This week we begin a
five-partserieson
developments in steel
and concrete
construction. Here,
Peter Trebiloock, Mark
Lawsonand Graham
Owens focus on long-
span structures for
commercial buildings.
1 Composite construction has
‘become the norm for medium: to
biti commercial buildings.
2 Space planning modules donot
‘change mach despite increasing
spans.
Peter Trebieockisan associate
architect at BDP and eensaltant
architect toSCI (he Stel
Construction Tstitue,
Mark Lavon eresearch manager
forbuildings at SCL
Graham Owen is acting eodrector
ofSCl
ak
soe ee
Init, St .
STRUCTURAL DEVELOPMENTS
1 STEEL FRAME DESIGN
Too many architects leave the determination
ofall structural matters to their consulting
engineer when, with some general
knowledge, valuable design timeeanbe
saved and eto spent inpursing
inappropriate or inadequate solutions
minimised. The aimaf this article isto
provide architects with guidanceon the
prime factors tobe considered, the options
available and the implications ofa given
choice of structure.
Composite construction
Composite construction entails the use of
sieel beams acting structurally withan
insitu lightly reinforced concrete slab o
steel decking used as permanent formwork.
Shear connectors are often used to develop
composite action between the conerete slab
and thesteel beams, Allmaterials act
together ‘compositely’ once the concrete has
gained sufficient strength, toprovidea
strong, efficient method of floor
construction, 1.
‘Today, over 50 per cent ofall eommercial
buildings are of eomposite construction
including over 80 per cent of buildings of five
storeys orhigher. The total office and retail
floorspace created inthis type of
construction is probably some 20 million sqm
overtthe past eight years.
‘The main reasons for using composite
construction in most instances are economic.
Faster erection facilitates earlier completion
which in turn reduces interest charges and
advances rental income. There can also be
savings in materials. A composite beam may
betwice the strength of the equivalent
non-composite beam in conventional
steelwork, but up to four times stiffer. This
means that shallower structural depths ean
be achieved using composite construction
Thispermits lower storey heights and
subsequent savingsin cladding costs or
rakes more room available for services
Within the same overall oor-to-floor height.
Although comparative design
demonstrates that savingsin steel weight
relative tonon-composite construction ean
'be80 t050 per cent, these savings do not
necessarily translate directly into overall
cost savings because of the need for shear
connectors, which arenecessary to develop
the composite action between the steel and
conerete. Nevertheless, savingsin the
overalleost of the superstructure (beams,
bs, columns) of atypieal building ean be
15.20 percent, not including the savings on
the cost ofthe external and internal fabric it
the shallower storey heightsare achieved.
Grid size
‘The choice of grid size (column spacing) is
important because although stee!is popular
due toits ability to span further than simple
reinforced concrete for the same structural
depth, costs per sq mise asthe column,
spacing increases. However, these
additional eosts may be smallin comparison
with the economic and funetional benefits
realised from greater areas of uninterrupted
useable floor space. Internal columns are
very unweleome in high-rise schemes, for
example, as they become so large in plan area
dueto high loading.
Column grids for many office
developments arein the6-9m range.
However, work patterns are evolving
rapidly due to changing commercial practice
and the advent of modern communications
and information technology, though the
1,5mmodule till dominates in space
planning terms,2. Today’sideal layout may
quickly become outdated and thereare many
iments for longer spans, particularly in
sal whenthey cabopeiove for on
modest premium, say 2t03 per cent ofthe
overall building cos.
‘A9m grid is more common today, anda
minimum standard in Stuart Lipton'srecent
schemes. Users and developers are
constantiy demanding more column-tree
space and 12-18m spansare becoming
inereasingly popular. Agents are finding.
column-free spaces easier tolet, especially in
the current market; they may well eommand
premium, A variety of structural solutions
forspans above 9m will be considered later.
