Professional Documents
Culture Documents
GU-450
Guidelines for Inspection and Integrity
Assessment of Carbon Steel Non-Piggable
Pipelines
Guidelines for Inspection and Integrity Assessment of CS Non-Piggable Pipelines Version 1
Signed :............................................................
(CFDH – Pipelines)
The following table lists the four most recent revisions to this document. Details of all revisions prior to
these are held on file by the issuing department.
Keywords:
This document
External MFL, Non
is thePiggable
propertyPipelines,
of Petroleum
Technical
Development
Integrity,
Oman,
Corrosion
LLC. Neither the whole nor any part
of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted
in any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior
written consent of the owner.
Page i
Guidelines for Inspection and Integrity Assessment of CS Non-Piggable Pipelines Version 1
Contents
Contents.......................................................................................................................................ii
1 Introduction...........................................................................................................................1
1.1 Purpose..............................................................................................................................1
1.2 Scope..................................................................................................................................1
1.3 Target audience..................................................................................................................1
1.4 Structure of This Document..............................................................................................1
2 Background............................................................................................................................2
3 Inspection strategy................................................................................................................3
3.1 Priority Setting for Baseline Inspection............................................................................3
3.2 Calculation of Minimum Acceptable Thickness...............................................................3
3.3 Above Ground pipelines....................................................................................................4
3.4 Class 1 and 2 Non Piggable Buried Pipelines..................................................................4
3.5 Selection of Inspection Areas:...........................................................................................6
4 Related Documents................................................................................................................7
4.1 Business Control Documents............................................................................................7
4.2 Review and Improvement..................................................................................................7
4.3 Step-out and Approval.......................................................................................................7
1 Introduction
1.1 Purpose
The purpose of this document is to provide guidance on the integrity assessment of non-
piggable pipelines. Guidance is given to define the inspection scope and the analysis of the
inspection results. This should enable the assurance of technical integrity and/or definition of
rehabilitation scope for pipelines of which at present the condition is unknown. The aim of
this procedure is to set out the basic steps that should be followed in order to accurately
determine the internal and external condition of non-piggable pipelines.
1.2 Scope
The scope of this guideline covers non-piggable pipelines all classes buried and above ground,
which total 153 at present (2003). Flowlines, are excluded from the scope of this document.
This document is to be used by the TTO/1 Integrity Engineers and Corrosion Engineers and
by the Asset Team Integrity Focal points. It is also to be used by external MFL contractors in
optimising locations for inspection.
The core requirement of this document is contained in sections 2 describing Non Piggable
Pipelines Inspection Guidelines. Note that there is a separate guideline being drafted for
flowline integrity management.
2 Background
Pipeline design guidelines are specified in SP1211 1. Within PDO, pipelines are categorised into
one of three “Pipeline Criticality Classes”; hereafter referred to as “Class 1”, “Class 2” and
“Class 3” respectively. Class 1 is further subdivided in Class 1a and Class 1b.
According to SP1211, All Class 1 pipelines shall be suitable to pass pigs, even if pig traps are
not permanently installed, but this is not always practicable for lines constructed in the past and
in particular short pipelines (e.g. less than 2 km) and headers are often not piggable. PDO now
operates about 83 non-piggable class-1 pipelines and about 84 non-piggable for class 2 & 3
pipelines, as listed in Table 1 below. Details are in Appendix B.
GGO 0 0 14 0 14
Total 30 58 53 26 167
Many of these non-piggable pipelines do not have a corrosion control strategy and the technical
integrity of most is unknown. This has been identified as providing a high integrity risk to PDO
with respect to loss of production, high cost of failure/degradation and high failure safety risk.
As part of the technical integrity drive and risk management strategy, a need was identified to
develop the strategy to assure the integrity of non-piggable pipelines as outlined in this
guideline.
As part of the non-piggable pipelines procedure a new assessment of the ACR of a pipeline shall
be carried out, and shall be approved by the Corrosion Engineer with the appropriate Technical
Authority (TA-2), Integrity Engineer and pipeline owner. The approval form shall be part of the
procedure and shall be signed off by all concerned parties before the ACR can be used in RBA.
The approval form will be referred to as the ACR report for non-piggable pipelines.
1
SP1211: “DEP 31.40.00.10-PDO Pipeline Engineering”
3 Inspection strategy
3.1 Priority Setting for Baseline Inspection
Class-1 pipelines shall have priority over class-2 pipelines. Class-1a pipelines shall have
priority over class-1b pipelines. Class 3 pipelines do not need to be inspected for internal
corrosion.
