You are on page 1of 45

FAKULTAS TEKNIK

PROGRAM STUDI TEKNIK SIPIL


UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI

DAFTAR ANALISA
Pekerjaan : Pembangunan Rumah Type Real Estate 180 m2
Lokasi : Perumahan SUKA TIDAK TIDUR
Provinsi : Bengkulu
T. Anggaran : 2019

Jumlah Harga Jumlah Harga


Analisa Uraian Pekerjaan Harga Satuan ( Rp).- Jumlah Harga ( Rp ),-
Bahan Rp,- Upah Rp,-

AHSP-Pper.A.2.2.1.9 1 M2 PEMBERSIHAN LOKASI DAN PERATAAN


UPAH
0.0500 Oh Pekerja Rp. 95,000.00 4,750.00 Rp. 4,750.00
0.0250 Oh Mandor Rp. 150,000.00 3,750.00 Rp. 3,750.00
Rp. 8,500.00
ABK-Pper.6.4 1 M' PENGUKURAN DAN PAS. BOUWPLANK
BAHAN
0.012 M3 kayu bekisting 5/7 cm Rp. 2,000,000.00 24,000.00 Rp. 24,000.00
0.02 Kg Paku campur Rp. 16,000.00 320.00 Rp. 320.00
0.012 M3 Kayu Papan Rp. 2,000,000.00 24,000.00 Rp. 24,000.00
1.000 M Tali Rp. 3,000.00 3,000.00 Rp. 3,000.00
UPAH
0.100 Oh Pekerja Rp. 95,000.00 9,500.00 Rp. 9,500.00
0.100 Oh tukang Rp. 150,000.00 15,000.00 15,000.00
0.010 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.005 Oh Mandor Rp. 170,000.00 850.00 Rp. 850.00
Rp. 78,320.00
AHSP-PT.A.2.3.1.1 1 M3 GALIAN TANAH BIASA ( - 1 M ) 980.45845
UPAH
0.750 Oh Pekerja Rp. 95,000.00 71,250.00 Rp. 71,250.00
0.025 Oh Mandor Rp. 170,000.00 4,250.00 Rp. 4,250.00
Rp. 75,500.00
AHSP-PT.A.2.3.1.1 1 M3 GALIAN TANAH BIASA ( - 2 M )
UPAH
0.750 Oh Pekerja Rp. 95,000.00 71,250.00 Rp. 71,250.00
0.025 Oh Mandor Rp. 170,000.00 4,250.00 Rp. 4,250.00
Rp. 75,500.00
AHSP-PT.A.2.3.1.9 1 M3 URUGAN TANAH KEMBALI
UPAH
0.500 Oh Pekerja Rp. 95,000.00 47,500.00 Rp. 47,500.00
0.050 Oh Mandor Rp. 170,000.00 8,500.00 Rp. 8,500.00
Rp. 56,000.00
AHSP-PT.A.2.3.1.10 1 M3 TIMBUNAN TANAH DIPADATKAN
BAHAN
1.200 M3 Tanah Urug Rp. 55,000.00 66,000.00 Rp. 66,000.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00 28,500.00 Rp. 28,500.00
0.010 Oh Mandor Rp. 170,000.00 1,700.00 Rp. 1,700.00
Rp. 96,200.00
AHSP-PT.A.2.3.1.11 1 M3 URUGAN PASIR
BAHAN
1.200 M3 Pasir urug Rp. 160,000.00 192,000.00 Rp. 192,000.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00 28,500.00 Rp. 28,500.00
0.010 Oh Mandor Rp. 170,000.00 1,700.00 Rp. 1,700.00
Rp. 222,200.00
AHSP-PPon.A.3.2.1.9 1 M3 PAS. BATU KOSONG/Anstampang
BAHAN
1.200 M3 Batu Belah Rp. 245,000.00 294,000.00 Rp. 294,000.00
0.432 M3 Pasir Urug Rp. 160,000.00 69,120.00 Rp. 69,120.00
UPAH
0.780 Oh Pekerja Rp. 95,000.00 74,100.00 Rp. 74,100.00
0.390 Oh Tukang Batu Rp. 150,000.00 58,500.00 Rp. 58,500.00
0.039 Oh Kepala Tukang Rp. 165,000.00 6,435.00 Rp. 6,435.00
0.039 Oh Mandor Rp. 170,000.00 Rp. 6,630.00
Rp. 508,785.00
AHSP-PPon.A.3.2.1.2 1 M3 PAS. PONDASI BATU KALI/GUNUNG: 1 PC : 4 PS
BAHAN
1.200 M3 Batu Kali/Gunung Rp. 245,000.00 294,000.00 Rp. 294,000.00
163.000 Kg Semen Portland Type I Rp. 1,130.00 184,190.00 Rp. 184,190.00
0.520 M3 Pasir Pasang Rp. 200,000.00 104,000.00 Rp. 104,000.00
UPAH
1.500 Oh Pekerja Rp. 95,000.00 142,500.00 Rp. 142,500.00
0.750 Oh Tukang Batu Rp. 150,000.00 112,500.00 Rp. 112,500.00
0.075 Oh Kepala Tukang Rp. 165,000.00 12,375.00 Rp. 12,375.00
0.075 Oh Mandor Rp. 170,000.00 12,750.00 Rp. 12,750.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
Rp. 862,315.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
AHSP-PD.A.4.4.1.9 1 M2 PASANGAN (1/2) BATA 1 PC : 4 PS
BAHAN
70.000 Bh Batu Bata Bolong Rp. 800.00 56,000.00 Rp. 56,000.00
11.500 Kg Semen Portland Type I Rp. 1,130.00 12,995.00 Rp. 12,995.00
0.038 M3 Pasir Pasang Rp. 200,000.00 7,600.00 Rp. 7,600.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00 28,500.00 Rp. 28,500.00
0.010 Oh Tukang Rp. 150,000.00 1,500.00 Rp. 1,500.00
0.010 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.015 Oh Mandor Rp. 170,000.00 2,550.00 Rp. 2,550.00
Rp. 110,795.00
ABK-PD.A.4.4.2.4 1 M2 PLESTERAN 1 : 4 TEBAL 15 mm
BAHAN
6.240 Kg Semen Portland Type I Rp. 1,130.00 7,051.20 Rp. 7,051.20
0.020 M3 Pasir Pasang Rp. 200,000.00 4,000.00 Rp. 4,000.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00 28,500.00 Rp. 28,500.00
0.150 Oh Tukang Batu Rp. 150,000.00 22,500.00 Rp. 22,500.00
0.015 Oh Kepala Tukang Rp. 165,000.00 2,475.00 Rp. 2,475.00
0.015 Oh Mandor Rp. 170,000.00 2,550.00 Rp. 2,550.00
Rp. 67,076.20
ABK-PBtn (6.4) 1 M3 LANTAI KERJA BETON TUMBUK
BAHAN
218.000 Kg Semen Portland Type I Rp. 1,130.00 246,340.00 Rp. 246,340.00
0.520 M3 Pasir Pasang Rp. 200,000.00 104,000.00 Rp. 104,000.00
0.87 M3 Koral Rp. 233,000.00 202,710.00 Rp. 202,710.00
200.00 ltr air Rp. 200 40,000.00 40,000.00
UPAH
1.200 Oh Pekerja Rp. 95,000.00 114,000.00 Rp. 114,000.00
0.200 Oh Tukang Batu Rp. 150,000.00 30,000.00 Rp. 30,000.00
0.020 Oh Kepala Tukang Rp. 165,000.00 3,300.00 Rp. 3,300.00
0.060 Oh Mandor Rp. 170,000.00 10,200.00 Rp. 10,200.00
Rp. 750,550.00
AHSP-PBtn.A.4.1.1.7 1 M3 MEMBUAT BETON K. 250
BAHAN
371.000 Kg Semen Portland Type I Rp. 1,130.00 419,230.00 Rp. 419,230.00
0.698 M3 Pasir Beton Curup Rp. 200,000.00 139,600.00 Rp. 139,600.00
1.047 M3 Koral Beton Rp. 233,000.00 243,951.00 Rp. 243,951.00
200.00 ltr air 200 40,000.00 40,000.00
UPAH
1.650 Oh Pekerja Rp. 95,000.00 156,750.00 Rp. 156,750.00
0.275 Oh Tukang batu Rp. 150,000.00 41,250.00 Rp. 41,250.00
0.028 Oh Kepala Tukang Rp. 165,000.00 4,620.00 Rp. 4,620.00
0.083 Oh Mandor Rp. 170,000.00 14,110.00 Rp. 14,110.00
Rp. 1,059,511.00
AHSP-PBtn.A.4.1.1.17 1 Kg. PEMBESIAN DENGAN BESI POLOS
BAHAN
1.050 Kg Besi Beton D12 Rp. 8,900.00 9,345.00 Rp. 9,345.00
0.015 M3 Kawat Beton Rp. 23,000.00 345.00 Rp. 345.00
UPAH
0.007 Oh Pekerja Rp. 95,000.00 665.00 Rp. 665.00
0.007 Oh Tukang Besi Rp. 150,000.00 1,050.00 Rp. 1,050.00
0.0007 Oh Kepala Tukang Rp. 165,000.00 115.50 Rp. 115.50
0.0004 Oh Mandor Rp. 165,000.00 66.00 Rp. 66.00
Rp. 11,586.50
AHSP-PBtn.A.4.1.1.20 1 M3. PEMBUATAN BEKISTING PONDASI
BAHAN
0.040 M3 Kayu Kelas IV Rp. 2,000,000.00 80,000.00 Rp. 80,000.00
0.300 Kg Paku campur Rp. 14,000.00 4,200.00 Rp. 4,200.00
0.100 Ltr Minyak Begisting Rp. 6,000.00 600.00 Rp. 600.00
UPAH
0.520 Oh Pekerja Rp. 95,000.00 49,400.00 Rp. 49,400.00
0.260 Oh Tukang kayu Rp. 150,000.00 39,000.00 Rp. 39,000.00
0.026 Oh Kepala Tukang Rp. 165,000.00 4,290.00 Rp. 4,290.00
0.026 Oh Mandor Rp. 170,000.00 4,420.00 Rp. 4,420.00
Rp. 181,910.00
AHSP-PBtn.A.4.1.1.21 1 M3. PEMBUATAN BEKISTING SLOOF
BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00 Rp. 80,000.00
0.300 Kg Paku campur Rp. 14,000.00 4,200.00 Rp. 4,200.00
0.100 Ltr Minyak Begisting Rp. 6,000.00 600.00 Rp. 600.00
UPAH
0.520 Oh Pekerja Rp. 95,000.00 49,400.00 Rp. 49,400.00
0.260 Oh Tukang kayu Rp. 150,000.00 39,000.00 Rp. 39,000.00
0.026 Oh Kepala Tukang Rp. 165,000.00 4,290.00 Rp. 4,290.00
0.026 Oh Mandor Rp. 170,000.00 4,420.00 Rp. 4,420.00
Rp. 181,910.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
AHSP-PBtn.A.4.1.1.21 1 M3. PEMBUATAN BEKISTING KOLOM
BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00 Rp. 80,000.00
0.400 Kg Paku campur Rp. 16,000.00 6,400.00 Rp. 6,400.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00 Rp. 1,200.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00 Rp. 40,250.00
2.000 Btg Dolken 15cm Rp. 7,500.00 15,000.00 Rp. 15,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00 62,700.00 Rp. 62,700.00
0.330 Oh Tukang kayu Rp. 150,000.00 49,500.00 Rp. 49,500.00
0.033 Oh Kepala Tukang Rp. 165,000.00 5,445.00 Rp. 5,445.00
0.006 Oh Mandor Rp. 170,000.00 1,020.00 Rp. 1,020.00
Rp. 261,515.00
AHSP-PBtn.A.4.1.1.23 1 M3. PEMBUATAN BEKISTING BALOK
BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00 Rp. 80,000.00
0.400 Kg Paku campur Rp. 14,000.00 5,600.00 Rp. 5,600.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00 Rp. 1,200.00
0.015 M3 Kayu Balok kelas IV Rp. 2,000,000.00 30,000.00 Rp. 30,000.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00 Rp. 40,250.00
2.000 Btg Dolken 15cm Rp. 7,500.00 15,000.00 Rp. 15,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00 62,700.00 Rp. 62,700.00
0.330 Oh Tukang kayu Rp. 150,000.00 49,500.00 Rp. 49,500.00
0.033 Oh Kepala Tukang Rp. 165,000.00 5,445.00 Rp. 5,445.00
0.033 Oh Mandor Rp. 170,000.00 5,610.00 Rp. 5,610.00
Rp. 295,305.00
AHSP-PBtn.A.4.1.1.26 1 M3. PEMBUATAN BEKISTING TANGGA
BAHAN
0.030 M3 Kayu kelas IV Rp. 2,000,000.00 60,000.00 Rp. 60,000.00
0.400 Kg Paku campur Rp. 14,000.00 5,600.00 Rp. 5,600.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00 Rp. 1,200.00
0.015 M3 Kayu Balok kelas IV Rp. 2,000,000.00 30,000.00 Rp. 30,000.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00 Rp. 40,250.00
2.000 Btg Dolken 15cm Rp. 7,500.00 15,000.00 Rp. 15,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00 62,700.00 Rp. 62,700.00
0.330 Oh Tukang kayu Rp. 150,000.00 49,500.00 Rp. 49,500.00
0.033 Oh Kepala Tukang Rp. 165,000.00 5,445.00 Rp. 5,445.00
0.033 Oh Mandor Rp. 170,000.00 5,610.00 Rp. 5,610.00
Rp. 275,305.00
AHSP-PBtn.A.4.1.1.24 1 M3. PEMBUATAN BEKISTING LANTAI
BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00 Rp. 80,000.00
0.400 Kg Paku campur Rp. 14,000.00 5,600.00 Rp. 5,600.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00 Rp. 1,200.00
0.015 M3 Kayu Balok kelas IV Rp. 2,000,000.00 30,000.00 Rp. 30,000.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00 Rp. 40,250.00
6.000 Btg Dolken 15cm Rp. 7,500.00 45,000.00 Rp. 45,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00 62,700.00 Rp. 62,700.00
0.330 Oh Tukang kayu Rp. 150,000.00 49,500.00 Rp. 49,500.00
0.033 Oh Kepala Tukang Rp. 165,000.00 5,445.00 Rp. 5,445.00
0.033 Oh Mandor Rp. 170,000.00 5,610.00 Rp. 5,610.00
Rp. 325,305.00
ABK-Ppw.BT.5 1 M3 BETON PONDASI PLAT 1 : 2 : 3
(180.859 Kg BESI )
Besi 16 1.000 M3 Beton K-250 Rp. 1,230,000.00 Rp. 1,230,000.00
281.166 Kg Pembesian Rp. 11,586.50 Rp. 3,257,729.86
0.200 M3 Begisting Rp. 181,910.00 Rp. 36,382.00
Rp. 4,524,111.86
ABK-Ppw.BT.S1 1 M3 BETON SLOOF 20/25
(176.46 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00 Rp. 1,230,000.00
besi 8 85.590 Kg Pembesian Rp. 11,586.50 Rp. 991,688.54
0.229 M3 Begisting Rp. 181,910.00 Rp. 41,657.39
Rp. 2,263,345.93

