Form No.

Field Performance Test Procedure


Date :
Enfourtech Corp. Ltd.

Field Performance Test;

1. Calculate the suction pressure gauge. (From another pump discharge


pressure gauge and ISOMETRIC drawing)
2. Measure the discharge pressure at site pressure gauge.
3. Install Ultrasonic Flowmeter and Measure the flow rate.
4. Measure the current from sub-station or control room.
5. Measure the existing motor rpm.
6. Plot the performance curve for below point by throttling the dischrage valve.
a. Shut-off (If possible), (expected 0% of discharge valve)
b. Minimum Flow (If possible), (expected 10% of discharge valve)
c. BEP Flow, (expected 50% of discharge valve)
d. Rated Flow, (expected 60% of discharge valve)
e. 120% BEP Flow, (expected 70% of discharge valve)

REQUIRED DATA
1. Suction Pressure by calculate from another pump discharge
pressure and ISOMETRIC drawing
2. Vapor pressure for calculating NPSHA
3. Motor Current
4. Flow
5. Discharge Pressure
6. Density at pumping temp
7. Viscosity
8. Motor cosΦ
9. Motor Efficiency
10. Site Voltage

Performance Test Enfourtech Corp. Ltd.