Assignment Q.

No 7
A power generator manufacturing company has three plants and four warehouses to
distribute generators. The demand, supply and transport cost is given in the following table.
Find the initial feasible solution (total transport cost matching the demand and supply) by
VAM method and find the optimal solution by MODI method to minimise the transport
cost

To P Q R S Supply
From

A 19 30 50 10 7
B 70 30 40 60 9
C 40 8 70 20 18
Demand 5 8 7 14 34