Tenants Status Date: 03-2-2020

OITC-1
1.0 G/F Tinytoots
I. Submission of Documents -

II. Schedule for fit-out - Ongoing construction

III. a. Ongoing fit-out status - 75% (Ongoing wall partitioning and ceiling works)
b. Architectural - 75% (Painting works ongoing)
c. Mechanical - 70% (AC Indoor unit installed, ongoing wiring and piping)
d. Electrical - 85% (Wiring installation and devices ongoing)
e. Plumbing -80% (Piping works ongoing)

IV. Others:
a. For follow-up schedule for initial leak testing of plumbing
b. For follow-up schedule for initial leak testing of aircon drain
c. Schedule of megger testing 1-week before operation

2.0 G/F SAMGYUPSALAMAT

I. Submission of Documents -

II. Schedule for fit-out - Ongoing construction (almost done)

III. a. Ongoing fit-out status - 90% (Almost complete wall partioning)


b. Architectural - 90% ( retouching)
c. Mechanical - 90%
d. Electrical - 90% (on going interior wiring of lightings)
e. Plumbing - 90% (kitchen plumbing not yet done)

IV. Others:
a. For follow-up schedule for initial leak testing of plumbing
b. For follow-up schedule for initial leak testing of aircon drain
c. Schedule of megger testing 1-week before operation

3.0 G/F MAMO (operational)


I. Submission of Documents -

II. Schedule for fit-out - Done

III. a. Ongoing fit-out status - 100%


b. Architectural - 100%
c. Mechanical - 100%
d. Electrical - 100%
e. Plumbing - 100%

IV. Others: for follow up


Inspection checklist:
1.0 2-pcs un-used hanger/rod for removal @ ceiling
2.0 Exposed wires should install box under the freezer
3.0 Schedule of load @ panelboard
4.0 Smoke detector @ kitchen area for replacement to heat detector
5.0 Provision of exit door @ kitchen area
6.0 Exposed wire should install moulding/flexible hose under the counter

For recommendations:
a sprinkler heads for adjustment/ actual is in upright position
b Provision of gas leak detector @ kitchen
c. Provision of drain pan of ACCU condenser @ front side
d. Re-schedule of megger testing 1-ckt#13 failed

OITC-2
1.0 5/F-unit 2-504A DONG FEI

I. Submission of Documents - Done

II. Schedule for fit-out - Ongoing construction

III. a. Ongoing fit-out status - 65% (Ongoing tiling works)


b. Architectural - 55% (ongoing painting works)
c. Mechanical - 60% (AC indoor unit installed, piping ongoing)
d. Electrical - 60% (Lightings installed, wirings, panelboards and devices ongoing)
e. Plumbing - NA

IV. Others:
a. For follow-up schedule for initial leak testing of aircon drain
b. Schedule of megger testing 1-week before operation

2.0 5/F-unit 2-5001A UNILAB CLOSE

I. Submission of Documents - Done

II. Schedule for fit-out - Ongoing construction

III. a. Ongoing fit-out status - 40% (wall installation ongoing)


b. Architectural - 10% (not yet started painting works)
c. Mechanical - 30% (piping ongoing)
d. Electrical - 60% (wiring installation ongoing)
e. Plumbing - NA

IV. Others:
a. For follow-up schedule for initial leak testing of aircon drain
b. Schedule of megger testing 1-week before operation

3.0 10/F-unit 1002-PRIVATE DERMA CLOSE

I. Submission of Documents - Done

II. Schedule for fit-out - Not yet started

III. a. Ongoing fit-out status -60% (wall installation ongoing)


b. Architectural - 0% (painting not yet started)
c. Mechanical - 10% existing AC copper tube and pipes
d. Electrical - 50% existing lights, and panelboard
e. Plumbing - NA

IV. Others:
a. For follow-up schedule for initial leak testing of aircon drain
b. Schedule of megger testing 1-week before operation

4.0 11/F-unit 1001-1002-ECOLAB CLOSE

I. Submission of Documents - NOT YET

II. Schedule for fit-out - Not yet started

III. a. Ongoing fit-out status - 0%


b. Architectural - 0%
c. Mechanical - 0%
d. Electrical - 50% existing lights, and panelboard
e. Plumbing - NA

IV. Others: