Professional Documents
Culture Documents
for
HPCL-MUMBAI REFINERY,
MUMBAI
Conducted by
APRIL 2017
We are thankful to M/s. HPCL, Mumbai Refinery, for their positive suppo rt in
undertaking this intricate task of Mandatory Energy Audit under PAT scheme of
Encon Act. The field studies would not have been completed on time without the
help interactions and timely support of following officers . We are grateful for
their co-operation during field studies and provision of all essential data for the
study.
Shashank Herlekar
Regional coordinator & Addl. Director PCRA WR
D. Roy Choudhury
Chief Regional Coordinator and Director
PCRA WR
Mumbai Refinery of M/s. HPCL, spread on an area of 321 Acres, is engaged in oil
processing. The installed (nameplate) capacity of the refinery is 7 .5 MMTPA.
This versatile refinery which is the first of India’s modern refineries, symbolizes
the country’s industrial strength and progre ss in the oil industry. Mumbai
Refinery has grown over the years as the main hub of petroleum products. The
refinery has reached to present level through several up -gradation and
restructuring processes.
Electricity and fossil fuels are the main resource s of energy. The refinery power
demand depends mainly on 7.18 MW X 4 nos. and 20.39 MW X 1 no. Gas Turbine
(GT) captive power plant and partly on grid. The refinery generates elect rical
power which is consumed for different purposes. It also purchases power from
the TATA Power grid at 110 KV and 22 KV and step down to 6.6 KV, 3.3 KV, 0.415
KV through transformers and is distributed for different purposes . The
dependency on own generation is because of higher power quality and
reliability.
A comprehensive energy conservation study of the plant was carried out by Team
PCRA to identify potential areas of energy conservation and recommend energy
savings measures along with cost benefit analysis.
Sr. Energy Saving Measures Investment Energy Kcals Thermal Electricity Payback
No savings savings in
MWH
Rs Lac Lakh Rs Month
1 HRSG 1 Efficiency improvement 877.9 35117063716
2 HRSG 3 Efficiency improvement 798.9 31956424873
3 HRSG 5 Efficiency improvement 634.6 26016695236
4 Dry flue gas loss in Boiler SG12 improvement 75.7 3332499612
5 Dry flue gas loss in Boiler SG10 improvement 246.8 10858567611
6
Replacement / Installation of VHP BFP Pump 50.0 83.1 1039.47 7
of Boiler SG12 with small size pump
7 Use of Plate Heat Exchanger instead of Fin Fan
coolers for Generator Lube Oil Cooling for all 50.0 93.77 1172.16 6
Gas Turbines
8 FD Fan Suction choked Filter replcement 20.0 38.5 530 6
9 VFD for FD Fan of SG-10 & SG-11 66 42.4 825.792 7
10
Interconnection of VHP BFW Header of Boiler 100.0 209.7 2621.5 6
SG-10, SG-11, and SG-12
11 Thermal Insulation heat loss reduction in CPP 4978399156
124.5
HRSG
12 Reducing pressure drop in various dryers by
120.0 76.3 954.0 18.9
replacing the decissicant
13 Improving & maintaining performance of
12.0 15.5 193.6 9.3
chillers
14 Replacing various lamps with LED lamps 157.0 134.6 1681.9 14.0
15 Replacing four SBR blowers (lobe type) with
128.0 114.0 1425.6 13.5
high efficiency turbo blower (centrifugal)
16 Installing solar hot water system for canteen
hot water applications 3.75 1.8 - 25.4
Total Oil equivalent MTOE = Thermal kcals / 10000000 converted in MTOE + MWH convertred in MTOE
i. GENERALPLANT/ESTABLISHMENT
DETAILS AND DESCRIPTIONS
The refinery has recently implemented the DHT project which includes
processing facilities such as a new Diesel Hydrotreating Unit, SRU, ARU, SWS
and necessary utilities and offsites. With the installed facilities, the refinery
shall be ab le to produce Gasoline and Diesel, meeting Euro IV quality
specifications, besides other petroleum products like LPG, Naphtha,
Kerosene, ATF, Fuel oil and Sulphur.
3 (a) Complete address of Unit's location (including Hindustan Petroleum Corporation Ltd
Chief Executive's name and designation) with Mahul, Chembur East, Mumbai 400 074
mobile, telephone, fax numbers and e-mail.
6 Period of field data collection survey of Energy Audit February 27th, 2017 to April 4th, 2017
Fuel Refinery
Lube Refinery
MS block
1. Tri-vector Power meter with 3 clamp-on type CTs for measurement of unbalanced and balance load.
2. Tri-vector Power meters with 1 clamp-on type CT for measurement of balance load.
3. Flue Gas analyzer.
4. Vane type Anemometer.
5. Hot wire type Anemometer.
6. Digital temperature indicator for liquids.
7. Digital temperature indicator for surface.
8. Infra red digital temperature indicator for surface.
9. Thermal Imager for thermography of electrical panels, HVAC & Chilled Water System
10. Digital Hygrometer for temperature and humidity measurement.
11. Transit time Ultrasonic non-contact flow meter for measurement of liquid flow rates.
12. Lux Meter.
13. Digital pressure gauges
14. Ultrasonic leak detector
15. Ultrasonic distance meter
Per unit
Description Rs cr UOM cost(Rs/T)
- Imported Crude 1147 405 TMT 28321
- Indigenous Crude 845 279 TMT 30287
other raw materials 3
Hydrogen 8 570.5 T 140228
BH/RLNG 7 2513.1 T 27854
Demmurage/wharfage 3
Manpower 31
chemicals and catalyst 8
M&R 13
Insurance & taxes 3
Equipment Hire Charges 0
Rent 0
Travelling and Conveyance 1
Printing and Stationery 0
Electricity 32 44326.18 7.22 Rs/KWH
Water 1
Security Expenses 2
Consultancy & Technical Services 0
Other purchased services 2
Sundry Exp. 1
Environment Protection / Upgradation 0
HQO overheads/inter-func.charges 3
Depreciation 34
Interest Exp. 6
Total 2151
The HPCL Mumbai Refinery has following four main processing complexes. The
Fuels Refinery produces fuels from the crude by distillation & by removing
impurities. It has two major complexes viz. Fuels Refinery, DHDS/DHT and GFEC.
DHDS/ DHT was commissioned in the year 2000/2011 respect ively for production
of various Bharat Grades diesel. GFEC was commissioned in 2010 for production
of Euro III/IV MS. The Lube Refinery manufactures lubricant base material,
which, after adding additives by Marketing is sold as finished lubricants for
automobiles.
FUELS REFINERY:
FR – CDU has design capacity to processes 3.5 MTPA imported Persian Gulf crude.
Crude oil is heated in crude preheat exchangers utilizing the available waste
heat. It is further heated in furnaces and then fractionated in the distillation
tower to get various products like LPG, Naphtha, Flash Blending Stock, Aviation
Turbine Fuel, Kerosene, MTO, Light Virgin Gas Oil, Heavy Virgin Gas Oil and
Reduced Crude Oil. From these products LPG, Naphtha, Kerosene & MTO are
finished products. Others are intermediate pr oducts going to further processing
units.
Reduced Crude Oil is the bottom product of CDU. It is further heated in VDU
furnace & then sent to distillation tower operating under vacuum condition.
Intermediate products are obtained from VDU. Lighter Vacuum Gas Oil goes to
diesel. The other intermedia te products viz. I SS (Side Stream), II SS & III SS go
to FCCU for converting into valuable products by cracking or to Lube Refinery
FRE – CDU has design capacity to processes 3.0 MTPA Bombay High low Sulphur
crude. Crude oil is heated in crude preheat exchangers utilizing the avai lable
waste heat. It is further heated in furnaces and then fractionated in the
distillation tower to get various products like Naphtha, Flash Blending Stock,
Kerosene, Light Virgin Gas Oil, Jute Batching Oil and Reduced Crude Oil. From
these products Naph tha, Kerosene are finished products. Others are
intermediate products going for secondary processing units.
The bottom product of CDU, Reduced Crude Oil from FRE CDU goes to FRE VDU.
Reduced Crude Oil is further h eated in VDU furnace & then sent to distillation
tower. Intermediate products are obtained from VDU. Lighter Vacuum Gas Oil
goes to diesel. The other intermediate products of FRE VDU viz. I SS (side
stream), II SS & III SS go to FCCU for converting into va luable products by
cracking. The bottom product Vacuum Tower Bottoms goes to fuel oil.
e. Naphtha Stabilizers:
Stabilized and sweetened Light Virgin Naphtha obtained from FR CDU is distilled
in this unit to produce raw Hexane, this is subsequently processed in NMP
extraction unit to remove aromatics for producing Food Grade Hexane. This
Hexane is used for extracting oil from seeds in the food industry.
Low value Vacuum distillates from FR & FRE VDU and Wax from Lube Refi nery
PDU are catalytically cracked in the FCC Unit to produce valuable products. The
products of this unit are unstab ilized cracked Naphtha, Cracked Gas Oil and
Residue. The cracked unstabilized naphtha is further separated into cracked LPG
& cracked naphtha. The cracked gas oil goes to diesel & resid goes to fuel oil.
Un-stabilized Cracked Naphtha and Cracked Gases produced in FCCU unit are
processed in this unit to yield Cracked LPG and Light Cracked Naphtha (LCN).
Cracked LPG is treated in DEA unit to remove Hydrogen Sulphide, whereas, LCN
is treated in Merox unit to remove Mercaptans. This treated LCN then goes to
PrimeG and then to Gasoline or petrol.
i. DHDS COMPLEX
This is the secondary processing unit complex. The purpose of the complex is to
reduce Sulphur in the diesel to meet various Bharat Fuel specifications. It has
the following units.