ABK-Ppw.BT.1a 1 M3 BETON TIE BEAM 20/25


( 192.270 Kg BESI )
besi 16 1.000 M3 Beton K-225 Rp. 1,230,000.00 Rp. 1,230,000.00
besi 10 85.590 Kg Pembesian Rp. 11,586.50 Rp. 991,688.54
0.229 M3 Begisting Rp. 181,910.00 Rp. 41,657.39
Rp. 2,263,345.93
ABK-Ppw.BT.9 1 M3 BETON KOLOM STRUKTUR 35/35
( 192.27 BESI )
besi 16 1.000 M3 Beton 1:3:5 Rp. 750,550.00 Rp. 750,550.00
besi 10 212.858 Kg Pembesian Rp. 11,586.50 Rp. 2,466,279.22
0.229 M3 Begisting Rp. 261,515.00 Rp. 59,886.94
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
Rp. 3,276,716.15
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
ABK-Ppw.BT.4 1 M3 BETON KOLOM PRAKTIS 15/15
( 195.15 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 750,550.00 Rp. 750,550.00
besi 8 195.150 Kg Pembesian Rp. 11,586.50 Rp. 2,261,105.48
0.530 M3 Begisting Rp. 261,515.00 Rp. 138,602.95
Rp. 3,150,258.43
ABK-Ppw.Bt.7 1 M3 BETON BALOK 25/30
( 86.57 kg besi )
besi 12 1.000 M3 Beton K-225 Rp. 1,201,000.00 Rp. 1,201,000.00
besi 10 122.600 Kg Pembesian Rp. 11,586.50 Rp. 1,420,504.90
0.260 M3 Begisting Rp. 181,910.00 Rp. 47,296.60
Rp. 2,668,801.50
ABK-Ppw.Bt.6 1 M3 BETON BALOK ANAK 10/25
( 176.46 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 750,550.00 Rp. 750,550.00
besi 8 176.460 Kg Pembesian Rp. 11,586.50 Rp. 2,044,553.79
0.273 M3 Begisting Rp. 181,910.00 Rp. 49,661.43
Rp. 2,844,765.22
ABK-Ppw.BT.1.ab 1 M3 BETON RING BALOK 15/15
( 176.46 BESI )
besi 12 1.000 M3 Beton K-225 Rp. 750,550.00 Rp. 750,550.00
besi 8 176.460 Kg Pembesian Rp. 11,586.50 Rp. 2,044,553.79
0.273 M3 Begisting Rp. 181,910.00 Rp. 49,661.43
Rp. 2,844,765.22
ABK-Ppw.BT.8 1 M3 BETON PELAT LANTAI Tebal = 15 cm
( 148.43 Kg BESI )
besi 10 1.000 M3 Beton K-225 Rp. 750,550.00 Rp. 750,550.00
148.430 Kg Pembesian Rp. 11,586.50 Rp. 1,719,784.20
0.045 M3 Begisting Rp. 325,305.00 Rp. 14,638.73
Rp. 2,484,972.92
ABK-Ppw.BT.8 a 1 M3 BETON PELAT LANTAI Tebal = 15 cm
( 98,28 Kg BESI )
1.000 M3 Beton K-225 Rp. 750,550.00 Rp. 750,550.00
besi 10 98.280 Kg Pembesian Rp. 11,586.50 Rp. 1,138,721.22
0.600 M3 Begisting Rp. 325,305.00 Rp. 195,183.00
Rp. 2,084,454.22
ABK-Ppw.BT.8 b 1 M3 BETON TANGGA
1.000 M3 Beton K-225 Rp. 750,550.00 Rp. 750,550.00
besi 10 235.990 Kg Pembesian Rp. 11,586.50 Rp. 2,734,298.14
0.030 M3 Begisting Rp. 275,305.00 Rp. 8,259.15
Rp. 3,493,107.29
ABK-Ppld (6.47.a) 1M2 PAS. LANTAI KERAMIK 40 x 40 CM
BAHAN
2.778 Bh Keramik 40 x 40 cm isi 6 lembar Rp. 30,000.00 83,334.00 Rp. 83,334.00
9.300 Kg Semen Portland Rp. 1,130.00 10,509.00 Rp. 10,509.00
0.018 M3 Pasir Pasang Rp. 200,000.00 3,600.00 Rp. 3,600.00
1.500 Kg Semen Warna Rp. 2,100.00 3,150.00 Rp. 3,150.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00 66,500.00 Rp. 66,500.00
0.350 Oh Tukang batu Rp. 150,000.00 52,500.00 Rp. 52,500.00
0.035 Oh Kepala Tukang Rp. 165,000.00 5,775.00 Rp. 5,775.00
0.0350 Oh Mandor Rp. 170,000.00 5,950.00 Rp. 5,950.00
Rp. 231,318.00
ABK-Ppld (6.47.a) 1M2 PAS. LANTAI KERAMIK 40 x 40 CM
BAHAN
6.250 Bh Keramik 40 x 40 cm isi 6 lembar Rp. 9,760.00 61,000.00 Rp. 61,000.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00 Rp. 11,300.00
0.045 M3 Pasir Pasang Rp. 200,000.00 9,000.00 Rp. 9,000.00
1.500 Kg Semen Warna Rp. 2,100.00 3,150.00 Rp. 3,150.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00 66,500.00 Rp. 66,500.00
0.350 Oh Tukang batu Rp. 150,000.00 52,500.00 Rp. 52,500.00
0.035 Oh Kepala Tukang Rp. 165,000.00 5,775.00 Rp. 5,775.00
0.0350 Oh Mandor Rp. 170,000.00 5,950.00 Rp. 5,950.00
Rp. 215,175.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
AHSP-PL.A.4.4.3.36 1 M2 PAS. LANTAI KERAMIK 20 X 20 CM
BAHAN
25.000 Bh Keramik 20 x 20 cm isi 25 lembar Rp. 2,200.00 55,000.00 Rp. 55,000.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00 Rp. 11,300.00
0.045 M3 Pasir Pasang Rp. 200,000.00 9,000.00 Rp. 9,000.00
1.500 Kg Semen Warna Rp. 2,100.00 3,150.00 Rp. 3,150.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00 66,500.00 Rp. 66,500.00
0.350 Oh Tukang batu Rp. 150,000.00 52,500.00 Rp. 52,500.00
0.035 Oh Kepala Tukang Rp. 165,000.00 5,775.00 Rp. 5,775.00
0.035 Oh Mandor Rp. 170,000.00 5,950.00 Rp. 5,950.00
Rp. 209,175.00
AHSP-PL.A.4.4.3.54 1 M2 PAS. DINDING KERAMIK 20 X 20 CM
BAHAN
25.000 Bh Keramik 20 x 20 cm Rp. 2,200.00 55,000.00 Rp. 55,000.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00 Rp. 11,300.00
0.045 Kg Pasir Pasang Rp. 200,000.00 9,000.00 Rp. 9,000.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00 66,500.00 Rp. 66,500.00
0.350 Oh Tukang batu Rp. 150,000.00 52,500.00 Rp. 52,500.00
0.035 Oh Kepala Tukang Rp. 165,000.00 5,775.00 Rp. 5,775.00
0.035 Oh Mandor Rp. 170,000.00 5,950.00 Rp. 5,950.00
Rp. 206,025.00
AHSP-PK.A.4.6.1.2 1 M3 PAS. KUSEN PINTU DAN JENDELA
BAHAN
0.040 M3 Kayu Kelas I Rp. 1,200,000.00 48,000.00 Rp. 48,000.00
0.400 Kg Paku campuran Rp. 14,000.00 5,600.00 Rp. 5,600.00
UPAH
4.000 Oh Pekerja Rp. 75,000.00 300,000.00 Rp. 300,000.00
12.000 Oh Tukang Rp. 100,000.00 1,200,000.00 Rp. 1,200,000.00
1.800 Oh Kepala Tukang Rp. 125,000.00 225,000.00 Rp. 225,000.00
0.200 Oh Mandor Rp. 120,000.00 24,000.00 Rp. 24,000.00
Rp. 1,802,600.00
ABK-PK.A.4.6.1.3 1 M3 RANGKA KUDA-KUDA KAYU
BAHAN
1.100 M3 Kayu Meranti 6/12 Rp. 2,500,000.00 2,750,000.00 Rp. 2,750,000.00
15.000 kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00 Rp. 375,000.00
5.600 kg Paku Kayu 10 cm Rp. 14,000.00 78,400.00 Rp. 78,400.00
UPAH
4.0000 Oh Pekerja Rp. 95,000.00 380,000.00 Rp. 380,000.00
12.0000 Oh Tukang Rp. 150,000.00 1,800,000.00 Rp. 1,800,000.00
1.2000 Oh Kepala Tukang Rp. 165,000.00 198,000.00 Rp. 198,000.00
0.2000 Oh Mandor Rp. 170,000.00 34,000.00 Rp. 34,000.00
Rp. 5,240,400.00
ABK-PK.A.4.6.1.3 1 M3 RANGKA KUDA-KUDA
BAHAN
1.100 M3 Kayu Meranti 6/12 Rp. 2,500,000.00 2,750,000.00 Rp. 2,750,000.00
15.000 kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00
5.600 Kg Paku Kayu 10 cm Rp. 14,000.00 78,400.00 Rp. 78,400.00
UPAH
4.0000 Oh Pekerja Rp. 95,000.00 380,000.00 Rp. 380,000.00
12.0000 Oh Tukang Rp. 150,000.00 1,800,000.00 Rp. 1,800,000.00
1.2000 Oh Kepala Tukang Rp. 165,000.00 198,000.00 Rp. 198,000.00
0.2000 Oh Mandor Rp. 170,000.00 34,000.00 Rp. 34,000.00
Rp. 5,240,400.00
AHSP-PK.A.4.6.1.15 1 M3 RANGKA GORDING
BAHAN
1.100 M3 Kayu gelam 6/12 Rp. 3,885,000.00 4,273,500.00 Rp. 4,273,500.00
15.000 Kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00 Rp. 375,000.00
3.000 Kg Paku 10 cm Rp. 14,000.00 42,000.00 Rp. 42,000.00
UPAH
6.700 Oh Pekerja Rp. 95,000.00 636,500.00 Rp. 636,500.00
20.100 Oh Tukang Rp. 150,000.00 3,015,000.00 Rp. 3,015,000.00
2.010 Oh Kepala Tukang Rp. 165,000.00 331,650.00 Rp. 331,650.00
0.335 Oh Mandor Rp. 170,000.00 56,950.00 Rp. 56,950.00
Rp. 8,730,600.00
AHSP-PK.A.4.6.1.15 1 M3 RANGKA RENG 3/4
BAHAN
1.100 M3 kayu meranti 6/12 Rp. 2,500,000.00 2,750,000.00 Rp. 2,750,000.00
15.000 Kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00 Rp. 375,000.00
3.000 Kg Paku 10 cm Rp. 14,000.00 42,000.00 Rp. 42,000.00
UPAH
6.700 Oh Pekerja Rp. 95,000.00 636,500.00 Rp. 636,500.00
20.100 Oh Tukang Rp. 150,000.00 3,015,000.00 Rp. 3,015,000.00
2.010 Oh Kepala Tukang Rp. 165,000.00 331,650.00 Rp. 331,650.00
0.335 Oh Mandor Rp. 170,000.00 56,950.00 Rp. 56,950.00
Rp. 7,207,100.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
AHSP-PK.A.4.6.1.15 1 M3 RANGKA GORDING
BAHAN
1.100 M3 Gording 4/3 Rp. 3,885,000.00 4,273,500.00 Rp. 4,273,500.00
15.000 kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00 Rp. 375,000.00
UPAH
14.000 Oh Pekerja Rp. 95,000.00 1,330,000.00 Rp. 1,330,000.00
12.000 Oh Tukang Rp. 150,000.00 1,800,000.00 Rp. 1,800,000.00
1.200 Oh Kepala Tukang Rp. 165,000.00 198,000.00 Rp. 198,000.00
0.200 Oh Mandor Rp. 165,000.00 33,000.00 Rp. 33,000.00
Rp. 8,009,500.00
AHSP-PK.A.4.6.1.5 1 M2 PASANGAN PINTU PANEL PAPAN
BAHAN
0.040 M3 Kayu Kelas II Rp. 2,000,000.00 80,000.00 Rp. 80,000.00
UPAH
1.000 Oh Pekerja Rp. 95,000.00 95,000.00 Rp. 95,000.00
3.000 Oh Tukang kayu Rp. 150,000.00 450,000.00 Rp. 450,000.00
0.300 Oh Kepala Tukang Rp. 165,000.00 49,500.00 Rp. 49,500.00
0.050 Oh Mandor Rp. 170,000.00 8,500.00 Rp. 8,500.00
Rp. 683,000.00
AHSP-PKaca.A.4.6.1.6 1 M2 PEK. PASANGAN DAUN JENDELA
BAHAN
0.0240 m3 Kayu kelas II, papan Rp. 2,500,000.00 60,000.0000 Rp. 60,000.00
UPAH
0.800 Oh Pekerja Rp. 95,000.00 76,000.00 Rp. 76,000.00
2.400 Oh Tukang kayu Rp. 150,000.00 360,000.00 Rp. 360,000.00
0.2400 Oh Kepala Tukang Rp. 165,000.00 39,600.00 Rp. 39,600.00
0.0400 Oh Mandor Rp. 170,000.00 6,800.00 Rp. 6,800.00
Rp. 542,400.00
AHSP-PKc.A.4.6.2.17 1 M2 JENDELA KACA BINGKAI 5 MM
BAHAN
1.100 M2 Kaca Bening 5 mm Rp. 102,000.00 112,200.00 Rp. 112,200.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00 1,425.00 Rp. 1,425.00
0.150 Oh Tukang Rp. 150,000.00 22,500.00 Rp. 22,500.00
0.015 Oh Kepala Tukang Rp. 165,000.00 2,475.00 Rp. 2,475.00
0.00080 Oh Mandor Rp. 170,000.00 136.00 Rp. 136.00
Rp. 138,736.00
AHSP-PPL.A.4.5.1.5 1 M2 PASANGAN PLAFON MULTIPLEKS
BAHAN
0.3750 lbr Multipleks Rp. 40,000.00 15,000.0000 Rp. 15,000.00
0.0300 kg Paku kayu Rp. 14,000.00 420.0000 Rp. 420.00
UPAH
0.100 Oh Pekerja Rp. 95,000.00 9,500.00 Rp. 9,500.00
0.100 Oh Tukang Rp. 150,000.00 15,000.00 Rp. 15,000.00
0.0100 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.0050 Oh Mandor Rp. 170,000.00 850.00 Rp. 850.00
Rp. 42,420.00
AHSP-PPL.A.4.5.1.5 1 M2 PAS. RANGKA PLAFOND
BAHAN
0.3750 lbr Kayu Rp. 45,670.00 17,126.2500 Rp. 17,126.25
0.0300 kg Paku kayu Rp. 14,000.00 420.0000 Rp. 420.00

