The tasks to power off the VNX5300 Unified system are covered by:
◆ Power off procedure ............................................................................ 2
Step Action
1. When possible, before you power down the VNX5300 Unified system,
be sure to notify all users of the powerdown.
Note: This healthcheck ensures that there are no major errors in the
system that would prevent the system from being turned on during the
power up process.
Step Action
4. To halt the Control Station and all the blades, type the following:
# /nasmcd/sbin/nas_halt now
******************************** WARNING! *****************************
You are about to HALT this VNX including all of its Control Stations
and Data Movers. DATA will be UNAVAILABLE when the system is
halted.
Note that this command does *not* halt the storage array.
5. Type yes.
It can take as long as 20 minutes to halt the server, depending on the
configuration of the VNX system. Wait until the command completes
before continuing. If the Control Station halted successfully, the Hyper
Terminal session will be unresponsive.
6. Unplug the power cables from the Control Station(s) and the blade
enclosure’s power supplies to the PDU.
7. If you are powering down the system completely, shutdown the storage
array:
Note: This step involves safely shutting down the SPs to preserve the
write cache and can be skipped if only the blade(s) and Control Station
are to be powered down
a. Stop all I/O activity and wait five minutes before continuing.
Note: All I/O activity flowing from the blades was stopped when the
blades were shutdown in step 4. If external hosts are attached to the
storage array, stop all I/O activity from these hosts.
b. Use the SPS power switches to power off the array. Turn off (0
position) the power switch on the standby power supplies (SPSs).
Make sure the SPS power indicators are off before continuing. See
Figure 1 on page 4.
c. Wait two minutes to allow the storage system to write its cache to
disk and to power off. Then, disconnect the power cables that run
from the SPSs to the DAE. For systems with a single SPS, after
waiting two minutes, unplug SP B and DAE 0 LCC B power cables
from the PDU.
d. If there are multiple DAEs present, disconnect the power cable from
each DAE to the PDU. This powers down the DAEs.
6Gb SAS
B #
Disk-array enclosure
X4
6Gb SAS
X4
3U A #
3
2U
2
2
1
1
0
0
Control Station MODEM plug A CS
optional B MGMT Serial Console
VGA socket
1U
MODEM plug A CS
Control Station B MGMT Serial Console
1U VGA socket
3
3
1
1
2
2
1
B
15 or 25 disk processor A
0