The DHT unit is designed to process the feed which mainly comprises straight
run diesel streams from FR/FRE CDU’s and light cycle oil (LCGO) streams from
FCCU/New FCCU. DHT unit is designed to process hot feed (directly from units)
as well as cold feed (from offsite storage tanks). The plant capacity is 2.2 million
tones per year with 8000 hours operating per year. The principal processing
objective of unit is to produce ULSD with sulfur content of 8 wt ppm or less.
About 540 Tons per day of Kerosene range product (TBP 140 -165 °C) will be
fractionated as a side stream product from fractionator column with flash point
above 38 °C.
a. NSU:
The Naphtha Splitter Unit splits the whole range naphtha into light naphtha (C5 -
90C) and heavy naphtha (90 -130 C) by the method of distillation.
b. NHT/CCR:
The purpose of this unit is to generate Reformate stream from straight run Heavy
Naphtha with high O ctane number and low Sulphur content for blending in Euro
IV MS pool. The design capacity of the unit is 545 TMTPA. Heavy Naphtha from
Naphtha Splitter Unit is hydrotreated to remove catalyst poison (Sulfur,
Nitrogen etc.). This hydrotreated naphtha is se nt for reforming and resultant
product (Reformate) high in RON is blended with MS pool.
c. PRIME G+:
The purpose of this unit is to desulfurize FCCU gasoline stream while maintaining
high Octane level (RON). The design capacity of the unit is 475 TMTPA. FCC
Naphtha is subjected to selective hydrogen desulphurization first, then split into
Light and Heavy FCCU gasoline. Light FCC gasoline is recovered as a final product
from this section. Heavy gasoline is further subjected to deep desulphurization
while minimizing loss of RON during desulphurization.
d. NHDT/ISOM:
The purpose of this unit is to upgrade Octane number of Light Naphtha and
generate Isomerate stream with very low benzene, olefin, Sulphur and aromatic
The Lube Refining complex of the refinery situated on the south side of the Fuels
refinery comprise of the following processing units. The Lube Refinery is
designed to manufacture 335 TMT of Lube Oil Base Stocks per year. A brief
description of the Processing units in the Lubes refinery is given below:
The feed to the unit is Reduced Crude Oil received from FR CDU. This unit is
identical to FR VDU. Product streams from the unit are various raw distillates
like Vacuum Gas Oil, I SS, II SS, III SS & Vacuum Tower Bottoms (VTB). Vacuum
Gas Oil goes to diesel while all SS go to solvent extraction units for making
Lubricating Oil Base Stoc ks. VTB is used for making asphalt or it goes to Propane
Deasphalting Unit for making Bright Stock.
The I SS, II SS & III SS intermediate products from FR VDU & LR VDU are the feed
streams for these units. Extraction is done with NMP to remove aromatics and
further hydrofined to improve their colour and colour stability. The products
are 150N, 500N, 1300N Raffinates and Extracts. The raffinates are further
processed in Propane De -waxing Unit to remove wax. Extracts are also valuable
products and can be sold as RPO and CBFS.
Feed to this unit is various hydrofined raffinates of 150N, 500N, 1300N & Bright
Stock. Wax from streams is removed to improve the pour point & the products
of this unit are various 150N, 500N, 1300N & Bright Stock Lube Oil Base Stocks.
Propane is used as a solvent for removing wax.
Feed to this unit is FR & LR VTB. The valuable oil from VTB which cannot be
separated by distillation is recovered by extraction with propane. The De -
asphalted Oil distillate is sent to Solvent Extraction Unit & Propane De -waxing
Unit above to make finishe d product called as Bright Stock. This is the most
valuable product in Lube Oils & it is mixed with various grades of Lube Oil
Products. This unit also produces very good quality of asphalt.
In order to meet current and future international Lube base stock standards,
HPCL has implemented the Lube Oil Base Stock Up -gradation Project (LOUP) at
Mumbai refinery to operate in conjunction with the existing lube plant. The
design intent of LOUP is to process waxy raffinates from the existing NMP
extraction unit into high quality Group II and Group III Lube Base Oils. LOUP is
designed to produce 227 KT/year of Group II base stock based on processing
100% Arab Light feeds.
The major raw material inputs, quantity and costs are given in the section 1.3
E n e r g y a n d U t i l i t y S y s t e m D e s c r i p t i o n
3.2.1 Electricity:
The electricity is procured from M/s Tata Power as well as generated through
gas turbine based captive power plant.
The Gas turbine Generating unit mainly consists of Gas Turbine, Reduction Gear
box, Electric Generator, Starting Diesel Engine & Auxiliary Gear box.
Four Gas Turbine Units of Mumbai Refinery a re double shaft simple open cycle
machine and one is single shaft simple open cycle machine. The gas turbine is
composed of Gas Generator along with compressor and power turbine drives the
generator through reduction gear.
FY 2 0 1 5 - 1 6 FY 2 0 1 4 - 1 5 FY 2 0 1 3 - 1 4
Generation Capacity of the plant (MWH) 421632 420480 420480
Gross Generation(MWH) 249685 150722 188433
Aux. Power Consumption (MU) Ni l Ni l Ni l
Energy Export to the Grid(MU) Ni l Ni l Ni l
Energy imported from the Grid (MWH) 453868 532510 457345
Energy Export to Township / other (MU) Ni l Ni l Ni l
Plant Load Factor Average** 0.592 0.358 0.448
The electricity is procured from Tata Power Ltd as well as through Open access, the details of the
consumption is as under.
66000
64000
62000
MWH/Month
60000
58000
56000
54000
52000
50000
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17
50000
40000
Ton/Month
30000
20000
10000
0
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17
The details source of steam generation and their percentage share for financial
year 2016-17 is sho wn in following table:
Heat Recovery Steam Generators are put at the exhaust side of GTG to recover
exhaust heat of GTG. By doing so, steam is generated for refinery use and co -
generation plant efficiency is optimized.
160M 3 /hr condensate is recovere d and 80M 3 /hr condensate is lost. 25M 3 /hr
steam is lost due to leakage and trapping system. 85M 3 /hr water after steam
generation and 15M 3 /hr water after sanitary usage is supplied to IETP where
20M 3 /hr rain water is added. 90M 3 /hr water from IETP is re used. 20M 3 /hr
water is reused as FGDS make up and remaining 70M 3 /hr water is supplied to
dematerialization plant. 30M 3 /hr water is used as fire water make up. Fresh
water consumption during the year 2016/17 is given below:
The compressor houses are located in the various department including DHDS,
LR, Utility as well as or Nitrogen generator.
While major part the compressed air is consumed for instrumentation as well
as nitrogen generation, a small part is utilized for the plant air applications.
The compressed air lines are interconnected for emergency usage; but the
inter-connection may not be suitable for complete plant load.
The chilled water is primarily used for space cooling including offices, control
and panel rooms. Centralized chillers are provided for administration building
as well as major panel rooms with air handling units are installed for the
individual locations.
A few of the areas are provided with Ductable split as well as split air
conditioners.
Sea cooling water (SCW) at the design rate of 2500 M 3 /hr is supplied by GEFC
SCW CT Pump, 2400M 3 /hr by DHDS SCW CT Pump, 2500M 3 /hr by LR SCW CT
Pump, FR/FRE sea cooling tower and LOUP SCW CT Pump. Bearing Cooling
Water (fresh water) at the design rate of 600 M 3 /hr is supplied by GEFC BCW
CT Pump, 250M 3 /hr by DHDS BCW CT Pump, 600M 3 /hr by DHT BCW CT Pump
and 165M 3 /hr by LOUP BCW CT Pum p.
D e t a i l e d P r o c e s s F l o w D i a g r a m a n d E n e r g y a n d
M a t e r i a l B a l a n c e
4.1 Flow chart showing flow rate, temperature, pressures of all input -
output streams:
P e r f o r m a n c e E v a l u a t i o n o f M a j o r U t i l i t i e s a n d
P r o c e s s E q u i p m e n t ’ s / S y s t e m s
5.1 List of equipment’s and process where performance testing was done:
The performance testing was done on the following systems wherever
possible and feasible.
Boiler
Turbines
Cooling Tower
Cooling Water Pumps
Process Pumps
Air Conditioning Units / AHUs
HVAC Chillers
Vapour Absorption Machines
HVAC Cooling Towers performance
HVAC Cooling Water Performance
Air Compressors
Air Dryers
Fans & Blowers
Motors
Lighting
Capacitor
Transformers
Electricity Bill
Solar Heating System
E n e r g y E f f i c i e n c y i n U t i l i t y a n d P r o c e s s S y s t e m
Chart
800
700
600
500
400
300
200
100
0
Apr 16 May 16 Jun 16 Jul 16 Aug 16 Sep 16 Oct 16 Nov 16 Dec 16
From above, it is clear that though crude input has increased in the
year 15-16 from the year 14 -15 by 7% , MBN has been reduced by 3.99
and KWH/ Ton of crude reduced by 4.49 due to various energy
conservation measures implimen ted at Refinery during the year.
The Co-Generation Captive Power Plant of the Mumbai Refinery comprises Gas Turbines to
generate continuous power output of 49.11 MW excluding its own requirement of power for
running its auxiliaries. The Gas turbine Generating unit mainly consists of Gas Turbine, Reduction
Gear box, Electric Generator, Starting Diesel Engine & Auxiliary Gear box. Four Gas Turbine Units
of Mumbai Refinery are double shaft simple open cycle machine and one is single shaft simple
open cycle machine. The gas turbine is composed of Gas Generator along with compressor and
power turbine drives the generator through reduction gear. The Gas turbine uses Natural Gas or
Naphtha as a fuel.
Heat Recovery Steam Generators are put at the exhaust side of GTG to recover exhaust heat of
GTG. By doing so steam is generated for refinery use and co-generation plant efficiency is
optimized.
