EQUIPMENT PERFORMANCE FORMULA

SCHEDULER HOUR
Working Schedule for OB Removal
Description Shift Start End Sub Rest Losses Grand Util
Long Shift I 8:00 AM 5:00 PM 9 1 0.75 7.25
45.49%
II 8:00 PM 12:00 AM 4 0 0.33 3.67
2 Shift I 8:00 AM 5:00 PM 9 1 0.75 7.25
60.42%
II 8:00 PM 5:00 AM 9 1 0.75 7.25
3 Shift I 7:00 AM 3:00 PM 8 1 0.67 6.33
II 3:00 PM 11:00 PM 8 1 0.67 6.33 79.17%
III 11:00 PM 7:00 AM 8 1 0.67 6.33

Working Schedule for Coal Production


Description Shift Start End Sub Rest Losses Grand Util
Long Shift I 8:00 AM 5:00 PM 9 1 0.75 7.25
45.49%
II 8:00 PM 12:00 AM 4 0 0.33 3.67
2 Shift I 8:00 AM 5:00 PM 9 1 0.75 7.25
60.42%
II 8:00 PM 5:00 AM 9 1 0.75 7.25
3 Shift I 7:00 AM 3:00 PM 8 1 0.67 6.33
II 3:00 PM 11:00 PM 8 1 0.67 6.33 79.17%
III 11:00 PM 7:00 AM 8 1 0.67 6.33

HOUR AVAILABLE PER MONTH JAN FEB MAR APR MAY JUN JUL
Calendar Days 31 28 31 30 31 30 31
Production Shutdown 1 0 0 1 2 0 0
Available Days 30 28 31 29 29 30 31
Hours/day 13 13 13 13 13 13 13
Available Working Hours per day 390 364 403 377 377 390 403
Weather Delay 34 34 34 34 34 34 34
Other Delay 98 91 101 94 94 98 101
Net Working Hours per month 258 239 268 248 248 258 268
AUG SEP OCT NOV DEC TOTAL UNIT
31 30 31 30 31 365 Day
1 1 0 6 1 13 Day
30 29 31 24 30 352 Day
13 13 13 13 13 156 Hour
390 377 403 312 390 4576 Hour
34 34 34 34 34 412.5 Hour
98 94 101 78 98 1144 Hour
258 248 268 200 258 3019.5 Hour