Brick Drain 3.20L
Brick Drain 3.20L
QUANTITY SHEET -1
Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity
(m)
(m) (m)
1 Earth work in Excavation
For Drain 1 39.00 1.5 0.9 52.65 cu m
52.65 cu m
2 Flat brick soling
Base 1 39.00 1.50 58.50 Sq.m
58.50 Sq.m
3 P. C. C. For Foundation:
For Drain 1 39.00 1.00 0.30 11.70 cu m
11.70 cu m
1st Class Brick Masonry in CM
(1:6) up to Plinth:
**Foundation:
1st Step:
Walls: 2 39.00 0.90 0.30 21.06 cu m
4 21.06 cu m
1st Class Brick Masonry in CM
(1:6) in Superstructure:
Walls:
2 39.00 1.00 0.90 70.20 sq m
70.20 sq m
Extara
Top of wall 2 39.00 0.23 1.00 17.55 sq m
17.55 sq m
7 20mm thick outside plaster:
Horizontal Wall 2 39.00 1.00 0.90 70.20 sq m
70.20 sq m
Net Quantity 70.20 sq m
DETAILED ESTIMATE
a) Sub -structure
DETAILED ESTIMATE
REPORT
(Rupees Three Lakhs Twenty
Est. Amount : Rs. 320000.00 Thousand Only)
The estimate has been framed to cover the probable cost of the
work Under 14th Finance Comission . The Junior Engineer of
Binnakandi Dev Block has prepared this estimate on the
request of the president and secretary of the above said Gram
Panchayat raising the issue of providing this work under at the
GP area. It is proposed to provide in the such GP area.
Rate : Current prevailing market rates for market rate item and Electrical SOR (Assam)
Schedule of rate for 2013-14 items.