You are on page 1of 32

Periodic Maintenance Work of the Project, "4/6 laning o

62+295 of NH-11 under NHDP Phase IIIA in t

INVOICE NO. OPAPL/Bharatpur/SC-WO/Maint/2019-20/RA NO.09/

NAME OF THE CONCESSIONER:-M/s. ORIENTAL PATHWAYS (AGRA) PVT

Address of the Company :- PLOT NO 871, NAGLA BHAMRA, POST - CH


POST- CHICHANA, Bharatpur, Rajasthan, 321203.

NAME OF THE EPC CONTRACTOR :- M/S. PRAKASH ASHAPLATING


TOLL HIGHWAYS (I) LTD.

Address of the Company :- 242, Subbash Nagar, Udaipur,Rajasthan,31

Invoice Period UP to 01.10.

S.No Description

A Total Amount Based on Works Executed

a) Work done

c) SGST 6 %.

d) CGST 6 %.

B Sub Total A {1A+1B+2}

C
D Recoveries

a) Retention Money.

b) Mobilization Advance.

Sub Total D

Net Payable(C+D)

This Bill Amount In Words: (Rupees One Crore Forty Nin

M/s. Oriental Pathways (Agra) Pvt Ltd.


ct, "4/6 laning of Agra-Bharatpur BOT Project from Km.17+756 to
P Phase IIIA in the State of Uttar Pradesh & Rajasthan."

019-20/RA NO.09/RAJ09 Date :- 08.11..2019

THWAYS (AGRA) PVT LTD. GSTN NO :-08AAACO7826R1ZP

HAMRA, POST - CHICHANA,

ASH ASHAPLATINGS AND


GSTN NO :-08AABCP0398N1ZY.

aipur,Rajasthan,313001

eriod UP to 01.10.2019 TO 31.10.2019

Upto Date Work Done


Previous Paid Amount This IPC Amount
Amount
(Rs)* (Rs)
(Rs)

INR 251,793,458.13 INR 250,068,846.35 INR 1,724,611.78

INR 251,793,458.13 INR 250,068,846.35 INR 1,724,611.78

INR 15,107,608.00 INR 15,004,131.00 INR 103,477.00

INR 15,107,608.00 INR 15,004,131.00 INR 103,477.00

INR 282,008,674.13 INR 280,077,108.35 INR 1,931,565.78


INR 282,008,674.13 INR 280,077,108.35 INR 1,931,565.78

INR 282,008,674.13 INR 280,077,108.35 INR 1,931,565.78

ne Crore Forty Nine Lakhs Forty Nine Thousand Eight Hundred Fifty Nine only)

For Prakash Asphaltings & Toll Highways (I) Limited.


NAME OF THE CONCESSIONER :- ORIENTAL PATHWAY
NAME OF THE CONTRACTOR :- PRAKASH ASPHALTINGS AND T
AGRA - BHARATPUR BOT PROJECT
SUB CONTRACT WORK ORDER- "For works to be executed in the state
1 Original Work Order No. & Date OPAPL/Bharatpur/SC-WO/Maint/2018-19/01 dated 01-Dec-2018.

2 Type of Sub Contract


Periodic Maintenance Work of the Project, "4/6 laning of A
under NHDP Phase IIIA in the State of Uttar Pradesh & Ra
3 SC Work Period - From and To 1-Dec-18 To 30-Jun-19 7 Months

4 Name of the Sub Contractor M/s Prakash Asphalting & Toll Highways (India) Lt
5 Address of the Sub Contractor 76, Mall Road, Mhow, Indore-453341.
6 PAN # of Sub Contractor. AABCP0398N.
7 GST # of Sub Contractor. 08AABCP0398N1ZY.
8 Period of Work. 01.11.2019 To 31.11.2019
9 BILL No 10
SUMMARY BILL OF QUANTITIES UPTO LAST BILL

Sl Item Description Unit Quantity Rate Amount (RS) Quantity


Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.25 kg per sqm on the existing
1 bituminous/granular surface cleaned with mechanical broom as directed SQM 3 57 006 16 57 12 092 400,700.83
by authorized representative of OPAPL.

Carrying out repair to POT Holes and necessary patch repair work to
2 existing Bituminous carriageway as per MORTH (Revision 5th) specification SQM 30 000 800 2 40 00 000 32,075.08
Clause 3004.

Milling of existing flexible pavement up to 50 mm depth and finished to


3 uniform level by Milling machine (Wirtgen Sensor Milling Machine) as SQM 30 000 48 14 40 000 54,250.90
directed by authorized representative of OPAPL.