Inarectangular gridit is most efficient to
design the more heavily loaded primary
beams tospan the shorterdistanees
between columns so that the depths of
A1wApmiser‘atte oat ef composite fons —
Column spacings Bux Gm grid Tem oon grid
Deck span 7 im 5.50
Seelteams 3s 46
Steel columns 10 i in
‘Trimmers, bracing, ote 4 4 4
Shear comectors 4 5 4
Eireprotection 10 2B 0
Steel decking and trimming 8 8 a
Gonerete WO) & mesh 16 16 fi
Totaly 0 units tT ant
Erectiontime(steelwork) Joo units 7 units “60 units
Construction time frame nd oor) 00 units SSunits 80
eeu
secondary and primary beams are similar.
Typical as-built costs ofthe 2
superstructure are in the range of £50-80/m'
depending on the complexity ofthe building,
Abreakdown of typical costs aid
‘construction times for composite floor
structures in medium-rise buildings is given
inthe table. The structural costs canbe up to
20per cent ofthe cost of the complete
scheme, but are typically about 15 per cent.
Composite beams
Composite beamsbehave essentially ikea
series of T-beams in which the conerete slab
acts.as the compression flangeand the
downstand sel section acts asthe tension-
resisting element. The structural connection
between the twomaterialsis made by shear
conneetors, Composite aetion serves to
increase both the strength and stiffness of
the steel section, permitting it to span
further or support heavier loads,
‘The overall structural depth not only
includes the steel section but also the
‘composite slab. For efficient design of
‘composite beamsit is often found that the
ratio of span to overal structural depthisin
the range o! 18-20. (Reinforved concrete
beamshavea 1:16-18.)
Composite decking
Thisis a profiled steel product, like roof
sheeting, but with embossments or other
‘mechanical means of improving the
conneetion between the decking and the
concrete placed on top ofit. Slab depths of
120-150mm are common today. Current
practiceisto design for the longest spans
which can be achieved without the need for
tengorary roping 3-9 mdeckspan
appears tobe the most popular,
Many deck profiles are availabe but
generally they are of two broad types -— the
Govetailand the trapezoidal. A 50!mm deep
Bflecanusalysuportiadsovera
mspan.
"The embosements or indentations inthe
profleareintended to improve the shear
Gand behaviour ofthe composite slabs. There
isno particular significance to the shape of
these embossments provided they are deep
enough toreduce the slip between the
concrete and the decking by a mechanism
Kenownas ‘mechonleal interlock.
Composite deckingis usually aid as long
sheets upto 12mlong andis fastened dows
atevery beam. Inthis way itoffers anumber
ofadvantages:
tit supports lads during construction
sitstablises the structural members and
stiffens the frame against wind loads
eit provides safe working platform
Siceasasatty net gabe ling objects
itacts as transverse reinforcement tothe
‘composite beams virtually eliminating the
Deed forlarge amounts reinforcement bars
tit dstributes shrinkagestrains, preventing
serious cracking of the concrete
‘eit develops composite action with the
onerete to resist the imposed latin
‘This formof construction ensures is
uickand easy to erect Large bundles of
Tecking can be lifted into place with limited
‘subsequent use of crane facilities. The extent
aferane use often determines the eriicl
path, soaserane use reducesso oes the
Srerallerection programine. Decking out
normally oecurschortiy after the math steel
members have been erected. Conerting is
Aone one rtivefoorstehind, aftershear
connectors, mesh reinforcement and edge
{rims have been positioned. Overall there
frefewer elementsom the etieal path, This
onstruction methodisnot very ssitiveto
the weather.
‘Shear connectors
Shear connectorsare usually 19mm in
diameter, 100mm long Studs with a formed
head and are individually welded through the
steel decking tothe steel flange by a hand-
operated welding gun, Each Weld takes
about twoto three seconds. The gun requires
2415 V 3-phase supply oramobile generator.
‘This on-site process cannot be used for
painted beams and is not reommended for
usein freezing conditions. Inssuch
circumstances the prewelding of studs may
beappropriate, Alternatively a shot-fired
connector could be used. This has the
advantage ofnot requiring site power and
can be used with painted beams. The shear
strength ofa 19mm diameter welded stud
can be up to 10tonnes compared to3.5 tonnes
forashat-fired connector, 4a-d,5.
Types of concrete
‘Twotypes of eonerete are used in the UK, a
lightweight aggregate concrete or the more
usual heavier version. The compressiye
strengths are typically 30 to 40 Nimm’. Both
canbe pumped into place, with the
lightweight conerete being easier to work.opin
ie
ea
‘acd Typical details of deck
attachment to beams. s, double
‘stud but jin; typical end
cantilever; typical edge deta
side cantilever wth stub bracket.
