Project : Submitted By:

Location : Brgy. Kamanga, Maasim, Sarangani Province


Owner :

Date:
Unit Material Equipment Total Unit
Item Description Qty Unit Unit Labor Cost Labor Cost Material Cost Total Amount
Cost Cost Cost

1 EARTH WORKS
1.1 Site Preparation - - - -
1.2 Excavation - - - -
Sub-total -
2 BEDDING WORKS
2.1 Compaction - - - -
2.2 Polyethylene Sheet 22773 sq.m 14 318,822.00 40.00 910,920.00 1,229,742.00
2.3 20 mm Dia. Gravel 569 cu.m 350.00 199,263.75 1500.00 853,987.50 1,053,251.25
Sub-total 2,282,993.25

TOTAL DIRECT COST 2,282,993.25

CONTINGENCIES

MARK-UP/SUPERVISION

WITH-HOLDING TAX

TOTAL PROJECT COST 2,282,993.25