UPAH
0.100 Oh Pekerja Rp. 95,000.00 9,500.00 Rp. 9,500.00
0.100 Oh Tukang Rp. 150,000.00 15,000.00 Rp. 15,000.00
0.0100 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.0050 Oh Mandor Rp. 170,000.00 850.00 Rp. 850.00
Rp. 44,546.25
AHSP-PA.A.4.5.2.38 1 M2 PAS. ATAP MULTIROOF
BAHAN
100.000 Lbr Multiroof Rp. 1,900.00 190,000.00 Rp. 190,000.00
- Rp. -
UPAH
0.120 Oh Pekerja Rp. 95,000.00 11,400.00 Rp. 11,400.00
0.060 Oh Tukang Rp. 150,000.00 9,000.00 Rp. 9,000.00
0.006 Oh Kepala Tukang Rp. 165,000.00 990.00 Rp. 990.00
0.006 Oh Mandor Rp. 170,000.00 1,020.00 Rp. 1,020.00
Rp. 212,410.00
AHSP-PA.A.4.5.2.39 1 M1 PAS. NOK ATAP MULTIROOF
BAHAN
100.000 Bh Multiroof Rp. 1,900.00 190,000.00 Rp. 190,000.00
- Rp. -
UPAH
0.120 Oh Pekerja Rp. 95,000.00 11,400.00 Rp. 11,400.00
0.060 Oh Tukang Rp. 150,000.00 9,000.00 Rp. 9,000.00
0.006 Oh Kepala Tukang Rp. 165,000.00 990.00 Rp. 990.00
0.006 Oh Mandor Rp. 170,000.00 1,020.00 Rp. 1,020.00
Rp. 212,410.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
ABK-PK.6.32 1 M1 PAS. ATAP MULTIROOF
BAHAN
100.000 Lbr Multiroof Rp. 1,900.00 190,000.00 Rp. 190,000.00

UPAH
0.120 Oh Pekerja Rp. 95,000.00 11,400.00 Rp. 11,400.00
0.060 Oh Tukang Rp. 150,000.00 9,000.00 Rp. 9,000.00
0.006 Oh Kepala Tukang Rp. 165,000.00 990.00 Rp. 990.00
0.006 Oh Mandor Rp. 170,000.00 1,020.00 Rp. 1,020.00
Rp. 212,410.00
AHSP-PA.A.4.5.2.39 1 M1 PAS. NOK ATAP MULTIROOF
BAHAN
1.1000 Bh Bubungan Multiroof Rp. 35,500.00 39,050.00 Rp. 39,050.00
0.0500 Kg Paku Rp. 25,000.00 1,250.00 Rp. 1,250.00
UPAH
0.2500 Oh Pekerja Rp. 95,000.00 23,750.00 Rp. 23,750.00
0.1500 Oh Tukang Rp. 150,000.00 22,500.00 Rp. 22,500.00
0.1500 Oh Kepala Tukang Rp. 165,000.00 24,750.00 Rp. 24,750.00
0.0130 Oh Mandor Rp. 170,000.00 2,210.00 Rp. 2,210.00
Rp. 113,510.00
AHSP-PA.A.4.6.1.21 1 M' PASANGAN LISPLANK PAPAN
BAHAN
0.0108 m' Kayu Kelas II (Papan Kamper) Rp. 1,600,000.00 17,280.0000 Rp. 17,280.00
0.1000 kg Paku Biasa 2"-5" Rp. 14,000.00 1,400.0000 Rp. 1,400.00
UPAH
0.1000 Oh Pekerja Rp. 95,000.00 9,500.00 Rp. 9,500.00
0.1000 Oh Tukang Rp. 150,000.00 15,000.00 Rp. 15,000.00
0.0200 Oh Kepala Tukang Rp. 165,000.00 3,300.00 Rp. 3,300.00
0.0500 Oh Mandor Rp. 170,000.00 8,500.00 Rp. 8,500.00
Rp. 54,980.00
AHSP-PPL.A.4.5.1.9 1 M' PAS. LIST PLAFOND PROFIL
BAHAN
0.350 M1 Kayu Profil Rp. 39,000.00 13,650.00 Rp. 13,650.00
0.010 Kg Paku 2" - 5" Rp. 14,000.00 140.00 Rp. 140.00
UPAH
0.050 Oh Pekerja Rp. 95,000.00 4,750.00 Rp. 4,750.00
0.050 Oh Tukang Rp. 150,000.00 7,500.00 Rp. 7,500.00
0.005 Oh Kepala Tukang Rp. 165,000.00 825.00 Rp. 825.00
0.003 Oh Mandor Rp. 170,000.00 510.00 Rp. 510.00
Rp. 27,375.00
AHSP-PPL.A.4.6.1.20 1 M2 PASANGAN RANGKA PLAFOND
BAHAN
0.016 M3 Kayu Kaso 5/7 Rp. 2,902,000.00 47,302.60 Rp. 47,302.60
0.250 Kg Paku 2" - 5" Rp. 14,000.00 3,500.00 Rp. 3,500.00
UPAH
0.200 Oh Pekerja Rp. 95,000.00 19,000.00 Rp. 19,000.00
0.300 Oh Tukang Kayu Rp. 150,000.00 45,000.00 Rp. 45,000.00
0.030 Oh Kepala Tukang Rp. 165,000.00 4,950.00 Rp. 4,950.00
0.010 Oh Mandor Rp. 170,000.00 1,700.00 Rp. 1,700.00
Rp. 121,452.60
AHSP-PCat.A.4.7.1.10 1 M2 CAT TEMBOK BARU
BAHAN
0.100 Kg Plamir Rp. 17,000.00 1,700.00 Rp. 1,700.00
0.100 Kg Cat Dasar Rp. 35,000.00 3,500.00 Rp. 3,500.00
0.260 Kg Cat Penutup 2 Kali Rp. 39,000.00 10,140.00 Rp. 10,140.00
UPAH
0.020 Oh Pekerja Rp. 95,000.00 1,900.00 Rp. 1,900.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.0063 Oh Kepala Tukang Rp. 165,000.00 1,039.50 Rp. 1,039.50
0.0030 Oh Mandor Rp. 170,000.00 510.00 Rp. 510.00
Rp. 18,789.50
AHSP-PCat.A.4.7.1.4 1 M2 CAT KAYU BARU
BAHAN
0.2000 Kg Cat menie Rp. 23,000.00 4,600.00 Rp. 4,600.00
0.150 Kg Plamir Rp. 55,000.00 8,250.00 Rp. 8,250.00
0.170 Kg Cat Dasar Rp. 24,000.00 4,080.00 Rp. 4,080.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00 Rp. 6,240.00
UPAH
0.070 Oh Pekerja Rp. 95,000.00 6,650.00 Rp. 6,650.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.0060 Oh Kepala Tukang Rp. 165,000.00 990.00 Rp. 990.00
0.0030 Oh Mandor Rp. 170,000.00 510.00 Rp. 510.00
Rp. 23,170.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
ABK-Ppw.C.8 1 M2 CAT PLAFOND TRIPLEKS
BAHAN
0.170 Kg Cat Dasar Rp. 24,000.00 4,080.00 Rp. 4,080.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00 Rp. 6,240.00
UPAH
0.070 Oh Pekerja Rp. 95,000.00 6,650.00 Rp. 6,650.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.0060 Oh Kepala Tukang Rp. 165,000.00 990.00 Rp. 990.00
0.0030 Oh Mandor Rp. 170,000.00 510.00 Rp. 510.00
Rp. 18,470.00
AHSP-PCat.A.4.7.1.10 1 M2 CAT PLAFOND MULTIPLEKS
BAHAN
0.100 Kg Plamir Rp. 55,000.00 5,500.00 Rp. 5,500.00
0.100 Kg Cat Dasar Rp. 24,000.00 2,400.00 Rp. 2,400.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00 Rp. 6,240.00
UPAH
0.020 Oh Pekerja Rp. 95,000.00 1,900.00 Rp. 1,900.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.0063 Oh Kepala Tukang Rp. 165,000.00 1,039.50 Rp. 1,039.50
0.0030 Oh Mandor Rp. 170,000.00 510.00 Rp. 510.00
Rp. 17,589.50
AHSP-PKunci.A.4.6.2.3 1 BH PAS. KUNCI TANAM 2 SLAAG
BAHAN
1.000 Bh Kunci Tanam Slag Rp. 30,000.00 30,000.00 Rp. 30,000.00
UPAH
0.010 Oh Pekerja Rp. 95,000.00 950.00 Rp. 950.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.050 Oh Kepala Tukang Rp. 165,000.00 8,250.00 Rp. 8,250.00
0.005 Oh Mandor Rp. 170,000.00 850.00 Rp. 850.00
Rp. 31,800.00
AHSP-PKunci.A.4.6.2.5 1 BH PAS. ENGSEL PINTU
BAHAN
0.015 Bh Engsel Pintu Rp. 95,000.00 1,425.00 Rp. 1,425.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00 1,425.00 Rp. 1,425.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.015 Oh Kepala Tukang Rp. 165,000.00 2,475.00 Rp. 2,475.00
0.00080 Oh Mandor Rp. 170,000.00 136.00 Rp. 136.00
Rp. 5,461.00
AHSP-PKunci.A.4.6.2.6 1 BH PAS. ENGSEL JENDELA
BAHAN
1.000 Bh Engsel Jendela Rp. 35,000.00 35,000.00 Rp. 35,000.00
UPAH
0.010 Oh Pekerja Rp. 95,000.00 950.00 Rp. 950.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.010 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.00050 Oh Mandor Rp. 170,000.00 85.00 Rp. 85.00
Rp. 36,035.00
AHSP-PKunci.A.4.6.2.11 1 BH PAS. GERENDEL PINTU
BAHAN
0.015 Bh Gerendel Pintu Rp. 95,000.00 1,425.00 Rp. 1,425.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00 1,425.00 Rp. 1,425.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.015 Oh Kepala Tukang Rp. 165,000.00 2,475.00 Rp. 2,475.00
0.00080 Oh Mandor Rp. 170,000.00 136.00 Rp. 136.00
Rp. 7,936.00
AHSP-PKunci.A.4.6.2.11 1 BH PAS. GERENDEL JENDELA
BAHAN
1.000 Bh Gerendel Jendela Rp. 15,000.00 15,000.00 Rp. 15,000.00
UPAH
0.020 Oh Pekerja Rp. 95,000.00 1,900.00 Rp. 1,900.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.020 Oh Kepala Tukang Rp. 165,000.00 3,300.00 Rp. 3,300.00
0.00100 Oh Mandor Rp. 170,000.00 170.00 Rp. 170.00
Rp. 17,070.00
AHSP-PKunci.A.4.6.2.9 1 BH PAS. HAK ANGIN JENDELA
BAHAN
1.000 Bh Hak Angin Rp. 7,500.00 7,500.00 Rp. 7,500.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00 1,425.00 Rp. 1,425.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.015 Oh Kepala Tukang Rp. 165,000.00 2,475.00 Rp. 2,475.00
0.00080 Oh Mandor Rp. 170,000.00 136.00 Rp. 136.00
Rp. 9,061.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
ABK-PKc.6.8 1 BH PAS. HANDLE/TARIKAN JENDELA
BAHAN
1.000 Bh Handle/Tarikan Jendela Rp. 15,000.00 15,000.00 Rp. 15,000.00
UPAH
0.010 Oh Pekerja Rp. 95,000.00 950.00 Rp. 950.00
- Oh Tukang Rp. 150,000.00 - Rp. -
0.010 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.00050 Oh Mandor Rp. 170,000.00 85.00 Rp. 85.00
Rp. 16,035.00
AHSP-PS.A.5.1.1.16 PEMASANGAN 1BH CLOSET DUDUK
BAHAN
1.0000 bh Closet duduk Rp. 2,149,000.00 2,149,000.00 Rp. 2,149,000.00
0.060 ls Perlengkapan Rp. 575,900.00 34,554.00 Rp. 34,554.00
UPAH
3.300 Oh Pekerja Rp. 95,000.00 313,500.00 Rp. 313,500.00
1.100 Oh Tukang Rp. 150,000.00 165,000.00 Rp. 165,000.00
0.0100 Oh Kepala Tukang Rp. 165,000.00 1,650.00 Rp. 1,650.00
0.1600 Oh Mandor Rp. 170,000.00 27,200.00 Rp. 27,200.00
Rp. 2,525,904.00
AHSP-PS.A.5.1.1.16 PEMASANGAN 1BH BATHTUB
BAHAN
1.0000 bh Buthtub Rp. 1,495,000.00 1,495,000.00 Rp. 1,495,000.00
6.000 kg semen pc Rp. 1,130.00 6,780.00 Rp. 6,780.00
0.0100 m3 pasir pasang 200000 2,000.00 2,000.00
7.0000 bh bata merah lokal 800 5,600.00 5,600.00
UPAH
1.000 Oh Pekerja Rp. 95,000.00 95,000.00 Rp. 95,000.00
1.500 Oh Tukang Rp. 150,000.00 225,000.00 Rp. 225,000.00
0.1500 Oh Kepala Tukang Rp. 165,000.00 24,750.00 Rp. 24,750.00
0.0500 Oh Mandor Rp. 170,000.00 8,500.00 Rp. 8,500.00
Rp. 1,862,630.00
AHSP-PS.A.5.1.1.26 PEMASANGAN PIPA PVC ø 2 Air Bersih
BAHAN
1.0000 m' Pipa PVC ø 3/4" Rp. 28,600.00 28,600.00 Rp. 28,600.00
0.3500 ls Perlengkapan Rp. 20,000.00 7,000.00 Rp. 7,000.00
UPAH
0.036 Oh Pekerja Rp. 95,000.00 3,420.00 Rp. 3,420.00
0.060 Oh Tukang Rp. 150,000.00 9,000.00 Rp. 9,000.00
0.0060 Oh Kepala Tukang Rp. 165,000.00 990.00 Rp. 990.00
0.0020 Oh Mandor Rp. 170,000.00 340.00 Rp. 340.00
Rp. 49,350.00
AHSP-PS.A.5.1.1.32 PEMASANGAN PIPA PVC ø 4" Air Kotor
BAHAN
1.0000 m' Pipa PVC ø 4" Rp. 144,100.00 144,100.00 Rp. 144,100.00
0.3500 ls Perlengkapan Rp. 124,000.00 43,400.00 Rp. 43,400.00
UPAH
0.081 Oh Pekerja Rp. 95,000.00 7,695.00 Rp. 7,695.00
0.135 Oh Tukang batu Rp. 150,000.00 20,250.00 Rp. 20,250.00
0.0135 Oh Kepala Tukang Rp. 165,000.00 2,227.50 Rp. 2,227.50
0.0040 Oh Mandor Rp. 170,000.00 680.00 Rp. 680.00
Rp. 218,352.50
ABK-Ppw.Sal 1 M1 PAS. SALURAN AIR HUJAN
BAHAN + UPAH
0.130 M3 Galian Tanah Biasa Rp. 75,500.00 9,815.000 Rp. 9,815.00
0.090 M3 Urugan Tanah Kembali Rp. 56,000.00 5,040.000 Rp. 5,040.00
0.030 M3 Urugan Pasir Rp. 140,000.00 4,200.000 Rp. 4,200.00
0.018 M3 Cor Beton 1: 2 : 3 Rp. 1,230,000.00 22,140.000 Rp. 22,140.00
0.060 M3 Pasangan Batu Bata 1 : 4 Rp. 110,795.00 6,647.700 Rp. 6,647.70
0.010 M2 Plesteran 1 : 4 Rp. 67,076.20 670.762 Rp. 670.76
Rp. 48,513.46