Providing & laying Bituminous Concrete wearing course using refinery


produced crumb rubber modified bitumen (CRMB-60) complete as per
approved overlay plan / drawing and MORT&H (Fifth Revision)
Specifications Clause 507. The BC shall be laid by Full Carriageway
4 width Sensor Paver with Big ski Multiplex levelling system consisting of 6 Cum 15 333 11 900 18 24 66 667 15,171.71
ultrasonic sensors / 2 Control box / connecting cables etc.

Providing and laying of Microsurfacing (Type-III, 6 to 8mm) composed of


modified bitumen emulsion, mineral aggregate, water and necessary
additives (if needed) proportioned, mixed and uniformly spread over a
5 SQM 50 667 140 70 93 333 49180.57
properly prepared surface for surface treatment of pavement as per
MORTH (Revision 5th) specification clause 514 and IRC SP 81-2008.

Providing & laying pavement marking with hot applied thermoplastic


6 paints conforming to ASTM D36/BS 3262 (Part - 1) as per drawing & SQM 15 556 550 85 55 556 4716.84
MORT&H (Revision 5th) Specifications Clause 803.
Repair/ Filling of Earthen shoulder in main carriageway, service road,
major/ minor junctions & rest area, satisfying the requirements of
7 minimum soaked CBR value (10%) as indicated in the of modified proctor SQM 78 562 40 31 42 471 64700.00
density with all leads & lIfts all complete as per drawings and MORT&H
specifications clause 3003.

Painting of Kerb / Crash barrier with two or more coats of Synthetic


8 enamel paint including a base coat of cement primer. Km 39.28 60 000 23 56 800 35.35
Painting of Structure Parapet/Retaining wall with two or more coats of
9 Synthetic enamel paint. SQM 3,100.00 110 799.83

10 Median kerb Height Raising by concrete M-20 grade. RM - 330 11,430.00

11 WMM Work Median Opening Cum - 1 261 30.00

12 CRMB Work For Median Opening Cum - 957 24.00

13 PGR PAINTING RM - 250 652.00

14 DBM LAYING CUM - 10 200 1,625.31

Total Amount of Work Order in Rs. 234,766,919

Submitted by For
M/s Prakash Asphalting & Toll Highways (India) Ltd.

Authorised Signatory
AL PATHWAYS (AGRA) PVT LTD
TINGS AND TOLL HIGHWAYS (I)LIMITED
OT PROJECT
in the state of Rajasthan."(Bharatpur Section)"
01-Dec-2018.

"4/6 laning of Agra-Bharatpur BOT Project from Km.17+756 to 62+295 of NH-11


Pradesh & Rajasthan."

ays (India) Ltd.

UPTO LAST BILL FOR THIS BILL UPTO DATE

Amount (RS) Quantity Amount (RS) Quantity Amount (RS)


6,411,213.28 1,728.59 27,657.44 402,429.42 6,438,870.72

25,660,064.00 - - 32,075.08 25,660,064.00

2,604,043.20 1,728.59 82,972.32 55,979.49 2,687,015.52

180,543,407.07 - - 15,171.71 180,543,407.07

6,885,279.80 - - 49,180.57 6,885,279.80

2,594,262.00 - - 4,716.84 2,594,262.00

2,588,000.00 100.00 4,000 64,800.00 2,592,000.00

2,120,700.00 4.52 2 70 900 39.86 2,391,600.00


87,981.30 1,512.22 1 66 344 2,312.05 254,324.95

3,771,900.00 - - 11,430.00 3,771,900.00

37,830.00 - - 30.00 37,830.00

22,968.00 - - 24.00 22,968.00

163,000.00 - - 652.00 163,000.00

16,578,197.70 114.97 11 72 738 1,740.29 17,750,936.07

250,068,846 1,724,611.78 251,793,458.13

Verified and Approved By


M/s. Oriental Pathways (Agra) Pvt Ltd (OPAPL)

Authorised Signatory
Name of Concessioner :- M/s.Oriental Pathways (Agra) Pvt. Ltd.

Name of EPC Contractor :- M/S. Prakash Asphaltings & Toll Highways (I) Ltd.

