Jain Engineers

Wadhwa Pristine
MANUAL EXCAVATION SUMMARY

MANPOWER CALCULATION
Sr No ITEM UNIT Quantity
A Labours NO 11
B Days For Excavation NO 10
C Total Man-Days (A*B) NO 110

LABOUR CHARGES
D Labour Rate Per Man Days RS 630
Total Amount (C*D) = 100*700 69300
Excavation Quantity Cu.M 84
Excavation Rate Per Cum =70000/84 Rs/Cu.M 825