Konsultan Perencana Konsultan Perencana


PT. Lex Civil Archiplan PT. Lex Civil Archiplan

Ziki Ramadhan Denni Hardian


Direktur 1 Direktur 2
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI

RENCANA ANGGARAN BIAYA


Pekerjaan : Pembangunan Rumah Type Real Estate 180m2
Volume : 1 UNIT
Lokasi : Perumahan SUKA TIDAK TIDUR
Kabupaten/Kota : Bengkulu
T. Anggaran : 2019

Harga Jumlah
No. Uraian Pekerjaan Analisa Volume Satuan Harga
(Rp.) (Rp.)
1 2 3 4 5 6=4X5
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi dan Perataan AHSP-Pper.A.2.2.1.9 208 m2 8,500.00 1,768,000.00
2 Pas. Bowplank dan Pengukuran ABK-Pper.6.4 48.4 m' 78,320.00 3,790,688.00
SUB TOTAL I 5,558,688.00
II PEKERJAAN TANAH/PASIR -
1 Pek. Galian Tanah Biasa AHSP-PT.A.2.3.1.1 70.166 m3 75,500.00 5,297,533.00
2 Pek. Urugan Tanah Kembali AHSP-PT.A.2.3.1.9 28.620 m3 56,000.00 1,602,720.00
3 Pek. Urugan Pasir AHSP-PT.A.2.3.1.11 18.490 m3 222,200.00 4,108,478.00
4 Pek. Urugan Tanah Peninggi Lantai AHSP-PT.A.2.3.1.10 17.25 m3 96,200.00 1,659,450.00
SUB TOTAL II 12,668,181.00
III PEKERJAAN BETON
1 Pek. Beton Pondasi ABK-Ppw.BT.5 31.1 m3 4,706,021.86 146,357,279.81
2 Pek. Lantai Kerja tebal 10 cm ABK-PBtn (6.4) 1.8 m3 325,305.00 585,549.00
3 Pek. Pelat Lantai 15 cm ABK-Ppw.BT.8 11.46 m3 2,810,277.92 32,205,784.96
4 Pek. Beton Tangga ABK-Ppw.BT.8 b 1.63 m3 3,768,412.29 6,142,512.02
5 Pek. Balok Sloof 15/20 ABK-Ppw.BT.8 b 0.430 m3 2,263,345.93 973,238.75
6 Pek. Balok Tie Beam 35/35 ABK-Ppw.BT.1a 11.025 m3 2,263,345.93 24,953,388.82
7 Pek. Kolom Utama 35/35 ABK-Ppw.BT.9 14.990 m3 3,276,716.15 49,117,975.12
8 Pek. Kolom Praktis 15/15 ABK-Ppw.BT.4 1.400 m3 3,150,258.43 4,410,361.80
9 Pek. Balok Utama 30/30 ABK-Ppw.Bt.7 11.610 m3 2,668,801.50 30,984,785.42
10 Pek. Ring balok 20/25 ABK-Ppw.BT.1.ab 0.510 m3 2,844,765.22 1,450,830.26
11 Pek. Balok Anak 20/25 ABK-Ppw.Bt.6 0.210 m3 2,844,765.22 597,400.70
12 Pek. Tangga ABK-Ppw.BT.8b 1.63 m3 375,000.00 611,250.00
SUB TOTAL III 298,390,356.66
IV PEKERJAAN PASANGAN
1 Pek. Pasangan Batu Kosong AHSP-PPon.A.3.2.1.9 3.92 m3 508,785.00 1,994,437.20
2 Pek. Pasangan Batu Kali 1 :4 AHSP-PPon.A.3.2.1.2 6.59 m3 862,315.00 5,682,655.85
3 Pek. Pasangan dinding 1:4 AHSP-PD.A.4.4.1.9 327.639 m2 110,795.00 36,300,763.01
4 Pek. Plesteran 1:4 ABK-PD.A.4.4.2.4 655.278 m2 67,076.20 43,953,558.18
5 Pek. Beton Tumbuk Bawah Lantai ABK-PBtn (6.4) 11.46 m3 750,550.00 8,601,303.00
6 Pas. Lantai Keramik 40 x 40 cm ABK-Ppld (6.47.a) 151.42 m2 215,175.00 32,581,798.50
7 Pas. Lantai Keramik 20 x 20 cm AHSP-PL.A.4.4.3.36 14 m2 209,175.00 2,928,450.00
8 Pas. Dinding Keramik 20 x 20 cm T 150 cm AHSP-PL.A.4.4.3.54 2.1 m2 206,025.00 432,652.50
SUB TOTAL IV 132,475,618.24
V PEKERJAAN KAYU KACA
1 Pek. Kusen pintu/jendela AHSP-PK.A.4.6.1.2 0.93 m3 1,802,600.00 1,676,418.00
2 Pek. Pasangan Kaca T. 5 mm AHSP-PKc.A.4.6.2.17 6.232 m2 138,736.00 864,602.75
3 Pek. Daun Pintu AHSP-PK.A.4.6.1.5 14.2 m2 683,000.00 9,698,600.00
4 Pek. Daun Jendela AHSP-PKaca.A.4.6.1.6 8.76 m2 542,400.00 4,751,424.00
5 Pek. Box Ventilasi LS 8 unit 50,000.00 400,000.00
SUB TOTAL V 17,391,044.75
VI PEKERJAAN ATAP
1 Pek. Rangka Kuda kuda ABK-PK.A.4.6.1.3 2.093 m3 5,240,400.00 10,968,157.20
2 Pek. Gording 4/3 AHSP-PK.A.4.6.1.15 0.12 m3 8,009,500.00 961,140.00
3 Pek. Nok Atap Multiroof AHSP-PA.A.4.5.2.39 53 m 113,510.00 6,016,030.00
4 Pek. Atap Multiroof ABK-PK.6.32 200.918 Lbr 212,410.00 42,676,992.38
5 Pek. Lisplank AHSP-PA.A.4.6.1.21 62.4 m' 54,980.00 3,430,752.00
6 Residu Atap LS 1 unit 450,000.00 450,000.00
SUB TOTAL VI 1 64,503,071.58
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI
VII PEKERJAAN PLAPOND
1 Pek. Plapond +Rangka Plafond Multipleks AHSP-PPL.A.4.5.1.5 212.1 m2 86,966.25 18,445,541.63
SUB TOTAL VII 18,445,541.63
VIII PEKERJAAN KUNCI / PENGGANTUNG
1 Pas. Kunci Pintu 2 Slaag AHSP-PKunci.A.4.6.2.3 13 bh 31,800.00 413,400.00
2 Pas. Grendel Pintu AHSP-PKunci.A.4.6.2.11 10 bh 7,936.00 79,360.00
3 Pas. Grendel Jendela AHSP-PKunci.A.4.6.2.11 15 bh 17,070.00 256,050.00
4 Pas. Handle Jendela ABK-PKc.6.8 15 bh 16,035.00 673,470.00
5 Pas. Engsel Pintu AHSP-PKunci.A.4.6.2.5 42 bh 5,461.00 163,830.00
6 Pas. Engsel Jendela AHSP-PKunci.A.4.6.2.6 30 bh 36,035.00 576,560.00
7 Pek. Tarikan Pintu LS 16 bh 100,000.00 2,850,000.00
8 Pek. Relling Tangga Steinless Steel LS 28.5 m 150,000.00 4,275,000.00

SUB TOTAL VIII 9,287,670.00


IX PEKERJAAN SANITASI
1 Pas. PDAM LS 1 unit 500,000.00 500,000.00
2 Pek. Sumur LS 1 unit 3,500,000.00 3,500,000.00
3 Instalasi Pipa Air Bersih AHSP-PS.A.5.1.1.26 51.42 m' 49,350.00 2,537,577.00
4 Instalasi Pipa Air Kotor AHSP-PS.A.5.1.1.32 31.85 m' 218,352.50 6,954,527.13
5 Pas. Kran Air Stailess Steel LS 12 unit 12,000.00 144,000.00
6 Pas. Bak Fiberglass LS 1 unit 250,000.00 250,000.00
7 Pas. Bak Cuci Piring LS 1 unit 179,000.00 179,000.00
8 Pintu PVC WC LS 4 unit 200,000.00 800,000.00
9 Pas Closet Duduk AHSP-PS.A.5.1.1.16 3 unit 2,525,904.00 7,577,712.00
10 Pas. Bak Kontrol LS 1 unit 1,000,000.00 1,000,000.00
11 Pek. Septictank dan Persapan LS 1 unit 10,000,000.00 10,000,000.00
12 Pek. Saluran Air Hujan ABK-Ppw.Sal 51.26 m' 48,513.46 2,486,800.06
13 Bathtub LS 1 m' 1,690,000.00 1,690,000.00
SUB TOTAL IX 37,619,616.19
X PEKERJAAN INSTALASI LISTRIK
1 Pek. Pas. Lampu TL LED 200x8 LS 4 unit 35,000.00 140,000.00
2 Pek. Downlight 20Watt LS 15 unit 45,000.00 675,000.00
3 Pek. Pas. Stop Kontak LS 10 unit 20,000.00 200,000.00
4 Pek. Pas. Saklar Tunggal LS 2 unit 15,000.00 30,000.00
5 Pek. Pas. Saklar Ganda LS 15 unit 20,000.00 300,000.00
6 Pek. Titik Api LS 1 unit 120,000.00 120,000.00
7 Pek. Box MCB LS 1 unit 80,000.00 80,000.00
8 Kabel Listrik LS 118.24 m' 5,000.00 591,200.00
9 Pipa Listrik LS 91.4 m' 7,000.00 639,800.00
10 Upah Pekerja LS 3 org 600,000.00 1,800,000.00
SUB TOTAL X 4,436,000.00
XI PEKERJAAN PENGECATAN SELURUH
1 Cat Kayu Dan Kusen AHSP-PCat.A.4.7.1.4 15.8 m2 23,170.00 366,086.00
2 Cat plafond ABK-Ppw.c.8 212.1 m2 18,470.00 3,917,487.00
3 Cat Tembok AHSP-PCat.A.4.7.1.10 248.3 m2 18,789.50 4,665,432.85
4 Cat lisplank AHSP-PCat.A.4.7.1.4 62.4 m2 25,835.00 1,612,104.00
SUB TOTAL XI 10,561,109.85
XII PEKERJAAN LAIN-LAIN
1 Pembersihan akhir pekerjaan LS 1.00 unit 2,500,000.00 2,500,000.00
SUB TOTAL XII 2,500,000.00
FAKULTAS TEKNIK
PROGRAM STUDI TEKNIK SIPIL
UNIVERSITAS BENGKULU
MANAJEMEN KONTRUKSI