Each waste heat steam generator is a Horizontal Natural Circulation Bi Drum, supplementary
fired water tube boiler. It generates steam at 15 kg/cm2 at 256° C. The HRSG steam generation
can be boosted up by supplementary firing by firing Natural Gas as and when required.
firing fuel HSD, Natural Gas, HSD, Natural Gas, HSD, Natural Gas,
Naphtha Naphtha Naphtha
HRSG Type Water tube Waste Heat Water tube Waste Water tube Waste
Recovery Boiler Heat Recovery Boiler Heat Recovery Boiler
Feed Water temperature, 110.8°C , 23.9 TPH 110.8°C , 27 TPH 111°C , 59.3 TPH
flow
As part of Energy Audit study the unit operating data collected during close to base load. During
the audit all the energy going in and going out was observed and measured during the test. The
Blow down was isolated, Desuperheating was in control mode, and Equipment changeover was
not performed for the data collection duration.
During the trials, the key parameters namely, unit load, main steam temperature, main steam
flow rate, gas flow rate, and other key parameter were monitored, and the fuel and flue gas
sample was collected as needed. The results are presented in the table. The key findings are as
follows:
GT PERFORMANCE UOM GT 1 GT 3 GT 5
Open Cycle Gross Heat Rate
(LHV Basis) kcal/kwh
3760 3663 4269
Parameter Unit HRSG 1 HRSG 3 HRSG 5
GT Exhaust Flow Rate TPH 155 154 367
GT Exhaust Enthalpy Kcal/kg 127 126 129
GT Exhaust energy Kcal/hr 19627709 19288397 47444627
Total energy gain by Water and
Steam Kcal/hr 11269747 11395728 35619658
HRSG Efficiency % 56.37% 57.58% 75.24%
Observations:
The HRSG efficiency was calculated from the calculation of the energy gain by the working
fluid water and energy supplied by the GT exhaust.
The Cogeneration efficiency is 66%.
The GT exhaust flow was calculated based on PTC 22 procedure.
From the above data, it has been observed that the HRSG efficiency is calculated as
56.37% for HRSG 1 and 57.58% for HRSG 3, and 75.24% for HRSG 5.
The Gas turbine Heat rate was calculated as 3760 kcal/kwh for GT 1 and 3663 kcal/kwh
for GT 3. The design heat rate was 3707 kcal/kwh. The GT 5 Heat rate was 4269 kcal/kwh.
Fuel Gas quality features have a major influence on GT and HRSG performance. The Gas sample
was taken and analysed by the internal lab of Mumbai Refinery. The Naphtha and Natural gas
sample analysis is presented as follows:
The Gas Turbine performance was calculated for the open cycle operation. The calculations are
as follows
Table 6: Gas Turbine Performance
Parameter UoM GT 1 GT 3 GT 5
Audit date 1/03/2017 1/03/2017 7/03/2017
CTG Power Output MW 7.18 7.28 15.75
CTG Exhaust Temperature °C 476.56 492.11 532.6456
CTG Exhaust Flow rate TPH 155 154 367
Inlet air Relative Humidity % 27.95 40.00 32
Ambient Temp at 35.61
°C
compressor inlet 30.85 36.58
Naphatha flow Rate m3/hr 1.42 9.14
Naphatha Temperature Degree C 30.00 30
NCV of fuel kj/kg 44350.4 44350.4 44350.4
Density gm/cc 0.694 0.694
Naphatha Mass Flow Rate kG/hr 985.5 6343.93
RLNG flow Rate nm3/hr 1832 2954.44
RLNG Temperature Degree C 30 30
NCV of RLNG kcal/M3 8353.6 8353.6
specific gravity 0.576 0.576 0.576
RLNG Mass Flow Rate kg/hr 1397 2253
Inlet fuel energy Naphatha Kcal/hr 10446088 0.0 67245670
Inlet fuel energy RLNG Kcal/hr 16531434.4 26660932
Fuel LHV Kcal/m3 45267 45267
Open Cycle Gross Heat Rate
kcal/kwh 4269
Without Correction Factor 3760 3663
The Gas Turbine 5 heat rate is very poor. It gives a very poor performance of gas turbine. The
GT 5 consuming more than design fuel energy. But at the same time they are giving less power
output. The improper combustion may be due to insufficient compressor discharge pressure,
problems in the GT blades or machine may need upration. With the preventive measures,
compressor water washing and overhauling will improve the performance of GT-5. HPCL
clarified that GT-5 overhauling is done after every 48000 hours of operation and it was carried
out 2 years ago. Compressor water washing is carried out during shut down as per OEM
recommendation.
The GT 3 Compressor has lower discharge pressure as compare to GT 3. Its adiabatic efficiency
is 1% less compare to GT 1.
CPH PERFORMANCE
Water Circuit
DM Plant Outlet to Preheater
Pressure kg/cm2g 15.00 15.00 15
DM Plant Outlet to Preheater
Temperature °C 34.00 35.00 29.85
DM Plant Outlet To Preheater Flow
rate TPH 10.30 14.60 67
Preheater Outlet to deaerator
Temperature °C 110.00 110.00 85.25
Preheater Outlet to deaerator Flow TPH 10.30 14.60 67.00
flue Gas circuit
Flue Gas Temp at CPH Inlet °C 271.99 311.28
Flue Gas Temp at CPH outlet °C 233 223.41 142.59
Calculation
Observations:
The exhaust flue gas temperature is higher than the design value of 110 °C. This will increase
the exhaust loss. The effectiveness of Condensate Pre Heater (CPH) is very low. This indicates
a poor heat transfer to the working fluid. In addition there is no flow meter, temperature
transmitter, and pressure transmitter in the line. Therefore, it is not possible for the control
room operator to monitor the temperature gain and performance of the CPH. It is
recommended to install all these transmitters. The energy saving recommendations are
given in Encon Savings.
Water Circuit
FW to HRSG Feed Control Station Valve
position % 44.0% 81.0% 60
FW to HRSG 1 Feed Control Station Valve
DP kg/cm2g 26.76 44.43
FW to economiser inlet Pressure kg/cm2 34.24 16.57 21.28
FW to economiser Inlet temperature °C 109.02 92.59 121.31
FW to economiser Inlet Flow TPH 17.66 19.19 54.30
Eco outlet temp °C 197.99 184.97 193.44
flue Gas circuit
Flue Gas Temp at Economiser Inlet °C 316.37 296.44 220.68
Flue Gas Temp at Economiser outlet °C 271.99 311.28
Calculation
Inlet FW Enthalpy Kcal/kg 110 93 122
Outlet FW Enthalpy Kcal/kg 201.7 188 197
Total Energy Gain Kcal/hr 1622403 1817632 4056622
Effectiveness % 42.9% 45.3% 72.6%
Observations:
Observations:
The Pinch Point of HRSG 1 and HRSG 3 is very high. This indicates a poor heat transfer to the
working fluid. The energy saving recommendation is given in Encon Savings.
SUPERHEATER PERFORMANCE
The Performance of Superheater Circuit of HRSG 1, HRSG 3, and HRSG 5 are as follows:
Observations:
3. The effectiveness of Superheater section of HRSG 1, HRSG 3, and HRSG 5 is very low. This
indicates a poor heat transfer to the working fluid. The energy saving recommendation
is given in Encon Savings.
The Utility boilers consists of 3 Boilers for steam generation. The generation is of 405
TPH of steam generation capacity.
The boiler can be operated with single fuel or dual fuel mode. The Boiler is operated with
Refinery fuel gas and Furnace Oil.
As part of Energy audit study the unit operating data collected during operating load for
Boiler SG 10 and Boiler SG 12. Other Boiler was stopped due to ongoing maintenance
work. During the audit all the energy going in and going out was observed and measured.
The Blow down was isolated, Desuperheating was in control mode, and Equipment
changeover was not performed for the data collection duration.
During the trials, the key parameters namely, unit load, main steam temperature, main
steam flow rate, gas flow rate, and other key parameter were monitored, and the flue
gas sample was collected as needed. The results are presented in the table. The key
findings are as follows:
1. The Boiler efficiency was calculated from the heat loss method.
2. From the above data, it has been observed that the Boiler efficiency is calculated as 79.69 %
for Boiler SG-10 and 80.73% for Boiler SG-12.
3. The Boilers are operating below their design capacity. The Energy conservations are given in
the Encon Savings
FUEL ANALYSIS
Fuel quality parameters have a major influence on Boiler performance. The Fuel sample was
taken monthly and analysed by the internal lab. The fuel sample analysis is presented as follows:
Furnace Oil
Density 0.977 gm/cc
Net Calorific value 9760 kcal/kg
Refinery fuel gas
CH4 7.5%
C2H6 10%
C2H4 0%
C3H8 9.8%
C3H6 5.1%
IC4 3.2%
NC4 6%
C4H8 3.1%
IC5 0.1%
H2 52.8%
C3H6 5.1%
N2 2.5%
The Boiler SG-12 and its component performance were calculated for the operating load. The
calculations are as follows
Table 15: Boiler SG-12 Performance
Boiler SG-12
Parameter UoM
Data
FW Inlet Control Valve Position, FCV, 30% % 37.27
Drum coil heater inlet pressure kg/cm2g 59.11
Drum Coil Heater Inlet temp °C 113.76
Drum coil Heater Outlet Temp °C 114.96
Eco Inlet Temperature °C 114.96
Eco Inlet Flow TPH 63.85
N2 % 2.5 0 0.8
S % 0 0.9 0.6
The Boiler efficiency is lower than the design value the primary reason is high flue gas loss and
higher value of Hydrogen in the fuel.
The fuel source of the boiler is Furnace Oil or Refinery Fuel Gas. The furnace Oil contains H2 about 11 % whereas,
the RFG contains more than 61% of H2 in fuel. The sources of hydrogen stream which may be entering in fuel gas
stream needs to be identified by Refinery and stop the same. The ratio of RFG to FO is currently 0.462. This needed
to be reduced to decrease the H2 losses in Fuel.
