ID Task Task Name Duration Start Finish Predecessors

Resource Names 17 Nov '19 08 Dec '19 29 Dec '19 19 Jan '20 09 Feb '20 01 Mar '20 22 Mar '20 12 Apr '20 03 May '20
Mode M T W T F S S M T W T F S S M T W T F S S M
1 A. PROJECT ANGGY 98 days Thu 12/12/19Sat 04/04/20
2 I. PEKERJAAN PERSIAPAN 2 days Thu 12/12/19Fri 13/12/19
3 I.1. Pembersihan lokasi 2 days Thu 12/12/19Fri 13/12/19 Pekerja[400%] Pekerja[400%]
4 I.2. Pengukuran dan pasang 2 days Thu Fri 13/12/19 3FF Tukang Kayu[400%] Tukang Kayu[400%]
5 bouwplank
I.3. Pengadaan Listrik dan air 1 day 12/12/19
Fri 13/12/19 Fri 13/12/19 4FF Tukang Listrik Tukang Listrik
6 kerja
7 17 days
II. PEKERJAAN GALIAN DAN URUGAN Sat 14/12/19Fri 03/01/20
8 II.1. Galian Tanah 5 days Sat 14/12/19 Thu 19/12/195 Pekerja[400%] Pekerja[400%]
9 II.2. Urugan kembali 2 days Fri 27/12/19 Sat 28/12/19 14 Pekerja[400%] Pekerja[400%]
10 II.3. Urugan pasir 1 day Fri 20/12/19 Fri 20/12/19 8 Pekerja[200%] Pekerja[200%]
11 II.4. Urugan Sirtu 1 day Fri 03/01/20 Fri 03/01/20 16 Pekerja[200%] Pekerja[200%]
12
13 III. PEKERJAAN BETON 51 days Wed 25/12/19 Sat 22/02/20
14 III.1. Pondasi P1 100.80.30 2 days Wed 25/12/19Thu 26/12/1929 Pekerja[200%] Pekerja[200%]
15 III.2. Pondasi P2 50.80.30 1 day Thu 26/12/19Thu 26/12/1914FF Pekerja[200%] Pekerja[200%]
16 III.3. Sloof 15.20 1 day Thu 02/01/20Thu 02/01/2045 Pekerja[200%] Pekerja[200%]
17 III.4. Kolom K1 15.25 1 day Sat 18/01/20 Sat 18/01/20 47 Pekerja[200%] Pekerja[200%]
18 III.5. Kolom praktis 12.12 1 day Sat 18/01/20 Sat 18/01/20 17SS Pekerja[200%] Pekerja[200%]
19 III.6. Balok Latei 12.12 1 day Mon 27/01/20Mon 27/01/2048 Pekerja[200%] Pekerja[200%]
20 III.7. Balok B1 15.30 1 day Sat 01/02/20 Sat 01/02/20 49 Pekerja[200%] Pekerja[200%]
21 III.8. Ring balk 12.20 1 day Sat 01/02/20 Sat 01/02/20 20SS Pekerja[200%] Pekerja[200%]
22 III.9. Ring gewel 12.20 1 day Sat 01/02/20 Sat 01/02/20 21SS Pekerja[200%] Pekerja[200%]
23 III.10. Plat rooftop 12cm 1 day Sat 01/02/20 Sat 01/02/20 22SS Pekerja[200%] Pekerja[200%]
24 III.11. Plat kanopi 10cm 1 day Tue 04/02/20Tue 04/02/2039 Pekerja[200%] Pekerja[200%]
25 III.12. Lantai kerja beton t= 5 cm 2 days Tue 18/02/20Wed 19/02/2083 Pekerja[200%] Pekerja[200%]
26 III.13. Tangga beton 12cm 1 day Sat 22/02/20 Sat 22/02/20 40 Pekerja[200%] Pekerja[200%]
27
28 IV. PEKERJAAN PEMBESIAN 53 days Sat 21/12/19Fri 21/02/20
29 IV.1. Pondasi P1 100.80.30 3 days Sat 21/12/19 Tue 24/12/1910 Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
30 IV.2. Pondasi P2 50.80.30 2 days Mon 23/12/19Tue 24/12/1929FF Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
31 IV.3. Sloof 15.20 4 days Fri 27/12/19 Tue 31/12/1915 Mandor;Pekerja[400%];Tukang Besi Mandor;Pekerja[400%];Tukang Besi
32 IV.4. Kolom K1 15.25 3 days Fri 27/12/19 Mon 30/12/1931SS Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
