Professional Documents
Culture Documents
ISSUE
EnergyAustralia staff: This Standard is for issue to all staff involved with the design and construction
of underground sub-transmission lines forming part of EnergyAustralia’s network, and for general
reference by field, technical and engineering staff.
Where this standard is issued as a controlled document replacing an earlier edition; remove and
destroy the superseded document.
All other persons involved with construction work in substations, including Accredited Service
Providers and Contractors: This document is issued on an uncontrolled basis. Users are responsible
for ensuring that the document they are using is current and includes any amendments issued since
the date on the document.
EnergyAustralia maintains a copy of this and other Network Standards together with updates and
amendments on www.energy.com.au.
EnergyAustralia also offers a subscription service which provides for updates and amendments to
standards on payment of an annual fee.
DISCLAIMER
As EnergyAustralia’s standards are subject to ongoing review, the information contained in this
document may be amended by EnergyAustralia at any time.
It is possible that conflict may exist between standard documents. In this event, the most recent
standard is to prevail.
This document has been developed using information available from field and other sources and is
suitable for most situations encountered in EnergyAustralia. Particular conditions, projects or localities
may require special or different practices. It is the responsibility of the local manager, supervisor,
assured quality contractor and the individuals involved to ensure that a safe system of work is
employed and that statutory requirements are met.
EnergyAustralia disclaims any and all liability to any person or persons for any procedure, process or
any other thing done or not done, as a result of this Network Standard.
INTERPRETATION
In the event that the user of this document is uncertain about any information or provision herein, the
user should contact EnergyAustralia for clarification. EnergyAustralia’s interpretation shall then apply
as though it was included in the Standard, and is final and binding.
Network Standard
NS 201
All Dielectric Self Supporting Fibre Optic Cabling for Installation
on Distribution Assets
February 2008
CONTENTS
1 INTRODUCTION ......................................................................................................... 1
1.1 Purpose ............................................................................................................ 1
1.2 Scope ............................................................................................................... 1
1.3 References and other relevant standards........................................................ 1
8 MINIMUM CLEARANCES............................................................................................ 7
8.1 ADSS Minimum Clearances from Aerial Fixed Attachments ........................... 7
8.2 ADSS Minimum Clearances from Ground ....................................................... 8
1 Introduction
1.1 Purpose
This document provides an overview of the minimum requirements that are to be used when
constructing an All Dielectric Self Supporting (ADSS) circular fibre optic cabling system
attached to EnergyAustralia assets.
An optical cable network must provide a very high service level for continuity of both internal
control networks and other services. Installation must be carried out by experienced
personnel in a professional manner in order to minimize the risk of subsequent failure.
1.2 Scope
The intent of this document is to provide a general guide to the technical issues that must be
addressed in the design and construction of an ADSS communications network on
EnergyAustralia assets. It is neither practical nor possible to cover every issue that may arise
during a network rollout. In the event that clarification is required the reader must contact the
Manager, Engineering Standards and Research.
NEG TC01 All Dielectric Self Supporting (ADSS) Cable on Poles - Design Guidelines
Planning and Design Standards for Electrical Network Communications
NS 203
Assets
NS 204 Communications Pits – Specifications and Installation Guidelines
Guidelines for design and maintenance of overhead distribution and
ENA C(b)1
transmission lines
ENA NENS National guidelines for safe approach distances to electrical and
04-2006 mechanical apparatus
NS 201
February 2008 2
2 Compliance Requirements
Design and construction shall:
• comply with all relevant provisions of applicable legislation, regulations and industry
codes of practice including any relevant Codes;
• comply with any other Australian Standards at the time relevant to the
telecommunications industry and the electricity industry;
• comply with such other codes, procedures or standards as agreed between the Parties
from time to time; and
• comply with EnergyAustralia documents including but not limited to Network Standards,
Network Management Plan and Electrical Safety Rules as relevant and appropriate.
