Professional Documents
Culture Documents
Supplemental information
ITER
TAPB Excavation Slopes
Design Check
October 2019
ITER
TAPB Excavation slope – Design Check
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
CONTENTS
1. INTRODUCTION....................................................................................................... 1
1.1 CHECK REQUIREMENTS .............................................................................. 1
5. LOADING .................................................................................................................. 2
APPENDICES
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
1. INTRODUCTION
The scope of the report is to undertake a review and check of the design of
soil nailed slopes forming the excavation for the construction of the TAPB
with respect to the stability of these slopes under the action of heavy
transport traffic. The review can be considered as a Category II check
since independent analyses has been undertaken.
4. GROUND MODEL
Due to the variation in level of the underlying limestone strata the depth of
the platform varies over the area of interest. Overlying the competent
limestone is a variable thickness of fractured limestone (occasionally not
recorded) over which has been placed the platform fill.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Critical sections for analysis have been identified as shown on the sketch
below and you can populate table 1 after your review of the site
investigation information.
Area
represented by
Profile 1
Area
represented by
Profile 2
Figure 1. Areas for selection of critical sections for analysis. Profiles 1 and
2 should be derived to be representative of area indicated.
5. LOADING
The loading is provided by the wheel loads from the heavy haulage trailer.
It is understood that the trailer shall distribute the loads from the
transported item evenly over the length of the trailer such that the applied
loading can be represented by a uniform surcharge. This uniform
surcharge can be modified to cater for rocking motion by using a 4/3
increase for the line of wheels nearest to the excavation edge and applying
an increased load intensity over the first wheel group (quarter of the ud
load strip).
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Based on the above loading the following loads were used in the analysis
presented here.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
If the rocking load is spread over the loaded area a uniform surcharge load
of approximately 50 kPa should be used.
For all loading cases the load is applied at a specified distance from the
crest of the slope. The sensitivity of the slopes to this offset distance can
be investigated, however the distance recommended by the Contractor of
X = 4.5m (refer to figure below) is to be used in the check analysis.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Turning x
p1 = 83.8 kN/m 1.13
p2 = 55.8 kN/m
q1
Standard q2
q1 = 63.2 kPa
q2 = 47.4 kPa
Turning
q1 = 71.2 kPa
q2 = 47.4 kPa
x 3B/4
B/4
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Turning x
p1 = 71.4 kN/m 1.13
p2 = 47.6 kN/m
q1
Standard q2
q1 = 53.9 kPa
q2 = 40.45 kPa
Turning
q1 = 60.6 kPa
q2 = 40.45 kPa
x 3B/4
B/4
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Two approaches can be adopted to check the design of the soil nailed
slope. The first approach is a permissible stress method (traditional
approach) where an overall global factor of safety is derived. The
selection of a permissible global safety factor should consider the
consequences of a failure, and as such typical values normally associated
with temporary works are not considered appropriate. A minimum value of
1.5 is recommended.
Combination 1 Combination 2
(DA1-1) (DA1-2)**
Definition
Actions (A) Multiply action by partial factor below
Permanent 1.35 1.0
unfavourable
Permanent favourable 1.0 1.0
Variable unfavourable 1.5 1.3
Variable favourable 0.0 0.0
Materials (M) Divide characteristic strength by partial factor below
Tan φ 1.0 1.25
c’ 1.0 1.25
Su 1.0 1.4
UCS 1.0 1.4
Bulk density 1.0 1.0
Resistances (R)* Divide by partial factor below
Overall stability 1 1
Bearing capacity 1 1
Sliding 1 1
Bond Stress, qs 18 1.8**
* generally the most critical case
** as per recommendations for Clouterre
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Platform fill
Fractured Limestone
Competent Limestone
Pull out test data is not available to evaluate the site-specific pull-out
resistance or the proposed anchors. Consequently, for the purposes of
this analysis the unit bond stress of the anchors should be derived from
published literature and correlations as presented in Appendix B and
summarised in Table 7 below.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Clouterre (1991)
FHWA (2015)
(used in analysis)
Calculation
(BS8006)**
** bond stress is dependent on depth and partial factor of 1.0 should be applied to
determine characteristic value
The soil nails and slope geometry is based on the Contractor design is
summarised in the following Table 9. It should be noted that your check
analysis should use independently derived soil parameters, bond stress
and ground profiles discussed earlier.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
11. CONCLUSIONS
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Based on site investigations performed at the ITER site the ground model can be
idealised to a platform constructed from compacted cohesionless material which
generally overlies fractured limestone or competent limestone. The Jacobs
Geotechnical Interpretative Report states that all the fill material can be described
as medium dense, dense or very dense.
The results of SPT tests carried out in the fill indicate that the density is
independent of depth as would be expected where a fill has been placed in layers
and compacted with similar plant. The percentage of fill material tested that
returned an SPT ‘N’ value greater than 30, the limit between medium dense and
dense is 75%, and the percentage which returned an ‘N’ value of greater than 50,
the limit between dense and very dense is 45%.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
Figure A1 – corrected ‘N’ values for platform material (from Jacob’s GIR)
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
-a- -b-
-c-
Figure B.1(a) bond stress (qs) versus pressremeter limit pressure (PL) for sand, (b)
weathered rock and (c) gravel, after Clouterre 1991.
Based on the above figures the values of unit bond stress can be derived.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
The ultimate bond stress can also be derived from the results of
pressuremeter tests using the following correlation (FHWA, 2003)
(ult) = 14 PL(6-PL) where PL has units of MPa and (ult) has units of kPa.
Table B.2 Bond stress for cohesionless material from FHWA correlation
Platform Fill Fractured Limestone
PL Bond stress (ult) PL Bond stress (ult)
(MPa) (kPa) (MPa) (kPa)
2.49 (min) 122 2.2 117
3.6 (char) 121 2.8 126
4.78* (max) 70 3.56 121
*single result
The application of the FHWA relationship used to derive the value of bond
stress for the fractured limestone in Table B.2 assumes that this material
can be treated as a gravel. This may yield overly conservative values of
bond stress.
In addition to the guidelines present in Table B.2, rock bond strength can
be estimated as 10% of the UCS strength or rock up to UCS = 4MPa but
not more than 300-400 kPa .
The FHWA manual also provides tables of typical ranges of bond stress as
reproduced below in Table B.3.
CE631 Coursework
ITER
TAPB Excavation slope – Design Check
CE631 Coursework