MEASUREMENT FOR KERB PAINTING

PERIOD FROM 01-11-2019 To 30-11-2019


Chainage Measurment
SR.
Date Side Length
No. From To Length Depth+Top
(KM)

1 9/Nov/19 46300 46400 LHS 100 0.35 35

2 9/Nov/19 46300 46400 RHS 100 0.34 34

3 8/Nov/19 49550 49600 RHS 50 0.35 17.5

4 8/Nov/19 49600 49700 RHS 100 0.35 35

5 8/Nov/19 49700 49750 RHS 50 0.35 17.5

6 8/Nov/19 49750 49800 RHS 50 0.36 18

7 8/Nov/19 49800 49850 RHS 50 0.36 18

8 8/Nov/19 49850 49900 RHS 50 0.35 17.5

9 8/Nov/19 49900 50000 RHS 100 0.35 35

10 7/Nov/19 50000 50100 RHS 100 0.35 35

11 7/Nov/19 50100 50200 RHS 100 0.34 34

12 7/Nov/19 50200 50250 RHS 50 0.35 17.5

13 7/Nov/19 50250 50300 RHS 50 0.33 16.5

14 7/Nov/19 50300 50400 RHS 100 0.35 35


15 7/Nov/19 50400 50450 RHS 50 0.34 17

16 7/Nov/19 50450 50500 RHS 50 0.37 18.5

17 2/Nov/19 50505 50550 RHS 45 0.37 16.65

18 2/Nov/19 50505 50555 LHS 50 0.36 18

19 2/Nov/19 50550 50555 RHS 5 0.34 1.7

20 2/Nov/19 50585 50600 LHS 15 0.3 4.5

21 2/Nov/19 50585 50600 RHS 15 0.33 4.95

22 2/Nov/19 50600 50615 LHS 15 0.35 5.25

23 2/Nov/19 50600 50615 RHS 15 0.38 5.7

24 2/Nov/19 50615 50640 LHS 25 0.35 8.75

25 2/Nov/19 50615 50640 RHS 25 0.39 9.75

26 1/Nov/19 50635 50700 RHS 65 0.38 24.7

27 1/Nov/19 50700 50750 RHS 50 0.36 18

28 1/Nov/19 50750 50800 RHS 50 0.35 17.5

29 2/Nov/19 50800 50850 RHS 50 0.35 17.5

30 2/Nov/19 50850 50900 RHS 50 0.32 16

31 2/Nov/19 50900 50950 RHS 50 0.33 16.5

32 2/Nov/19 50950 51000 RHS 50 0.32 16

33 7/Nov/19 51000 51100 RHS 100 0.33 33


34 7/Nov/19 51100 51130 RHS 30 0.34 10.2

35 7/Nov/19 51300 51400 RHS 100 0.34 34

36 7/Nov/19 51400 51500 RHS 100 0.35 35

37 7/Nov/19 51500 51550 RHS 50 0.34 17

38 6/Nov/19 51550 51600 RHS 50 0.35 17.5

39 6/Nov/19 51600 51700 RHS 100 0.34 34

40 6/Nov/19 51700 51750 RHS 50 0.34 17

41 6/Nov/19 51740 51800 LHS 60 0.34 20.4

42 6/Nov/19 51750 51800 RHS 50 0.42 21

43 6/Nov/19 51825 51850 RHS 25 0.41 10.25

44 6/Nov/19 51825 51850 LHS 25 0.35 8.75

45 6/Nov/19 51850 51870 RHS 20 1.2 24

46 6/Nov/19 51850 51870 LHS 20 1.2 24

47 6/Nov/19 51870 51900 RHS 30 0.34 10.2

48 6/Nov/19 51900 51950 RHS 50 0.36 18

49 6/Nov/19 51950 52000 RHS 50 0.35 17.5

50 6/Nov/19 52000 52050 RHS 50 0.35 17.5

51 6/Nov/19 52050 52150 RHS 100 0.35 35

52 6/Nov/19 52150 52250 RHS 100 0.35 35


53 6/Nov/19 52270 52300 RHS 30 0.34 10.2

54 6/Nov/19 52300 52350 RHS 50 0.36 18

55 5/Nov/19 52350 52400 RHS 50 0.34 17

56 5/Nov/19 52400 52450 RHS 50 0.42 21

57 5/Nov/19 52450 52500 RHS 50 0.34 17

58 5/Nov/19 52500 52550 RHS 50 0.35 17.5

59 5/Nov/19 52550 52600 RHS 50 0.34 17

60 5/Nov/19 52600 52700 RHS 100 0.36 36

61 5/Nov/19 52700 52800 RHS 100 0.35 35