REKAPITULASI :
I . PEKERJAAN PERSIAPAN …………………………………………… Rp. 5,558,688.00
II . PEKERJAAN TANAH/PASIR ........………………………………… Rp. 12,668,181.00
III . PEKERJAAN BETON……………... …………………………………… Rp. 298,390,356.66
IV . PEKERJAAN PASANGAN ……………………………...…………… Rp. 132,475,618.24
V . PEKERJAAN KAYU, KACA… ………………………………………… Rp. 17,391,044.75
VI . PEKERJAAN ATAP ………………………………………………………… Rp. 64,503,071.58
VII . PEKERJAAN PLAFOND …………………………………………………… Rp. 18,445,541.63
VIII . PEKERJAAN KUNCI / PENGGANTUNG …………………………… Rp. 9,287,670.00
IX . PEKERJAAN SANITASI........................................................................................ Rp. 37,619,616.19
X . PEKERJAAN INSTALASI LISTRIK………………………………… Rp. 4,436,000.00
XI . PEKERJAAN PENGECATAN …………………………………………… Rp. 10,561,109.85
XII . PEKERJAAN LAIN-LAIN …………………………………………… Rp. 2,500,000.00
SUB JUMLAH…………………………. Rp. 613,836,897.89
KEUNTUNGAN 15% ……………… Rp. 92,075,534.68
PPN 10% …………………...……………… Rp. 9,207,553.47
JUMLAH TOTAL …………………...… Rp. 715,120,042.05
JUMLAH DIBULATKAN Rp. 715,120,000.00

Terbilang : Tujuh Ratus Lima Puluh Juta Seratus Lima Puluh Lima Rupiah

Bengkulu, APRIL 2019


Konsultan Perencana
PT. Lex Civil Archiplan

Direktur
Total 3
Produktivitas/Hari Jumlah Produktivitas Durasi
No. Jenis Pekerjaan Volume Pekerjaan
(Orang/Volume) Pekerja Per Hari (Hari)
14 Sanitasi
Pasang Keramik 1 :. 5 m2 5 25 m2 16.10 m2 1
Kloset 2 2
Septictank dan bak kontrol 4 4
Total 7

15 Plesteran 1 :. 9 m2 20 180 m2 1055.28 m2 6

16 Elektrikal dan mekanikal 6 2

17 Plumbing 6 2

18 Pengecatan dan Finishing


Pemasangan pintu dan jendela 2 2
Pengecetan Dinding 1 :. 30 m2 10 300 m2 248.30 m2 2
Pengecatan kusen+pintu+jendela 1 :. 15 m2 4 60 m2 15.80 m2 1
Pengecetan listplank 1 :. 10 m2 2 20 m2 62.40 m2 1
Pengecatan Plafond 1 :. 30 m2 6 180 m2 212.10 m2 1
Pemasangan kitchen set 2 1
Total 8

19 Landscaping 6 3
TIME SCHEDULE
PEMBANGUNAN RUMAH REAL ESTATE DUA LANTAI
LUAS RUMAH 180 m²
KOTA BENGKULU
DANA BOBOT DURASI BOBOT JADWAL WAKT
NO. JENIS PEKERJAAN ( Rp.) (%) ( Hari ) PER HARI 1 2 3 4 5 6 7
(%) ######
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
1 PEKERJAAN PERSIAPAN 5,558,688 0.906 3 0.302
2 PEKERJAAN CIVIL WORK DAN PONDASI 193,214,730 31.477 15 2.063
3 PEKERJAAN KOLOM LANTAI 1 26,764,168 4.360 12 0.356
4 PEKERJAAN BALOK DAN PELAT LANTAI 64,399,220 10.491 21 0.498
5 PEKERJAAN TANGGA 6,142,512 1.001 11 0.095
6 PEKERJAAN KOLOM LANTAI 2 26,764,168 4.360 11 0.396
7 PEKERJAAN DINDING, KUSEN LANTAI 1 31,489,739 5.130 9 0.560
8 PEKERJAAN DINDING, KUSEN LANTAI 2 31,489,739 5.130 6 0.815
9 PEKERJAAN PLUMBING 9,492,104 1.546 2 0.773
10 PEKERJAAN RING BALOK 1,450,830 0.236 16 0.014
11 PEKERJAAN ATAP 64,503,072 10.508 5 2.159 50.
46.260
12 PEKERJAAN INSTALASI LISTRIK 4,436,000 0.723 2 0.361 42.108
13 18,445,542 3.005 2 1.502 38.620
PEKERJAAN PLAFOND
32.922 35.417
14 PEKERJAAN PLESTERAN 43,953,558 7.160 6 1.221
15 PEKERJAAN SANITASI 31,488,615 5.130 7 0.772 23.600
16 PEKERJAAN LANTAI 41,183,102 6.709 3 2.162
17 PEKERJAAN PENGECATAN DAN FINISHING 10,561,110 1.721 8 0.210 9.158
18 PEKERJAAN LAIN-LAIN (LANDSCAPING) 2,500,000 0.407 3 0.136
0.000
Kemajuan Fisik Per Minggu 9.158 14.442 9.322 2.495 3.204 3.487 4.152
613,836,897 100 % 143
Komulatif (%) 9.158 23.600 32.922 35.417 38.620 42.108 46.260
ULE

JADWAL WAKTU PELAKSANAAN (MINGGU KE-)


8 9 10 11 12 13 14 15 16 17 18 19
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

98.284 100.000

79.445

63.500 63.601 63.702


57.291
50.178
46.260
42.108

3.918 7.113 6.208 0.101 0.101 15.743 18.839 1.249


50.178 57.291 63.500 63.601 63.702 79.445 98.284 100.000
DAFTAR ANALISA
Pekerjaan : Pembangunan Rumah Type Real Estate 250 m2
Lokasi : Perumahan CINTA SEJATI
Provinsi : Bengkulu
T. Anggaran : 2017

Jumlah Harga
Analisa Uraian Pekerjaan Harga Satuan ( Rp).-
Bahan Rp,-

AHSP-Pper.A.2.2.1.9 1 M2 PEMBERSIHAN LOKASI DAN PERATAAN


UPAH
0.1000 Oh Pekerja Rp. 95,000.00
0.0500 Oh Mandor Rp. 150,000.00

ABK-Pper.6.4 1 M' PENGUKURAN DAN PAS. BOUWPLANK


BAHAN
0.012 M3 kayu bekisting 5/7 cm Rp. 2,000,000.00 24,000.00
0.02 Kg Paku campur Rp. 16,000.00 320.00
0.012 M3 Kayu Papan Rp. 2,000,000.00 24,000.00
1.000 M Tali Rp. 3,000.00 3,000.00
UPAH
0.100 Oh Pekerja Rp. 100,000.00
0.100 Oh tukang Rp. 150,000.00
0.010 Oh Kepala Tukang Rp. 165,000.00
0.005 Oh Mandor Rp. 170,000.00

AHSP-PT.A.2.3.1.1 1 M3 GALIAN TANAH BIASA ( - 1 M ) 980.45845


UPAH
0.750 Oh Pekerja Rp. 95,000.00
0.025 Oh Mandor Rp. 170,000.00

AHSP-PT.A.2.3.1.1 1 M3 GALIAN TANAH BIASA ( - 2 M )


UPAH
0.900 Oh Pekerja Rp. 95,000.00
0.045 Oh Mandor Rp. 170,000.00

AHSP-PT.A.2.3.1.9 1 M3 URUGAN TANAH KEMBALI


UPAH
0.500 Oh Pekerja Rp. 95,000.00
0.050 Oh Mandor Rp. 170,000.00

AHSP-PT.A.2.3.1.10 1 M3 TIMBUNAN TANAH DIPADATKAN


BAHAN
1.000 M3 Tanah Urug Rp. 55,000.00 55,000.00
UPAH
0.500 Oh Pekerja Rp. 95,000.00
0.050 Oh Mandor Rp. 170,000.00

AHSP-PT.A.2.3.1.11 1 M3 URUGAN PASIR


BAHAN
1.200 M3 Pasir urug Rp. 160,000.00 192,000.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00
0.010 Oh Mandor Rp. 170,000.00

AHSP-PPon.A.3.2.1.9 1 M3 PAS. BATU KOSONG/Anstampang


BAHAN
1.200 M3 Batu Belah Rp. 245,000.00 294,000.00
0.432 M3 Pasir Urug Rp. 160,000.00 69,120.00
UPAH
0.780 Oh Pekerja Rp. 95,000.00
0.390 Oh Tukang Batu Rp. 150,000.00
0.039 Oh Kepala Tukang Rp. 165,000.00
0.039 Oh Mandor Rp. 170,000.00

AHSP-PPon.A.3.2.1.2 1 M3 PAS. PONDASI BATU KALI/GUNUNG: 1 PC : 4 PS


BAHAN
1.200 M3 Batu Kali/Gunung Rp. 245,000.00 294,000.00
163.000 Kg Semen Portland Type I Rp. 1,130.00 184,190.00
0.520 M3 Pasir Pasang Rp. 200,000.00 104,000.00
UPAH
1.500 Oh Pekerja Rp. 95,000.00
0.750 Oh Tukang Batu Rp. 150,000.00
0.075 Oh Kepala Tukang Rp. 165,000.00
0.075 Oh Mandor Rp. 170,000.00

AHSP-PD.A.4.4.1.9 1 M2 PASANGAN (1/2) BATA 1 PC : 4 PS


BAHAN
70.000 Bh Batu Bata Bolong Rp. 800.00 56,000.00
11.500 Kg Semen Portland Type I Rp. 1,130.00 12,995.00
0.043 M3 Pasir Pasang Rp. 200,000.00 8,600.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00
0.010 Oh Tukang Rp. 150,000.00
0.010 Oh Kepala Tukang Rp. 165,000.00
0.015 Oh Mandor Rp. 170,000.00

ABK-PD.A.4.4.2.4 1 M2 PLESTERAN 1 : 4 TEBAL 15 mm


BAHAN
6.240 Kg Semen Portland Type I Rp. 1,130.00 7,051.20
0.024 M3 Pasir Pasang Rp. 200,000.00 4,800.00
UPAH
0.300 Oh Pekerja Rp. 95,000.00
0.150 Oh Tukang Batu Rp. 150,000.00
0.015 Oh Kepala Tukang Rp. 165,000.00
0.015 Oh Mandor Rp. 170,000.00

ABK-PBtn (6.4) 1 M3 LANTAI KERJA BETON TUMBUK


BAHAN
230.000 Kg Semen Portland Type I Rp. 1,130.00 259,900.00
0.6379 M3 Pasir Pasang Rp. 200,000.00 127,580.00
0.7607 M3 Koral Beton Rp. 233,000.00 177,243.10
200.00 ltr air 200 40,000.00
UPAH
1.650 Oh Pekerja Rp. 95,000.00
0.275 Oh Tukang Batu Rp. 150,000.00
0.028 Oh Kepala Tukang Rp. 165,000.00
0.083 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.7 1 M3 MEMBUAT BETON K. 250


BAHAN
371.000 Kg Semen Portland Type I Rp. 1,130.00 419,230.00
0.698 M3 Pasir Beton Curup Rp. 200,000.00 139,600.00
1.047 M3 Koral Beton Rp. 233,000.00 243,951.00
200.00 ltr air 200 40,000.00
UPAH
1.650 Oh Pekerja Rp. 95,000.00
0.275 Oh Tukang batu Rp. 150,000.00
0.028 Oh Kepala Tukang Rp. 165,000.00
0.083 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.17 1 Kg. PEMBESIAN DENGAN BESI POLOS


BAHAN
1.050 Kg Besi Beton D12 Rp. 8,900.00 9,345.00
0.150 M3 Kawat Beton Rp. 23,000.00 3,450.00
UPAH
0.070 Oh Pekerja Rp. 95,000.00
0.070 Oh Tukang Besi Rp. 150,000.00
0.0070 Oh Kepala Tukang Rp. 165,000.00
0.0040 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.20 1 M3. PEMBUATAN BEKISTING PONDASI