Site welding of studs.
‘Web openings such as this canbe
‘sed for runing services of
‘modest se,
because ofits rounded ageregate. Although
thelightweightmixisabout percent more
expensive, thisis more than offset by the
savings resulting from the weight reduetion
ofthe floor.
However, suppliers ofready-mixed
conereteare sometimes reluctant to store
the more expensive lightweight aggregate
unless they are convinced they willenjoy a
Jargeand regular demand
Design methods and codes
‘Thedesign of omposite slabsis covered in
BS5960 Part 4:1982. Ironically, BS5950
Part, which deals with composite beams,
was only published in September 1990. As
1992approaches Eurocode dis being
repared. Itlargely reflects BS 5950 Part 3
Batwillaiso cover the design of eomposite
slabs and stee! decking.
Long:span alternatives
One ofthe principal advantages ofsteel over
conerete sits ability tospan further with
Jess material. Fabricated tapered girders,
haunched beams, parallel beam
composite trusses, stub girders and
+ castellated beams may allbe viable. The
optimum solution depends on:
spans of primary and secondary beams
span/depth ratio
necessity tocontribute to sway resistance
sross-sectional area of service ducts
location of major duets across span,
ding consideration of gener
distribution routes and erassover positions
@looseness of fit between serviees and
structure, especially important for shell and
core developments where particular tenants
may require additional servicing,
Ofeourseas spansincrease sodoes the
depth ofstructure, Toavoid inereasing the
floor-to-loor depth to accommodate the
integration of services, there area number of
solutions which ineorporate these services
within the overall structuralzone. Itisnow
almost inevitable that building services will
change significantly during the life ofa
‘commercial building whereas the structure
will not and the designer should take this
fundamental prineiple into aecount when
determining structural solutions,
inwebs of composite beams
is appropriate for lightly serviced
ings, and is one of the most commonly.
used methods of incorporating services
within thestrueturalzone, 6,7. Upto 70 per
cent of the depth of the beam can be safe
used provided that openingsare located
towards the centre of the span. The
advantage of this system is that
modest sized openimgs can be formed wherestubs leaving space for secondary
beams and services distribution
‘9 Castellated beams —long spans
with gt loads
LO Stub girder floor under
‘construction.
11 Haunching of beam at columa,
herein composite construction.
12 Haunched beams at Grand
Buildings, Trafalgar Square.
13 Typical tapered beam profiles
(Ward Structures) and bottom, an
‘example of running larger services
‘where the beam shallower in
‘order to minimise floor sandwich
depth
114 Example of tapered beam oor
structure.
15,16 Composite trus wth service
‘routes in principle and onsite.
0 AszeAptit
they areneeded. The composite action
around openings means that the loss of
strength ofthe beam dueto web openingsis
often not significant.
Castellated beams
Castellated beams have been used as
secondary beams in some buildings, but they
suffer from low shear resistance and cannot.
readily resist heavy point loads. They have
primarily been used aslong-span roof beams
where theirattractive shape s often
expressed architecturally. With only light
loading they can readily span 15 m without
intermediate supports, 9.
‘Stub girders
Inthissystem, tension is resisted by the
bottom chord (usually a stee! column section)
and compression resisted by the slab. Shear
istransferred by stubs on the bottom chord
and the slab openings are located adjacent to
the stubs. Secondary beams are designed as
continuous beams spanning over the bottom
chord. Stub girders are most efficient in the
12-15mspanrange, but they have been
designed up to27m span, 8, 10.
Haunched beams
Inthis system the beams are stiffened at the
connection with the column, thus minimising,
the structural depth and allowing the
servicesto pass underneath the beams,
11,12. (The main beams are usually too
shallow for holes tobe formed in the web.)
Unfortunately the column size increases
significantly and there may be difficulties in
arranging service around the haunehing.
Sometimes tis difficult to achieve continuity
at the corners ofthe building. Haunched
beams were used in the construction
of Grand Buildingsin Trafalgar Square
in London.
