TABEL 1

PERHITUNGAN CUT & FILL PROYEK KABIL


LOKASI : PULAU BAII ( PT. PATHAWAY INT'L)
BENGKULU
LUAS LEVEL LEVEL RENCANA CUT FILL
NO ID
(m²) EXISTING (m) stripping (m) (m³) (m³)
1 A1 10,000 1.51 0.38 11,345 31,200
2 A2 10,000 1.63 0.38 12,475 31,200
3 A3 10,000 2.47 0.38 20,948 31,200
4 A4 10,000 2.75 0.38 23,694 31,200
5 A5 7,096 1.74 0.38 9,635 22,140
6 B1 10,000 1.68 0.38 13,044 31,200
7 B2 10,000 1.74 0.38 13,647 31,200
8 B3 10,000 2.25 0.38 18,706 31,200
9 B4 10,000 2.39 0.38 20,075 31,200
10 B5 7,096 1.58 0.38 8,490 22,140
11 C1 10,000 2.28 0.38 19,031 31,200
12 C2 10,000 2.25 0.38 18,689 31,200
13 C3 10,000 1.86 0.38 14,782 31,200
14 C4 10,000 2.24 0.38 18,640 31,200
15 C5 7,096 1.16 0.38 5,545 22,140
16 D1 10,000 1.98 0.38 15,973 31,200
17 D2 10,000 2.10 0.38 17,226 31,200
18 D3 10,000 2.19 0.38 18,125 31,200
19 D4 10,000 2.00 0.38 16,175 31,200
20 D5 7,096 1.66 0.38 9,056 22,140
21 E1 10,000 1.94 0.38 15,575 31,200
22 E2 10,000 2.16 0.38 17,808 31,200
23 E3 10,000 2.19 0.38 18,058 31,200
24 E4 10,000 1.98 0.38 15,950 31,200
25 E5 7,096 1.95 0.38 11,141 22,140
26 F1 10,000 1.89 0.38 15,075 31,200
27 F2 10,000 2.04 0.38 16,570 31,200
28 F3 10,000 2.10 0.38 17,189 31,200
29 F4 10,000 1.99 0.38 16,057 31,200
30 F5 7,096 1.93 0.38 11,011 22,140
31 G1 10,000 2.34 0.38 19,567 31,200
32 G2 10,000 2.50 0.38 21,186 31,200
33 G3 10,000 2.23 0.38 18,457 31,200
34 G4 10,000 1.98 0.38 15,986 31,200
35 G5 7,096 1.65 0.38 8,998 22,140
36 H1 10,000 3.00 0.38 26,200 31,200
37 H2 10,000 3.57 0.38 31,886 31,200
38 H3 10,000 1.56 0.38 11,829 31,200
39 H4 10,000 2.25 0.38 18,738 31,200
40 H5 7,096 1.91 0.38 10,864 22,140
41 I1 10,000 3.65 0.38 32,700 31,200
42 I2 10,000 3.14 0.38 27,588 31,200
43 I3 10,000 2.25 0.38 18,724 31,200
44 I4 10,000 2.53 0.38 21,516 31,200
45 I5 7,096 2.21 0.38 12,981 22,140
46 J1 10,000 3.01 0.38 26,323 31,200
47 J2 10,000 3.00 0.38 26,192 31,200
48 J3 10,000 2.13 0.38 17,462 31,200
49 J4 10,000 2.50 0.38 21,153 31,200
50 J5 7,096 2.42 0.38 14,456 22,140
51 K1 10,000 2.08 0.38 17,036 31,200
52 K2 10,000 2.16 0.38 17,794 31,200
53 K3 10,000 2.10 0.38 17,150 31,200
54 K4 10,000 2.32 0.38 19,440 31,200
55 K5 7,096 2.45 0.38 14,717 22,140
56 L1 10,000 2.22 0.38 18,400 31,200
57 L2 10,000 2.17 0.38 17,888 31,200
58 L3 10,000 2.08 0.38 16,950 31,200
59 L4 10,000 2.24 0.38 18,550 31,200
Lampiran 1
PERHITUNGAN CUT & FILL PROYEK KABIL
LOKASI : PULAU BAII ( PT. PATHAWAY INT'L)
BENGKULU
LUAS LEVEL LEVEL RENCANA CUT FILL
NO ID
(m²) EXISTING (m) stripping (m) (m³) (m³)
60 L5 7,096 2.40 0.38 14,298 22,140
61 M1 10,000 2.35 0.38 19,704 31,200
62 M2 10,000 2.33 0.38 19,478 31,200
63 M3 10,000 2.13 0.38 17,488 31,200
64 M4 10,000 1.50 0.38 11,220 31,200
65 M5 7,096 2.14 0.38 12,457 22,140
66 N1 10,000 2.18 0.38 17,976 31,200
67 N2 10,000 2.20 0.38 18,207 31,200
68 N3 10,000 2.21 0.38 18,294 31,200
69 N4 10,000 2.61 0.38 22,275 31,200
70 N5 7,096 2.57 0.38 15,555 22,140
71 O1 10,000 2.44 0.38 20,642 31,200
72 O2 10,000 2.39 0.38 20,145 31,200
73 O3 10,000 2.05 0.38 16,661 31,200
74 O4 10,000 1.63 0.38 12,492 31,200
75 O5 7,096 2.22 0.38 13,064 22,140
76 P1 10,000 1.61 0.38 12,347 31,200
77 P2 10,000 1.42 0.38 10,436 31,200
78 P3 10,000 1.64 0.38 12,558 31,200
79 P4 10,000 1.36 0.38 9,816 31,200
80 P5 7,096 1.57 0.38 8,444 22,140
81 Q1 10,000 1.68 0.38 13,033 31,200
82 Q2 10,000 1.63 0.38 12,480 31,200
83 Q3 10,000 1.68 0.38 13,000 31,200
84 Q4 10,000 2.20 0.38 18,222 31,200
85 Q5 7,096 2.11 0.38 12,306 22,140
86 R1 10,000 1.74 0.38 13,567 31,200
87 R2 10,000 1.42 0.38 10,433 31,200
88 R3 10,000 1.59 0.38 12,075 31,200
89 R4 10,000 2.08 0.38 17,037 31,200
90 R5 7,096 2.18 0.38 12,737 22,140
91 S1 10,000 2.11 0.38 17,250 31,200
92 S2 10,000 1.33 0.38 9,452 31,200
93 S3 10,000 1.46 0.38 10,786 31,200
94 S4 10,000 1.71 0.38 13,272 31,200
95 S5 7,096 2.11 0.38 12,276 22,140
96 T1 10,000 3.91 0.38 35,309 31,200
97 T2 10,000 1.26 0.38 8,811 31,200
98 T3 10,000 1.64 0.38 12,586 31,200
99 T4 10,000 1.95 0.38 15,662 31,200
100 T5 7,096 2.27 0.38 13,411 22,140
101 U1 4,000 2.00 0.38 6,480 12,480
102 U2 4,000 1.13 0.38 3,000 12,480
103 U3 4,000 2.01 0.38 6,500 12,480
104 U4 4,000 2.06 0.38 6,700 12,480
105 U5 2,781 2.14 0.38 4,889 8,677

