Professional Documents
Culture Documents
B
eing versatile, economical, and durable (under
certain conditions), reinforced concrete and
prestressed concrete are the most widely used
structural materials throughout the world. Unfortunately,
corrosion of steel reinforcement is a major cause of dura-
bility problems in aged reinforced concrete structures.1 In
■ This paper discusses the design philosophy and the well-preserved structures, corrosion is prevented due to the
flexural performance under service loads of the pre- alkalinity of the solution filling the concrete pores, which
cast, prestressed concrete girders made of innova- promotes the formation of a thin oxide layer inducing
tive materials and novel composite manufacturing passivation of steel. However, this passivity may be lost
technologies for a recently constructed pedestrian when carbonation occurs or a critical amount of chloride
bridge. ions reaches the steel surface.2 Chloride-induced corrosion,
which occurs in reinforced concrete structures exposed to
■ The two girders, cast in the shape of double-tees seawater or deicing salts, is particularly critical because it
with shortened flange overhangs, were prestressed progresses rather rapidly. Reinforced concrete durability
with carbon-fiber-reinforced polymer tendons and thus depends on a sufficiently thick and dense concrete
reinforced with basalt-fiber-reinforced polymer cover, the effectiveness of which is time limited and
bars. susceptible to overwhelming phenomena, such as cracking
and local damage.
■ Carbon-fiber-reinforced polymer prestressing
technology can be successfully used in thin-walled A strategy for ensuring the long-term durability of re-
concrete sections beyond the limits suggested by inforced concrete and prestressed concrete structures is
current literature and without significant technolog- to use reinforcement that is not susceptible to corrosion.
ical drawbacks. Fiber-reinforced polymers (FRPs) are a proven nonmetallic
Table 1 shows the mechanical properties measured by matrix. The fibers were produced from basalt rock through
the manufacturer on the specific production lot and the a melting process. Due to their fairly recent commercial
values exhibited by conventional low-relaxation steel availability, their use is not currently addressed by ACI
strands that have the same nominal diameter but slightly Committee 440.
higher cross-sectional area. A comparison between the
two sets of data shows how carbon-fiber-composite cable Characterization tests were performed according to ACI
can be considered a more efficient prestressing material 440.3R guidelines18 following the methods currently used
than traditional high-strength steel because of its higher for other FRP reinforcement. Table 2 gives the results of
breaking load and lower modulus of elasticity. The high those tests.
tensile strength of carbon-fiber-composite cable allows
a high prestressing rate, while the lower elastic modulus Unlike a steel bar, the tensile strength of FRP bars varies
reduces losses due to the elastic shortening and creep of with their diameter while the longitudinal modulus does
concrete. The nominal failure capacity guaranteed by the not change appreciably. This phenomenon is primarily due
manufacturer is 60.7 kip (270 kN), a value slightly higher to the effects of shear lag as the matrix transfers stresses
than the capacity of the steel strand. from outer fibers to inner fibers within the bar.19
T = time Design
66 ft (clear span)
Girder DT1
14 ft 3 in.
Girder DT2
Figure 1. Diagram of the pedestrian bridge. Note: 1 in. = 25.4 mm; 1 ft = 0.305 m.
1ft 2in.
-17in.
No.3 at 8in.
1ft 2in.
No.4 at 6in.
No.3 at 8in.
No.4 at 6in.
-3in.
3 in.
0in.
4in.
1ft 3in.
No.8 No.3 at 3in.
VWG-BFRP-m
No.3 at 6in.
VWG-BFRP-s
+12in. T9
2ft 6in.
T8 VWG-T9-m
2ft 2in.
T7 VWG-T9-s
T6 CFRP
1ft 3in.
T5 Tendons
Sleeve ˣ 10ft T4
T3
+28in. No.8 T2
+30in. T1 VWG-T1-m
VWG-T1-s
6in.