62 4/Nov/19 52800 52850 RHS 50 0.34 17

63 4/Nov/19 52850 52900 RHS 50 0.35 17.5

64 4/Nov/19 52850 52900 LHS 50 0.34 17

65 4/Nov/19 52925 52950 RHS 25 0.34 8.5

66 4/Nov/19 52925 52950 LHS 25 0.34 8.5

67 4/Nov/19 52950 53000 RHS 50 0.35 17.5

68 4/Nov/19 52950 53000 LHS 50 0.34 17

69 4/Nov/19 53000 53050 RHS 50 0.36 18

70 4/Nov/19 53250 53300 RHS 50 0.34 17

71 4/Nov/19 53300 53400 RHS 100 0.33 33


72 4/Nov/19 53400 53450 RHS 50 0.34 17

73 4/Nov/19 53450 53500 RHS 50 0.35 17.5

74 4/Nov/19 53500 53600 RHS 100 0.35 35

75 3/Nov/19 53600 53650 RHS 50 0.33 16.5

76 3/Nov/19 53650 53700 RHS 50 0.31 15.5

77 3/Nov/19 53700 53750 RHS 50 0.3 15

78 3/Nov/19 53750 53800 RHS 50 0.32 16

79 3/Nov/19 53800 53850 RHS 50 0.34 17

80 3/Nov/19 53850 53900 RHS 50 0.34 17

81 10/Nov/19 60080 60100 LHS 20 0.35 7

82 10/Nov/19 60080 60100 RHS 20 0.34 6.8

83 10/Nov/19 60120 60150 RHS 30 0.35 10.5

84 10/Nov/19 60120 60150 LHS 30 0.34 10.2


Grand Total Area. (KM) 4.52
) Pvt. Ltd.

Highways (I) Ltd.

Remark.
Name of Concessioner :- M/s.Oriental Pathways (Agra) Pvt. Ltd.

Name of EPC Contractor :- M/S. Prakash Asphaltings & Toll Highways (I) L

MEASUREMENT FOR DBM Laying


PERIOD FROM 01-11-2019 To 30-11-2019
Chainage Measurment
SR.
Date Side
No. From To Length Width Sqm. Depth

1 12/Nov/19 48927 48990 LHS 63 3.45 217.35 0.07

2 12/Nov/19 49456.5 49620 LHS 163.5 3.20 523.2 0.07

3 18/Nov/19 35049 35106 RHS 57 3.20 182.4 0.07

4 24/Nov/19 43875 43926.8 RHS 51.8 2.90 150.22 0.07

5 24/Nov/19 43964.2 43981.5 RHS 17.3 2.90 50.17 0.07

6 24/Nov/19 43669.5 43787 RHS 117.5 2.90 340.75 0.07

7 24/Nov/19 44008 44050 RHS 42 3.65 153.3 0.07

8 24/Nov/19 44139 44150 RHS 11 3.00 33 0.07

9 24/Nov/19 44050 44073 RHS 23 3.40 78.2 0.07


Grand Total QTY. (CUM)
Agra) Pvt. Ltd.

Toll Highways (I) Ltd.

ying
019
t
Qty. Remark.
Cum

DBM
14.13
DBM
36.62
DBM
11.86
DBM
9.76
DBM
3.26
DBM
22.15
DBM
9.96
DBM
2.15
DBM
5.08
115.0
Name of Concessioner :- M/s.Oriental Pathways (Agra) Pvt. Ltd.

Name of EPC Contractor :- M/S. Prakash Asphaltings & Toll Highways (I) Ltd.

MEASUREMENT FOR DBM Laying Tack Coat


PERIOD FROM 01-11-2019 To 30-11-2019

SR. Chainage Measurment


Date Side
No. From To Length Width Sqm.

1 12/Nov/19 48927 48990 LHS 63 3.45 217.35


2 12/Nov/19 49456.5 49620 LHS 163.5 3.20 523.2
3 18/Nov/19 35049 35106 RHS 57 3.20 182.4
4 24/Nov/19 43875 43926.8 RHS 51.8 2.90 150.22
5 24/Nov/19 43964.2 43981.5 RHS 17.3 2.90 50.17
6 24/Nov/19 43669.5 43787 RHS 117.5 2.90 340.75
7 24/Nov/19 44008 44050 RHS 42 3.65 153.3
8 24/Nov/19 44139 44150 RHS 11 3.00 33
9 24/Nov/19 44050 44073 RHS 23 3.40 78.2
Grand Total QTY. (CUM) 1728.6
(Agra) Pvt. Ltd.