TOTAL 960,701 2.34 1,655,294 2,966,187

2,069,117.80
21,287

7
3,295,763
Estimasi produksi alat berat
Jenis alat berat "Backhoe SK 07"
Nilai
No Faktor koofesien Sat
Koefesien
1 Swing bucket assumed 90o 0.90 -
2 Kedalaman potong 90% -
3 Bucket fill tabah lempung basah/pasir 0.90 -
4 Tipe material common earth 0.90 -
5 Waktu effektif 1 jam = 50 menit 0.83 -
6 Cycle output (tipe SK 07) 160.00 siklus/jam
7 Kapasitas bucket 1.00 m3 0.375
8 Total Produksi 97.2 m /jam
3

Jenis alat berat " Dump truck kap. 6 m3

No Faktor kebutuhan waktu Durasi Sat


a Waktu tempuh pergi untuk titik 4.20 menit
0 m - 500 m kearea dumping (+1, 6 km)
b Waktu tempuh pergi untuk titik
500 m - 1000 m kearea dumping (+1, 6 km) 5.20 menit
c Waktu tempuh pergi untuk titik
1000 m - 1500 m kearea dumping (+1, 6 km) 6.20 menit
d Waktu tempuh pergi untuk titik
1500 m - 2000 m kearea dumping (+1, 6 km) 7.20 menit
e Waktu manuver 3.00 menit
f Waktu dumping 3.00 menit
g Kapasitas dump truck (dt) 6.00 m3
h Koefesien Waktu effektif ( 1 jam = 50 menit) 0.83
Catt: Kecepatan rata-rata 30 km/jam

Id Keterangan Jumlah Sat


I Total produksi per jam (jarak 0-500 m) 29.41 m3
(60 menit / ((2 x a)+ e + f)) x g x h
II Total produksi per jam (jarak500 -1000 m) 26.79 m3
(60 menit / ((2 x b)+ e + f)) x g x h
III Total produksi per jam (jarak1000 -1500 m) 24.59 m3
(60 menit / ((2 x c)+ e + f)) x g x h
IV Total produksi per jam (jarak1500 -2000 m) 22.73 m3
(60 menit / ((2 x c)+ e + f)) x g x h

A Kebutuhan minimal dump truck (0 - 500m) 3.3048 buah


agar backhoe tidak delay ( 8 / I ) 4 buah

B Kebutuhan minimal dump truck (500 - 1000m) 3.6288 buah


agar backhoe tidak delay ( 8 / I ) 4 buah

C Kebutuhan minimal dump truck (1000 - 1500m) 3.9528 buah


agar backhoe tidak delay ( 8 / I ) 4 buah
D Kebutuhan minimal dump truck (1500 - 2000m) 4.2768 buah
agar backhoe tidak delay ( 8 / I ) 5 buah

Total durasi (jam) 1 set alat berat


(1 unt Backhoe SK 07 dan 4 unt Dumptruck)
22.5