The Hydrogen in fuel should be within 10% to keep the losses “Heat loss due to H2 in fuel” within 5%.
FD Fan of Boiler SG 12
Table 5: FD Fan
Parameter UoM Test Data Note
Suction Air pressure mmwc -0.3
FD Fan Damper Position % 87.6
Discharge Air Pressure, (SCAPH Inlet) mmwc 71.6
discharge Air temperature (Scaph
°C 36.1
Outlet
Discharge Air Flow rate TPH 80.4
FD Fan Amp amp 257.9
FD Fan Power Consumption kW 166.8
Fan Isentropic head Nm/kG 623.5
Density kg/m3 1.153
Flow rate m3/s 19.38
FD Fan Efficiency % 8.72%
FD Fan Hydraulic Power kW 15
FD Fan of Boiler SG-12 is working on extremely low efficiency. The FD Fan suction filter
was found choked/ damaged during the field visit. The Fan is consuming power but not
able to deliver the air to the boiler. The isentropic head of the FD Fan is very low.
Boiler SG-10 is 140 ton boiler. During the audit 2 burners are fired with FO and 1 is with
Refinery Fuel Gas. Due to process limited requirement it was not possible to run the boiler
at design load. Therefore, the trial data is collected at 100.2 TPH steam flow. The test data
analysis and observations is given below. The Boiler SG-10 and its component performance
were calculated for the operating load. The calculations are as follows
Table 17:Boiler SG-10 Performance
Test
Parameter UoM Design data
Parameter
Eco Inlet Pressure KSC 42.39
Eco Inlet Temperature °C 131.16
ECo Inlet Flow TPH 99.71
Eco Outlet Temp °C 188.86
Drum Pressure kg/cm2g 40.73
Drum Level % 51.34
Steam temp before Ds oC 260.74
Desuperheating water Pressure,
kg/cm2g 67.84
before BFW Heater
Desuperheating water
°C 108.48
Temperature
Desuperheating spray Flow kg/hr 5031.90
Main Steam Outlet Pressure kg/cm2g 38.5
Main Steam Outlet
°C 359.8
Temperature
Main Steam Outlet Flow TPH 100.2
Fuel Parameter
FO Oil Pressure kG/cm2g 13.1
FO Oil Temperature °C 169.2
FO Oil Flow kG/hr 4334.5
RFG Temperature °C 47.1
RFG Flow kG/hr 1442.0
Furnace Pressure mmwc 81.8
O2 % eco outlet % 2.1
Furnace Temp at Boiler bank
°C 386.9
outlet/eco inlet
temp at Eco outlet °C 185.7
Calculation
The Boiler efficiency is lower than the design efficiency. The primary reason for lower efficiency
is high flue gas loss. The Flue gas temperature at stack is 185.7 Degree C. which is much higher
than the expected value.
Observations:
The Fan Efficiency is very low to 36.22%.The fan is operating below it isentropic head at this
efficiency level. The energy conservation opportunity is given in encon savings.
convective Radiation
surface Surface Temp in
Location S.No Details Image No. heat loss, heat loss,
temp, °C area, m2 Degree °k
watt watt
1 Soot Blower MOV-1017 3232 260 0.13 533 0.70 492.58
Superheater outlet hdr vent line 0.07
2 3233, 3234 209
no insulation and valve leakage 482 0.30 169.93
Superheater header bad 3.00
3 3235 93
insulation 366 3.09 1083.52
4 Drum Manholes no insulation 3237, 3241 234 3.14 507 15.24 9707.97
5 Startup vent line passing 3236 90 0.11 363 0.10 35.80
6 Drum level transmitter pipe 3238 234 0.17 507 0.81 515.02
Drum level instrumentation line 0.14
7 3239 234
no insulation 507 0.69 436.86
steam atomizing line no 1.05
SG- 12 8 3240 234
insulation 507 5.08 3235.99
Boiler
9 Economiser manhole 3242 90 0.79 363 0.74 257.79
Deaerator Steam line header 0.13
10 3243, 3244 360
valve no insulation 633 1.04 1061.48
11 MP Steam to Deaerator 3245 234 0.11 507 0.53 337.08
BFP Suction line valve no 3246, 1.00
12 103
insulation in 15 valves 3247, 3248 376 1.30 477.01
PRDS (MP PRDS) Control Valve 0.17
13 3249 78
leakage 351 0.10 34.06
14 CBD Tank 3250 108 4.00 381 5.75 2154.01
15 Economiser Outlet Duct 3252 60 4.00 333 0.54 163.76
16 Mud Drum Bad Insulation 3253 100 1.57 373 1.92 693.15
17 VHP Header (Ground Floor) 3254 166 1.00 439 3.01 1449.65
18 BFW Control Valve 3255 122 0.20 395 0.36 142.16
3256 &
19 VHP Header 2 (First Floor) 3257 111 1.00 384 1.52 576.58
HP Steam Line to SG-10-5001
20 Blower 3258 169 1.00 442 3.09 1507.81
SG-10 21 VHP Steam from SG-12 3259 234 1.00 507 4.85 3090.14
Boiler 22 SG-10 Steam Drum 5V 3261 206 0.11 479 0.45 254.01
23 Steam Drum Hole 3262 225 1.57 498 7.24 4447.12
Towards Steam Drum 3 (Line
24 Uninsulated) 3263 239 0.79 512 3.92 2544.79
3264 &
25 Back Side of Steam Drum 3265 241 0.11 514 0.55 360.12
26 Steam Drum Hole 3266 231 1.57 504 7.49 4715.93
Drum Pressure Gauge Line no
HRSG 3
27 insulation after valve, 1/2" 3267 160 0.11 433 0.31 145.83
The sea cooling water is handled by GEFC, FR, FRE, DHDS, LR and LOUP cooling
towers. The bearing cooling water (fresh water) is cooled by GEFC, DHDS, DHT
and LOUP BCW cooling towers.
The actual air flow rate is calculated based on air velocity measurement
but could not be compared with de sign air flow rate due to non-
availability of design specification data .
Actual air flow rate (kg/hr)= Fan effective area (M 2 ) x Air velocity
(M/Sec) x 3600 x Air density (kg/M 3 ) x Temperature correction factor
The data was collected from DCS for the following pumps and other
equipments.
The overall (pumps and motor together) operating efficiency of the pumps
were computed (under throttled conditions) by computing hydraulic and actual
power, the details are as under.
HPCL opined that for various identified pumps, motors, specific limitation is
occurring due to low unit through put during survey, revamp study is in progress
in a few units, etc. HPCL informed that VFD can be implimented for motors of
31 P1C and E (FRE), 32P7A , review shall be done by them for FR - 12 P9 A/B,
GFDS - 101-PM-1001A, 101-PM-1002A, 101-PM-1003A, 102-PM-1001B, 102-PM-
2001B, 102-PM-2004A, 103-PM-2001A, 103-PM-2004A, 103-PM-1001B, 103-PM-
2003A, 103-PM-2006A, 103-PM-2009A, 107-PM-1003A, 109-PM-1001A. For
these identified motors, the unit is undergoing revamp and post revamp flow
requirements will change. It was informed that for pump 105 -PM-1003 A /B ,
both pumps were operating during survey, however in normal condition only one
pump operates with 90% valve opening. For 107 -PM-1003 A and 107-PM-1001A
plant is operating at lower thruput since revam ping activities. For LR block MP -
305C, 307 C and MP 312 A PDU current feed rate is low , however in future it
may increase to design level. Trimming of impeller option shall be considered
for short duration savings. For MP -4121A , PDA unit is designed to run both BS
and Cat fee dmode. During Cat feed mode , recycle comes down. Hence VFD
option is not required. In LR unit , other identified pumps are running as per
process requirement, demand of various grades, throughput etc.
HPCL informed that for 31 - FAN 1A , 32 FAN 1B and 32 F 1002 VFD option is
feasible to improve efficiency further.
The efficiency of some of the is marginally on the lower side. However, the
fans are provided with variable speed based control to modulate the speed
based on the operating load.
The Administration Bui lding is equipped with AHU -1, AHU-2 and AHU-3. The
conditioned air is supplied to the r oom/space by ducting network .
Packaged type air conditioners are provided in Annexe Building at all floors,
along with ducting network. CISF security office , Laboratories, DCS Control
rooms and MSS-10, MSS-11are also provided with water/air cooled AHUs.
Velocity of the return air fed to the machine along with the cross -
sectional area, to compute flow rate.
Flow Rate of Air (kg/hr)= Average Air velocity (M/s) x Cross sectional area of the
air flow (M 2 ) x Specific Gravity of Air
Air Conditioning Effect (TR)= Air flow rate (kg/hr) x Enthalpy difference between
the air at inlet & outlet of the evaporator coil (kJ/kg) / (4.18 x 3024)
Air Conditioning Effect (kW)= Air flow rate (kg/hr) x Enthalpy difference be tween
the air at inlet & outlet of the evaporator coil (kJ/kg) / 3600= 3.512 x Air
Conditioning Effect (TR)
Specific Power Consumption (kWh/TR) =Power consumption (kW) / Air Chilling
Effect (TR)
The performance of the various machines was evaluated, the details of which
are as under.
