LANCO INFRATECH LIMITED

(EPC Division)
2 x 507.5 MW UDUPI THERMAL POWER PROJECT
KOLACHURU POST, UDUPI
KARNATAKA.

MATERIAL INSPECTION REPORT

P.O.No. LITL/UPCL/ELEC/BUSDUCT/NGEP/PO/009 Ref No SPBD/01


P.O.Date 13/03/2008 Date 29/11/2008
Name of the
Supplier Control & Switchgears Ltd
D.C No. 12
L. R No 5741, 5801, 5815 (Dt.11 , 12 & 15-11-2008)
Date of receipt 20, 23 & 25/11/2008
Qty. Qty. Qty.
Sl. No Description of the material Receive Accepte Rejecte
d d d
1 6.6 KV, 2500 A BUS DUCTS
Element with Enclosure and busbar (153.469 Mtrs) 26 cases 26 cases NIL

2 11 KV, 2500 A BUS DUCTS


Element with Enclosure and busbar (62.49 Mtrs) 12 cases 12 cases NIL

3 Rain hoods (6.6 KV -29 no's & 11 KV -15 no's) 03 cases 03 cases NIL

Note: Physically Inspected and found Ok as per P.O

Inspected By LITL (EPC) Stores

Engineer-In-Charge (LITL-EPC)
SPBD/01
29/11/2008

Remarks

Packed in
wooden crate
and kept near
SWYRD - SW

LITL (EPC) Stores


LANCO INFRATECH LIMITED
(EPC Division)
2 x 507.5 MW UDUPI THERMAL POWER PROJECT
KOLACHURU POST, UDUPI
KARNATAKA.

MATERIAL INSPECTION REPORT

P.O.No.:- LITL/NPCL/ELEC/NGRs/PO/014 Sl. No. :- Urja/NGR/01


P.O.Date:- 13/03/2008
Name of the Supplier/Manufacturer:- Urja Electricals pvt Ltd. MRN No:& Date:
D.C No.: 12
L. R No: PNA 1304 (Dt.13-11-2008)
Date of Material receipt: 18/11/2008
Date :- 19/11/2008