33 IV.5. Kolom praktis 12.12 5 days Fri 27/12/19 Thu 02/01/2031SS Mandor;Pekerja[400%];Tukang Besi Mandor;Pekerja[400%];Tukang Besi
34 IV.6. Balok Latei 12.12 1 day Fri 24/01/20 Fri 24/01/20 58SS+3 days
Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
35 IV.7. Balok B1 15.30 2 days Tue 28/01/20Wed 29/01/2058 Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
36 IV.8. Ring balk 12.20 4 days Tue 28/01/20Fri 31/01/20 35SS Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
37 IV.9. Ring gewel 12.20 4 days Tue 28/01/20Fri 31/01/20 36SS Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
38 IV.10. Plat rooftop 12cm 2 days Tue 28/01/20Wed 29/01/2037SS Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
39 IV.11. Plat kanopi 10cm 1 day Mon 03/02/20Mon 03/02/2023 Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
40 IV.12. Tangga beton 12cm 3 days Wed 19/02/20Fri 21/02/20 54 Mandor;Pekerja[200%];Tukang Besi Mandor;Pekerja[200%];Tukang Besi
41
42 V. PEKERJAAN BEGESTING 47 days Wed 25/12/19
Tue 18/02/20

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: msproj11
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Resource Names 17 Nov '19 08 Dec '19 29 Dec '19 19 Jan '20 09 Feb '20 01 Mar '20 22 Mar '20 12 Apr '20 03 May '20
Mode M T W T F S S M T W T F S S M T W T F S S M
43 V.1. Pondasi P1 100.80.30 2 days Wed 25/12/19Thu 26/12/1929 Tukang Kayu[200%] Tukang Kayu[200%]
44 V.2. Pondasi P2 50.80.30 2 days Wed 25/12/19Thu 26/12/1943FF Tukang Kayu[200%] Tukang Kayu[200%]
45 V.3. Sloof 15.20 3 days Sat 28/12/19 Tue 31/12/1931FF Tukang Kayu[200%] Tukang Kayu[200%]
46 V.4. Kolom K1 15.25 6 days Fri 03/01/20 Thu 09/01/2016 Tukang Kayu[200%] Tukang Kayu[200%]
47 V.5. Kolom praktis 12.12 7 days Fri 10/01/20 Fri 17/01/20 46 Tukang Kayu[200%] Tukang Kayu[200%]
48 V.6. Balok Latei 12.12 1 day Sat 25/01/20 Sat 25/01/20 34 Tukang Kayu[200%] Tukang Kayu[200%]
49 V.7. Balok B1 15.30 2 days Thu 30/01/20Fri 31/01/20 35 Tukang Kayu[200%] Tukang Kayu[200%]
50 V.8. Ring balk 12.20 3 days Thu 30/01/20Sat 01/02/20 49SS Tukang Kayu[200%] Tukang Kayu[200%]
51 V.9. Ring gewel 12.20 3 days Thu 30/01/20Sat 01/02/20 50SS Tukang Kayu[200%] Tukang Kayu[200%]
52 V.10. Plat rooftop 12cm 3 days Thu 30/01/20Sat 01/02/20 51SS Tukang Kayu[200%] Tukang Kayu[200%]
53 V.11. Plat kanopi 10cm 1 day Mon 03/02/20Mon 03/02/2039SS Tukang Kayu[200%] Tukang Kayu[200%]
54 V.12. Tangga beton 12cm 1 day Tue 18/02/20Tue 18/02/2083 Tukang Kayu[200%] Tukang Kayu[200%]
55
56 VI. PEKERJAAN PASANGAN DAN 48 days Mon Sat
57 PLESTERAN
VI.1. Pasangan terasram tebal 1/2 1 day 20/01/20
Mon 14/03/20
Mon 18 Mandor;Pekerja[400%];Tukang Mandor;Pekerja[400%];Tukang Batu[300%]
58 Bata
VI.2.1Pasangan
PC : 3 PSDinding Bata 6 days 20/01/20
Tue 20/01/20
Mon 57 Batu[300%]
Mandor;Pekerja[400%];Tukang Mandor;Pekerja[400%];Tukang Batu[300%]
59 merah tebal 1/2 bata
VI.3. Pasangan 1 PC
Rollag : 6 PS 1 day
Bata 21/01/20
