Update 7‐23‐15
What are we working on this month?
• Footers at east curtain wall are complete.
• Interior wall masonry is ongoing. Exterior walls for
music rooms is ongoing.
• Second floor masonry is ongoing at elevator and
elsewhere.
• Duct installation is ongoing.
• Light gauge studs are being installed for soffits.
• Gym trusses and ductwork painting is near completion.
• Ceiling unit heaters in Gyms are being installed.
• Door frames are being installed on 1st level.
• Joists and decking installation is underway for the 3rd
level.
All exterior foundations are set!
6th grade hallway !
Vocal music room is taking shape !
Second floor masonry work is almost
complete!
Gym ceiling and walls have been
painted !
What’s next at the middle school ?
• 3rd floor decking and masonry walls
• Brick veneer near main office
• Continue to frame out the class rooms
• Installation of mechanical systems such as
plumbing and HVAC will continue as additional
spaces are completed
• Finishes will begin in August in main office
area and kitchen.
High School Construction Update
What are we working on this month at
the High School?
• Painting in corridors is almost complete in the 700 / 800 wing.
• Corridor lighting in being installed.
• Window replacement is ongoing. Currently finishing up in
courtyard.
• Ceramic tile in group restrooms is near completion on 1st level.
• Rubber tile installation is in progress in corridors and
classrooms on 2nd level.
• Gypsum board ceilings and soffits being installed in corridors.
• All sprinkler heads have been replaced throughout the
building.
• Painting at stairwells is complete, floor tile is going in.
Veneer of the auditorium wall is being
repaired !
The former entrance to the A/P and
Guidance offices !
The new entrance to the A/P and
Guidance offices !
Aux I gym has been painted !
Caulking of metal panels is
progressing!
The 800 hallway is starting to take
shape !
The 600 wing workroom is coming
together as well !
What’s next at the High School ?
• Finish all flooring in 700 wing
• Complete ceiling tile installation and
replacement in 700 / 800 wing
• Install technology package and network gear
for all classrooms in 600, 700 and 800 wings
• Complete roofing work in occupied areas
• Finish window replacement in occupied areas
• Punch list walk through on 8/5/15.