• be aware of and reference NEG-TC01, All Dielectric Self Supporting Cable on Poles –
Design Guidelines
3.1 Abbreviations
ABC Aerial Bundled Cable
ADSS All Dielectric Self Supporting cable
AS Australian Standards
CMEN Common Multiple Earth Neutral
EA EnergyAustralia
EPR Earth Potential Rise
ES Electrical Standard
GIS Geographic Information System
HFC Hybrid Fibre Coaxial cable network
HV High Voltage
IM Integral Messenger
kN kilo Newton
kV kilo Volt
LFI Low Frequency Induction
LV Low Voltage
NS Network Standard
OH&S Occupational Health and Safety
PE Photo Electric (Cell)
PSTN Public Switched Telephone Network
UGOH Underground to Overhead transition structure
XLPE Cross-linked polyethylene
NS 201
3 February 2008
3.2 Definitions
ADSS All Dielectric Self Supporting fibre optic cable which is
nonconductive, self supporting and is capable of being
erected under tension between supports. It does not
require a separate catenary.
Catenary A separately constructed strength member attached to a
pole to which communications equipment and cable may
be attached. This also includes that part of an integral
bearer cable which is used to support wires and cables
which are enclosed in a cover or sheath.
Down Traffic Side The side of the pole on the far side of the on-coming traffic
(of a pole) (with pole and on-coming traffic on same side of road).
Earth Potential Rise The potential with respect to remote earth potential to
which a location rises due to the flow of current in the
earth.
High Voltage High voltage is normally more than 1,000 volts AC or 1500
volts DC
Hybrid Fibre Copper Telco network cable consisting of copper co-axial and
fibre optics.
Low Voltage Low voltage is normally more than 50 volts AC or 120
volts ripple free DC but is not more than 1,000 volts AC or
1500 volts DC.
Low Frequency Induction The generation of induced voltages in conductors
inductively coupled to a power line due to 50 Hz currents
flowing in the power line and using the earth as a return
path.
Make Ready Work The work which is required to be carried out prior to or at
the time when equipment is being attached to a pole in
order to ensure compliance with the requirements of this
document or the requirements of other relevant
authorities.
Normal Shared Use Shared use of a pole under conditions which comply with
this document and do not unduly stress the pole. This
does not include poles which are specifically listed as
Special Shared Use poles.
Pole Pole owned by EnergyAustralia.
Project Manager The person managing the design and construction of the
relevant ADSS project.
Special Shared Use Shared use of poles of a type specified by
EnergyAustralia and as defined in this document.
NS 201
February 2008 4
4 Regulatory Issues
All work carried out on EnergyAustralia’s network and/or its poles must be in accordance with
EnergyAustralia’s Electrical Safety Rules.
Design and construction must comply with all relevant provisions of applicable legislation,
regulations and industry codes of practice as well as any relevant Australian and International
Standards, as detailed in Standards Clause and Occupational Health and Safety Clause of
the Design and Deployment Agreement.
4.1 Asbestos
All materials and equipment used for construction of EnergyAustralia’s assets are to be free
from asbestos and / or asbestos related products. Suppliers are expected to comply with the
Occupational Health and Safety Act 2000 (NSW) together with the Occupational Health and
Safety Regulation 2001 (NSW) and confirm in writing that all products supplied to
EnergyAustralia contain no asbestos related materials.
4.2 Environment
ADSS project plans shall consider the environmental impacts of the proposed installation and
satisfy the requirements of the Environmental Planning and Assessment Act 1979. An
Environmental Impact Assessment may be required before works can commence. Refer to
NUS 174 – Environmental Procedures, for further information regarding environmental
issues. Alternatively, contact EnergyAustralia.
4.3 Council
Relevant local councils must be informed, in writing, with a minimum of 40 days notice, of any
EnergyAustralia plans to construct aerial communications infrastructure. Councils must be
asked to advise if special zoning or consent requirements apply to the proposed works in the
relevant area.
NS 201
5 February 2008
The majority of the EnergyAustralia poles are desapped or treated hardwood poles with some
poles being of a spun concrete construction with internal metal strength members.
