PLANNED ACTUAL

Excavation (m3) 17.90% 21.29% 9982


Concrete (m3) 5.14% 4.70% 68611
Formwork (m2) 3.48% 2.52% 336374
Steel (kg) 3.85% 3.02% 5901759
Block (m2) 1.16% 1.81% 199954
Backfilling (m3) 9.28% 11.02% 53982
PLANNED ACTUAL

Excavation (m3) 1787.00 2125.00


Concrete (m3) 3527.00 3226.00
Formwork (m2) 11717.00 8460.00
Steel (kg) 226996.00 178469.00
Block (m2) 2329.00 3626.00
Backfilling (m3) 5007.00 5950.00
Construction Pro

25.00%

21.29%

20.00%

17.90%

15.00%

10.00%

5.14%
5.00% 4.70%

3.48%

2.52

0.00%
Excavation (m3) Concrete (m3) Formwork (m2)
3.48%

2.52

0.00%
Excavation (m3) Concrete (m3) Formwork (m2)
Construction Progress Todate

PLANNED ACTUAL

9.28%

3.85%
3.48%
3.02%
2.52%
1.81%
1.16%

Formwork (m2) Steel (kg) Block (m2) Backfi


3.85%
3.48%
3.02%
2.52%
1.81%
1.16%

Formwork (m2) Steel (kg) Block (m2) Backfi


L

11.02%

9.28%

Backfilling (m3)
Backfilling (m3)