Professional Documents
Culture Documents
Kebutuhan Wiremesh PDF
Kebutuhan Wiremesh PDF
Kebutuhan Wiremesh PDF
Koefisien Volume
Volume Beton
Wiremesh Wiremesh
Item Pekerjaan
a b c = (a x b)
m2/m3 m3 m2
Main Road (Sta 0+000 ‐ Sta 0+025) 6.67 650.63 4337.54
9.08 (1) Perkerasan Beton, Single Wire Mesh
Simpang Sebidang 6.67 170.99 1139.96
Main Road (Sta 0+000 ‐ Sta 0+100) 3.33 210.00 700.00
9.08 (3) Perkerasan Beton Dengan Double Wiremesh Main Road (Sta 1+750 ‐ Sta 1+850) 3.33 981.00 3270.00
Simpang Sebidang 3.33 348.85 1162.82
Total 10610.32