QUANTITY SHEET -1
Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity
(m)
(m) (m)
1 Earth work in Excavation
Footing 8 1.2 1.2 0.6 6.912 cu m
L.W.= 9+.8=9.8m 3 9.80 0.80 1.10 25.87 cu m
SW1=3.5-.8=2.7m 4 2.70 0.80 1.10 9.50 cu m
SW2=3.8-.8=3m 3 3.00 0.80 1.10 7.92 cu m
H.W.=2.1-.8=1.3m 1 1.30 0.80 1.10 1.14 cu m
51.35 cu m
2 Flat brick soling
a) Footing base 8 1.20 1.20 11.52 Sq.m
b) Floor Base 1 9.00 5.00 45.00 Sq.m
56.52 Sq.m
3 P. C. C. For Foundation:
L.W.= 9+.8=9.8m 3 9.80 0.80 0.20 4.70 cu m
SW1=3.5-.8=2.7m 4 2.70 0.80 0.20 1.73 cu m
SW2=3.8-.8=3m 3 3.00 0.80 0.20 1.44 cu m
H.W.=2.1-.8=1.3m 1 1.30 0.80 0.20 0.21 cu m
8.08 cu m
1st Class Brick Masonry in CM
(1:6) up to Plinth:
**Foundation:
1st Step:
L.W.= 9+.6=9.6m 3 9.60 0.60 0.30 5.18 cu m
SW1=3.5-.6=2.9m 4 2.90 0.60 0.30 2.09 cu m
SW2=3.8-.6=3.2m 3 3.20 0.60 0.30 1.73 cu m
H.W.=2.1-.6=1.5m 1 1.50 0.60 0.30 0.27 cu m
2nd Step:
L.W.= 9+.5=9.5m 3 9.50 0.50 0.30 4.28 cu m
SW1=3.5-.5=3m 4 3.00 0.50 0.30 1.80 cu m
SW2=3.8-.5=3.3m 3 3.30 0.50 0.30 1.49 cu m
H.W.=2.1-.5=1.6m 1 1.60 0.50 0.30 0.24 cu m
3rd Step:
L.W.= 9+.4=9.4m 3 9.40 0.40 0.30 3.38 cu m
SW1=3.5-.4=3.1m 4 3.10 0.40 0.30 1.49 cu m
SW2=3.8-.4=3.4m 3 3.40 0.40 0.30 1.22 cu m
H.W.=2.1-.4=1.7m 1 1.70 0.40 0.30 0.20 cu m
**Plinth:
L.W.= 9+.3=9.3m 3 9.30 0.30 0.60 5.02 cu m
SW1=3.5-.3=3.2m 4 3.20 0.30 0.60 2.30 cu m
SW2=3.8-.3=3.5m 3 3.50 0.30 0.60 1.89 cu m
H.W.=2.1-.3=1.8m 1 1.80 0.30 0.60 0.32 cu m
4
**Steps:
Bottom 1 2.70 0.90 0.15 0.36 cu m
Middle 1 2.70 0.60 0.15 0.24 cu m
Top 1 2.70 0.30 0.15 0.12 cu m
33.64 cu m
1st Class Brick Masonry in CM
(1:6) in Superstructure:
Walls:
Drawing Room 2 4.20 1.00 3.00 25.20 sq m
2 3.50 1.00 3.00 21.00 sq m
Bed Room 2 4.20 1.00 3.00 25.20 sq m
2 3.20 1.00 3.00 19.20 sq m
Dinning Room 2 4.20 1.00 3.00 25.20 sq m
2 3.50 1.00 3.00 21.00 sq m
136.80 sq m
Ceiling:
Drawing Room 1 4.20 3.50 1.00 14.70 sq m
Bed Room 1 4.20 3.20 1.00 13.44 sq m
Dinning Room 1 4.20 3.50 1.00 14.70 sq m
42.84 sq m
Deduction: (From Walls)
(Common Door Shared)D 0.5*4 + 1*1 1.20 1.00 2.10 7.56 sq m
D1 0.5*1 0.90 1.00 2.00 0.90 sq m
W 0.5*6 1.50 1.00 1.40 6.30 sq m
14.76 sq m
Net Quantity 164.88 sq m
7 20mm thick outside plaster:
Horizontal Wall 2 9.30 1.00 4.80 89.28 sq m
Vertical Wall 2 7.60 1.00 4.80 72.96 sq m
Steps:
Sides 2 1.00 0.90 0.15 0.27 sq m
2 1.00 0.60 0.15 0.18 sq m
2 1.00 0.30 0.15 0.09 sq m
Riser 3 2.70 1.00 0.15 1.22 sq m
Trade 3 2.70 0.30 1.00 2.43 sq m
166.43 sq m
Deduction: (From Walls)
D 0.5*2 1.20 1.00 2.10 2.52 sq m
W 0.5*6 1.50 1.00 1.40 6.30 sq m
8.82 sq m
Net Quantity 157.61 sq m
L=6.8+ 2(.45x)
L=6.8+ 2(.45*.663)
L=7.4m
Total Weight of 25 mm Dia. Bars 161.70 kg
12mm Dia. Anchor Bar: 2 6.57 m @ 0.88kg/m 11.56 kg
L= 6.4-2(0.025)+2(9*.012)
L=6.57m
Total Weight of 25 mm Dia. Bars 11.56 kg
Stirrups: 6 mm dia. Bars: 23 2.00 m @ 0.22kg/m 10.12 kg
l=.3-2(cover)-2(stirrup dia.)
l=.3-2(.025)-2(.006)
l=0.238m
b=.75-2(cover)-2(stirrup dia.)
b=.75-2(0.025)-2(.006)
b=0.688m
L=2(l+b)+24d
L=2(.238+.688)+ 24*.006=2 m
a) Sub -structure
b) M20 grade concrete or Prop. 1:1.5:3 5.376 Cu m 6063.65 32598.18
(B) In super structure from plinth level up
to 1st floor level.
b) M20 grade concrete or Prop. 1:1.5:3 3.30 Cu m 6241.39 20571.62
DETAILED ESTIMATE