You are on page 1of 1

Siemens Pte Ltd

Jln Tenggiri No. 1


Batu Ampar

TRANSMITTAL-DOCUMENT

Project Code 22OP-01023 TR No TR-01023-SIE-MSP-00012


SubContractor PT MEGA SYNERGY POWERINDO Date 16 Aug 2019
Package FABRICATION - E&I Response By Date 19 Aug 2019
PO Number 2AG-PENDING Attention To WINSTON@MSPOWERINDO.COM

Construction Client Rev Ver. Issue Equipment


S/N Document Title Remarks
Drawing Number Doc. No. No. No. Purpose Tag No.

IFC - Issued
076328C-SI-89- E AND I - CABLE
1 0 1 for False
E-XX-0009 SCHEDULE
Construction
2

10

11

12

LEGEND: NOTE :
Code 1 : Revise and Resubmit If Client Comments = Yes, please submit as next revision,version 1.
Code 2 : To be issued as Final Provided comments are incorporated If Client Comments = No, Please submit as current revision, next
Code 3 : No Comments - Final issue version.

Prepared By Arman - Digitally signed by - Arman


ReceivedBy
DN: cn=- Arman, o=Siemens-
Partner,
email=arman.ext@siemens.com
Reason: Acknowledgement
Date: 2019.08.16 12:44:40
+08'00'

Date 16 Aug 2019 Date