delay : 250
Settings:
Overload: Ir = 1.00 x 0.88 x In
Magnetic: Im(Isd) = 10.0 x Ir
tm = 60 ms
Page : 2 / 7 Calculation results

Switchboard2 ( B2) Calculated Circuit :

Upstream : TR1
Downstream : Air cond
Voltage : 400 V

B2 Busbars:
Designation: STANDARD Dimensions: 0.0 m-2// 5.0 mmx50 mm
Type : Standardised edgewise Metal: Copper
Ambient temperature: 30 °C I available: 1190 A
Short-circuit temperature: 145 °C Isc max: 18.59 kA
Ks : 0.90 Isc peak (k 37.18 kA
Ecodial 3 Technical documentation

Page : 3 / 7 Calculation results

Circuit : Air cond ( Q3-C3-L3) Calculated

Upstream : Switchboard2
Downstream :
Voltage : 400 V

Circuit breaker: Q3
Name: C801N-50.0 kA Frame rating: 800 A
Trip unit rating (In): 800.0 A Trip unit: STR25DE
Number of poles: 3P3TU
Discrimination limit:
BC reinforced by cascading: 50.0 kA
Earth leakage protection: No
Earth leakage protection device : -
Sensitivity : -
Delay : -

Settings:
Overload: Ir = 1.00 x 0.92 x In
Magnetic: Im(Isd) = 10.0 x Ir
tm = 60 ms

Busbar trunking system (BTS): C3


Type: KVA80 PER In permissible: 800.0 A
Length: 50.0 m U (%): 1.68 %
Calculation mode : Sub-feeder K user: 1.00
Installation method: Flat Application: Transport link
Sizing constraint: demand current
The thermal withstand was checked
Voltage drop upstream circuit downst.
U (%) 0.11 1.68 1.79

Calculation results:
Isc upstr. Ik3max Ik2max Ik1max Ik2min Ik1min I fault
(kA) 18.5904 15.6878 13.4781 12.6737 11.5263 10.2520 11.1504
R (m ) 4.3264 9.2014 18.4028 14.2664 21.5960 17.4596 15.2619
X (m ) 12.9945 13.3695 27.0541 14.1445 27.0541 14.1445 13.9245
Results of calculations as per UTE C15-500 (CENELEC R064-003).
UTE approval 15L-506
Assumptions and choice of devices are the responsibility of the user.

Load
I: 721.71 A Polarity of circuit: 3P + N
P: 400.00 kW Earthing arrangement: TNS
Power factor 0.80 Phase distribution: -
Ku: 1.0
Ecodial 3 Technical documentation

Page : 4 /7 Calculation results

Circuit : To switch.2 ( Q4-C4) Calculated

Upstream : Switchboard2
Downstream : Switchboard 2
Voltage : 400 V

Circuit breaker: Q4
Name: NS400N-45.0 kA Frame rating: 400 A
Trip unit rating (In): 400.0 A Trip unit: STR23SE
Number of poles: 3P3TU
Discrimination limit: 12 kA
BC reinforced by cascading: 50.0 kA
Earth leakage protection: No
Earth leakage protection device : -
Sensitivity : -
Delay : -

Settings:
Overload: Ir = 0.80 x 0.98 x In
Magnetic: Im(Isd) = 10.0 x Ir
tm = 60 ms

Cable : C4
Length: 25.0 m Installation method: D(16)
Cable type: Single-core Number of layers: 1
Insulation: XLPE Nb additional touching circuits: 0
Arrangement of conductors: Trefoil Iz : 350.6 A
Sizing constraint: demand current
Correction ( Temperature x Installation method x Neutral x Grouping x User / Protection ) :
0.93 x 1.00 x 1.00 x 1.00 x 1.00 / 1.00 = 0.93
CSA (mm²) theoretical used reference metal
Per phase 1 x 224.0 1 x 240.0 Copper
Neutral 1 x 224.0 1 x 240.0 Copper
PE 1 x 120.0 1 x 120.0 Copper

Voltage drop upstream circuit total.


U (%) 0.11 0.42 0.53

Calculation results:
Isc upstr. Ik3max Ik2max Ik1max Ik2min Ik1min I fault
(kA) 18.5904 15.6716 13.5662 13.3761 12.1004 11.7673 10.9903
R (m ) 4.3264 6.2545 12.5091 8.3727 13.6766 9.5402 12.0159
X (m ) 12.9945 14.9945 30.0041 17.0945 30.0041 17.0945 17.1745

Results of calculations as per UTE C15-500 (CENELEC R064-003).


UTE approval 15L-506
Assumptions and choice of devices are the responsibility of the user.

Load
I: 306.00 A Polarity of circuit: 3P + N
P: 169.60 kW Earthing arrangement: TNS
Power factor 0.80 Phase distribution: -
Ku: 1.0
Ecodial 3 Technical documentation

Page : 5 / 7 Calculation results

Circuit : Switchboard 2 ( B5) Calculated

Upstream : To switch.2
Downstream : Offices
Voltage : 400 V

Busbars: B5
Designation: STANDARD Dimensions: 0.0 m-1// 5.0 mmx32 mm
Type : Standardised edgewise Metal: Copper
Ambient temperature: 30 °C I available: 400 A
Short-circuit temperature: 145 °C Isc max: 15.67 kA
Ks : 0.90 Isc peak (k 31.34 kA