Sr. Desired
LOCATION CAPACITY POWER Load SPC Savings
No. Power Observation
TR kW TR kW/TR kW kWh
Fresh Air
Damper
Annex Building 2 - Ground Floor
closed, on
circulation
PK – 1 11 3.7 0.9 4.10 Filters
1 choked
2 PK – 2 11 7.7 1.9 4.02 Filters dusty
3 PK – 3 11 8.1 2.0 4.08 Filters dusty
PK – 4 11 8.8 2.1 4.10 Filters
4 choked
Fresh Air
Annex Building 2 - First Floor Damper
closed
5 PK – 1 11 9.2 2.2 4.10
6 PK – 2 11 9.2 2.2 4.10
7 PK – 3 11 9.6 2.3 4.09
8 PK – 4 9.92 9.5 2.3 4.11 Filters dusty
9 PK – 5 9.92 9.2 2.2 4.10
Main Gate - CISF Security
10 GF AHU – 1 16.37 6.6 5.8 1.14 Filters are
11 GF AHU – 2 16.37 5.98 7.3 0.82 choked. Near
AHU – 1 16.37 14.5 10.9 1.33 AHU no
12 insulation
Laboratory
13 TFA – 1 NA 3.6 13.6 0.27
14 TFA – 2 NA 4.25 6.4 0.66
15 TFA – 3 NA 4.37 6.8 0.64
16 TFA – 4 NA 3.72 15.3 0.24
17 TFA – 6 NA 3.74 20.5 0.18 Filters are
18 AHU – 4 NA 2.04 5.3 0.38 dusty.
GFEC SRR Fresh Air
AHU 9.7 20.7 0.47 Damper is
19 NA
closed.
DHT SRR
20 AHU – 1 NA 7.5 15.8 0.47
New administration building, Laboratory and MSS -10 AHU’s are assisted with
chilled water system.
The chilling effect (TR) and energy efficiency ratio can be computed by indirect
method, as under:
Condenser heat removal rate (TR)= Specific heat (kCal/kg/ o C) x specific gravity x
Flow rate (M 3 /hr) x Temperature difference of water at inlet and outlet ( o C) x
1000/ 3024
Chilling effect (TR) = Condenser heat removal rate (TR) – (0.9 x Compressor
motor power) /3.516
Specific Power Consumption (kW /TR) =0.9 x Power consumption (kW) / Air
Chilling Effect (TR)
Refrigeration Effect (TR)= Specific heat (kCal/kg/ o C) x specific gravity x Flow rate
(M 3 /hr) x Temperature difference of chilled water at inlet and outlet ( o C) x 1000/
3024
Design Parameters
Motor Rating kW NA 15 90 55 90 75
Actual Parameters
Method (V or Z method) Z Z Z Z Z Z
M 5 5 10 10 3 4
The detailed observation study carried out at DHDS, Nitrogen LR and Utilities
compressor system. The observations include pressure readings at inlet and
outlet of filter, dryer & receiver, inlet valve position, unload valve position,
flow rate noted down and current measurements carried out wherever
possible and feasible.
C- C-
87-C- 716-C- 505-CM- DHT DHT
1230 123 C4 C12 C9 C7
01-A 1011 1001 B A
D 0E
Suction
Pressure kg/cm2 NA NA NA NA NA NA NA NA NA NA NA
DP At
Filters mm WC 10 NA NA NA NA 40 130 120 110 140 300
Discharge
Pressure kg/cm2 8 7.76 7.75 7.5 7.6 7.8 7.7 7.8 7.8 7.8 8
Discharge
Temperat 0C 98 110 75 112 132 110 NA 85
ure
Dryer
Inlet kg/cm2 8 7.6 7.5 Air from receiver is
Pressure going to NA
Dryer GFEC,NFCCU,DHT
Outlet kg/cm2 6.6 7.55 NA ,NAD Dryers
Pressure
Receiver
Pressure kg/cm2 6.6 7 NA 7.5 7.5 7.5
Pressure
drop in kg/cm2 1.4 0.76 0.7 0.3 0.2 0.3
dryer
circuit %
2.6 3.8
Generat 17.5% 9.8% 9.3% 3.8%
% %
ed
Inlet
Valve % 100 21 48 34 100 85 100 100 46 49 73
Position
Unload
Valve % 12 13 10 0 0 0 0 0 0 0 11
Position
Flow Rate
m3/hr 940 7500 4597 NA NA NA NA NA
Current
Amp 70 105 69.56 41 36 118 64 65 110 110 65
Pressure
loss 1.00 0.37 0.33 0.00 0.00 0.00
kg/cm2
% 0.0 0.0
12.5% 4.8% 4.3% 0.0%
Generat % %
ed
Power % Input
loss power
0.0 0.0
12.5% 4.8% 4.3% 0.0%
% %
No. of
Drains 1 3 2 2 2 3 3 3 3 3 3
Remarks For high Air flow is There are 9 air compressors out of which 3
pressure not available air compressors are running, 3 air
there is for old air compressors are stand by and 3 air
booster dryer. compressors are under maintenance. The
compress dryers are common and readings provided
or. separately.
The pump-up test could not be carried out due to large capacity compressors
and continuous nature of plant operation.
The possibility of installing auto -drain valve for all the vent points in the
compressor house may also be ascertained.
The pressure drop in on the higher side. HPCL informed that dessicant for GFEC
air dryer has been replaced, planning done for NFCCU, DHT and DHDS dessicant
replacement.
The load analysis for electrical motors of capacity >75kW is listed below.
The drop in motor efficiency is just 1 to 3% till an operating load of around 50%;
but the drop becomes steep as the load start falling below 50%. Depending on
the actual load, the motor consumes 5 to 15% additional power while operating
at smaller loads.
The following motors were observed to be loaded below 50% of the rated
capacity.
HPCL opined that for various identified pumps, motors, specific limitation is
occurring due to low unit through put during survey, revamp study is in progress
in a few units, etc. HPCL informed that VFD can be implimented for motors of
31 P1C and E (FRE) , 32P7A , review shall be done by them for FR - 12 P9 A/B,
GFDS - 101-PM-1001A, 101-PM-1002A, 101-PM-1003A, 102-PM-1001B, 102-PM-
2001B, 102-PM-2004A, 103-PM-2001A, 103-PM-2004A, 103-PM-1001B, 103-PM-
2003A, 103-PM-2006A, 103-PM-2009A, 107-PM-1003A, 109-PM-1001A. For
these identified motors, the unit is undergoing revamp and post revamp flow
requirements will change. It was informed that for pump 105-PM-1003 A /B ,
both pumps were operating during survey, however in normal condition only one
pump operates with 90% valve opening. For 107 -PM-1003 A and 107-PM-1001A
plant is operating at lower thruput since revamping activities. For LR block MP -
305C, 307 C and MP 312 A PDU current feed rate is low , however in future it
may increase to design level. Trimming o f impeller option shall be studied for
short duration savings. For MP -4121A , PDA unit is designed to run both BS and
Cat fee dmode. During Cat feed mode , recycle comes down. Hence VFD option
is not required. For other, pumps are running as per process r equirement,
demand of various grades, throughput etc.
The illumination in the plant is provided with the help of 125/ 160 / 230 / 400
W MVL and SVL at most of the places along with LED of 45 W at some place s.
The measurements are listed below.
BCW Plant
NMP-2 Plant
Pump Slab 29 40 29 91 32 M.V.L. Yes 160 / 400
Drum 29 44 56 59 39 M.V.L. Yes 160
Furnace 5 7 11 10 9 M.V.L. Yes 160
Tower 11 5 6 8 11 M.V.L. Yes 160
Tank Area 7 11 6 8 9 M.V.L. Yes 160
Compressor Shed 13 10 7 54 21 M.V.L. Yes 125
DWA Plant
Plant Area 5 10 9 11 15 M.V.L. Yes 160
Pump Slab 16 20 21 11 12 M.V.L. Yes 160
PDU Plant
Filter Area 11 8 14 16 7 M.V.L. Yes 160
Pump Slab 24 20 30 32 36 M.V.L. Yes 125 / 160
Tower 35 40 8 11 28 M.V.L. Yes 125 / 160
NMP-1 Plant
Compressor 20 25 47 35 31 M.V.L. Yes 125 / 160
Pump Slab 45 35 38 31 49 M.V.L. Yes 125
Tower 42 15 38 26 35 M.V.L. Yes 125 / 160
High Mast Tower 68 61 64 71 54 S.V.L. No 400
VPS-LR
Pump Slab 15 32 59 71 8 M.V.L Yes 250
High Mast Tower 71 82 79 82 45 S.V.L. No 125 / 400
Drum 190 200 35 76 112 M.V.L. Yes 125
Hydrogen Plant
Furnace-1 13 21 36 42 51 M.V.L. Yes 125
Furnace-2 11 12 14 15 17 M.V.L. Yes 160
Furnace-3 14 13 29 24 22 M.V.L. Yes 160
Pump Slab 29 31 28 24 26 M.V.L. Yes 160
Boiler House
Compressor 42 36 49 55 51 M.V.L. Yes 125 / 160 /
400
Pump Slab 100 55 54 81 92 M.V.L. Yes 125
ARU+SWS+SRU+GTU
Pump Slab-1 16 49 53 94 81 M.V.L. Yes 230
Pump Slab-2 11 30 18 48 77 M.V.L. Yes 230
Pump Slab-3 62 27 64 22 34 M.V.L. Yes 230
DHT
Pump Slab 74 173 98 104 81 M.V.L. Yes 125
Furnace 84 92 51 102 67 M.V.L. Yes 125 / 250
Heat Exchanger 6 8 16 50 49 M.V.L. Yes 125 / 250
Compressor Shed-Ground 151 68 36 64 41 M.V.L. Yes 125 / 250
Floor
Compressor Shed-First Floor 102 119 145 132 144 M.V.L. Yes 125 / 250 /
400
The street light illumination requirement is fulfilled with 250 W SVL at all the
places.