& Toll Highways (I) Ltd.

Tack Coat
2019

Remark.

DBM

DBM

DBM

DBM

DBM

DBM

DBM

DBM

DBM
Name of Concessioner :- M/s.Oriental Pathways (Agra) Pvt. Ltd.

Name of EPC Contractor :- M/S. Prakash Asphaltings & Toll Highways (I) Ltd.

MEASUREMENT FOR DBM MILLING


PERIOD FROM 01-11-2019 To 30-11-2019

SR. Chainage Measurment


Date Side
No. From To Length Width Sqm.
1 12/Nov/19 48927 48990 LHS 63 3.45 217.35
2 12/Nov/19 49456.5 49620 LHS 163.5 3.20 523.2
3 18/Nov/19 35049 35106 RHS 57 3.20 182.4
4 24/Nov/19 43875 43926.8 RHS 51.8 2.90 150.22
5 24/Nov/19 43964.2 43981.5 RHS 17.3 2.90 50.17
6 24/Nov/19 43669.5 43787 RHS 117.5 2.90 340.75
7 24/Nov/19 44008 44050 RHS 42 3.65 153.3
8 24/Nov/19 44139 44150 RHS 11 3.00 33
9 24/Nov/19 44050 44073 RHS 23 3.40 78.2
Grand Total QTY. (CUM) 1728.6
(Agra) Pvt. Ltd.

& Toll Highways (I) Ltd.

LLING
2019

Remark.

DBM
DBM
DBM
DBM
DBM
DBM
DBM
DBM
DBM
Name of Concessioner :- M/s.Oriental Pathways (Agra) Pvt. Ltd.

Name of EPC Contractor :- M/S. Prakash Asphaltings & Toll Highways (I) Ltd.

MEASUREMENT FOR SHOULDER

PERIOD FROM 01-11-2019 To 30-11-2019

Chainage
Length Width
SR. No. Date Side Area SQM
From To (Mt.) (Mt.)

1 10/Nov/19 45400 45450 LHS 50 2 100

Grand Total QTY. (CUM) 100.0


vt. Ltd.

ghways (I) Ltd.

Remarks
Name of Concessioner :- M/s.Oriental Pathways (Agra) Pvt. Ltd.

Name of EPC Contractor :- M/S. Prakash Asphaltings & Toll Highways (I) Ltd.

MEASUREMENT FOR STRUCTURE PARAPET/RETAINING WALL PAINTING

PERIOD FROM 01-11-2019 To 30-11-2019


Measurment
SR. No. Date Chainage Side Remark.
Length Depth+Top Sqm.
1 6-Nov-19 42640 LHS 2.1 1.45 3.045