Figure 2. Cross section of the double tee with concrete topping and curb. Note: BFRP = basalt-fiber-reinforced polymer; CFRP
= carbon-fiber-reinforced polymer; VWG = vibrating wire gauge. No. 3 = 10M; no. 4 = 13M; no. 8 = 25M; 1 in. = 25.4 mm; 1 ft =
0.305 m.
68 ft 8 in.
33 ft 1 ft 4 in.
S Bearing plate
7 ft 1 ¼ in.
Girder DT1
VWG-BFRP-m S VWG-BFRP-s
VWG-T9-m VWG-T9-s 3 ft
VWG-T1-m VWG-T1-s
34 ft 4 in. 34 ft 4 in.
Figure 3. Plan view of the double-tee girder DT1. Note: BFRP = basalt-fiber-reinforced polymer; VWG = vibrating wire gauge. 1 in.
= 25.4 mm; 1 ft = 0.305 m.
full section of the girders after the concrete topping cast- tendon strain is above 0.005 and 0.65 for compression-con-
ing. As previously specified, the environmental reduction trolled behavior when the net tendon strain is below 0.002.
factor CE was adopted to account for long-term exposure to The section lies in the transition zone: the strength re-
environmental loads. A step-by-step analytical procedure duction factor, computed as a function of the net strain in
based on the model proposed by Naaman24 was adopted to the furthest tendon at failure, is 0.82. Further discussion
compute concrete creep and shrinkage. of flexural resistance factors for the design of concrete
structures prestressed with CFRP is provided by Kim and
Equation (1) was used to calculate the CFRP relaxation Nickle25 and Forouzannia et al.26
losses after a 75-year service life. The resulting nomi-
nal flexural capacity and cracking moment of the single The factored flexural capacity of each girder, com-
double tee, including the concrete topping and curb, at the plete with concrete topping and curb, is 1899 kip-ft
75-year service life were 2306 and 1050 kip-ft (3127 and (2575 kN-m), a value exceeding the design demand at
1424 kN-m), respectively. ultimate.
Note: n/a = not applicable. 1 in. = 24.5 mm; 1 ksi = 6.895 MPa.
Figure 4. Carbon-fiber-composite cable and steel strand coupling anchorage system. Note: CFRP = carbon-fiber-reinforced
polymer.
with six vibrating wire gauges (VWGs): four installed on advantage of the gradual energy release caused by the
the CFRP tendons and two installed on the BFRP rein- elevated temperature, which lowers the yielding point of
forcement. The top tendon T9 and the bottom tendon T1 of steel. This process cannot be adopted for FRP tendons
a selected stem of girder DT1 were instrumented with two because they would be degraded by the heat. Rather, FRP
gauges at the double-tee midspan (VWG-T9-m and VWG- tendons must be severed using a high-speed grinder. For
T9-s) and two more at about 3 ft (0.9 m) from one of the this reason, the tension was released at the two ends of the
end sections (VWG-T9-s and VWG-T9-s) (Fig. 2 and 3). prestressing bed by cutting the steel rather than the CFRP
VWG-BFRP-m and VWG3-BFRP-s were installed on the strands. After the end release, the CFRP strands between
BFRP longitudinal reinforcement similarly to the gauges the two double tees were carefully cut using a grinder.
on the monitored stem, at the double-tee midspan and at The prestress release took place 24 hours after casting.
3 ft from the same end section, respectively. At that time, the measured concrete compressive strength
was 5307 psi (36.59 MPa). Following these operations, the
Tensioning girders were successively demolded.