First Floor
1 Room No. 102 6.0 3.0 495 460 432 471 468 489 467 445 462 481 495 432 467
2 Room No. 103 6.0 3.0 494 482 471 489 486 468 472 479 459 475 494 459 478
3 Room No. 108 6.0 3.0 495 468 437 469 482 439 467 459 471 472 495 437 466
4 Room No. 111 6.0 3.0 412 398 368 385 389 410 402 378 381 377 412 368 390
5 Room No. 113 5.4 3.6 120 129 139 147 121 118 135 145 128 152 152 118 133
6 Room No. 119 5.4 4.8 163 144 151 149 164 158 162 167 152 159 167 144 157
7 Room No. 121 5.4 3.6 393 408 397 412 389 372 410 409 394 381 412 372 397
8 Room No. 122 5.4 3.6 358 408 352 348 349 359 356 365 364 368 408 348 363
9 Room No. 124 5.4 3.6 313 323 351 361 323 346 335 339 342 348 361 313 338
10 Room No. 127 5.4 3.6 228 217 221 235 230 231 225 234 231 209 235 209 226
11 Room No. 128 9.0 4.8 213 230 219 239 215 231 224 229 218 245 245 213 226
12 Room No. 131 5.4 3.6 321 342 303 337 312 324 331 329 315 311 342 303 323
13 Room No. 133 5.4 3.6 222 205 246 248 229 245 234 231 237 234 248 205 233
14 Room No. 135 5.4 3.6 225 230 238 268 229 258 239 254 249 251 268 225 244
15 Room No. 136 5.4 3.6 223 225 308 287 224 265 268 275 279 261 308 223 262
16 Room No. 137 5.4 3.6 238 268 254 245 246 235 338 246 249 261 338 235 258
17 Room No. 139 5.4 3.6 313 298 258 254 256 267 254 256 261 303 313 254 272
18 Room No. 140 5.4 3.6 316 342 331 325 331 316 319 324 312 298 342 298 321
19 Room No. 144 5.4 3.6 264 262 256 249 246 254 259 256 261 241 264 241 255
20 Room No. 146 5.4 3.6 398 341 361 352 356 384 359 364 345 348 398 341 361
21 Room No. 147 5.4 3.6 367 349 356 372 346 349 354 356 356 354 372 346 356
22 Room No. 148 5.4 3.6 375 382 368 379 364 368 375 378 364 365 382 364 372
23 Room No. 149 5.4 3.6 346 313 356 349 346 316 345 346 339 352 356 313 341
24 Room No. 150 3.0 2.4 248 268 279 268 256 268 276 271 269 269 279 248 267
25 Room No. 152 5.4 3.6 289 238 301 298 239 241 254 246 267 261 301 238 263
26 Room No. 155 6.6 3.6 238 268 289 299 289 298 275 268 264 301 301 238 279
27 Room No. 159 4.8 3.6 400 473 421 458 423 435 425 426 406 441 473 400 431
Second Floor
1 Room No. 203 6.0 3.0 425 437 413 419 415 410 428 425 426 439 439 410 424
2 Room No. 206 6.0 3.0 183 193 384 394 212 235 356 361 264 250 394 183 283
3 Room No. 210 6.0 3.0 470 350 357 402 346 359 364 379 365 425 470 346 382
4 Room No. 211 6.0 3.0 319 249 258 301 265 254 287 259 285 267 319 249 274
5 Room No. 217 5.4 3.6 213 287 203 225 215 264 235 246 259 266 287 203 241
6 Room No. 218 5.4 3.6 168 187 213 203 179 198 201 212 176 198 213 168 194
7 Room No. 220 5.4 3.6 285 350 439 387 356 365 389 312 410 314 439 285 361
8 Room No. 223 5.4 3.6 276 321 305 310 286 298 285 279 309 278 321 276 295
9 Room No. 225 5.4 3.6 208 256 230 247 246 235 249 257 210 212 257 208 235
10 Room No. 226 5.4 3.6 208 210 225 252 210 245 248 236 237 198 252 198 227
11 Room No. 227 3.6 2.4 273 252 230 280 256 249 243 256 261 255 280 230 256
12 Room No. 229 5.4 3.6 360 368 390 331 356 364 354 359 361 289 390 289 353
13 Room No. 231 5.4 3.6 250 226 252 241 235 256 249 235 239 233 256 226 242
14 Room No. 232 5.4 3.6 196 270 256 238 229 235 259 245 256 183 270 183 237
15 Room No. 233 5.4 3.6 350 312 357 389 356 345 359 368 375 319 389 312 353
16 Room No. 235 3.6 2.4 273 280 283 243 256 249 259 267 249 261 283 243 262
17 Room No. 236 5.4 3.6 256 308 313 289 259 284 287 289 294 263 313 256 284
18 Room No. 237 5.4 3.6 347 312 328 331 336 349 315 324 334 355 355 312 333
19 Room No. 238 5.4 3.6 203 230 258 281 210 245 265 278 279 271 281 203 252
20 Room No. 239 5.4 3.6 253 270 249 252 265 251 267 261 259 261 270 249 259
21 Room No. 240 5.4 3.6 350 313 298 320 312 324 336 326 310 337 350 298 323
22 Room No. 241 5.4 3.6 177 160 158 147 156 154 168 157 149 163 177 147 159
23 Room No. 242 5.4 3.6 282 256 242 273 279 278 268 269 257 233 282 233 264
24 Room No. 245 5.4 3.6 385 346 358 399 365 354 359 358 368 349 399 346 364
The capacitor banks are fitted in the feeder of MSS 1, 4, 5, 7, 8, and 11.
KVAR rating of capacitors was not available.
The ampere measurements of capacitor banks are shown in the following
table.
Description Rating Current (Amp) Remark
kVAR Amp R Y B
MSS 4 - HT Panel 3.3KV
Capacitor Bank II - Feeder 31 0.0 279.0 277.0 277.0
MSS 1 - HT Panel 3.3KV
Capacitor Bank I - Feeder 27 0.0 180.0 178.0 178.0
MSS 5 - HT Panel 3.3KV
Capacitor Bank - Feeder 17 0.0 72.3 72.3 72.3
MSS 7 - HT202 Panel 6.6KV
Capacitor Bank I 0.0 130.3 134.2 131.8
Capacitor Bank II 0.0 96.7 91.0 93.7
MSS 8 - HT203 Panel 6.6KV
Capacitor Bank I 0.0 126.8 127.2 127.4
MSS 11 HVSB 2 Panel 6.6KV
Capacitor Bank I - Feeder 3 0.0 113.0 113.0 113.0
Capacitor Bank II - Feeder 20 0.0 111.7 112.0 111.7
MSS 11 HVSB 2 Panel 6.6KV
Capacitor Bank I - Feeder 8 0.0 110.0 110.0 109.0
Capacitor Bank II - Feeder 25 0.0 84.0 84.0 84.0
LRS 1 - TR2 Panel 6.6KV
Capacitor Bank - Feeder 9 0.0 106.1 117.5 117.7
LRS 2 - 6.6 KV Panel 6.6KV
Capacitor Bank I - Feeder 1 0.0 43.5 43.6 43.3
Capacitor Bank II - Feeder 34 0.0 33.1 33.0 33.1
The electricity is procured from Tata Power Ltd as well as through Open access,
the details of the consumption is as under.
It is observed LPG is utilized to generate hot water for use in canteen & worker
amenities areas.
The possibility of installing solar hot water system to generate hot water for
both the canteen & worker amenities areas. The capacity of the hot water (at
60 o C) system for canteen can be around 5000 litres per day based on the
present load.
E v a l u a t i o n o f E n e r g y M a n a g e m e n t S y s t e m
HPCL's Mumbai Refinery use energy in various forms viz., fuel, steam,
electricity, etc. in different processing units to convert crude oil to
valuable petroleum products. Most of these refinery processes are
energy intensive and use part of the finished products produced in the
refinery to derive their energy requirement. Thus any reduction in
consumption of energy directly results in higher availability of finished
products, which in turn results in higher profit. Hence, energy
conservation has direct impact on refinery's profits.
The approved energy policy of HPCL, MR is stated below.
Effective energy management is not only good for industry, but also
becoming a requirement. It is best achieved with ISO 50001. The
international standard outlines energy management practices that are
considered to be the best, globally. HPCL MR is in the process of
implementing ISO 50001 at their refinery.
The benchmark and target values are set annually for energy
consumption (as a fraction of crude processed) based on past data as
well as consumption of other refineries.
The values are monitored at regular interval and deviations, if any, are
studies and remedied, wherever possible and feasible.
The compressed air leak testing, trap testing is also carried out at
periodic interval to identify and rectify loss -point.
The life cycle cost is considered while procuring any major energy
consuming equipments / systems.
Strengths:
Weakness:
E n e r g y C o n s e r v a t i o n M e a s u r e s a n d
R e c o m m e n d a t i o n s
The performance of some of the chiller is on the lower side; which may be
improved through improved maintenance practices.
A 5000 LPD solar hot water system may be installed to meet the hot water
requirements of various canteen and convenience areas.
a) ADMIN BUILDING_NEW
CAPEX MODEL
The facility can install 170 kWp (Thumb rule 1 kWp occupies 100 Sq. ft and for
shadow clearance and walk way we considered 20 Feet thereby for 1 kW we
require 120 Sq. feet) solar roof top system (Solar PV system) with net metering
facility to reduce the energy consumption. Irradiation level in Mumbai region is
5.05 sun hours. Therefore, tentatively a 170 kWp solar PV system generates
2,48,200 kWh per annum (as the solar plant will be active on sunny days only,
considered 365 days per year) i.e. ,680 units per day. Considering Rs. 65 per watt
peak, 170 kWp system costs around Rs. 1,10,50,000. Based on DISCOM tariff of
Rs. 6/ kWh, the payback period works out to 8 years and Return on Investment
(ROI) is 71.55% with an IRR of 6%. The detailed calcul ation is presented as
Annexure-2 to this report. HPCL informed that roof top solar for admin building
is under consideration.
b) ADMIN BUILDING_OLD
CAPEX MODEL
c) ELECTRICAL BUILDING
CAPEX MODEL
The facility can install 25 kWp (Thu mb rule 1 kWp occupies 100 Sq. ft and for
shadow clearance and walk way we considered 20 Feet thereby for 1 kW we
require 120 Sq. feet) solar roof top system (Solar PV system) with net metering
facility to reduce the energy consumption. Irradiation level i n Mumbai region is
5.05 sun hours. Therefore, tentatively a 25 kWp solar PV system generates
36,500 kWh per annum (as the solar plant will be active on sunny days only,
considered 365 days per year) i.e.,100 units per day. Considering Rs. 65 per watt
peak, 25 kWp system costs around Rs. 16,25,000. Based on DISCOM tariff of Rs.