2 6-Nov-19 42640 RHS 2.1 1.45 3.045

3 6-Nov-19 43040 LHS 4.6 1.45 6.67

4 6-Nov-19 43040 RHS 4.6 1.45 6.67

5 6-Nov-19 43245 LHS 5.6 1.45 8.12

6 7-Nov-19 43245 RHS 5.6 1.45 8.12

7 7-Nov-19 43640 LHS 4.6 1.45 6.67

8 7-Nov-19 43640 RHS 4.6 1.45 6.67

9 7-Nov-19 44080 LHS 5.6 1.45 8.12

10 7-Nov-19 44080 RHS 4.6 1.45 6.67

11 8-Nov-19 44440 LHS 5.6 1.45 8.12

12 8-Nov-19 44440 RHS 4.6 1.45 6.67

13 8-Nov-19 44840 LHS 4.6 1.45 6.67

14 9-Nov-19 44840 RHS 4.6 1.45 6.67

15 9-Nov-19 45250 LHS 4.1 1.45 5.945

16 9-Nov-19 45250 RHS 4.1 1.45 5.945

17 9-Nov-19 45750 LHS 3.1 1.45 4.495

18 9-Nov-19 45750 RHS 3.6 1.45 5.22

19 10-Nov-19 45900 LHS 8.6 1.45 12.47

20 10-Nov-19 45900 RHS 8.6 1.45 12.47

21 10-Nov-19 46460 LHS 3.1 1.45 4.495

22 11/Nov/19 46460 RHS 3.1 1.45 4.495

23 11/Nov/19 46760 LHS 3.1 1.45 4.495

24 11/Nov/19 46760 RHS 3.1 1.45 4.495


25 11/Nov/19 46850 LHS 5.1 1.45 7.395

26 11/Nov/19 46850 RHS 5.1 1.45 7.395

27 11/Nov/19 46950 LHS 4.6 1.45 6.67

28 11/Nov/19 46950 RHS 4.6 1.45 6.67

29 11/Nov/19 47575 LHS 8.6 1.45 12.47

30 11/Nov/19 47575 RHS 8.6 1.45 12.47

31 11/Nov/19 47870 LHS 4.1 1.45 5.945

32 11/Nov/19 47870 RHS 4.6 1.45 6.67

33 11/Nov/19 47970 LHS 4.1 1.45 5.945

34 11/Nov/19 47970 RHS 4.4 1.45 6.38

35 12/Nov/19 48270 LHS 4.1 1.45 5.945

36 12/Nov/19 48270 RHS 4.1 1.45 5.945

37 12/Nov/19 48950 LHS 4.1 1.45 5.945

38 12/Nov/19 48950 RHS 4.1 1.45 5.945

39 12/Nov/19 49668 LHS 4.1 1.45 5.945

40 12/Nov/19 49668 RHS 4.1 1.45 5.945

41 12/Nov/19 50275 LHS 8.1 1.45 11.745

42 12/Nov/19 50275 RHS 8.1 1.45 11.745

43 12/Nov/19 50430 LHS 4.1 1.45 5.945

44 12/Nov/19 50430 RHS 4.1 1.45 5.945

45 12/Nov/19 50600 LHS 4.1 1.45 5.945

46 13/Nov/19 50600 RHS 4.1 1.45 5.945

47 13/Nov/19 50760 LHS 4.1 1.45 5.945

48 13/Nov/19 50760 RHS 4.1 1.45 5.945

49 13/Nov/19 51035 LHS 3.1 1.45 4.495

50 13/Nov/19 51035 RHS 3.1 1.45 4.495

51 13/Nov/19 51242 RHS 17.6 1.25 22 Median

52 13/Nov/19 51242 RHS 17.6 1.25 22

53 13/Nov/19 51483 LHS 5.6 1.45 8.12

54 13/Nov/19 51483 RHS 12.6 1.45 18.27

55 13/Nov/19 51861 RHS 18.2 1.2 21.84


56 13/Nov/19 52258 RHS 19.7 1.2 23.64

57 13/Nov/19 52258 LHS 16.6 1.45 24.07

58 13/Nov/19 52825 LHS 4.1 1.45 5.945

59 13/Nov/19 52825 RHS 4.1 1.45 5.945

60 14/Nov/19 53170 LHS 3.1 1.45 4.495

61 14/Nov/19 53170 RHS 3.1 1.45 4.495

62 14/Nov/19 56067 LHS 4.6 1.45 6.67

63 14/Nov/19 56067 RHS 4.6 1.45 6.67

64 14/Nov/19 56225 LHS 317 1.2 380.4

65 14/Nov/19 56225 RHS 317 1.2 380.4

66 14/Nov/19 56225 LHS 15.6 1.2 18.72 Median

67 14/Nov/19 56225 RHS 15.6 1.2 18.72 Median

68 14/Nov/19 56225 LHS 4 1.3 5.2 Medain Wall Agra

69 14/Nov/19 56225 RHS 4 1.3 5.2 Medain Wall Bharatpur

70 15/Nov/19 56900 LHS 6.6 1.45 9.57

71 15/Nov/19 56900 RHS 7.6 1.45 11.02

72 15/Nov/19 58150 LHS 4.1 1.45 5.945

73 15/Nov/19 58150 RHS 4.6 1.45 6.67

74 15/Nov/19 59940 LHS 6.1 1.45 8.845

75 15/Nov/19 59940 RHS 7.6 1.45 11.02

76 15/Nov/19 60104 LHS 11.7 1.2 14.04

77 15/Nov/19 60104 RHS 19 1.2 22.8

78 15/Nov/19 60104 LHS 11.7 1.2 14.04 Median

79 15/Nov/19 60104 RHS 19 1.2 22.8 Median

80 16/Nov/19 61130 LHS 5.7 1.45 8.265

81 16/Nov/19 61130 RHS 6.1 1.45 8.845

82 16/Nov/19 61200 LHS 4.7 1.45 6.815

83 16/Nov/19 61200 RHS 6.1 1.45 8.845

84 16/Nov/19 61650 LHS 9.2 1.45 13.34

85 16/Nov/19 61650 RHS 12.6 1.45 18.27

Grand Total Area. (SQM) 1512


Wall Bharatpur