prediction of losses. The strains detected at 3 ft (0.9 m) (Table 3). The original design requires the girders to remain
from the end section (VWG-T9-s and VWG-T1-s) show a uncracked under service loads, and the test was run accord-
partial loss of bond of the bottom tendon T1. This phenom- ingly. The effects of the 100 lb/ft2 (4.8 kN/m2) distributed
enon was not expected because both VWGs were meant live load on the fully completed bridge (double tees with
to be installed beyond the development-length zone of the topping and curbs) were considered to back-calculate the
tendons. However, the sleeves installed on tendons T2 and point load that would produce the same effect on the double
T3 at the two ends of the double tees (Fig. 2) may have tees only. This resulted in a 27 kip (120 kN) test load in
negatively affected the bond behavior of tendon T1. addition to the self-weight, which was supposed to produce a
maximum moment of 809 kip-ft (1100 kN-m) on the single
Load test double tee. The test condition corresponds to the 85% of the
double-tee cracking moment, defined as that which forces
As shown in Fig. 5, the flexural response under service the concrete from the initial compressive stress of -1840 psi
conditions, a static load test was conducted on the in- (-12.7 MPa) to the cracking tensile stress of 673 psi (4.64
strumented girder DT1 at the precasting plant before its MPa), computed per ACI 318-14 recommendations and
installation on-site. The test, conducted according to a accounting for concrete strength gain over time.
three-point loading scheme over the 66 ft (20 m) effective
span, took place 26 days after casting. Four rectangular hollow steel tubes placed over prismatic
concrete elements were used as supports (Fig. 6). A
Test arrangement soft wood interface was provided between the supports
and the girder bearing plates to help the leveling process
The test load magnitude was designed to avoid concrete and prevent stress concentration during the test. Three
cracking. The analytical procedure was refined to ac- rectangular concrete blocks, each of them weighing 9 kip
count for the actual properties of the concrete used and (40 kN), were used to apply the intended load by means of
the progressive gain of strength and stiffness due to aging a crane (Fig. 5).
1.2% 80
70
1.0%
% of guaranteed strength
60
0.8% 50
Strain
0.6% 40
30
0.4% VWG-T1-m
VWG-T9-m 20
0.2% Average at midspan
10
Analytical prediction
0.0% 0
Figure 5. Strains in carbon-fiber-reinforced polymer tendons Figure 6. Double-tee girder loading phase, dial gauges, and
at midspan. Note: 1 ft = 0.305 m. supports.
30.00
66 ft (clear span)
25.00
33 ft 33 ft
20.00
16 ft 6 in. 16 ft 6 in. 16 ft 6in. 16 ft 6 in.
Load, kip
S
15.00
Figure 7. Dial gauge locations. Note: DG = dial gauge. 1 in. = Figure 8. Load-deflection curves. Note: DG = dial gauge. 1 in.
25.4 mm; 1 ft = 0.305 m. = 25.4 mm; 1 kip = 4.448 kN.
8 0 kip at 24 hours
0.50
Analytical (27 kip at
Deflection, in.
12 T9 0 hours)
Depth, in.
0.75
16
1.00
20
1.25
9 kip at 0 hours 18 kip at 0 hours 24
1.50 27 kip at 0 hours 27 kip at 24 hours
0 kip at 24 hours Analytical 28 T1
1.75
Figure 9. Deflection profile along the beam axis. Note: 1 in. = Figure 10. Measured strain profile at girder DT1 midspan. Note:
25.4 mm; 1 ft = 0.305 m; 1 kip = 4.448 kN. 1 in. = 25.4 mm; 1 kip = 4.448 kN.
and the top tendon T9 differ by +3% and -6%, respectively, predictions. All calculations were performed based on es-
from the analytical predictions. Only the strain measured tablished theories and mechanical models and demonstrated
on the BFRP mesh is considerably higher than the predict- that the implementation of CFRP tendons may not require
ed analytical value (+36%). additional design efforts by practitioners.
Notation
T = time
Y = relaxation rate
Review policy
Abstract
This paper was reviewed in accordance with the
This paper deals with the design philosophy and the Precast/Prestressed Concrete Institute’s peer-review
flexural performance under service loads of the precast, process.
prestressed concrete girders constituting the deck of
a recently constructed pedestrian bridge. This simple Reader comments
structure combines innovative materials and novel
composite manufacturing technologies to ensure that Please address reader comments to journal@pci.org or
degradation due to steel corrosion does not undermine Precast/Prestressed Concrete Institute, c/o PCI Journal,
the longevity of the bridge. 200 W. Adams St., Suite 2100, Chicago, IL 60606. J