6/ kWh, the payback period works out to 8 years and Return on Investment (ROI)
is 71.55% with an IRR of 6%. The detailed calculation is presented as Annexure -
2 to this report.
CAPEX MODEL
The facility can install 60 kWp (Thumb rule 1 kWp occupies 100 Sq. ft and for
shadow clearance and walk way we considered 20 Feet thereby for 1 kW we
require 120 Sq. feet) solar roof top system (Solar PV system) with net metering
facility to reduce the energy consumption. Irradiation level in Mumbai region is
5.05 sun hours. Therefore, tentatively a 60 kWp solar PV system generates
87,600 kWh per annum (as the solar plant will be active on sunny days only,
considered 365 days per year) i.e.,240 units per day. Considering Rs. 65 per watt
peak, 60 kWp system costs around Rs. 39,00,000. Based on DISCOM tariff of Rs.
6/ kWh, the payback period works o ut to 8 years and Return on Investment (ROI)
is 71.55% with an IRR of 6%. The detailed calculation is presented as Annexure -
1 to this report.
Present Condition
The HRSG exhaust temperature is very high as compare to design and industry standard. This is primarily due
to insufficient heat transfer in the steam generator. All the sections of HRSG 1 and HRSG 3 have poor heat
transfer. This includes high Pinch point. There is a need of improving the HRSG heat transfer by improving
the performance for all the sections. This will leads to increase the efficiency of HRSG by 20%. Therefore, it
is recommended to do the detailed HRSG internal tubes inspection and take corrective action including
cleaning/ replacement of the tubes. The HRSG 5 has high flue gas inlet temperature and has very poor
superaheater section performance. The tuning of the GT exhaust temperature/ checking the Superheater
tube deposits will help in improving the section performance. HPCL informed that chemical cleaning
procedure of the boilers as done in past will be followed in future. The expected performance may be as
follows:
8.10 Dry Flue Gas loss in Boiler SG-12 and Boiler SG-10
The Boiler SG10 and Boiler SG12 both have high dry flue gas loss. This is primarily due to excess air flow in
the boiler and insufficient heat transfer in the boiler. With the inspection , checking tubes, maintanence /
cleaning tube deposits , etc. the performance will be increase. HPCL informed that inspection, cleaning of
boiler is done periodically in refinery as planned schedule. The expected performance may be as follows:
8.11 Replacement of VHP BFP Pump of Boiler SG12 with small size pump
The VHP BFP of Boiler SG-12 is operating at very low efficiency. Currently , pump is designed for the 164 TPH
flow with an efficiency of 72%. The combined efficiency of the pump is 33%. Therefore, even the pump is
giving only 64 TPH as per need but motor loading is 92%. That is why there is a need of small size pump, the
efficiency can be improved upto 70%. With the introduction of new pump the option will be flexible as in low
load , the small size pump will be used which have the same dynamic pressure as existing above. HPCL
informed that VFD is in line for this BFP pump motor, hence power consumption and other parameters will
be reviewed again by HPCL. The Encon Calculations are given below.
Parameter UoM Design Operating
Pump Efficiency % 72.75% 33.19%
Flow TPH 164 64
Power Consumption kW 359 331
Expected power consumption with pump
curve kW 225.00
Pump hydraulic power kW 110
Power Saving with new 200 kW pump kw 131
Yearly Saving in kW kWh 1039470
Investment Rs 5,000,000
Payback month 7
8.11 Use of Plate Heat Exchanger instead of Fin Fan Coolers for Generator Lub Oil Cooler water and
cleaning of suction filter of fan
The Generator lub oil is cooled by closed circuit water which flows through the fin fan coolers then passess
through the Lub Oil cooler and transfer energy. With the present system the maximum cooling can be
achieved only upto the ambient dry bulb temperature. With the use of Plate heat exchanger where the
Cooling Tower water will be used for cooling the Closed circuit DM water. GT-1 water requirement calculated
as 270 m3/hr, GT-2 as 157.5 m3/hr, GT-5 as 189 m3 /hr , total requirement as 616 m3/hr. HPCL opined that
this much additional raw water avialibility is not possible. The scheme is given below
Proposed Scheme
Cold Water Cooling water In
Lub Oil to Bearing
Lub Oil Cooling
Hot Return Oil
Cooler Plate Heat
Hot Water Water Out
Exchanger
Parameter UoM GT 1 GT 3 GT 5
Present Power Consumption by Fin Fans kW 36 36.9 75.10
Cooling Water Inlet Temp oC 55 55 55
Cooling Water Outlet Temp oC 38.70 41 44
Effectiveness of Fin Fans % 49.4% 42.4% 33.3%
Saving with Replacing the GT Fin Fan
Coolers with Plate Heat Exchanger kw 36 37 75
Yearly saving in kW by replacing Fin Fans
and Pump kWh 285120 292248 594792
Yearly saving considering 8 Rs/Unit Rs 2280960 2337984 4758336
Investment Rs 5000000
Payback Month 6
The FD Fan of Boiler SG-10 is operating in a part load with there is a yearly variation in the Air flow
requirement of the Boiler. The FD Fan efficiency comes very low to 37%. Therefore, to save the power from
yearly operations variations the VFD is recommended for the FD Fan for SG-10 and similarly , for SG-11 as
informed by HPCL. The encon savings are given below.
During the field visit it is observed that all the suction filter of the FD fan is choked. The suction velocity is
hardly .1 to .5 m/s. It is also damaged in many places. During the data collection and analysis the FD Fan
efficiency comes very low. The reason predicted is Fan motor is working hard to deliver the Air to the boiler
but at the same time as the suction filters are choked therefore it is consuming extra kW to achieve the
desired need of the boiler. HPCL informed that action has been iniated and replacement planned for both
SG-10 and SG-12 FD fan suction filters. The Encon saving calculations are given below
Replacement of FD Fan Suction Filter of SG-12 boiler
Parameter UoM Data
Present FD fan Efficiency % 9%
Power Consumption kW 167
hydraulic Power needed kW 14.5
Fan efficiency Improvement after replacing suction filter % 60%
Fan Discharge pressure mmWc 71.57
Fan discharge pressure with improved condition mmWc 300
Hydraulic Power needed with improved condition kW 58
Power Consumption after improvement considering 60% Fan efficiency kW 100
Saving in Power consumption kW 67
Saving in kW yearly kWh yearly 530640
Yearly Saving considering 8 Rs/Unit Rs 4245120
Investment Rs 2000000
Payback Month 6
At Present the VHP water Header is not interconnected. The Individual pump is running for
the boilers SG-10 and SG-12. In both the boilers the Pump is operating in part load operation
at close to 50%. With the interconnection of the header the 1 pump can be stopped in one of
the boilers. HPCL informed that the scheme is under consideration. The encon calculation is
given below
Parameter UoM Data
Present Power consumption of both the boilers kW 640.62
The total BFW water needed for boilers TPH 172.97
the capacity of 1 VHP BFW Pump TPH 192
Power Consumed by SG-12 VHP Pump kW 331
Saving with stopping 1 VHP Pump kWh 331
Yearly saving kWh 2621520
Yearly Saving in Rs Rs 20972160
Investment Rs 10000000
Payback period Months 6
There are 6 numbers of SBR blowers (lobe type) in WWTP , out of which 4 are running and
two are stand by. 3 running blowers are provided with VFD and one non VFD blower. Four
lobe type blowers can be replaced with high efficiency turbo blower (PM motor, airfoil
dynamic centrifugal type). HPCL informed that the scheme is being worked out with the
help of vendor.
A) ADMIN BUILDING_NEW
List of Assumptions
Particulars/ Name of item Value Unit
Year wise % Increase in the Savings 5.0% Percentage
Year wise % Increase in the Operation cost 5.0% Percentage
Discount factor 10.0% Percentage
Operating cost as % investement 1.0% Percentage
Project Economics:
Project Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Investment ₹ 110,50,000.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Savings /Year 0 ₹ 14,89,200.00 1563660.00 1641843.00 1723935.15 1810131.91 1900638.50 1995670.43 2095453.95 2200226.65 2310237.98 2425749.88 2547037.37 2674389.24 2808108.70 2948514.14 3095939.84 3250736.84 3413273.68 3583937.36 376
Cost of Operation
0 110500.00 116025.00 121826.25 127917.56 134313.44 141029.11 148080.57 155484.60 163258.83 171421.77 179992.86 188992.50 198442.12 208364.23 218782.44 229721.56 241207.64 253268.02 265931.43 279
/Year
Net Savings 0 1378700.00 1447635.00 1520016.75 1596017.59 1675818.47 1759609.39 1847589.86 1939969.35 2036967.82 2138816.21 2245757.02 2358044.87 2475947.12 2599744.47 2729731.70 2866218.28 3009529.20 3160005.65 3318005.94 348
Discounted Cash
-11050000.00 1253363.64 1196392.56 1142011.08 1090101.49 1040551.42 993253.63 948105.74 905010.02 863873.20 824606.24 787124.14 751345.77 717193.69 684593.97 653476.06 623772.61 595419.31 568354.79 542520.48 517
flows
Simple Payback
8.0
Period (Years)
NPV of the
7905828.76
Project
IRR (%) 6%
List of Assumptions
Particulars/ Name of item Value Unit
Year wise % Increase in the Savings 5.0% Percentage
Year wise % Increase in the Operation cost 5.0% Percentage
Discount factor 10.0% Percentage
Operating cost as % investement 1.0% Percentage
Project Economics: Fig : Rs.
