You are on page 1of 2

QUANTITATIVE METHODS (Operations Research) – Expected time(𝒕𝒆 )- the average time an

various applications of mathematics in business or any activity would require if it were repeated a large
complex system. number of times.

OPERATIONS RESEARCH- specifically, the discipline of 𝑡𝑒 = 𝑡𝑜 + 4𝑡𝑚 +𝑡𝑝


applying quantitative methods oriented to planning. 6
Where;
NETWORK MODELS involve project scheduling 𝑡𝑜 - optimistic time
techniques that are designed to aid the planning and 𝑡𝑚 - most likely time
control of large-scale projects having many interrelated
𝑡𝑝 – pessimistic time
activities.

Uses of Network Analysis: Slack time- the amount of time that can be added
1. Planning to an activity without increasing the total time
2. Measuring progress to schedule required on the critical path; the length of time an
3. Evaluating changes to schedule activity can be delayed without forcing a delay for
4. Forecasting future progress the entire project.
5. Predicting and controlling costs
3. Critical Path Method (CPM)- like PERT, it is a
SAMPLE APPLICATIONS network technique, but unlike PERT, it uses
1. Building construction deterministic time and cost estimates, its
2. Book publishing
advantages.
3. New product planning
4. Feasibility studies
5. Research and development projects Crash time - time to complete an activity assuming
6. Auditing that all resources were devoted to the task
(overtime, extra crew, etc.)
PROJECT SCHEDULING TECHNIQUES
1. Gantt or Bar charts- a type of bar chart that LEARNING CURVES
illustrates the scheduled start and finish of -describe the efficiencies arising from experience,
elements of a project over time because with experience comes increased
2. Program Evaluation and Review Technique- productivity. This productivity increases with
developed to aid managers in controlling large- production size, but at a decreasing rate as
scale, complex problems.
diagrammed below:
Pert Diagram- a probabilistic diagram of the
interrelationship of a complex series of activities; a
free-form network showing each activity as a line
between events.

Events- discrete moments in time representing the Experience


start or finish of an activity; they consume no
resources. The time required to perform a given task becomes
progressively shorter, but this is applicable only to
Activities- tasks to be accomplished; they consume the early stages of production or any new task.
resources, (including time) and have a duration over
time
The curve is expressed as a percentage of reduced
 Types of Activity
1. Series- an activity cannot be performed time (usually between 60% and 80%) to complete a
unless another activity is undertaken. task of each doubling of cumulative production.
2. Parallel- can be performed simultaneously. Hence, the time required is reduced by 20% to 40%
each time cumulative production is doubled.
 Critical Path- longest path through the network
Assumptions:
1. The cumulative average time per unit is reduced
by a certain percentage each time production
doubles.
2. Incremental unit time ( time to produce the last
unit) is reduced when production doubles.

PROBABILITY ANALYSIS
PROBABILITY is important to management
decision-making because of the unpredictability of
future events.

Decision-making under conditions of risk- occurs


when the probability distribution of the possible
future states of nature is known.

Decision-making under conditions of uncertainty-


occurs when the probability distribution of possible
future states of nature is not known and must be
subjectively determined.

The probability of an event varies from 0 to 1


a. 0 probability- the event cannot occur
b. Probability of 1 (or 100%) the event is certain to
occur

BASIC TERMS USED WITH PROBABILITY


1. Two events are mutually exclusive if they
cannot occur simultaneously.
2. The joint probability of two events is the
probability that both will occur.
3. The conditional probability of two events is the
probability that one will occur given that the
other has already occurred.
4. Two events are independent if the occurrence
of one has no effect on the probability of the
other.

Expected value
The expected value of an action is found by
multiplying the probability of each outcome by its
pay-off and summing the products.

You might also like