Tue 27/01/20
Tue 58 Batu[300%]
Tukang Batu Tukang Batu
60 merah tebal 1 bata
VI.4. Plesteran bata1 biasa
PC : 31pc
PS : 6ps13 days 28/01/20
Tue 28/01/20
18/02/20Tue 03/03/2083 Mandor;Pekerja[400%];Tukang Batu[300%] Mandor;Pekerja[400%];Tukang Batu[300%]
61 VI.5. Acian Dinding 7 days Wed 04/03/20Wed 11/03/2060 Mandor;Pekerja[400%];Tukang Batu[300%] Mandor;Pekerja[400%];Tukang Batu[300%]
62 VI.6. Benangan sudut 5 days Fri 06/03/20 Wed 11/03/2061FF Mandor;Pekerja[400%];Tukang Batu[300%] Mandor;Pekerja[400%];Tukang Batu[300%]
63 VI.7. Railling Kaca 2 days Tue 10/03/20Wed 11/03/2062SS+3 daysMandor;Tukang Besi[300%] Mandor;Tukang Besi[300%]
64 VI.8. Pas.Batu alam 4 days Wed 11/03/20Sat 14/03/20 63SS+1 dayTukang Batu Tukang Batu
65
66 VII. PEKERJAAN KUSEN, PINTU, 9 days Sat Tue
67 JENDELA & BOVENLIST
VII.1. Pintu PJ1 3 days 21/03/20 31/03/20
Sat 28/03/20 Tue 31/03/2069 Tukang Besi[200%] Tukang Besi[200%]
68 VII.2. Pintu PJ2 3 days Sat 28/03/20 Tue 31/03/2067SS Tukang Besi[200%] Tukang Besi[200%]
69 VII.3. Pintu P1 5 days Mon 23/03/20Fri 27/03/20 72 Tukang Besi Tukang Besi
70 VII.4. Pintu P2 5 days Mon 23/03/20Fri 27/03/20 69SS Tukang Besi[200%] Tukang Besi[200%]
71 VII.5. Pintu P3 5 days Mon 23/03/20Fri 27/03/20 70SS Tukang Besi Tukang Besi
72 VII.6. Jendela J1 1 day Sat 21/03/20 Sat 21/03/20 96SS Tukang Besi Tukang Besi
73 VII.7. Jendela J2 1 day Sat 21/03/20 Sat 21/03/20 72SS Tukang Besi Tukang Besi
74 VII.8. Jendela J3 1 day Sat 21/03/20 Sat 21/03/20 73SS Tukang Besi Tukang Besi
75 VII.9. Jendela J4 1 day Mon 23/03/20Mon 23/03/2070SS Tukang Besi Tukang Besi
76 VII.10. Bovenlight 1 day Mon 23/03/20Mon 23/03/20 75SS Tukang Besi Tukang Besi
77
78 VIII. PEKERJAAN RANGKA ATAP 13 days Mon 03/02/20 Mon 17/02/20
79 VIII.1. Pasang rangka atap 6 days Mon Sat 08/02/20 23 Mandor;Tukang Besi[300%] Mandor;Tukang Besi[300%]
80 galvalum c75.75atap genteng aspal 5 days
VIII.2. Penutup 03/02/20
Mon 10/02/20Fri 14/02/20 79 Pekerja[400%] Pekerja[400%]
81 VIII.3. Pasang aluminium foil 2 days Fri 07/02/20 Sat 08/02/20 80SS-2 days
Tukang Kayu Tukang Kayu
82 VIII.4. Kalsiplank 2 days Sat 15/02/20 Mon 17/02/20 80
83 VIII.5. Bubungan 2 days Sat 15/02/20 Mon 17/02/20 80 Tukang Batu Tukang Batu
84

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: msproj11
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors
Resource Names 17 Nov '19 08 Dec '19 29 Dec '19 19 Jan '20 09 Feb '20 01 Mar '20 22 Mar '20 12 Apr '20 03 May '20
Mode M T W T F S S M T W T F S S M T W T F S S M
85 IX. PEKERJAAN PLAFOND 6 days Thu 12/03/20Wed 18/03/20
86 IX.1. Rangka Plafond 3 days Thu 12/03/20Sat 14/03/20 62 Pekerja[200%];Tukang Kayu[200%] Pekerja[200%];Tukang Kayu[200%]
87 IX.2. Pas.Plafond 2 days Mon 16/03/20Tue 17/03/2086 Tukang Kayu[200%] Tukang Kayu[200%]
88 IX.3. List plafond 4 days Sat 14/03/20 Wed 18/03/2087FF Tukang Kayu Tukang Kayu
89