In addition to the power network assets, the poles are also used for supporting a number of
other types of equipment such as public street lighting, special lighting, supporting road and
street signs and traffic signal equipment. There may also be other private and public
communications networks which can utilise both copper and optic fibre based cables. In
addition there are a number of HFC networks which involve stranded cable, fibre optic cable,
co-axial cable and network components. Some poles support mobile phone transmitter units,
which emit high frequency electromagnetic radiation and may require disconnection prior to
1
working on the pole . Refer to the owner of the installation using the 24-hour number
attached to the equipment.
6 Exclusions
This Network Standard describes the requirement for the aerial communications systems
deployed with cable that is circular in cross-section and entirely non-conductive (all-
dielectric). Excluded are cabling systems that contain conductive cable components such as
metallic armouring, integral bearer wires or metallic catenary supports.
This Network Standard does not describe the requirements for ADSS to be installed in areas
of extreme pollution. ADSS must not be installed without prior consultation with
EnergyAustralia in areas where there is a perceived risk that extreme pollution may cause the
outer sheath of the cable to become conductive and be subject to electrical tracking or other
electric field effects.
Some specific pole types will require modifications to the normal attachment to the pole to
facilitate safe access and operation of the power system equipment such as air break
switches, pole mounted transformers.
Service poles should not be used for main communications lines.
1
Refer to NS 102, Working on Poles with Mobile Phone Transmitter Installations
NS 201
February 2008 6
7 Pole Classifications
Not all poles within the area serviced by EnergyAustralia are owned by EnergyAustralia2. The
Project Manager is responsible for confirming the ownership of any pole. Plans from
EnergyAustralia’s GIS may provide an indication of those poles owned by EnergyAustralia.
Poles proposed to be used for the construction of the communication network can be
classified as being one of three types, i.e.
• staked pole, (refer to NS 145 Pole Inspection and Treatment Procedures, a reinforced
(nailed or splinted) pole, a pole with the original foundation supplemented with a
structural support system).
• limited life pole, (refer to NS 145 Pole Inspection and Treatment Procedures, for
definition).
• stayed pole, (where a stay wire or wires are used between the pole and a support point
to adequately counter the resultant conductor tension).
• stay pole, (an additional pole providing suitable leverage to which a stay wire is
attached to counter conductor tension).
• steel pole supporting overhead mains
• steel street lighting column
• pole supporting electrolysis drainage cables or associated equipment
• pole supporting public transport conductor or associated equipment
• pole on which a strained configuration is employed (Tension Structure)
The installation of ADSS fittings on Special Shared use poles may require the relocation of
existing plant, or the construction of additional overhead infrastructure, such as a cross arm
or stand-off bracket.
It is recommended to avoid locating ADSS terminations on Special Shared Use poles.
2
Common-Use Pole. Refer to NS 145. A pole belonging to another public utility or authority, on which
EnergyAustralia’s wires are attached. The pole is mainly used to carry conductors belonging to the owner of the pole.
NS 201
7 February 2008
• Defective Poles – A single 75mm wide highly visible orange band secured around the
pole at least 2.4m above ground but below 3m, encircling the whole pole, marked with
Black “X X X”s
• Condemned Poles – A single orange band as above, plus a permanently marked “X”
painted 1.8 m above ground on opposite sides of the pole with slashes ‘/’ ‘\’ at least
500 mm long, using white paint.
Condemned poles must be removed from service or stabilised without undue delay. If you
find a pole you consider to be dangerous, you must report it immediately to the
EnergyAustralia Supervisor/Contract Officer/Customer Service Office to ensure appropriate
action is taken.
In the case of a condemned pole the Project Manager shall organise that the pole be
replaced as part of the Make Ready Work program prior to installation of any further
infrastructure.
8 Minimum Clearances
Notes:
1. For voltages 66kV and above, the cable manufacturer shall be asked to advise as to the
cable placement, which minimises electric field effects, based upon the overhead
electricity construction. The cable manufacturer may suggest the use of an anti-tracking
cable sheath and/or corona coils.
In considering the point of attachment for ADSS cables, the designer, Project Manager and
installer shall consider:
NS 201
February 2008 8
• Access requirements for future repairs and maintenance of the ADSS cable and other
aerial plant.
• The mid-span clearance of the cable considering the sag of ADSS and overhead
conductors
Please also refer to NEG TC 01, ADSS Cables on Poles – Design Guidelines.