BAHAN
0.040 M3 Kayu Kelas IV Rp. 2,000,000.00 80,000.00
0.300 Kg Paku campur Rp. 16,000.00 4,800.00
0.100 Ltr Minyak Begisting Rp. 6,000.00 600.00
UPAH
0.520 Oh Pekerja Rp. 95,000.00
0.260 Oh Tukang kayu Rp. 150,000.00
0.026 Oh Kepala Tukang Rp. 165,000.00
0.026 Oh Mandor Rp. 170,000.00
AHSP-PBtn.A.4.1.1.21 1 M3. PEMBUATAN BEKISTING SLOOF
BAHAN
0.045 M3 Kayu kelas IV Rp. 2,000,000.00 90,000.00
0.300 Kg Paku campur Rp. 16,000.00 4,800.00
0.100 Ltr Minyak Begisting Rp. 6,000.00 600.00
UPAH
0.520 Oh Pekerja Rp. 95,000.00
0.260 Oh Tukang kayu Rp. 150,000.00
0.026 Oh Kepala Tukang Rp. 165,000.00
0.026 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.21 1 M3. PEMBUATAN BEKISTING KOLOM


BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00
0.400 Kg Paku campur Rp. 16,000.00 6,400.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00
2.000 Btg Dolken 15cm Rp. 7,500.00 15,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00
0.330 Oh Tukang kayu Rp. 150,000.00
0.033 Oh Kepala Tukang Rp. 165,000.00
0.006 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.23 1 M3. PEMBUATAN BEKISTING BALOK


BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00
0.400 Kg Paku campur Rp. 16,000.00 6,400.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00
0.015 M3 Kayu Balok kelas IV Rp. 2,000,000.00 30,000.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00
2.000 Btg Dolken 15cm Rp. 7,500.00 15,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00
0.330 Oh Tukang kayu Rp. 150,000.00
0.033 Oh Kepala Tukang Rp. 165,000.00
0.033 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.26 1 M3. PEMBUATAN BEKISTING TANGGA


BAHAN
0.030 M3 Kayu kelas IV Rp. 2,000,000.00 60,000.00
0.400 Kg Paku campur Rp. 16,000.00 6,400.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00
0.015 M3 Kayu Balok kelas IV Rp. 2,000,000.00 30,000.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00
2.000 Btg Dolken 15cm Rp. 7,500.00 15,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00
0.330 Oh Tukang kayu Rp. 150,000.00
0.033 Oh Kepala Tukang Rp. 165,000.00
0.033 Oh Mandor Rp. 170,000.00

AHSP-PBtn.A.4.1.1.24 1 M3. PEMBUATAN BEKISTING LANTAI


BAHAN
0.040 M3 Kayu kelas IV Rp. 2,000,000.00 80,000.00
0.400 Kg Paku campur Rp. 16,000.00 6,400.00
0.200 Ltr Minyak Begisting Rp. 6,000.00 1,200.00
0.015 M3 Kayu Balok kelas IV Rp. 2,000,000.00 30,000.00
0.350 Lbr Plywood T = 9 mm Rp. 115,000.00 40,250.00
6.000 Btg Dolken 15cm Rp. 7,500.00 45,000.00
UPAH
0.660 Oh Pekerja Rp. 95,000.00
0.330 Oh Tukang kayu Rp. 150,000.00
0.033 Oh Kepala Tukang Rp. 165,000.00
0.033 Oh Mandor Rp. 170,000.00

ABK-Ppw.BT.5 1 M3 BETON PONDASI PLAT 1 : 2 : 3


( 374,41 Kg BESI )
Besi 16 1.000 M3 Beton K-250 Rp. 1,230,000.00
374.410 Kg Pembesian Rp. 31,780.00
0.200 M3 Begisting Rp. 182,510.00

ABK-Ppw.BT.S1 1 M3 BETON SLOOF


( 118,34 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 165.369 Kg Pembesian Rp. 31,780.00
0.700 M3 Begisting Rp. 192,510.00

ABK-Ppw.BT.1a 1 M3 BETON TIE BEAM


( 127,56 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 138.883 Kg Pembesian Rp. 31,780.00
0.440 M3 Begisting Rp. 192,510.00

ABK-Ppw.BT.9 1 M3 BETON KOLOM STRUKTUR


( 127,56 BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 120.326 Kg Pembesian Rp. 31,780.00
0.400 M3 Begisting Rp. 261,515.00

ABK-Ppw.BT.4 1 M3 BETON KOLOM PRAKTIS


( 135,71 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 196.237 Kg Pembesian Rp. 31,780.00
0.800 M3 Begisting Rp. 261,515.00
ABK-Ppw.Bt.7 1 M3 BETON BALOK
( 124.,1 kg besi )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 138.883 Kg Pembesian Rp. 18,000.00
0.440 M3 Begisting Rp. 192,510.00

ABK-Ppw.Bt.6 1 M3 BETON BALOK ANAK


( 154,28 Kg BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 192.000 Kg Pembesian Rp. 18,000.00
0.540 M3 Begisting Rp. 192,510.00

ABK-Ppw.BT.1.ab 1 M3 BETON RING BALK


( 118,34 BESI )
besi 12 1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 8 165.369 Kg Pembesian Rp. 18,000.00
0.700 M3 Begisting Rp. 192,510.00

ABK-Ppw.BT.8 1 M3 BETON PELAT LANTAI Tebal = 20 cm


( 148.43 Kg BESI )
besi 10 1.000 M3 Beton K-225 Rp. 1,230,000.00
148.430 Kg Pembesian Rp. 18,000.00
0.045 M3 Begisting Rp. 326,105.00

ABK-Ppw.BT.8 a 1 M3 BETON PELAT LANTAI Tebal = 15 cm


( 98,28 Kg BESI )
1.000 M3 Beton K-225 Rp. 1,230,000.00
98.280 Kg Pembesian Rp. 18,000.00
0.600 M3 Begisting Rp. 326,105.00

ABK-Ppw.BT.8 b 1 M3 BETON TANGGA


1.000 M3 Beton K-225 Rp. 1,230,000.00
besi 10 158.730 Kg Pembesian Rp. 18,000.00
0.030 M3 Begisting Rp. 276,105.00

ABK-Ppld (6.47.a) 1M2 PAS. LANTAI KERAMIK 60 x 60 CM


BAHAN
2.778 Bh Keramik 40 x 40 cm isi 6 lembar Rp. 30,000.00 83,334.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00
0.045 M3 Pasir Pasang Rp. 200,000.00 9,000.00
1.500 Kg Semen Warna Rp. 2,100.00 3,150.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00
0.350 Oh Tukang batu Rp. 150,000.00
0.035 Oh Kepala Tukang Rp. 165,000.00
0.0350 Oh Mandor Rp. 170,000.00

ABK-Ppld (6.47.a) 1M2 PAS. LANTAI KERAMIK 40 x 40 CM


BAHAN
6.250 Bh Keramik 40 x 40 cm isi 6 lembar Rp. 9,760.00 61,000.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00
0.045 M3 Pasir Pasang Rp. 200,000.00 9,000.00
1.500 Kg Semen Warna Rp. 2,100.00 3,150.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00
0.350 Oh Tukang batu Rp. 150,000.00
0.035 Oh Kepala Tukang Rp. 165,000.00
0.0350 Oh Mandor Rp. 170,000.00

AHSP-PL.A.4.4.3.36 1 M2 PAS. LANTAI KERAMIK 20 X 20 CM


BAHAN
25.000 Bh Keramik 20 x 20 cm isi 25 lembar Rp. 2,200.00 55,000.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00
0.045 M3 Pasir Pasang Rp. 200,000.00 9,000.00
1.500 Kg Semen Warna Rp. 2,100.00 3,150.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00
0.350 Oh Tukang batu Rp. 150,000.00
0.035 Oh Kepala Tukang Rp. 165,000.00
0.035 Oh Mandor Rp. 170,000.00

AHSP-PL.A.4.4.3.54 1 M2 PAS. DINDING KERAMIK 20 X 20 CM


BAHAN
25.000 Bh Keramik 20 x 20 cm Rp. 2,200.00 55,000.00
10.000 Kg Semen Portland Rp. 1,130.00 11,300.00
0.045 Kg Pasir Pasang Rp. 200,000.00 9,000.00
UPAH
0.700 Oh Pekerja Rp. 95,000.00
0.350 Oh Tukang batu Rp. 150,000.00
0.035 Oh Kepala Tukang Rp. 165,000.00
0.035 Oh Mandor Rp. 170,000.00

AHSP-PK.A.4.6.1.2 1 M3 PAS. KUSEN PINTU DAN JENDELA


BAHAN
1.100 M3 Kayu Kelas II Rp. 4,000,000.00 4,400,000.00
0.400 Kg Paku campuran Rp. 16,000.00 6,400.00
UPAH
6.000 Oh Pekerja Rp. 95,000.00
18.000 Oh Tukang Rp. 150,000.00
2.000 Oh Kepala Tukang Rp. 165,000.00
0.200 Oh Mandor Rp. 170,000.00

ABK-PK.A.4.6.1.3 1 M3 RANGKA KUDA-KUDA BAJA


BAHAN
1.000 M3 baja ringan Rp. 5,000,000.00 5,000,000.00
0.150 kg Paku Biasa 2"-5" Rp. 25,000.00 3,750.00

UPAH
0.1500 Oh Pekerja Rp. 140,000.00
0.2500 Oh Tukang Rp. 125,000.00
0.0250 Oh Kepala Tukang Rp. 150,000.00
0.0750 Oh Mandor Rp. 140,000.00
ABK-PK.A.4.6.1.3 1 M3 RANGKA KUDA-KUDA
BAHAN
1.100 M3 Kayu kelas II Rp. 4,000,000.00 4,400,000.00
15.000 kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00
5.600 Kg Paku Kayu 10 cm Rp. 16,000.00 89,600.00
UPAH
4.000 Oh Pekerja Rp. 95,000.00
12.000 Oh Tukang Rp. 150,000.00
1.200 Oh Kepala Tukang Rp. 165,000.00
0.200 Oh Mandor Rp. 170,000.00

AHSP-PK.A.4.6.1.15 1 M3 RANGKA GORDING


BAHAN
1.100 M3 Kayu kelas II Rp. 4,000,000.00 4,400,000.00
15.000 Kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00
3.000 Kg Paku 10 cm Rp. 16,000.00 48,000.00
UPAH
6.700 Oh Pekerja Rp. 95,000.00
20.100 Oh Tukang Rp. 150,000.00
2.010 Oh Kepala Tukang Rp. 165,000.00
0.335 Oh Mandor Rp. 170,000.00

AHSP-PK.A.4.6.1.15 1 M3 RANGKA RENG 3/4


BAHAN
1.100 M3 Kayu kelas II Rp. 4,000,000.00 4,400,000.00
15.000 Kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00
3.000 Kg Paku 10 cm Rp. 16,000.00 48,000.00
UPAH
6.700 Oh Pekerja Rp. 95,000.00
20.100 Oh Tukang Rp. 150,000.00
2.010 Oh Kepala Tukang Rp. 165,000.00
0.335 Oh Mandor Rp. 170,000.00

AHSP-PK.A.4.6.1.15 1 M3 RANGKA KASO 5/7


BAHAN
1.100 M3 Kayu Duren Rp. 2,952,000.00 3,247,200.00
15.000 Kg Besi Strip tebal 5mm Rp. 25,000.00 375,000.00
3.000 Kg Paku 10 cm Rp. 16,000.00 48,000.00
UPAH
6.700 Oh Pekerja Rp. 95,000.00
20.100 Oh Tukang Rp. 150,000.00
2.010 Oh Kepala Tukang Rp. 165,000.00
0.335 Oh Mandor Rp. 170,000.00

AHSP-PK.A.4.6.1.5 1 M2 PASANGAN PINTU PANEL PAPAN


BAHAN
0.040 M3 Kayu Kelas II Rp. 2,500,000.00 100,000.00
UPAH
1.000 Oh Pekerja Rp. 95,000.00
3.000 Oh Tukang kayu Rp. 150,000.00
0.300 Oh Kepala Tukang Rp. 165,000.00
0.050 Oh Mandor Rp. 170,000.00

AHSP-PKaca.A.4.6.1.6 1 M2 PEK. PASANGAN DAUN JENDELA


BAHAN
0.0240 m3 Kayu kelas II, papan Rp. 2,500,000.00 60,000.0000
UPAH
0.800 Oh Pekerja Rp. 95,000.00
2.400 Oh Tukang kayu Rp. 150,000.00
0.2400 Oh Kepala Tukang Rp. 165,000.00
0.0400 Oh Mandor Rp. 170,000.00

AHSP-PKc.A.4.6.2.17 1 M2 JENDELA KACA BINGKAI 5 MM


BAHAN
1.305 M2 Kaca Bening 5 mm Rp. 203,016.00 264,935.88
UPAH
0.015 Oh Pekerja Rp. 95,000.00
0.150 Oh Tukang Rp. 150,000.00
0.015 Oh Kepala Tukang Rp. 165,000.00
0.00080 Oh Mandor Rp. 170,000.00

AHSP-PPL.A.4.5.1.5 1 M2 PASANGAN PLAFON GIPSUM


BAHAN
0.3640 lbr GYPSUM Rp. 63,000.00 22,932.0000
0.1100 kg Paku skrup Rp. 40,000.00 4,400.0000
UPAH
0.100 Oh Pekerja Rp. 95,000.00
0.050 Oh Tukang Rp. 150,000.00
0.0050 Oh Kepala Tukang Rp. 165,000.00
0.0050 Oh Mandor Rp. 170,000.00

AHSP-PPL.A.4.5.1.5 1 M2 PAS. PLAFOND MULTIPLEKS


BAHAN
0.3470 lbr Plafond Multipleks 12 mm Rp. 181,500.00 62,980.5000
0.1100 kg Paku Piser Rp. 35,200.00 3,872.0000
0.8300 kg Compoun 5,000.00
UPAH
0.100 Oh Pekerja Rp. 95,000.00
0.050 Oh Tukang Rp. 150,000.00
0.0050 Oh Kepala Tukang Rp. 165,000.00
0.0050 Oh Mandor Rp. 170,000.00