90 X. PEKERJAAN LANTAI 5 days Thu 19/03/20Tue 24/03/20
91 X.1. Pasang lantai keramik 40/40 3 days Thu 19/03/20Sat 21/03/20 88 Pekerja;Tukang Batu[200%] Pekerja;Tukang Batu[200%]
92 X.2. Pasang lantai keramik20/20 1 day Mon 23/03/20Mon 23/03/2091 Tukang Batu Tukang Batu
93 X.3. Pasang keramik dinding 20/202 days Mon 23/03/20Tue 24/03/2091 Tukang Batu Tukang Batu
94
95 XI. PEKERJAAN CAT-CATAN 6 days Thu 19/03/20Wed 25/03/20
96 XI.1. Cat dinding exterior 4 days Sat 21/03/20 Wed 25/03/2098 Tukang Cat[400%] Tukang Cat[400%]
97 XI.2. Cat dinding interior 3 days Sat 21/03/20 Tue 24/03/2096SS Tukang Cat[400%] Tukang Cat[400%]
98 XI.3. Cat plafond 2 days Thu 19/03/20Fri 20/03/20 88 Tukang Cat[200%] Tukang Cat[200%]
99
100 XII. PEKERJAAN SANITASI 92 days Wed 18/12/19 Fri 03/04/20
101 XII.1. Pasang kloset jongkok 2 days Wed 01/04/20Thu 02/04/2067 Tukang Batu[200%] Tukang Batu[200%]
102 XII.2. Pasang kran air 3/4" 1 day Thu 02/04/20Thu 02/04/20101FF Tukang Batu Tukang Batu
103 XII.3. Pasang flordrain 1 day Thu 02/04/20Thu 02/04/20102FF Tukang Batu Tukang Batu
104 XII.4. Pasang pipa PVC 3/4" 2 days Wed 01/04/20Thu 02/04/20101SS Tukang Batu Tukang Batu
105 XII.5. Pasang pipa PVC 3" 1 day Thu 19/12/19Thu 19/12/198FF Mandor;Tukang Batu[300%] Mandor;Tukang Batu[300%]
106 XII.6. Pasang pipa PVC 4" 1 day Thu 19/12/19Thu 19/12/19105FF Tukang Batu Tukang Batu
107 XII.7. Pek. Septictank dan resapan1 day Fri 20/12/19 Fri 20/12/19 106 Tukang Batu Tukang Batu
108 XII.8. Pasang bak kontrol 2 days Wed 18/12/19Thu 19/12/19106FF Mandor;Tukang Batu[300%] Mandor;Tukang Batu[300%]
109 XII.9. Pasang sink dapur 1 day Fri 03/04/20 Fri 03/04/20 101 Tukang Batu Tukang Batu
110 XII.10. Pasang tandon air 1 day Sat 21/12/19 Sat 21/12/19 107 Tukang Batu Tukang Batu
111 XII.11. Pasang pompa air 1 day Thu 19/12/19Thu 19/12/19106FF Tukang Listrik Tukang Listrik
112
113 XIII. PEKERJAAN LISTRIK 4 days Wed 01/04/20 Sat 04/04/20
114 XIII.1. Pasang Mcb+Box 1 day Wed 01/04/20Wed 01/04/20101SS Tukang Listrik Tukang Listrik
115 XIII.2. Sambung antar gedung 1 day Fri 03/04/20 Fri 03/04/20 101 Tukang Listrik Tukang Listrik
116 XIII.3. Instalasi titik lampu 4 days Wed 01/04/20Sat 04/04/20 114SS Tukang Listrik[200%] Tukang Listrik[200%]
117 4 days
XIII.4. Instalasi stop kontak penerangan Wed 01/04/20Sat 04/04/20 116SS Tukang Listrik[200%] Tukang Listrik[200%]
118 XIII.5. Pasang lampu SL 11 Watt 1 day Sat 04/04/20 Sat 04/04/20 115 Tukang Listrik Tukang Listrik
119 XIII.6. Pasang stopkontak 1 day Sat 04/04/20 Sat 04/04/20 118SS Tukang Listrik Tukang Listrik
120 XIII.7. Pasang saklar engkel 1 day Sat 04/04/20 Sat 04/04/20 119SS Tukang Listrik Tukang Listrik
121 XIII.8. Pasang saklar seri 1 day Sat 04/04/20 Sat 04/04/20 120SS Tukang Listrik Tukang Listrik

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: msproj11
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only