Tapered beams
Fabricated seetions are most likely tobe
‘economie for spans above 12m, These are
fabricated from steel plates rather than
standard sections. The taper of the bottom
flange is usually 5 to6°—such that the beam
depth is reduced by halfat the supports
relative tomid span, Services are located in
the triangular voids adjacent tothe columns,
43,14. (Foradetailed treatment of tapered
‘beams see AJ 1.10.86 p65.)
Composite trusses
‘The benefits of composite action inthis
instance lead to areduction in the sizeof the
topchord and permit offset ofthe bracing
member from its regular position where this
‘would, say, interfere with a servicesroute.
Itisalso possible to provide a greater zone
for services by omitting bracing members at
mid span. The main disadvantage of the truss
is the expense of fabrication and additional
fire protection. Composite trusses re only
likely to be the preferred solution forspansin
exeess of 2m, 15,16
Parallel beam systems
Inthis method developed by consulting
engineer Peter Brett, the primary or spine
‘beams are arranged in pairs with one beam
passing either side ofeach column, Shear s
transferred intothe columnsby means of
brackets. The secondary or'rib beams pass
over the spine beams at right angles, 17.
Because ofthis continuity, beam lengths are
only limited by handling and transportation
requirements. The piece’ count is
significantly lower than for conventional
construction saving both erection time
and costs.
Superficially this approach appears to lead
todeeper construction. But because ofits
continuity, both primary and secondary|
17 Aparalel beam system, where
members do not haetobe cut to
bay size lenths,
1BThe ASW-Cuble system,
providing alarge clear service void,
Srectalinear cousin ofthe
{tiangulated space frame though
the surface can act compastely
witha concrete or,
‘beams ean be very shallow for their spans
and overall depths are comparable with
conventional construction. Its suitable for
spansupto 15m.
“Aunique steel and conerete flooring.
system will be launched in 1991. The
ASW-Cubic system isa two-layer structural
grillage of steel members made up ina
modular arrangement from standard steel
sections and bolted together onsite, 18. It
mits alarger, regular zone for services
Between the structural layers thansome of
the other beam arrangements. Todateit has
‘been used for long-span roof applications
suchas the award-winning 170m span
Stansted Airport jumbo jet hangar, but will
beapplicable to commercial buildings
providing greater floor spans in
twodirections while offering a smaller
depth to: span ratio,
he difference bet ween the flooring and
roofing systemsis that forthe floor the top
chords ofthe framework are embedded in,
and act compositely with, aconerete floor
slab. Thisallows the use of shallower
overall onstruction depth than the roof but
retains the facility for services installation in
the void between conerete slab and
suspended ceiling. Construction of the
conerete floor slab follows established
techniques for constructing metal deck
‘composite flooring but omits the time
coneumingand expensive installation of
shearstuds.
Vibration response
Asspans inerease soo concerns about
possible floor vibrations in high specification
commercial buildings. Contrary to what
right be expected, long-span composite
beamsare no more prone to vibration
problems than others because composite
action increases the monolithie behaviour of
the whole structure.
Thenatural frequency of efficiently
designed composite beamsis common
the range of 4 to Geycles/see, decreasing with
increasing span. Similar values are
appropriate for non-composite beams, which
willbe deeper and heavier than composite
‘beams for the same loading and span
characteristics. A lower limit of natural
frequency of cycles/see can be used in
long-span composite buildings, provided
cheeks are made on the likely response of the
structure (see the Steel Construction
Institute's Design guide on the vibration.
offtoors)..
‘The natural frequency of atypical
composite floor structure should not exceed
4 eyclesisee without doing more detailed
calculations ofthe structural response.
(People walk at 1-2 eycles/see.) The vibrati
Frequency can be tested by special
though thisisrarely necessary. Care should
be taken when delicate machinery needs to
beinstalled.
Vertical cores
‘These not only provide forstairs lift shafts,
service ducts, toilet accommodation and so
on, They usually act asa key vertical
structural element offering lateral stability
tothe main structural frame, Concrete cores
canbe slowerto construct and openings for
doorways and service penetrations must be
carefully predetermined as later alterations
may be expensive and dificult. The number
‘and size of the openings may be limited due to
structural requirements. That they donot
require additional fire protection isa strong
advantage and perhaps explains why
they are the most common farm of core
inthe UK.