AHSP-PA.A.4.5.2.38 1 M2 PAS. ATAP SENG GELOMBANG


BAHAN
0.700 Lbr Seng Gelombang Rp. 63,000.00 44,100.00
0.020 Kg Paku Seng 7cm Rp. 27,000.00 540.00
UPAH
0.120 Oh Pekerja Rp. 95,000.00
0.060 Oh Tukang Rp. 150,000.00
0.006 Oh Kepala Tukang Rp. 165,000.00
0.006 Oh Mandor Rp. 170,000.00
AHSP-PA.A.4.5.2.39 1 M1 PAS. NOK ATAP SENG
BAHAN
0.300 Bh Seng Gelombang Rp. 63,000.00 18,900.00
0.040 Kg Paku Seng Rp. 27,000.00 1,080.00
UPAH
0.150 Oh Pekerja Rp. 95,000.00
0.070 Oh Tukang Rp. 150,000.00
0.007 Oh Kepala Tukang Rp. 165,000.00
0.006 Oh Mandor Rp. 170,000.00

AHSP-PA.A.4.5.2.38 1 M2 PAS. ATAP MULTIROOF


BAHAN
2.6500 Lbr Multiroof 2 x 5 Rp. 96,500.00 255,725.00
0.0750 Kg Paku Seng/Payung Rp. 28,000.00 2,100.00
UPAH
0.2000 Oh Pekerja Rp. 95,000.00
0.1000 Oh Tukang Rp. 150,000.00
0.0100 Oh Kepala Tukang Rp. 165,000.00
0.0010 Oh Mandor Rp. 170,000.00

AHSP-PA.A.4.5.2.39 1 M1 PAS. NOK ATAP MULTIROOF


BAHAN
1.1000 Bh Bubungan Multiroof Rp. 35,500.00 39,050.00
0.0500 Kg Paku Rp. 25,000.00 1,250.00
UPAH
0.2500 Oh Pekerja Rp. 95,000.00
0.1500 Oh Tukang Rp. 150,000.00
0.1500 Oh Kepala Tukang Rp. 165,000.00
0.0130 Oh Mandor Rp. 170,000.00

AHSP-PA.A.4.6.1.21 1 M' PASANGAN LISPLANK PAPAN


BAHAN
0.0145 m' Kayu Kelas II (Papan Kamper) Rp. 5,000,000.00 72,500.0000
0.0600 kg Paku Biasa 2"-5" Rp. 25,000.00 1,500.0000
UPAH
0.1500 Oh Pekerja Rp. 95,000.00
0.2500 Oh Tukang Rp. 150,000.00
0.0250 Oh Kepala Tukang Rp. 165,000.00
0.0750 Oh Mandor Rp. 170,000.00

AHSP-PPL.A.4.5.1.9 1 M' PAS. LIST PLAFOND PROFIL


BAHAN
1.050 M1 Kayu Profil Rp. 39,000.00 40,950.00
0.010 Kg Paku 2" - 5" Rp. 14,000.00 140.00
UPAH
0.050 Oh Pekerja Rp. 95,000.00
0.050 Oh Tukang Rp. 150,000.00
0.005 Oh Kepala Tukang Rp. 165,000.00
0.003 Oh Mandor Rp. 170,000.00

AHSP-PPL.A.4.6.1.20 1 M2 PASANGAN RANGKA PLAFOND


BAHAN
0.016 M3 Kayu Kaso 5/7 Rp. 2,952,000.00 48,117.60
0.250 Kg Paku 2" - 5" Rp. 14,000.00 3,500.00
UPAH
0.200 Oh Pekerja Rp. 95,000.00
0.300 Oh Tukang Kayu Rp. 150,000.00
0.030 Oh Kepala Tukang Rp. 165,000.00
0.010 Oh Mandor Rp. 170,000.00

AHSP-PCat.A.4.7.1.10 1 M2 CAT TEMBOK BARU


BAHAN
0.100 Kg Plamir Rp. 55,000.00 5,500.00
0.100 Kg Cat Dasar Rp. 24,000.00 2,400.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00
UPAH
0.020 Oh Pekerja Rp. 95,000.00
0.063 Oh Tukang Rp. 150,000.00
0.0063 Oh Kepala Tukang Rp. 165,000.00
0.0030 Oh Mandor Rp. 170,000.00

AHSP-PCat.A.4.7.1.4 1 M2 CAT KAYU BARU


BAHAN
0.2000 Kg Cat menie Rp. 23,000.00 4,600.00
0.150 Kg Plamir Rp. 55,000.00 8,250.00
0.170 Kg Cat Dasar Rp. 24,000.00 4,080.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00
UPAH
0.070 Oh Pekerja Rp. 95,000.00
0.090 Oh Tukang Rp. 150,000.00
0.0060 Oh Kepala Tukang Rp. 165,000.00
0.0030 Oh Mandor Rp. 170,000.00

ABK-Ppw.C.8 1 M2 CAT PLAFOND TRIPLEKS


BAHAN
0.170 Kg Cat Dasar Rp. 24,000.00 4,080.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00
UPAH
0.070 Oh Pekerja Rp. 95,000.00
0.090 Oh Tukang Rp. 150,000.00
0.0060 Oh Kepala Tukang Rp. 165,000.00
0.0030 Oh Mandor Rp. 170,000.00

AHSP-PCat.A.4.7.1.10 1 M2 CAT PLAFOND GYPSUM


BAHAN
0.100 Kg Plamir Rp. 55,000.00 5,500.00
0.100 Kg Cat Dasar Rp. 24,000.00 2,400.00
0.260 Kg Cat Penutup 2 Kali Rp. 24,000.00 6,240.00
UPAH
0.020 Oh Pekerja Rp. 95,000.00
0.063 Oh Tukang Rp. 150,000.00
0.0063 Oh Kepala Tukang Rp. 165,000.00
0.0030 Oh Mandor Rp. 170,000.00

AHSP-PKunci.A.4.6.2.3 1 BH PAS. KUNCI TANAM 2 SLAAG


BAHAN
1.000 Bh Kunci Tanam Slag Rp. 66,000.00 66,000.00
UPAH
0.010 Oh Pekerja Rp. 95,000.00
0.500 Oh Tukang Rp. 150,000.00
0.050 Oh Kepala Tukang Rp. 165,000.00
0.005 Oh Mandor Rp. 170,000.00

AHSP-PKunci.A.4.6.2.5 1 BH PAS. ENGSEL PINTU


BAHAN
0.015 Bh Engsel Pintu Rp. 95,000.00 1,425.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00
0.150 Oh Tukang Rp. 150,000.00
0.015 Oh Kepala Tukang Rp. 165,000.00
0.00080 Oh Mandor Rp. 170,000.00

AHSP-PKunci.A.4.6.2.6 1 BH PAS. ENGSEL JENDELA


BAHAN
1.000 Bh Engsel Jendela Rp. 35,000.00 35,000.00
UPAH
0.010 Oh Pekerja Rp. 95,000.00
0.100 Oh Tukang Rp. 150,000.00
0.010 Oh Kepala Tukang Rp. 165,000.00
0.00050 Oh Mandor Rp. 170,000.00

AHSP-PKunci.A.4.6.2.11 1 BH PAS. GERENDEL PINTU


BAHAN
0.015 Bh Gerendel Pintu Rp. 95,000.00 1,425.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00
0.150 Oh Tukang Rp. 150,000.00
0.015 Oh Kepala Tukang Rp. 165,000.00
0.00080 Oh Mandor Rp. 170,000.00

AHSP-PKunci.A.4.6.2.11 1 BH PAS. GERENDEL JENDELA


BAHAN
1.000 Bh Gerendel Jendela Rp. 15,000.00 15,000.00
UPAH
0.020 Oh Pekerja Rp. 95,000.00
0.200 Oh Tukang Rp. 150,000.00
0.020 Oh Kepala Tukang Rp. 165,000.00
0.00100 Oh Mandor Rp. 170,000.00

AHSP-PKunci.A.4.6.2.9 1 BH PAS. HAK ANGIN JENDELA


BAHAN
1.000 Bh Hak Angin Rp. 7,500.00 7,500.00
UPAH
0.015 Oh Pekerja Rp. 95,000.00
0.150 Oh Tukang Rp. 150,000.00
0.015 Oh Kepala Tukang Rp. 165,000.00
0.00080 Oh Mandor Rp. 170,000.00

ABK-PKc.6.8 1 BH PAS. HANDLE/TARIKAN JENDELA


BAHAN
1.000 Bh Handle/Tarikan Jendela Rp. 15,000.00 15,000.00
UPAH
0.010 Oh Pekerja Rp. 95,000.00
0.100 Oh Tukang Rp. 150,000.00
0.010 Oh Kepala Tukang Rp. 165,000.00
0.00050 Oh Mandor Rp. 170,000.00

AHSP-PS.A.5.1.1.16 PEMASANGAN 1BH CLOSET DUDUK


BAHAN
1.0000 bh Closet duduk Rp. 2,849,000.00 2,849,000.00
0.060 ls Perlengkapan Rp. 2,849,000.00 170,940.00
UPAH
3.300 Oh Pekerja Rp. 95,000.00
1.100 Oh Tukang Rp. 150,000.00
0.0100 Oh Kepala Tukang Rp. 165,000.00
0.1600 Oh Mandor Rp. 170,000.00

AHSP-PS.A.5.1.1.16 PEMASANGAN 1BH CLOSET JONGKOK


BAHAN
1.0000 bh Closet jongkok Rp. 365,000.00 365,000.00
6.000 kg semen pc Rp. 1,130.00 6,780.00
0.0100 m3 pasir pasang 200000 2,000.00
7.0000 bh bata merah lokal 800 5,600.00
UPAH
1.000 Oh Pekerja Rp. 95,000.00
1.500 Oh Tukang Rp. 150,000.00
0.1500 Oh Kepala Tukang Rp. 165,000.00
0.0500 Oh Mandor Rp. 170,000.00

AHSP-PS.A.5.1.1.26 PEMASANGAN PIPA PVC ø 2 Air Bersih


BAHAN
1.0000 m' Pipa PVC ø 3/4" Rp. 28,600.00 28,600.00
0.3500 ls Perlengkapan Rp. 28,600.00 10,010.00
UPAH
0.036 Oh Pekerja Rp. 95,000.00
0.060 Oh Tukang Rp. 150,000.00
0.0060 Oh Kepala Tukang Rp. 165,000.00
0.0020 Oh Mandor Rp. 170,000.00

AHSP-PS.A.5.1.1.32 PEMASANGAN PIPA PVC ø 4" Air Kotor


BAHAN
1.0000 m' Pipa PVC ø 4" Rp. 281,500.00 281,500.00
0.3500 ls Perlengkapan Rp. 281,500.00 98,525.00
UPAH
0.081 Oh Pekerja Rp. 95,000.00
0.135 Oh Tukang batu Rp. 150,000.00
0.0135 Oh Kepala Tukang Rp. 165,000.00
0.0040 Oh Mandor Rp. 170,000.00

ABK-Ppw.Sal 1 M1 PAS. SALURAN AIR HUJAN


BAHAN + UPAH
0.130 M3 Galian Tanah Biasa Rp. 93,150.00 12,109.500
0.090 M3 Urugan Tanah Kembali Rp. 56,000.00 5,040.000
0.030 M3 Urugan Pasir Rp. 140,000.00 4,200.000
0.018 M3 Cor Beton 1: 2 : 3 Rp. 1,230,000.00 22,140.000
0.060 M3 Pasangan Batu Bata 1 : 4 Rp. 111,795.00 6,707.700
0.010 M2 Plesteran 1 : 4 Rp. 67,876.20 678.762
Jumlah Harga
Jumlah Harga ( Rp ),-
Upah Rp,-

9,500.00 Rp. 9,500.00


7,500.00 Rp. 7,500.00
Rp. 17,000.00

Rp. 24,000.00
Rp. 320.00
Rp. 24,000.00
Rp. 3,000.00

10,000.00 Rp. 10,000.00


15,000.00 15,000.00
1,650.00 Rp. 1,650.00
850.00 Rp. 850.00
Rp. 78,820.00

71,250.00 Rp. 71,250.00


4,250.00 Rp. 4,250.00
Rp. 75,500.00

85,500.00 Rp. 85,500.00


7,650.00 Rp. 7,650.00
Rp. 93,150.00

47,500.00 Rp. 47,500.00


8,500.00 Rp. 8,500.00
Rp. 56,000.00

Rp. 55,000.00

47,500.00 Rp. 47,500.00


8,500.00 Rp. 8,500.00
Rp. 111,000.00
Rp. 192,000.00

28,500.00 Rp. 28,500.00


1,700.00 Rp. 1,700.00
Rp. 222,200.00

Rp. 294,000.00
Rp. 69,120.00

74,100.00 Rp. 74,100.00


58,500.00 Rp. 58,500.00
6,435.00 Rp. 6,435.00
Rp. 6,630.00
Rp. 508,785.00

Rp. 294,000.00
Rp. 184,190.00
Rp. 104,000.00

142,500.00 Rp. 142,500.00


112,500.00 Rp. 112,500.00
12,375.00 Rp. 12,375.00
12,750.00 Rp. 12,750.00
Rp. 862,315.00