Within class 1 pipelines, high pressure wet gas pipelines should have the highest priority. In
addition, the inspection program is to be also based on future requirements of pipelines.
A- Production rate (Oil deferment consequences):- Pipelines transporting a net oil of more
than 1500 cu.m/day (hypothetical value representing about 1% of PDO production.
Prior to inspection, the potential corrosion type shall be assessed making use of Table 2 and the
resulting Minimum Allowable Thickness (MAT) shall be calculated as depicted in Figure 1 and
described in Appendix 3. The threshold T = (t – MAT) shall be calculated. A spread sheet for
this calculation is readily available with TTO/13.
Defect length
General corrosion Defect
depth
Defect length
L/t=80 Groovingcorrosion
L/t=20 Pittingcorrosion
Defect depth
80%
General corrosion
Groovingcorrosion
Pittingcorrosion
Corrosion MAT
Tolerance
All above ground Class 1 and 2 non-piggable pipelines should be inspected using external MFL
or similar type scanning inspections tools. For oil service, it is acceptable to inspect the bottom
half of the pipeline where water is expected to settle and corrosion to occur. For gas or water
service, the full circumference should be inspected. In addition road crossings should be
inspected making use of Long Range Ultrasonic Testing or full excavation. Further guidance on
selection of inspection location are provided in section 3.5
The inspection scope depends on the pipeline length. In the case of less than 100% inspection, a
number of sections (at least 4) should be selected along the pipeline where corrosion is most
susceptible.
For pipelines less than 10 km, half of the pipeline length should be inspected with a
minimum of 2km. If there are no defects with a depth in excess of the set threshold T,
then the inspection can be considered to be representative for the whole pipeline.
Otherwise, the remainder of the pipeline should be inspected except in those cases
where the requirement for line abandonment is already obvious.
A minimum of 20% of the total length should be inspected with a minimum of 500
m. If there are no defects with a depth in excess of the set threshold T, then the
inspection can be considered to be representative for the whole pipeline. Otherwise,
another 20% of the pipeline should be inspected except in those cases where the
requirement for line abandonment is already obvious.
There are approximately 55 class 1 (1a & 1b) pipelines distributed throughout PDO areas. 27 of
these in the North, mainly in Lekhwair and Yibal, 4 in the South mainly in Marmul and 24 lines
for the Infrastructure team. These pipelines range in diameter from 4-inch up to 36-inch and in
length from 0.41 km up to 31 km. There are approximately 26 Class-2 pipelines distributed
throughout PDO areas. 19 of these in the North and 7 in the South. These pipelines range in
diameter from 2-inch up to 16-inch and in length from 0.1 km up to 11.5 km.
The following activities to be carried out in order to reach a decision on the integrity and fitness
for purpose:-
2- Carry out External MFL inspection at above ground sections of the pipeline. This
is applicable for lines with diameters between 4”-12” as these are the current MFL
tool inspection ranges.
4- Excavate a number of locations as given in Table 3 and inspect a full joint using
manual UT or external MFL and if corrosion is found that requires monitoring then
AutoUT maybe used for those locations. It is also recommended that these excavated
locations to be inspected via LRUT for +/- 10m in both directions from the end of
the excavation.
A Pipe-RBA assessment shall be made on basis of the inspection results, taking into
consideration that the pipeline has only been inspected over a small percentage.
If the inspection shows severe corrosion and the asset team are still keen in using the pipeline
for a limited period of time (up to 3 years) in order to allow time for replacement, then the
pipeline shall be hydrotested to 1.25XMAOP. It is crucial to state that hydrotesting the pipeline
will not guarantee occurrence of future leaks but will rule out burst type of failure.
The figure below gives guidance on the areas to be inspected during locations selection
exercise.
Inspection Location
Selection
4 Related Documents
4.1 Business Control Documents
Reference is made in this Guideline to the following PDO Business Control Documents, the
latest issue of which shall be used.
Specifications
Pipeline Operations and Maintenance SP1210
Pipeline Engineering SP1211
This Guideline will be reviewed and updated once approved. The review authority will be
(UEL, CFDH Pipelines).
Step out for 2 years is allowed but on every occasion of step out should be advised to UEL giving
the reason for the step out.
Contractor The party, which carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a
project, or operation or maintenance of a facility. The Company
may undertake all or part of the duties of the Contractor.
Company Contract Holder The person assigned by the Company and named in the Contract
Document having single point responsibility for the activity
management of the contract.
Corporate Functional The person responsible for the discipline to which the standard
Discipline Head belongs.
Abbreviations