Vertical steel bracing or plated steel cores
are usually easier and quicker toerect, are
lightweight and can be prefabricated. Zones
for services and door openings should be
positioned in general termsat anearly stage
inthe design although exaet dimensioningis
not required until later provided that bracing
members remain unaffected, 19abc, 20.
Steel cores can be built simultaneously
with the main frame whereas conerete ones
‘must generally be built inadvance. Itis not
‘unusual fora building to have more than one
type of core depending upon the structural
requirements nd relative positions of the
coreson plan. Thefire prot
coresis the most diffieult problem to salve.
Often the steelworkis protected by a fire
protecting wall.
2 A0eapeion
1819abe Steel-braced core
configurations. bracing with
ny
bracing which s convenient for door
=)
Sie
“be
Steel plate cores may be used where more
stiffhessis required than with the usual k’
braced cores. The stiffened plates are more
akin to bridge construction than to buildings,
and are more efficient when designed for
heavy shearloads.
Fire protection
Current Building Regulations require all
structural steel which supports more than
the roof ofa building or isused in buildings of
more than one storey tobe protected ayainst
fire. This can be achieved by encasing the
steel neoncrete or protecting it by the
application of sprayed insulation,
{ntumeseent coatings, insulated blankets,
‘board casings or ined metal casings. The
choice depends on matters such as cost,
whether the steel will remain exposed
visually, what other elements will be fixed to
the members (such as partitions), how long
the method will take and whether it can be
satisfactorily executed simultaneously with
othersite activities,
Ttisnot unusual forthe perimeter
steelwork tobe encased inconerete,
regardless of the method used elsewhere due
toconerete'shigh durability in this
potentially corrosive conditions along the
cladding ine, Hollow steel sections, ifused
may be filled with concrete or water to
improve their fire resistance but interflling
for fire protection has only been used on one
‘major project todate.
Steel members ean be delivered tosite
pre-encased where later shuttering around
sections would prove difficult. However, this,
often eaves pockets around the joints which
require time-consuming mamual filling,
‘Typically 40 per cent of steelwork used in
modern buildings is protected by spray-
applied material which isusually the
cheapest method, 40 per cent by board
casings, and 10 per cent iseneased in
conerete, particularly perimeter members
and columns. Intumescent paint isonly used
onabout 2 percent of total application but,
thisis likely toincrease as off-site painting
‘becomes more accepted and paint
thicknesses, and hence costs, are reduced
Spray material is most inconvenient when it
420
isapplied adjacent to perimeter areas where
cladding tradesare performing their workat
thesame time.
Despite the decreasing costs offre
protection the need tofire protect steels,
Viewed by the majority ofits specifiersasits
major weakness, as the processis disruptive
and isa separate and additional site activity.
‘The controversial proposals to change the
Building Regulations relating to fire safety
may reduce the degree of protection
required and/or provide alternative ways of
achievingit. The draft amendments
suggested eliminating all four-hour and most
two-hour fire-resisting periods, exeept in
high buildings, increasing compartment
sizes, allowing the greater use of
combustible materials and redueing the
levels of structural fire resistance, However,
due tothe level ofprotest at these
government measures, which also
include greater reliance upon active fire
protection ystems, no changes will be
introduced without further detailed
consideration,
Future systems
Most ofthe alternatives discussed above
relate tothe choice of floor systems which in
‘one way or another are supported by a grid of
columns. The resulting visual effect is
usually lost or suppressed behind suspended
ceilings and under raised fcors. This isnot
necessarily undesirable but it may become
possible to express the structure ifarchitects
and engineers develop other systems which
canbe implemented by fabricators and
rectors.
Overview
Steel and composite construction providea
freedom to span longer distances more
economically in commercial buildings.
Seleetion of the optimum system depends on
balancingarchitectural, structural, services
and cost erteria, and on evaluating the
options early enough in design. Barly advice
‘onseleetion and detailed design information
‘ean be obtained from the Stee! Construction
Institote’spublieationsand its Advisory
Service (O34 23345).
Met apniven sa
B19q26