Rp. 56,000.00
Rp. 12,995.00
Rp. 8,600.00

28,500.00 Rp. 28,500.00


1,500.00 Rp. 1,500.00
1,650.00 Rp. 1,650.00
2,550.00 Rp. 2,550.00
Rp. 111,795.00

Rp. 7,051.20
Rp. 4,800.00

28,500.00 Rp. 28,500.00


22,500.00 Rp. 22,500.00
2,475.00 Rp. 2,475.00
2,550.00 Rp. 2,550.00
Rp. 67,876.20
Rp. 259,900.00
Rp. 127,580.00
Rp. 177,243.10
40,000.00

156,750.00 Rp. 156,750.00


41,250.00 Rp. 41,250.00
4,620.00 Rp. 4,620.00
14,110.00 Rp. 14,110.00
Rp. 821,453.10

Rp. 419,230.00
Rp. 139,600.00
Rp. 243,951.00
40,000.00

156,750.00 Rp. 156,750.00


41,250.00 Rp. 41,250.00
4,620.00 Rp. 4,620.00
14,110.00 Rp. 14,110.00
Rp. 1,059,511.00

Rp. 9,345.00
Rp. 3,450.00

6,650.00 Rp. 6,650.00


10,500.00 Rp. 10,500.00
1,155.00 Rp. 1,155.00
680.00 Rp. 680.00
Rp. 31,780.00

Rp. 80,000.00
Rp. 4,800.00
Rp. 600.00

49,400.00 Rp. 49,400.00


39,000.00 Rp. 39,000.00
4,290.00 Rp. 4,290.00
4,420.00 Rp. 4,420.00
Rp. 182,510.00
Rp. 90,000.00
Rp. 4,800.00
Rp. 600.00

49,400.00 Rp. 49,400.00


39,000.00 Rp. 39,000.00
4,290.00 Rp. 4,290.00
4,420.00 Rp. 4,420.00
Rp. 192,510.00

Rp. 80,000.00
Rp. 6,400.00
Rp. 1,200.00
Rp. 40,250.00
Rp. 15,000.00

62,700.00 Rp. 62,700.00


49,500.00 Rp. 49,500.00
5,445.00 Rp. 5,445.00
1,020.00 Rp. 1,020.00
Rp. 261,515.00

Rp. 80,000.00
Rp. 6,400.00
Rp. 1,200.00
Rp. 30,000.00
Rp. 40,250.00
Rp. 15,000.00

62,700.00 Rp. 62,700.00


49,500.00 Rp. 49,500.00
5,445.00 Rp. 5,445.00
5,610.00 Rp. 5,610.00
Rp. 296,105.00

Rp. 60,000.00
Rp. 6,400.00
Rp. 1,200.00
Rp. 30,000.00
Rp. 40,250.00
Rp. 15,000.00

62,700.00 Rp. 62,700.00


49,500.00 Rp. 49,500.00
5,445.00 Rp. 5,445.00
5,610.00 Rp. 5,610.00
Rp. 276,105.00

Rp. 80,000.00
Rp. 6,400.00
Rp. 1,200.00
Rp. 30,000.00
Rp. 40,250.00
Rp. 45,000.00

62,700.00 Rp. 62,700.00


49,500.00 Rp. 49,500.00
5,445.00 Rp. 5,445.00
5,610.00 Rp. 5,610.00
Rp. 326,105.00

Rp. 1,230,000.00
Rp. 11,898,749.80
Rp. 36,502.00
Rp. 13,165,251.80

Rp. 1,230,000.00
Rp. 5,255,426.82
Rp. 134,757.00
Rp. 6,620,183.82

Rp. 1,230,000.00
Rp. 4,413,701.74
Rp. 84,704.40
Rp. 5,728,406.14

Rp. 1,230,000.00
Rp. 3,823,960.28
Rp. 104,606.00
Rp. 5,158,566.28

Rp. 1,230,000.00
Rp. 6,236,411.86
Rp. 209,212.00
Rp. 7,675,623.86
Rp. 1,230,000.00
Rp. 2,499,894.00
Rp. 84,704.40
Rp. 3,814,598.40

Rp. 1,230,000.00
Rp. 3,456,000.00
Rp. 103,955.40
Rp. 4,789,955.40

Rp. 1,230,000.00
Rp. 2,976,642.00
Rp. 134,757.00
Rp. 4,341,399.00

Rp. 1,230,000.00
Rp. 2,671,740.00
Rp. 14,674.73
Rp. 3,916,414.73

Rp. 1,230,000.00
Rp. 1,769,040.00
Rp. 195,663.00
Rp. 3,194,703.00

Rp. 1,230,000.00
Rp. 2,857,140.00
Rp. 8,283.15
Rp. 4,095,423.15

Rp. 83,334.00
Rp. 11,300.00
Rp. 9,000.00
Rp. 3,150.00

66,500.00 Rp. 66,500.00


52,500.00 Rp. 52,500.00
5,775.00 Rp. 5,775.00
5,950.00 Rp. 5,950.00
Rp. 237,509.00

Rp. 61,000.00
Rp. 11,300.00
Rp. 9,000.00
Rp. 3,150.00
66,500.00 Rp. 66,500.00
52,500.00 Rp. 52,500.00
5,775.00 Rp. 5,775.00
5,950.00 Rp. 5,950.00
Rp. 215,175.00

Rp. 55,000.00
Rp. 11,300.00
Rp. 9,000.00
Rp. 3,150.00

66,500.00 Rp. 66,500.00


52,500.00 Rp. 52,500.00
5,775.00 Rp. 5,775.00
5,950.00 Rp. 5,950.00
Rp. 209,175.00

Rp. 55,000.00
Rp. 11,300.00
Rp. 9,000.00

66,500.00 Rp. 66,500.00


52,500.00 Rp. 52,500.00
5,775.00 Rp. 5,775.00
5,950.00 Rp. 5,950.00
Rp. 206,025.00

Rp. 4,400,000.00
Rp. 6,400.00

570,000.00 Rp. 570,000.00


2,700,000.00 Rp. 2,700,000.00
330,000.00 Rp. 330,000.00
34,000.00 Rp. 34,000.00
Rp. 8,040,400.00

Rp. 5,000,000.00

21,000.00 Rp. 21,000.00


31,250.00 Rp. 31,250.00
3,750.00 Rp. 3,750.00
10,500.00 Rp. 10,500.00
Rp. 5,066,500.00
Rp. 4,400,000.00

Rp. 89,600.00

380,000.00 Rp. 380,000.00


1,800,000.00 Rp. 1,800,000.00
198,000.00 Rp. 198,000.00
34,000.00 Rp. 34,000.00
Rp. 6,901,600.00

Rp. 4,400,000.00
Rp. 375,000.00
Rp. 48,000.00

636,500.00 Rp. 636,500.00


3,015,000.00 Rp. 3,015,000.00
331,650.00 Rp. 331,650.00
56,950.00 Rp. 56,950.00
Rp. 8,863,100.00

Rp. 4,400,000.00
Rp. 375,000.00
Rp. 48,000.00

636,500.00 Rp. 636,500.00


3,015,000.00 Rp. 3,015,000.00
331,650.00 Rp. 331,650.00
56,950.00 Rp. 56,950.00
Rp. 8,863,100.00

Rp. 3,247,200.00
Rp. 375,000.00
Rp. 48,000.00

636,500.00 Rp. 636,500.00


3,015,000.00 Rp. 3,015,000.00
331,650.00 Rp. 331,650.00
56,950.00 Rp. 56,950.00
Rp. 7,710,300.00

Rp. 100,000.00
95,000.00 Rp. 95,000.00
450,000.00 Rp. 450,000.00
49,500.00 Rp. 49,500.00
8,500.00 Rp. 8,500.00
Rp. 703,000.00

Rp. 60,000.00

76,000.00 Rp. 76,000.00


360,000.00 Rp. 360,000.00
39,600.00 Rp. 39,600.00
6,800.00 Rp. 6,800.00
Rp. 542,400.00

Rp. 264,935.88

1,425.00 Rp. 1,425.00


22,500.00 Rp. 22,500.00
2,475.00 Rp. 2,475.00
136.00 Rp. 136.00
Rp. 291,471.88

Rp. 22,932.00
Rp. 4,400.00

9,500.00 Rp. 9,500.00


7,500.00 Rp. 7,500.00
825.00 Rp. 825.00
850.00 Rp. 850.00
Rp. 46,007.00

Rp. 62,980.50
Rp. 3,872.00

9,500.00 Rp. 9,500.00


7,500.00 Rp. 7,500.00
825.00 Rp. 825.00
850.00 Rp. 850.00
Rp. 85,527.50

Rp. 44,100.00
Rp. 540.00

11,400.00 Rp. 11,400.00


9,000.00 Rp. 9,000.00
990.00 Rp. 990.00
1,020.00 Rp. 1,020.00
Rp. 67,050.00

Rp. 18,900.00
Rp. 1,080.00

14,250.00 Rp. 14,250.00


10,500.00 Rp. 10,500.00
1,155.00 Rp. 1,155.00
1,020.00 Rp. 1,020.00
Rp. 46,905.00

Rp. 255,725.00
Rp. 2,100.00

19,000.00 Rp. 19,000.00


15,000.00 Rp. 15,000.00
1,650.00 Rp. 1,650.00
170.00 Rp. 170.00
Rp. 293,645.00

Rp. 39,050.00
Rp. 1,250.00

23,750.00 Rp. 23,750.00


22,500.00 Rp. 22,500.00
24,750.00 Rp. 24,750.00
2,210.00 Rp. 2,210.00
Rp. 113,510.00

Rp. 72,500.00
Rp. 1,500.00

14,250.00 Rp. 14,250.00


37,500.00 Rp. 37,500.00
4,125.00 Rp. 4,125.00
12,750.00 Rp. 12,750.00
Rp. 142,625.00

Rp. 40,950.00
Rp. 140.00

4,750.00 Rp. 4,750.00


7,500.00 Rp. 7,500.00
825.00 Rp. 825.00
510.00 Rp. 510.00
Rp. 54,675.00
Rp. 48,117.60
Rp. 3,500.00

19,000.00 Rp. 19,000.00


45,000.00 Rp. 45,000.00
4,950.00 Rp. 4,950.00
1,700.00 Rp. 1,700.00
Rp. 122,267.60

Rp. 5,500.00
Rp. 2,400.00
Rp. 6,240.00

1,900.00 Rp. 1,900.00


9,450.00 Rp. 9,450.00
1,039.50 Rp. 1,039.50
510.00 Rp. 510.00
Rp. 27,039.50

Rp. 4,600.00
Rp. 8,250.00
Rp. 4,080.00
Rp. 6,240.00

6,650.00 Rp. 6,650.00


13,500.00 Rp. 13,500.00
990.00 Rp. 990.00
510.00 Rp. 510.00
Rp. 44,820.00

Rp. 4,080.00
Rp. 6,240.00

6,650.00 Rp. 6,650.00


13,500.00 Rp. 13,500.00
990.00 Rp. 990.00
510.00 Rp. 510.00
Rp. 31,970.00

Rp. 5,500.00
Rp. 2,400.00
Rp. 6,240.00

1,900.00 Rp. 1,900.00


9,450.00 Rp. 9,450.00
1,039.50 Rp. 1,039.50
510.00 Rp. 510.00
Rp. 27,039.50

Rp. 66,000.00

950.00 Rp. 950.00


75,000.00 Rp. 75,000.00
8,250.00 Rp. 8,250.00
850.00 Rp. 850.00
Rp. 151,050.00

Rp. 1,425.00

1,425.00 Rp. 1,425.00


22,500.00 Rp. 22,500.00
2,475.00 Rp. 2,475.00
136.00 Rp. 136.00
Rp. 27,961.00

Rp. 35,000.00

950.00 Rp. 950.00


15,000.00 Rp. 15,000.00
1,650.00 Rp. 1,650.00
85.00 Rp. 85.00
Rp. 52,685.00

Rp. 1,425.00

1,425.00 Rp. 1,425.00


22,500.00 Rp. 22,500.00
2,475.00 Rp. 2,475.00
136.00 Rp. 136.00
Rp. 27,961.00

Rp. 15,000.00

1,900.00 Rp. 1,900.00


30,000.00 Rp. 30,000.00
3,300.00 Rp. 3,300.00
170.00 Rp. 170.00
Rp. 50,370.00

Rp. 7,500.00

1,425.00 Rp. 1,425.00


22,500.00 Rp. 22,500.00
2,475.00 Rp. 2,475.00
136.00 Rp. 136.00
Rp. 34,036.00

Rp. 15,000.00

950.00 Rp. 950.00


15,000.00 Rp. 15,000.00
1,650.00 Rp. 1,650.00
85.00 Rp. 85.00
Rp. 32,685.00

Rp. 2,849,000.00
Rp. 170,940.00

313,500.00 Rp. 313,500.00


165,000.00 Rp. 165,000.00
1,650.00 Rp. 1,650.00
27,200.00 Rp. 27,200.00
Rp. 3,527,290.00

Rp. 365,000.00
Rp. 6,780.00
2,000.00
5,600.00

95,000.00 Rp. 95,000.00


225,000.00 Rp. 225,000.00
24,750.00 Rp. 24,750.00
8,500.00 Rp. 8,500.00
Rp. 732,630.00

Rp. 28,600.00
Rp. 10,010.00

3,420.00 Rp. 3,420.00


9,000.00 Rp. 9,000.00
990.00 Rp. 990.00
340.00 Rp. 340.00
Rp. 52,360.00
Rp. 281,500.00
Rp. 98,525.00

7,695.00 Rp. 7,695.00


20,250.00 Rp. 20,250.00
2,227.50 Rp. 2,227.50
680.00 Rp. 680.00
Rp. 410,877.50

Rp. 12,109.50
Rp. 5,040.00
Rp. 4,200.00
Rp. 22,140.00
Rp. 6,707.70
Rp. 678.76
Rp. 50,875.96

Bengkulu, April 2019


Konsultan Perencana

CV. MENCARI CINTA SEJATI

You might also like