Project Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Investment ₹ 32,50,000.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Savings /Year 0 ₹ 4,38,000.00 459900.00 482895.00 507039.75 532391.74 559011.32 586961.89 616309.99 647125.48 679481.76 713455.85 749128.64 786585.07 825914.32 867210.04 910570.54 956099.07 1003904.02 1054099.22 1106804.19 1162144.39 1220251.61 1281264.20 1345327.41 1412593.78
Cost of Operation
0 32500.00 34125.00 35831.25 37622.81 39503.95 41479.15 43553.11 45730.76 48017.30 50418.17 52939.08 55586.03 58365.33 61283.60 64347.78 67565.17 70943.42 74490.60 78215.13 82125.88 86232.18 90543.78 95070.97 99824.52 104815.75
/Year
Net Savings 0 405500.00 425775.00 447063.75 469416.94 492887.78 517532.17 543408.78 570579.22 599108.18 629063.59 660516.77 693542.61 728219.74 764630.73 802862.26 843005.38 885155.65 929413.43 975884.10 1024678.30 1075912.22 1129707.83 1186193.22 1245502.88 1307778.03
Discounted Cash
-3250000.00 368636.36 351880.17 335885.61 320618.08 306044.54 292133.42 278854.63 266179.42 254080.35 242531.25 231507.10 220984.05 210939.32 201351.17 192198.84 183462.53 175123.33 167163.17 159564.85 152311.90 145388.63 138780.06 132471.87 126450.43 120702.68
flows
NPV of Savings 5575243.75
Simple Payback
8.0
Period (Years)
NPV of the
2325243.75
Project
ROI (%) 71.55
IRR (%) 6%
List of Assumptions
Particulars/ Name of item Value Unit
Year wise % Increase in the Savings 5.0% Percentage
Year wise % Increase in the Operation cost 5.0% Percentage
Discount factor 10.0% Percentage
Operating cost as % investement 1.0% Percentage
Project Economics: Fig : Rs.
Project Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Investment ₹ 16,25,000.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Savings /Year 0 ₹ 2,19,000.00 229950.00 241447.50 253519.88 266195.87 279505.66 293480.95 308154.99 323562.74 339740.88 356727.92 374564.32 393292.54 412957.16 433605.02 455285.27 478049.53 501952.01 527049.61 553402.09 581072.20 610125.81 640632.10 672663.70 706296.89
Cost of Operation
0 16250.00 17062.50 17915.63 18811.41 19751.98 20739.58 21776.55 22865.38 24008.65 25209.08 26469.54 27793.01 29182.67 30641.80 32173.89 33782.58 35471.71 37245.30 39107.56 41062.94 43116.09 45271.89 47535.49 49912.26 52407.87
/Year
Net Savings 0 202750.00 212887.50 223531.88 234708.47 246443.89 258766.09 271704.39 285289.61 299554.09 314531.80 330258.39 346771.30 364109.87 382315.36 401431.13 421502.69 442577.82 464706.71 487942.05 512339.15 537956.11 564853.92 593096.61 622751.44 653889.01
Discounted Cash
-1625000.00 184318.18 175940.08 167942.81 160309.04 153022.27 146066.71 139427.31 133089.71 127040.18 121265.62 115753.55 110492.02 105469.66 100675.58 96099.42 91731.27 87561.66 83581.59 79782.42 76155.95 72694.32 69390.03 66235.94 63225.21 60351.34
flows
NPV of Savings 2787621.88
Simple Payback
8.0
Period (Years)
NPV of the
1162621.88
Project
ROI (%) 71.55
IRR (%) 6%
List of Assumptions
Particulars/ Name of item Value Unit
Year wise % Increase in the Savings 5.0% Percentage
Year wise % Increase in the Operation cost 5.0% Percentage
Discount factor 10.0% Percentage
Operating cost as % investement 1.0% Percentage
Project Economics: Fig : Rs.
Project Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Investment ₹ 65,00,000.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Savings /Year 0 ₹ 8,76,000.00 919800.00 965790.00 1014079.50 1064783.48 1118022.65 1173923.78 1232619.97 1294250.97 1358963.52 1426911.69 1498257.28 1573170.14 1651828.65 1734420.08 1821141.09 1912198.14 2007808.05 2108198.45 2213608.37 2324288.79 2440503.23 2562528.39 2690654.81 2825187.55
Cost of Operation
0 65000.00 68250.00 71662.50 75245.63 79007.91 82958.30 87106.22 91461.53 96034.60 100836.33 105878.15 111172.06 116730.66 122567.19 128695.55 135130.33 141886.85 148981.19 156430.25 164251.76 172464.35 181087.57 190141.95 199649.04 209631.50
/Year
Net Savings 0 811000.00 851550.00 894127.50 938833.88 985775.57 1035064.35 1086817.56 1141158.44 1198216.36 1258127.18 1321033.54 1387085.22 1456439.48 1529261.45 1605724.53 1686010.75 1770311.29 1858826.86 1951768.20 2049356.61 2151824.44 2259415.66 2372386.44 2491005.77 2615556.05
Discounted Cash
-6500000.00 737272.73 703760.33 671771.22 641236.17 612089.07 584266.84 557709.26 532358.84 508160.71 485062.49 463014.20 441968.10 421878.64 402702.34 384397.69 366925.06 350246.65 334326.35 319129.70 304623.80 290777.26 277560.12 264943.75 252900.85 241405.36
flows
NPV of Savings 11150487.51
Simple Payback
8.0
Period (Years)
NPV of the
4650487.51
Project
ROI (%) 71.55
IRR (%) 6%
List of Assumptions
Particulars/ Name of item Value Unit
Year wise % Increase in the Savings 5.0% Percentage
Year wise % Increase in the Operation cost 5.0% Percentage
Discount factor 10.0% Percentage
Operating cost as % investement 1.0% Percentage
Project Economics: Fig : Rs.
Project Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Investment ₹ 39,00,000.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Savings /Year 0 ₹ 5,25,600.00 551880.00 579474.00 608447.70 638870.09 670813.59 704354.27 739571.98 776550.58 815378.11 856147.02 898954.37 943902.08 991097.19 1040652.05 1092684.65 1147318.88 1204684.83 1264919.07 1328165.02 1394573.27 1464301.94 1537517.03 1614392.89 1695112.53
Cost of Operation
0 39000.00 40950.00 42997.50 45147.38 47404.74 49774.98 52263.73 54876.92 57620.76 60501.80 63526.89 66703.23 70038.40 73540.32 77217.33 81078.20 85132.11 89388.71 93858.15 98551.06 103478.61 108652.54 114085.17 119789.43 125778.90
/Year
Net Savings 0 486600.00 510930.00 536476.50 563300.33 591465.34 621038.61 652090.54 684695.07 718929.82 754876.31 792620.13 832251.13 873863.69 917556.87 963434.72 1011606.45 1062186.77 1115296.11 1171060.92 1229613.97 1291094.66 1355649.40 1423431.87 1494603.46 1569333.63
Discounted Cash
-3900000.00 442363.64 422256.20 403062.73 384741.70 367253.44 350560.10 334625.55 319415.30 304896.42 291037.50 277808.52 265180.86 253127.18 241621.40 230638.61 220155.04 210147.99 200595.81 191477.82 182774.28 174466.36 166536.07 158966.25 151740.51 144843.21
flows
NPV of Savings 6690292.50
Simple Payback
8.0
Period (Years)
NPV of the
2790292.50
Project
ROI (%) 71.55
IRR (%) 6%
The data collection has been carried out diligently and truthfully;
All data monitoring devices are in good working condition and have been
calibrated or certified by approved agencies authorized and no tempering of such
devices has occurred;
All reasonable professional skill, care and diligence had been taken in preparing
the energy audit report and the contents thereof are a true representation of the
facts;
Adequate training provided to personnel involved in daily operations after
implementation of recommendations; and
The energy audit has been carried out in accordance with the Bureau of Energy
Efficiency (Manner and Intervals of Time for the Conduct of Energy Audit)
Regulations, 2010.
Signature
Name of the accredited energy auditor
Accreditation details
Seal
C Degree Centigrade
A Ampere
APFC Automatic Power Factor Controller
Avg. Average
CHW. Chilled Water
cm. Centimeter
Cr. Crores
CT Cooling Tower
CW Cooling Water
DBT Dry Bulb Temperature
DG Diesel Generating
Dia. Diameter
Effn. Efficiency
gm. Gram
hr. Hour
Ins Insulated
HPCLMR Hindustan Petroleum Corporation Ltd
Mumbai Refinery
Kcal Kilo Calories
Kg. Kilogram
KL Kilo Liter
KV Kilo Volt
kVA Kilo Volt Ampere
kVAr Kilo Volt Ampere Reactive
kW Kilo Watts
kWh Kilo Watt Hour
lit Liters
lt Liters
Ltd. Limited
M or m Meter
Max. Maximum
MD Maximum Demand
Min. Minimum
Mm Millimeter
MT Metric Ton
MW Mega Watts
No. Number
OLTC Online Tap Changer
PCRA Petroleum Conservation Research
Association
p.a. Per Annum
PF Power Factor
Rpm Revolutions per minute
Rs. Rupees
Sec. Second
SEC Specific Energy Consumption
Temp. Temperature
TPH Tones Per Hour
TR Tons of Refrigeration
V Voltage
Signature Signature
Name of energy manager Name of accredited energy auditor
Name and full Company a ddress Accredat ion details and seal