Sr. No Activities Time November-2016 December-2016 January-2017 February-2017 March-2017 April-2017


1 PFD , P&ID Finalisation & approval 1 week
2 Layout Preparation & approval 1 week
3 Capex preparation 1 week
4 Capex approval 1 week
5 Detailing & approval
Emulsifier Storage tanks Data Sheet preparation & approval 1 week
Pump data sheet preparation & approval 1 week
Hot water bath data sheet preparation & approval 1 week
6 Process & Layout HAZOP 1 week
7 Project Buildup in SAP
PR creation for major equipments & inquiry floating 1 week
PR creation for the piping, fittings & miscelleneous items 1 week
PR creation for the Structural material 1 week
PR creation for the Electrical material 1 week
PR creation for the Utility items 1 week
PR creation for the Civil materails 1 week
PR creation for the Piping fabrication & erection work 1 week
Service PR for the major activities 1 week
Service PR for the miscelleneous activities 1 week
9 Quotation review, comparision, negotiation & Ordering
Major equipments 1 week
Pumps 1 week
Instruments 1 week
Electrical items 1 week
Structural material 1 week
Civil Material 1 week
13 Delivery time
Emulsifier Storage Tank 10 weeks
Hot water bath 8 weeks
Load cells 12 weeks
ON-OFF valve 10 weeks
Pumps 6 weeks
Motors 4 weeks
Structural material 2 weeks
Civil Material 1 week
Cable & Cable Tray 3 weeks
Piping Material 4 weeks
9 Civil Work
Site Clearance & Safety Permission 1 week
Foundation work for the storage tanks & Dyke Wall preparation 4 weeks
Gantry Column foundation for Pipe rack 2 weeks
04 Nos. Pump foundation 2 weeks
Earthing pit 1 week
10 Structural work
Load Cell Frame fabrication for 03 nos Emulsifier Storage Tanks 1 week
Pipe rack fabrication 2 weeks
11 Plant readiness for the hot work 1 week
12 Modification Job
V-101, V-201 & V-301 Isolation, Piping Tagging & Dismantling 1 week
04 Nos. 1 Kl Batch Tank Isolation, Piping Tagging & Dismantling 1 week
Structural work for the lifting arrangement for batch tank & vessels 1 week
Lug fabrication for the installation of the load cell for tanks & vessels 3 weeks
14 Equipment Erection
Erection of Emulsifier Storage Tanks 1 week
Installation of Pumps 1 week
15 Piping fabrication & Erection
Process piping 3 weeks
Utility piping 1 week
16 Electrical work
Cable tray fabrication & installation 1 week
Cable laying 1 week
Cable connection to panel & termination 3 days
Floor lighting with fabrication 3 days
Earthing bonding 1 week
Load Cell Connection 5 days
17 Instrumentation
SOP preparation for the logic development 3 days
Logic development in SCADA 2 weeks
Instrument cable tray fabrication & installation 01 week
Cable lying on Cable Tray 04 days
Termination between Panel to JB & JB to Field 04 days
ON-OFF valve installation, connection & termination 1 week
Pre visit of Engineer For Load Cell Installation clearance 1 day
Work on recommendation of site engg. For Load Cell installation 2 days
Load Cell installation,calibration & commissioning for the Emulsifier Storage tanks 2 weeks
Load Cell installation,calibration & commissioning for the Batch Tanks 2 weeks
Load Cell installation,calibration & commissioning for the Vessels 10 days
Panel & logic testing SCADA 3 days
Field Instruments Loop testing 3 days
Dry run trial 1 day
18 Pre-commissioning activity 3 days
19 Commissioning