Notes:
1. Some local councils and private land-holders impose minimum clearances different from
those in the above table. The Project Manager shall confirm with the relevant authorities
whether different clearances are required.
2. Over land in industrial areas, in particular driveways where LV cables exist, the ADSS
can be installed below 6500mm PROVIDED the ADSS cables are located a minimum of
125mm higher than the LV cable.
3. *The NSW Maritime Crossing Guide must be referred to for ADSS installations with
water crossings. The installer must adhere to any clearance implied or mandated by this
Guide. The Manager – Engineering Standards and Research can advise
EnergyAustralia’s nominated expert for this document. Note that alterations may be
required to existing signage should there be any change to safety clearance.
NS 201
9 February 2008
NS 201
February 2008 10
NS 201
11 February 2008
NS 201
February 2008 12
NS 201
13 February 2008
ADSS Hanger Fitting – Line Deviation Max 30 Degrees, 350m < Span < 600m
NS 201
February 2008 14
ADSS Double Yoke Hanger Fitting – Line Deviation Max 60 Degrees, 350m < Span < 600m
ADSS Double Termination Fitting – Line Deviation greater than 60 Degrees, 350m
< Span < 600m
The shackles, chain and other fittings used for the long-span terminations must be rated at
70kiloNewton. Long-span terminations must use tongue bolts, rather than hook-bolts.
Structural rods used for long-span fittings are longer than those used for shorter spans.
• All steelwork, including bolts passing through timber, shall be hot dipped galvanised to
AS-1650 (Hot dipped galvanising on ferrous articles) and/or as appropriate AS-1214
(Hot dipped galvanised coatings on threaded fasteners )
• All galvanised bolts shall be coated before installation on their threaded section with
a KOPR-KOTE anti-seize lubricant, stockcode H19942.
After tightening nuts on their bolt, the thread immediately behind the nut must be burred to
prevent loosening.
Readers are advised to make themselves aware of the specific OH&S requirements when
working on CCA (treated) poles.
The preferred location for pole-mounted ADSS Splice Enclosures is the down-traffic side of
the pole. However, the location shall be selected with consideration given to the visual
3
Extract from Network Standard NS 122, Pole Mounted Substation Construction
NS 201
15 February 2008
amenity of the installation, future access by means of a ladder or otherwise and current or
planned additions to the pole.
4
As defined in the EA Electrical Safety Rules (table 5.1).
NS 201
February 2008 16
• The coil bracket shall be mounted below the splice enclosure, with approximately 90
degrees rotation between the two fixtures.
• The coil must be suitably secured to the bracket with cable ties and the bottom of the
coil must be secured to avoid swinging in the wind.
NS 201
17 February 2008
Note that the fitting may also be attached below the cross-arm.
NS 201
February 2008 18
5 One solution that would be satisfactory is to fabricate a gasket of 1 or 2mm thick, black “Neoprene”
(polychloroprene ) for fitting between the stainless steel band and the pole.
NS 201
19 February 2008
NS 201
February 2008 20
NS 201
21 February 2008
NS 201
February 2008 22
the Project Manager should consider requesting that this facility be suspended during the
construction phase.
The Project Manager shall request standard installation instructions and manuals, for the
cable and fittings used from the suppliers.
NS 201
23 February 2008
NS 201
February 2008 24
Network Standard NUS 100 - Field Recording of Network Assets and NS 104 Network
Project Design Plans, provides details of requirements which must be followed by
EnergyAustralia personnel, Accredited Service Providers and contractors to EnergyAustralia,
for recording site specific details of infrastructure and services work.
Overhead and underground infrastructure work and network additions and alterations must
be notified as completed, by the Project Manager or Supervisor.
As-built alterations to design plans must be highlighted on the plans and approved by the
EnergyAustralia Network Inspector or EnergyAustralia Project Manager/Co-ordinator.
All completed plans and field recordings, and other documents which record network
additions and alterations, including, but not limited to:
NS 201
© EnergyAustralia.
Revision History
Initial issue: 24/11/2006
Document Control
UNCONTROLLED COPY