Sri K.V.Ramana Reddy, B.E, The Joint Director (R&B),
Dy. Executive Engineer(R&B), Road Research Station,
Sub Division Medak, Errum Manzil, Hyderabad
Medak
Lr. No. DEE/R&B/MDK/SN road via Bujrampally /HLB/2019-20/ Dated: -2019.
Sir,
Sub:- (R&B) Medak Sub Division – “Construction of HLB at km 4/0-2 on
Shankarampet narayankhed via Bujrampally in Medak district. “-
Necessary Test results of samples – Request - Regarding.
With reference to the subject cited above, I Submit that the subject work was let
out to M/s HSR Ventures Pvt Ltd.
I herewith furnish the Aggregate samples collected from quarry to be used for
the subject work to your kind office.
Samples:
1. 10mm nominal size HBT metal
2. 20mm nominal size HBT metal
3. 40mm nominal size HBT metal
Yours Faithfully,
From:- To:-
Sri M.Chandraiah, M.Tech., M/s JMC Constructions Pvt.Ltd.,
District Roads & Builidngs Officer, #8-3-944/4, Ground floor,
Medak District. Yellareddyguda, SVR Travel lines
Ameerpet, Hyderabad.
Gentlemen,
Sub:- (R&B) Medak Division – “Improvements and Strengthening of Hyderabad –Medak –
Bodhan road from km 80/3 -85/0 (Medak town limits) in Medak District” – Slow
Progress of work – 2nd Notice issued – Regarding.
%%%%
The above work was let out to you vide Superintending Engineer (R&B) Circle,
Sangareddy agreement reference 1st cited above, with a stipulation to complete the work within (18)
months from the date of entering into agreement i.e., by 06-10-2018.
Further this office issued notices vide reference 3rd & 5th cited to speed up the work
and complete the entire work within the agreement period. But there is no response from your end.
As reported by the Deputy Executive Engineer (R&B) Sub – Division, Medak vide
reference 4th cited, there is no progress in speeding up of the work and standstill since long time no
activity is seen at site.
Therefore you are requested to submit EOT proposals and speed up the work by
engaging sufficient men and machinery to maintain the rate of progress and you are requested to
resume the work and show the progress within (07) days .Otherwise action will be initiated as per
agreement condition to terminating the work under 60 ©.
Yours Sincerely
Sd/-
District Roads & Buildings Officer,
Medak District.
Copy submitted to the Superintending Engineer/R&B/Circle, Sangareddy for favour of
Kind information.
Copy to the Assistant Executive Engineer (R&B) Medak Section for information.
From: To:
Sri. K.V.Ramana Reddy, B.E., The Executive Engineer(R&B),
Dy.Executive Engineer (R&B), Division Medak
Sub- Division : Medak.
%%%%
The above work was let out to M/s JMC Constructions vide Superintending Engineer
(R&B) Circle, Sangareddy agreement reference 1st cited above, with a stipulation to complete the
work within (18) months from the date of entering into agreement i.e., by 06-10-2018.
In compliance to the noticed issued vide reference 6th cited it is submitted that the
work is not yet resumed and there are no activity of work as on today i.e., 21-12-2018.
I request to the Executive Engineer (R&B) Division, Medak to kindly take necessary
action as deemed fit as per the agreement conditions at the earliest.
Yours faithfully,
From:- To:-
Sri M.Chandraiah, M.Tech., M/s JMC Constructions Pvt.Ltd.,
District Roads & Builidngs Officer, #8-3-944/4, Ground floor,
Medak District. Yellareddyguda, SVR Travel lines
Ameerpet, Hyderabad.
Gentlemen,
%%%%
The above work was let out to you vide Superintending Engineer (R&B) Circle,
Sangareddy agreement reference 1st cited above, with a stipulation to complete the work within (18)
months from the date of entering into agreement i.e., by 06-10-2018.
As reported by the Deputy Executive Engineer (R&B) Sub – Division, Medak vide
reference 4th cited, there is no progress in speeding up of the work with this rate of progress of work
it is very difficult to achieve the mile stone given by you.
Therefore you are requested to speed up the wok and accelerate the rate of progress
by engaging sufficient men and machinery to maintain the rate of progress as per mile stone and
complete the entire work within the agreement period. Otherwise action will be initiated as per
agreement condition for imposing liquidated damages.
Yours Sincerely
Copy to the Assistant Executive Engineer (R&B) Medak Section for information.
GOVERNMENT OF TELAGANA
ROADS & BUILDINGS DEPARTMENT
From:- To:-
Gentlemen,
%%%%
The above work was let out to you vide Superintending Engineer (R&B) Circle,
Sangareddy agreement reference 1st cited above, with a stipulation to complete the work within (18)
months from the date of entering into agreement i.e., by 06-10-2018.
As reported by the Deputy Executive Engineer (R&B) Sub – Division, Medak vide
reference 2nd cited, As per the construction programme submitted by the agency till the end of 1st
mile stone i.e., Nine months from the date of handing over the site, the progress of work is very slow
and lagging the 1st mile stone target. You are failed to achieve the rate of progress as per the
construction programme. With this progress of work it is very difficult to achieve further mile stones
given by you.
Therefore you are requested to speed up the wok and accelerate the rate of progress
by engaging sufficient men and machinery to maintain the rate of progress as per mile stone and
complete the entire work within the agreement period and you are requested to submit revised
programme of work. Otherwise action will be initiated as per agreement condition for imposing
liquidated damages.
Yours Sincerely
Sd/-
District Roads & Buildings Officer,
Medak District.