PESTECH ENERGY SDN BHD

FAT Tentative Program for 1 typical Relay Panel & Communication Converter Panel

Client: Press Metal Bintulu Sdn Bhd

No. Time List of Activity

Opening Meeting
1 9.00 - 9.30 am - Tentative Program Briefing
- Documentation Checking
Physical Inspection/Visual Inspection (Relay Panel & Communication Converter Panel)
- Cubicle dimension
- Paintwork
A01 - AC and DC Circuit Check (Relay Panel & Communication Converter Panel)
2 9.30 – 10.00 am - AC/DC MCB
- Panel Lighting
- Socket Outlet
- Thermostat
- Wiring
A02 - Alarm and Annunciator Test & S02 - Supervisory Alarm and Indication Test
3 10.00 – 10.30 am - Red Window
- Amber Window
- Checking on the functionality of supervisory alarm signal and indication.
C01 - Current Differential Relay Test (7SD522)
- Physical Inspection
- Measurement Accuracy Check
- Current Differential Operating Current Test
- Current Differential Operating Time
4 10.30 – 12.30 pm
- Distance Polar Characteristic Test
- Distance Zone Timing Test
- Distance VT Supervision Test
- Distance SOTF Timing Test
- DEF Test

5 12.30 – 1.30 pm Lunch Break


C01 - Current Differential Relay Test (RED670)
- Physical Inspection
- Measurement Accuracy Check
- Current Differential Operating Current Test
- Current Differential Operating Time
6 1.30 – 3.00 pm
- Distance Polar Characteristic Test
- Distance Zone Timing Test
- Distance VT Supervision Test
- Distance SOTF Timing Test
- DEF Test
O01- Overcurrent & Earth Fault Relay Test (7SJ62)
- Physical Inspection
- Measurement Accuracy Check
7 3.00 – 3.30 pm
- Pick up and Drop off Test
- Operating Time Test
- Tripping characteristic
C02 - Breaker Fail Relay Test (7VK61)
- Physical Inspection
8 3.30 – 4.00 pm - Measurement Accuracy Check
- P/u and drop off test
- Operating Time Test
Closing Meeting
9 4.00 - 5.00 pm - FAT Report Checking & Signing
- Documentation Compiling/Copy Works