Page : 6 / 7 Calculation results

Circuit : Offices ( Q6-C6-L6) Calculated

Upstream : Switchboard 2
Downstream :
Voltage : 400 V

Circuit breaker: Q6
Name: NS250N-36.0 kA Frame rating: 250 A
Trip unit rating (In): 200.0 A Trip unit: TM-D
Number of poles: 3P3TU
Discrimination limit:
BC reinforced by cascading: 45.0 kA
Earth leakage protection: No
Earth leakage protection device : -
Sensitivity : -
Delay : -

Settings:
Overload: Ir = 1.00 x In
Magnetic: Im(Isd) = 10.0 x Ir

Busbar trunking system (BTS): C6


Type: KVA20 PER In permissible: 200.0 A
Length: 0.0 m U (%): 0.00 %
Calculation mode : Sub-feeder K user: 1.00
Installation method: Flat Application: Transport link
Sizing constraint: demand current
The thermal withstand is not verified
Voltage drop upstream circuit downst.
U (%) 0.53 0.00 0.53

Calculation results:
Ecodial 3 Technical documentation
Isc upstr. Ik3max Ik2max Ik1max Ik2min Ik1min I fault
(kA) 15.6716 15.6716 13.5662 13.3761 12.1004 11.7673 10.9903
R (m ) 6.2545 6.2545 12.5091 8.3727 13.6766 9.5402 12.0159
X (m ) 14.9945 14.9945 30.0041 17.0945 30.0041 17.0945 17.1745
Results of calculations as per UTE C15-500 (CENELEC R064-003).
UTE approval 15L-506
Assumptions and choice of devices are the responsibility of the user.

Load
I: 180.43 A Polarity of circuit: 3P + N
P: 100.00 kW Earthing arrangement: TNS
Power factor 0.80 Phase distribution: -
Ku: 1.0

Page : 7 / 7 Calculation results

Circuit : Parking ( Q7-C7-L7) Calculated

Upstream : Switchboard 2
Downstream :
Voltage : 400 V

Circuit breaker: Q7
Name: NS250N-36.0 kA Frame rating: 250 A
Trip unit rating (In): 200.0 A Trip unit: TM-D
Number of poles: 3P3TU
Discrimination limit:
BC reinforced by cascading: 45.0 kA
Earth leakage protection: No
Earth leakage protection device : -
Sensitivity : -
Delay : -

Settings:
Overload: Ir = 1.00 x In
Magnetic: Im(Isd) = 10.0 x Ir

Cable : C7
Length: 30.0 m Installation method: EJ(1)
Cable type: Multicore Number of layers: 1
Insulation: XLPE Nb additional touching circuits: 0
Arrangement of conductors: Iz : 245.6 A
Sizing constraint: demand current
Correction ( Temperature x Installation method x Neutral x Grouping x User / Protection ) :
1.00 x 1.00 x 1.00 x 1.00 x 1.00 / 1.00 = 1.00
CSA (mm²) theoretical used reference metal
Per phase 1 x 51.0 1 x 70.0 Copper
Neutral 1 x 51.0 1 x 70.0 Copper
PE 1 x 35.0 1 x 70.0 Copper

Voltage drop upstream circuit total.


U (%) 0.53 0.83 1.36
Ecodial 3 Technical documentation

Calculation results:
Isc upstr. Ik3max Ik2max Ik1max Ik2min Ik1min I fault
(kA) 15.6716 11.3430 9.8208 7.7951 8.2024 6.2231 5.8937
R (m ) 6.2545 14.1874 28.3748 24.2384 33.9847 29.8483 32.3240
X (m ) 14.9945 17.3945 34.8041 21.8945 34.8041 21.8945 21.9745
Results of calculations as per UTE C15-500 (CENELEC R064-003).
UTE approval 15L-506
Assumptions and choice of devices are the responsibility of the user.

Load
I: 200.00 A Polarity of circuit: 3P + N
P: 110.85 kW Earthing arrangement: TNS
Power factor 0.80 Phase distribution: -
Ku: 0.8

Single line diagram

800kVA 400V 50Hz


T1 Ikmax=18.8 kA
Ib=1099.7 A

5.0m-dU=0.11%
KTA12 PER
C1
Ikmax=18.59 kA

C1251N-1250.0 A
Q1 STR25DE
Ir:1.00x0.88xIn
Im(Isd):10.0xIr Ikmax=18.59 kA
B2
C801N-800.0 A NS400N-400.0 A
Q3 STR25DE Q4 STR23SE
Ir:1.00x0.92xIn Ir:0.80x0.98xIn
Im(Isd):10.0xIr Im(Isd):10.0xIr

50.0m-dU=1.68% D(16)-25.0m-dU=0.42%
KVA80 PER Ph=1x240.0-Copper
C3 C4
Ikmax=15.69 kA N=1x240.0-Copper
PE=1x120.0-Copper Ikmax=15.67 kA
B5
Ikmin=10.2520 kA NS250N-200.0 A NS250N-200.0 A
L3 id:11.1504kA Q6 TM-D Q7 TM-D
Ir:1.00xIn Ir:1.00xIn
dU total=1.79 %
Im(Isd):10.0xIr Im(Isd):10.0xIr

x1 0.0m-dU=0.00% EJ(1)-30.0m-dU=0.83%
KVA20 PER Ph=1x70.0-Copper
C6 C7
Ikmax=15.67 kA N=1x70.0-Copper
PE=1x70.0-Copper
Ikmin=11.7673 kA Ikmin=6.2231 kA
L6 id:10.9903kA L7 id:5.8937kA
dU total=0.53 % dU total=1.36 %

x1 x1

Number : 1001 Customer :


Name : Guided example / Eng. THABIT F. SYASNEH
Schematic : Single line diagram
Site : Guided example Designation : Installation network Diagram
1:/ 1