Professional Documents
Culture Documents
2011 11 18 Lci Chicago MTG Barshan
2011 11 18 Lci Chicago MTG Barshan
Presented By:
Afshan Barshan
General Outline
• Overview
• Production Management Process
• The Skender Journey
• Panel Discussion
• Plus / Delta & Questions
Lean Project Delivery System
Operation PROJECT
USE
Alteration
Maintenance DEFINITION
Purposes
Decomm.
Design
Commiss- Criteria
ioning
Work Structuring Design
Production Control Concepts
Installation
LEAN
PRODUCTION Process LEAN
Procurement
Design DESIGN
Logistics Detailed Product
Scopes/ Design
Engineering
LEAN
SUPPLY Ballard, 2000 adapted by Afshan Barshan
The Last Planner
Work Structuring
Production Control
Lean Construction – Definition
Master Schedule
Phase Lookahead
Master Schedule
Schedule Schedule
Master Schedule
Phase Lookahead
Master Schedule
Schedule Schedule
Phase Schedule
Phase Lookahead
Master Schedule
Schedule Schedule
The Process
• Working meetings with Last
Planners
• Typical Phases:
• Preconstruction
• Site
• Substructure
• Shell/Core/Rough/Skin
• Finishes
Phase Lookahead
Master Schedule
Schedule Schedule
The Process
• Challenging in an open forum:
• Durations
• Sequencing
• Coordination
• Confirmation of milestones
• Constraints
Lookahead Schedule
Phase Lookahead
Master Schedule
Goal of Lookahead Schedule Schedule
• Maximize reliability
• Shape work flow and rate
• Match work flow and capacity
• Get it right the first time (quality)
Phase Lookahead
Master Schedule
How to Achieve Schedule Schedule
• Drive Accountability
• Focus on task hands-off – quality/ready/clean/safe
• Screen for constraints
• Develop detailed plans for work to be done
• Maintain backlog of ready work
• Team approach to managing short term coordination
• Use strategic buffers
• Can be done vs. Will be done
Lookahead Schedule
Work Flow
Filter
Issue Log
Milestone
Quality
Milestone
Daily Constraints
Tasks
Accountability builds Reliability
Phase Lookahead
Master Schedule
How to Measure Schedule Schedule
Performance Measurements
• Monitor – DAILY
• Update – WEEKLY
PPC
• Monitors all planned activities
• “On schedule” does not mean 100% PPC
• Track parties responsible for variances, some of
which could lead to delays – and quickly correct
them .before they become larger issues
• Hold parties accountable to their commitment
PPC
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
5/30/11
10 12
6/6/11
6
6/13/11
9
6/20/11
6/27/11
23 23
7/4/11
7/11/11
34 35
7/18/11
38
7/25/11
8/1/11
31 31
8/8/11
40
8/15/11
50
8/22/11
Measuring Success
55
8/29/11
70
9/5/11
Weeks
65
9/12/11
Activities
9/19/11
74 77
9/26/11
65
10/3/11
10/10/11
74 73
10/17/11
PPC
94
10/24/11
10/31/11
141
11/7/11
11/14/11
11/21/11
11/28/11
12/5/11
Weighted Average
12/12/11
12/19/11
0
20
40
60
80
100
120
140
160
Activities
Phase Lookahead
Master Schedule
Measuring Success Schedule Schedule
• Commitment
• Culture – Improvement = Change
• Partnership
• Educating Clients
• Attitude - If better is possible good is not
enough!!
The Skender Journey
Panel Discussion
Project Background
• Scope
• ICU Refurbishment
• Inpatient Unit Refresh
• Project Team
• NMH
• Gensler
• SCC
• Trades
• Contract - GMP
Project Challenges
• Aggressive Schedule
• Logistics
• Communication
• Evolving Scopes
Project Phasing
Lookahead Schedule Preconstruction
Lookahead Schedule Construction
PPC
82%
84%
86%
88%
90%
92%
94%
96%
98%
100%
19
10/10/11
77
10/17/11
100%
97%
10/24/11
135
95%
10/31/11
141
89%
11/7/11 168
92%
Project PPC
11/14/11
11/21/11
11/28/11
12/5/11
12/12/11
12/19/11
Weeks
12/26/11
1/2/12
1/9/12
Activities
1/16/12
1/23/12
PPC
1/30/12
2/6/12
2/13/12
2/20/12
Weighted Average
2/27/12
0
20
40
60
80
100
120
140
160
180
Activities
Plus/Delta & Questions